Transcript
Page 1: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Work Breakdown

Structure

Page 2: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Project Scope Management

• Includes the processes required to ensure

that the project includes all the work

required, and only the work required, to

complete the project successfully

– Collect Requirements

– Define Scope

– Create Work Breakdown Structure (WBS)

– Verify Scope

– Control Scope

Page 3: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Planning Processes

Work Breakdown

Structure with RAM

Estimate Duration

and Resources

Network Analysis

Schedule Development

Project Baseline

Page 4: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

A deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Each descending level represents an increasingly detailed definition of the project work.

PMBOK® Guide Definition

WBS Definition

Page 5: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

The tool for breaking down a

project into its component parts

(work package).

It is the foundation of project

planning and one of the most

important techniques used in

project management.

Work Breakdown Structure

Page 6: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Project X

Work Breakdown Structure

Page 7: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Software

Development

Prepare

Func.Specs.

Approve

Requirements

Prepare

Test plan

Prepare

Test data

Conduct

Testing

Code

Programs

Customer

Requirements

Acceptance

TestingTesting Training

WBS in Graphical Form

Page 8: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

1.2.2.1

Dig

trenches

1.2.2.2

Install

pipe &

hardware

1.2.2.3

Cover

sprinkler

system

1.2.3.1

Remove

debris

1.2.3.2

Prepare

soil

1.2.3.3

Plant

lawn

seed

1.3.2.1

Mark

fence line

& post

1.3.2.2

Install

post

1.3.2.3

Install

fencing

& gates

1.3.2.4

Paint

fence

1.3.1

Acquire

fence

material

1.3.2

Construct

fence

1.2.1

Acquire

lawn

material

1.2.2

Install

sprinkler

system

1.2.3

Plant

grass

1.2.4

Plant

shrubs

1.1

Design

home

landscape

1.2

Put in

lawn

1.3

Build

fence

1.0

Home

Landscape

project

WBS in Graphical Form

Page 9: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

1. Software Development

1.1Customer Requirements

1.1.1 Approve Requirements

1.1.2 Prepare Functional Specifications

1.2Code Programs

1.3Testing

1.3.1 Prepare Test Plan

1.3.2 Prepare Test Data

1.3.3 Conduct Testing

1.4Training

1.5Acceptance Testing

WBS in Outline Form

Page 10: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

1.0 Home Landscaping Project

1.1 Design home landscape

1.2 Put in lawn

1.2.1 Acquire lawn material

1.2.2 Install sprinkler system

1.2.2.1 Dig trenches

1.2.2.2 Install pipe and hardware

1.2.2.3 Cover sprinkler system

1.2.3 Plant grass

1.2.3.1 Remove debris

1.2.3.2 Prepare soil

1.2.3.3 Plant lawn seed

1.2.4 Plant shrubs

1.3 Build fence

1.3.1 Acquire fence material

1.3.2 Construct fence

1.3.2.1 Mark fence line and post

1.3.2.2 Install post

1.3.2.3 Install fencing and gates

1.3.2.4 Paint fence

WBS in Outline Form

Page 11: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Provides a detailed illustration of the project scope

Create accurate cost and schedule estimates

Monitor progress easily

Basis for building project teams

Advantages of WBS

Page 12: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

WBS Decomposition

Page 13: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

WBS Organized by Product

Page 14: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

WBS Organized by Phase

Page 15: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

WBS must be broken down starting at the top

Work packages must add up to the summary task (100% Rule)

Each summary task and work package must be named an activity that produces a product (use SMART Technique)

Criteria for a Successful WBS

Page 16: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

specific

measurable

agreed upon

realistic

time-bound

Criteria for a Successful WBS

S

M

A

R

T

Page 17: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Estimating

Page 18: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Planning Processes

Work Breakdown

Structure with RAM

Estimate Duration

and Resources

Network Analysis

Schedule Development

Project Baseline

Page 19: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Factors Affecting Resource Estimating

Work Methodology Statutory Requirements

Specifications Project Duration

Resource Availability

Page 20: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Estimating Work Process

AlignmentScope of

Work

Prepare

Estimate

Document

Estimate

Review

Estimate

Adjust

Estimate?

Project

Execution

Project

Completion

Establish

Standards

Database

Revise Estimate

(Based on External Review) Yes

Reality Check

(Based on Internal Review)

Lessons Learned for Continuous Improvement

Estimate Feed-back for Continuous Improvement

No

Page 21: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Estimating Techniques

Expert Judgment

Analogous Estimating

Definitive Estimating

Parametric Modeling

Page 22: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Analogous Estimating

500 m2:US$ 650,000

≈ 200 m2:US$ 260,000

Page 23: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Analogous Estimating

10%10%

15%

20%

45%

InitiationRequirements

Design

Coding

Testing

SOFTWARE DEVELOPMENT

Page 24: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Analogous Estimating

2.2.1

Dig

trenches

2.2.2

Install

pipe &

Hardware

2.2.3

Cover

sprinkler

System

2.3.1

Remove

debris

2.3.2

Prepare

soil

2.3.3

Plant

lawn

Seed

3.2.1

Mark

fence line

& post

3.2.2

Install

post

3.2.3

Install

fencing

& gates

3.2.4

Paint

fence

3.1

Acquire

fence

Material

3.2

Construct

fence

2.1

Acquire

lawn

Material

2.2

Install

sprinkler

System

2.3

Plant

grass

2.4

Plant

shrubs

1.0

Design

home

Landscape

2.0

Put in

Lawn

3.0

Build

fence

Home

Landscape

Project

100%

25% 10%9% 3% 42% 7%

2% 2% 2% 1%

4% 47% 49%

4% 5% 1%3% 1%5%

Page 25: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Definitive Estimating

2.2.1

Dig

trenches

2.2.2

Install

pipe &

Hardware

2.2.3

Cover

sprinkler

System

2.3.1

Remove

debris

2.3.2

Prepare

soil

2.3.3

Plant

lawn

Seed

3.2.1

Mark

fence line

& post

3.2.2

Install

post

3.2.3

Install

fencing

& gates

3.2.4

Paint

fence

3.1

Acquire

fence

Material

3.2

Construct

fence

2.1

Acquire

lawn

Material

2.2

Install

sprinkler

System

2.3

Plant

grass

2.4

Plant

shrubs

1.0

Design

home

Landscape

2.0

Put in

Lawn

3.0

Build

fence

Home

Landscape

Project

25k 10k9k 3k 42k 7k

2k 2k 2k 1k

4k 47k 49k

4k 5k 1k3k 1k5k

100k

Page 26: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Parametric Estimating

Page 27: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Create your

Project’s WBS

Workshop Time

Page 28: Work Breakdown Structure - Mekong Instituteintranet.mekonginstitute.org/.../Modules/Module6/PPT/WBS_Estimate.pdf · that the project includes all the work ... Work Breakdown Structure

http://www.mekonginstitute.org/

Tasks Duration Responsible

Persons/

Team

Remark

Simple Work plan