Page 1: Risk assessment

Risk Assessment

Production Name EspionageCompany Name TRC Production

Location A School – Conference RoomProduction Date January 2014

Risk Assessment Date 8th DecemberDirector Teeagen Naik

Production Coordinator Chris Harding

≠ = Checked

Number Hazard Tick Description/Action1 Access2 Alcohol Alcohol will be

prohibited on set.3 Animals ≠4 Confined Spaces ≠ Spaces are relatively

clear and open for the filming we

require.5 Fatigue/Tiredness Allocated break and

lunch time will be notified to our actors.

If in the case of an urgent break in the reason of tiredness/ fatigue or any other

reason that will effect the

performance of the filming, it will be taken into strong

consideration.6 First Aid ≠ First Aid kits and

facilities will be close to the filming point

so it will not be far to go. The chance of injury is extremely unlikely due to the nature of our story

however it is there in case of internal

problems.7 Fire ≠ Fire extinguishers are

nearby and around set if the unlikely need to use them

occurs.

Page 2: Risk assessment

8 Flammable Materials 9 Public

10 Hazardous Substances ≠11 Heat In the case of heat,

air conditioners will be around to cool of

the area.12 Lifting Equipment Equipment needed is

of a light/medium weight therefore will not come to an issue

13 Noise ≠ As it is a fairly isolated area noise

levels should be low.14 Smoking on set No smoking on set.

Breaks are allocated to our actors. If the need to smoke they can do during their breaks however must leave the premises to do so.

15 Technical Facilities ≠16 Vehicles17 Water ≠18 Working at Height ≠ No high working

required.19 Rehearsal Space ≠ Space for rehearsal

will be made.20 Lone working


Recommended