Upload
hiren-patel
View
115
Download
1
Embed Size (px)
DESCRIPTION
this might be helpful to you frnds.
Citation preview
City Gas Distribution in India Key Trends and Outlook
5th Annual Conference
9th March 2010
2.
Presentation Outline
Key Market Drivers and Developments
CGDCGDBusiness Business
EconomicsEconomics
Gas Supplies InfrastructureInfrastructure
PolicyPolicy Regulations
Key Discussion Points
Key Discussion Points
3.
Domestic discoveries and LNG sources provide a strong impetus to CGD development…
Supply ProjectionsSupply Projections
• Traditional sources of supply (APM gas) are declining
• Fields discovered in early NELP rounds have started production and some more expected to start in the medium term
• CBM fields to add to regional gas supplies
• Greenfield LNG import terminals as well as expansion plans of existing LNG terminals are proposed
0
50
100
150
200
250
300
FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17
MM
SCM
D
Existing Fields New Domestic Fields CBM New Gas Finds LNG
4.
• Domestic Supplies– As per the Gas utilization policy, CGD sector is prioritized after fertilizer,
petroleum and power projects
– Allocation from RIL’s KG-D6 field is 5 MMSCMD for domestic and CNG segments and additional of 2 MMSCMD on a fallback basis, for industrial & commercial segments
– Many power plants are being planned in expectation of additional natural gas supplies
– Demand of a city is relatively small with a slow build up phase, making it unattractive from the perspective of volumes
• RLNG Supplies– Significant LNG import capacity exists/planned, but securing volumes for a
sustainable CGD business could be an issue
…however it is important to secure supplies for the CGD sector
Though supplies have increased, securing gas could be a challenge for the CGD sector
Though supplies have increased, securing gas could be a challenge for the CGD sector
5.
New gas supplies have stimulated gas transmission development…
Current Future
• New pipelines to connect new demand centers – bidding initiated
• National Gas Grid to integrate sources with demand centers
• Gas Highways (under NGHDAI) being proposed to increase connectivity
6.
Regulations to have a significant bearing on investment flow in infrastructure…
2006 2007 2008 2009 2010
PNGRB Act Enacted
CGD regulations notified by PNGRB
Pipeline regulations notified
Potential refinements in regulations
More Cities
GOI notified the Board and the Act
PNGRB published EOIs for more than 60 cities and commenced bidding process for identified cities
7.
• Board has:
– Shown commitment to the spirit of the PNGRB Act
– Shown keenness to move with speed
– Adopted a consultative approach
– Laid emphasis on transparency
– Shown preference to less intrusive regulation
– Signaled independence
PNGRB has shown a proactive approach to ensure rapid development…
8.
A number cities bid out and a number of CGD projects are under implementation…
PNGRB has published EOIs for more than 60 citiesPNGRB has published EOIs for more than 60 cities
IGL
MNGL- Pune
CUGL – Agra & Lucknow
TNGCL - TRIPURA
VMSS – Baroda
BGL – VIJAYWADA
MGL- Mumbai
GGCL- Surat, Ank, Bharuch
UNDER IMPLEMENTATION
IMPLEMENTED
CGD BIDDING - PNGRB
AGL – M.P
Sabarmati Gas
Bokaro
GAEL- Faridabad
GAEL – A’bad & Baroda
BGL – HYDERABAD
GGL- Kota
GGL- Dewas
GGL - SONIPAT
CHANDIGARH
GHAZIABAD GGL- MEERUT
DSM -MATHURA
BGL – KAKINADA
RAJMUNDRI
YANAM
Green Gas- Kanpur & Bareilly
Allahabad & Jhansi
Shahdol
9.
…however recently the authorization power of PNGRB has been contested leading to a temporary pause
• High court order implies that PNGRB needs to secure powers for authorization.
• Steps are being taken to ensure that pace of development of infrastructure is not reduced.
• The recent bidding rounds have evoked an interest in the investor community and also among some companies not in the CGD business.
Many projects have been planned so that regions across India are covered in the next 5-10 years. An empowered regulator could facilitate faster
development of the infrastructure in CGD.
Many projects have been planned so that regions across India are covered in the next 5-10 years. An empowered regulator could facilitate faster
development of the infrastructure in CGD.
10.
Regulations have been conceptualized considering many parameters…
Intention to have serious bidders with thorough
workings
Intention to have serious bidders with thorough
workings
Level playing field to non-energy sector players
Level playing field to non-energy sector players
Flexibility of entering into technical tie-ups likely to allow entry of non-energy sector entities into the CGD space
Flexibility of entering into technical tie-ups likely to allow entry of non-energy sector entities into the CGD space
Benefits to new entity (Exclusivity)
Benefits to new entity (Exclusivity)
Time allowed by PNGRB for bid submission to allow entities to do a thorough working before submission of bids
(having 25 year validity)
Time allowed by PNGRB for bid submission to allow entities to do a thorough working before submission of bids
(having 25 year validity)
Five year marketing exclusivity for new cities to encourage faster network penetration with a view to capture
maximum customer base and enjoy commodity margins
Five year marketing exclusivity for new cities to encourage faster network penetration with a view to capture
maximum customer base and enjoy commodity margins
CGD Regulations encourage faster network coverage with benefits to both CGD entity and end- consumers
CGD Regulations encourage faster network coverage with benefits to both CGD entity and end- consumers
Benefits to consumer (Open Access)
Benefits to consumer (Open Access)
Open access of the distribution network after the exclusivity period to allow competition and choice to consumer
Open access of the distribution network after the exclusivity period to allow competition and choice to consumer
11.
…However recent bids show significant variation in the biddable parameters suggesting a ‘Need to Rethink’
0
100
200
300
400
Year 1
Year 3
Year 5
Year 7
Year 9
Year 1
1Yea
r 13
Year 1
5Yea
r 17
Year 1
9Yea
r 21
Year 2
3Yea
r 25
B1 B2 B3
NETWORK TARIFFNETWORK TARIFF
0
5
10
15
20
25
Year 1
Year 3
Year 5
Year 7
Year 9
Year 1
1
Year 1
3
Year 1
5
Year 1
7
Year 1
9
Year 2
1
Year 2
3
Year 2
5
B1 B2 B3
COMPRESSION CHARGECOMPRESSION CHARGE
0
50
100
150
200
250
300
Year 1 Year 2 Year 3 Year 4 Year 5
B1 B2 B3
INCH KMINCH KM
0
5000
10000
15000
20000
25000
30000
Year 1 Year 2 Year 3 Year 4 Year 5
B1 B2 B3
NOS. OF DOMESTIC CONSUMERSNOS. OF DOMESTIC CONSUMERS
Rs/
MM
Btu
Rs/
Kg
12.
Rethinking may be required on several counts such as …
To provide consumers lowest possible network tariff & compression charge. This would eventually reduce the delivered price to customer
To provide consumers lowest possible network tariff & compression charge. This would eventually reduce the delivered price to customer
Regulation’s IntentionRegulation’s Intention
Will lowest tariff hamper future network expansion plans ?
Should low/zero tariff be encouraged?
Will lowest tariff hamper future network expansion plans ?
Should low/zero tariff be encouraged?
Question ?Question ?
Faster penetration of distribution network and reach to all segments of consumers
Faster penetration of distribution network and reach to all segments of consumers
Regulation’s IntentionRegulation’s Intention
Is there some assumption made in respect of monitoring mechanism?
Is there some assumption made in respect of monitoring mechanism?
Question ?Question ?
Recent bids and authorization process have raised questions on efficacy of regulations. However, it should be appreciated that regulation evolves over a period of time and a healthy debate among the stakeholders would
assist the evolution process to be faster.
Recent bids and authorization process have raised questions on efficacy of regulations. However, it should be appreciated that regulation evolves over a period of time and a healthy debate among the stakeholders would
assist the evolution process to be faster.
13.
Some rethinking on policy front could make the CGD segment more attractive…(Report of the Expert Group)
• Domestic Segment - LPG
– Prices to be increased by at-least Rs 100
– Prices to be periodically revised based on increase in paying capacity
• CNG Segment – Petrol and Diesel
– Prices to be market determined both at the Refinery gate and Retail
level
Reduced subsidization in pricing of alternative fuels will further enhance business economics of CGD entities
Reduced subsidization in pricing of alternative fuels will further enhance business economics of CGD entities
14.
Climate change related initiatives to further boost market attractiveness of CGD business…
India’s target on reducing carbon intensity
India’s target on reducing carbon intensity
• Days before the Copenhagen Summit India had declared a target of reducing amount of CO2emissions per unit of GDP by 20-25% between 2005 and 2020
• This should lead to greater emphasis on natural gas, which produces for the same amount of heat lesser CO2 relative to liquid fuels (30% lesser) and coal (45% lesser)
• Days before the Copenhagen Summit India had declared a target of reducing amount of CO2emissions per unit of GDP by 20-25% between 2005 and 2020
• This should lead to greater emphasis on natural gas, which produces for the same amount of heat lesser CO2 relative to liquid fuels (30% lesser) and coal (45% lesser)
Methane-to-Market (M2M) initiative
Methane-to-Market (M2M) initiative
• Goal of promoting recovery and usage of methane from coal mines, landfills, oil and gas fields, etc
• Potential to reduce net methane emissions by up to 50 MMTPA of carbon equivalent by 2015 and continue at that level or higher in the future
• Goal of promoting recovery and usage of methane from coal mines, landfills, oil and gas fields, etc
• Potential to reduce net methane emissions by up to 50 MMTPA of carbon equivalent by 2015 and continue at that level or higher in the future
15.
Going forward, some concerns of the stakeholders would need to be addressed (1/2)
• Players
– Will sector be able to secure gas supplies?
– Will the PSU domination in bidding continue?
– Will aggressive bidding be allowed?
– Would pricing reform for alternative fuels be implemented?
•Consumers
– If a license is issued for a city does it mean that consumers will get
connected as envisaged?
– What if the selected entity is weak or underperforming?
16.
Going forward, some concerns of the stakeholders would need to be addressed (2/2)
Investors
– Will the CGD business economics continue to remain attractive?
– How will the business risks change?
– What type of new players would be interested in the CGD business?
Regulator
– How should the bid process change taking into account the experience
from the past bidding rounds?
– Will all the required powers be vested in PNGRB to enable it function
effectively?
17.
To summarize…Significant infrastructure projects
planned to cover the key regions of
country
Government initiatives on
climate change, pricing
of alternative fuels are all supportive of CGD market development
Improved availability of domestic gas supplies but securing supplies would be important
Gas Supplies
Regulations
First ever competitive bidding of
CGD in the country.
Learnings and “need for rethink”
Healthy debate required for further evolution of regulations.
CGDCGDBusiness Business
EconomicsEconomics
Gas Supplies InfrastructureInfrastructure
PolicyPolicy Regulations
18.
CRISIL Risk and Infrastructure Solutions LimitedA Subsidiary of CRISIL Limited
www.crisil.com
19.
0
5
10
15
20
25
30
35
Industrial Domestic CNG Commercial
$/M
MBt
u
Delivered Price of Gas Alternate Fuel Prices
Though CGD business looks profitable but underlying risks needs to be appreciated
Margins of various segments
Volume intensity
High margin segment doesn’t offer good volume intensity
Industrial Retail
Bulk
Low High
High
LowDomestic
CNGCommercial
ProfitabilityWeighted Average
Cost of Gas + Network charge
Margins•Commodity•Infrastructure
Discount to Alternate Fuel
Long gestation period coupled with low volume off-take can adversely impact the CGD business.
Long gestation period coupled with low volume off-take can adversely impact the CGD business.
A typical CGD networks costs around Rs.250-300 Crores to service volumes of a level of around 1.5 MMSCMD. The build-up of volumes is quite slow and customer penetration of a reasonable
level of 50-60% is achieved only after 9-10 years.
20.
Returns of CGD business is a function of margins on commodity , infrastructure and overall volumes
Margins Commodity
Operational Costs
Demand
Supply of Commodity
Profitability
Volumes
Pricing[Alternate Fuels]
Commodity Costs
Margins Infrastructure
Asset Utilization
External Factors
• Crude Prices• Regulations• Policy Issues•Demand-Supply dynamics
There are significant external factors such as crude prices, regulations / policies that can impact the overall returns
There are significant external factors such as crude prices, regulations / policies that can impact the overall returns
21.
Implementation of City Gas Distribution - Benefits to all stakeholders
• Industrial consumers
– Continuous supply
– Low inventory cost
– Increased operational efficiency
• Domestic and commercial customers
– Cleaner fuel
– More convenient fuel alternative –indoors
• Transportation
– Reduces emissions
– Higher safety in combustion (higher flash point)
– Quieter operation (less vibration and less odour than diesel)
• Reduction of import dependence as NG replaces FO, LPG and Diesel
• Reach of LPG cylinders in rural areas
• Feel good factor – convenience, savings
Benefits to GovernmentBenefits to Government
The returns of CGD business is not only limited to the CGD entity but benefits all the stakeholders
The returns of CGD business is not only limited to the CGD entity but benefits all the stakeholders
Benefits to ConsumersBenefits to Consumers
• Better environment as adoption of NG significantly reduces the CO2 emissions
Benefits to SocietyBenefits to Society
• Higher realization at retail level compared to bulk sales acts as an incentive for gas suppliers
Benefits to Upstream entitiesBenefits to Upstream entities