Idaho Capitol Commission Capitol Restoration and Expansion Gary A. Daniel Idaho Capitol Commission

State Capitol Restoration 2

Embed Size (px)

DESCRIPTION

A view of the most critical phases of the Idaho State Capitol restoration from its 30-month mid point through the final finishes of the upper floors.

Citation preview

Page 1: State Capitol Restoration 2

Idaho Capitol Commission

Capitol Restoration and

Expansion

Gary A. DanielIdaho Capitol Commission

Page 2: State Capitol Restoration 2

Capitol RestorationApril 2008

Page 3: State Capitol Restoration 2

May 2008

Capitol Restoration

Page 4: State Capitol Restoration 2

June 2008

Capitol Restoration

Page 5: State Capitol Restoration 2

July 2008

Capitol Restoration

Page 6: State Capitol Restoration 2

August 2008

Capitol Restoration

Page 7: State Capitol Restoration 2

August 2008

Capitol Restoration

Page 8: State Capitol Restoration 2

September 2008

Capitol Restoration

Page 9: State Capitol Restoration 2

October 2008

Capitol Restoration

Page 10: State Capitol Restoration 2

Capitol Restoration

Page 11: State Capitol Restoration 2

Capitol RestorationNovember 2008

Page 12: State Capitol Restoration 2

December 2008

Capitol Restoration

Page 13: State Capitol Restoration 2

December 2008

Capitol Restoration

Page 14: State Capitol Restoration 2

Capitol Restoration

Page 15: State Capitol Restoration 2

Capitol RestorationJanuary 2009

Page 16: State Capitol Restoration 2

Capitol RestorationFebruary 2009

Page 17: State Capitol Restoration 2

Capitol RestorationMarch 2009

Page 18: State Capitol Restoration 2

Capitol RestorationApril 2009

Page 19: State Capitol Restoration 2

• Project budget: $122,500,000

• Expenditures thru 12/31/09: $121,500,000

• Scheduled Substantial Completion date: November 13, 2009

• Actual Substantial Completion• November 12, 2009