Transcript
Page 1: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Century pipeline refurbishment

project

Tim Akroyd, MMG Century Mine

Chris Austin, Nacap Australia

November 2013

Page 2: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

250 kilometres north/north west of Mt Isa

Page 3: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Mine site

Page 4: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

• 1887 First silver, lead and zinc discovery in area.

• 1887-1960 Intermittent production from area.

• Late 1930s Start of modern exploration in the area.

• 1986 CRAE select the area and applied for EPM.

• 1990 Century discovery hole drilled on 4th April.

• 1990-1996 Resource definition drilling and feasibility.

• 1997 Century acquired by Pasminco – Native Title issues resolved.

• 2000 Century officially opened on 4th April.

• 2002 Officially reached full production on 31st August Awarded MINEX on 2nd September.

• 2009 MMG buys majority of OZ Minerals assets, including Century

Century’s history

Page 5: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Production data

• 24,000 tonnes of ore processed daily

• 900,000 tonnes of zinc concentrate

• 70,000 tonnes of lead concentrate

Page 6: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline summary

• 304Km from Lawn Hill (mine-site) to Karumba

• 300NB X70 grade steel pipe

• Pipewall varies in thickness from

• 8.4mm at Lawn Hill to

• 4.8mm at Karumba

• HDPE liner nominally 7.5mm thick

• 1.2Km flanged strings

• Buried to a minimal depth of 750mm

• Directional drilling under all major rivers

• Single pump station at Lawn Hill

• Instrumentation

• Pressure - start and end, plus 5 intermediate positions

• Flowrate - start and end, with differential leak detection alarms

• Density – start and end

• Pig launching and receival stations

• Impressed current cathodic protection system

Page 7: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline profile

0

1

2

3

4

5

6

7

8

9

0

20

40

60

80

100

120

140

160

180

0 50 100 150 200 250 300 350

Pip

e W

all T

hic

kne

ss (

mm

)

Elev

atio

n (

m)

Pipeline Distance (km)

Page 8: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Lawn Hill (mine site) pump station

• 3 x Wirth Triplex Diaphragm Pump 8¾" x 14" • 1.13MW VSD Motors • Parallel arrangement • Discharge pressure – 20MPa (max)

Page 9: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline monitoring spools (original design)

Monitoring Spools • KP82

• KP85

• KP107

• KP138

• KP152

• KP156

• KP256

• KP265

• KP296

• Unlined approximately 8m in length • 2 x 50mm riser • 1 x pressure gauge on selected risers (5 spools) • Susceptible to external interference

Page 10: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline operations and maintenance

• Pipeline operates continually at approximately 270m3/hr – 300m3/hr

• Zinc and lead concentrates are pumped in batches separated by water.

• Zinc and lead batches are often in the pipeline at the same time

• In the event of an outage pipeline must restart within about 12 hours to minimise trail-out and mixing of zinc and lead concentrate

• Changes in friction losses along the length of pipeline are closely monitored – used to infer slurry deposition within the pipeline

• Pigging using soft foam or medium density pigs occurs as required

Page 11: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline operational advantages

Reduced life cycle cost compared to road transport

• For a similar operation to Century, over 20yrs, approximate Life Cycle Costs

• Pipeline $400M

• Road transport $650M

Lower operational risk profile

• High likelihood of vehicle accidents, with very serious consequences, particularly on public roads

Unaffected by surface weather conditions

• During wet season the roads to Century and Karumba are often cut for several weeks

Page 12: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline operational history

2003 - liner failed in D38 string (KP115 - KP116)

• String was bypassed while method of repair was determined

• Liner was removed and string returned to service

• 2 x unlined monitoring spools were installed at either end of the D38 string

• Subsequent clock face spot thickness testing showed minimal corrosion/erosion in monitoring spools

Page 13: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Pipeline operational history continued

2009 - D38 string failed, following a pipeline restart

• D38 string was replaced with a thick wall unlined pipe

• An inline reduced bore ball valve was inserted ahead of the failed string to assist repairs.

• The valve was left in the pipeline after repairs were completed

2011 - During programmed inspections of monitoring spools, near through wall failure was identified at KP296

• All unlined monitoring spools were thickness tested using phase array technology

• Any areas of spot corrosion were repaired using Kevlar/fibreglass wrap

Page 14: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

2012 Refurbishment plan

• De-slurry pipeline via water pumping only

• Completely dewater pipeline using compressed air and medium and soft density foam pigs (due to valve restriction at KP115)

• Replace unlined D38 string with HDPE lined steel pipe

• Replace all monitoring spools with new

• Encase new monitoring spools in concrete access chambers

Page 15: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Project lead-in, minimising outage time

A number of mitigation measures were identified up-front to minimise the down-time for the refurbishment scope including:

• Fast-tracked contract with flexible commercial terms

• Fast-tracked camp supply to support pipeline project and reduce travel time to maximise driving safety and reduce fatigue (this became increasingly important when the shut-down was prolonged).

• The dedicated local camp accommodation also maximised available working time during execution of the works

Page 16: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Project lead-in, minimising outage time

Further mitigation measures included:

• Additional material procurement (eg – twice the required qty of HDPE pipe) + back-up spools (if required)

• 3D Laser Survey of monitoring spools to ensure precise fabrication (and therefore fit-up)

• Early engagement of local plant suppliers/sub-contractors to ensure sufficient resource pooling during the shut-down scope

• Early identification of shut-down teams required for pipeline scope and early engagement of the same

Page 17: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

New D38 string construction

• DN300 (12”) pipeline welding

Page 18: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

New D38 string construction – HDPE liner pull-back

Page 19: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

New D38 string construction – HDPE liner insertion

Page 20: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Dewatering challenges

• Soft foam and medium density pigs used due to reduced bore ball valve

• Air bypassed pigs creating numerous hydraulic locks in pipeline

• Pigs were removed from Lawn Hill (the start) of the pipeline three days after launch

Page 21: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Dewatering challenges Pipeline profile with potential water retention zones

Page 22: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

How dewatering was achieved

• Safe depressurisation of pipeline via open ends and intermittent venting from small (less than 1”) bleed valves on monitoring spool blinds – day and night operations

• Use of tanker trucks to remove water from upstream sections of the pipeline, water brought back to mine site at Lawn Hill

• Hot taps installed on under-side of monitoring spools adjacent to pipeline low-points to assist with dewatering effort

Page 23: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Dewatering into tankers at KP82

Page 24: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Bi-di pig launched downstream of KP115 valve

• Bi-direction pig launched from KP138 to dewater pipeline through to Karumba

Page 25: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

• Original foam pig dewatering duration was 5 days of 24-hour dewatering followed by 6 days to perform spool change-outs and D38 installation.

• Actual dewatering duration was 30 days including staged pipeline release to enable spool change-out and D38 pipe-string tie-in

• Further delays mitigated by:

• Twice daily management meetings to track dewatering operations and maximise opportunities and synergies to mitigate delays to pipeline re-commissioning

Minimising downtime

Page 26: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

• Further delays mitigated by:

• Early engagement of water tankers to remote areas of pipeline to assist with dewatering

• Fast-tracked hot tapping service (including fittings)

• Availability of specialist pipeline Contractor services, including provision of coded welders, pre-fabricated and pre-tested pig traps

• Rolling pipeline roster to ensure continuous resourcing during shut-down up to and including re-commissioning

Minimising downtime

Page 27: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Monitoring spool replacement underway

Page 28: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Installation of new D38 string

Page 29: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Installed (new) D38 string

Page 30: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

The result

• D38 string replaced with lined pipe and buried

• All monitoring spools replaced

• Concrete access chambers installed

• Routine wall thickness inspection program of all monitoring spools

Page 31: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Don’t get bitten!

Page 32: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

• Flanged joints about every 1-2 kilometres introduce potential leak points

• Matching of flange/HDPE ends and correct use of gaskets when new technologies replace old

• Lined pipe removes ability to hot tap (without detriment to the liner) in case of (pressure) air-lock issues during testing, commissioning, operational error, dewatering works or on re-start after shut-down. Consider high point vent and low-point drain locations during design stage

Challenges of HDPE lined pipe

Page 33: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Further challenges of HDPE lined pipe

• Leak detection methods between HDPE liner and inner wall of steel pipe need to be considered at design stage, including monitoring regime

• Unknown impact of rigid-style pigging through HDPE liner

• Lack of experience and available operational data/history from the industry

• Constructability and maintenance (eg – very limited resources for HDPE pull-back available within Australia)

Page 34: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Results of 2012 refurbishment:

• Pipeline is now in a better than as-designed condition

• New D38 string means that pipeline is now fully lined (end to end), except for dedicated monitoring spools.

• Reduced risk of external interference

• Improved access to allow for complete monitoring of corrosion of unlined monitoring spools and faster response in the unlikely event of an incident

• Removal of KP115 in-line valve allows future use of bi-directional pigs for cleaning/batching/dewatering operations as required

Project benefits

Page 35: Tim Akroyd, Tim Akroyd, Concentration Manager, MMG Century - Century pipeline refurbishment project

Lessons for industry

• Pipelines have excellent operational advantages, including lower operational risk profiles and reduced life cycle costs, but can be challenging to operate

• The minerals processing industry lacks specialist “in-house” knowledge

• Collaboration with specialist contractors (design, construction, operation, maintenance as required) enables the best outcomes


Recommended