7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
1/10
DEVELOPMENT OF STEEL AND COMPOSITE SOLUTIONS FOR
OUTSTANDING VIADUCTS ON THE SPANISH H.S.R. LINES
Francisco Millanes Matoa, Luis Matute Rubiob, Miguel Ortega Cornejoc, Daniel Martnez
Agromayord, Enrique Bord Bujalancec
aProf., PhD., Eng., Universidad Politcnica de Madrid, President IDEAM S.A., Madrid, Spain.
b Prof. Eng. Universidad Europea de Madrid. General Manager IDEAM S.A., Madrid, Spain.c Prof. Eng. Universidad Europea de Madrid. Proyect Manager IDEAM S.A., Madrid, Spain.
dEng. Proyect Manager IDEAM S.A., Madrid, Spain.
Abstract: After the recent experience with the project and execution of Arroyo las
Piedras viaduct, IDEAM is involved in the development of new steel and composite
solutions for the Spanish High Speed Railway Bridges. Viaduct over river Ulla, presently at
its first stages of construction, will feature the longest span in H.S.R. Composite Bridges, with
a main span of 240 m, ousting the bridge over river Main in Nantenbach (208 m span).
Another recent experience on H.S.R. Composite Bridges is Archidona Viaduct, with a mainspan 65 m long with only one central fixed point and a total length between expansion joints
of 3150 m, the longest H.S.R. viaduct in the world without joints and expansion devices.
1 Arroyo las Piedra. The first composite viaduct on the Spanish HSRL
Arroyo las Piedras viaduct [1, 2] is the first composite steel-concrete high speed railway
bridge in Spain, located on the Crdoba-Mlaga H.S.R. Line (Fig. 1).
Fig. 1: Elevation view of Arroyo las Piedras viaduct.
The structural typology is a continuous beam with spans of 50,4+17x63,5+44,0+35,0 m.When designed and built, it was the longest-span viaduct of its type, 0,50 m longer than the
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
2/10
2 VII Congresso de Construo Metlica e Mista
Orgon viaduct on the French TGV Mediterrane. The piers are remarkably high, since several
of them exceed 93,0 m.
The cross section of the deck is made up of two 3,85 m deep twin-plate girders plus a top
slab 14,0 m wide, whose thickness ranges from 0,41 m in the decks longitudinal axis to 0,22
m at the edge of the cantilevers. Fig. 2 shows the cross section in sagging areas. It is similar to
the typical twin girder solutions, although some modifications were implemented:
- Cross truss diaphragms situated every 8,0 m were used instead of full-webdiaphragms.
- The bottom steel truss was replaced by a series of precast slabs 2 m long each and 0,14m thick, longitudinally connected to each other only in the lateral cast-in-place
concrete strip at the bottom corner of the cross section [1, 2]
- External inclined steel plates, placed at the top and bottom of the steel beams, replacethe longitudinal web stiffeners. They improve the stability of compressed flanges and
webs both in erection and service conditions.
- S-355 J2W weathering steel was used in the main structure.The cross section in the hogging areas (Fig. 3) is similar to the sagging cross section, but
double composite action is obtained by bottom in situ concreting over collaborating precast
slabs. This slab is connected with studs and passive reinforcement to the main girders, and
allows the maximum thickness of sheet steel in the bridge to be as little as 40,0 mm, much
thinner than in classical twin girder solutions.
Fig. 2: Mid-span bending cross section
Fig. 3: Hogging cross section
The bridge was built by launching the deck from both abutments, with all the structural
steel, the complete bottom concrete and the top precast slabs being present, however not yet
connected to the deck. The top reinforcement steel is also placed in its final position, leavingthe bridge ready once closed, to concrete the top slab (Fig. 4).
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
3/10
VII Congresso de Construo Metlica e Mista 3
For the first time on HSRL in Spain, impact transmitters (Fig. 5) were fitted on both
abutments, incorporating shock absorbing devices against seismic force, the sites
acceleration was high compared with usual levels in Spain (0,10 g). Thus, slow displacements
due to thermal and rheological actions were able to develop with hardly any resistance whilst,
at the same time, the decks horizontal forces due to railway stock braking are transmitted to
both abutments with hardly any displacements. Besides, the force transmitted to the
substructure during an earthquake is restricted to controlled values. The seismic isolation
system also includes guided, sliding supports in P1 to P7, P12 to P19 and abutments, and
fixed supports in two directions in the highest piers, P-8 to P-11. No isolators were arranged
in the cross direction, where the flexibility called for is entrusted to the piers elastic
deformation [1, 2].
Fig. 4: Underneath view during launching Fig. 5: Longitudinal viscous damper-shock transmission
2 Archidona Viaduct.
Another recent experience of the development of high speed composite bridges is
Archidona Viaduct (Fig. 6) located on the Crdoba-Granada H.S.R.L., with a main span 65
m long, with only one central fixed point and a total length between expansion joints of 3150
m. It is currently the longest H.S.R. Viaduct in the world without joints and expansion
devices. The deck consists of a continuous double composite beam with spans of
35+29x50+2x65+30x50+35 m. The fixed points, materialised by means of a Delta-shaped
pier located between the two 65-m long spans, was designed to withstand very high seismic
forces.
Fig. 6: Elevation view of Archidona Viaduct.
This projects restrictions were certainly singular:
- important seismic actions (basic seismic acceleration: 0,11 g; design seismicacceleration: 0,18 g);
- average pier height around 25 m;
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
4/10
4 VII Congresso de Construo Metlica e Mista
- prevention, as far as possible, of placing of expansion joints within the deck,respecting the maximum longitudinal displacements of 1200 mm at the expansion
joints, as defined by ADIF.
A possible solution consisting of multiple isostatic spans, generally appropriate for long
viaducts with short piers, was ruled out because of the excessive deformability of the
[piers+foundations] system against braking and service seism forces, whose subsequent
displacements were not acceptable for the track. Besides, the substructure was penalized
when withstanding the maximum design seism. Since it was not advisable, owing to
maintenance reasons, to place track expansion devices within the deck, the fixed point could
only be located in the middle (approximately) of the 3150 m-long deck. Therefore, the
resulting lengths subjected to expansion were around 1600 m, something that could not be
solved resorting to concrete deck solutions, because of the tolerable displacement range of
expansion devices. Consequently, a composite deck solution helped solve this technical
problem.
The decks cross section consists of two steel twin girders (Fig 7) 2,95 m deep, with an
upper concrete slab 0,40 m thick connected to the webs. The webs were 6,00 m apart at theirtop, slightly leaning outwards reaching 6,60 m at the bottom. A lower concrete slab closes the
section and fulfils a double purpose: it provides a compression head (double composite
action) in the hogging sections and it closes the torsional flux in sagging sections, a concept
that had been previously implemented in Arroyo las Piedras Viaduct.
Fig. 7: Sagging cross-section
The typical pier was a frame (Fig 8) with two constant-section reinforced concrete shafts
and the same inclination as that of the decks webs. The trapeze shape renders the necessary
stiffness against seismic actions. The deck is transversely linked to the pier by means of
seismic stop dices, whereas it is longitudinally free and supported on sliding spherical
bearings. The piers foundations consisted of 4 piles 2,00 m in diameter and 30,00 m longThe central pier (Fig 9), which constituted the only longitudinally fixed point, was
designed as a triangular cell comprising two leaning typical piers which met at the apex. The
triangles base linked the shafts starts together as well as their pile rafts, with 14 piles each (
2,0 m and 32,0 m long). The deck, which next to the main pier experiences a slight depth
increase, is embedded in the piers head.
Owing to the maximum dilatable length, about 1600 m, continuous composite decks allow
us to solve a technical problem beyond the prestressed concrete technology, since a 30-40%
joint displacement reduction is attainable.
- thermal displacements barely exceed those reached in concrete solutions by 10%;- shrinkage effects are reduced by approximately 50% as a consequence of the restraint
created by the steel subsection;- longitudinal creep deformations are inexistent because the deck is not prestressed.
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
5/10
VII Congresso de Construo Metlica e Mista 5
Fig. 8: Typical pier front view. Fig. 9: Central pier elevation.
The maximum displacements at the expansion joints located at each abutment are +594mm gaping (deck contraction) and -386 mm closing (deck dilatation). In order to better
counteract the decks shortening (gaping joint) the following design measures were taken:
- Use of full-section precast slabs in sagging sections. By casting them in advance,shrinkage strain is reduced and it is also possible to take advantage of prefabrication in
such a long structure. Only the precast slabs joints and studs holes are cast on site.
The slab in the hogging sections consists of traditional transversely ribbed precast
slabs, on top which the rest of the section was cast on site.
- Reduction of rheological deformations by means of an adjustment dowel. The deckserection was conceived in four stages, two starting from the abutments and two from
the central pier. The segments connection (and, at the same time, the release of the
temporary restraints at the abutments) takes place at about 750 m from both the centralpier and the abutments. By erecting an intermediate adjustment span (Fig. 10), longer
than the typical one, erection shrinkage can be neutralised. Total shrinkage
displacement, about 270 mm, turns out to attain only 66 mm at the expansion joint.
Fig. 10: Shrinkage deformation reduction by adjustment of erection process.
- A contrast study between the design temperatures and displacements put forward indesign codes and the actual ones measured in Arroyo las Piedras Viaduct was
performed, in order to control the design hypotheses considered when proportioning
the expansion joints.
The central pier was designed as the unique longitudinal central fix point of the deck, and
has to resist the whole longitudinal seismic reaction, with a value about 100.000 kN. Thatforce is resisted with a foundation of 28 piles 2,0 m. Due to the structural importance, and
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
6/10
6 VII Congresso de Construo Metlica e Mista
the high magnitude of the forces, studies for characterizing the terrain were carried out for
defining their properties. A geophysical study of the terrain around the central pier was
developed, so as to define more accurately the seismic parameters of the ground, as well as
the resisting parameters for the sizing of the piles, and the verification of ground collapse
when it is subject to seismic force. Dynamic and pseudostatic finite element models were
done to calibrate the good correlation between the conventional spring models used at
foundation pre-sizing stage.
It is important to emphasize that the composite decks relative axial flexibility, sensibly
higher to conventional concrete box girders, even though if the additional flexibility
contributed by the eventual upper reinforced slabs cracking under seismic forces is
considered, together with the flexibility due to the axial elongation of each one of the lateral
stretch with 1575 m length, allow to reduce sensibly the seismic longitudinal force in
comparison to the maximum value of the design Spectrum. For the fundamental longitudinal
period (T=2,86 s), the seismic force obtained from the design spectrum in the central fixed
point, 100.000 kN, lead to a result about 20% of the maximum value (Fig. 11). Composite
deck characteristics result, therefore, much more adapted than concrete deck solutions so asto respond to this type of situations in long viaducts located in high seismic zones.
Fig. 11: Reduction of the seismic force for a longitudinal seismic action.
3 Viaduct over river Ulla.
Viaduct over river Ulla [2,3] constitutes the most audacious and high-profile intervention
in the High Speed Atlantic Railway Line to Galicia and Spains northwest regions. It is
currently on its first stages of construction. Its location, close to the firth of Ulla, in a
landscape of outstanding natural beauty and strong environmental constraints, was the object
of a project tender among the most renowned Spanish specialists. The proposed alternative
presented in this paper was finally chosen. The project constraints focused specially the
following aspects:
The outstanding nature of the project, which required serious consideration of theaesthetic qualities and viaduct integration into the landscape.
The reduction of the number of piers in the water course, within the limits of HSRbridges, minimizing the impact on the marshes and riversides.
The erection procedures, that being suitable to the works scale, shall be kept asindependent as possible from the river watercourse, to avoid environmental damageas much as possible.
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
7/10
VII Congresso de Construo Metlica e Mista 7
Visual transparency and minimal bridge interference with the surroundinglandscape.
All these determining factors guided the solution to a haunch steel-concrete composite
lattice, with double composite work at the hogging zone, three main spans measuring 225+
240+225 meters long, and several approaching spans measuring 120 m long, which means a
main span about 20% longer than the current world record, the Nantenbach bridge in
Germany, with a single 208 m long span.
The resulting viaduct is 1620 m long with a span distribution of 50 + 80 + 3x120 + 225 +
240 + 225 + 3x120 + 80 metres (Fig. 12).
Fig. 12: View of Viaduct over river Ulla.
The structural solution of steel lattice with double steel-and-concrete composite action
adequately solves the previously stated conditions.
The deck was designed as a haunch lattice in the five main spans (Fig. 12), ranging from
9,15 m to 17,90 m, and as a 9,15 m constant depth lattice in the approach spans.
The four central piers, with architectonical shapes (Fig. 13), are rigidly connected to the
lattice deck creating composite frames which bestow the required stiffness upon the threecentral spans (Fig. 14) in order to withstand the stresses arising from loads acting on alternate
spans within the stringent deformation limitations in HSRL bridges.
Fig. 13: Lateral view of the main span of Viaduct over river Ulla.
The lateral piers (Fig. 15) are designed with a lighter cross-section consisting of two
separate concrete shafts embedded in the deck and in the foundation. This allowed to preserve
some degree of stiffness against alternate loads as well as the necessary flexibility to permit of
temperature and shrinkage imposed displacements.
The structures design, preserving the structural orthodoxy, has placed special care on the
integration of shapes and geometry between the concrete piers and the decks steel lattice.
The smooth depth variation along the deck, with an upward concavity, confers a serene visual
integration over the Ulla rivers course. The colour choice, pearly grey for concrete and green
for the lattice, enhances that effect (Fig. 13).
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
8/10
8 VII Congresso de Construo Metlica e Mista
Fig. 14: View of the two inner piers P-6&P-7 Fig. 15: View of the two outer piers P5&P-8
Piers show a double typology well differenced. Firstly, the four main piers are rigidly
connected to the deck, configuring a frame which increases the structure stiffness and
enhances its behaviour regarding horizontal forces. These calyx-shaped piers are formed by a
trapezium head measuring 17,5 m high and 11,00 m to 16,00 m wide, and a shaft measuring
8,00 m wide, growing with a 1H:25V slope in piers P6 and P7 (Fig. 14) and a 1H:50V slope
in piers P5 and P8 (Fig. 15). The average height of the piers, measured up to the lattices
lower member, is about 42 m (60 m up to the crowning point).
The stiffness of these piers has been optimized in order to restrain deck rotations at the pier
section but avoiding that bending moments taken by the pier itself and then transmitted to the
foundations were a decisive design constraint.
In this way, piers P5 and P8 (Fig. 15) at the sides of 225 m spans, have been designed withtwo detached shafts from base to head, in order to avoid the excessive bending moments
arising from the decompensation of a 225 m span next to a 120 m span, and those produced
by the temperature and shrinkage displacements, both of them greater than in central piers due
to their further distance to the neutral displacement point.
Side span piers P1 to P4 and P9 to P11 are of a more conventional design. Their box girder
cross section with a 0,30 m wall thickness and a 3,50 m x 8,50 m head section, varies in depth
both transversely and longwise. The pier height ranges from 52 m to less than 20 m.
The main spans are designed with a double haunch lattice deck, with a total depth ranging
from 9.15 m at the midspan section to 17,90 m at the section over pier (Fig. 16). The lattices,
which are modulated in 15 m long segments, are separated 6 m, measured between the upper
flange midpoints, showing a 1H/17.5V outward slope. The adjacent spans giving access to thedepth-varying main ones have been designed with constant depth.
Both the upper and lower members cross-sections are parallelogram-shaped girders,
measuring 0,80 m wide and 1,00 m deep the upper chord and 1,20 m the lower one. Diagonal
members are also parallelogram-shaped (0,8 m wide and 1,00 m deep).
The upper member shows a boxed beam head embedded in the concrete slab which lodges
the connection, allowing a shear transference closer to the center of gravity of the composite
upper chord and minimizing the appearance of local forces and moments in the connections.
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
9/10
VII Congresso de Construo Metlica e Mista 9
Fig. 16: Cross sections.
The steel grade is S-355-J2+N and K2+N for the approach spans and S-460-M and ML for
the three main spans.
The upper slab depth is 0,46 m at mid-span and 0,25 m over the steel upper chords. The
slab, made of cast in place C35/45 concrete, is poured over precast concrete slabs bridging the
space between steel upper members of both lattices. The lateral cantilever part of the slab is
cast using a movable formwork.
Along the hogging zone, a C50/60 concrete slab is arranged between members, allowing a
double composite action. The thickness of this lower slab ranges from 0,30 m to 1,10 m.Along the sagging zone, the decks lower face is closed visually using precast concrete plates,
with no structural role but to create a path to allow for extremely easy inspection and
maintenance.
4 Abroigal Viaduct.
Certain circumstances advice that steel solutions be used, for example with skewed lower
crosses without enough clearance. That happens in Abroigal Viaduct, near Atocha HSR
Station in Madrid, where there are multiple crossings. That laid the design of a double
bowstring arch bridge with a Nielsen suspension system. The arch bridge spans 91 m, with a
rise of 14.50 m (Figs. 17, 18). The hangers anchorages at the tie beams are spaced about
10.10 m (which is also the separation between the transverse girders). Both the arches, tie
beams, hangers and transverse beams are made of S-355 structural steel, with S-460 steel for
the arch-tie beams joint webs. The transverse girders are composite and connected to the
concrete floor.
Fig. 17: Elevation and cross section of the Viaduct.
7/28/2019 Viaducts on the Spanish H.S.L Lines.doc
10/10
10 VII Congresso de Construo Metlica e Mista
Fig. 18: Elevation and cross section of the Viaduct.
One of the most remarkable features is the chosen solution for the decks superstructure,
conceived as an alternative to the usual subsystem of longitudinal steel girders where the
precast slabs rest, and on top of which the slab is cast. Precast U-shaped beams were used
instead. Those used for the track infrastructure and railway traffic are 8,0 m wide, while those
for the sidewalks are 2,345 m wide.
Both kinds of beams have holes located at the support section, right where the transverse
girders studs are. The concrete beams are erected isostatically, but those for the track are
linked together by means of a steel tube welded to a plate at the support section. The total
dead load is similar to the case of a slab across the whole width.
This system avoids the use of longitudinal steel between the transverse girders andincreases the separation between the latter. However, monolithic response as a composite
beam must be developed in a very short distance. Most of the load is carried through the
concrete web of the track U-beam. Therefore, the maximum bending moment (almost
constant along the transverse girder) takes place very near the intersection of the transverse
beam and the tie beams. This leads to very high tangential stresses, which affect several
design aspects: stud layout, concrete strength, concrete-stud transfer reinforcement and
transverse girder working as a structural steel subsection alone.
Concerning the traffic retaining, this function has not been trusted to the U-beams webs,
but to a third rail or counter-rail.
References
[1] Millanes F.; Pascual J.; Ortega M. Arroyo las Piedras Viaduct: The first Composite
Steel-Concrete High Speed Railway Bridge in Spain. Structural Engineering
International, Vol. 17, Nr. 4 (Eds.: IABSE), pg. 292-297, November 2007.
[2] Millanes F. Outstanding composite steel-concrete bridges in the Spanish HSRL. 7th
International Conference on Steel-Bridges. (Eds.: IABSE). Guimaraes. Portugal 2008.
[3] Millanes F.; Matute L.; Ortega M.; Martn J.; Pajuelo D.; Gordo C. Viaduct over the
Ulla river in the HSRL Eje Atlntico in Spain. An outstanding structure in the field of
Composite Steel-Concrete HSRL Bridges. Eurosteel 2008. Graz, Austria. September
2008.