JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
34
1. INTRODUCTION The proposed project is located at village Basha, Kachnari, Mohania & Garha of Jabalpur Development Authority,Jabalpur, M.P. The Land use of project site is residential cum commercial development as per approved Master Plan of Jabalpur Development Authority. The objective of the study is to carry out Environmental Impact Assessment (EIA) for the proposed project to meet the environmental compliance laid down by the Ministry of Environment and Forest (MoEF), Govt. of India. The scope of the study would be as per the EIA guidelines outlined by the MoEF for Area & township development project.
Fig. 1. Jabalpur Development Authority Master Plan
Project Site
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
35
2.0 PROJECT DETAILS The proposed project is planned on at Village Basha, Kachnari, Mohania & Garha of Jabalpur Development Authority, Jabalpur, M.P. on a total Plot area of 951621.33 sq m. Jabalpur Development Authority (JDA) prepared a Master Plan for Development of Residential Township at Village: Basha, Kachnari, Mohania & Garha, Jabalpur on 9,51,621.33 Sq. m. of Land designed to accommodate 22240 residential Nos. of population. The Land use of the project site is Residential and Commercial as per the Approved Master Plan of JDA. Out of 9,51,621.33 Sq. m. of Land, approx. 1,85,000 Sq. m. of Land is already acquired and balance land is in the process of acquisition which is likely to be completed by 31.03.2018. The scheme comprises of Plotted Colony and Group Housing Plots for all sections of society including Economic Weaker Section (EWS) & Low Income Group (LIG). The Township also provides Plots for Social Infrastructures like – Schools, Health Centre, Shopping, etc. as per the norms of JDA. JDA propose to develop Utilities, Services & Road Infrastructure only & sell the Residential Plots, Group Housing Plots & Social Infrastructure Plots to prospective eligible individuals/ agencies as per the norms of JDA. Allottees of Plots will construct buildings after obtaining Building Plan & other related approvals. The targeted date of completion of the project is 31.12.2021 . The salient features of the project are given in table: 1 below
Table1. Salient features of Proposed Project
S.
No. Description
Quantity Unit
GENERAL
1 Plot Area 951621.33 SQM
2 Area Under College & Railway Boundary 40000.00 SQM
3 Net Plot Area 911621.33 SQM
4 Proposed Built Up Area NIL SQM
5 Total no of Plotted Housing DU's 2166 NOS
6 Total no of Group Housing DU's 2318 NOS
7 Cost of Project 69 CR
8 Estimated Total Population of Entire Project Including
Group Housing Pockets 31198 PERSONS
9 Estimated Population of Plotted colony & Community
facilities (Residential-10830+4374 Floating) 15204 PERSONS
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
36
WATER
10 Total Water Requirement 1928.4 KLD
11 Waste water Generation 1389.2 KLD
RAIN WATER HARVESTING
12 No of RWH of Pits Proposed 2 NOS
13 Total Volume of Rain Water Harvesting Pits CUM
GREEN AREAS
14 Proposed Open & Green Area (10.52%) 95879.8 SQM
WASTE GENERATION
15 Municipal Solid Waste Generation 4.99 TPD
16 Quantity of E-Waste Generation- Kg/Day 39 KG/DAY
17 Quantity of Hazardous waste Generation 0.12 LTS/DAY
POWER
18 Total Power Requirement 14000 KVA
19 DG set backup 100 KVA
NOTE: Group Housing plots will have their own Waste collection/Treatment system,
Rain Water Harvesting system, Power Back up, UGT, Fire Fighting systems. Hence
not included in above calculations - PP of Gr housing pocket will obtain separate
environment Clearance for their projects.
3.0 CONNECTIVITY
The Project site is well connected to NH-7 and NH-37 A which are situated at 1.37Km west and 1.70 KM North direction from the project site. Almost all the surrounding and nearby areas are connected with network of roads. Jabalpur Railway Station is around 6.22 km in east direction. Google image showing location and connectivity of project site is as given below (Ref, fig.2
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
37
Fig 2: Project site Location on Google Image
Fig 3 10 Km Radius Map
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
38
4.0 PROJECT SURROUNDINGS
Project site at village Basha, Kachnari, Mohania & Garha of Jabalpur, M.P. Location coordinate of project site are 230 10’ 49.15”N and 790 53’ 07.79” E. The Project site is well connected to NH-7 and NH-37 A which are situated at 1.37Km west and 1.70 KM North direction from the project site. Almost all the surrounding and nearby areas are connected with network of roads. Jabalpur Railway Station is around 6.22 km in east direction and nearest airport is Jabalpur Airport at about 16.5 Km East. The details of site surroundings are given below in Table- 2.
Table-2: Site and Surrounding of the project Site
S. No. Particulars Details
1. Nearest National Highway NH 7 1.37 km N, NH 37A 1.70 km N
2. Nearest Railway Station Jabalpur Railway Station: 6.22 km, E
3. Nearest Airport Jabalpur Airport: 16.5 Km E
4. Nearest Town/ City Its in the vicinity of Jabalpur city
5. River Body Narmada River 7.10 km S
6. Hills/ Valleys Not within 10 km from the project site
7. Site Topography Plain
8. Archaeologically Important Site Nil
9. National Parks/ Wildlife Sanctuaries
Not within 10 km.
10. Delhi State Boundary Not within 10 km.
11. Seismicity The study area falls under Seismic Zone-III
5.0 OCCUPANCY DETAILS The total population of the project will be approx. 15204 persons including 10830 residents, 2172 Non residential & 2202 visitors/guests. Details of population are given below in Table -3.
Table -3 Population Detail
POPULATION
RESIDENTIAL DU'S POP/DU
TOTAL POPULATION
PLOTTED COLONY PLOTS/DU'S 2166 5 10830
TOTAL 10830
NON RESIDENTIAL
COMMUNITY HALL/COMMERCIAL (Employees etc. )
NURSERY SCHOOL 2626
657
PRIMARY SCHOOL
HIGHER SEC SCHOOL 4441 1110
CONVT SHOPPING 2389 239
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
39
HEALTH CENTRES 1722 50
COMMUNITY HALL 10
POLICE STN 815 82
FACILITY MANAGEMENT STAFF LS 25
TOTAL 2172
VISITORS
RESIDENTIAL 1083
CONVT SHOPPING & COMMUNITY HALL 792
SCHOOLS/COLLEGE 177
HEALTH CENTER 100
POLICE STATION 50
TOTAL VISITORS 2202
TOTAL POPULATION 15204
6.0 WATER DEMAND 6.1 Water supply & source
The water supply for the project during operation phase will be sourced from water supply department of Jabalpur Municipal Corporation. The total water demand works out to approximately 1928 KLD. Details of daily water requirement, waste water generation & reuse of treated water are given below in Table 4 and water balance diagram is given in Figure-5. Below.
Table 4: Calculations for Daily Water Demand for the Project
SN Particulars Water Demand (KLD)
1 Total Water Demand 1928
2 Fresh Water Requirement 1928
3 Total Waste water Generation 1389
4 Water Used for Flushing 574
5 Water used for Landscaping 336
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
40
Water balance is given below:-
Fig 5: Water Balance Diagram for the Project
7.0 SEWAGE GENERATION
Construction phase: Quantity of sewage generated during the construction phase will be negligible and proper management will be done by providing mobile toilets. Septic tank & soak pit will be provided on site for treatment. Operational Phase: Sewage generated during operation phase would be approx 1389 KLD.
8.0 WASTE GENERATION, COLLECTION, TRANSPORT AND DISPOSAL
Solid waste would be generated both during the construction as well as during the operation phase. The solid waste expected to be generated during the construction phase will comprise of used bags, bricks, concrete, tiles, wood etc. T
Waste generation during Operation Phase During operation phase municipal solid waste would be generated from the project. The quantification of different type of waste likely to be generated are given below in table:5 below
Table 5: Quantity of Waste Generation during operation phase
WASTE GENERATION Total Waste Generation 4.99 TPD
Organic Waste Generation 2.99 TPD
E- Waste Generation 38.6 KG/Day
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
41
Hazardous Waste Generation (DG Waste Oil)
0.12 Lts/ Day
(Source: The solid waste generation has been calculated @ 0.5 kg per capita per day basis ad per guideline of (CPHEEO) manual.) Following arrangements will be made at the site in accordance to Municipal Solid Wastes (Management and Handling) Rules, 2016
� Collection and Segregation of waste
1. A door to door collection system will be adopted for collection of domestic waste
in colored bins from household units. 2. Biodegradable & non biodegradable waste shall be separately collected to
ensure segregation at source. 3. For commercial occupancy, adequate number of colored bins separate for Bio-
degradable and Non Bio-degradable will be placed at planned location. 4. Litter bin will also be provided in open areas like parks etc. Treatment of Bio-Degradable wastes Biodegradable /Organic and Horticultural Waste would be treated in Organic Waste Converter installed at site. Generated compost would be used as manure for horticulture development. Non Biodegradable waste Recyclables, such as plastic, rubber, wood pieces, glass etc will be segregated from non biodegradable waste & sold to authorize vendors for recycling & remaining inert waste shall be sent to land fill site through authorized vendor as per the guidelines of Municipal Solid Wastes (Management and Handling) Rules, 2016.
9.0 POWER REQUIREMENT DETAILS The power supply shall be supplied by Purva Kshetra Vidyut Vitran Company Ltd. The estimated electrical demand load & proposed power back to be used during power failure shall be as per details given in Table:6 below.
Table: 6 Power & DG detail
POWER Total Power Requirement 14000 KW
DG set backup 100 KVA
9.1 BACKUP POWER DETAILS
There is a provision of 100 KVA DG set for power back up in the Project. The DG set will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion.
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
42
10.0 STORM WATER DRAINAGE & RAIN WATER HARVESTING SYSTEM A network of covered/underground storm water drain will be developed to collect rain water runoff from roof tops, hard & soft areas – roads, paths, parking & open areas, vegetated surfaces planned on the ground. Strom water would be channelized to rain water harvesting structure designed to charge the rain water to ground water aquifer. The storm water will pass through the desilting chamber/oil& grease separator before finally discharging to percolation tank. Design details of Rain Water Harvesting structure are given in the table 7 & Figure 8 below
Table 7: Calculations for storm water Harvesting Potential
RAIN WATER HARVESTING
PARTICULARS ROAD/PAVEMENT/PARKING
AREAS GREEN AREA
Area (Sq.m.) 323237.10 95879.81
Runoff coefficient 0.7 0.2
Rainfall (m) 1.2684 1.2684 Harvesting potential (cu.m.) 286995.7563 24322.7902 Net water availability and potential for recharge (cu.m.) per year (considering 20% losses)
249054.8
Table 8: Calculations for Rain water Harvesting Pit Design
Rain Water Harvesting Pit Design
Particulars Values Unit
Peak hourly rate taken @ 60 mm/hr for one hour duration
14726.52 CUM
Peak hourly rate taken @ 60 mm/hr for 15 min duration
3681.63 CUM
Volume of recharge pit 28.5 CUM
No. of recharge pit required 129.18 No.
Proposed No of Recharge Pits 130 No.
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
43
Total of 130 Rain Water Harvesting pits are planed rain water recharge within the project premises.
Figure-6: A typical Recharge pit
11.0 LANDSCAPE & SHELTERBELT DEVELOPMENT
Total green area measures 95879 m2 i.e. 10.52% of the net plot area. Approx. 50% of area would be used for peripherial tree plantation, road side plantation & remaining area would be used for plantation of shrubs, lawn, and ground cover. There are several trees which will be planted along the sides of the Project boundary. For tree plantation preference will be given to local tree with large leafs & dense foliage for shading & reduction of air & noise pollution. The plant species would be selected from the list given below:
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
44
THE LIST OF PLANT SPECIES LIKELY TO BE PLANTED
SN Botanical Name Common Name
1 Ficus Infectoria Pakur
2 Delonix regia Gulmohur
3 Cassia fistula Amaltas
4 Azadirachtha Indica Neem
5 Peltophorum ferrugineum Copper pod
6 Ficus retusa Usha
7 Alstonia Scholaris Scholar tree
8 Thespesia populnea Paras Pipal
9 Churasia tabularis Chukrasia
10 Anthocephalus cadamba Kadamba
11 Jacaranda mimosifolia Jacaranda
12 Mimusops Elengi Maulsari
13 Plumeria alba Temple tree
14 Terminalia arjuna Arjuna
15 Bauhinea Variegata Kachnar
16 Sarca indica Ashoka
17 Silver oak Grevillea Robusta
18 Semal Bombax Ceiba
19 Pilkhan Ficus
12.0 PARKING FACILITIES
For smooth circulation & reduction of pollution separate entry & exits with gates of adequate sizes are planned for the vehicles & also for the movement of fire engine. Provision for car/vehicle parking is planned. Apart from peripheral roads for vehicular movement internal roads/pavements are planned for traffic free movement of pedestrians.
13.0 Risk and Hazards 13.1 Seismicity
Based on the tectonic features and records of earthquake, a Seismic Zoning map has been developed for the country by Bureau of Indian Standard (BIS). The area under study falls in Seismic Zone-III. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structures. The structural design shall be vetted by the agency nominated by local body. Earthquake resistant construction techniques will also be used.
13.2 Emergency Lighting
The emergency lights operated on battery power would be provided at appropriate locations.
13.3 Fire Safety
The owner of the plot sold by JDA shall be responsible for Fire Clearance and shall
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
45
made arrangements for fire safety in proposed sector 7, 8 & 9.
14.0 ENVIRONMENTAL POLLUTION MITIGATION MEASURES 14.1 Air Pollution
Increased traffic generation due to project is not going to cause significant increase in atmospheric concentration of gases and will not result in heat island formation as adequate landscaping has been provided. Mitigation Measures for Air Pollution during Construction Stage Air quality around the project site will be impacted during construction stage. Various construction activities especially related to handling of loose material are likely to generate fugitive dust that will affect the air quality of the surrounding area of the project site. To minimize such impacts following measures has been proposed:
� All the loose material either stacked or transported will be provided with suitable
covering such as tarpaulin, etc. � Water sprinkling shall be done at the locations where dust generation is
anticipated. � To minimize the occupational health hazard, proper personal protective gears i.e.
mask shall be provided to the workers who are engaged in dust generation activity.
Mitigation Measures for Air Pollution during Operational Stage Operation of DG Sets is the only source of air pollution during operational phase. Sufficient stack height will be provided for proper dispersion of pollutants. Also, it is proposed to minimize air pollution by providing plantation as buffer on the periphery of the project site and on the open spaces. An area of 95879.8m2 i.e. 10.52% of the net plot area has been kept for green development & plantation purposes.
14.2 Water Pollution
The source of water pollution during construction and operation phase is due to waste water generated from toilets and washing.
14.3 Noise Environment
It is envisaged that within the site there shall be maximum movement of light motor vehicles like cars and 2-wheelers which will lead to some increase in noise levels. It is proposed to minimize the noise levels by providing plantation as buffer on the sides of internal roads, on the open spaces inside and around the periphery of whole complex. Proper maintenance of the internal roads will also be carried out and Informatory signboards shall be provided to encourage vehicle owners to maintain their vehicle, not to blow horns and follow the emission standards fixed by Government Authorities. DG sets will be kept in the acoustic chamber and ambient noise will be within the CPCB standard limits.
JABALPUR DEVELOPMENT
AUTHORITY
PROPOSED RESIDENTIAL CUM COMMERCIAL SCHEME
NO. 65 AT VILLAGE BASHA, KACHNARI, MOHANIA &
GARHA OF JABALPUR DEVELOPMENT AUTHORITY,
JABALPUR, M.P.
CONCEPTUAL PLAN
ITHC/PRJ/17-18/EIA/88 IND TECH HOUSE CONSULT
46
Mitigation Measures for Noise Pollution during Construction Stage During the construction stage, expected noise levels shall be in the range of 80-85 dB (A) which will decrease with increase in distance as per the Inverse Square Law. Administrative as well as engineering control of noise will be implemented. Isolation of noise generation sources and temporal differentiation of noise generating activities will ensure minimum noise at receiver’s end. To prevent any occupational hazard, ear muff / ear plug shall be given to the workers operating machinery. Use of such machinery shall not be allowed during night hour. Careful planning of machinery operation and scheduling of operations shall be done to minimize such impact. Mitigation Measures for Noise Pollution during Operation Stage It is envisaged that there shall be maximum movement of light motor vehicles like cars and 2-wheelers which will lead to some increase in noise levels. It is proposed to minimize the noise levels by providing plantation as buffer on the open spaces and around the periphery of whole complex. Informatory signboards shall be provided to encourage vehicle owners to maintain their vehicle, not to blow horns and follow the emission standards fixed by Government Authorities. DG sets will be kept in the acoustic chamber and ambient noise will be within the CPCB standard limits.
15.0 CONSTRUCTION MATERIALS
The following construction materials are required for residential construction;
1. Coarse sand 2. Fine sand 3. Stone aggregate 4. Cement 5. Fly Ash 6. Bricks
7. Pavors 8. Conc, CI, GI, CPVC, UPVC pipes .
16.0 LIST OF MACHINERY USED DURING CONSTRUCTION
(i) Dumper (ii) Concrete mixer with hopper (iii)Concrete Batching Plant (iv) Cranes (v) Concrete pressure pumps (vi) Mobile transit mixer