L3 CMP Games DesignSIMS Concept Schedule
Monday Tuesday Wednesday Thursday Friday Saturday Sundayw/b 30.01.12
w/b 06.02.12 Begin Initial notes
Finish basic notes and measurements
Begin basic model of study area
Create basic model of library
Add detail to study area using notes
w/b 13.02.12 Create production log
Add detail to library
Update production log
Take detailed notes and sketches of study area
Work to mostly finish study area
w/b 20.02.12
Half-Term
w/b 27.02.12 Continue to work on library too a near finished standard
Update production log
w/b 05.03.12 Finalise both models until completion
Update production log
Complete both models and finalize production log
Dead line
Harry’s lesson
Other lessons
Study time
Task 1 - Outline Choose and commit to model two areas Produce Schedule – include LightBot overrun and new Deadline. List any problems you might have that you need to take into account – Modeller skills, time management etc. Start production log. Task 2 - Plan Shoot reference imagery and textures, make measurements and draw diagrams – Include this in your production log – either directly blogged or within a PowerPoint presentation / Word document. Schedule in review sessions. Task3 - Respond Build the two objects in stages – be careful not to focus on just one or parts of one. Plan out the production carefully – break it up into chunks. Task 4 - Review Write an evaluation of your project. Leave enough time for this before the deadline. You can’t fully evaluate the work until the project is finished and presented.
L3 CMP Games DesignSIMS Concept Schedule
Monday Tuesday Wednesday Thursday Friday Saturday Sundayw/b 30.01.12
w/b 06.02.12 Begin Initial notes
Finish basic notes and measurements
Begin basic model of study area
Create basic model of library
Add detail to study area using notes
w/b 13.02.12 Add detail to library
Create production log
Take detailed notes and sketches of study area
Work to mostly finish study area
w/b 20.02.12
Half-Term
w/b 27.02.12 Continue to work on library too a near finished standard
Update production log
w/b 05.03.12 Finalise both models until completion
Update production log
Study area completed
Dead line
w/b 12.03.12 Update production log
Continue to work on library to a near finished standard
w/b 19.03.12 Finalize library task
Update production log
Complete library task
w/b 26.03.12 Finalize production log
Review bot study area and library
Deadline
Harry’s lesson
Other lessons
Study time
Task 1 - Outline Choose and commit to model two areas Produce Schedule – include LightBot overrun and new Deadline. List any problems you might have that you need to take into account – Modeller skills, time management etc. Start production log. Task 2 - Plan Shoot reference imagery and textures, make measurements and draw diagrams – Include this in your production log – either directly blogged or within a PowerPoint presentation / Word document. Schedule in review sessions. Task3 - Respond
L3 CMP Games Design SIMS Concept Schedule
Monday Tuesday Wednesday Thursday Friday Saturday Sundayw/b 30.01.12
w/b 06.02.12 Begin Initial notes
Finish basic notes and measurements
Begin basic model of study area
Create basic model of library
Add detail to study area using notes
Task 1 - Outline Choose and commit to model two areas Produce Schedule – include LightBot overrun and new Deadline. List any problems you might have that you need to take into account – Modeller skills, time management etc. Start production log. Task 2 - Plan Shoot reference imagery and textures, make measurements and draw diagrams – Include this in your production log – either directly blogged or within a PowerPoint presentation / Word document. Schedule in review sessions. Task3 - Respond
w/b 13.02.12 Add detail to library
Create production log
Take detailed notes and sketches of study area
Work to mostly finish study area
w/b 20.02.12
Half-Term
w/b 27.02.12 Continue to work on
Update production log
library too a near finished standard
w/b 05.03.12 Finalise both models until completion
Update production log
Study area completed
Dead line
w/b 12.03.12 Update production log
Continue to work on library task
w/b 19.03.12 Work on library to a near completion
Complete library task
w/b 26.03.12 Finalize production log
Review both study area and library
Deadline