46 Westgate
Josh DobsonJames Shackleton
Lim Woanteng
BIMcampusTeam 3
Site Information
The Union Rooms
Abandoned Offices
Adjacent Plots
Precedents
Pointcloud Data
CDM Co-ordination
Design Development
Level 0
0
Level 1
4000
Level 2
8000
Level 3
12000
Level 4
16000
Level 1A
7140
Level 2A
10700
Level 3A
14300
-
---
2
A(00)GAS001
Level 0
0
Level 1
4000
Level 2
8000
Level 3
12000
Level 4
16000
Level 1A
7140
Level 2A
10700
1
A(00)GAS001
Level 3A
14300
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 100
Project Number A(00)GAS001
Author
Section 001
Project Name
Project Status
12/06/13Checker
1 : 100Section 11 1 : 100
Section 32
Level 0
0
Level 1
4000
Level 2
8000
Level 3
12000
Level 4
16000
1
A(00)GAS002
1200
0
Level 5
17500
ABCDEF-
---
Basement
-4000
2
A(00)GAS002
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAS001
Author
Section 001
46 Westgate
Planning
12/06/13Checker
1 : 50Section 11
UP
UP
1
A(00)GAS001
-
---
1 2 4 5 6
AB
C
D
E
F
3
2250
5000 4800 5000
11 m²113.4 SF
lift shaft7
11 m²122.9 SF
Mens WC8
16 m²174.7 SF
Womens WC9
7 m²73.1 SF
Plant access shaft10
3 m²36.2 SF
Cleaners Store11
6 m²62.2 SF
Disabled WC12
156 m²1676.0 SF
Theatre & GalleryEntrance
14
275 m²2963.4 SF
Gallery15
36 m²388.1 SF
Cafe16
2
A(00)GAS002
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP001
Author
Level 0 Plan
46 Westgate
Planning
01/06/14Checker
1 : 50Level 01
UP
DN
15890
3650
0
1825
018
250
1
A(00)GAS001
4000
-
---
2
A(00)GAS001
1
A(00)GAS001
-
---
2059
2
A(00)GAS001
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 100
Project Number A(00)GAP001
Author
Level 0 & 1 Plan
Project Name
Project Status
12/09/13Checker
1 : 100Level 01 1 : 100
Level 12
1 2 3 4 5 6
AB
C
D
F
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP000
Author
Basement Plan
46 Westgate
Planning
01/10/14Checker
UP
UP
1
A(00)GAS001
-
---
1 2 4 5 6
AB
C
D
E
F
3
2250
5000 4800 5000
11 m²113.4 SF
lift shaft7
11 m²122.9 SF
Mens WC8
16 m²174.7 SF
Womens WC9
7 m²73.1 SF
Plant access shaft10
3 m²36.2 SF
Cleaners Store11
6 m²62.2 SF
Disabled WC12
156 m²1676.0 SF
Theatre & GalleryEntrance
14
275 m²2963.4 SF
Gallery15
36 m²388.1 SF
Cafe16
2
A(00)GAS002
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP001
Author
Level 0 Plan
46 Westgate
Planning
01/06/14Checker
1 : 50Level 01
UP
DN
UP
1
A(00)GAS001
-
---
4600
3600
1 2 4 5 6
AB
C
D
E
F
3
2215
75 m²811.7 SF
Theatre17
10 m²108.4 SF
Dressing Room18 2
A(00)GAS002
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP002
Author
Level 1 Plan
46 Westgate
Planning
01/06/14Checker
1 : 50Level 11
UP
1
A(00)GAS001
-
---
1 2 4 5 6
AB
C
D
E
F
3
8 m²86.3 SF
WC21 52 m²
555.9 SF
Theatre Store / BackStage
22
4 m²47.6 SF
Plant Access Shaft23
267 m²2876.7 SF
Gallery24
2
A(00)GAS002
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP003
Author
Level 2 Plan
46 Westgate
Planning
01/06/14Checker
1 : 50Level 21
1
A(00)GAS001
-
---
1 2 4 5 6
AB
C
D
E
F
3
8 m²86.3 SF
WC26
476 m²5121.8 SF
Gallery27
2
A(00)GAS002
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP004
Author
Level 3 Plan
46 Westgate
Planning
01/06/14Checker
1 : 50Level 31
1 2 4 5 6
AB
C
D
E
F
3
Drawn
Dwg. No.
Scale at A1
Project No.
Drawing
Project
Status
Rev.
Date
this drawing is copyright - check all dimensions on site - inform architect / so of any discrepancies - work to figured dimensions only - do not scale
Rev. Amendment Date
Checked 1 : 50
003 A(00)GAP005
Author
Roof Plan
46 Westgate
Planning
01/10/14Checker
Structural Design
CK21 Meeting
Mega-nodes
Construction Process
foundations
basement retaining walls
steel columns 305 x 305 x 97UC
steel I-beams 305 x 165 x 40UB
primary mega-structure
secondary mega-structure
Next Week at Campus...
MEP Modelling
Clash Removal