Transcript
Page 1: WPN2 Daily Activity Report 03-May-2011

 

SISI NUBI 2A PROJECT

DAILY ACTIVITY REPORTWPN2 Site Works

REPORTED DATE :

CUT OF TIME :

SAFETY MANPOWERTO DAY CUMM. NO. SUM

Manhour 1392 5112 1 TOTAL  : SPU   13 6.00 AM   Cloudy

CeRMA 0 0 2 TOTAL : ENG/PJC   20

Nearmiss 0 0 3   EPC‐1 : PT Meindo Elang Indah   83 12.00 AM   Clear

FAC 0 0 TOTAL :   116

RWDC 0 0   6.00 PM   Not reported

Material Damage 0 0   VESSEL/BARGEAccident/Incident 0 0   N O. V ES SE L/ BA RG E   PAX/POB   POSITION PUR POSE   12.00 PM   Not reported

HSE Induction 1 4 1 EB  507 211 / 250 WPN2 Acc. Barge

Tool Box 1 8 2 ASL Triaksa WPN2   AHT

Safety Talk 0 2 3 Pesut Mahakam WPN2 Crew Boat

HSE Drill 0 4 4 Logindo Sparrow WPN2 ‐ Handil Crew Boat

HSE Observation 0 0 5 Elang  Tangguh 101 WPN2 Tug Boat

6 S ur ya Indah WPN2 Tug  Boat

HIGHLIGHT ISSUEBPN Team conducted management visit for SIMOPS

Mustering & POB Control drill ‐ improvement on POB Control by counting from T‐Card

Start working on 8:30 due to late opening permit by OA (1 Operator, Gas Test only 1 ea) 

Piping activities waiting for JRA for piping  dismantling, unbolt ‐ bolt tightenin, flushing and drying, Leak test and grossleak

Equipment for Hydrotest still not available on site

 

ACTIVITYNO. TO DAY ACTIVITY PROGRESS NO. TOMORROW PLAN

1   Install gusset plate on weather deck for module 1 (3 of  7) 40% 1 Install gusset plate for mezzanine deck Module 1

2   Install cable tray support at lower deck 100% 2 Intsall E&I support at mezzanine deck

3   Install tubing tray support  at lower deck 100% 3 Intsall scaffolding at sump deck and lower deck

4   Modify manifold header at extension platform module 2 4 Fabrication at EB507

3‐May‐2011

6.00 PM (DAYSHIFT)

COMPANY

WEATHERDESCRIPTION

      S      A      F      E      T      Y      S      T      A      T      U      S

      S      A      F      E      T      Y      E      V      E      N      T

ns a   s ca o n g a  ower  ec   an   mezzan ne  ec rans er ma er a  y us ng crane  arge an   pe es a  crane

6   Fabrication at EB507   6   Install extension platform module 2

7   fit up & welding closed drain

TYPE OF WORK PERMIT SUM TYPE OF WORK PERMIT SUM

Hotwork Naked Flame   5   Hotwork Naked Flame   8

Hotwork Non Naked Flame   4   Hotwork Non Naked Flame   8

Cold Work   12   Cold Work   9

PROGRESSNo. Scope Description   % Completed : Plannned 7.3% Actual 9.5%

Structural   Completion Date : Baseline 27‐Jun‐2011 Forecast 27‐Jun‐2011

S001   Preparation work, scaffolding & install gusset plate for Module 2

S002   Preparation work, scaffolding & install gusset plate for Module 1

S003 Survey underwater

S004 Mudmat cutting removal

S005 Install Anode

S 00 6 CP Guide Under Water

S 00 7 CP Guide Above Water

S008 Extension Deck Module ‐2

S009 Extension Deck Module ‐1

S010 Install Appurtenance

Piping

P001 Install Temporary Platform, Lifting and Install  WHCP

P 00 2 F ir e Water

P 00 3 O pe n Drain

P004 Hydraulic

P005 Methanol Injection

P006 Closed Drain

P 00 7 W el l Service

P008 Venting

P009 Sample Connection

P010 Utillities

Electrical/Instrument

EI001 Support  Installation

EI002 Tray Installation

EI003 Tubing Installation

EI004 Instrument Cable Installation

EI005 Electrical & Grounding Cable Installation

EI006 Instrument & Electrical Installation

EI007 Instrument Cable Termination & Hook‐Up

EI008 Electrical Cable Termination & Hook‐Up   RFC Sub‐System

EI009 Sand Monitoring System   No of  Sub System   Issued Awaiting Rejected   Approved

EI010 Fire Gas Detector Modification & PCS/SSS Modiftcation   Approval

EI011 WHCP

EI012 Relocation Lighting due to Structural Module Installation

Reported by Sisi Nubi 2a Site Planner

ENG/PJC

0

1%

1%

0%

0%

020 0 0

5%

Planned 

Work Permit

0%

0%

Progress

100%

0%

On Going Work Permit

0%

21%

0%

0%

18%

24%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

30%

0%

0%

5%

0%

0%

 

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

12.00%

14.00%

16.00%

18.00%

20.00%

0%

20%

40%

60%

80%

100%

120%

     2     3

      ‐     A    p    r

     3     0

      ‐     A    p    r

     7      ‐

     M    a    y

     1     4

      ‐     M    a    y

     2     1

      ‐     M    a    y

     2     8

      ‐     M    a    y

     4      ‐

     J    u    n

     1     1

      ‐     J    u    n

     1     8

      ‐     J    u    n

     2     5

      ‐     J    u    n

     D    a     i     l    y     P    r    o    g    r    e    s    s     V    a     l    u    e

     C    u    m    m    u     l    a    t     i    v    e     P    r    o    g    r    e    s    s     V    a     l    u    e

Date

S‐Curve Actual vs Plan Progress

Plan Daily Progress Actual Daily Progress

CummulativePlan Daily P ro gr es s C um A ct ua l D ai ly Progress

Page 2: WPN2 Daily Activity Report 03-May-2011

Recommended