Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Work Accomplished to Date:• Install Water Service Connection into Foundations• Install Internal Plumbing• Completed 12” Pipe Installation at Maiden Lane Stream Crossing

Work Planned for Next Two Weeks:

September 6, 2021 to September 10, 2021• Install Water Services into Foundations• Install Plumbing Connections in Houses• Restoration of Maiden Lane Stream Crossing

September 13, 2021 to September 18, 2021

• Install Water Services into Foundations• Install Plumbing Connections in Houses

Page 1 of 5

Page 2: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Figure 1: Water Main Installation Summary Middletown and Durham

Page 2 of 5

Completed Waterline

Remaining Waterline to be installed

Water Line Project(30,202 feet total to install)

Start Date: September 8, 2019

Installed Pressure tested and disinfected

Feet % Feet %

29,610 100 23,584 78

Wells(128 total)

Start Date: TBD

Abandoned Converted to Monitoring Well

Number % Number %

0/125 0 0/3---,-:

Durh,~rn Center ystem

l--

1 ;L--\',_ 1---- \: ~~j I

-. ----•,.

i- H,;,,cu, --"-" ~ ;=-- r

Page 3: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Figure 2: Full-Service Connection SummaryDurham

Anticipated work limits for next two weeks

Page 3 of 5

Internal Plumbing Complete(119 total in Durham)

Start Date: May 2022

Installed Pressure tested and disinfected

Number % Number %

49 41 49 41

Connections into Foundations(119 total in Durham)

Start Date: May 2022

Installed

Number %

53 45

*---*

Page 4: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Figure 3: Main Structure SummaryMiddletown and Durham

Page 4 of 5

Altitude Valve VaultStart Date: April 5, 2021

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Cherry Hill Water Storage Tank

Booster Station

Meter Vault

Pressure Relief Valve and Vault

Long Hill Pump Station

Altitude Valve Vault

Booster StationStart Date: April 7, 2021

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Meter BuildingStart Date: TBA

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

PRV and VaultStart Date: November 2020

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Water Storage TankStart Date: May 2020

Pre-cast Building Set

Interior Work

Electrical

Instrumentation

Finish Site Work

Testing

Structure On-Line

Long Hill Pump StationStart Date: TBD

VFDs Installed

Hydropneumatic Tanks Removed

Chlorination System Installed

LegendPending

Ongoing

Complete

Page 5: Work Planned for Next Two Weeks: September 6, 2021 to

Bi-Weekly Progress ReportDurham Meadows Superfund Project, Durham & Middletown, CT

US Army Corps of Engineers Contract No. W912WJ19C0002September 3, 2021

Page 5 of 5

Maiden Lane Stream Crossing


Recommended