- * Susan D. Ritenour O n e Energy Place Secretary and Treasurer and Regulatory Manager
Pensacola, Florida 32520-0781
Tel850 444 6231 Fax 850 444 6026 S D R l TEN O@sou th ernco corn
POWER A SOUTHERN COMPANY
March 31, 2004
Ms. Blanca Bayo, Director Division of the Commission Clerk and Administrative Services Florida Public Service Commission 2540 Shumard Oak Boulevard Tallahassee FL 32399-0850
Dear Ms. Bayo:
In accordance with Rule 25-6.078, Gulf Power Company is enclosing an original and fifteen copies of its 2004 Underground Differential Cost Report (Form PSCEAG 13) and the supporting work papers.
Also enclosed are an original and fifteen copies of the Company's tariff sheets listed below. A coded copy of each tariff sheet has been provided to show the changes to the existing tariff sheets.
ldentif ication New Sheet Underground Second Rev. Sheet No. 4.23
Fourth Rev. Sheet No. 4.24 Eighth Rev. Sheet No. 4.25 Twelfth Rev. Sheet No. 4.26 Original Sheet No. 4.26.1 Original Sheet No. 4.26.2 Original Sheet No. 4.26.3 Seventh Rev. Sheet No. 4.27 Seventh Rev. Sheet No. 4.28 Eighth Rev. Sheet No. 4.28.1 Fourth Rev. Sheet No. 7.26 Second Rev. Sheet No. 7.26.2 First Rev. Sheet No. 7.26.3 Third Rev. Sheet No. 7.26.4
Form 9
Old Sheet First Rev. Sheet No. 4.23 Third Rev. Sheet No. 4.24 Seventh Rev. Sheet No. 4.25 Eleventh Rev. Sheet No. 4.26
Sixth Rev. Sheet No. 4.27 Sixth Rev. Sheet No. 4.28 Seventh Rev. Sheet No. 4.28.1 Third Rev. Sheet No. 7.26 First Rev. Sheet No. 7.26.2 Original Sheet No. 7.26.3 Second Rev. Sheet No. 7.26.4
Ms. Blanca Bayo March 31,2004 Page Two
The revised tariff sheets include the new cost differentials shown in the report. In addition to the changes related to pricing, the Company has deleted previously numbered Options 2 and 5 from the “Underground Distribution Facilities for New Residential Subdivisions” section. These infrequently used options allowed the Applicant to supply and install some of the material. In order to presewe the highest standards of workmanship and reduce the number of delays in service, these options are being eliminated. There remain three options for the Applicants.
The Company has expanded the cost per foot scenarios for three phase facilities required in the typical subdivision. These three phase facilities are most often used for lift stations. The new options are more representative of actual scenarios in today’s construction environment.
Additionally, the Company has eliminated the cost per foot for underground service from overhead facilities. Instead of the standard per foot price, individualized cost differential computations will be calculated. This will eliminate a customer being charged an average price and will more accurately reflect the cost causation.
In summary, the proposed offerings provide options to the Applicants while at the same time fairly reimburse the Company for the costs to provide these services. Please return a copy of the approved tariff sheets to my attention.
Sincerely, m
Iw
Enclosures
cc: Beggs and Lane Jeffrey A. Stone, Esquire
Index to Worksheets
Summary of 21 0 hot Subdivision Differential Cost
210 Lot Typical Subdivision Base Price
21 0 Lot Typical Subdivision Reconciliation Worksheet
Summary of 176 Lot Subdivision Differential Cost
I76 Lot Typical Subdivision Base Price
176 Lot Typical Subdivision Reconciliation Worksheet
Page
3
4
5
6
7
8
Page 2
Typical Subdivision Summary of 210 Lot Subdivision
Differential Cost I
(1) (2) (3) (4) (5) (6) (7) (8)
Total Credits for Credited Total URD Applicants URD Overhead Differential
Option URD Lot ($1 Supplying Lot ($) URD Cost ($) OH tot ($) OH Cost ($) per Lot ($) Cost Per Doing & Cost per Total Cost Per Total Cost
2 I 0-Lot Work 2 1 0-LOT 2 1 0-LOT 2 1 0-Lot 2 1 0-LOT 21 0-LOT
I $1,354 $0 $4,354 $284,340 $941 $1 97,534 $41 3 2 $1,354 $1 20 $1,234 $259,060 $941 $1 97,534 $293 3 $1,354 $208 $1,146 $240,698 $941 $1 97,534 $205
Digs I Installs I Provides I Digs installs I 21;: Pri and Sec Pri and Sec Pri and Sec Service 1 Service
Customer's choice of construction method. URD cost per lot as shown on Page 4 of April 1 , 2004 filing. Credit to Applicant for doing a portion of the installation - see Page 4 of these work papers. Column 2 minus column 3. Column 4 multiplied by number of lots. OH cost per lot as shown on Page 4 of April 1, 2004 filing. Column 6 multiplied by number of lots. Column 4 minus column 6.
I Option k Trench 1 Duct I Duct 1 Trench I Duct I Duct Option
I 1 Gulf Gulf Gulf Gulf Gulf
Applicant Applicant Gulf Gulf Guff Applicant Amlimnt Amlicant Gulf Gulf
2 3
~
Gulf Gutf Gulf
Digs I Installs Pri and Sec Pri and Sec
Gulf Gulf
Gulf Gulf Gulf Guff
Provides Digs installs Pri and Sec Service Service I Duct I Trench 1 Duct
I Amlicant I Gulf ~ I Gulf Applicant Applicant Applicant Apdimnt
Installs Service
Duct Gulf Gutf Gulf
Page 3
Typical Subdivision Developer Options 210 Lot Subdivision
Digs installs Provides Digs Installs Provides Credited Credited URD Total OH Cost ($) Option Pri and Sec Pri and Sec Pri and Sec Service Service Service URD Cost ($) Cost ($) per OH Cost ($) per Lot
Trench Duct Duct Trench Duct Duct 210 - Lot Lot 2io - tot 210 - Lot 210 - Lot 1 Gu If Gulf Gulf Gulf Gulf Gulf $284,340 $1,354 $197,534 $941 2 I Applicant Applicant Gulf Gulf Gulf Gulf $259,060 $1,234 $197,534 $941
Total Cost: (Base Price)
Activity $ COST/LOf Total Cost ($) 210-LOT 210 - tot Description
A Applicant trenches & installs primary & sec. duct $120.38 $25,280
B c I I I
I Total I $207.82) $43,642
Applicant suppties primary and secondary duct $87.441 $18,362 I
Price / Lot Total Price
210 - Lot 210 - Lot 1 None $0 $0 2 A $120.38 $25,280
L. 3 A+B $207.82 $43,642
Option Activities Performed by the Applicant ?eduction ($: Reduction ($1
Page 4
T y pi ca I Sub d iv isio n Summary of 176 Lot Subdivision
Differential Cost
(6)
Total Overhead Cost Per
OH Lot ($) 176-LOT
$702
(1 )
Option
(7)
Total OH Cost ($)
176-LOT
$123,541 1 2 3
Provides Pri and Sec
Duct Gulf
(2)
Total URD
Cost Per URD Lot ($
176-LOT
$1,065 $1,065 $1,065
Digs Installs Installs Service Service Service Trench Duct Duct
Gu tf Gulf Gulf
( 3 )
Credits for Ap pli ca n ts
Doing & Supplying
Work
$0 $83
$753
Gulf Applicant
(4)
C red i ted URD
Cost per Lot ($)
176-LOT
$1,065 $982 $912
Gulf Gulf Gulf Gulf Gulf Gulf
Total URD Cost ($)
'l76-LOT
$1 87,440 $1 72,828 $1 60,438
(8)
Differential cost
per Lot ($) 176-LOT
$363 $280 $21 0
Customer's choice of construction method. URD cost per lot as shown on Page 8 of April 1, 2004 filing. Credit to Applicant for doing a portion of the installation - see Page 7 of these work papers. Column 2 minus column 3. Column 4 multiplied by number of lots, OH cost per lot as shown on Page 8 of April 1, 2004 filing. Column 6 multiplied by number of lots. Column 4 minus column 6.
Digs I Option IPri and Sec
I 2 I Amlicant I 3 I Applicant
Installs Pri end Sec
Duct Gulf
ADPI ica n t Applicant
Page 6
Typical Subdivision Developer Opt ions 176 Lot Subdivision
Digs Installs Provides Digs Installs Provides Credited Credited URD Total OH Cost ($) Option Pri and Sec Pri and Sec Pri and Sec Service Service Service URD Cost ($) Cost ($) per Lot OH Cost ($) per Lot
Trench Duct Duct Trench Duct Duct 176 - Lot 176 - Lot 176 - Lot 176 - Lot 1 Gulf Gulf Gulf Gulf Gulf Gulf $187,440 $1,065 $1 23,54 1 $702 2 Applicant Applicant Gulf Gulf Gulf Gulf $1 72,828 $982 $1 23,54 1 $702
Total Cost (Base Price)
Activ i ty
A
$ COST/LOT'Total Cost ($)
Applicant trenches & installs primary & sec duct $83 $14,612 176 - Lot 176 - Lot
Description
I $70 8 IApplicant supplies primary and secondary duct I $12,390
1 2 A 3
I Optton 1 None $0 $0
$83 $14,612 A+B $753 $27,002
Price I Lot Total Price eduction ($ Reduction ($) Activities Performed by the Applicant
P 2 l 0 - L o t I 210-Lot I
Page 7
176 Lot Single Family Residential and Breakdown of Credits Worksheet
Trench & Trench & Trench & Service Install Transformers Tracer Wire Inst. I Duct Inst 2 Duct Inst. 3 Duct Trenching Tracer Stores Service (2) Primary Secondary
Material Labor Material Labor Material Labor Material Labor Matenal Labor tabor - Labor Labor Labor Handtins Ensineennq Total
Meters and Transformers 00 7 dL! l i 2 D J N 1 2 2 G-l c i-; 227 94
Cable - Primary & Secondary c 9 5 1 7433 " I 1 7 ' 1 6 1059 4? i- 340.87
Cable - Services ->7 00 si !IT fi 00 20 P5 144 00
Trench Primary And Secondary 36 00 26 00 3 Ob 1 (J 820 75.00 A
Trench Service Install Tracer Wire Duct - Pri and Secondary
Material Labor
Tracer Wire Material Labor
Duct Service Material Labor
Total
i I-! 01; ;I: 1 2 132 00 G 5 3 i LICJ 8 02 A
70 40 -1 23 5240 B
18.00 B 10 z 2 3 28
2 I4 0 34 2 48
63 29 41 30 6 63 40.53
C' 53 :3 15 14 76
78.90 9451 a312 7843 9067 75 16 17204 4012 2 14 0 3 5 36.00 26 00 3 00 11400 6 93 43.43 120.00 1,064 80
0 35 :? o ao
- Notes,
( 7 ) Total ties to Page 8 of Gulf Power Company Underground Distribution Differential Cos1 Reporf filed Apnl 1, 2004. {2) Total ties Page 7 of these workpapers under Activity Section
Aclivrty A Total = 75+8.02 83 02 Activity B Total = 52 4+j8 70 40
Page 8
Gulf Power Company
2004 Underground Distribution Differential Cost
Report to the
Florida Public Service Commission
Gulf Power Company 2004 Underground Distribution Differential Cost
Report to Florida Public Service Commission
Section
Typical 210 Lot Subdivision:
Typical 21 0 Lot Subdivision:
Typical 210 Lot Subdivision:
Typical 21 0 Lot Subdivision:
Typical 176 Lot Subdivision:
Typical 176 Lot Subdivision:
Typical 176 Lot Subdivision:
Typical -l76 Lot Subdivision:
2003 Operating Expenses
2003 Joint Trenching
Table of Contents
Overhead vs. Underground Summary Sheet - Cost Per Lot - Single Family Residence
Overhead Material and Labor Estimates - Cost Per Lot - Single Family Residence
Underground Material and Labor Estimates - Cost Per lot - Single Family Residence
Subdivision Drawing
Overhead vs. Underground Summary Sheet - Cost Per Lot - Single Family Residence
Overhead Material and Labor Estimates - Cost Per Lot - Single Family Residence
Underground Material and Labor Estimates - Cost Per Lot - Single Family Residence
Subdivision Drawing
Overhead Vs. Underground
Underground Residential Distribution
4
5
6
7
8
9
10
11
12
13
2003 Year-End Customer Summary Overhead Vs. Underground 14
Page 2
Gulf Power Company Submits the Following Data On The 210 Lot
Typical Subdivision For Information Purposes Only In Accordance With
Commission Order No. Docket No.
Page 3
Gulf Power Company Overhead VS Underground
Summary Sheet Cost Per Lot
210 Lot Single Family Residential
Aprif 1,2004 Filing
Labor Material Total
I Overhead I 552 - 389 94 1
1 Underground I
738 - 616
1,354
I Drfferential 1
186 - 227 413
Page 4
Gulf Power Company Cost Per Lot
Overhead Material And Labor 210 Lot Single Family Residential
2004
I Item I IMaterial(l)I [Labor(.l.)] Service (2) Primary Secondary Initial Tree Trim Poles Transformers (3)
Subtotal Stores Handling (5)
Su bto ta I Engineering (6)
37 18 7
93 201
39 22 6
99 116 169
356 451 33
389 451 101
Total 389 552
I Total I 76 40 13 99 209 370
807 33
840 101
94 I
(1) Includes Sales Tax (2) Includes Meter (3) Includes Ground Rods, Arresters and Cutouts (4) I n c I udes Ad m i n i s t ra t ive , Ge ne ra I Ex pe n se s , and T ra n s po rta t io n (5) 16% of All Material (Less Meters and Transformers) (6) 18.0% of All Material & Labor (Less Meters and Transformers)
Page 5
Gulf Power Company Cost Per Lot
Underground Material And Labor 210 Lot Single Family Residential
2004
I Item I I Material (1) I [Labor(4)] Service (2) Primary Secondary Transformers (3) T&l 1 duct T&l2 ducts T&l3 ducts Service Trenching Tracer Wire
Subtotal Stores Handling (5)
Subtotal Engineering (6)
Total
103 137 75
242
3
560 56
616
616
112 127 63 68 68 21 4
114 1 1
588
588 150
738
(I) Includes Sales Tax (2) Includes Meter (3) Includes Ground Rods, Arresters and Cutouts (4) Includes Administrative, General Expenses, and Transportation (5) 16% of All Material (Less Meters and Transformers) (6) 18.0% of All Material & Labor (less Meters and Transformers)
I Total I 215 264 138 310 68 21 4
114 14
1,148 56
1,204 150
1,354
Page 6
Gulf Power Company Overhead VS Underground
Summary Sheet Cost Per Lot
176 Lot Single Family Residential
April I, 2004 Filing
I Item I I Overhead I Labor Material Total
412 290 702
I Underground I 595 470
1,065
1 Differential I
183 180 363
Page 8
Gulf Power Company Cost Per Lot
Overhead Material And Labor I76 Lot Single Family Residential
2004
I Item I I Material ( 7 ) 1 p i G q l Service (2) Primary Secondary Initial Tree Trim Poles Transformers (3)
Subtotal Stores Handting (5)
Subtotal Engineering (6)
Total
26 I 1 7
75 145
265 25
290
290
30 14 7
63 91
131
336
336 76
412
(I) Includes Sales Tax (2) Includes Meter (3) Includes Ground Rods, Arresters and Cutouts (4) Includes Administrative, General Expenses, and Transportation (5) 16% of All Material (Less Meters and Transformers) (6) 18.0% of All Material & Labor (Less Meters and Transformers)
I Total I 56 25 14 63
166 276
60 1 25
626 76
702
Page 9
Gulf Power Company Cost Per Lot
Item
Underground Material And Labor I76 Lot Single Family Residential
2004
I Material (1) 1 Service (2) Primary Secondary Transformers (3) T&l I duct T&l2 ducts T&l3 ducts Service Trenching Tracer Wire
Su btota I Stores Handling (5)
Subtotal Engineering (6)
Total
79 83 91
172
2
427 43
470
470
95 79 75 40 36 26 3
114 7
475
475 120
595
( I ) Includes Sales Tax (2) Includes Meter (3) Includes Ground Rods, Arresters and Cutouts (4) Includes Administrative, General Expenses , and Trans porta tion (5) 16% of All Material (Less Meters and Transformers) (6) 18.0% of All Material & Labor (Less Meters and Transformers)
I Total I 173 162 166 212
36 26
3 114
9
901 43
945 120
1,065
Page IO
Revised 03/17/04
Florida Public Service Commissison Order No
Docket No. Gufl Power Company
GULF POWER COMPANY 2003 OVERHEAD VERSUS UNDERGROUND EXPENSES
ACCOUNT NUM8ER
583- 111,112, 113
583 - 200
583 - 900
584 -1 11,331,332,333
585 - 400
584 - 900,950,951
593 - 100
593 - 200,201,203,205, 208,209,210,211 , 250,251,295,400
OPER. AND MAINT. EXPENSES OVERHEAD UNDERGROUND
Install & Remove OH Transformers $603,455
OH Transformers - First Cost ($234,251 )
OH Line - Operations $934,279
Install & Remove UG Transformers
UG Transformers - First Cost
UG Line - Operations
Tree Trim
OH Poles, Towers, Conductor
594 - 100,500, 503,505, 51 1
595 - 100
595 - 200,300, 301
UG Line - Maintenance
OH Transformers - Maintenance
UG Transformers - Maintenance
TOTAL
$3,537,527
$4,873,773
$352,200
($1 87,485)
$577,8 3 1
$1,831,157
$761,606
$1 0,476,389
$99,218
$2,672,92 1
Page 12
Revised 03/17/04
Florida Public Service Commissison Order No.
Docket No Gufl Power Company
GULF POWER COMPANY JOINT TRENCHING
UG RESIDE NTl AL DI STRl B UTI0 N 2003
NONE DONE IN 2003
Page 13
Revised 03/17/04
YEAR
1972 1973 1974 1975 1976 1977 1978 1979 1980 (1) 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 200 1 2002 2003
GULF POWER COMPANY
OVERHEAD VERSUS UNDERGROUND YEAR - END CUSTOMERS
1972 - 2003 OVERHEAD
150,536 158,548 163,310 165,857 170,138 173,308 177,427 181,130 181,937 187,221 191,692 197,457 203,256 208,594 21 2,725 21 7,208 220,563 223,631 226,880 230,755 236,862 242,534 247,576 249,649 254,725 260,160 264,133
271,620 274,558 278,223 282,068
268,21 a
UNDERGROUND
Florida Public Service Commission Order No.
Docket No. Gulf Power Company
6,088 7,260 8,432 9,281 10,589 13,041 14,124 15,605 23,756 26,405 29,481 34,293 42,061 49,099 54,005 56,336 59,184 61,695 63,569 65,476 68,178 71,273 74,070 75,465 80,107 85,196 89,839 95,333 98,499 101,962 105,700 1 1 1,790
TOTAL
156,624 165,808 171,742 175,138 180,727 186,349 191,551 196,735 205,693 21 3,626 221 , I 73 231,750 245,317 257,693 266,730 273,544 279,747 285,326 290,449 296,231 305,040 31 3,807 321,646 325,114 334,832 345,356 353,972 363,551 370,t 19 376,520 383,923 393,858
(1) The underground customers increases substantially due to an error in recording overhead and underground accounts. The problem was discovered and corrected in November 1980.
Page 14
\ GULF&
PAGE
POWER 4 SOUTHERN COMPANY
EFFECTIVE DATE
Section No. IV Second Revised Sheet No. 4.23 Canceling First Revised Sheet No. 4.23
6.2.2
6.2.3
6.2.4
6.2.5
(continued)
Any Applicant seeking the installation of underground distribution facilities pursuant to a written request hereunder shall execute the Agreement For Underground Construction Standards set forth in Section VI1 of this tariff, Standard Contract Forms, at Sheet no. 7.25. Failure to execute said agreement within 180 days after the delivery by Gulf Power Company of a binding cost estimate shall result in forfeiture of the deposit made. Any subsequent request for underground facilities will require the payment of a new deposit and the presentation of a new binding cost estimate. For good cause Gulf may extend the 180 day time limit. Upon execution of the Agreement For Underground Construction Standards, payment in full of the differential cost specified in the binding cost estimate, and compliance with the requirements of this tariff, Gulf shall proceed to install the facilities identified in a timety manner.
As a condition precedent to the conversion of any overhead distribution facilities, the Applicant shall have executed agreements with all affected pole licensees (e.g. telephone, cable TV, etc.) for the simultaneous conversion of those pole licensees’ facilities and provide Gulf with a copy of the Agreement(s). Such agreements shall specifically acknowledge that the affected pole licensee will coordinate the conversion with Gulf and other licensees in a timely manner so as to not create unnecessary delays. Failure to present to Gulf Power Company executed copies of any necessary agreements with affected pole licensees within 180 days after delivery of the binding cost agreement to the Applicant shall result in forfeiture of the deposit paid for the binding cost estimate, the return of any differential cost paid for the binding cost estimate, the return of any differential cost paid less any actuat cost incurred, and the termination of any Agreement For Underground Construction Standards entered into between the Applicant and Gulf Power Company.
CHANGES TO PLANS. The Applicant shall pay for all additional costs incurred by the Company due to changes made by the Applicant in the subdivision layout or grade after original agreed upon design has been completed by the Company.
UNDERGROUND INSTALLATIONS NOT COVERED. Where the Applicant requests underground electric facilities not specifically covered by these Rules and Regulations, or in areas where the terrain, loads, and/or equipment are not typical, and where overhead facilities would otherwise normally be provided, the Applicant and the Company may enter into an agreement outlining the terms and conditions of the installation prior to such installation.
TYPE OF SYSTEM PROVIDED. Underground residential distribution facilities are of standard Company design, generally with alt cable in duct or conduit and above-grade appurtenances. Unless otherwise stated, service provided will be 120/240 volt single phase. If other types of facilities are requested by the Applicant or required by governmental authority, the Applicant or governmental authority will pay the additional costs if any.
ISSUED BY: Susan Story
,
(b) Schedulina, Clearina, and Gradinq. Rights of way and easements suitable to the Company must be furnished by the Applicant in reasonable time to meet service requirements, and must be cleared of trees, tree stumps, paving and other obstructions, staked to show property lines and final grade, and must be graded to within six (6) inches of final grade by the Applicant before the Company will commence construction, all at no charge to the Company. Such clearing and grading must be maintained by the Applicant during construction by the Company.
I I Grade stakes must be provided at transformer locations.
I o U L F l r \ POWER
A SOUTHERN COMPANY
Section No. IV Fourth Revised Sheet No. 4.24 Canceling Third Revised Sheet No. 4.24
PAGE EFFECTIVE UATE t 6.2.6 OWNERSHIP OF UNDERGROUND FACILITIES. The Company will install, own, and maintain the
electric distribution facilities up to the designated point of delivery except as otherwise stated. Any payment made by the Applicant under the provisions of these Rules will not convey to the Applicant any rights of ownership. The Applicant may, subject to a contractual agreement with the Company, construct and install a portion of the underground distribution facilities provided:
(a)
(b)
(c)
(d)
Such work meets the Company's construction standards;
The Company will own and maintain the completed distribution facilities;
such agreement is not expected to cause the general body of ratepayers to incur greater costs;
the Applicant agrees to pay Gulf Power Company's current applicable hourly rate for engineering personnel for all time spent reviewing and inspecting the Applicants work done; and
(e) the Applicant agrees to rectify any deficiencies found by Gulf Power Company prior to the connection of any customers to the underground electric distribution system or the connection of the underground electric distribution facilities to Gulf Power Company's distribution system. Furthermore, the deficiencies must be corrected in a timely manner or Gulf shall construct the system improvement using overhead facilities and the Applicant will have to pay the cost of such improvement and the cost of its removal before the corrected underground facilities will be connected.
6.2.7 RIGHTS OF WAY AND EASEMENTS. (a) General Requirements. The Company shall construct, own, operate, and maintain distribution
facilities only along easements, public streets, roads, and highways which the Company has the legal right to occupy, and on public lands and private property across which rights of way and easements satisfactory to the Company may be obtained without condemnation or cost to the Company.
Should paving, grass, landscaping, or sprinkler systems be installed prior to the construction of the underground distribution facilities, the Applicant shall pay the added costs of trenching, backfilling, and restoring the paving, grass, landscaping, and sprinkler systems to their original condition.
ISSUED BY: Susan Story
Section No. IV Eighth Revised Sheet No. 4.25 Canceling Seventh Revised Sheet No. 4.25
POWER 4 SOUTHERN COMPANY
r PAGE EFFECTIVE DATE 1
6.2.8
6.2.9
6.3.1
6.3.2
DAMAGE TO COMPANY'S EQUIPMENT. The Applicant shall be responsible to ensure that the Company's distribution facilities once installed, are not damaged, destroyed, or otherwise disturbed during the construction of the project. This responsibility shall extend not only to those in his employ, but also to his subcontractors. Should damage occur, the Applicant shall be responsible for the full cost of repairs.
PAYMENT OF CHARGES. The Company shall not be obligated to install any facilities until payment of applicable charges, if any, has been completed.
6.3 UNDERGROUND DISTRIBUTION FACILITIES FOR NEW RESIDENTIAL SUBDIVISIONS
AVAILABILITY. After receipt of proper application and compliance by the Applicant with applicable Company rutes and procedures, the Company will install underground distribution facilities to provide single phase service to new residential subdivisions of five (5) or more building lots.
CONTRIBUTION BY APPLICANT. (a) Prior to such installations, the Applicant and the Company will enter into an agreement
outlining the terms and conditions of installation, and the Applicant will be required to pay the Company in advance the entire cost as described below:
Option
1. Gulf supplies and installs all primary, secondary, and service trench, duct, and cable.
2. Applicant installs primary and secondary trench and duct system. Gulf supplies primary and secondary duct and supplies and installs service duct. Gulf supplies and installs primary, secondary, and service cable.
3. Applicant supplies and installs primary and secondary trench and duct. Gulf supplies primary and secondary cable. Gulf supplies and installs service duct and cable.
tow Density High Density Subdivision Subdivision ($ per lot) ($ per lot)
$41 3 $363
$293 $280
$206 $210
All construction done by the Applicant must meet the Company's specifications. All installations must be approved by the Company's authorized representative.
(b) The Applicant is required to pay a charge per foot and a cost differential for transformers and services (see "Three Phase Lift Station" charts below) for three phase commercial loads requiring 1201240 volt open delta, 120/208 volt wye, or 277/480 vott wye service in new residential subdivisions for each three phase service. This average cost will be added to the advanced payment in 6.3.2(a) above.
ISSUED BY: Susan Story
\ GULF&
PAGE
POWER A SOUTHERN COMPANY
EFFECTIVE DATE
Section No. IV Twelfth Revised Sheet No. 4.26 Canceling Eleventh Revised Sheet No. 4.26
SINGLE PHASE $1 0.85 per ft
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$6.40 per ft plus 3ph padmount tx,
pad, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
$4.41 per ft plus 3ph padmount tx,
pad, and ug service minus 3 oh transformers,
3 cutouts, 3 arresters, cluster mt, and service
TWO PHASES $7.04 per ft
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$5.05 per ft plus 3ph padmount tx,
pad, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
$2.59 per ft plus 3ph padmount tx,
pad, and ug service minus 3 oh transformers,
3 cutouts, 3 arresters, cluster mt, and service
6.3.2 (continued)
$5.80 per ft plus 2 padmount t x ,
2 pads, and ug service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service
THREE PHASE LIFT STATION COSTS TO PROVIDE 3 PH SVC TO LIFT STATION WAN TYPICAL SUBDlVlSlON - OPTION 1
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service
CUSTOMER REQU
MOTOR SIZE
minus one oh transformer, cutout, arrester, and service
$1 -82 per ft plus 2 padmount tx,
2 pads, and ug service minus 2 o h transformers,
2 cutouts, 2 arresters, and
< 5HP
minus one oh transformer, cutout, arrester, and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and
minus one oh transformer, cutout, arrester, and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and
5HP < X < 25HP
service $1 -82 per ft
plus 2 padmount tx,
> 25HP
service $0 cost per ft
plus 2 padmount tx,
CUSTOMER REQl
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
MOTOR SIZE < 5HP
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service and service
5HP X e 25HP
> 25HP
EST: 120/208 or 277/480 AVAILABLE UNDERGROUND FACILITIES
THREE PHASES $0 cost per it
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$0 cost per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 3ph padmount tx, pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
service $0 cost per ft
plus 2 padmount tx,
ISSUED BY: Susan Story
\ GULF&
PAGE
POWER A SOUTHERN COMPANY
EFFECTIVE DATE
Section No. IV Original Sheet No. 4.26.1
$10.45 per ft plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$6.00 per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $4.01 perft
plus 3ph padmount t x , pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
$6.84 per ft plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$4.85 per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $2.39 per ft
plus 3ph padmount tx, pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
6.3.2 (continued)
$5.60 per ft plus 2 padmount tx,
2 pads, and ug service minus one oh transformer,
cutout. arrester. and service
THREE PHASE LIFT STATION COSTS TO PROVIDE 3 PH SVC TO LIFT STATION WAN TYPICAL SUBDIVISION - OPTION 2
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus one oh transformer,
cutout. arrester. and service
CUSTOMER REQUEST: 120/208 or 277/480
I AVAILABLE UNDERGROUND FACILITIES
$1.62 per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
$1.62 per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
MOTOR SIZE
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
< 5HP
5HP c X c 25HP
> 25HP
CUSTOMER REQl
MOTOR SIZE < 5HP
5HP < X < 25HP
.
> 25HP
SINGLE PHASE TWO PHASES THREE PHASES $0 cost per ft
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$0 cost per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 3ph padmount tx, pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
EST: 120/240 OPEN DELTA AVA1 LABLE U NOERGROU N D FACl LlTlES
SINGLE PHASE TWO PHASES THREEPHASES $0 cost per ft
plus 2 padmount tx, 2 pads, and ug service
minus one oh transformer, cutout. arrester. and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
ISSUED BY: Susan Story
1 GULFI-
1
PAGE EFFECTlVE DATE
POWER A SOUTHERN COMPANY
MOTOR SIZE e 5HP
Section No. IV Originat Sheet No. 4.26.2
SINGLE PHASE $4.66 per ft
plus 2 padmount tx, 2 pads, and ug service
minus one oh transformer, cutout, arrester, and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug servtce minus one oh transformer,
cutout. arrester. and service
6.3.2 (continued)
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus one oh transformer,
cutout. arrester. and service
THREE PHASE LIFT STATION COSTS TO PROVIDE 3 PH SVC TO LIFT STATION WAN TYPICAL SUBDIVISION - OPTION 3
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
CUSTOMER REQUEST: 120/208 or 277/480 AVAl LAB LE U N D E RG RO U N D FACl UTI ES
$0 cost per ft plus 2 padmount tx,
2 pads, and ug service minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 2 padmount tx, 2 pads, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters,
and service
MOTOR SIZE
> 25HP
c 5HP
plus 2 padmount tx, 2 pads, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0.68 per ft
plus 2 padmount tx, 2 pads, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters,
and service
5HP < X < 25HP
> 25HP
SINGLE PHASE $8.56 per ft
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$4.1 1 per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $2.12 per ft
plus 3ph padmount tx, pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
TWO PHASES $5.89 per ft
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$3.90 per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $1.44 per ft
plus 3ph padmount tx, pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
THREE PHASES $0 cost per ft
plus 3ph padmount tx, pad, and ug service
minus one oh transformer, cutout, arrester, and service
$0 cost per ft plus 3ph padmount tx, pad, and ug service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 3ph padmount tx, pad, and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt. and service
CUSTOMER REQUEST: 120/240 OPEN DELTA AVAILABLE UNDERGROUND FACILITIES
.
PAGE EFFECllVE DAT€ I
\ GULF& Section No. IV Original Sheet No. 4.26.3
4 SOUTHERN COMPANY
6.3.2 (continued)
(c) The Applicant is required to pay all additional costs required for a service lateral length in excess of the minimum which would have been needed to reach the Company’s designated point of delivery.
(d) The above charges are based upon arrangement of distribution facilities that will permit sewing the local single-phase underground distribution system within the subdivision from existing overhead feeder mains. If the feeder mains or other three-phase facilities within the subdivision are deemed necessary by the Company to provide and/or maintain adequate service and are required by the Applicant or governmental agency to be installed underground, the Applicant shall pay the Company the estimated cost differential between the underground feeder mains, or other three-phase facilities and the equivalent overhead facilities.
6.3.3
6.3.4
FAClLlTJES TO BE UNDERGROUND. All service laterals and secondary and single phase primary conductors shall be underground. Appurlenances such as transformers, pedestal-mounted terminals, switching equipment, and meter cabinets may be placed above ground. Feeder mains required within a subdivision may be overhead if the Applicant and the Company determine that the additional cost of underground is not justified for that particular location, unless otherwise required by governmental authority, in which case the differential cost will be borne by the Applicant or governmental authority.
POINT OF DELIVERY. The point of delivery to the building shall be determined by the Company and normally will be at the point of the building nearest the point at which the underground secondary system is available to the property to be served. If the point of delivery on any building is more than fifty (50) feet in length from the available secondary system (seventy [70] feet for low density subdivisions), then the Applicant may be required to make additional payment for the excess length.
ISSUED BY: Susan Story
\ G U L F 6
PAGE
POWER 9 SOUTHERN COMPANY
EFFECTlVE DATE
Section No. IV Seventh Revised Sheet No. 4.27 Canceling Sixth Revised Sheet No. 4.27
6.3.5
6.3.6
6.4.1
6.4.2
6.4.3
LOCATION OF METER AND SOCKET & SERVICE ENTRANCE FACILITIES. The Applicant shall install a meter socket and suitable service entrance facilities at the point designated by the Company in accordance with the Company's specifications. Service conductors shall be installed, where possible, in a direct line to the point of delivery.
DEVELOPMENT OF SUBDIVISIONS. The above charges are based on reasonably full and timely use of the land being developed. Where the Company is required to construct underground electric facilities through a section or sections of the subdivision or development where, in the opinion of the Company, service will not be required for at least two years, the Company may require a deposit from the Applicant before construction is commenced. This deposit, to guarantee performance, will be based on the estimated total cost of such facilities rather than the differential cost. The amount of the deposit, without interest, in excess of any charges for underground service will be returned to the applicant on a pro-rata basis at quarterly intervals on the basis of installations to new customers. Any portion of such deposit remaining unrefunded, after five years from the date the Company is first ready to render service from the extension, will be retained by the Company.
6.4 UNDERGROUND DISTRIBUTION TO MULTIPLE-OCCUPANCY RESIDENTIAL BUILDINGS
AVAILABILITY. After receipt of proper application and compliance by the Applicant with applicable Company rules and procedures, the Company will install underground distribution facilities within that tract of land upon which multiple-occupancy residential buildings containing five (5) or more separate dwelling units will be constructed.
CONTRIBUTION BY APPLICANT. Service for new multiple-occupancy residential buildings will be constructed underground within the property to be served to the point of delivery at or near the building by the Company at no charge to the Applicant, provided the Company is free to construct its service extension or extensions in the most economical manner and reasonably full use is made of the tract of land upon which the multiple-occupancy buildings will be constructed. The Applicant must pay a cost differential for any non-residential service such as a pool or office building.
METER SOCKETS AND SERVICE ENTRANCE FACILITIES. The Applicant shall install service entrance facilities including meter sockets or suitable facilities for installation of the Company's meters at a location suitable to the Company. Meter sockets of facilities for installation of the Company's meters shall be a type and manufacture approved by the Company.
ISSUED BY: Susan Story
,
PAGE
4 GULF&
EFFECTIVE DATE
POWER A SOUTHERN COMPANY
6.5.1
6.5.2
6.5.3
Section No. IV Seventh Revised Sheet No. 4.28 Canceling Sixth Revised Sheet No. 4.28
6.5 OTHER UNDERGROUND DISTRIBUTION FACILITIES
APPLICABILITY. This subpart applies to requests for underground facilities addressing new construction or the conversion of existing overhead facilities except in cases involving underground facilities in new residential subdivisions. Requests for underground facilities in new residential subdivisions are controlled by subpart 6.3 of this tariff. In order for the Company to take action pursuant to a request for conversion:
(1) the conversion area must be at least two contiguous city blocks or 1000 feet in length;
(2) all electric services to the real property on both sides of the existing overhead primary lines must be part of the conversion; and
(3) all other existing overhead utility facilities (e.g. telephone, CATV, etc.) must also be converted to underground facilities.
NON-BINDING COST ESTIMATES. An Applicant may obtain a non-binding estimate of the charges the Applicant would be obligated to pay in order for the Company to provide underground distribution facilities. This non-binding estimate will be provided to the Applicant without any charge or fee upon completion of the Application for Underground Cost Estimate set forth in Section VI1 of this tariff, Standard Contract Forms, at Sheet No. 7.43.
BINDING COST ESTIMATES. An Applicant, upon payment of a non-refundable deposit and completion of the Application for Underground Cost Estimate set forth in Section VI1 of this tariff, Standard Contract Forms, at Sheet No. 7.43, may obtain an estimate of the charges for underground distribution facilities, which estimate the Company would be bound to honor as provided below. The deposit amount, which approximates the engineering costs for underground facilities associated with preparing the requested estimate, shall be calculated as follows:
New Construction Urban Commercial Urban Residential Rural Residential
Conve rs ion Urban Commercial Urban Residential Rural Residential 210 Lot Subdivision 176 Lot Subdivision
ISSUED BY: Susan Story
$1 , I 13.00 per trench mile $ 834.00 per trench mile $1,274.00 per trench mile
$2,274.00 per overhead primary mile $3,702.00 per overhead primary mile $3,004.00 per overhead primary mile $2,849.00 per overhead primary mile $4,982.00 per overhead primary mile
Section No. VI Eighth Revised Sheet No. 4.28.1 Canceling Seventh Revised Sheet No. 4.28.1
POWER A SOUTHERN COMPANY
PAGE EFFECTIVE DATE
6.5.3 (continued)
An Applicant desiring the Company to proceed with construction of the underground facilities described in a binding cost estimate may enter into a contract with the Company based on said estimate on or before the 180th day following Applicant's receipt of the estimate. So long as the contract is entered into by such date, the contract shall provide that the charges the Applicant is obligated to pay for installation of the underground facilities will be the actual costs incurred subject to the limitation that the charges to the Applicant will not exceed 110 percent of the amount set forth in the binding estimate. So long as said contract is entered into by the date specified above, it shall further provide that the total charges the Applicant is obligated to pay for installation of underground facilities determined as set forth in section 6.5.4 beiow shall be reduced by the amount of the posted deposit associated with the binding cost estimate.
6.5.4
6.5.5
6.5.6
CONTRIBUTION BY APPLICANT. Prior to the installation of underground facilities covered by this subpart, the Applicant and the Company must enter into a contractual agreement setting forth the terms and conditions of the installation. The charge to be paid by the Applicant for underground facilities pursuant to the contractual agreement shall be determined as follows:
The cost of construction of the underground distribution facilities including the construction cost of the underground service lateral(s) to the meter(s) of the customer(s);
plus (if applicable) the estimated remaining book value of any existing facilities to be removed as part of the conversion of existing overhead facitities to underground, less the estimated net salvage value of the facilities to be removed;
minus the estimated construction cost to build new overhead facilities, including the service drop(s) to the meter(s) of the customer(s).
If the installation of the underground facilities is made pursuant to a contractual agreement based on a binding cost estimate received by the Applicant no more than 180 days prior to the date of the contractual agreement, the provisions of section 6.5.3 shall limit and modify the contribution to be paid by the Applicant for underground facilities.
METER SOCKETS AND SERVICE ENTRANCE FACILITIES. The Applicant shall install service entrance facilities including meter sockets or suitable facilities for installation of the Company's meters at a location suitable to the Company. Meter sockets or facilities for installation of the Company's meters shall be of a type and manufacture approved by the Company.
UNDERGROUND SECONDARY LATERAL SERVICE IN AN OVERHEAD RESIDENTIAL OR COMMERCIAL AREA. When requested by a residential or commercial Applicant, the Company will install, own, and maintain an underground secondary service lateral from its overhead facilities to the Applicant's point of delivery. The Applicant shall install a meter socket and suitable service entrance facilities at the point designated by the Company in accordance with the Company's specification. Prior to such installation, the Applicant and the Company will enter into an agreement outlining the terms and conditions of the installation, and the Applicant will be required to pay the Company in advance the cost differential between an overhead service and an underground service. The Applicant may participate in the process by trenching and installing the duct and/or providing the duct.
Section No. VI1 Fourth Revised Sheet No. 7.26 Canceling Third Revised Sheet No. 7.26
NOW, THEREFORE, in consideration of the premises and of the mutual agreements hereinafter set forth, it is agreed by and between the parties as follows:
1. The Utility hereby agrees to permit the Applicant to construct and install all or a portion of the underground distribution facilities described herein below at the above location provided:
a) such work meets the Utility’s construction standards, as set forth below:
(1) system must meet the specifications set forth in Exhibit “D”. Conduit shall be installed in the locations specified in Exhibit “C”;
Conduit to be placed in any Utility underground distribution
( 2 ) cover or at a depth that meets applicable codes and is satisfactory to the utility and the applicant;
Primary and secondary conduit must be buried with 30” of
(3) underground service entrance shall be in accordance with Exhibit “B”;
The connection between the meter enclosure and the
(4) install a tracer wire in the trench with the conduit as specified in Exhibit “E”;
Where the applicant installs the conduit, the applicant must
(5) When the Utility supplies the conduit to the Applicant, the Utility shall take ownership of that conduit at the time it is installed by the Applicant and all other provisions of this agreement have been satisfied. When the Applicant supplies and installs the conduit, the Utility shall take ownership of that conduit at the time the cable has been installed in the conduit by the Utility and all other provisions of this agreement have been satisfied. Until such time that the Utility takes ownership of the conduit, the Applicant, or Contractor acting for the Applicant, shall be responsible for accessing and repairing the conduit;
(4) Utility shall be responsible for accessing, in a reasonable manner, and repairing the conduit and cable. The Applicant’s
After which time the Utility takes ownership of the conduit, the
ISSUED BY: Susan Story EFFECTIVE:
Section No. VI1 Second Revised Sheet No. 7.26.2 Canceling First Revised Sheet No. 7.26.2
3. in Gulf Power Company’s Tariff for Retail Electric Service, Section 6.2.6, under Ownership of Underground Facilities. A copy of said tariff is attached hereto.
By this agreement, the Applicant agrees to adhere to and meet the provisions set forth
4. The Applicant agrees to follow the distribution plan prepared by the Utility, and attached hereto as Exhibit “C”, showing the location of all facilities to be constructed or installed pursuant to this agreement, and agrees to cause all of its contractors and employees to follow such plan. Applicant agrees that any work performed by the Applicant or its contractor shall be in accordance with National Electrical Safety Code (NESC) and local building and safety codes. Applicant agrees that all persons performing work will be licensed by appropriate authorities and will obtain necessary permits.
5. responsible for any accident or damage, to persons or property, which may occur as a result or in any way connected to the Applicant, its employees or contractors installing and constructing the facilities that are the subject of this agreement. The Applicant hereby agrees to indemnify and hold harmless the Utility against any and all liability, loss, cost, damage, or any expense connected therewith, including a reasonable attorney’s fee incurred in the defense of any type of court action related thereto, which may accrue to the Utility by reason of negligence, default, misconduct or strict liability of the Applicant, its employees or contractors in the installation and construction of the facilities described in this agreement. Applicant is not a contractor, subcontractor or employee of the Utility, and performs the installation and construction of the facilities described herein as an entity completely separate and apart from the Utility.
Applicant hereby expressly agrees that the Utility shall in no way be liable or
6. The Applicant agrees to cause to be conveyed to the Ulility, without cost, all easements, including rights of ingress and egress, necessary or convenient to the Utility or required by it for the purpose of operating, maintaining, and removing said underground electrical distribution lines and other necessary equipment.
7. Exhibit “A”, or subdivision of that property, a covenant running with the property and inuring to the benefit of the Utility that requires all electric service to that property to be underground electric service, and that no electric service shall be overhead, except where the Utility determines it is necessary based on its sole discretion. This covenant shall bind the Applicant, its successors and assigns as set forth in paragraph 9. The Utility agrees to provide
Applicant agrees to include in all conveyances of the property described in
ISSUED BY: Susan Story EFFECTIVE:
Section No. VI1 First Revised Sheet No. 7.26.3 Canceling Original Sheet No. 7.26.3
underground electric service in accordance with Exhibit “C” upon application for service by an owner or occupant and no such owner or occupant shall be provided electric service other than underground. Said electric service will be provided by the Utility under applicable Rate Schedules and its Rules and Regulations as filed with the Florida Public Service Commission.
8. parks and public ways encompassed within the perimeter of Exhibit “C” shall be subject to a paramount right of the Utility to utilize the same for construction, repair, maintenance and operation of an underground electrical distribution system; and no owner or occupant shall so use or occupy his property as to obstruct or interfere with the construction, repair, maintenance or operation of said electric distribution system.
The rights of owners and occupants and of the public, in and to the streets, alleys,
9. The Applicant agrees to pay to the Utility the difference between the estimated cost of the underground electrical distribution facilities and the estimated cost of equivalent overhead electrical distribution facilities and applicable non-typical charges as set forth in Gulf Power Company’s Tariff for Retail Electric Service, Section IV, Part 6. This difference is $ foregoing differential will take into account the cost of the underground facilities constructed and installed by the Applicant.
and has this day been paid by the Applicant to the Utility. The
10. assigns of the Utility but shall not be assignable by the Applicant except with the written consent of the Utility first had and obtained; provided, however, that this prohibition shall not be construed to prevent the Applicant from conveying any portion of the property in the Development shown on Exhibit “A”, if such conveyance is made in accordance with the terms of this instrument.
This Agreement shall be binding upon and inure to the benefit of the successors and
ISSUED BY: Susan Story E F F ECTl VE :
Section No. VI1 Third Revised Sheet No. 7.26.4 Canceling Second Revised Sheet No. 7.26.4
By: Title:
Print Name:
WITNESS:
11. in witness whereof, acknowledge this agreement for Underground Construction Standards sei forth above as properly executable:
Representatives from the Utility and the Applicant, through their signatures below, and
By: Marketing General Manager
ATTEST:
IN WTTNESS WHEREOF, the parties hereto have caused this instrument to be properly executed in four counterparts as of the day and year first above written.
APPLICANT: GULF POWER COMPANY: II
Date: 11 Date:
Correspondence with the Applicant should be addressed to:
NAME:
FIRM:
ADDRESS:
CITY: STATE: ZIP CODE:
ISSUED BY: Susan Story EFFECTIVE:
POWER A SOUTHERN COMPANY
PAGE
I 6.2.2 (continued)
EF FECnVE DATE - Section No. IV Second&& Revised Sheet No. 4.23 Canceling First RevisedQegmd Sheet No. 4.23
Any Applicant seeking the installation of underground distribution facilities pursuant to a written request hereunder shall execute the Agreement For Underground Construction StandardsHe&k Seww set forth in Section VI1 of this tariff, Standard Contract Forms, at Sheet no. 7.25. Failure to execute said agreement within 180 days after the delivery by Gulf Power Company of a binding cost estimate shall result in forfeiture of the deposit made. Any subsequent request for underground facilities will require the payment of a new deposit and the presentation of a new binding cost estimate. For good cause Gulf may extend the 180 day time limit. Upon execution of the Agreement For Underground Construction StandardsWric SSFWW ' , payment in full of the differential cost specified in the binding cost estimate, and compliance with the requirements of this tariff, Gulf shall proceed to install the facilities identified in a timely manner.
As a condition precedent to the conversion of any overhead distribution facilities, the Applicant shall have executed agreements with all affected pole licensees (e.g. telephone, cable TV, etc.) for the simultaneous conversion of those pole licensees' facilities and provide Gulf with a copy of the Agreement(s). Such agreements shall specifically acknowledge that the affected pole licensee will coordinate the conversion with Gulf and other licensees in a timely manner so as to not create unnecessary delays. Failure to present to Gulf Power Company executed copies of any necessary agreements with affected pole licensees within 180 days after delivery of the binding cost agreement to the Applicant shall result in forfeiture of the deposit paid for the binding cost estimate, the return of any differential cost paid for the binding cost estimate, the return of any differential cost paid less any actual cost incurred, and the termination of any Agreement For Underground Construction Standards- entered into between the Applicant and Gulf Power Company.
6.2.3 CHANGES TO PLANS. The Applicant shall pay for all additional costs incurred by the Company due to changes made by the Applicant in the subdivision layout or grade after original aqreed upon desian " Company.
6.2.4 UNDERGROUND INSTALLATIONS NOT COVERED. Where the Applicant requests underground electric facilities not specifically covered by these Rules and Regulations, or in areas where the terrain, loads, and/or equiDment a r e i f not typical, and where overhead facilities would otherwise normaliy be provided, the Applicant and the Company may enter into an agreement outlining the terms and conditions of the installation prior to such installation.
6.2.5 TYPE OF SYSTEM PROVIDED. Underqround residential distribution facilities are of standard Companv desiqn, aenerallv with all cable in duct or conduit and above-qrade apourtenances. Unless otherwise stated, service provided will be 120/240 volt sinqle phase. If other tvpes of facilities are requested bv the Amlicant or required bv qovernmental authoritv, the Applicant or qovernmental authoritv will Dav the additional costs if anv.
I JSSUED BY: Susan story-
\ GULF&
PAGE
POWER A SOUTHERN COMPANY
EP FECTIVE DATf - Section No. IV FourthTtwd Revised Sheet No. 4.24 Canceling Third- Revised Sheet No. 4.24
6.2.6 OWNERSHIP OF UNDERGROUND FACILITIES. The Company will install, own, and maintain the electric distribution facilities up to the designated point of delivery except as otherwise stated. Any payment made by the Applicant under the provisions of these Rules will not convey to the Applicant any rights of ownership. The Applicant may, subject to a contractual agreement with the Company, construct and install a h + a portion of the underground distribution facilities provided:
Such work meets the Company’s construction standards;
The Company will own and maintain the completed distribution facilities;
such agreement is not expected to cause the general body of ratepayers to incur greater costs;
the Applicant agrees to pay Gulf Power Company’s current applicable hourly rate for engineering personnel for all time spent reviewing and inspecting the Applicants work done; and
the Applicant agrees to rectify any deficiencies found by Gulf Power Company prior to the connection of any customers to the underground electric distribution system or the connection of the underground electric distribution facilities to Gulf Power Company’s distribution system. Furthermore, the deficiencies must be corrected in a timely manner or Gulf shall construct the system improvement using overhead facilities and the Applicant will have to pay the cost of such improvement and the cost of its removal before the corrected underground facilities will be connected.
6.2.7 RIGHTS OF WAY AND EASEMENTS. (a) General Requirements. The Company shall construct, own, operate, and maintain distribution
facilities only along easements, public streets, roads, and highways which the Company has the legal right to occupy, and on public lands and private property across which rights of way and easements satisfactory to the Company may be obtained without condemnation or cost to the Company.
(b) Schedulina, Clearina, and Gradinq. Rights of way and easements suitable to the Company must be furnished by the Applicant in reasonable time to meet service requirements, and must be cleared of trees, tree stumps, paving and other obstructions, staked to show property lines and final grade, and must be graded to within six (6) inches of final grade by the Applicant before the Company will commence construction, all at no charge to the Company. Such clearing and grading must be maintained by the Applicant during construction by the Company. Grade stakes must be provided at transformer locations.
Should pavinq, qrass, landscapha, or sprinkler systems be installed prior to the construction of the underaround distribution facilities, the Applicant shall Day the added costs of trenchina, backfillina, and restorinq the paving, qrass. landscaping, and sprinkler svstems to their oriainal condition.
ISSUFr) RY: m ~ t a n r -
\ GULF &
PAGE
POWER A SOUTHERN COMPANY
EFFECTIVE DATE
Section No. IV EiqhthSew+h Revised Sheet No. 4.25 Canceling Seventh- Revised Sheet No. 4.25
6.2.8
6.2.9
6.3.1
6.3.2
DAMAGE TO COMPANY'S EQUIPMENT. The Applicant shall be responsible to ensure that the Company's distribution facilities once installed, are not damaged, destroyed, or otherwise disturbed during the construction of the project. This responsibility shall extend not only to those in his employ, but also to his subcontractors. Should damage occur, the Applicant shall be responsible for the full cost of repairs.
PAYMENT OF CHARGES. The Company shall not be obligated to install any facilities until payment of applicable charges, if any, has been completed.
6.3 UNDERGROUND DISTRIBUTION FACILITIES FOR NEW RESIDENTIAL SUBDlVISIONS
AVAILABILITY. After receipt of proper application and compliance by the Applicant with applicable Company rules and procedures, the Company will install underground distribution facilities to provide single phase service to new residential subdivisions of five (5) or more building lots.
CONTRIBUTION BY APPLICANT. (a) Prior to such installations, the Applicant and the Company will enter into an agreement
outlining the terms and conditions of installation, and the Applicant will be required to pay the Company in advance the entire cost as described below:
Option ($ per lot) 1. Gulf supplies and installs all primary, secondary, $41-
Low Density Subdivision
and service trench, duct, and cable.
- 2.gApplicant installs primary and secondary trench and duct system. Gulf supplies primary and secondary duct and supplies and installs service duct. Gulf supplies and installs primary, secondary, and service cable.
$29-
- 3.4,Applicant supplies and installs primary and $2064234 secondary trench and duct. Gulf supplies primary and secondary cable. Gulf supplies and installs service duct and cable.
w
High Density Subdivision
$36- w69
Phc
($ per lot) =a
All construction done bv the Applicant must meet the GomDanv's specifications. All installations must be approved bv the Companv's authorized representative.
The Amlicant is required to pav a charqe per foot and a cost differential for transformers and services (see "Three Phase Lift Station" charts below) for three phase commercial loads requirinq 120/240 volt oDen delta, 120/208 volt w e , or 277/480 volt w e service in new residential subdivisions for each three phase service. This averacle cost will be added to the advanced pavment in 6.3.2(a) above.
(b)
ISSUED BY: Susan Stow-
\ GULF&
PAGE
POWER A SOUTHERN COMPANY
EFFECTlVE DATE
Section No. IV TwelfthHewMb Revised Sheet No. 4.26 Canceling Eleventhh&i Revised Sheet No. 4.26
6.3.2 (continued)
THREE PHASE LIFT STATION COSTS TO PROVIDE 3 PH SVC TO LIFT STATION WAN TYPICAL SUBDIVISION - OPTION 1
CUSTOMER REQl
MOTOR SIZE < 5HP
5HP c X 25HP
> 25HP
IST: 120/208 or 277/480 AVAILABLE UNDERGROUND FACl LIT1 ES
SINGLE PHASE $1 0.85 Der ft
plus 3ph padmount tx, pad, and ua service
minus one oh transformer, cutout, arrester, and
service $6.40 per ft
plus 3 ~ h padmount tx, pad, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $4.41 Der ft
plus 3ph padmount tx, pad. and ug service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
TWO PHASES $7.04 per ft
plus 3ph oadmount tx, pad, and uq service
minus one oh transformer, cutout, arrester, and
service $5.05 Der ft
plus 3ph padmount tx, pad, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $2.59 per ft
plus 3ph padmount tx, pad, and uq service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt. and service
2 $0 cos? per ft
plus 3ph padmount tx, pad. and uq service
minus one oh transformer, cutout, arrester, and
service $0 cost Der ft
plus 3ph padmount tx, pad, and UQ service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 3ph padmount tx, pad, and uq service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
CUSTOMER REQUEST: 120/240 OPEN DELTA
2 pads, and ug service minus one oh transformer,
cutout, arrester, and
2 Dads, and uq service
cutout, arrester, and
2 pads, and uu service
> 25HP
plus2oadmount tx, 2 pads, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $1.82 per ft
plus 2 oadmount tx, 2 pads, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters,
and service
ISSUED BY: Susan Stow
plus 2 padmount tx, 2 pads, and uq service
minus 2 o h transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 2 padmount tx, 2 pads. and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters,
and service r plus 2 padmount tx, 2 pads, and uq service
minus 2 oh transformers, 2 cutouts. 2 arresters, and
service $0 cost per ft
plus 2 padmount tx, 2 pads, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters,
and service
\ GULF&
PAGE
A SOUTHERN COMPANY
EFFECTIVE DATE
Section No. IV Original Sheet No. 4.26.1
MOTOR SIZE < 5HP
5HP < X < 25HP
> 25HP
SINGLE PHASE TWO PHASES $10.45 per ft
plus 3ph Dadmount tx, pad, and uq service
minus one oh transformer, cutout, arrester, and
$6.00 Der ft plus 3 ~ h padmount tx, pad, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
$4.01 Der ft plus 3 ~ h padmount tx, pad, and ua service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
$6.84 Der ft plus 3ph Dadmount tx, pad, and UQ service
minus one oh transformer, cutout, arrester. and
$4.85 Der ft plus 3ph padmount tx, pad, and ua service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
$2.39 per ft plus 3 ~ h padmount tx, pad, and uq service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
service service
service service
6.3.2 (continued)
$5.60 Der ft plus 2 padmount tx,
2 pads, and UQ service minus one oh transformer,
cutout, arrester, and service
plus 2 Dadmount tx, 2 Dads. and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $1 -62 per ft
~ l u s 2 Dadmount tx.
SUmELfi
THREE PHASE LIFT STATION COSTS TO PROVIDE 3 PH SVC TO LIFT STATION WAN TYPICAL SUBDIVISION - OPTION 2
$0 cost Der ft plus 2 Dadmount tx,
2 Dads. and uq service minus one oh transformer,
cutout, arrester, and
$0 cost Der ft plus 2 padmount tx,
2 pads, and ua service minus one oh transformer,
cutout, arrester, and service service
$n rnst npr ft $0 cost Der ft
plus 2 padmount tx, 2 pads, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
$0 cost per ft ~ l u s 2 Dadmount tx,
plus 2 padmount tx, 2 Dads, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
$0 cost per ft ~ l u s 2 Padmount tx.
service service
CUSTOMER REQUEST: 120/208 or 277/480 AVAILABLE UNDERGROUND FACILITIES
CUSTOMER REQl
MOTOR SIZE < 5HP
5HP < X < 25HP
> 25HP
THREE PHASES $0 cost per ft
plus 3ph padmount tx, pad. and ug service
minus one oh transformer, cutout, arrester, and
service $0 cost per ft
plus 3oh Dadmount tx, pad, and UCI service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost Der ft
plus 3ph padmount tx, pad, and uq service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
2 pads, and UQ service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
2 Dads, and UQ service - minus 2 oh transformers, minus 2 oh transformers, -
2 cutouts, 2 arresters, 2 cutouts, 2 arresters, -
2 pads, and uq service
and service and service
POWER A SOUTHERN COMPANY
PAGE
Section No. IV Original Sheet No. 4.26.2
EFFECnVE DATE
$5.89 per ft plus 3 ~ h Padmount tx, pad, and uu service
minus one oh transformer, cutout, arrester, and
service $3.90 Der ft
plus 3ph padmount tx, pad, and UQ service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $1.44 per ft
plus 3ph padmount tx, pad, and ua service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
6.3.2 (continued)
THREE PHASES $0 cost per ft
plus 3 ~ h padmount tx, pad, and uq service
minus one oh transformer, cutout, arrester, and
service $0 cost per ft
plus 3ph padmount tx, pad, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $0 cost per ft
plus 3 ~ h padmount tx, pad, and uq service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt. and service
THREE PHASE LIFT STATION COSTS TO PROVIDE 3 PH SVC TO LIFT STATION WAN TYPICAL SUBDIVISION - OPTION 3
MOTOR SEE - e 5HP
5HP < X < 25HP
> 25HP
CUSTOMER REQUEST: 120/208 or 277/480 AVAILABLE UNDERGROUND FACILITIES
SINGLE PHASE TWO PHASES $4.66 per ft
plus 2 Dadmount tx, 2 pads. and ua service
minus one oh transformer, cutout, arrester, and
$0.68 De rf t plus 2 padmount tx,
2 Dads, and uq service minus 2 oh transformers,
2 cutouts, 2 arresters, and
$0.68 per ft plus 2 Padmount tx.
$0 cost per ft plus 2 padmount tx,
2 pads, and uq service minus one oh transformer,
cutout, arrester, and
$0 cnst npr ft plus 2 padmount tx,
2 Dads, and uq senrice minus 2 oh transformers,
2 cutouts, 2 arresters, and
$0 cost per ft plus 2 Dadmount tx.
service service
service service
MOTOR SIZE < 5HP -
5HP < X e 25HP
> 25HP
SINGLE PHASE $8.56 Der ft
plus 3ph padmount tx, pad, and UCI service
minus one oh transformer, cutout, arrester, and
service $4.1 1 per ft
plus 3ph padmount tx, pad, and uq service
minus 2 oh transformers, 2 cutouts, 2 arresters, and
service $2.12 per ft
plus 3ph padmount tx, pad, and ua service
minus 3 oh transformers, 3 cutouts, 3 arresters, cluster mt, and service
CUSTOMER REQUEST: 1201240 OPEN DELTA AVAILABLE UNDERGROUND FAClLfTlES
THREE PHASES $0 cost per ft
plus 2 padmount tx, 2 pads, and ua service
minus one oh transformer, cutout. arrester, and
service
plus 2 padmount tx, 2 pads, and uq service
minus 2 oh transformers, 2 cutouts. 2 arresters. and
service $0 cost per ft
plus 2 padmount tx.
$0 cnst per f t
2 pads, and ua service minus 2 oh transformers,
2 cutouts, 2 arresters, and service
2 pads, and UQ service minus 2 oh transformers,
2 cutouts, 2 arresters,
2 pads, and ua service minus 2 oh transformers,
2 cutouts, 2 arresters, and service and service
\ GULF&
r PAGE EFFECTlVE DATE 1
I POWER A SOUTHERN COMPANY I
Section No. IV Original Revised Sheet No. 4.26.3
6.3.2 (continued)
(c) The Applicant is required to pay all additional costs required for a service lateral length in excess of the minimum which would have been needed to reach the Company's designated point of delivery.
The above charges are based upon arrangement of distribution facilities that will permit serving the local single-phase underground distribution system within the subdivision from existing overhead feeder mains. If the feeder mains or other three-phase facilities within the subdivision are deemed necessary by the Company to provide and/or maintain adequate service and are required by the Applicant or governmental agency to be installed underground, the Applicant shall pay the Company the estimated cost differential between the underground feeder mains, or other three-phase facilities and the equivalent overhead facilities.
(d)
6.3.3 FACILITIES TO BE UNDERGROUND. All service laterals and secondary and single phase primary conductors shall be underground, Appurtenances such as transformers, pedestal-mounted terminals, switching equipment, and meter cabinets may be placed above ground. feeder mains required within a subdivision may be overhead if the Applicant and the Company determine that the additional cost of underground is not justified for that particular location, untess otherwise required by governmental authority, in which case the differential cost will be borne by the Applicant or governmental authority.
6.3.4 POINT OF DELIVERY. The point of delivery to the building shall be determined by the Company and normally will be at the point of the building nearest the point at which the underground secondary system is available to the property to be served. If t h e point of delivery on any building is more than fifty (50) feet in length from the available secondary system (seventv 1701- feet for low density subdivisions), then the Applicant may be required to make additional payment for the excess length.
ISSUED BY: Susan Stow-
4 G U L F 6 POWER
A SOUTHERN COMPANY
Section No. IV Seventh%# Revised Sheet No. 4.27 Cancelinq Sixth% Revised Sheet No. 4.27
PAGE EFFECTtVE DATE
6.3.5 LOCATION OF METER AND SOCKET & SERVICE ENTRANCE FACILITIES. The Applicant shall install a meter socket and suitable service entrance facilities at the point desiqnated by the Company in accordance with the Company's specifications. Service conductors shall be installed, where possible, in a direct line to the point of delivery.
6.3.6 DEVELOPMENT OF SUBDIVISIONS. The above charqes are based on reasonablv full and timely use of the land beins developed. Where the Companv is required to construct underQround electric facilities throuqh a section or sections of the subdivision or development where, in the opinion of the
Company, service will not be required for at least two years, the Company may require a deposit from the Applicant before construction is commenced. This deposit, to guarantee performance, will be based on the estimated total cost of such facilities rather than the differential cost. The amount of the deposit, without interest, in excess of any charges for underground service will be returned to the applicant on a pro-rata basis at quarterly intervals on the basis of installations to new customers. Any portion of such deposit remaining unrefunded, after five years from the date the Company is first ready to render service from the extension, will be retained by the Company.
6.4 UNDERGROUND DISTRlBUTtON TO MULTIPLE-OCCUPANCY RESIDENTIAL BUILDINGS
6.4.1
6.4.2
6.4.3
AVAILABILITY. After receipt of proper application and compliance by the Applicant with applicable Company rules and procedures, the Company will install underground distribution facilities within that tract of land upon which multiple-occupancy residential buildings containing five (5) or more separate dwelling units will be constructed.
CONTRIBUTION BY APPLICANT. Service for new multiple-occupancy residential buildings will be constructed underground within the property to be served to the point of delivery at or near the building by the Company at no charge to the Applicant, provided the Company is free to construct its service extension or extensions in the most economical manner and reasonably full use is made of the tract of land upon which the multiple-occupancy buildings will be constructed. The Applicant must pav a cost differential for anv non-residentiat service such as a pool or office buildinq.
METER SOCKETS AND SERVICE ENTRANCE FACILITIES. The Applicant shall install service entrance facilities including meter sockets or suitable facilities for installation of the Company's meters at a location suitable to the Company. Meter sockets of facilities for installation of the Company's meters shall be a type and manufacture approved by the Company.
% GULF&
PAGE
POWER A SOUTHERN COMPANY
EFFECTWE DATE
Section No. IV Seventh- Revised Sheet No. 4.28 Canceling S i x t h W Revised Sheet No. 4.28
6.5 OTHER UNDERGROUND DISTRIBUTION FAC I LIT1 ES
6.5.1 APPLICABILITY. This subpart applies to requests for underqround facilities addressinq new construction or the conversion of existinq overhead facilities except in cases involvinq underqround facilities in new residential subdivisions. Requests for underqtound facilities in new residential subdivisions are controlled bv subpart 6.3 of this tariff. In order for the ComDanV to take action pursuant to a request for conversion:
(1) the conversion area must be at least two contiguous citv blocks or 1000 feet in lenqth;
(2) all electric services to the real propertv on both sides of the existinq overhead priman/ lines must be part of the conversion; and
(3) all other existinq overhead utilitv facilities (ea. telephone, CATV, etc.) must also be converted to underqround facilities.
6.5.2 NON-BINDING COST ESTIMATES. An Applicant may obtain a non-binding estimate of the charges the Applicant would be obligated to pay in order for the Company to provide underground distribution facilities. This non-binding estimate will be provided to the Applicant without any charge or fee upon completion of the Application for Underground Cost Estimate set forth in Section VI1 of this tariff, Standard Contract Forms, at Sheet No. 7.43.
6.5.3 BINDING COST ESTIMATES. An Applicant, upon payment of a non-refundable deposit and completion of the Application for Underground Cost Estimate set forth in Section VI1 of this tariff, Standard Contract Forms, at Sheet No. 7.43, may obtain an estimate of the charges for underground distribution facilities, which estimate the Company would be bound to honor as provided below. The deposit amount, which approximates the engineering costs for underground facilities associated with preparing the requested estimate, shall be calculated as follows:
New Construct ion Urban Commercial Urban Residential Rural Residential
Conversion Urban Commercial Urban Residential Rural Residential 210 Lot Subdivision 176 Lot Subdivision
$1 , I 13.00 per trench mile $ 834.00 per trench mile $I ,274.00 per trench mile
$2,274.00 per overhead primary mile $3,702.00 per overhead primary mile $3,004.00 per overhead primary mile $2,849.00 per overhead primary mile $4,982.00 per overhead primary mile
\ GULF&
PAGE
POWER A SOUTHERN COMPANY
EFFECTIVE DATE - Section No. VI EiqhthShw4-b Revised Sheet No. 4.28.1 Canceling SeventhSMk Revised Sheet No. 4.28.1
6.5.3 (continued)
An Applicant desirina the Companv to proceed with construction of the underqround facilities described in a bindinn cost estimate mav enter into a contract with the Companv based on said estimate on or before the 180th dav followina ADplicant's receipt of the estimate. So lonq as the contract is entered into by such date, the contract shall provide that the charaes the Applicant is obliaated to pav for installation of the underqround facilities will be the actual costs incurred subject to the limitation that the charqes to the Applicant will not exceed 110 Dercent of the amount set forth in the bindina estimate. So lona as said contract is entered into bv the date specified above, it shall further provide that the total charaes the ADplicant is obliaated to pav for installation of underqround facilities determined as set forth in section 6.5.4 below shall be reduced bv the amount of the posted deposit associated with the bindinq cost estimate.
6.5.4 CONTRIBUTION BY APPLICANT. Prior to the installation of underqround facilities covered bv this subpart. the Applicant and the Companv must enter into a contractual aqreement settinq forth the terms and conditions of the installation. The charae to be Daid bv the Applicant for underqround facilities pursuant to the contractual aqreement shall be determined as fotlows:
The cost of construction of the underground distribution facilities including the construction cost of the underground service lateral(s) to the meter(s) of the customer(s);
plus (if applicable) the estimated remaining book value of any existing facilities to be removed as part of the conversion of existing overhead facilities to underground, less the estimated net salvage value of the facilities to be removed;
minus the estimated construction cost to build new overhead facilities, including the service drop(s) to the meter@) of the customer(s).
If the installation of the underground facilities is made pursuant to a contractual agreement based on a binding cost estimate received by the Applicant no more than 180 days prior to the date of the contractual agreement, the provisions of section 6.5.3 shall limit and modify the contribution to be paid by the Applicant for underground facilities.
6.5.5
6.5.6
METER SOCKETS AND SERVICE ENTRANCE FACILITIES. The Applicant shall install service entrance facilities including meter sockets or suitable facilities for installation of the Company's meters at a location suitable to the Company. Meter sockets or facilities for installation of the Company's meters shall be of a type and manufacture approved by the Company.
UNDERGROUND SECONDARY LATERAL SERVICE IN AN OVERHEAD RESIDENTIAL OR COMMERCIAL AREA. When requested by a residential or commercial Applicant, the Company will install, own, and maintain aE+@+@wie underground secondary service lateral from its overhead facilities to the Applicant's point of delivery. The Applicant shall install a meter socket and suitable senrice entrance facilities at the point designated by the Company in accordance with the Company's specification. Prior to such installation, the Applicant and the Company will enter into an agreement outlining the terms and conditions of the installation, and the Applicant will be required to pay the Company in advance the m t differential 6e6.t-between an overhead service and an underground servicez&-.! : The Applicant may participate in the process bv trenchinq and installina the duct and/or providinq the duct.
Section No. VI1 F a u r t h W Revised Sheet No. 7.26 Cancelinq ThirdSeawtd Revised Sheet No. 7.26
NOW, THEREFORE, in consideration of the premises and of the mutual agreements hereinafter set forth, it is agreed by and between the parties as follows:
1. The Utility hereby agrees to permit the Applicant to construct and install all or a portion of the underground distribution facilities described herein below at the above location provided:
a) such work meets the Utility’s construction standards, as set forth below:
( 1 ) system must meet the specifications set forth in Exhibit “D”. Conduit shall be installed in the locations specified in Exhibit “C”;
Conduit to be placed in any Utility underground distribution
(2) Primary and secondary conduit must be buried with 30,’ of
7 or at a depth that meets applicable codes and is satisfactory to the utility and the applicant;
,. /‘ ,? cover&::!; I ’/! JQ-
(3) underground service entrance shall be in accordance with Exhibit “B”;
The connection between the meter enclosure and the
(4) install a tracer wire in the trench with the conduit as specified in Exhibit “E’;
Where the applicant installs the conduit, the applicant must
( 5 ) When the Utility supplies the conduit to the Applicant, the Utility shall take ownership of that conduit at the time it is installed by the Applicant and all other provisions of this agreement have been satisfied. When the Applicant supplies and installs the conduit, the Utility shall take ownership of that conduit at the time the cable has been installed in the conduit by the Utility and all other provisions of this agreement have been satisfied. Until such time that the Utility takes ownership of the conduit, the Applicant, or Contractor acting for the Applicant, shaIl be responsible for accessing and repairing the conduit ;
(6) Utility shall be responsible for accessing, in a reasonable manner, and
After which time the Utility takes ownership of the conduit, the
repairing the conduit and cable. The Applicant’s
ISSUED BY: Susan Story- EFFECTIVE: “bW
Section No. VI1 S e c o n d W Revised Sheet No. 7.26.2 Canceling First RevrsedQwgwd Sheet No. 7.26.2
3. By this agreement, the Applicant agrees to adhere to and meet the provisions set forth in Gulf Power Company’s Tariff for Retail Electric Service, Section 6.2.6, under Ownership of Underground Facilities. A copy of said tariff is attached hereto.
4. The Applicant agrees to follow the distribution plan prepared by the Utility, and attached hereto as Exhibit T”, showing the location of all facilities to be constructed or installed pursuant to this agreement, and agrees to cause all of its contractors and employees to follow such plan. Applicant agrees that any work performed by the Applicant or its contractor shall be in accordance with National Electrical Safety Code { N E S C ) H & H ~ and local building and safety codes. Applicant agrees that all persons performing work will be licensed by appropriate authorities and will obtain necessary permits.
5. responsible for any accident or damage, to persons or property, which may occur as a result or in any way connected to the Applicant, its employees or contractors installing and constructing the facilities that are the subject of this agreement. The Applicant hereby agrees to indemnify and hold harmless the Utility against any and all liability, loss, cost, damage, or any expense connected therewith, including a reasonable attorney’s fee incurred in the defense of any type of court action related thereto, which may accrue to the Utility by reason of negligence, default, misconduct or strict liability of the Applicant, its employees or contractors in the installation and construction of the facilities described in this agreement. Applicant is not a contractor, subcontractor or employee of the Utility, and performs the installation and construction of the facilities described herein as an entity completely separate and apart from the Utility.
Applicant hereby expressly agrees that the Utility shall in no way be liable or
6. The Applicant agrees to cause to be conveyed to the Utility, without cost, all easements, including rights of ingress and egress, necessary or convenient to the Utility or required by it for the purpose of operating, maintaining, and removing said underground electrical distribution lines and other necessary equipment.
7. Exhibit “A”, or subdivision of that property, a covenant running with the property and inuring to the benefit of the Utility that requires all electric service to that property to be underground electric service, and that no electric service shall be overhead, except where the Utility determines it is necessary based on its sole discretion. This covenant shall bind the Applicant, its successors and assigns as set forth in paragraph 244. The Utility agrees to provide
Applicant agrees to include in all conveyances of the property described in
ISSUED BY: Susan Stow- -iL17
9 A EFFECTIVE: L 1.
Section No. VI1 First RevisedWgwa4 Sheet No. 7.26.3 Cancelinq Oriqinal Sheet No. 7.263
underground electric service in accordance with Exhibit "C" upon application for service by an owner or occupant and no such owner or occupant shall be provided electric service other than underground. Said electric service will be provided by the Utility under applicable Rate Schedules and its Rules and Regulations as filed with the Florida Public Service Commission.
- 8% parks and public ways encompassed within the perimeter of Exhibit "C" shall be subject to a paramount right of the Utility to utilize the same for construction, repair, maintenance and operation of an underground electrical distribution system; and no owner or occupant shall so use or occupy his property as to obstruct or interfere with the construction, repair, maintenance or operation of said electric distribution system.
The rights of owners and occupants and of the public, in and to the streets, alleys,
- 9 . a The Applicant agrees to pay to the Utility the difference between the estimated cost of the underground electrical distribution facilities and the estimated cost of equivalent overhead electrical distribution facilities and applicable non-typical charges as set forth in Gulf Power Company's Tariff for Retail Electric Service, Section Tv, Part @4. This difference is $ foregoing differential will take into account the cost of the underground facilities constructed and installed by the Applicant.
and has this day been paid by the Applicant to the Utility. The
- 10.44- This Agreement shall be binding upon and inure to the benefit of the successors and assigns of the Utility but shall not be assignable by the Applicant except with the written consent of the Utility first had and obtained; provided, however, that this prohibition shall not be construed to prevent the Applicant from conveying any portion of the property in the Development shown on Exhibit "A", if such conveyance is made in accordance with the terms of this instrument.
ISSUED BY: Susan Stow- EFFECTIVE: -
Section No. VI1 T h i r d S x e d Revised Sheet No. 7.26.4 Canceling Second- Revised Sheet No. 7.26.4
- 1 1 -4-Z Representatives from the Utility and the Applicant, through their signatures below, and in witness whereof, acknowledges this agreement for Underground Constructionti Standards set forth above as properly executable:
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be properly executed in four counterparts as of the day and year first above written.
APPLICANT:
By: Title:
Print Name:
WITNESS:
GULF POWER COMPANY:
By: Marketing General Manager
ATTEST:
Date:
Correspondence with the Applicant should be addressed to:
NAME:
FIRM:
ADDRESS:
CITY: STATE: ZIP CODE:
ISSUED BY: 3nnn
EFFECTIVE: