~r.: .~eLl;'?e c,:.c.eeeeeo~.oooooooooooooooooooo
Ministry of Road Transport & Highways
STANDARD DATAFOR ANALYSIS OF
BOOKRATES
(First Revision)
Published by :Indian Roads Congresson behalf of the Govt. of India,Ministry of Road Transport & Highways
Copies can be had from the Secretary,Indian Roads Congress, Jamnagar House,New Deihl 110011
NEW DELHI - 2003Price Rs. 12001-
(Plus packing and postage charges)
FllSt PublishedFllSt RevisionReprintedReprinted
April. 1994June.2003September. 2003September, 2004
f
f
f
(The Rights of Publication and Translation are Reserved)
~ ff4441
41
41
41
~
-)I ,_
Printed at Aravali Printers & Publishers (P) Ltd . New Delhi-l 10020(500 copies)
,t
FOREWORD TO THE FIRST REVISION
I have great pleasure to present the first revised edition of the Standard Data Book for Analysis of Ratesfor Road and Bridge Works.
The Standard Data Book for Analysis of Rates for Road and Bridge Works was first brought out bythis Ministry in the year 1994. Since then analysis of rates and estimates for National Highway Works areprepared on the basis of the Data Book. This scientific approach provides for uniformity in inputs for variousitems of works, besides standardization in, nomenclature. Further its compatibility with the specificationsof work is ensured, which had been changed to equipment intensive construction in around 1985 from labour-intensive construction methods. The later still forms the basis for analysis of rates adopted by State PWDs,Owing to its merits, ,Ministry's Standard Data Book is being adopted by various agencies for projects otherthan National Highways.
However, a need had been felt for revision and updation of the Standard Data Book on account of thefollowing: (i) (ii)(iii)_. ("IV)
(v)
(vQ
Technological upgradation as per currently revised MORT&H Specifications for Road and Bridge Workspublished in August, 2001.Increased level of 'mechanization.Changes in size, capacity and types of equipment since 1994.Rationalisation in overheads and contractor's profit, based on experience and general increase inproject 'size.Inclusion of new Chapters on Concrete Pavement, Gao-synthetics, Reinforced Earth and Maintenanceof Roads.Incorporation of use of f1yash in road construction.
This revised edition of the Standard Data Book has been finalised in a record time with proper research,analysis and validation, along with a user-friendly Window-based soflYlare for efficient applicaton, This wouldnot have been possible without untiring efforts ofconcemed officers and staff of the Ministry of Road Transport& Highways, Indian Roads Congress and RITES, consultants engaged for the work. I would like to expressmy appreciation of SlShri S.C. Sharma and C.C. Bhattacharya, former DG(RD) & AS for their valuableguidance. I would also like to express my appreciation for commendable efforts put in by S/Shri Jai Prakash,S.K. Kaistha, R.S. Ninan, A.P.S. Sethi, Chief Engineers, Shri S.S. Nahar, Superintending Engineer,S/Shri Sudip Chaudhary and Atul Kumar, Executive Engineers of the Ministry of Road Transport & Highways,Shri G. Sharan, Secretary, IRC, S/Shri R.K Jain & KB. Thandavan, Technical Consultants, IRC andShri S.C. Kakkar, Under Secretary, IRC and S/Shri N. Venkataraman & Harbhajan Singh of RITES.
I ar . sure this Data Book, in its present form, would prove to be very useful to all practicing HighwayEngineers. The Data Book, however, needs to be updated periodically with changes of technology andenvironment. The Ministry would, therefore, welcome the feedback/suggestions from users, so that any furtheramplification/modification/updating may be attempted in due course.
New DelhiJanuary, 2003.
(N.K. Sinha)Direclor General (Road Development) &Special Secretary to the Govt. of India
oo
444
ttt41414141414141
:;;: .,.'
""",,,,,,,,,,,,,""".."," !
eeeeeeee.-oooooooooooooooooo
KSOUMYSORE
CONTACT
HOME ABOUT PROGRNAIES ADr.ISStON DEPARnENT EXAMS RESU.TS ADlaI FACImES
KSOU_ ...
_Us
ABOUT US
ICamataIla State Open UrWersly plays a significant role In pnxTICIUngthe desired growth of
higher education through Open clstataleilmlng system (001.). 0.. aM1by WII be a super
P3W8' only when I: ad*!ves the targeb!d growth of higher education, which I: achieves the
targeted growth of higher educaUon. which IS possible I7f the .Intervention of open and
di5lanc:e learning. The UnIversly having II strong genesis of the InstIllte of Correspondence
Course and Contirll*lg Course and CDnth*1g fducatIon (ICCa.CE), a f*Jneer In the AsIan
mntInent. was established In 1996 under the state enactment: - KSOU Act 1992. As lucidly
Insaibed In its motto -Higher EducatIc:ln to Everyone Everywhere,. XSOU Is evoMng the
.str'abgies to reach the door-steps rI the .studs1ts not only In the state of Kamataka btt also
In the autry and abroad. For thIs-pupose, KSOU has established regional COU1byand
~ For this purpose, KSOU has established regIanaI ~ even In abroad.
DurIng 2~2DI0 the student eNOIment In the UriYersIty has crossed 1.00 Iakh. Dlmg
2010-2011 the UnIw!rsity IS expetted to enroll rNf!I 2.00 IilIkh students which are possible
ttvol9t Its state-of,.rt 1nIia5trucbJre, cornmIlted staff, and managerial sIdIs. ()Jr COl'I'lmldy
of learners lndudes Academidans, AdmllllmatM, Exel:utIYe;s.0Iftcers of cemat and stateGovet'M1eftts, PoMk:Ians, L.egaI Experts, Artists, Fanners, WrileIs, Meda Persons,
TechnIdans. and others whose age ~ ranges.from 18 to 80 yeBr$.
The UntYersIty l!I'IlXlUfa9l!S the students of SChecUe castes and 5l:tledt* Tribes by ~ of
Fee ReImbursement under sqsr gt;lVel'M'Il!nt sd1oIarsNps. It also encourages the students ofecooomicaDy weaker sectlons under -Huktha ~' PrasaiIraanga is playing a signIftcant
role In promoting the fleId oIl1erabft ttvoogh the publcatlons of great WOI1ts01 renowned
http://ksoumysore. edu.in/ AboutU s.html
Page 1 ofl
HELP
-. I. ,
21/10/11
ttttt41414141
-rItI~
,0I'Io~e
~
CONTENTS
PART A. ROAD WORKS
PartA.Road WorksChapter Item No. Description Page
Basic Approach and General Conditions for the Preparation of Standard Data Book 3
1. Carriage of Materials 9
Preamble 9
1.1. Loading and Unloading of Stone Boulder/Stone Aggregates! 10
SandlKankarIMoorum
1.2. Loading andUnloading of Stone Boulder by Manual Means 11
1.3. Loading and Unloading of Cement or Steel 11by ManualMeans and Stacl
PartA.Road WorksChapter Item No. Description
2.11. Dismantling of Fencing
2.12. Dismantling of CI Water Pipe line
2.13. Removal of Cement Concrete Pipe of Sewer Gutter
2.14. Removal of TelephoneJEleclric Poles & lines
3. Earthwork, ErosIon Control and Drainages
Preamble
3.1. Excavation in Soil by Manual Means
3.2. Excavation in Ordinary Rock by Manual Means
3.3. Excavation in Soil with Dozer with lead upto 100 m
3.4. Excavation in Ordinary Rock with Dozer with leadupto 100 m
3.5. Excavation in Hard Rock (requiring blasting) .with disposal upto 1000"m
3.6. Excavation in Soil using Hydraulic Excavator CK 90 andTipper with disposal upt!> 1000 m .
3.7. Excali3!ion in Ordinary Rock using Hydraulic ExcavatorCK 90 and Tipper with disposal upto 1000 m
3.8. Excavation in Hard Rock (blasting prohibited)
3.9. Excavatlon in Hard Rock (controlled blasting) with disposalupto 1000 m .
3.10. Excavation in Marshy Soil
3.11. Removal of Unserviceable Soil with disposat upto 1000 m
3.12. Pre-splitting of Rock Excavation Siopes
3.13. Excavation for Structures
3.14. .Scarifying Existing Granular Surface to a depth of50 mm by Manual Means
3.15. Scarifying Existing Bituminous Surface to a depth of 50 mmby Mechanical Means
3.16. Construction of Embankment with Material obtained fromBorrowpils
(vi)
~
tt
t
tPage
t
42 tI
42 tI
43 tI
44 45 45 48til
49til
50til
50til
51 til
til52 til
53 54 56 57 58 5960 67 67 68
~ ,~,
-'.oooo'0ooI
o
oool:0
~
fb
PartA.Road Worlu!Chapter Item No. Description - Page
3.17. Construction of Embankment with Material 70deposited from Roadway Cutting
3.18. Construction of SUbgrade and Earthen Shoulders 713.19. Compacting Original Ground 723.20. Stripping' and Storing Top Soil 743.21. Stripping, Storing and Re-Iaying Top Soil from Borrow Areas 74. .
in Agriculture Fields
3.22. TUrfing with Sods 753.23. Seeding and MUlching 763.24. Surface Drains In Soil 773.25. Surface Drains in Ordinary Rock 793.26. Surface Drains in Hard Rock 803.27. Sub-Surface -Drains with Perforated Pipe 803.28. Aggregate Sub-Surface Drains 813.29. Underground Drain at "Edgeof Pavement 823.30. Preparation and Surface Treatment of Formation 823.31. Construction of Rocklin Embankment 833.32. Excavation in Hilly Areas in Soil by Mechanical Means 843.33 Excavation in Hilly Areas in Ordinary Rock by Mechanical 85
Means not requiring Blasting
3.34. Excavation in Hilly Areas in Hard Rock requiring Blasting 863.35. Work in Urban Roads 873.36. Construction of Embankment with FlyashIPond Ash available 89
from Coal or Lignite Buming Thermal Plants as Waste.Material
4. SUb-Bases, Bases (Non-Bituminous) and ShouldersPreamble
4.1. Granular Sub-Base with Close Graded Material
4.2. Granular Sub-Base with Coarse Graded Material
4.3. Lime Stabilization for Improving Subgrade
91
91
9295 ....
97
(vii)
(vIII)
ttt
Page 99 100 101 102 103 104 107 109 110 112 11.3 114 114 '.~, 116 / 118 121 121 123 124 125 128 130 132 135 138
PartA.RoadWorksChapter Item No. Description
Lime Treated Soil for Sub-Base
Cement Treated Soil Sub-BaseJBase
Cement Treated Crushed Rock or Combinationin Sub-BaseJBase
4.7. Making 50 mm x 50 mm Furrows
4.8. Inverted Choke
4.9. Water Bound Macadam
4.10. Crushed Cement Concrete Sub-BaseJBase
4.11. Penetration Coat Over Top .Layer of Crushed CementConcrete Base
4.4.
4.5.4.6.
4.12. Wet Mix Macadam
4.13. Construction of Median and Island with Soil taken fromRoadWay cutting
4.14. ConstruCtion of Median and Island with Soil taken fromBorrow Areas
.4.15. Construction of Shoulders
4.16. Footpaths and Separators
4.17. Crusher Run Macadam Base
4.18. Lime, Flyash Stabilised Soil Sub-Base
5. Bases and Surface Courses (Bituminous)
Preamble
5.1. Prime Coat
5.2. Tack Coat
5.3. Bituminous Macadam
5.4. Bituminous Penetration Macadam
5.5. Built-up Spray Grout
5.6. Dense Graded Bituminous Macadam
5.7. Semi-Dense Bituminou~ Concrete 5.8. Bituminous Concrete
-.,I
e~
~ee"
PartA.RoadWorksChapter Item No. Description Page
5.9. Surface Dressing
5.10. Open-GradedPremix Surfacing
5.11. Close-GradedPremix SurfacinglMixed Seal Surfacing
5.12. Seal Coat
5.13. Supply of Stone Aggregates for Pavement Courses
5.14. MasticAsphalt
5.15. Slurry Seal
5.16. Recyclingof Bituminous Pavementwith.CentralRecyclingPlant
5.17. Fog Spray
5.18. BituminousCold Mix (Including GravelEmulsion)
5.19. Sand Asphalt Base Course
5.20. ModifiedBinder
5.21. Crack Prevention Courses
5.22. RecipeCold Mixes
~,0,OJ
ooooooob,9b
6. Cement Concrete Pavement
Preamble
6.1. Dry Lean Cement Concrete Sut>.Base
6.2. Cement Concrete Pavement
6.3. Rolled Cement Concrete Base
6.4. TransitionSection between Rigid and Flexible Pavements
6.5. Constructionof BaseJSut>.Baseof Pavementwith LeanConcrete - Flyash
6.6. Cement - Flyash Concrete Pavement
7. Geosynthetlcs and Reinforced Earth
Preamble
7.1. Sut>.SurfaceDrain with Geotextiles .
7.2. NarrowFilter Sut>.SurfaceDrain
(IX)
141
143
146
147
150
151
153
157
159
160
168
170
172
177
181
181
183
184
187
188
189
191
194
194
195
196
Page
41197
41198 199 205 C205 C207 C209 211 213 215 216
~218 220 221 .' " 221 222 223 225 226 228 229 230 231 233 ".~.
PartA.Road WorksChapter Item No. Description
7.3. Laying Paving Fabric Beneath a Pavement Overlay
7.4. Laying Boulder Apron in Crates of Synthetic Geogrids
7.5. Reinforced Earth Structures
8. Traffic Signs, Markings and other Road Appurtenances
Preamble
Cast.in-Situ Cement Concrete M 20 Kerb
Cast.in-Situ Cement Concrete M 20 Kerb with Channel
Printing New Letters and Figures of any Shade
Retro-Reflectorised Traffic Signs
Direction and Place Identification Signs upto 0.9 sqmSize Board
Direclionand Place Identification Signs with Sizemore than 0.9 aqm Size Board
Overhead Signs
Painting Two Coats on New Concrete Surfaces
Painting on Steel Surfaces
Painting on Wood Surfaces
Painting Unes, Dashes, Arrows, etc. on Roads in Two Coatson NewWork
Painting Unes, "Dashes, Arrows, etc. on Roads in TwoCoats on Old Work
Road Marking with Hot Applied Thermoplastic Compoundwith Reflectorising Glass Beads on Bituminous Surface
Kilometre Stone
Road Delineators
Boundary Pillar
G.!. Barbed Wire Fencing 1.2 m High
G.!. Barbed Wire Fencing 1.8 m High
Fencing with Welded Steel Wire Fabric 75 mm x 50 mm
8;1.
8.2.
8.3.
8.4.
8.5.
8.6.
I8.7.
~ 8.8.f:"
l:i8.9.
"~I 8.10.'i!iiii'l 8.11.!'iI~
0!.
m8.12.
It 1l.13."L!i,'
8.14.
8.15.
8.16.
8.17.
8.18.
8.19.
(x)
J..
4
4
44444
PartA.Road WorksChapter Item No. Description Page
9. Pipe Culverts 270
270
271
272
9.1.
9.2.
Preamble
PCC 1:3:6 in Foundation
I..aying Reinforced Cement Concrete PipeNP 4IPrestressed Concrete Pipe on First Class Beddingin Single Row .
I..aylng Reinforced Cement Concrete PipeNP 4IPrestressed Concrete Pipe on First Class Beddingin Double Row
2749.3.
10. Maintenance of Roads 277
Preamble 27710.1. Restoration of Rain Cuts 27810.2. Maintenance of Earthen Shoulders (filling with fresh soil) 279. .10.3. Maintenance of Earthen Shoulders (stripping excess soil) 280
10.4. FiRingPot-holes and Patch Repairs with 281Open-Graded Premix Surfacing, 20 mm
10.5. Filling Pot-holes and Patch Repairs with Bituminous 282Concrete, 40 mm
10.6. Crack Filling 28310.7. Dusting 284
10.8. Fog Seal, Crack Prevention Courses, Slurry Seal, 284Surface Dressing for Maintenance Works
10.9. Repair of Joint Grooves with Epoxy Mortar 285
10.10. Repair of Old Joints Sealant 286
10.11. Hill Side Drain Clearance 286
10.12. landslide Clearance in Soil 287
10.13. landslide Clearance in Hard Rock Requiring Blasting 288
10.14. Snow Clearance on Roads with Dozer 289
10.15. Snow Clearance on Roads with Snow Blowers 290
(xii)
- PartA. Road Works Chapter Item No. 11. Horticulture 11.1. 11.2. 11.3. 11.4. 11.5.t' 11.6. 11.7. 11.8. 11.9. 11.10. 11.11. 11.12. 11.13.0 11.14.
11.15. 11.16. 11.17.t 11.18.11.19. 11.20.~ 11.21.000 ,
0
Description Page
291
Preamble 291
Spreading of Sludge Farm Yard Manure orland Good Earth 292
Grassingwith 'Doob' Grass 292
Making Lawns including Ploughing and Draggingwith 294'Swagha' breaking'ofClod
Maintenanceof Lawns or Turfing of Slopes 295
Turfing Lawnswith Fine Grassing including Ploughing, 295Dressing
Maintenanceof Lawnswith Fine Grassing for the First Year 296
Planting andMaintaining of Permanent Hedges 297
Planting and Maintaining of Flowering Plants and Shrubs 299
_ Planting of Trees and their Maintenance for One Year 300
Renovationof Lawns inclUding,Weeling, Forking the Ground, 301Top Dressingwith Forked Soil
Supply of SiteWell Decayed Farmyard Manure 302
Supply at Site of Work/Store-Deoiled Neem Cake 302
SupplyingSludge 303
Half Brick Circular Tree Guard 303
Edgingwith 2nd Class Brick, Laid Dry Lengthwise 304
MakingTree Guard 1.3m High from Empty Bitumen Drums 305
MakingTree Guard 2.0 m High from Empty Bitumen Drums 306
Wrought Iron and Mild Steel Welded Work 307
Tree Guardwith MS Iron 308
Tree Guardwith MSAngle Iron and Steel Wire . 309
CompensatoryAfforestation 310
(xiii)
B. BRIDGE WORKS
tt
t
Page 315 318 tI
318 tI
321 330. 331 331 332 333 333 335348
til
350 351 ~371 377 383 389 395 401 407 413 419 ,
: \! '
, "
Part B.Bridge WorksChapter Item No. Description
Basic Approach for the Preparation of Standard Data Book
12. FoundationPreamble
12.1 Excavation for structures
12.2 Filling Annular Space' Around Footing. in Rock
12.3 Sand Filling in Foundation Trenches
12.4 PCC 1:3:6 in Foundation12.5 Brick Masonry Work in Cement Mortar 1:3 in Foundation
12.6 Cement Mortar 1:312.7 Stone Masonry in Cement Mortar 1:3 in Foundation
12.8 Plain/Reinforced Cement Concrete in Open Foundation
12.9 Providing & Constructing Temporary Island for Constructionof Well Founcfalion
12.10 Providing and Laying Cutting Edge of Mild Steel for WellFoundation .
12.11 Plain/Reinforced Cement Concrete in Well Foundation
12.12 Sinking of6 m Extemal Diameter Well through all Typeof Strata
12.13 Sinking of 7 m Extemal Diameter Well through all Typesof Strata
12.14 Sinking of 8 m External Diameter Well through all Typesof StrataSinking of 9 m External Diameter Well through all Typesof StrataSinking of 10 m External Diameter Well through all Typesof StrataSinking of 11 m External Diameter Well through all Typesof StrataSinking of 12 m External Diameter Well through all Typesof StrataSinking of Twin D-Type Well through all Types of Strata
Pneumatic Sinking of Wells with Equipment
12.15
12.16
12.17
12.18
12.19
12.20
(xiv)
PartB. . Bridge WorksChapter Item No. 12.21"12.22 12.23 12.24 12.25 12.26 12.27 12,28 12.29 12.30 .; 12.31 12.32
00 12.3300 12.34
0 12.3500 12.36
0 12.370 12.380 12.390000
f
Description Page
Sand Filling in Wells 422'
Providing Steel Liner 10 mm Thick for Curbs and 6 mm Thick 422for Steining of Wells
Bored Cast-ln-8itu M 35 Grade RCC Pile of 423Diameter 750 mm
Bored Cast-In-Situ M 35 Grade RCC Pile of 424Diameter 1000 mm
Bored Cast-In-Situ M 35 Grade RCC Pile of 425Diameter 1200 mm
Driven Cast-In-Place M 35 Grade RCC Pile of 427Diameter 750 mm
Driven Cast-In-Place M 35 Grade RCC Pile of 428Diameter 1.000mm
Driven Cast-In-Place M 35 Grade RCC Pile of 430Diameter 1200 mm
Driven Precast Vertical M 35 Grade RCC Pile of 431Diameter 500 mm
Driven Precast Vertical M 35 Grade RCC Pile of 432Diameter 750 mm
Driven Precast Vertical M 35 Grade RCC Pile of '714Diameter 1000 mm
Driven Precast Vertical M 35 Grade RCC Pile of Size 435300 mm x 300 mm
Driven Precast Vertical M 35 Grade RCC Pile of Size 436500 mm x 500 mm
Driven Precast Vertical M 35 Grade RCC Pile of Size 437750 mm x 750 mm
Driven Vertical Steel Piles of H-Section Steel Column 438400 mm x 250 mm (ISHB series)
Driven Vertical Steel Piles of H-Section Steel Column 439450 mm x 250 mm (ISHB series)
Pile Load Test on Single Vertical Pile 440
Cement Concrete for Reinforced Concrete in Pile Cap 441Levelling Course for Pile Cap 447
(xv)
cccCee(
e462
463'" .
464 465
466 469
471
471
472 489
490
i
,
Part B .Bridge WorksChapter Item No.
DescriptionPage
44812.40
12.41
13. Substructure
13.1
13.213.3
13.4
13.5
13.613.7
13.8
13.9
13.10
13.11
13.12
13.13
13.1413.15
13.16
14. Superstructure
, 1
Supplying, Fitting and Placing Uncoated HYSD BarReinforcement in FoundationSupplying, Fitting and Placing Uncoated Mild SteelReinforcement in Foundation
PreambleBrick Masonry Work in 1:3pointing with Cement Mortar (1:3) on Brick Work
Plastering with Cement Mortar (1:3) on Brick Work
Stone Masonry Work in Cement Mortar 1:3
PlaintReinforced Cement Concrete in Substructure
Supplying, Fitting & Placing HYSD Bar Reinforcement
Supplying, Fitting & Placing Mild Steel Reinforcement
Providing Weep Holes in Brick MasonrylPlainJ-Reinforced Concre~eBackfilling Behind Abutment, Wing Wall and Return Wall
Providing and Laying of Filter Media with Granular Materials
Supplying, Fitting and Fixing Cast Steel Rocker Bearing
supplying, Fitting and Fixing Forged Steel Roller Bearing
Supplying, Fitting and Fixing Sliding Plate Bearing with PTFESurface Sliding on Stainless SteelSupplying, Filling and Fixing Elastomeric Bearing
Suppling, Fitting and Fixing Sliding Plate Bearing withStainless Steel Plate with Mild Steel Matrix
Supplying, Fitting and Fixing POT-PTFE Bearing
14.114.2
14.3
PreambleFurnishing and .Placing Reinforced/Prestressed Concrete
Supplying, Fitting and Placing HYSD Bar Reinforcement
High Tensile Steel Wires/Strands Including all Accessories
for Stressing
(XVI)
449
450
450
451
451
452453455
459460
461
467
468
,.e!t,~o0,
oooooooo0'ooooo
i
o
PartB.Bridge WorksChapter Item No. Description Page
14.4 492
14.5
14.6
14.7
14.8
14.9
14.10
14.11
14.12
-14.13
14.14
14.15
14.16
14.17
14.18
14.19
14.20
14.21
14.22
14.23
14.24
Providing and Laying Cement Concrete Wearing Coat M 30Grade Including Reinforcement
Mastic Asphalt
Construction of Pre-Cast RCC Railing of M 30 Grade,Aggregate Size not Exceeding 12 mm
Construction of RCC RaUlng of M 30 Grade, In-situwith 20 mm Nominal Size
Providing. Fitting and Fixing Mild Steel Railing
Drainage Spouts
PCC M 15 Grade Levelling Course Below Approach Slab
ReinforcedCemllnt Concrete Approach Slab
Providing Anti"Corrosive Treatment to HYSD Reinforcementwith FusiOn Bonded Epoxy Coating (FBEC)
Providing, Precasting, Transpqrtingand Placing in PositionPreeast-Pretensionild Concrete Girders
Providing and Fixing Helical Pipes in Voided Concrete Slabs
Crash Barriers
Painting on Concrete Surface
Buried Joint
Filler Joint
Asphaltic Plug Joint
Elastomeric Slab Steel Expansion Joint
Compression Seal Joint
Strip Seal Expansion Joint
Modular Strip/Box Seal Joint Beyond 70 mm and uptoto 140mm
Modular Strip/Box Seal Joint Beyond 140 mm and upto .to 210 mm
15. River Training & Protection Works
Preamble
15.1 Providing and Laying Boulders Apron on River Bed
15.2 Boulder Apron Laid in Wire Crates
(xvii)
493
495
497
498499
500
500
501
502
504
505
505
506
507
510
512
513
515
516
517
519
519
520521
444
Part B. ..; tBridge Works tChapter Item No. Description Page t
15.3 Cement Concrete Blocks (size 0.5xO.5xO.5 m) 522 t15.4 .Providing and Laying Pitching on Slopes 522 15.5 Providing and Laying Filter Material Undemeath Pitching 523 in Slopes C15.6 Geotextlle Filter 524 f15.7 Toe Protection 525
Providing and Laying FlooringC
15.8 525
15.9 Dry Rubble Flooring 526C
15.10 Curtain Wall 527 15.11 Flexible Apron 527
C
15.12 Gabion Structure for Retaining Earth 528 15.13 Gabion Structure for Erosion Control, River Training Works 530
and Protection Works ,16. Repair and Rehabilitation 532
Preamble 532 16.1 . Removal of Existing Cement Concrete Wearing Coat 533 ,.
including its Disposal 18.2 Removal of Existing Asphaltic Wearing Coat 533 16.3 Guniting Concrete Surface with Cement Mortar Applied with 534 Compressor16.4 Providing and Inserting Nipples with Approved 535
Fixing Compound 16;5 Sealing of CracksIPorous Concrete by Injection Process 536 16.6 . . Pa~ing of Damaged Concrete Surface with 537 -. POlYmerConcrete16.1 Sealing of CrackIPorous Concrete with Epoxy 538
Grout by Injdon through Nipples 16.8 Applying Epoxy Mortar Over Leached, Honey Combed and 539 Spalled Concrete Surface and Exposed Steel Reinforcement16.9 Removal of DefecUveConcrete 540 16.10 Applying Pre-Packed Cement Based Polymer for 541
Replacement of Spalled Concrete (xviii) 1
-oooo
PartB.Bridge Works'Chapter Item No. Description Page
16.11
16.12
16.13
16.14
16.1~16.1616.1716.1816.1916.2016.2J16.2216.23
Epoxy Bonding of New Concrete to Old Concrete
Providing Extemal Prestressing with High Tensile SteelWireslStrands-Span 25 m
Providing Extemal Prestressiilg with High Tensile SteelWireslStrands-Span 50 rn
p'rovidingExtemal Prestressing with High Tensile SteelWirelStrands-Span 100 m
Replacement of BearingsRectification of BearingsReplacement of Expansion JointsReplacement of Damaged Concrete RailingReplacement of Crash BarrierReplacement of Damaged Mild Steel RaifingRepair of Crash Barrie!
Repair of RCC RailingRepair of Steel Railing
17. Usage Rates of Plant and Machinery
(xix)
542
542
544
546
547548549550550551552553554
555
MHlimetrecentimelreMetreKilometreSquare metreHectrareSquare KilometreCubic MetreLitreKilolitreKilogramquintaltonnetonne kilometreMinislJy Qf Road Transport and HighwaysIndian StandanlIndian Roads CongressTools and PlantsGaJvanlsedlronCast IronReinfon:ed cement ConcretePlain Cement ConcreteGround LevelRupeesDiameterMinimumMaximumNumberHolrThat isFor exampleWater Bound MacadamBituminous MacadamSemI-Dense Bituminous Concrete. Bituminous ConcreteFront end LoaderOptimum Moisture ContentLead in KilometreHot Mix PlantRoad RollerWet Mix Macadam
ff
fIfI
41
414141
,..,.
ABBREVITA11QNS
mmemmkmSqmhaSq.kmcumIklkgqttkmMoRT&HISIRCT&PGlaRCCPCCGLRsDiaMinMaxNo.hri.e,egWBMBMSDBeBeFE loaderOMCLHMPRRWMM
(xx)
,.eeeeo0,
oooo0;
!0:oooioo ,0'
PART-A
ROADWORKS
tt
),- -.
':
eoooooooooooooooof>
tb
A. Road Works
Basic Approach and General Conditions for the Preparationof Standard Data Book
The basic approach for the preparation of Standard Data Book for Road Works is indicated as under:
Description of Items
1. The description of items is given briefly and linked with the relevant clause of the MoRT&HSpecifications for Road and Bridge Works, which may be referred for detailed description, provisions.and interpretation ..
2. Mechanical Means
Due to mechanization of construction work, rate analysis for various items have been preparedusing mechanical means. However, manual means have also been provldedforcertain cases,where areas maybe inaccessible for machines or quantum of work may not be large enough tojustify use of machines.
3. Overhead Charges
The overhead charges include the following elements :
i. Site accommodation, selling up plant, access road, water supply, electricity and general sitearrangements.
ii. Office fumiture, equipment and communications
iii. Expenditure on
a) Corporate office of contractorb) Site supervision
c) Documentation and "as builr draWings
w. Mobilisation/de-mobilisation of resources
v. Labour camps with minimum amenities and transportation to work sites
vi. Light vehicles for site supervision including administrative and managerial requirements
vii. Laboratory equipment and quality control including field and laboratory testing
3
ix. watch and ward
----_.
viii. Minor T&P and survey instruments and setting out works, including verification of line,dimensions, trial pits and bore holes, where reqUired
x. Traffic management during construction
xi. Expenditure on safeguardiJ19environment
xii. Sundries
xiii. Anancing Expenditure
xiv. saleslTum over tax
>N. Work Insurance/compensation
3.1. For the purpose of calCulation of overhead charges, the projects are categorized into 2 typesas under and overhead charges, provided as indicated against each.
Category 1:Cost up to Rs. 50 crores 10percent
Category 2: Cost above Rs. 50 crores 8 percent
4. Contractor Profit: 10 per cent of cost of works
Contractor profit is also added on overhead charges.
5. Basic Inputs
Basic inputs are only given in the standard data book. The rates for material and labour are to beobtained from local authorities for thlil area where the project is located.
6. Plants and EqUipment
6.1. A dozer is proposed for excavation where cutting and filling for the roadway is within 100 m. Forlonger leads, a combination of hydraulic excavator and tipper is proposed.
6.2. Keeping in view the job and managerial factors and thlil aglil factor of machines, the output of plantand lilquipment is taken approximately 70 per cent of thlil rated capacity given by manufactureunder ideal conditions.
4
t'-tt
,,eoo~
oooooooo
9
6.3. It has been assumed lhat a water tanl(er would make one trip per hour on an average. Watercharges have flOt'beert inQIUdedfor items Where the Rlquirement is very nominal. It is assumedthat the same would be covered under sundries.
6.4. Output of plant/equipment is considered for the compacted quantities.
6.5. The usage charges for machines include ownership charges, cost of repair and maintenanceincluding replacement of lyres and running and operating charges which includes crew, fuel andlubricants. '
7. Materials
7.1. Quantities of materialsgivenin the rate analysis are approximate for the purpose of estimatingand include normal wastages. ActUal consumption would have to be based on mix design.
7.2. '. The rates fo material shoukBnclude basic costat locations of stone crushers, loading, unloading,cost fo carriage and stacking at plant sites as the case may be.
7.3. The alternative proposal for curshingown aggregate by installing Crusher should be comparedwith procurement of crushed aggregates from the market and proposal found economical may beadopted.
7.4. The specifications of materials shall be govemed by section 1000 of MoRT&H Specifications forRoad and Bridge Works.
8. Labour
8.1. The labour wages should be as per rates fixed by state government.
8.2. One mate 'has been provided for 25 labours.
8.3. Skilled labour include mason, carpenter, blacksmith, mechanics and other trades.
9. Carriage of Materials
9.1. The unit for vehicle for carriage has been taken as under.
a) In hours where lead Is defined inclUding time required tor loading and unloading.
b) In tonne - km where lead Isvariable. The loading and unloading for such cases have beenprovided.separately ,
5
I
9.2.
10.
10.1.
10.2.
10.3.
10.4.
10.6.
10.7.
10.8.
IIIi.1
'I
iL
General:
t
C
C
~~
44ttt41
41
41
41
41411
411
411
Where the quantity of material to be transported is small such as dismantled materials and !besame are required to be loaded manually, provision oftraclor-Irolley has been made instead~)tipper.
The clause numbers refer to MoRT&H Specifications for Road and Bridge Works.
Assumptions made have been indicated in respective chapter in the form of notes, where required.
Sundries to cater for unforeseen contingency and miscellan~us items have been added in theoverhead charges ..
Arrangement tor traffic dUringconstruction shall be as per Clause 112 of MoRT&H Specificationsfor Road and Bridge Works.
The supply of materials will be taken either at the location of mixing plant or at the work site asthe case may be.
ContractorwiJl make his own arrangements tor borrowing earth. However, compensation for earthtaken from private land has been inclUded in the rate analysis for construction of embankmentwith borrowed earth .
The reqWrlll1lt!nt of machinery has been worked out assuming effective working period of 6 hoursper shift of 8 hours.
The costof earthwork in urban roads will be comparatively higher due to following reasons: _>.
a) There is mixed traffic on urban roads IikesJow moving hand and animal driven carts, rickshaws,cycles, twoJIhree wheeler apart from the usual vehicular traffic reSUltinginto traffic jams. Thiscauses loss of working time which may be in the range of 10-15 per cent.
b) There is considerable disruption of traffic adversely affecting the efficiency of the workingparties including machines due to congestion caused by pedestrian traffic, local road sidevenders, parking of vehicles by the road side, encroachments by the shopkeepers and localshops who make use of the berms of the road in front of these shops and unauthorizedconversion of road berms into mini local market. The output of manpower and machines isSUbstantially reduced due to factors mentioned above.
c) Cost of living in urban areas is comparatively more reSUlting into higherwages.
d) .Attimes, work is executed during ni';jhttime due to heavy traffic during day lime: This involvesextra expenditure by way of making arrangement for lighting and special transport for workingparties due to odd hour.
6
.'eeooooooooooo
In the light of above, the authorities engaged in preparing the cost estimates may exercise theirjudgment and cater for the additional cost to the extent of2to 3 per cent. keeping in view theseverity of factors mentioned above. Support details for the "exb
8
444
'<
10.23. Grade of cement may be adopted as per mix design.
10.24. Quantities of cement in various grades of cement concrete have been taken as per IRC:21-2000"and IRC:18-2000.
10.25. The rates for rigid, semi-rigid and flexible crash barriers have been analysed in Chapter-8.
10.26. The coarse and fine aggregates shall conform to IS:383.
10.27. Certain equipments like road rollers, are required to be available at site for complete period of theshift, though from the consideration of their output, they may be required only for 3 to 4 hours.This is necessitated to match with the output of other associated machines like HMP, Paversetc. in such cases, the hire charges of road rollers have been multiplied with a factor of 0.65 toaccount for the idle period.
10.28. For pricing of RCCsiab culverts, the items given in respective chapters in bridge section may bereftered.
10.29. Wherever electric generator has not been provided to run a plant or equipment, it is assumed thatit is fitted with a diesel engine.
10.30. Some of the firms in the field of construction chemicals have evolved new brands of chemiCals for_ water proofing, sealing of cracks, cementing compunds etc. The m..arketcan be explored to meetsuch requirements.
10.31. Some of majorsteel producing firms have evolved thermo-mechanically treated steel whiCh hasenhanced strength, better corrosion resistance. ductility, weld ability and high temperature thermalresistance. Enquiries frOm these firms can be made on techniCal specifications and use of sue'"products considered in works based on performance in works where these have already beenused.
10.32. Provision of fly ash has been made in embankment construction, sub-base construction and incement concrete pavement.
10.33. The Standard Data Book is for Department use only. It cannot be produced in Court of Law asreference/authority and thus is a privilege document.
10.34. In case it is decided to include the following iterna and their maintenance in the BOQ, the scopeand specifications should be worked out and defined in a detailedmannerinthe tender documentto avoid any dispute during execution.
MoRT&H Clause
120122124
Item
Site office and furniture for Engineer and his staff.Site residential accommodation for Engineer and other supervisory staff.Providing and maintaining vehicle for the Engineer ..
e,o:4)ooo
Cbapter-1
Carriage of Materials
Preamble:
1. The provision of tipper has been made in hours where lead is known like disposal of the materials upto1000 m. In case where lead is variable like carriage of hot mix or concrete mix from plants or earthfrom borrow areas, provision has been made in terms of tonne-kilometer (t-kml, which can be adoptedas per actual conditions.
2. Provision has been made for a tractor trolley instead of tipper where dismantled materials of sorts ormaterial having more volume as compared with weight are required 10 be transported. This arrangementwill be economical.
3. The cost of carriage wiUvary depending upon the riding surface of the road. Provision has accordinglybeen made considering surface roads, unsurfaced graveled roads and katcha tracks.
4. Analysis for iOading has been done both for manual and mechanical means for adoption as per actualsituations.
5. Where loading is done by mechanical plant like HMP or batching plant and there is automatic loadingin tippers, provision of loading and un-loading has been made at rate of 10 per cent of cost of carriagEfto account for time taken by the tipper for getting loaded at the plant and un-loading in .the paver orotherwise at site.
6. Although the market rates for supply of aggregates at site are generally taken for estimation purpose,rate for crushing of aggregate'have also been analysed as most of the contractors prefer to crush theirown aggregates in case of large projects exceeding RS.50 crores in value.
7. The cost of ma~\ilrialshall be evaluated considering the cost at crushing plants and cost of carriageincluding loading and unloading or the rates for supply at site depending upon system being followedat particular locations. These rates should be compared with the rates for own crushing and carriageby the construction agency.
9
444
C
tt
)..
Chapter-1
Carriage of Materials
Sr. Reference to Description UnitQuantity Rate
No. MoRT&HRs.
Specifications
1.1. Loadln!! and Unloading of StoneBoulderlStone Aggregates/SandiKankarlMoorum
Placing tipper at loading point, loadingwith front end loader. dumping, turningfor retum trip, excluding time for haulageandretum trip.
Unit= cumTaking output = 5.5 cum
Time required foro Positioning of tipper atloading pointii) Loading by front end loader 1 cum
bucket capacity@ 25 cum per houriii) Maneuvering, reversing, dumping and
turning for returnill) Waiting time, unforeseen
contingencies, etc.
1 Min13Min
2 Min
4 Min
Tolal 20 Min
a) MachineryTipper 5.5 tonnes capacity hourFront end-loader 1 cum bucket capacity hour@25cumlhour
0.330.33
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
10
eee.,e.,oooooooooo0'oo~ob
Road Works: l-Carriage of Materials
Sr.. Reference to DeserlPtJonUnit Quantity Rate
No. MoRT&HAs.
Speeifk:atlons
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/5.5
Note: Unloading will be by tipping.
1.2. Loading and Unloading of Stone Boulders by
Manual Mellns
Unit =cumTaking output =5.5 cum
a) LlIbourMate day 0.11
Mazdoor for loading and unloading day 0.75
b) MachineryTIpper 5.5 tonne capacity hour 0.75. ,
c) Overheads @ .; % on (a+b)
d) Contrllctor's profit @ %on (lI+b+c)
Cost for 5.5 cum = a+b+c+d
Rate pel' cum = (a+b+c+d)/5.5
Note: Unloading will be by tipping.
1.3. Loading and Unloading of Cement orSteel by Manual Means and Stacking
Unit = tonneTaking output = 10 tonnes
a) LabourMate day 0.08
Mazdoor for loading and unloading day . 2.00
11
44
ttttt
)..
>c
---------,
Road Worb : j-Cerriage ofMatcrials
Sr. Reference to Description Unit Quantity Rate
No. MoRT&HRs.
Specifications
b) MachineryTruck 10tonne capacity hour 2.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ %on (a+b+c)
Cost for 10 tonries =a+b+c+d
Rate per tonnes = (a+b+c+d)/10
1.4. Cost of Haulage excluding Loading andUnloading
Haulage of materials by tipperexcluding costof loading.unloadingandstacking.
Unit = lkm
Taking output 10 tonries loadand lead10 km = 100 lkm
Case-I: Surfaced Road
Speed with load 25 kmlhour
Speedwhile returningempty: 35 kmIhour
a) MachineryI) TIpper 10 tonne capacity~
TImetakenfor onwardhaulagewith hour 0.4loadTIme taken for empty return trip hour 0.29
b) Overheads @ % on (a)
c) Contractor's profit @ %on (a+b)
Cost for 100 lkm = a+b+c
Rate per lkrn = (a+b+c)/100
12
ooooooooo
Road Works: I-Carriage of Materials
.
Sr. Reference to Description Unit Quantity Rate
No. MoRT&H Rs.
Specifications
Case-II: Unsurfaced Gravelled Road
Speed with load : 20 kmlhourSpeed for empty retumtrip: 30 kmlhour
a) MachineryI) Tipper 10 tonnes capacity .Time taken for onward haulage with loadTime taken for empty retum trip
hourhour
0.50.33
b) Overheads @ % onla)
c) Contractor's profit @ Ok on Ia+b)
Cosl for 100 lkm = a+b+c
Rate per t.km C"(a+b+c)/100
Case-lll : Katcha Track and Track In RiverBediNallah Bed and Choe Bed
Speed with load : 10 kmlhourSpeed while retuming empty : 15 kmlhour
a) Machinery .I) Tipper 10 tonnes capacityTime taken for onward haulage.Time taken for empty retum trip
hourhour
10.67
b) Overheads @ % on la)
c) Contractor's profit @ % on la+b)
Cosl for 100 tkrn = a+b+c
Rate per t.km = la+b+c)/100
13
. RoadWorks: l-CaniageofMaterials
Sr. Reference to Description Unit QuantityRate
No. MoRT&HRs.
Specifications
1.5. Hand Broken Stone Aggregates 63 mmNominal Size
Supply of quarried stone, hand breaking intocoarse aggregate 63 mm nominal size .(passing 80 mm and retained on 50 mmsieve) and stacking as directed;
Unit = cumTaking output = 1 cum
a) LabOurMateMazdoor
dayday
0.061.5
b) MaterialSupply of quarried stone 150-200 mm size cum
. c) Overheads @ ';;on (a+b)
d) Contractor's profit @ % on (a+b+c)
1.10
Rate per cum = a+b+c+d1.6. Crushing of Stone Aggregates 13.2mm
Nominal Size
Crushing of stone boulders of 150 mm size inan integrated stone crushing unit of200 tonnesper hour capacity comprising of primary andsecondary crushing units, belt conveyor andvibrating screens to obtain stone aggregates of13.2 mm nominal size.
Unit: cumTaking Output = 600 cum at crusher location
a) LabourMate dayMazdoor Skilled dayMazdoor including breaking of any over- daysize boulder
0.76217
14
..
,tt
).
,.e!
oooooooo
~1t
Road Works: l-CarriageofMateriais
Sr. Reference to.Description Unit .Quantlty Rate
No. MoRT&HRs.
Spec.ifications
b) MaterialStone Boulder of size 150 mm and below cum 800
c) MachineryIntegrated stone crusher of 200 TPHincluding beltconveyor and vibrating
screensFront end loader 1 cum bucket capacityTipper 5.5 cum capacity
d) Overhead charges@ .~ on (a+b+c)
e) Contractor's proflt@ % on (a+b+c+d)
Hour 6
HourHour
2020
CasHor 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/600
Note: 1. 800 cum of stone boulders are needed toget 600 cum of stone i:hips of size 13.2
mm.2. 95 per cent of above cost will be attributed
to the production of 600 cum of stone chipsof 13.2 mmsize and balance 5 Jl!!r cent tothe production of stone dust which comesout as a by-product.
3. The integrated stone crusher includesprimary and secondary crushing units.
1.7. Crushing of Stone Aggregates 20 mmNominal Size
Crushing of stone boulders of 150 mm size inan integrated stone crushing unit of 200 tonnasper hour capacity comprising of primary andsecondary crushing units, belt conveyor andvibrating screens to obtain stone aggregatesof 20 mm nominal size.
Unit: cumTaking Output = 670 cum at crusher location
15
Road Works: I-Carriage of Material.
Sr. Reference to Description Unit Quantity RateNo. MoRT&H Rs.
Specifications
Nota:
a) LabourM~ d~MazdoorSkilled dayMazdoor including breakingot any size dayboulder
b) MaterialStone Boulderot size 150mm and below cum
c) MachineryIntegratedstonecrusherot200 TPH Hourincludingbeltconveyor andvibratingscreensFront end loader 1 cum bucket capacity HourTIpper 5.5 cum capacity Hour
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit@ %on (a+b+c+d)
Cost tor 670 cum = a+b+c+d+eRate per cum = (a+b+c+d+e)l670
1. 800 cum ot stone boulders are needed toget 600 cum ot stone chips ot size 20 and40mm.
2. 90 percent ot abovecostwill beattributedto the production of 670 cum ot stoneaggregatesot 20mmsizeand balance10percentwill be tor smallersizeaggregatesand stone dust which comes out as a by-product
3. The integrated stone crusher includesprimaryand secondary crushing units.
Crushing of Stone Aggregates 40 mmNominal' Size
Crushingot stonebouldersot 150mmsizein an integratedstone crushing unitot 200tonnes per hour capacity comprising otprimaryandsecondarycrushingunits,bEillconveyor and Vibratingscreens to obtainstone aggregatesof 40 mm nominalsize.
2020
0.76217
800
6
1.8.
16
"
tt
4141
~.;,
~
,o.ooooooo.oooooL
f
Road Works: l-CarriageofMaterials
Sr. Reference toDescription Unit
Quantity Rate
No. MoRT&HRs.
Specifications
Unit: cumTaking Output = 750 cum at crusherlocation.
a) LabourMateMazdoor SkilledMazdoor
daydayday
0.76217
b) MaterialStone Boulder of size 150 mm andbekiW cum 800
c) MachineryIntegrated stone crusher of 200TPH Hourincludiing belt conveyor and vibrating
screensfront end loader 1 cum bucketcapacily HourTipper 5.5 cum capacity Hour
6
2020
d) Overhead charges @ % on (a+b+c) .
e) eontractor'S proflt@ % on (a+b+c+d)
Cost for 750 cum = (a+b+c+d+e}xO.85
Rate per cum = (a+b+c+d+e)"O.85nSO
Note: 1. 800 cum of stone boulders are needed toget 600 cum of stone chips of size 13.2
mm.2. 85 per cent of above cost will be attributed
to the production of 750 cum of stoneaggregates of 40 mm size and balance 15per cent will be for smaller size aggregatesand slone dust which comes out as a by-
product
3. The integrated stone crusher includesprimary and secondary crushing units.
17
Chapter-2
Site Clearance
Preamble:
1. Unless otherwise stated, the rates indude sorting and disposal of unserviceable material and stackingof serviceable material with aillifls and upto a lead of 1000 m.
2. The rates indude T&P and scaffolding required for items ofdismanUing ~
3. Carriage of dismanUed materials, bushes, branches of tree, etc., has been catered with a tractor-trolley of 3 tonne.s capacity with manual loading and unloading @ 2lrips per hour within a lead of1000 m. This will be economical for such works as compared with a tipper.
4. For cutting oftJ:eesabove 1800 mm girth, 4 mazdoors have been considered to cater for large sizetrees, which win fall in this categOlY;
5. Where only grasslwild growth is met, item No.2 l.e, dearing grass and removal of rubbish can be'applied. As regards wild growth disposa.1of grass, the same can be dried and burnt
6. The dismanUing of struetureshas been catered both by manual and mechanical means. The estimatorcan use his discretion depending upon quantum of work and 'particular site conditions.
7. Cutting of rivets has been provided separately.
8. Dismantling of Humepipes has been catered manually as pipes can be easily rolled by men to asuitable stacking place Within the right of way,
9. For dismanUingof structures, which remain submerged in water, the cost may be enhanced by 50percent
10. DismanUing of utilities is required to be done under the supervision ofconcemed departments withprior information to the users. .
11. In certain itemsofdismanUing, like, pipe culverts, utilities, etc., excavation in earth and dismantlingof masonry works is notinctuded in this analysis for which suitable notes have been inserted. Theseitems are required to be priced separately based on actual quantities at site and nature of work.
12. The dismanUed materials should be examined and a realistic assessment and provision made afterdue process for the credit for such materials, which can be utilized fotworks or auctioned.
13. In case where lead for disposal is more than 1000 rn, extra cost of carriage is required to be addedbased Oil tonne-kilometerage.
14. All minor T&P items required for dismantling are already induded in overhead charges.
15. For dismanUing of utility services like water pipe lines, electric and telephone lines, prior intimationshould be given to users.
18
41
41
41
41
41
41
f.ttt
,..
.>.
~
~
.~
~
~IIoC)qdd
{'
o~
~.
Pfob
Chapter~2
Site Clearance
Sr. Reference to DescriptionUnit Quantity Rate
No. MoRT&HRs.
Specifications
/,
2.1. 201 Cutting of Trees, Includinll cutting o.fTrunks, Branches and Removal
. ~ / Cutting of trees, including cutting of trunks,branches and removal of stumps, roots,stacking of serviceablematerial with all liltsand upto a leadof 1000mand earth filling inthe depression/pit
Unit = Each(i) Girth from 300mm to 600mm
a) LabourMate dayMazdoors for cuttingtrees including daycutting, refilling,.compactionof backfillingandstackingof serviceablematerialswithin 1000m leadby manualmeans.
0.020.60
b) MachineryTractor-trolley hour 0.10
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate for each tree = a+b+c+d
(ii) Girth from 600mm to 900 mm
a) LabourM~ dayMazdoorsfor cuttingtrees including daycutting, refilling,compactionof backfilling,andstackingof serviceablematerialswithin 1000 m leadby manual means
0.040.90
19
Road Worlcs: 2Site Cleanmce
Sr. Reference to Descr1ptfon Unit Quantity Rate:No. MoRT&H Rs.
Specifications
b) MachineryTractor-trolley hour 0.30
c) Overheads @ % on (a+b)
d) Contractors profit @ % on (a+b+c)
Rate for each tree = a+b+c+d(iii) Girth from 900 mm to 1800 mm
a) LabourMate day 0.08 \
Mazdoors for culling treesIncluding day 2.00culling, refilling,compactionof backfillingandstacking of serviceablematerialswithin 1000m
b) MachineryTractor-trolley hour 0.40
c) Overheads @ "10 on (a+b)
d) Contractor's profit @ "10 on (a+b+c)
Rate for each tree = a+b+c+d(iv)Glrth above 1800mm
a) LabourMate day 0.16Mazdoorsfor culling trees including day 4,00culling refilling,compactionof backfillingand stackingof serviceablematerialswithin 1000m
b) MachineryTractor-trolley hour 0.60
1c) Overheads @ "10 on (a+b)
d) Contractor's profit @ "10 on (a+b+c)
Rate for each tree = a+b+c+d:! I.,i.~ '?-,I
L 20
~
~
~
)~ .
,.,.',oC')C')oo
Road Works: 2-Sile Clearance
Sr. Reference to Description Unit Quantity Rate
No. MoRT&H Rs.
Specifications
2.2. 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish uptoa distance of 50 metres outside the peripheryof the area .
By Manual MeansUnit = Hectare .Taking output = 1 Hectarea) Labour
Mare dayMazdoor day
2.0050.00
b) Over~ads @ % on (a)
c) Contractor's profit @. % on (a+b)
Rate per Hectare = a+b+c~-_..2.3. 201 Clearing and Grubbing Road Land
Clearing and grubbing road land includinguprooting rank vegetation, grass, bushes,shrubs, saplings and trees girth upto 300 mm,removal of stumps of trees cut earlier anddisposal of unserviceable materials andstacking of serviceable. material to be used orauctioned. upto a lead of 1000 m including'removal and disposal of top organic soil notexceeding 150 mm in thickness.
Unit = HectareTaking output = 1 Hectare
21
RoadWorks: 2Sitc Ctcaranceff
4141
..
sr Reference to Description Unit Quantity RateNo;, MoRT&H RS.
Specifications ,.- ..... . --
I. By Manual Means f
A. In area of light jungle
a) LabourMale day 6.00Mazdoor day 150.00
b) MachineryTractor-trolley hour 1.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ %on (a+b+c)
Rate per Hectate = a+b+c+dB. In area of thorny jungle
a) LabourMale day 8.00Mazdoor day 200.00
b) MachineryTractortroIley hour 2.00
c) Overheads @ %on (a+b)
d) Contractor's profit @ %on (a+b+c)
Rate per Hectare = a+b+c+dII. By Mechanical Means :
A. in area of light jungle
a) LabourMate day 0.16Mazdoor day 4.00
22II-
,te:~
~.'ci~,
o!0;
0\0;,0'0',
o(,
01.,
Road WorIcs: 2-Site Clearance
Sr. Reference to Descrlptl4n Unit Quantity RateNo. MoRT&H Rs.
Specifications.
b) MachineryDozer80HPwith attachmentfor removal hour 10,00of trees & stumpsTractor-trolley hour 1.00
c) Overheads @ ~. on (a+b)
d) Contractor's profit @ % on (a+b+l:)
Rate per Hectare = a+b+c+d
B. In area of thorny Jungle
a) LabourMate dayMazdoor day
b) MachineryDozer80HPwith attachment for removal hourof trees & stumpsTractor-trolley hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
12.00
1.50
Rate per Hectare = a+b+c+d
2.4. Dismantling of Structures202Dismantlingofexistingstructures likeculverts,bridges, retaining walls and other structurecomprising of masonry, cement concrete,wood work, steel work, including T&P andscaffoldingwherever neCessary,sorting thedismantledmaterial,disposalof unserviceablematerialandstackingtheserviceablematerialwith alilifls and lead of 1000 metres.
Unit = cumTakingoutput= 1.25cum
23
Road Wodcs : 2-8i C1eIIrance
"II
Reference to Description Unit Qllantlty
Sr. Rate.No. MoRT&H ~
Specifications 2.4. (i) 202 (i) Lime/Cement Concrete
i. By Manual Means:
A. Lime concrete, cement concrete gradeM10 and beiow
a) LabourMateMazdoorfor dismaritJingand loading
dayday
0.041.00
b) MachineryTractor-trolley
chour 0.27
c) Overheads @ % on (a+b)
d) Conqactor'sprofit @ ~. on (a+b+c)
Cost for 1.25cum =a+b+c+d
Rate per cum = (a+b+c+d)/1.25
B. Cement concrete grade M15 & M20
a) LabourMateMazdoorfor dismantlingand loading
dayday
0.051.25
b) MachineryTractor-trolley hour 0.27
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
24
Ifot\~r
1Q, ':'-1lase/IIasos
Sr. Reference to Description Unit Quantity RateNo. MoRT&H Rs.
Specifications
Ellndlng materialElinding Material @0.08cumper 10 sqm for cumgrading I material
OR
28.80
Binding Material @O.06cumper 10 sqm for cumgrading II material(Any one ot the aggregate grading, screeningand binding material may be used as per .design)
CO,stotwater ' Kl
28.80
,144.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 36(f cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)l360EI. By Mechanical Means
Unit = cumTaking output = 360 cuma) Labour
MateMazdoor skilledMazdoor
daydayday
0.682.0015.00
b) MachineryMolor grader 110 HP @ 50 cumlhr. for hour 7.20spreadingVibratory roller 8-10 lonne @60 cumlhr. hour 6.00
OR,
Smooth 3-wheeled steel roller hour [email protected] lanker 6 KL capacity hour 24.00
106
1
4
i4,ttt
tt
t
':.
ooo s,o
('
('
('
RoadWodcs:4-Sub-_
Reference to Description Unlt Quantity Rate
MoRT&H Rs.Specifi.catlons
c) MaterialSame as in case of manual means
d) Overheads @ ,% on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 360. cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)l360
Note: As three wheeled smooth rollers are also verycommonly Used, the same has been providedas an alternative.
405 Crushed cement Concrete Sub-BaseIBase
Breaking and crushing of material obtainedby breaking damaged cement concrete slabsto size range not exceeding 75 mm asspecified in Table 400.7 transporting theaggregates obtained from breaking of cementconcrete slabs at a lead of L km, laying andcompacting the same as sub.baseJbasecourse, constructed as WBM to Clause 404except the use of screening or bindingmaterial.
Unit = cumTaking output =360 cum
a) LabourMate day 4.16Mazdoor skilled day 2.00Mazdoor for crushing broken cement day 102.00concrete pavement/slabs into aggregate
107
RDocIW~: 4-Sub-Bose/BIseS
Sr. Reference toDescription Unit Quantity
Rate
No. MoRT&HRs~
Specifications
b) MachineryMotor grader 110 HP @50cumlhr. hoUr 6.00
Vibratory roller 8-10 tonne @ 60 cum hoUr 6.00
per hour
OR
Smooth 3-wheeled steel roller@30 hoUr 12.00
cumlhr.Front end loader 1 cum bucket capacity hoUr 6.00
TIpper 10 tonne capacity t.km 720xl
Add 10 per cent of cost of carriage tocover cost of loading and unloading
Water tanker 6 Kl capacity with 5 km hoUr 12.00
lead hour @ 1lrip per hour
c) M~terlalMaterial available from dismanUed concreteslab alter crushinglbreaking and onlycarriage is required to be provided
Cost of water Kl72.00
d) Overheads @ % on (a+b+c)
e) ContractOr's profit @ % on (a+b+c+d)
Cost for 360 cum = a+b+c+d+eRate per cum = (a+b+c+d+e)/360
Note: 1. It is assumed that dismantling of concreteslab/pavement has been consideredseparately. Hence same is not added Inthis analysis. Only labour for crushing thedismanUed slab lnto aggregate has beenadded. Carriage from stock pile to worksite has been provided with a lead of l
krn.
108
Sr. Reference to Description unn- Quantity RateNo. MoRT&H Rs.
Specifications
c) MaterialCrushed stone aggregate 11.2 mm size cum 97.50Bitumen tonne 0.25
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 7500 sqm = a+b+c+d+eRate per sqm = (a+b+c+d+e)/7500
Note: Though vibratory roller is required only for 3hours as per norms, the same is required tobe available at site for 6 hours to match withother machines. The usage rates of vibratoryroller have been multiplied with a factor of0.65.
4.12. 406 Wet Mix Macadam
Providing, laying, spreading and compactinggraded stone aggregate to wet mix macadamspecification including premixing the materialwith water at OMC in mechanical mix plantcarriage of mixed material by tipper to site,laying in uniform layers with paver in sub-baselbase course on well prepared surfaceand compacting with vibratory roller to achievethe desired density.
Unit = cumT!lking output = 225 cum (195 tonne)a) Labour
Male day 0.48
Mazdoor skilled day 2.00Mazdoor day -10.00
110
e~
eeeoee('J
e0'eooooooooo ',!.v-o
o('
o
Road WOIb: 4-Su.b-BasoJBases
Sr. Ref.rence to Description Unit Quantity , RateNo. MoRT&H Rs.
Specifications
b) MachInery,Wet mix plant of 75 tonne hourly capacity hour 6.60Electric generating set, 125IWA hour 6.00Front end lOader 1 cum capacity hour 6.00Paver finisher hour 6.00VibratOlYroIler 8-10 tonne hour 6.00 x 0.65"
OR
Smooth 3-wheeJed steel roller@8-10 hour 12.00tonneWater tanker hour 3.00Tipper t.km 495xl
Add 10 per cent of cost of carriage to covercostof loading and unloading
c) Matvlal (Table 400-11)45 mm to 22.4 mm @30percent cum 89.1022.4 mm to 2.36 mm @40percent cum 118.802.36 mm to 75 micron @30 per cent cum 89.10Cost of water KL 18.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ ~. on (a+b+c+d)
Cost for 225 cum = a+b+c+d+eRate per cum" (a+b+c+d+e)l225
Note: "1. Though vibratory roller is required only for3 hours as per norms, the same is requiredto be,available at site for 6 hours to matchwith other machines. The usage rates ofvibratory roller have been multiplied with afactor of 0.65.
11l
Road Wades: 4-Sub-BaseJBases
0.246.00
Sr; Reference to DescriptionUnit Quantity Rate
No. MoRT&HRs.
SPElcificatlons . .
4.13 .. 407
\
2. As 3-wheeled smooth steel rollers arecommonly in use, the same has beenprovided as an altemative which can beused if the thickness of individual layerdoes not exceed 100 mm. .
Construction of Median and Island. withSoil taken from Roadway cutting
Construction of Median and Island above roadlevel with approved material deposited at sitefrom roadway cutting and excavation for drainand foundation of other structures, spread,graded and compacted as per Clause 407.
Unit = cumTaking output =21 cum
a) LabourMateMazdoor
b) MachineryWater tanker 6 KL with 5 km lead and1 trip per hourPlate compactor@ 3.5 cum per hour
c) MaterialCost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ 0;' on (a+b+c+d)
Cost for 21 cum = a+b+c+d+eRate per cum = (a+b+c+d+e)l21
112
dayday
hour
hour
. KL
1.00
6.00
6.00
oooooooooooo "oo('
('
o
Reference toMoRT&H
Specifications
Note:
4.14. 407
b) MachineryWater tanker with 5km leadPlate Compactor@ 3.5 cum per hourHydraulic Excavator 1.0 cum bucketcapacity @ 60 cum per hourTipper 10 tonne capacity
Add 10 per cent of cost of transportationto cover cost of loading and unloading
c) MaterialCost of water
d) Overheads @ % on (a+b+c)
113
hour 1.00hour 6.00hour O.$()
t.km 52.5 x L
KL 6.00
Sr.No.
Reference toMQRT&H
Specifications
Note:
4.15.
4.16. 409
- -- -------,---
DescriptionUnit Quantity Rate
Rs.
e) Contractor's profit @ % on (a+b+c+d)
Cost for 21 cum = a+b+t+d+e
Rate per cum = (a+b+c+d+e)/21
This analysis provides formedian and island .with earthen top. In case the surface isrequired to be turfed or planted with shrubs,the same is required to be provided Sep;ll"8telyas per analysis given in the Chapter onhorticulture. In case surface finish is of hardtype. the same may be provided separately
as per approved design.
Construction of Shoulders
A. Earthen ShoulB. Hard ShouldersRate as applicable for sub-base and orbase may be adopted as per approved
design.
C. Paved ShouldersThe rate may be adopted as applicable fordif(erentlayersol pavementdepellding uponapproved design of paved shoulders.
Footpaths and Separators
Construction of footpath/separator 'a/ providInga 150 mm compacted granular sub-base as .per Clause 401 and 25 mm thick cementconcrete grade M15, overlaid with precastconcrete tiles in cement mortar 1:3 includingprovision of all drainage arrangements but
excluding kerb channel.
Unit = sqmTaking output = 300 sqm
1\4
Road WClIb: 4-Sub-Base/Bases
Sr.No.
Reference toMoRT&H
Speclfi~atlons
Description Unit Quantity RateRs.
day 1.36day 4.00day 30.00
hour 0.75
hour 2.00
hour 6.00
cumcumcum
20.7926.7311.88
a) LabourMateMasonMazdoor
b) MachineryVibratory road roller 8-10 [email protected] hourWarer tanker 6 KL capacity @ 1 tripperhourConcrete mixer 0.410.28 cum perhour
c) MaterialI) For granular sub-base material
53 mm to 26.5 mm@35 per cent26.5 mm to 4.75 mm@45 per cent2.36 mm below@20 per cent
.Ii) For cement concrete grade MiS, 7.5 cum
Aggregate 12mm [email protected] cum 6.75concreteSand@ 0.45 cum/cum of concrele cum 3.38Cement Ionne 1.88
ill) For cement plaster 1:3SandCement
cumIonne
3.841.83
Iv) Precast cement concrete tilesTiles size 300 x 300 mm and 25 mm thick Nos 3300.00
v) RCCpipesPipes200 mm dia, 2.5 m long for drainage mtr 22.50
KL 12.00vi) Cost of waterd) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 300 sqm a+b+c+d+e
Rate per sqm (a+b+c+d+e)/300
us
ooo
Sr. Reference to Description . Unit Quantity . RateNo. MoRT&H Rs.
Specifications
4.17. 410 Crusher Run Macadam Base
Providing aushed stone aggregate; depositingon a prepared surface by hauling vehicles,spreading and mixing with a motor grader,watering and compacting with a vibratory roDarto Clause 410 to form a layer of sub-baselbase. .
Unit = cumTa~ngoutput=360cum
A. By Mix In Place Method
a) LabourMateMazdoor s~lIedMazdoor
dayday day
0.482.0010.00
b) MachineryTractor attached with rotavator@25cum hour 12.00per hourMotor grader 110 HP hour 6.00Vibratory roller8-10 tonne @ 60 cum per hour 6.00hourWater tanker hour 6.00.
!.\ c) Material~ Aggregate at site
I) For 53 mm maximum size63 mm to 45 mm @ 33 per cent cum 157.4622.5 mm to 5.6 mm @ 32 per cent cum 151.06Below 5.6 mm @ 35 per cent cum 166.68Cost of water Kl 36.00
OR
116
.' ..'::........... ".......'.' ..!;:-\;'i;~~~io:ti~~~~~.;.
Road Works: 4-Sub-BaseIBases
Sr. Reference to Description Unit . Quan~ty . Rate. INo. MoRT&H
Rs..Specifications
i) For 53 mm maximum size63mm to 45 mm @ 33 per cent cum22.5 mm to 5.6 mm @32 per cent cumBelow5.6 mm@ 35 per cent Cum
98.4094.41104.18
\:i
~
4'!. ,
c) MaterialAggregateat site
OR
il) For 45 mm maximum size45 mm 10 22.5 rrim @ 5 percent cum22.4 mm to 5.6 mm @ 50 per cent cumBelow5.6 mm @45 per cent cumCostotwater Kl
15.06148.50133.4318.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 225 cum = a+b+c+d+eRate per cum = (a+b+c+d+e)/225
4.18. Suggestive Lime.Flyash Stabilised Soli Sub-Base
,
\Constructionot sub-base using lime -llyashadmixlurewilhgranularsoil, free fromorganicmatter/deleteriousmaterialor clayeysiltsandlow plasliclty clays haVingPI between5 and20andliqUidlimitlessthan 25 andcommercicildry lime,slakedat siteor pre-slakedwithGaOconlent not less than 50 per cent, lIyash toconform to gradation as per Clause 4.3 otIRC: 88-1984, lime + lIyash content rangingbetween10 to 30 per cent, the minimumun-confinedcompressjvestrengthandCBRvalueafter28dayscuringand4 days soakingto be7.5 kg!sqcmand25 per cent respectively,allas specifiedin IRe: 88-1984.
118
e.-.'010:
?,
oooooooooooooo
RDadWorks: 4-Sul>-1laseIBases
Reference to DescriptIon UnIt Quantity. RateMoRT&H
Rs.Specifications
Unil= cum
Takingoutpui =480 cum (720 tonnes, density1.50tlcum)
Assumptions m;ldeTolal mass laken for analysis = 7201Lime + Flyash admixture@20percenl = 0.2 x 720 = 1441Soil = 720.;144 ,. 576 I
576 /1.6=360cumLime + Ftyash = 1441Ratio Lime 4 : Flyash 16Lime =29 kg.Ftyash = 115 kg.
at LabourMate day 0.24Mazdoor day 6.00Mazdoor (Skilled) day 1.00
b) MachineryHydraUlic excavator 0,90 cum buckel hour 6.00capacily@60cumlhr. for 360 cum soiiTIpper 10T capacity for carriage olsoil l.km 578xL578tonne5TIpper 10T capacity for carriage of t.krn 115x L115 tonnes flyashTIpper 10T capacity for carriage of hour 3.0029 tonnesof lime from store 10work sile
Add 10 per cent.of cost of carriage 10cover cost of loading and unloading
Traclorwilh disc harrows for pulverlsalion hour 6.00Motor grader 110 HP@50cum per hour hour 9.60for mixing in-place and gradingVibratory roller 8-10 tonne hour 6.00water lanker hour 12.00
119
Sr.No.
-
Reference toMoRT&H
Specifications
Road WOIb: 4-&Jl>.1IasoIBases
Description
c) Material. Slaked LimeCompensation foi earth taken from privatesource
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 480 cum = a+b+c+d+e
Rate percurn = (a+b+c+d+eV480
Note: 1. Cof11lensation for earth winvalY from placetQ place and will have to be assessedrealistically as per particular ground--situation. In case earth is available fromGovt Iand,compensation for earth will notbe required. The position is required to beclearly stated in the cost estimate.
2. Cost of flyash has not been considered assame will be available free of cost Onlycarriage of flyash has been provided.
3. Lime + Flyash has been taken as 20 percent of total mass and ratio of lime andflyash as 1:4 for estimating purposes. Totalquantities will be as per approved design.
120
Unit Quantity
tonnecum
29.00360.00
I
Rate..~
. Rs. ,
\ 4,, 4.\.'4
>4
4
4,44
,e0e~
00000000
:oj,.
l>0
{I
f"('
Chapter-'S
Bases and Surface Course (Bituminous)
Preamble:
1. Various alternatives for machines and materials have been provided. The one that suits a particularsituation and design may be adopted.
2. The Clauses of MoRT&H Specifieatlons, which have been mentioned tor each item, may be referred tordetailed specifications and construclion procedure. The rate analyses mention. only brief description.
3. The machinery and equipment included in various analysis are as per various specifieatlons of MoRT&Hand are mandatory. As perthe present trend,contraetors areprocuring machinery and equipment ofhigher capacily. Provision has accordingly been made.
4. The outputs taken for the construclion equipment are tor the compacted quantities of the relevantitems and not for loose quantities.
5. In case of prime coat and tack coat, minimum quantities of binder indicated in specifications havebeen taken. Adjustment, plus or minus, can be made tor the variation between this quanlily and theactual quanlily approved by the EngineeraflertheprelirTiinarytrials.
6. The items of bituminous works required under maintenance have been added in the Chapter onMaintenance.
7. Tack coat and prime coat, wherever provided, are required to be measured and paid separately.
8. Cleaning of surface is a part of the prime coat and tack coat. As such cleaning of surface has not beenprovided tor bituminous courses as the same is already catered inprimeJtack coat. However, tor thosecases where such coats are not required to be done, cleaning of surface shall be included.
9. It is presumed that tack coat, where required, will be provided immediately preceding the bituminouslayer.
10. Rolling of bituminous courses is required to be done as per Clause 501.6. Provision in the analyseshas accordingly been made. It has been observed during actual praclice at work sites, that theavailabilily of road roller is generally inadequate. As compaclion is the key to good construction, thispoint is being specifically highlighted to ensure that road rollers are deployed at site as per provision inthe rate analyses.
11. Spreading of bituminous materials shall be done by mechanical means except in areas where amechanical paver cannot have access.
12. The source of all materials to be used on the project must be tested and expressly approved by theEngineer.
121
Road Works: 5-Bases and Surface Course (Bituminous)
444
13. Quantities of materials taken in the analyses are for the purpose of cost estimate only. The'.a4quantity shall be as per job mix formula. . . "'.
14. Choice of grade of bitumen shall be made as per the gUidelines given in Appendix-4 of MoRT&r.Specifications.
415. The specification and requirements for modified binder with various type of modifiers have been laic 4down in Clause 521 of MoRT&H Specifications and IRC: SP:53-2002 which shall be followed.
. 416. The guidelines given vide Annexure - A to Clause 501 of MoRT&H Specifications in regan! to protection .
of environment shall be followed for a particular situation..
17. The quantities taken as output of the it\lm in the rate analysis are the compacted quantities and the quantities of aggregates taken under the head 'material'are the un-eompacted quantities for the procurement purposes.
18. The approximate proportions byweigtlt of different aggregates and bitumen CorbyVolume in unavoidable cases) necessary to produce the intended mix satisfying the job requirements and meeting thedesignated Specifications are for estimating purpose only .. The actual quantities should be worked out.on the basis of job mix formula adopted for the job. after working out the same in the laboratory forparticular aggregates and bitumen approved by the Engineer.
122
"- .--I
"
h
ooo
Sr.No.
5.1.
Chapter- 5
Bases and Surface Course (Bituminous)
Reference toMoRT&H
Specifications
502
Description
Prime coat
Providing and applying primer' coat withbitumen emulsion on prepared sUrfa,ce ofgranular base including clearing of road surfaceand spraying primeratlhe' rate of 0.60 kg!sqm using mechanical means.
Unit"'sqmTaking output'" 3500 sqm
a) LabourMaleMazdoor
b) MachineryMechanical broom @ 1250 sqrn per hourAir compressor 250 cfmBitumen pressure distributor @ 1750 sqmperhourwater lanker 6 KL capacity @ 1 tripper hour
c) MaterialBitumen emulsion @ 0.6 kg per sqmCost of water
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 3500 sqm '" a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
123
Unit
dayday
Quantity RateRs.
-0.08
2.00
hour 2.80hour 2.80hour 2.00
hour 1.00
.'j
tonne 2.10 ,.KJ.. 6.00
\,
I,j1
,
Sr.No.
5.2.
Reference toMoRT&H
Specifications
Note:
503
1Ir'_-----
Rood Wodcs: S-Bases and Surface cowse (Bituminous)
Description Unit
Bitumen primer has been proVided @0.60kgper sqm as per Clause 502.8. Payment shallbe made with adjustmen~' plus or minus, forthe variation between this quantity and theactual quantity approved by the Engineer alterthe preliminary trials refe~ to in Clause No.502.4.3.
Tack Coat
Providing and applying lack coat Withbitumenemulsion using emulsion pressure distributorat the rate of 0.20 kg per sqm on the preparedbituminous/granular surface cleaned withmechanica, broom.
Unit = sqmTaking output = 3500 sqm
a) Labour
Mate dayMazdoor day
b) MaChinery
Mechanical broom @ 1250 sqm per hour hourAir compressor 250 cfm hourEmulsion pressure distributor hour@1750sqmperhour
c) Material
Bitumen emulsion @ 0.2 kg per sql"(! tonne
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm (a+b+c+d+e)/3500
124
Quantity
0.082.00
2.802.802.00
0.70
t
t
~
,441
f4441
41
,..
Ra. Rs.
{'
('
('
Rood W(lIks: 5-Bases and Surface Course (Bituminous)
-Refercence to Description Unit Quantity Rate
MoRT&H Rs.
Specifications
Note: 1. Bitumen emulsion has been provided@ 0.20 kg per sqm as per Clause 503.8.Payment shall be made with adjustment,pius or minus, for the variation betweenthis quantity and actual quantity approvedby the Engineer after preliminary trialsreferred to in Clause 503.4.3.
2. An output of 3500 sqm has beenconsidered in case of prime coat and tackcoat which can be covered by bituminous -courses on the same day.
504 -SltuminousMacadam
Providing and l
Road Worb: 5-1lases and Surface Course (Bituminous) .~
ISr.No.
Reference toMoRT&H
Specifications
DescriptionUnit Quantity .
b) Machinery iBatch mix HMP 100-120 TPH @75tonne hour 6.00 ;..per hour actual output
AMechanicalbroom hydraulic@ 1250 sqm hour 2..20per hour 4Air compressor 250 cfm hour 2.20 Paver finisher hydrostalic with sensor hour 6.00 control @ 75 cum per hourGenerator25O KVA hour 6.00 '.Front end loader 1 Cum bucket capacity hour 6.00 ':,4Tipper.10 tonne capacity t.km 450 x lAdd 10 per cent of cost of carriage to :~cover cost of loading and unloading '-41Smooth wheeled roller 8-1 0 tonnes for hour 6.00 x 0.65 41inilialbreak down rolling
tVibratory roller 8 tonnes for intermediate hour 6.00' x 0.6$trolling
Fipish rolling with 6-8 tonnes smooth hour 6.00 x 0.65 411wheeled tandem roller
~t, "c) Material . I) Bitumen @ 3.3 per cent of mix tonne 14.85Weight of mix = 205 x 2.2 = 450 tonne ,.. ii) Aggregate, \. Total weight of mix = 450 tonnes, Weight of bitumen = 14.85 tonnes Weight of aggregate =450 -14.85 =435.15 tonne.sTaking density of aggregate = 1.5 ton/cum Volume of aggregate =290.1 cum "Grading I (40 mm nominal size) 37.5-25mm 15 percent cum 43.5125-10 mm 45 percent cum 130.55 10-5 mm 25 percent cum 72.53 '.5 mm and below 15 per cent : cum 43.51 OR 126 *,..7
ooooo
sr.No.
Reference toMoRT&H
Specifications
"Note:
Road Works: S-B and Surface COUJSO (Biblminous)
Description
(19 mm nominal size)40percent40 percent20 percent
Grading II25-10mm105mm5 mm and below
'Any one of the altemative may be adoptedas per approved design
d) Overhead charges@ % on (a+b+c)
e) Contractor's profit@ % on (a+b+c+d)
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+ll')/20S
'1. Although the roller are required only .for 3.hours as per norms of output, but the samehave to be available at site for six hours asthe hot mix plant and paver will take sixhours for mixing and paving the output cif450 tonnes considered in this analysis.Tocaterforthe idle period of this rollers,their usage rates have been multiplied bya factor of 0.65.
2. Quantity of bitumen has been taken foranalysis purpose. The actual quantity wmdepend upon job mix formula.
3. Labour for traffic control, watch and wardand other miscellaneous duties at siteincluding sundries have been included inadministrative overheads of the Contractor.
4. In case 8M Is laid over freshly laid tackcoat, provision of mechanical broom and2 mazdoors for the same shall be deietedas the same has been included in the costof tack coal
127
Unit Quantliy
cumcumcum
RateRs.
116.04116.0458.02
~ WOlks:.s.:Bases and SurliIceCoune (BilumiDous)
0.326.00
44
ttt
'.i1
Sr. Reference to Description Unit Quantity . RatfNo. MoRT&HRs.Specifications
-.5.4\
*'
505 Bituminous Penetration Macadam
Construction of penetration macadam overprepared base by providing a layer ofcompactedcrushed coarse aggregateusingchips spreaderwith alternate applicationsofbituminous binder andkey aggregates androllingwitha smoothwheeled steelroller8-10tonnecapacity to achieve the desireddegreeof compaction.
A. 50 mm thick
Unit = sqmTaking output =4500 sqm (225cum)
a) LabourMate dayMazdoor includingfor brooiningof key dayaggregatesMazdoor skUled day
b) MachineryHydraulicself propelled chipspreader hourbothfor aggregatesand keyaggregates@ 1500 sqm per hour for 4500 x2 sqm = 9000 sqmBitumenpressuredistributorfor hour@ 1750sqmper hourTIpper5.5 cumcapacity for carriageof houraggregatesfrom stockpile tochip spreaderVibratory roller 8 tonnes hourFront end loader 1 cum bucket capacity hour
c) MaterialBitumen @ 5 kg per sqm tonneCrushedstonecoarse aggregatepassing cum45 mmand retained on 2.8 mmsieve@ 0.06cum per sqmKeyaggregatespassing22.4 mmand cumretainedon 2.8 [email protected]
128
2.00
6.00
2.57
10.00
6.006.00
22.50270.00
67.50
Road Works: S-Bases and Surface Course (Bituminous)
..sr, Rererence to DesCription Unit Quantity RateNo. MoRT&H
Rs.
Specifications
d) Overhead charges @ %on (a+b+c)
e) Contractor's profit@ % on (a+b+c+d)
Cost for 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)l45!l!l
Note: 2 tipperswill be neededto match the capacityof chip spreaderand front.end loader.
B. 75 mm thick
Unit=sqmTaking output = 45011.sqm (337.5 cumcompacted)
a) LabourMate day - 0.40Mazdoor includingfor broomingof key day 8.00
aggregatesMazdoor skilled day 2.00
ooooooooo
ooe
b) MachineryHydraulicself propelledchlp.spread~r hourbolh for aggr'egatesand key aggregates@ 1500 sqm per hour for4500 x 2 sqmBitUmenpressure disbibutor for hour@ 1750sqm per hourTipper 5.5 cumcapacity for carriage of houraggregatesfrom stockpile to chip spreaderVibratoryroller 8 tonnes hourFront end loader 1 cum bucket capacity hour
6.00
2.57
10.00
6.006.00
c) MaterialBitumen @ 6.8 kg per sqm tonneCn,lshedstonecoarse aggregate (loose) cumpassing63 mm and retained on 2.8 [email protected] cum per sqmKeyaggregatespassing 26.5 mmandretainedon2.8 mm sieve @ 0.018 cum cumpersqm
30.60405.00
81.00
129
'III
q
!I
!:
Road Worts: 5-Basesaod Surface Course (Bituminous)
t41Sr. Reference to Description
Unit Quantity Rare 41No. MoRT&H
Rs.Specifications d) Overhead charges@ % on (a+btc) e) Contractor's Profit @ % on (a+b+c+d) .Cost for 4500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/4500 Note: 2 tippers and 2 rollers Willbe needed to match the capacity of chip spreader and front end loader. 5.5. 506 Built-up Spray Grout PrOViding, laying and rolling of bUilt-up spray grout layer over prepared base consis6ng of a two layer composite constr~tion of compacted crushed coarse agg!l!gates using motor grader for aggregates. Key stone chipsspreader may be used with application of
.:- bituminous binder after each layer, and with key aggregates placed on top of the secondlayer to serve as a base conforming to the fine, grades and cross-section specified, the compacted layer thickness being 75 mm. . Unit = sqrn ~,
Taking output = 3000 sqm (225 cum)10
\ \
a) Labour
Mate day 0.40 Mazdoor inclUding for blOOmingof keyagg!l!gates day 6.00 Mazdoor skilled day 2.00 130
',:,,'
..\
-*~-,.~oooooooooo
Reference toMoRT&H
Specifications
Note:
L _ooo
Road Works: S-Bases and Surface CllUI1lC (Bituminous)
Description Unit Quantity RateRs.
b) MachineryHydraulic self propelledchip spreader hourboth for aggregatesandkey aggregates@ 1500sqm per hour for 3000 x 3 sqmBilumenpressure distributorfor hour3000 x 2 sqm@ 1750sqm per hourTIpper 5.5 cumcapacity hourVibratory roller 8 tonnes hourFront end lOader1 cum bucket capacity hour
c) MaterialBitumen 30 kg per 10sqm@ 15 kg tonneper 10sqm for each layerCrushedsloneOOllfSeaggregatepassing cum53mm and retainedon2.8 mmsieve@ 0.5 cum per 10sqm for each layerKey aggregatespassing22.4 mm and cumretained on 2.8 [email protected] cumper10sqm
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit@ % on (a+b+c+d)
.cost for 3000 sqm = a+b+c+d+eRate per sqm = (a+b+c+d+eV3000
2lippers will beneededtomatchthecapacityof hydraulic chip spreader and front endloader.
131
6.00
3.43
10.006.006.00
9.00
300.00
39.00
;.1
j
Sr.No.
5.6.
i thEI
Road Wodcs: 5-1lases and SurfiIce Course (Bitumin9US) 4
. Description Unit Quantity R".~
Reference toMoRT&H
Specifications
507Dense Graded Bituminous Macadam
Provid"lIlgand /aying dense graded bittlminousmacadam with 100-120 TPH batch type HMPProducing an average output of 75 tonne perhour using crushed aggregates of specifiedgrading, premixed with bituminous binder@ 4.0 to 4.5 per cent by w~ight of total mixand filler, transporting the hot mix to work site,laying With a hydrostatic paver finisher withsensor conlrolto the required grade, level andalignmel)t, rolling with smooth Wheeled,vibraloly and .tandem roUers to achieve thedesired compaction as per MoRT&HSpecifications Clause 507 complete in aUrespects;
Unit = cumTaking output = 195 cum (450 tonne)
a) Labour
Mate dayMazdoorWOrkingwilh HMP, mechanical daybroom, paver, roUer,asphalt culler andassistance for selling outlines, levelsand layout of construction
SkiUed mazdoor for checking line and daylevels
0.8416.00
5.00
b) Machinery
Batch mix HMP @ 75 tonne per hourPaver finisher hYdrostatic With sensorcontrol @ 75 cum per hourGeneralor250 ~A
Front end loader 1 cum bucket capacityTIpper 10 tonne capacity
Add 10 per cent of cost of carriage 10cover cost of loadin!! and unloading
hour 6.00hour 6.00
hour 6.00hour 6.00l.km 450 x L
132
~
~
tttt
'" I
$toNo.
ooo
Reference toMoRT&H
SpeGificatlons
Road Works:.5-Bases ODdSurface Cowse (Bi1llminous)
Description
Smoothwheeled roller8-10 tonne forinitial break downrollingVibralolyroller 8 tonne for intermediateromngFinish rollingwith 13-8tonne smoothwheeledtandemroller
Unit Quantity RateRs.
hour 6.00 x 0.65*
hour 6.00 x 0.65*
hour 6.00 x 0.65*
c) Materials
I) Bitumen @4.25 per cent of weight tonne 19.13of mix
iI) AggregateTotalweight of mix
Road Worb: S-Bases and Smface Course (Bilulllinous)
t
>;~ 4Sr. Reference to Description Unit Quantity Ra~No. MoRT&HRs.Specifications
....Note: *1. Although the rollers are required only for 3hours as per noons of output, but the samehave to be available at site for six hours asthe hot mix plant and paver will take sixhours for mixing and paving the output of450 tonne considered in this analysis.To cater for the idle period of these rollers,their Usage rates have been multiplied by .a factor of 0.65.
134
i
t~,
';,~ ,
2. Quantity of Bitumen has been taken foranalysis purpose. The actual quantity Viilldepend upon job mix formula.
3. labour for traffic; control, walch and wardand other miscellaneous duties at siteincluding sundries have been included inadministrative overheads of thecontractor.
4. In case DBM is laid over freshly laid tackcoal, provision of mechanical broom and2 mazdoors shan be deleted as the samehas been included in the cost of tack coal
, .I\ /\ .;\.~
5. The individual density for each size ofaggregates to be uSedfor construction i.e. 37.5-25 mm, 25-10 mm etc. should befound in the laboraloly 'and accordi