Transcript
Page 1: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Page 2: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Sponsors

Port of Tacoma WSDOTCity of Fife SSA Marine City of Tacoma Pierce CountyMarine View Ventures FMSIB

Tideflats Area Transportation StudyFinal Report

Page 3: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

• Identify future transportation needs for the growth of freight-related traffic to and from the Tideflats area

• Increase mobility and accessibility by reducing traffic congestion

• Promote regional economic competitiveness

• Accomplish a coordinated transportation plan

Tideflats Area Transportation StudyGoals and Objectives

Page 4: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyStudy Area

Page 5: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyTruck Volumes

Page 6: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyExisting Traffic “Hot Spots”

Page 7: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyBaseline Projects

Page 8: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyHousehold and Employment Growth

Page 9: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyTraffic and Truck Growth

Page 10: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyFirst Level Screening Criteria

Page 11: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudySecond Level Evaluation Criteria

Page 12: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyRecommended Projects

Tideflats Area Access

Page 13: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyRecommended Projects

Port Access

Page 14: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyRecommended Projects

Industrial Access

Page 15: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Tideflats Area Transportation StudyRecommended Projects

Local Access

Page 16: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

• Cost of Recommended Projects is $290-335 Million• Tideflats Area Access: $140-150 Million • Industrial Access: $110-130 Million• Port Access: $5-10 Million• Local Access: $35-45 Million

• Baseline projects total $485-540 Million• Existing Funding Commitments is $196 Million• Remaining Funding Need over 20 Years estimated

$579-679 Million

Tideflats Area Transportation StudyOrder of Magnitude Costs

Page 17: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

• Medium- and long-term transportation requirements to accommodate area traffic growth

• Coordinated recommendations that meet the needs of stakeholders

• Information needed to support funding pursuits

Tideflats Area Transportation StudyOutcomes

Page 18: Tideflats Area Transportation Study Final Report PPT 11-06-16

PORT OF TACOMA

Next Steps, Questions and Answers