Reconstruction of the Saint-Jacques overpass
Presentation of mitigation measuresMay 15, 2014
2
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
3
COMPLETE CLOSURE OF ST-JACQUES BETWEEN GIROUARD AND DÉCARIE
ONE (1) LANE IN EACH DIRECTION ON BOULEVARD DÉCARIE BETWEENDE MAISONNEUVE AND ST-JACQUES (EXPECTED COMPLETION TIME: MID-JUNE)
RUE ST-JACQUES BETWEEN DÉCARIE AND ST-RÉMI: ONE (1) LANE IN EACH DIRECTION
WORK ON RUE SHERBROOKE OUEST, BETWEEN DÉCARIE AND GREY, WITH ONE (1) LANE AVAILABLE WESTBOUND (DURATION: 6 TO 8 WEEKS)
ROADWORK ZONE
COMPLETE CLOSURE OF THE ST-JACQUES ONRAMP TO THE A-720 EASTBOUND
4
PERMANENT RESERVED LANE ON SHERBROOKE EST & OUEST BETWEEN GIROUARD AND TRENHOLME
OPENING OF THE DE MAISONNEUVE EXIT ON THE A-15 SOUTHBOUND
TEMPORARY RESERVED LANE ON SHERBROOKE EST
OPENING OF THE SHERBROOKE U-TURN AREA
TEMPORARY RESERVED LANE ON UPPER-LACHINE
LEFT-TURN LANE ON SHERBROOKE EST FOR THE A-15 NORTHBOUND
MITIGATION MEASURES
5
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians• Detour - network for trucks and automobiles• Review• Noise management• Communications media
PRESENTATION PLANNING
6
MITIGATION MEASURESOpening of the Girouard onramp to the A-15 southboun d
7
MITIGATION MEASURESAddition of a right-turn lane on chemin de la Côte-S t-Luc
8
MITIGATION MEASURESOpening of the De Maisonneuve exit on the A-15 south bound
9
MITIGATION MEASURESOpening of the Sherbrooke U-turn
10
MITIGATION MEASURESModification of signage in the roadwork area
11
MESURES D’ATTÉNUATIONModification des feux de circulation du secteur
MODIFICATION OF TRAFFIC LIGHTS IN THE ROADWORK AREA
12
MITIGATION MEASURESAddition of permanent and temporary reserved lanes on rue Sherbrooke
PERMANENT RESERVED LANE ON SHERBROOKE EST & OUEST BETWEEN GIROUARD AND TRENHOLME
TEMPORARY RESERVED LANE ON SHERBROOKE EST
LEFT-TURN LANE ON SHERBROOKE EST FOR THE A-15 NORTHBOUND
13
MITIGATION MEASURESImplementation of a temporary reserved lane on chem in Upper-Lachine
14
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
15
BICYCLE NETWORK AND DETOUR FOR PEDESTRIANS
16
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound
• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound • Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area
• Implementation of a reserved lane on rue Sherbrooke• Implementation of a temporary reserved lane on chemin Upper-
Lachine• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
17
DETOURNetwork for trucks and automobiles
18
PRESENTATION PLANNING• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn• Modification of signage and traffic lights in the roadwork area
• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
19
• Mitigation measures offer :• More route flexibility over the road network;• Improved capacity on rue Sherbrooke Est at the onramp to the A-
15 northbound;• More efficient public transportation service thanks to additional
reserved lanes.
• All the preferential measures for buses will favour modal transfer.
• Simulations indicate that the impacts on the Sud-Ouest borough are minor.
REVIEW
20
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
21
NOISE BARRIER
22
NOISE BARRIER
23
• Roadwork description• Mitigation measures:
• Opening of the Girouard onramp to the A-15 southbound• Addition of a right-turn lane on chemin de la Côte-St-Luc
• Opening of the De Maisonneuve exit on the A-15 southbound
• Opening of the Sherbrooke U-turn
• Modification of signage and traffic lights in the roadwork area• Implementation of a reserved lane on rue Sherbrooke
• Implementation of a temporary reserved lane on chemin Upper-Lachine
• Bicycle network and detour for pedestrians
• Detour - network for trucks and automobiles
• Review• Noise management• Communications media
PRESENTATION PLANNING
• Neighbourhood committees• Leaflets distributed door-to-door• Website dedicated to the project www.turcot.gouv.qc.ca• Dedicated telephone line 514 873-1372• Turcot email: [email protected]• Twitter @MTQ_Turcot• Monthly electronic bulletins (subscribe via the Turcot website)• Advertising and notices in newspapers• Radio circulation 730 AM and traffic columnists• Ambient noise monitoring system accessible through the website
COMMUNICATIONS MEDIA
25