IMPROVING PROJECT HANDOVER

APM Improving project handover, 6 April 2017

Embed Size (px)

Citation preview

Page 1: APM Improving project handover, 6 April 2017

IMPROVING PROJECT

HANDOVER

Page 2: APM Improving project handover, 6 April 2017

RESEARCH TOPIC

How can we hand

projects over better?

Page 3: APM Improving project handover, 6 April 2017
Page 4: APM Improving project handover, 6 April 2017
Page 5: APM Improving project handover, 6 April 2017
Page 6: APM Improving project handover, 6 April 2017
Page 7: APM Improving project handover, 6 April 2017
Page 8: APM Improving project handover, 6 April 2017
Page 9: APM Improving project handover, 6 April 2017
Page 10: APM Improving project handover, 6 April 2017
Page 11: APM Improving project handover, 6 April 2017
Page 12: APM Improving project handover, 6 April 2017
Page 13: APM Improving project handover, 6 April 2017

A project is a delivery device for benefits

Handover is the start not the end

Page 14: APM Improving project handover, 6 April 2017
Page 15: APM Improving project handover, 6 April 2017

“At 30 September 2015 the GMPP

contained 143 major projects representing

a £405 billion investment over the next 25+

years that will improve the UK’s

infrastructure, transform public services and

safeguard national security”

Infrastructure and Projects Authority

Annual Report on Major Projects 2015-16

APM:

22,350 individual and 590

corporate members

making it the largest

professional body of its

kind in Europe

Page 16: APM Improving project handover, 6 April 2017

“Worldwide, infrastructure spending will grow from $4 trillion per year in

2012 to more than $9 trillion per year by 2025. Overall, close to $78

trillion is expected to be spent globally between 2014 and 2025.”

Capital project and infrastructure spending Outlook to 2025 - PWC &

Oxford Economics

Page 17: APM Improving project handover, 6 April 2017

x 78

Page 18: APM Improving project handover, 6 April 2017

Infrastructure projects alone

equate to 12% of GLOBAL GDP

Page 19: APM Improving project handover, 6 April 2017

A GOOD HANDOVER

The client gets what they pay for, when they were expecting to get it, it

does what you all agreed it would and they know what to do with it once

they’ve got it

Page 20: APM Improving project handover, 6 April 2017

A GOOD HANDOVER

You as PM have done your job well – reputation / market value /

personal satisfaction

You walk away feeling good leaving happy clients

You get more work – you sold a good car!

Page 21: APM Improving project handover, 6 April 2017

After 2 months, PMs are rarely judged on how well they managed the

project, they are judged on whether the benefits the project was funded to

deliver in the first place actually transpired.

As a practitioner, are you prepared to leave your professional reputation in

the hands of people improperly briefed?

Page 22: APM Improving project handover, 6 April 2017
Page 23: APM Improving project handover, 6 April 2017

APPROACH

Page 24: APM Improving project handover, 6 April 2017

INTERVIEWS:

Page 25: APM Improving project handover, 6 April 2017

OUTPUTS

Page 26: APM Improving project handover, 6 April 2017

WHAT IS HANDOVER?

“The point in the life cycle where

deliverables are handed over to the sponsor

and users”. APM

“The project should have a clear end with a

correct handover of information and

responsibility.” PRINCE2

Page 27: APM Improving project handover, 6 April 2017

MAYBE IT’S…

practical completion.

the end of the defects and liability period

when the on site support from the project team leaves site

no more snags noted on the snagging list and all are signed off as complete

once the last of three post occupancy evaluations is completed

when no members of the project team are involved on a scheme anymore

financial close

when the benefits established at the outset have been delivered (which

could be when the project deliverables have completed their lifespan and

been decommissioned)

Page 28: APM Improving project handover, 6 April 2017

How would

you define

“handover”?

Page 29: APM Improving project handover, 6 April 2017

IT’S NOT A DATE

IT’S A PROCESS

Page 30: APM Improving project handover, 6 April 2017

HANDOVER IS A TRANSITION

of…

Ownership

Management

Responsibility

Knowledge

Continuity

Benefit realisation

Operational responsibility

Page 31: APM Improving project handover, 6 April 2017

SURVEY RESPONDENTS:

Page 32: APM Improving project handover, 6 April 2017

TOP 2 CONSENSUS POSITIONS – 85%

AGREE

Page 33: APM Improving project handover, 6 April 2017
Page 34: APM Improving project handover, 6 April 2017
Page 35: APM Improving project handover, 6 April 2017

“It often is but phasing would be better”

“The project team's behaviour is to focus on completion of the

project, and view end-user training as part of project

completion”

Page 36: APM Improving project handover, 6 April 2017

“Depends on the

client - outcomes can

be patchy as a result

of client's level of

requirements”

“The sub-

contractor

produces

documentation in a

standard format for

each project

delivery”

“Project teams only ever focus

on completing the project and

moving on their next project”

Page 37: APM Improving project handover, 6 April 2017

4 EMERGENT AREAS

Commercial / Contractual

Process

Data and Knowledge Transfer

People

Page 38: APM Improving project handover, 6 April 2017

TOP 3 FROM EACH AREA – COMMERCIAL /

CONTRACTUAL

Requirements need to be written in to tender

documentation / contracts in as much detail and as

specifically as possible. The more accurate the

specification, the more likely the output to fulfil the needs

of the commissioners.

Whole life cost must be considered if at all possible.

Incentivise success.

Page 39: APM Improving project handover, 6 April 2017

TOP 3 FROM EACH AREA – PROCESS

Handover is a process not a date. Planning for it should be from

the start of the project and it should be viewed as an incremental

transfer of knowledge and operation from project team to business as

usual. Incorporate a series of mini-handovers throughout the project

phase (sample rooms, dry runs, simulations, data readiness tests).

The benefits and deliverables must be measurable and

communicable from the start. ‘Softer’ benefits are still measurable

“What gets measured, gets managed”.

Involve end users from the outset.

Page 40: APM Improving project handover, 6 April 2017

TOP 3 FROM EACH AREA – DATA &

KNOWLEDGE TRANSFER

Documentation must be written for the end users.

Collate lessons learned as the project progresses. It

provides more meaningful data for future projects, it can be

tied to stage gateways or key deliverables. It also provides a

form of decision log

Agree the information requirements at the outset.

Page 41: APM Improving project handover, 6 April 2017

TOP 3 FROM EACH AREA – PEOPLE

Get good people on your project and keep them for as long as

you are able. Fight for the project team you want and fight to keep

them.

Definition of stakeholders should be carried out throughout

and in detail. Don’t assume a single end user representative is

sufficient or will yield the best outcomes.

The Client role is pivotal. Not necessarily in a ‘customer is always

right’ way although that is a factor. In the transcripts of the interviews

the word that was most frequently repeated was ‘client’.

Page 42: APM Improving project handover, 6 April 2017

How do you define “the client” and

what do you think their role would be?

Page 43: APM Improving project handover, 6 April 2017
Page 44: APM Improving project handover, 6 April 2017
Page 45: APM Improving project handover, 6 April 2017
Page 46: APM Improving project handover, 6 April 2017

What are their drivers?

What does a good transition mean to them?

Do they know what they need

to do to be ready?

Page 47: APM Improving project handover, 6 April 2017
Page 48: APM Improving project handover, 6 April 2017

What if there had been 2 sessions built

in as part of the purchase?

1. Come and see the car being made

& have a photo sat in the car

pressing all the buttons

2. Test drive at a local track?

Page 49: APM Improving project handover, 6 April 2017

3 THINGS TO CHECK TOMORROW

What changes in practice are required by BAU

to deliver them?

How can the project team better prepare

the end users in advance?

What benefits are your project(s) enabling?

Page 50: APM Improving project handover, 6 April 2017

THANK YOU