Upload
miroslaw-dabrowski
View
2.732
Download
6
Embed Size (px)
Citation preview
PRIN
CE2®
, P3O
®, M
SP®,
MoP
®, M
_o_R
®, M
oV®,
ITIL
®, P
3M3®
are
regi
ster
ed tr
adem
arks
of A
XELO
S Lt
d. T
he sw
irl lo
go™
is a
trad
emar
k of A
XELO
S Lt
d
Course administration
Course introduction
Start and finish Course style
LunchCoffee and breaks
M00 - Course introduction 2/17 | 2/434
Course objectives
At the end of this course, you will be able to: The underpinning philosophy, principles,
terminology of PRINCE2 Understand PRINCE2 project lifecycle including
processes and themes Define PRINCE2 roles and responsibilities Describe PRINCE2 techniques and procedures The products/artefacts produced by PRINCE2Main goal Attempt Foundation exam with confidence Communicate freely within PRINCE2 project,
understanding its principles and philosophySecondary goal Benefits and value of project management and
PRINCE2
Course introduction
M00 - Course introduction 3/17 | 3/434
Please share with the class: Your name and surname Your organization Your profession Title, function, job responsibilities
Your familiarity with the project management
Your experience with PRINCE2/PMBOK/IPMA
Your personal session expectations
Course introduction
Let’s Get to Know Each Other
M00 - Course introduction 4/17 | 4/434
Day
1
Module Subject Start End Total Time(in hours)
01 Defining project management and PRINCE2 09:00 11:00 02:00
02 Organization theme 11:00 12:15 01:15
03 Starting up a Project (SP) 12:15 13:00 00:45
Lunch 13:00 13:30 00:30
04 Business Case theme 13:30 14:45 01:15
05 Initiating a Project (IP) 14:45 16:30 01:45
Recap Day 1 (including sample exam questions) 16:30 17:00 00:30
Total Training Time 08:00
Course agenda - Day 1
Course introduction
M00 - Course introduction 5/17 | 5/434
Day
2
Module Subject Start End Total Time(in hours)
Review Day 1 09:00 09:15 00:15
06 Plans theme 09:15 10:30 01:15
07 Quality theme 10:30 11:45 01:15
08 Risk theme 11:45 13:00 01:15
Lunch 13:00 13:30 00:30
09 Managing a Stage Boundary (MSB) 13:30 15:15 01:45
10 Progress theme 15:15 16:30 01:15
Recap Day 2 (including sample exam questions) 16:30 17:00 00:30
Total Training Time 08:00
Course agenda - Day 2
Course introduction
M00 - Course introduction 6/17 | 6/434
Day
3
Module Subject Start End Total Time(in hours)
Review Day 2 09:00 09:15 00:15
11 Controlling a Stage (CS) 09:15 10:45 01:30
12 Change theme 10:45 13:00 02:15
Lunch 13:00 13:30 00:30
13 Managing Product Delivery (MPD) 13:30 14:45 01:15
14 Closing a Project (CP) 14:45 15:15 00:30
15 Directing a Project (DP) 15:15 16:00 00:45
Foundation exam 16:00 17:00
Total Training Time 07:00
Course agenda - Day 3
Course introduction
M00 - Course introduction 7/17 | 7/434
PRINCE2 Foundation certification
Foundation Exam Paper based and closed book exam Only pencil and eraser are allowed Simple multiple (ABCD) choice exam Only one answer is correct 75 questions, pass mark is 35 (50%) max 70 points, 5 questions of control
1 hour exam No negative points, no “Tricky Questions”
No pre-requisite for Foundation exam Sample, two (official) mock exams are
provided to you
Course introduction
Candidates completing an examination in a language that is not their mother tongue, will receive additional time
M00 - Course introduction 8/17 | 8/434
PRINCE2 Practitioner certification
Practitioner Exam Paper based and open book exam Reference to PRINCE2 Handbook ONLY
Handbook is provided for students
2:30 hour exam 4 questions worth 20 marks each (80
marks), pass mark is 35 (50%) Dictionary/translation lists allowed for non-
native speakers Non-scientific calculator for basic
calculations
Foundation certification is required
Course introduction
Candidates completing an examination in a language that is not their mother tongue, will receive additional time
M00 - Course introduction 9/17 | 9/434
PRINCE2 Professional certification
Professional Exam (January 2012) Assessment is against 19 individual
performance criteria (there is no written examination) Level 0, 1, 2, 3
2.5 day exam (in PRINCE2 Professional assessment centre)
Group activities and exercises (usually in groups of 4, as well as a one-to-one interview, and your performance will be rated)
Based on a fictional project case study
Practitioner certification is required
Course introduction
Candidates completing an examination in a language that is not their mother tongue, will receive additional time
M00 - Course introduction 10/17 | 10/434
PRINCE2 official handbook and examination syllabus
Course introduction
PRINCE2 syllabus section code and titleOV Overview, Principles and Tailoring PRINCE2BC Business Case themeOR Organization themeQU Quality themePL Plans themeRK Risk themeCH Change themePG Progress themeSU Starting up a Project processDP Directing a Project processIP Initiating a Project processSB Managing a Stage Boundary processCS Controlling a Stage processMP Managing Product Delivery processCP Closing a Project process
Module slide number / total module slides
Slide number / total slides
Module number and name
Syllabus Handbook Page
PRINCE2handbook page
PRINCE2 syllabus section code
M00 - Course introduction 11/17 | 11/434
PRINCE2 interactive study guide mind map
Course introduction
See Appendix #2 for more mind maps from AXELOS Global Best Practice
M00 - Course introduction 12/17 | 12/434
PRINCE2 interactive glossary
Course introduction
quizlet.com/45249735/
M00 - Course introduction 13/17 | 13/434
PRINCE2 Project Processes vs Products vs Roles vs Responsibilities Matrix
Course introduction
M00 - Course introduction 14/17 | 14/434
PRINCE2 Process model
Course introduction
M00 - Course introduction 15/17 | 15/434
PRINCE2 – Free complete set of PRINCE2 document templates
Course introduction
M00 - Course introduction 16/17 | 16/434
About course author - Mirosław Dąbrowski
Course introduction
twitter.com/mirodabrowski
linkedin.com/in/miroslawdabrowskigoogle.com/+miroslawdabrowski
miroslaw_dabrowski
www.miroslawdabrowski.com
Mirosław DąbrowskiAgile Coach, Trainer, Consultant(former JEE/PHP developer, UX/UI designer, BA/SA)
Creator Writer / Translator Trainer / Coach
• Creator of 50+ mind maps from PPM and related topics (2mln views): miroslawdabrowski.com
• Lead author of more than 50+ accredited materials from PRINCE2, PRINCE2 Agile, MSP, MoP, P3O, ITIL, M_o_R, MoV, PMP, Scrum, AgilePM, DSDM, CISSP, CISA, CISM, CRISC, CGEIT, TOGAF, COBIT5 etc.
• Creator of 50+ interactive mind maps from PPM topics: mindmeister.com/users/channel/2757050
• Product Owner of biggest Polish project management portal: 4PM: 4pm.pl (15.000+ views each month)
• Editorial Board Member of Official PMI Poland Chapter magazine: “Strefa PMI”: strefapmi.pl
• Official PRINCE2 Agile, AgilePM, ASL2, BiSL methods translator for Polish language
• English speaking, international, independenttrainer and coach from multiple domains.
• Master Lead Trainer & Coach• 11+ years in training and coaching / 15.000+ hours• 100+ certifications• 5000+ people trained and coached• 25+ trainers trained and coached
linkedin.com/in/miroslawdabrowski
Agile Coach / Scrum Master PM / IT architect Notable clients
• 8+ years of experience with Agile projects as a Scrum Master, Product Owner and Agile Coach
• Coached 25+ teams from Agile and Scrum• Agile Coach coaching C-level executives • Scrum Master facilitating multiple teams
experienced with UX/UI + Dev teams• Experience multiple Agile methods• Author of AgilePM/DSDM Project Health Check
Questionnaire (PHCQ) audit tool
• Dozens of mobile and ecommerce projects• IT architect experienced in IT projects with budget
above 10mln PLN and timeline of 3+ years• Experienced with (“traditional”) projects under high
security, audit and compliance requirements based on ISO/EIC 27001
• 25+ web portal design and development and mobile application projects with iterative,incremental and adaptive approach
ABB, AGH, Aiton Caldwell, Asseco, Capgemini, Deutsche Bank, Descom, Ericsson, Ericpol, Euler Hermes, General Electric, Glencore, HP Global Business Center, Ideo, Infovide-Matrix, Interia, Kemira, Lufthansa Systems, Media-Satrun Group, Ministry of Defense (Poland), Ministry of Justice (Poland), Nokia Siemens Networks, Oracle, Orange, Polish Air Force, Proama, Roche, Sabre Holdings, Samsung Electronics, Sescom, Scania, Sopra Steria, Sun Microsystems, Tauron Polish Energy, Tieto, University of Wroclaw, UBS Service Centre, Volvo IT…miroslawdabrowski.com/about-me/clients-and-references/
M00 - Course introduction 17/17 | 17/434
Accreditations/certifications (selected): CISA, CISM, CRISC, CASP, Security+, Project+, Network+, Server+, Approved Trainer: (MoP, MSP, PRINCE2, PRINCE2 Agile, M_o_R, MoV, P3O, ITIL Expert, RESILIA), ASL2, BiSL, Change Management, Facilitation, Managing Benefits, COBIT5, TOGAF 8/9L2, OBASHI, CAPM, PSM I, SDC, SMC, ESMC, SPOC, AEC, DSDM Atern,DSDM Agile Professional, DSDM Agile Trainer-Coach, AgilePM, OCUP Advanced, SCWCD, SCBCD, SCDJWS, SCMAD, ZCE 5.0, ZCE 5.3, MCT, MCP, MCITP, MCSE-S, MCSA-S, MCS, MCSA, ISTQB, IQBBA, REQB, CIW Web Design / Web Development / Web Security Professional, Playing Lean Facilitator, DISC D3 Consultant, SDI Facilitator, Certified Trainer Apollo 13 ITSM Simulation …
11. Progress theme12. Controlling a Stage (CS)13. Change theme14. Managing Product Delivery
(MPD)15. Closing a Project (CP)16. Directing a Project (DP)
1. Defining project management and PRINCE2
2. PRINCE2 principles3. Organization theme4. Starting up a Project (SP)5. Business Case theme6. Initiating a Project (IP)7. Plans theme8. Quality theme9. Risk theme10. Managing a Stage Boundary
(MSB)
Agenda
Defining project management and PRINCE2
M01 - Defining project management and PRINCE2 2/29 | 19/434
What is PRNCE2?
PRINCE2 is detailed project management method (HOW) PRINCE2 is a structured (sequential) project management
method based on principles and themes that originate from lessons learned from projects
The PRINCE2 project management approach is: process based product based
PRINCE2 provides easy to understand project lifecycle PRINCE2 creates project organisation structure with clearly
defined roles and responsibilities PRINCE2 recognizes performance projects factors for time,
costs, quality, scope, benefits and risks
Defining project management and PRINCE2
M01 - Defining project management and PRINCE2 3/29 | 20/434
1970s•PROMPT
1983•PROMPT II
1996•PRINCE2
2002•PRINCE2
update
2005•PRINCE2
update
2009•PRINCE2
update
2013•AXELOS
acquisition (new logo)
•No changes in content
2015•PRICE2 Agile
PRINCE2 history
Defining project management and PRINCE2
M01 - Defining project management and PRINCE2 4/29 | 21/434
Project definition according to PRINCE2
Defining project management and PRINCE2
© A
XELO
S Lt
d. 2
013.
Mat
eria
l is
repr
oduc
ed u
nder
lice
nce
from
AXE
LOS.
"A temporary organization that is created for the purpose of
delivering one or more business products according to an agreed
Business Case"
3OV0102M01 - Defining project management and PRINCE2 5/29 | 22/434
Project management cycle according to PRINCE2
Defining project management and PRINCE2
© A
XELO
S Lt
d. 2
013.
Mat
eria
l is
repr
oduc
ed u
nder
lice
nce
from
AXE
LOS.
Plan
Delegate
Monitor
Control
5M01 - Defining project management and PRINCE2 6/29 | 23/434
5 Factors that differentiate Projects from Business As Usual (BAU)
Defining project management and PRINCE2
Factor
Change Temporary Cross-Functional Unique Uncertainty
3OV0203
Changes in the business as Usual (BAU) in the form of a new products delivered by the project and with those new products there will be changes in the organization (e.g. new processes, training to the end users, etc.).
The project has a finite beginning and end of what distinguishes it from what every day dealing with the client organization.
Similarly each project phase has it's starting and ending date (with agreed tolerances).
Customers and suppliers have various perspectives, motivations, expectations and attitudes to the project
Bringing together of a temporary team with different skills working together to introduce a change that will impact others outside of the team.
The project is implemented in a unique environment / context
Among other things, the uniqueness is also another period of time in which the project is conducted (different place in time, different laws and regulations, etc.)
Project involves a higher risk level than regular business operations
Each project is uncertain venture can be successful or a failure to enhance the chance of successful completion of the project we need to manage uncertainty in the project, i.e.. the risk
M01 - Defining project management and PRINCE2 7/29 | 24/434
6 project performance variables (effectiveness aspects)
Defining project management and PRINCE2
Project
costs
timescales
quality
scope
risk
benefits
5OV0101M01 - Defining project management and PRINCE2 8/29 | 25/434
PRINCE2 structure
PRINCE2 method involves 4 integrated elements: The principles - 7 rules (a project compliant with PRINCE2 must be
compliant with all the principles) The themes - 7 project management areas The processes - 7 groups of activities specifying step by step what
should/must be done within the project its lifecycle Tailoring PRINCE2 to the project - tailoring PRINCE2 method to suit
the project/organisation environment/context requirements
PRINCE2 method also provides 2 general techniques: product-based planning quality review
Defining project management and PRINCE2
5OV0103M01 - Defining project management and PRINCE2 9/29 | 26/434
PRINCE2 Themes
PRINCE2 Principles
Progress
BusinessCase
Organisation
Quality
Risk
Change
Plans
PROJECT ENVIRONMENT
© A
XELO
S Lt
d. 2
013.
Mat
eria
l is
repr
oduc
ed u
nder
lice
nce
from
AXE
LOS.
PRINCE2 Processes
6OV0103M01 - Defining project management and PRINCE2 10/29 | 27/434
Pre-project Initiationstage
Final deliverystage
After the project
Subsequent delivery stage(s)
Subsequent delivery stage
General process model at PRINCE2
Defining project management and PRINCE2
© A
XELO
S Lt
d. 2
013.
Mat
eria
l is
repr
oduc
ed u
nder
lice
nce
from
AXE
LOS.
113OV0206
Legend• SP - Starting up a Project• IP - Initiating a Project • SB - Managing a Stage Boundary
• MPD - Managing Product Delivery • CP - Closing a Project • DP - Directing a Project• CS - Controlling a Stage
Directing
Managing
Delivering
SP
IP CS CS CS
MSB MSB MSB CP
DP
MPD MPD MPD MPD MPDMPD
MPD MPD MPD
M01 - Defining project management and PRINCE2 11/29 | 28/434
Pre-project Initiationstage
Final deliverystage Post-project
Two-stage project PRINCE2 model
Defining project management and PRINCE2
DP
MSB CP
IP
SPDirecting
Managing
DeliveringMPD
CS
MPD
MPD
© A
XELO
S Lt
d. 2
013.
Mat
eria
l is
repr
oduc
ed u
nder
lice
nce
from
AXE
LOS.
Legend• SP - Starting up a Project• IP - Initiating a Project • SB - Managing a Stage Boundary
• MPD - Managing Product Delivery • CP - Closing a Project • DP - Directing a Project• CS - Controlling a Stage
A project has at least 2 management stages:• Initiation stage (during which
the project is planned)• At least one more to cover
the delivery of the project’s specialist products
OV0206M01 - Defining project management and PRINCE2 12/29 | 29/434
Directing
Managing
Delivering
DP
Pre-projectInitiation Stage +
Final deliverystage
Post-project
One-stage project PRINCE2 model (shortest possible version of PRINCE2)
Defining project management and PRINCE2
© A
XELO
S Lt
d. 2
013.
Mat
eria
l is
repr
oduc
ed u
nder
lice
nce
from
AXE
LOS.
OV0206
SP
CP
IP
CS
MPDMPD
MPD
Legend• SP - Starting up a Project• IP - Initiating a Project • SB - Managing a Stage Boundary
• MPD - Managing Product Delivery • CP - Closing a Project • DP - Directing a Project• CS - Controlling a Stage
M01 - Defining project management and PRINCE2 13/29 | 30/434
What PRINCE2 does not provide?
PRINCE2 method does not include: Specialist aspects (PRINCE2 is purely general in
nature, not industry/domain specific) Detailed project management techniques (see
PMBOK Guide) Leadership/coaching/mentoring skills Soft-skills Communication techniques Human resource management Contract negotiations Software for project management …
Defining project management and PRINCE2
6M01 - Defining project management and PRINCE2 14/29 | 31/434
Applies to any type or project and business domain Project security with EWIs and risk management Accountability with clearly defined roles Project process analysis and optimisation Efficient use of senior management
time by “management by exception” License-free Full project control/assurance Common vocabulary and approach Tailored project documentation Proven integration with Agile (e.g. DSDM/Scrum)
Defining project management and PRINCE2
Key benefits of adopting PRINCE2
7OV0201M01 - Defining project management and PRINCE2 15/29 | 32/434
PRINCE2 and integration with Agile -> Proven integration between PRINCE2 and Agile…
Defining project management and PRINCE2
Keith Richards, KRC Consultants; Lead Author of:• DSDM Atern (method and official handbook)• Agile Project Management: Running PRINCE2
Projects with DSDM Atern
Agile Project Management: Running PRINCE2 Projects with DSDM Atern• ISBN-13: 978-0113310586• Publisher: TSO (The Stationery Office) (2007)
M01 - Defining project management and PRINCE2 16/29 | 33/434
PRINCE2 and integration with Agile -> PRINCE2 Agile
Defining project management and PRINCE2
Keith Richards, agileKRC; Lead Author of:• PRINCE2 Agile (method and official handbook)
M01 - Defining project management and PRINCE2 17/29 | 34/434
Relationship with other AXELOS Global Best Practices
Defining project management and PRINCE2
Portfoliomanagement
Portfolio(s) Office
Programmemanagement
Programme(s)Office
Project(s) Office
Projectmanagement
Projectmanagement
Projectmanagement
Man
agem
ent o
f Risk
(M_o
_R)
ITIL
Man
agem
ent o
f Val
ue (M
oV)
6
RESI
LIA
M01 - Defining project management and PRINCE2 18/29 | 35/434
The Portfolio, Programme, and Project
Management Maturity
Model (P3M3)
ITILMaturity
Model(IMM)
Relationship with other AXELOS Global Best Practices and Models
Defining project management and PRINCE2
ITILPortfolio, Programme and Project
Offices(P3O)
Management of Value(MoV)
Management of Risk
(M_o_R)
Best practice guides
AXELOS common glossary
PRINCE2Maturity
Model(P2MM)
Models
(MoP)Management of Portfolios
(MSP)Managing Successful Programmes
(PRINCE2)PRojects IN Controlled Environments
Portfolio Office
Programme Office
Project Office
RESILIA
M01 - Defining project management and PRINCE2 19/29 | 36/434
How PRINCE2 fits with other AXELOS Global Best Practice Guides
Defining project management and PRINCE2
P3O
MoP
M_o_R
MSPMoV
ITIL
RESILIA
Can be used as a method for delivering IT projects having requirements regarding reporting, compliance, control and risk management
Integrates with PMOs by dedicated roles strictly responsible for project support and project assurance
Support project monitoring and control at the portfolio level with KPIs, KRIs and EWIs
PRINCE2 uses risk management process defined in M_o_Rallowing PRINCE2 to be easily integrated within enterprise risk management (ERM)
Offers predictable products delivery within programme
Provides framework for producing products acting as options for value improvement proposals framework
Can be used as a method for implementing Cyber Resilience into IT services
M01 - Defining project management and PRINCE2 20/29 | 37/434
M01 - Defining project management and PRINCE2 21/29 | 38/434
PRINCE2 in numbers (version 2009)
Defining project management and PRINCE2
7
7
7
40
10
4
2
2
5
6
26
Principles
Themes
Processes
Sub-processes
Project roles
QA roles
Procedures
Techniques
Project factors
Performance factors
Management products
3Issue types3 Budget types
M01 - Defining project management and PRINCE2 22/29 | 39/434
M01 - Defining project management and PRINCE2 23/29 | 40/434
World’s best known Project Management standardization/certifications bodies
Defining project management and PRINCE2
M01 - Defining project management and PRINCE2 24/29 | 41/434
World’s best known Project Management publications
Defining project management and PRINCE2
4th version(2015)
5th version(2013)
4th version(2009)
6th version(2012)
11th version
M01 - Defining project management and PRINCE2 25/29 | 42/434
AXELOS PRINCE2, PMI PMBOK Guide, IPMA ICB, APM Body of Knowledge, TenStep
Defining project management and PRINCE2
PRINCE2 PMI PMBOK Guide IPMA ICB APM Body of Knowledge TenStep
Type Methodology/Method Standard Competency Best Practice Methodology
Model Process based Process based Competency/skills based Recommendations/ Guidelines Process based
Roles & responsibilities PM competencies
Tools & Techniques 2
Document outlines
Soft skills mentioned
Certifications Foundation, Practitioner, Professional, Agile
CAPM, PMP, PGMP, PFMP, PMI-SP, PMI-
RMP, PMI-ACP, PMI-PBALevel D, C, B, A
APM IC, APMP, APM PPQ, PQ, APM Project Risk
Management L1 and L2Fn-TSPM, TSPM
Accr
edita
tion
of training materials
Commercialmethodologytrainers PMP required
training organizations
in some countries only, not unified
Number of certified people
Foundation: 776,000+Practitioner: 400,000+
Professional: 100+PRINCE2 Agile: -
CAPM: 30,000+PMP: 686,500+
PMI-ACP: 10,000+
Level D: 170,000+Level C: 61,000+Level B: 13,000+
Level A: 800+
no data no data
M01 - Defining project management and PRINCE2 26/29 | 43/434
Module review and summary
Project definition Project management cycle 5 Factors that differentiate
Projects from BAU 6 project performance
variables PRINCE2 structure 7 Principles 7 Themes 7 Processes Tailoring PRINCE2 project
PRINCE2 general process model
What PRINCE2 does not provide
Key benefits of adopting PRINCE2
Defining project management and PRINCE2
M01 - Defining project management and PRINCE2 27/29 | 44/434
Q&A
Defining project management and PRINCE2
M01 - Defining project management and PRINCE2 28/29 | 45/434
I hope you enjoyed this presentation. If so, please like, share and
leave a commentbelow.
Endorsements on LinkedIn are also
highly appreciated! (your feedback = more free stuff)
MIROSLAWDABROWSKI.COM/downloads