Page 1: Project: Talley Road Phase I Non-Tolled (BC03)

Limits: Potranco Road (FM 1957) to Wiseman Blvd.

Contractor: Texas Sterling Construction

Engineer: CP&Y, Inc.

Construction Cost: $22,305,572.62

Construction NTP: 11/11/19

Contract Completion Date: 07/05/22

Projected Completion Date: 04/25/22

Scope: Expand from an existing two-lane ruralroadway to a four-lane urban roadway consistingof two 12-foot travel lanes in each direction, amedian, curb, and sidewalk.

Status: 40% Paid Out, 41% Time used

Monthly Activity:

• Installing 16” D.I. Watermain on Talley Road

• Installing 24” RCP on Talley Road.

• Installing 4X4 SBC Boxes

• Installing culvert boxes

• Installing CMP 30” pipe and structure

• Placing and building forms for bridge deck.

Updated: March 09, 2021

ALAMO REGIONAL MOBILITY AUTHORITYCOUNTY OF BEXAR

Project: Talley Road Phase I – Non-Tolled (BC03)