Progress Since 2012 Name Suburb Region/District Project Type Project Description Current
Status
2nd Bulk Liquids Berth Port Botany Eastern City
District
Freight Planning approval to develop a second Bulk Liquids
Berth (BLB2) at Port Botany was received in 2008. On
31 May 2011, John Holland Pty Ltd was engaged to
construct the BLB2. The berth became operational in
December 2013. The main products handled at the BLB
are refined fuels, gases and chemicals / other bulk
liquids. BLB2 comprise a steel piled pier adjacent to the
existing BLB1; associated infrastructure such as marine
loading arms, fire fighting equipment, onshore support
facilities and pipelines from existing user sites to the new
berth. The open access, multi user berth operates on a 24
hour/ 7 day per week basis. BLB2 has been designed to
accommodate 120,000 dead weight tonne vessels to a
maximum of 270m length overall.
Completed
Abbotsford Wharf -
Wharf Upgrade
program
Abbotsford Eastern City
District
Maritime The upgrade aims to provide easier access to the wharf,
better weather protection, additional seating, improved
safety, quicker and more efficient boarding and
disembarking, increased capacity and more efficient
interchange with other modes of transport.
Planning
Acacia Avenue
cycleway
Lake Munmorah Central Coast Walking and Cycling Shared Path cycleway alongside Acacia Avenue Completed
Name Suburb Region/District Project Type Project Description Current
Status
Additional Boating
Access Points at
Middle Harbour
(Investigation),
Willoughby
Castle Cove North Maritime Planning
Additional Boating
Access Points on the
Nepean River
(Investigation)
Penrith West Maritime Investigation and concept designs for eight passive craft
access points to the Neapean River.
Planning
Airds Road cycleway Leumeah Western City
District
Walking and Cycling Shared Path cycleway alongside Airds Road Completed
Airport East Precinct Mascot Eastern City
District
Road Roads east of the airport will be upgraded and the
General Holmes Drive rail level crossing will be
removed by constructing a road underpass. This would
improve the movement of rail freight facilities to and
from Port Botany, and improve traffic flow and access to
the airport and Port Botany. Key features and benefits of
the project are replacing the General Holmes Drive rail
level crossing with a road underpass that links General
Holmes Drive, Botany Road and Wentworth Avenue to
improve the movement of rail freight and improve access
to the Airport, Mascot and the eastern suburbs; providing
improvements to the Mill Pond Road intersections with
General Holmes Drive and Botany Road to support
future growth and access to the airport; widening Joyce
Drive and General Holmes Drive between O'Riordan
Street and Mill Pond Road to three lanes in each
direction to improve traffic flow around the airport and
to Port Botany; creating a new shared path to link to the
existing cycle way on Wentworth Avenue to improve
connections for pedestrians and cyclists; and retaining
the northbound bus stop on Botany Road close to the
existing location to meet community needs.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Airport North Precinct Mascot Eastern City
District
Road Roads north of Sydney Airport are being upgraded to
improve traffic flow and connections to the airport and
Port Botany. Key features of the upgrade include
converting the southern sections of Robey Street and
O’Riordan Street into one-way roads; widening
O’Riordan Street to provide six through lanes between
Bourke Road and Robey Street; reconfiguring the
existing traffic lights on O’Riordan Street between
Qantas Drive and Bourke Road; and upgrading the
footpath on the eastern side of O’Riordan Street. The
upgrades will help increase traffic capacity and reduce
congestion along O’Riordan Street, and improve access
to Sydney Airport domestic terminals.
Planning
Airport Street
cycleway
Temora Riverina - Murray Walking and Cycling Road Shoulder cycleway alongside Airport Street Completed
Airport West Precinct Arncliffe Eastern City
District
Road Marsh Street, Arncliffe is being widened to three lanes
westbound to relieve congestion and improve traffic
flow. The project supports and complements upgrades to
Sydney Airport’s internal road network. Key features
include widening Marsh Street to three lanes westbound
between the Giovanni Brunetti Bridge and the M5
interchange, meaning Marsh Street would be three lanes
in both directions; providing a dedicated cycleway on the
southern side of Marsh Street to connect the existing
path on the bridge to the Eve Street cycleway; providing
a pedestrian crossing at the intersection of Marsh Street
and Flora Street; and minor widening of the existing
eastbound and westbound lanes to provide wider, safer
lanes for motorists. Key benefits include increasing
traffic capacity and reduce congestion on Marsh Street
for westbound traffic; improving cycle access in the area
and increase safety for cyclists; and improving
pedestrian access in the area.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Albert Street
cycleway
Moruya South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Albert Street Completed
Albion Park
Interchange -
Commuter Parking
Albion Park Rail Illawarra
Shoalhaven
Parking Conversion of an existing staff car park to provide two
extra commuter car parking spaces.
Completed
Albion Park
Interchange - Transport
Access Program
Upgrade
Albion Park Rail Illawarra
Shoalhaven
Interchange Improvements to the transport interchange facilities and
access at Albion Park Station included redesigning and
regrading of the ramp on the western side of the station
to make it wheelchair compliant; improving pedestrian
access to the western side bus stop on the Princes
Highway; providing a more user friendly bicycle parking
facility; and providing a formalised ‘kiss and ride’ area
for passenger pick up and drop off.
Completed
Albion Park Rail
Bypass - Princes
Highway Upgrade
Albion Park Illawarra
Shoalhaven
Road Planning is underway for a future extension of the M1
Princes Motorway between Yallah and Oak Flats to
provide a bypass of Albion Park Rail. The bypass will
complete the 'missing link' for a high standard road
between Sydney and Bomaderry.
Planning
Albion Park Station Refresh Package 3a
Albion Park Rail North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Albury Station Refresh Package 4a
Albury Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Alfords Point Road
Upgrade
Alfords Point South District Road Alfords Point Road will be widened between the
Georges River and Brushwood Drive. The upgrade will
reduce congestion, improve travel times and improve
road safety. The upgrade will also provide improvements
to the local road network.
In-Progress
Alice Street Harris Park Central City Road Install pedestrian fence and kerb ramp/footpath works in
Alice Street east of Good Street, Harris Park. Includes
construction of pedestrian fence on both sides of Alice
Street east of the existing pedestrian crossing and also to
upgrade footpath/kerb ram
Completed
Allambie Road
cycleway
Allambie
Heights
North District Walking and Cycling Road Shoulder cycleway alongside Allambie Road Completed
Allandale Road Cessnock Hunter Road Install traffic signals at McGrane St, and left in left out
on eastern leg of Jurd St
Not Started
Allawah Interchange -
Transport Access
Program Upgrade
Hurstville South District Interchange The transport interchange facilities at Allawah have been
upgraded to make it easier for commuters to access the
station by different transport modes. The upgrade
included changes to bus stops, footpaths and ramps, a
new 'kiss and ride' pedestrian drop-off zone, bicycle
racks, shelters, fencing, guides for the visually impaired
and signage on both sides of the station to improve
accessibility.
Completed
Allworth Boat Ramp
Improvements (Car
Park and Lighting)
Allworth Hunter Maritime Works include the installation of a new toilet, improve
lighting and investigating the removal of Allworth
Swimming baths.
Planning
Alpine Way Khancoban Riverina Murray Road VAS curve warning signs Completed
Alpine Way Geehi Riverina Murray Road VAS curve warning signs Completed
Angels Beach Drive East Ballina North Coast Road Install roundabout and provide superelevation, RRPMs
and curve advisory signs
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Anzac Park Boating
Access Improvements
(Dinghy Storage and
Launching Facility),
Tea Gardens
Tea Gardens Hunter Maritime Installation of new dinghy launching and storage
facilities within Anzac Park.
Planning
Apex Park Boat Ramp
& Car Park Upgrade,
Wagga Wagga (Lake
Albert)
Lake Albert Riverina Murray Maritime Upgrade of the Apex Park boat ramp facility at Lake
Albert. Works include: Widening the existing boat ramp
to 8m and installation of lane dividers to make it a two
lane ramp; expansion and redevelopment of the existing
car park to increase car/trailer parking capacity
(resealing, linemarking, signage, solar lighting); and
improvements to the lake foreshore including
stabilisation of 215m of the foreshore using Elcorock
sand bags (to replace failed retaining walls), installation
of boat tie up points and installation of rubbish stations.
Planning
Apex Park Boat Ramp
Facility Upgrade, Lake
Hume
Lake Hume
Village
Riverina Murray Maritime Upgrade of the Apex Park boat ramp facility. The project
will be staged with Stage 1 to involve the development
of a Master Plan for the site and Stage 2 to comprise
construction of identified infrastructure priorities.
Planning
Apex Park Boat Ramp
Upgrade, Narooma North Narooma South East and
Tablelands
Maritime Additional Funding for the upgrade of the boat ramp
facility at Apex Park, Narooma. Works include:
construction of a new two lane concrete boat ramp,
construction of a new modular centre ramp pontoon,
refurbishment of the existing jetty.
Completed
Appin Road Cataract Illawarra
Shoalhaven
Road Realign curve from between 200-600 to between 600-
1000m, provide appropriate super elevation, install wire
rope barrier on roadside from no barrier and widen
shoulder to 2.5m outside curve and 1m inside curve
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Armidale Interchange -
Transport Access
Program Upgrade
Armidale New England North
West
Interchange Interchange upgrade at Armidale railway station and
coach depot. The upgrade at the railway station included
resurfacing of the car park, nine extra commuter car
parking spaces including one accessible parking space,
improving footpaths, installing new signage and bicycle
parking facilities, as well as upgrades to lighting. The
upgrade at the Visitor Information Centre coach
interchange included a new bus shelter, lighting, CCTV
surveillance cameras and accessibility upgrades to the
existing rest rooms. The new shelter will keep
passengers out of the elements while waiting for coaches
and disembarking.
Completed
Armidale Regional Council Truck Wash Capacity Upgrade
Armidale New England
North West
Freight Install dedicated 50mm mains water service with associated meter and backflow device to truck wash.Install a new pressure pump for Bay 2 (currently unequipped) and upgrade current pressure pump on Bay 1 (pump is 10+ years old)Install two 22,700 litre poly tanks for pump draw off reservoir.Upgrade AvData controller to service additional wash bay.Install colour bond fencing to separate the two wash bays.
Planning
Armidale Road Nymboida North Coast Road Improve vertical alignment, superelevation, horizontal
alignment and install shoulders, CAMs and guideposts
Completed
Arncliffe Interchange -
Commuter Parking
Arncliffe Eastern City
District
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Arncliffe Interchange -
Transport Access
Program Upgrade
Arncliffe Eastern City
District
Interchange Arncliffe Station is now accessible for all customers with
four new lifts connecting the concourse, platform and
street levels. The lifts will make commuting easier for
our customers, especially those with a disability, the
elderly, parents with prams and travellers with luggage.
Key features of the upgrade include four new lifts; new
canopies on the footbridge and platforms; upgraded
CCTV surveillance cameras and announcement systems;
new sheltered bus stops, taxi rank and kiss and ride area
along Firth Street; new family accessible toilets at the
platform level; two new accessible parking spaces within
the existing car park off Burrows Street; upgraded stairs
and wayfinding signage; and new bicycle racks.
Completed
Artarmon Interchange -
Transport Access
Program Upgrade
Artarmon North District Interchange Improvements to the accessibility at Artarmon Station
included two new lifts, a new pedestrian bridge to
improve access from Hampden Road and a new
accessible parking space on Hampden Road.
Completed
Artarmon Station Refresh Package 2
Artarmon Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Ashfield Interchange -
Commuter Parking
Ashfield Eastern City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Ashfield Interchange -
Commuter Parking
Ashfield Eastern City
District
Parking A new multi-storey car park on Brown Street will
include 120 new commuter spaces, fencing, lighting and
CCTV to boost access and security.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Ashfield Station Refresh Package 2
Ashfield Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Asquith Interchange -
Commuter Parking
Asquith North District Parking The project includes constructing a 42 space commuter
car park on Jersey Street North; two accessible parking
spaces close to the station (within the Haldane Street car
park); a pedestrian link from the car park to the station;
and improved lighting and CCTV surveillance.
In-Progress
Asquith Station Refresh Package 1
Asquith South East and Tablelands
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Auburn Interchange -
Transport Access
Program Upgrade
Auburn Central City
District
Interchange Improvements to the transport interchange facilities at
Auburn Station included upgrading the Northumberland
Road ‘kiss and ride’ facility to incorporate seating and
signage; removing the existing stairs that lead to the
ramp at the Railway Station entrance and exit at South
Parade; and installing a new weather wall at the South
Parade bus stop.
Completed
Austinmer Interchange
- Commuter Parking
Austinmer Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Austinmer Interchange
- Transport Access
Program Upgrade
Austinmer Illawarra
Shoalhaven
Interchange Improvements to Austinmer Station included redesigning
and rebuilding the ramp to platform 2.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Automatic Train
Protection
Haymarket Eastern City
District
Rail The Automatic Train Protection (ATP) Program will see
the Sydney Trains metropolitan and NSW TrainLink
intercity rail network fitted with new equipment to
improve rail safety by monitoring a train’s speed and
position on the network and automatically intervening or
braking to ensure safe operations.
In-Progress
Back Creek Boating
Access Improvements,
South West Rocks
South West
Rocks
North Coast Maritime Planning
Backmans Swamp
Creek cycleway
Orange Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Backmans Swamp
Creek
Completed
Ballina Interchange -
Transport Access
Program Upgrade
Ballina North Coast Interchange Construction of new waiting areas and installation of
additional lighting.
Completed
Ballina Road
cycleway
East Lismore North Coast Walking and Cycling Shared Path cycleway alongside Ballina Road Completed
Ballina Trawler
Harbour Development
(Investigation), Ballina
West Ballina North Coast Maritime Preparation of a development options review to
determine the preferred use of the Ballina Trawler
Harbour Precinct.
Planning
Balmain East Wharf -
Wharf Upgrade
Program
Balmain East Eastern City
District
Maritime The new wharf is made up of a steel floating pontoon, a
concrete fixed entry platform and an aluminium
gangway connecting the entry platform to the pontoon.
The pontoon has a curved roof, glass panels and new
seating offering some protection from the weather and
improved amenity. The new wharf provides better
protection from the wind, rain and sun; improved safety
for customers; improved access for mobility impaired
customers and customers with prams; quicker and more
efficient boarding and disembarking; and future capacity
for two ferries to berth at the wharf at the same time.
Completed
Balmain Thames Street
Wharf - Wharf
Upgrade Program
Balmain Eastern City
District
Maritime Ferry wharf upgrade to improve the safety and amenity
for passengers and better accessibility for customers with
mobility aids.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Balmoral Reserve Boat
Ramp Car Park
Upgrade, Balmoral
Balmoral Hunter Maritime Upgrade of the Balmoral Reserve boat ramp car park.
Works include: formalisation (sealing and line marking)
of the existing gravel car park, improvements to the boat
ramp manouevring area and formalisation of boat rigging
and wash down area.
Planning
Balranald Caravan Park
Boat Ramp Pontoon,
Balranald
Balranald Far West Maritime Installation of two 8m pontoons at the boat ramp (one
either side of the ramp) and construction of two unisex
toilets on the upper level trailer parking area at the site.
Planning
Balranald Truck Wash Project
Balranald Far West Freight Extend existing concrete apron to accommodate road train configuration vehicle. Install new Avdata or similar operations system including water supply and pressure pump system. Install water treatment facility and outfall retention. Area lighting and access ladders.
Planning
Bandon Road Link Vineyard Western City
District
Road A new road corridor is planned between Richmond
Road, Marsden Park and Windsor Road, Vineyard. This
is part of the North West Growth Centre Road Network
Strategy that was confirmed by the NSW Government in
July 2015. The preferred corridor would cater for a new
four lane divided road including a central median to
allow for future widening; an off-road shared path for
pedestrians and cyclists; a new road underpass of the
Richmond railway line at Vineyard; and traffic light
intersections and a central median to improve road
safety.
Planning
Bankstown Interchange
- Commuter Parking
Bankstown South District Parking Conversion of existing staff car park to provide ten extra
commuter car parking spaces, including two accessible
parking spaces.
Completed
Bankstown Interchange
- Transport Access
Program
Bankstown South District Interchange Improvements to Bankstown Station included new stairs
and ramps to improve circulation at the northern and
southern station entrances; relocation and installation of
additional ticket barriers; installation of a covered
walkway to the bus interchange; widening the staircase
access to platform; and installation of bicycle parking
facilities.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Barangaroo Ferry Hub Barangaroo Eastern City
District
Maritime The Barangaroo Ferry Hub will serve Sydney’s newest
commercial district and provide increased capacity for
ferry services to meet future demand. The new ferry hub
will provide berthing space for additional ferry services
from the Parramatta River, as well as direct access to and
from the Eastern Suburbs and lower North Shore. The
new ferry hub will connect customers to the city centre
via Wynyard Walk, a high quality pedestrian link
between Barangaroo and Wynyard Station. Key features
include two new ferry wharves with a landing and ramp
to connect the floating pontoon to the land; two berthing
faces for ferries on each pontoon; new facilities for
customer safety and comfort at each wharf, including
seating, lighting, passenger information display and
weather protection; integrated electronic ticketing system
for public transport in Sydney using the Opal card; and
public amenities such as bins, ticket vending machines,
wayfinding and signage.
In-Progress
Barmedman Road
cycleway
Temora Riverina - Murray Walking and Cycling Shared Path cycleway alongside Barmedman Road Completed
Barrenjoey Road Bilgola North Road CAMs, curve advisory signs and warning signs Completed
Barrington Bridge
Replacement - Bridges
for the Bush - Tranche
2
Barrington Hunter Road The Barrington Bridge which crosses the Barrington
River at Barrington, was built in 1920. The bridge is
located on Thunderbolts Way, which is an important
freight link between the Mid North Coast and the New
England Tablelands serving tourism, livestock and
timber industries. The timber truss bridge is narrow and
requires a high level of maintenance. The proposal is to
replace the bridge with a conctete structure on a new
alignment. Design is progressing.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Barton Highway Safety
Works
Murrumbateman South East &
Tablelands
Road A package of safety works was undertaken on the Barton
Highway. Safety works at the intersection of McIntosh
Circuit and the Barton Highway included providing
turning lanes on the Barton Highway and McIntosh
Circuit and improving lighting. Safety at the Euroka
Avenue intersection with the Barton Highway was
improved including widening the shoulder on the
northbound lane, building new designated turning lanes
into Euroka Avenue and some vegetation removal to
improve sight distance. A curve on the Barton Highway
just south of Murrumbateman Road was realigned and a
turning lane was built for vehicles turning right into
Murrumbateman Road. A one kilometre section of the
Barton Highway at Capricorn Corner was realigned
given its crash history. Construction of 4.5 kilometres of
new road at Gounyan curves was undertaken to remove
seven bends in the highway. A 1.2 kilometre southbound
overtaking lane has also been built to replace the existing
northbound overtaking lane. Other safety works being
planned along sections of the Barton Highway include
extending culverts, removing trees, flattening
embankments and installing safety barriers.
Completed
Bass Point Boat Ramp
Car Park Upgrade,
Shell Cove
Shell Cove Illawarra
Shoalhaven
Maritime Planning
Batemans Bay
Interchange - Transport
Access Program
Upgrade
Batemans Bay South East &
Tablelands
Interchange Construction of new drop off and pick up areas. Completed
Batemans Bay Sewage
Pump-out Facility North Batemans
Bay
South East and
Tablelands
Maritime Planning
Batemans Bay/Clyde
River Boating
Infrastructure Upgrades
Batemans Bay South East and
Tablelands
Maritime Planning
Name Suburb Region/District Project Type Project Description Current
Status
Bathurst Station Refresh Package 2a
Bathurst Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Baulkham Hills
Interchange -
Commuter Parking
Baulkham Hills Central City
District
Parking New commuter car park at Torrs Street providing 183
commuter car parking spaces, including four accessible
parking spaces.
Completed
Baulkham Hills
Interchange - Transport
Access Program
Upgrade
Baulkham Hills Central City
District
Interchange New bus shelters have been installed on Windsor Road
and Old Northern Road, as well as improvements
delivered to lighting and footpaths. Kiss and ride
facilities are now available on Railway Street, with new
pram ramps also delivered on Olive Street.
Completed
Bayview Wharf
Upgrade & New
Pontoon, Bayview
Bayview North Maritime Upgrade of the existing Bayview wharf which is in poor
condition. Works include staibilsation of the stone
groyne (that joins the wharf to the shore), and
replacement of some fender piles, decking planks, wharf
beams, and fastenings. The improvement works also
include the installation of a new pontoon to provide short
term berthings for boats.
Planning
Beauty Point Boat
Ramp Facility
Upgrade, Wallaga Lake
Wallaga Lake South East and
Tablelands
Maritime Upgrade of the Beauty Point boat ramp. Works include:
replacement of the existing gravel boat ramp with a new
concrete double ramp, enlargement and upgrade of the
existing site access road and ramp approach, enlargement
and formalisation of car/trailer parking.
Planning
Beecroft Interchange -
Commuter Parking
Beecroft North District Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Bega Bypass Bega South East &
Tablelands
Road The 3.5 kilometre, two lane bypass takes heavy vehicles
out of Bega CBD and improves safety. A new
roundabout south of the Bega River Bridge was also
installed and the intersection at Finucane Lane was
rebuilt to improve sight distance and road safety. The
bypass supports the region's economy by allowing the
Princes Highway between the Snowy Mountains
Highway and the Victorian border to be used by B
double heavy vehicles by providing an approved route at
Bega without sharp corners.
Completed
Belgrave Street Manly North Road Pedestrian protection at traffic lights Completed
Bellambi Interchange -
Commuter Parking
Bellambi Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Bellambi Station Refresh Package 3a
Bellambi North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Bellevue Estate
cycleway
Mudgee Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Bellevue Estate Completed
Bells Line of Road -
Castlereagh
Connection Corridor
Preservation
South Windsor Western City
District
Road Transport for NSW is investigating a suitable corridor
for the Bells Line of Road – Castlereagh Connection to
provide an alternative route across the Blue Mountains.
The investigation would identify a suitable corridor
connecting the Bells Line of Road east of Kurrajong
Heights with the Sydney Motorway Network.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Bells Line of Road
Corridor Improvement
Program
Berambing Western City
District
Road Road safety and traffic efficiency are being improved on
Bells Line of Road between Lithgow and Kurrajong
Heights by providing more overtaking lanes and wider
sealed shoulders. This includes safety improvements on
Chifley Road between Bell and Lithgow including curve
and grade improvements at Scenic Hill and a road over
rail bridge replacement at Clarence.
In-Progress
Belmore Interchange -
Commuter Parking
Belmore South District Parking Conversion of existing staff car park to provide five
extra commuter car parking spaces.
Completed
Belmore Station Refresh Package 4
Belmore Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Belmore Street
cycleway
Junee Riverina - Murray Walking and Cycling Shared Path cycleway alongside Belmore Street Completed
Bemboka Bridge
Upgrade - Bridges for
the Bush - Program 1
Morans Crossing South East &
Tablelands
Road The project includes upgrades to the road approaches and
improved safety with the improvement of existing traffic
barriers to current Australian standards. Key features
include widening of the bridge and both road
approaches, specifically to allow an increase in traffic
lane width, an increase in shoulder width and provision
for cyclists on the bridge; intersection upgrade works at
Polacks Flat Road to improve sight distance to the west;
realignment of the unnamed access track intersection
immediately west of the bridge to improve sight
distances; and two permanent combined sedimentation
and accident spill basins. The upgrade improves freight
productivity by removing a significant freight bottleneck.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Berala Interchange -
Transport Access
Program Upgrade
Berala Central City
District
Interchange Improvements to Berala interchange include a new lift; a
new canopy; a family accessible toilet; undercover
bicycle racks; improved interchange areas, including kiss
and ride zones, two accessible parking spaces and an
upgraded bus shelter; upgrades to lighting and CCTV
surveillance; and improved wayfinding signage.
In-Progress
Berala Station Refresh Package 1
Berala South East and Tablelands
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Berkeley Harbour
Boating Facilities
Improvements
(Investigation), Lake
Illawarra
Berkeley Illawarra
Shoalhaven
Maritime Planning
Bernera Road
cycleway
Prestons Western City
District
Walking and Cycling Shared Path cycleway alongside Bernera Road Completed
Berowra Interchange -
Commuter Parking
Berowra North District Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Berry Interchange -
Commuter Parking
Berry Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Berry to Bomaderry -
Princes Highway
Upgrade
Bomaderry Illawarra
Shoalhaven
Road The upgrade will provide around 10.6 kilometres of four-
lane highway with median separation between Mullers
Lane, Berry and Cambewarra Road, Bomaderry. Once
the highway upgrade between Berry and Bomaderry is
built it will complete four lanes of divided highway
between Waterfall and Jervis Bay Road, Falls Creek.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Beverly Hills
Interchange - Transport
Access Program
Upgrade
Beverly Hills South District Interchange Improvements to Beverly Hills interchange include new
pick up and drop off areas, new taxi rank and bus shelter.
Completed
Beverly Hills Station Refresh Package 4
Beverly Hills Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Bexley North
Interchange -
Commuter Parking
Bexley North Eastern City
District
Parking Conversion of existing staff car park to provide five
extra commuter car parking spaces
Completed
Birchgrove Wharf -
Wharf Upgrade
Program
Birchgrove Eastern City
District
Maritime The wharf upgrade will provide improved customer
amenity such as better protection from the wind, rain and
sun, seating and waiting areas; improved safety for
customers; improved access for mobility impaired
customers and customers with prams; quicker and more
efficient boarding and disembarking; increased wharf
capacity for future growth of ferry services; more
efficient interchanges with other modes of transport, both
public and private; and better way finding signage.
Planning
Black Diamond
Place cycleway
Bulli Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Black Diamond
Place
Completed
Blackheath Station Refresh Package 4a
Blackheath Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Blacktown Interchange
- Commuter Parking
Blacktown Central City
District
Parking Conversion of existing staff car park to provide 113 extra
commuter car parking spaces.
Completed
Blacktown Interchange
- Commuter Parking
Blacktown Central City
District
Parking New multi-storey commuter car park providing 489 new
commuter car park spaces, including 15 accessible
parking spaces, eight motorcycle spaces and 40 spaces
for securing bicycles. The car park also includes lifts,
security lighting and CCTV surveillance. Parking is free
and available 24 hours, seven days a week.
Completed
Blacktown Interchange
- Transport Access
Program Upgrade
Blacktown Central City
District
Interchange Improvements to Blacktown interchange will include
extending the station concourse to allow for additional
ticket barriers and provide more space for better
passenger circulation.
In-Progress
Blacktown Road
cycleway
Blacktown Central City
District
Walking and Cycling Shared Path cycleway alongside Blacktown Road Completed
Blacktown Station Refresh Package 1
Blacktown Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Blaxcell Street Granville Central City Road The proposal is to raise the existing pedestrian crossing
on Blaxcell Street, immediately north of Thomas Street,
Granville. The project will include construction of a
wombat crossing with associated signs and line
markings, and realignment of the existi
Completed
Blaxland Interchange -
Commuter Parking
Blaxland Western City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Blaxland Interchange -
Transport Access
Program Upgrade
Blaxland Western City
District
Interchange New steel canopies were installed on the station platform
to provide better protection for customers against rain
and sun exposure.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Blaxland Road
cycleway
Ryde North District Walking and Cycling Shared Path cycleway alongside Blaxland Road Completed
Blaxland Station Refresh Package 3a
Blaxland North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Boambee Creek Boat
Ramp Upgrade, Coffs
Harbour
Toormina North Coast Maritime Upgrade of the Boambee Creek boat ramp. Works
include replacement of the old exisiting ramp with a new
precast concrete ramp and repairs to the upper section of
the ramp.
Planning
Boating Access
Improvements (New
Pontoons) at
Macksville
Macksville North Coast Maritime Improvements to boating infrastructure at River Street
Reserve, Macksville. Works include the upgrade to the
existing timber jetty (including the installation of a roof),
the installation of a new pontoon and gangway facility
west of the jetty, and access improvements from the site's
toilets to the jetty and new pontoon.
Planning
Boating Access
Improvements at
Willoughby’s
Beach, Murray Valley
Regional Park
Deniliquin Riverina Murray Maritime Construction of a single lane concrete boat ramp at
Willoughby's Beach for access to the Edward River for
small boats and non-powered watercraft (as this site is an
entry/exit point for the Edward River Canoe Trail). Other
works include the formalisation of a car park area at the
site.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Bobs Farm to Anna
Bay - Nelson Bay Road
Upgrade Stage 3
Bobs Farm Hunter Road Nelson Bay Road has been upgraded from Bobs Farm to
Anna Bay. Key features of the upgrade include provision
of a second carriageway between Cromarty Lane and
Port Stephens Drive roundabout, Anna Bay; rebuilding
the existing carriageway; landscaped median to separate
opposing traffic; ten upgraded bus bays; new u-turn
facilities to provide safe access to properties along the
route; pedestrian refuges in the median adjacent to bus
bays; wider shoulders; and improved intersections. The
upgrade has resulted in improved safety for motorists,
cyclists and pedestrians; better bays for bus passengers;
reduced traffic delays; and more reliable travel times for
motorists using this section of Nelson Bay Road.
Completed
Bohnock Boat Ramp
Facility Upgrade Bohnock Hunter Maritime Upgrade of the existing boat ramp facility at Bohnock.
Works include widening/extending the existing boat
ramp, the installation of an on-ramp centre pontoon,
extension and sealing of the car park, and the installation
of a fish cleaning table.
Planning
Bolivia Hill - New
England Highway
Upgrade
Bolivia New England North
West
Road Planning is underway to upgrade the New England
Highway at Bolivia Hill. The existing highway through
the area has narrow traffic lanes shoulders, with a rock
face on one side and a steep, rocky valley on the other.
The project involves building about 2.1 kilometres of
new road pavement, a new 320 metre long bridge that
avoids the creek line, 3.5 metre wide lanes in each
direction and widened road shoulders to improve safety.
Planning
Bomaderry (Nowra)
Interchange -
Commuter Parking
Bomaderry Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Bomaderry Station Refresh Package 2a
Bomaderry Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Bombo Interchange -
Commuter Parking
Bombo Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Bondi Junction Station Refresh Package 1
Bondi Junction Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Booth Street Annandale Eastern City Road Install illuminated pedestrian crossing signs at existing
Booth Street, Annandale raised pedestrian crossing.
Not Started
Bowling Alley Point
Boat Ramp Upgrade,
Chaffey Dam
Bowling Alley
Point
New England
North West
Maritime Planning
Bowral Interchange -
Commuter Parking
Bowral South East &
Tablelands
Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Bowral Station Refresh Package 4a
Bowral Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Bradwardine Road
cycleway
Windradyne Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Bradwardine Road Completed
Braidwood Truck Wash Upgrade
Braidwood South East and
Tablelands
Freight Install high pressure pump, upgrade lighting, upgrade fall on hardstand
Planning
Bridge Reserve Boat
Ramp Facility
Upgrade, Clarence
Town
Clarence Town Hunter Maritime Planning
Bridges for the Bush -
Program 2
Condobolin Central West &
Orana
Road Replacement of six heritage timber truss bridges (to
Higher Mass Limit standard) and upgrade of six heritage
timber truss bridges to provide ongoing safe service
levels. Addressing the state's deficient rural bridges is a
key priority for NSW investment as the bridges currently
present the most critical restrictions to freight access.
In-Progress
Brig O'Johnston Bridge
Upgrade - Bridges for
the Bush - Program 2
Clarence Town Hunter Road The bridge over the Williams River at Clarence Town
was built in 1880 and is the oldest surviving timber truss
bridge in NSW. Rehabilitation work is required to
strengthen the bridge to meet current vehicle loads and
heavy vehicle requirements, as well as help to reduce
future maintenance costs. The upgrade will improve road
freight productivity.
In-Progress
Briner Bridge Upgrade
- Bridges for the Bush -
Tranche 2
Ulmarra North Coast Road Briner Bridge, which was built in 1908, is a Dare truss
bridge located between the villages of Ulmarra and
Tucabia on Coldstream Terrace. The single span bridge
crosses the Upper Coldstream River and is one of six
operable Dare truss bridges and one of two single-span
Dare truss bridges in NSW. Planning is under way to
ensure the upgrade work preserves important heritage
aspects of the structure.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Bringelly Road
Upgrade Stage 1 -
Camden Valley Way to
King Street
Leppington Western City
District
Road The Bringelly Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney Airport at Badgerys
Creek. It will also improve safety, increase road capacity
and reduce congestion and travel times in the future. The
key features of Stage 1 include upgrading Bringelly
Road to a four lane divided road between Camden
Valley Way and King Street; east of the Upper Canal
bridge to Eastwood Road will be a six lane divided road;
an 80km/h speed limit and two metre wide shoulders;
three metre wide off-road shared pedestrian and cyclist
path; bus priority at traffic lights and indented bus bays;
extending the current noise wall on Cowpasture Road
240 metres along Camden Valley Way.
In-Progress
Bringelly Road
Upgrade Stage 2 - King
Street to The Northern
Road
Rossmore Western City
District
Road The Bringelly Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney Airport at Badgerys
Creek. It will also improve safety, increase road capacity
and reduce congestion and travel times in the future. The
key features of Stage 2 include upgrading from two lanes
to a four lane divided road with a central median, which
would allow for widening to six lanes, when required; a
speed limit of 80 km/h; a three metre wide off road
shared pedestrian and cyclist path with crossings at
traffic lights to improve safety; designated turning lanes
at traffic lights along with bus priority and indented bus
bays on both sides of Bringelly Road; new signalised
intersections; and new bridges over South Creek.
In-Progress
Brisbane Water Drive Tascott Central Coast Road Install kerbside barrier (southbound) to prevent vehicles
from running onto shared pedestrian/cycle path on
Brisbane Water Drive, Tascott.
Completed
Broadmeadow
Interchange -
Commuter Parking
Broadmeadow Hunter Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Broadmeadow
Interchange - Transport
Access Program
Upgrade
Broadmeadow Hunter Interchange The upgrade to Broadmeadow Station includes three new
lifts located at Platform 2/3, Brown Road entrance and
Graham Road entrance; new weather protection canopies
at the station entrances and on Platform 2;
reconfiguration of the station entrances on Brown Road
and Graham Road; upgraded security features including
lighting and CCTV camera surveillance; improved
wayfinding signage including tactile signage for vision
impaired station users; footpath upgrades in the vicinity
of the station entrances on Brown Road and Graham
Road; a new electrical substation on Brown Road; and
power upgrades.
In-Progress
Broadmeadow Station Refresh Package 1a
Broadmeadow Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Broken Hill Truckwash Facility
Broken Hill Far West Freight Construction of new truckwash (greenfield project) in broken Hill. The truck wash will be a one bay facility to cater for up to B-Double. It is drive- through truck wash and is able to cater for longer vehicles up to A triples..The project will consist of:1. Civil and siteworks - bitumising of site, installation of stormwater drainage and fencing2. Provision of directory signage3. Construction of roofing for truckwash facility4. Structure plumbing and drainage works5. Sewer reticulation works6. Electrical and communication works7. Pumping and control systems8. Installation of water recycling unit9. Construction and installation of truckwash bay10. Installation of wheelwash units11. AVData connection to site to ensure linkage to other truckwash facilities.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Brooklyn Waterfront
Master Plan
(Development)
Brooklyn North Maritime Planning
Broughton Street
cycleway
Concord Eastern City
District
Walking and Cycling Shared Path cycleway alongside Broughton Street Completed
Browns Creek Non-
powered Boating
Access Improvements,
Taree
Taree Hunter Maritime Provision of a small craft launch site into the sheltered
waters of Browns Creek for use by canoeist and
kayakers.
Planning
Brungle Road South Gundagai Riverina Murray Road Localised shoulder widening, W-beam Barrier,
delineation improvements
Completed
Brunswick Heads Boat
Harbour Master Plan
Development
Brunswick
Heads
North Coast Maritime Planning
Brunswick Street Boat
Ramp Upgrade, Ballina Ballina North Coast Maritime Installation of a pontoon at the existing boat ramp at
Riverview Park, Brunswick Street, Ballina. The project
also includes opportunities for investigation in to car
parking improvements at the site.
Planning
Brunswick Street
cycleway
Lismore Heights North Coast Walking and Cycling Shared Path cycleway alongside Brunswick Street Completed
Brushgrove Boat Ramp
and Car Park Upgrade
(Wingfield Bridge)
Cowper North Coast Maritime Replacement of the current boat ramp with a new boat
ramp; and
construction of a new car park adjoining the boat ramp
and pontoon.
Planning
Budd Park Pontoon
Upgrade,
Murwillumbah
South
Murwillumbah
North Coast Maritime Upgrade and relocation of the existing pontoon at Budd
Park to a more suitable location within the park.
Planning
Bulahdelah Bypass -
Pacific Highway
Upgrade
Bulahdelah Hunter Road The upgrade of the Pacific Highway at Bulahdelah
involved the construction of about 8.6 kilometres of four
lane divided road with an eastern bypass of the
Bulahdelah township.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Bullaburra, Ridge
Street to Genevieve
Road
Bullaburra Western City
District
Road The existing Great Western Highway was upgraded from
a two lane highway to a four lane divided highway from
west of Ridge Street, Lawson to 400 metres west of
Genevieve Road.
Completed
Bulli Interchange -
Commuter Parking
Bulli Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Bulli Road Toongabbie Central City Road Install pedestrian refuge island, street lighting, kerb and
gutter works on Bulli Road, East of Bungaree Road.
Completed
Bulli Station Refresh Package 4a
Bulli Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Burnett Street -
Ledger Road
cycleway
Merrylands Central City
District
Walking and Cycling Shared Path cycleway alongside Burnett Street -
Ledger Road
Completed
Burnum Burnum
Sanctuary Boat Ramp
Upgrade, Woronora
Woronora South Maritime Upgrade of the existing boat ramp and installation of a
new pontoon adjacent to the boat ramp at Burnum
Burnum Sanctuary, Woronora.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Burrill Lake Bridge -
Princes Highway
Upgrade
Burrill Lake Illawarra
Shoalhaven
Road Key features of the new bridge include a 290 metre long
bridge spanning the lake on a new alignment to the east
of the existing bridge; roundabouts on either side of the
crossing to connect the A1 Princes Highway to local
roads; a pedestrian and cycle path on the new bridge,
connecting to new paths on both sides and linking to the
Ulladulla cycle path; pedestrian paths underneath both
ends of the new bridge; the new bridge and highway
would be higher than the future 1 in 100 year flood level
and reduce the impact of flooding; complete removal of
the existing causeway and bridge; and a southern
foreshore park on the existing bridge approach.
In-Progress
Burwood Station Refresh Package 1
Burwood Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Bus Priority
Infrastructure Program
Parramatta Central City
District
Bus Projects are being delivered along Sydney's most
important bus routes that make bus services faster and
more reliable. Measures include red bus lanes, bus
priority at traffic lights, changed parking restrictions and
clearways, and relocating bus stops.
In-Progress
Cabarita Wharf -
Wharf Upgrade
Program
Cabarita Eastern City
District
Maritime The wharf upgrade will provide improved customer
amenity such as better protection from the wind, rain and
sun, seating and waiting areas; improved safety for
customers; improved access for mobility impaired
customers and customers with prams; quicker and more
efficient boarding and disembarking; increased wharf
capacity for future growth of ferry services; more
efficient interchanges with other modes of transport, both
public and private; and better way finding signage.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Cabramatta
Interchange -
Commuter Parking
Cabramatta Western City
District
Parking Conversion of existing staff car park to provide seven
extra commuter car parking spaces.
Completed
Camden Haven River
Recreational Boating
Facilities Study
(Investigation)
Dunbogan North Coast Maritime Funding to undertake a review of existing Council
managed boating facilities on the Camden Haven River.
The study is to include a condition assessment of
recreational boating infrastructure; community
consultation on existing facilities; review of population
and boating demand forecasts and identification of future
site upgrades and site redundancies.
Planning
Camden Street
cycleway
Wilton Western City
District
Walking and Cycling Shared Path cycleway alongside Camden Street Completed
Camden Valley Way
Upgrade
Leppington Western City
District
Road Camden Valley Way was upgraded between Oran Park
Drive and Bringelly Road. The key features of the
project included two lanes upgraded to a four lane
divided road; a posted vehicle speed limit of 80 km/h; a
three metre wide, off-road shared pedestrian/cyclist path
on the western side of the road; traffic lights at Forest
Lawn Memorial Gardens Cemetery, Cowpasture Road
South, Heath Road, St Andrews Road, Raby Road,
Catherine Field Road and Springfield Road; the
realignment of Denham Court Road and Ingleburn Road
to a four-way intersection with traffic lights; temporary
u-turn facilities located opposite traffic lights at the
intersections of Forest Lawn Memorial Gardens
Cemetery and St Andrews Road; new bridges; and bus
priority capability at traffic lights and indented bus bays
on each side of Camden Valley Way.
Completed
Campbelltown
Interchange -
Commuter Parking
Campbelltown Western City
District
Parking Conversion of existing staff car park to provide 154 extra
commuter car parking spaces.
Completed
Campbelltown
Interchange -
Commuter Parking
Campbelltown Western City
District
Parking Car park with an extra 450 parking spaces. In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Campbelltown Road,
Camden Valley Way to
Denham Court Road
Edmondson Park Western City
District
Road Planning and designing is underway for a proposed
upgrade of Campbelltown Road between Hume Highway
/ Camden Valley Way, Casula and Brooks Road,
Denham Court. Key features of the proposed upgrade
include an upgrade from a generally two lane to a four
lane divided road with a central median; a wide central
median which will allow room for widening to six lanes,
if required in the future, between The Hume Motorway
overbridge and Zouch Road; new signalised
intersections; an off-road shared pedestrian/cyclist path
generally on the western side of Campbelltown Road;
designated turning lanes and bicycle and pedestrian
crossing provisions at traffic lights; and an additional
bridge over the M31 Hume Motorway to allow for the
widening of Campbelltown Road. The construction
phase of the project will be undertaking in stages. The
first stage will be approximately 1.2 kilometre section
between from East Town Road Centre and to New
Macdonald Road.
Planning
Campsie Interchange -
Commuter Parking
Campsie South District Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Campsie Interchange -
Transport Access
Program Upgrade
Campsie South District Interchange Improvements to the transport interchange facilities at
Campsie Station included seating at the eastbound bus
stops on South Parade; improving bus stops on South
Parade for customer safety and comfort; improving
footpath pavements on route to and at the three on-street
commuter car parks; installing clear and direct way-
finding signage; and installing disabled car parking
spaces on North Parade, including lighting upgrades.
Completed
Canal Street
cycleway
Leeton Riverina - Murray Walking and Cycling Shared Path cycleway alongside Canal Street Completed
Name Suburb Region/District Project Type Project Description Current
Status
Canberra Station Refresh Package 1a
Kingston ACT Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Canley Vale
Interchange -
Commuter Parking
Canley Vale Western City
District
Parking New multi-storey commuter car park providing 122
commuter car parking spaces including a lift, stairs,
lighting and CCTV cameras.
Completed
Canley Vale
Interchange -
Commuter Parking
Canley Vale Western City
District
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Canley Vale
Interchange - Transport
Access Program
Upgrade
Canley Vale Western City
District
Interchange Improvements to accessibility at Canley Vale Station
included the construction of new accessible ramps on
both sides of the station, new stairs and bike racks on
both sides of the station, and improved safety through
additional CCTV surveillance cameras and lighting, new
tactiles on the platform, new handrails and signage.
Completed
Canley Vale Road Canley Heights Western City Road Upgrade existing raised pedestrian crossing west of
Ascot Street, Canley Heights to improve its accessibility
and safety of pedestrians. The works will ensure a flat
transition between footpath and the raised platform and
relocate the drainage lintel and
Not Started
Canley Vale Road
cycleway
Canley Heights Western City
District
Walking and Cycling Shared Path cycleway alongside Canley Vale Road Completed
Canley Vale Station Refresh Package 4
Canley Vale Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Captain Cook Bridge
South Boating Access
Improvements
(Investigation), Taren
Point
Taren Point South Maritime Passive craft launching facility including a jetty for both
passive craft and small vessel access. Upgrade to
foreshore and provision of a seating area and kayak
assembly point.
Planning
Captain Cook Park
Boating Facilities
Improvements
(Investigation), Ballina
Ballina North Coast Maritime Investigation into the installation of a new pontoon at
Captain Cook Park for short term boat mooring and
passenger exchange.
Planning
Cargo Movement
Coordination Centre
Botany Bay Eastern City
District
Rail The NSW Cargo Movement Coordination Centre is
working with industry to optimise how cargo moves
through Port Botany, Port Kembla and regional NSW
across supply chain interfaces and networks. It aims to
better coordinate the activities of operators across the
landside cargo transport chain – including stevedores,
road and rail freight operators, network operators and
terminals – to create a more efficient, higher performing
freight network which maximises existing capacity. The
centre is focused on the state-wide freight network; bulk
commodities (such as grain and coal) as well as
container freight; and key supply chain interfaces (ports,
road, rail and intermodal terminals). It will help towards
the target of doubling rail’s mode share of container
movements through NSW ports by 2020.
In-Progress
Caringbah Interchange
- Transport Access
Program Upgrade
Caringbah South District Interchange New steel canopies were installed on the station platform
to provide better protection for customers against rain
and sun exposure.
Completed
Caringbah Station Refresh Package 1
Caringbah Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Carlingford
Interchange -
Commuter Parking
Carlingford Central City
District
Parking Commuter car park providing up to 150 new spaces. Planning
Caroline Chisholm
Drive
Winston Hills Central City Road Install a refuge island in Caroline Chisolm Drive west of
Hilcrest Avenue, Winston Hills. The proposed works
includes conversion of an existing traffic island to a
refuge island, with upgrades of existing kerb ramps and
street lighting infrastructure.
Completed
Carramar Station Refresh Package 1
Carramar Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Carrington Boat Ramp
Facility Improvements
(Investigation)
Carrington Hunter Maritime Planning
Carrington Road
cycleway
Marrickville Eastern City
District
Walking and Cycling Bicycle Path cycleway alongside Carrington Road Completed
Cary Street Toronto Hunter Road Install pedestrian fencing Design Only
Completed
Casino Interchange -
Transport Access
Program Upgrade
Casino North Coast Interchange Construction of a new taxi rank and relocation of
existing car parking spaces.
Completed
Casino Station Refresh Package 2a
Casino Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Castle Hill -
Showground Road
Upgrade
Castle Hill Central City
District
Road Showground Road is being upgraded between Carrington
Road and Old Northern Road, Castle Hill from a two
lane to a four lane divided road to reduce congestion and
increase traffic capacity to meet predicted growth from
development in the area. Key features include widening
of Showground Road to at least four lanes between
Carrington Road and Old Northern Road with additional
turning lanes at key intersections; upgrading the
intersection of Showground Road and Pennant Street to
include additional turning lanes and a bus priority
measure; installing new traffic lights at the intersections
of Showground Road with Rowallan Avenue and
Cheriton Avenue; changing the intersection of
Showground Road and Britannia Road to left-in/left-out
access; installing a central concrete median with
landscaped planter bays at a number of locations along
the road; and providing a concrete footpath to both sides
of the road between Carrington Road and Pennant Street.
In-Progress
Cattai Ridge Road Glenorie Central City Road Install roadside w-beam barrier and and CAMS Completed
Name Suburb Region/District Project Type Project Description Current
Status
CBD and South East
Light Rail
Moore Park Eastern City
District
Light Rail The CBD and South East Light Rail is a new light rail
network for Sydney, currently under construction. The
12 kilometre route will feature 19 stops, extending from
Circular Quay along George Street to Central Station,
through Surry Hills to Moore Park, then to Kensington
and Kingsford via Anzac Parade, and Randwick via
Alison Road and High Street. Key features include high
frequency ‘turn up and go’ light rail services operating
every four minutes in the peak in the CBD, and every
eight minutes in the peak from Moore Park to Randwick
and Kensington; reliable and high-capacity services;
additional special event services between Central and the
Moore Park and Alison Road stops; a one-kilometre
pedestrian zone along George Street, between Hunter
and Bathurst Streets; and a fleet of electric-powered light
rail vehicles with air conditioning and accessible low-
floor design.
In-Progress
Centennial Park
cycleway
Woollahra Eastern City
District
Walking and Cycling Shared Path cycleway alongside Centennial Park Completed
Central Coast
Highway, Brisbane
Water Drive, Manns
Road Intersection
Upgrade
West Gosford Central Coast Road The upgrade provides a range of benefits for businesses,
motorists and the community, including: the newly
aligned intersection at Brisbane Water Drive and Manns
Road will substantially improve traffic flow and improve
access to local businesses; the Central Coast Highway
westbound exit ramp onto the newly constructed Grieve
Close underpass will provide improved access to local
businesses; the traffic lights at Manns Road and Grieve
Close intersection will provide access into Grieve Close
and the link road connecting to Dyer Crescent; improved
access to new developments including the Riverside
Park; urban design improvements will improve the visual
appeal and amenity in the commercial area; and shared
pedestrian and cycle paths along the Central Coast
Highway, Manns Road and Brisbane Water Drive will
improve connectivity to existing paths.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Central Coast
Highway, Carlton Road
to Ocean View Drive
Erina Heights Central Coast Road The upgrade of the Central Coast Highway between
Carlton Road, Erina Heights and Ocean View Drive,
Wamberal involved widening to two lanes in each
direction. The project improves safety for motorists,
cyclists and pedestrians; increases capacity to improve
traffic flow and reduce travel times and congestion;
improves access for public transport; and formalises
parking arrangements.
Completed
Central Coast
Highway, Frederick
Street Intersection
Upgrade
East Gosford Central Coast Road The upgrade involved road widening to provide a
dedicated right turn lane eastbound on the Central Coast
Highway (York Street) into Frederick Street (south) to
reduce queues during peak periods; extensions of the
shared pedestrian/cycle paths and pedestrian facilities on
the southern side of the intersection to Albany Street;
adjustments to traffic light phasing to allow extra time
for pedestrians to cross before traffic proceeds; and
stormwater drainage improvements and utility
relocations.
Completed
Central Coast
Highway, Racecourse
Road Intersection
Upgrade
West Gosford Central Coast Road The upgrade includes the following improvements:
providing a left turn lane with traffic light control on the
Central Coast Highway (eastbound) for vehicles turning
on to Racecourse Road. This will allow for an additional
through lane for motorists travelling east on the highway;
providing a left turn lane with traffic light control on
Racecourse Road (southbound) for vehicles turning onto
the Central Coast Highway. This will separate left
turning traffic from through and right turning traffic to
provide extra capacity for this leg of the intersection;
providing a new pedestrian crossing on the western leg
of the Central Coast Highway and installing pedestrian
traffic lights within the median on Racecourse Road
(southbound); and providing a 2.5 metre wide shared
path along the northern side of the Central Coast
Highway and extending along Racecourse Road to allow
cyclists and pedestrians to safety cross the road.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Central Coast
Highway, Wisemans
Ferry Road Intersection
Upgrade
Somersby Central Coast Road Key features of the upgrade include lengthening the
existing right turn lane and providing a second right turn
lane from the Central Coast Highway (from Gosford)
into Wisemans Ferry Road, to reduce queuing and
improve safety; providing an additional left turn lane
with both lanes under traffic light control from
Wisemans Ferry Road into the Central Coast Highway
(to Gosford), to improve safety by removing the need to
merge; providing a continuous lane on Wisemans Ferry
Road for southbound vehicles exiting the M1 Pacific
Motorway heading towards the Central Coast Highway
to improve safety by removing the need to merge;
providing a new right turn lane from Wisemans Ferry
Road onto the northbound on-ramp of the M1 Pacific
Motorway to improve safety by separating traffic
movements; providing a new car pool car park with
approximately 100 parking spaces; and providing an off
road cycle path between Wisemans Ferry Road and
Kangoo Road.
Completed
Central Interchange -
Transport Access
Program Upgrade
Haymarket Eastern City
District
Interchange Installation of lifts and construction of accessible ramps. Completed
Cessnock Road Weston Hunter Road Install raised island with additional give way sign and
move give way line forward using kerb extensions
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Charles Kay Drive and
Brunswick Road Safety
Improvements
Terrigal Central Coast Road The Terrigal Drive intersections at Charles Kay Drive
and Brunswick Road were improved to improve safety
and traffic flow along Terrigal Drive. Key features of the
upgrade include new traffic lights at the Charles Kay
Drive and Brunswick Road intersections; widening
Terrigal Drive between Duffys Road and Charles Kay
Drive to provide two through lanes in each direction and
additional left and right turn lanes out of Charles Kay
Drive; providing a shared pedestrian and cycle path on
the southern side of Terrigal Drive between Duffys Road
and Bellbird Avenue; and providing pedestrian traffic
lights east of Duffys Road to improve safety for
pedestrians crossing Terrigal Drive.
Completed
Charleyong Bridge
Replacement - Bridges
for the bush - Tranche
2
Tomboye South East and Tablelands
Road The Charleyong Bridge is a single-span Allen truss
timber bridge built in 1901, which crosses the
Mongarlowe River at Marlowe. The bridge is located
on Main Road 92 connecting Braidwood and Nowra via
Nerriga, which is a regionally important link for goods,
quarried material and stock between Nowra, Braidwood
and Canberra. The bridge is proposed to be replaced as
it does not meet current loading standards and has
become increasingly expensive to maintain.
Replacement of the bridge would greatly improve
regional and local freight route continuity and allow
Higher Mass Limit Vehicles to use the road.
Planning
Chatham Road Eastwood North Road Install high friction surface, CAMs and RRPMs Completed
Chester Hill Station Refresh Package 1
Chester Hill Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Chiswick Wharf -
Wharf Upgrade
Program
Chiswick Eastern City
District
Maritime The wharf upgrade will provide improved customer
amenity such as better protection from the wind, rain and
sun, seating and waiting areas; improved safety for
customers; improved access for mobility impaired
customers and customers with prams; quicker and more
efficient boarding and disembarking; increased wharf
capacity for future growth of ferry services; more
efficient interchanges with other modes of transport, both
public and private; and better way finding signage.
In-Progress
Church Point
Commuter Wharf
Expansion, Pittwater
Church Point North Maritime Expansion of the existing commuter wharf at Church
Point with the addition of two new finger pontoon
sections to provide an additional 34 boat tie up spaces for
off shore commuters boats.
Planning
Church Street Singleton Hunter Road Raised intersection thresholds, side road closure, signs,
line marking
Completed
Church Street Parramatta Central City Road Install pedestrian fencing and refuge Completed
Clarence River Canoe
and Kayak Trail
Access Improvements
Harwood North Coast Maritime Investigation to determine options for locations for
lauching facilties - Various locations shall be assessed.
Planning
Clarendon Interchange
- Transport Access
Program Upgrade
Clarendon Western City
District
Interchange Improvements to accessibility at Clarendon Station
included the construction of a new accessible ramp and
new stairs, and improved safety through the installation
of additional CCTV surveillance cameras and lighting.
Completed
Clarrie Purnell Park
Boat Ramp Upgrade,
Condong
Condong North Coast Maritime Improvements to the boat ramp facility at Clarrie Purnell
Park, Condong. Works include river bank stabilisation
and installation of a new public toilet facility at the site.
Planning
Cleopatra Drive
cycleway
Rosemeadow Western City
District
Walking and Cycling Shared Path cycleway alongside Cleopatra Drive Completed
Name Suburb Region/District Project Type Project Description Current
Status
Clyde Street South Granville Central City Road Raise the existing pedestrian crossing in Clyde Street
between Dellwood Street and Bennet Street, South
Granville. The project will include construction of a
wombat crossing, with refuge island and realignment of
the existing kerb and gutter.
Completed
Cobar Wash Bay Facility
Cobar Far West Freight -Single Wash Bay Ramp with capacity to accommodate Road Train (Road Train -Length [36.5m + 3m wash down area ] approx. 40 metre pad length Minimum 7.5% -- Maximum 10 % with 1% lean to a side) -Waiting area for another Road Train-Security fences-Wash bay equipment -Ponding system ( sediment and evaporation)-Automated charging for usage (AV data system)-Lighting (LED Front & back or both sides Sensor on arrival at night)
Planning
Cobb Highway, New
Bridge at Echuca-
Moama - Bridges for
the Bush - Program 1
Moama Riverina - Murray Road The Echuca-Moama bridge crossing would consist of a
new road with a bridge across the Murray River in NSW
and a bridge across the Campaspe River in Victoria. It
would connect the Cobb Highway in Moama to the
Murray Valley Highway at Echuca, along a distance of
about 4.1 kilometres. The existing bridge would continue
to operate.
Planning
Cockatoo Island Wharf
- Wharf Upgrade
Program
Woolwich North District Maritime The wharf upgrade will provide improved customer
amenity such as better protection from the wind, rain and
sun, seating and waiting areas; improved safety for
customers; improved access for mobility impaired
customers and customers with prams; quicker and more
efficient boarding and disembarking; increased wharf
capacity for future growth of ferry services; more
efficient interchanges with other modes of transport, both
public and private; and better way finding signage.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Coffs Harbour Bypass -
Pacific Highway
Upgrade
Coffs Harbour North Coast Road The project will provide a bypass of the commercial
districts of Coffs Harbour. It is proposed to extend from
south of Englands Road to Sapphire Beach. The concept
design, now under review, includes the possibility of
three tunnels through the steep ridges to the west of
Coffs Harbour; structures to pass over local roads and
creeks as well as a viaduct over the North Coast
Railway; and upgrading parts of the local road network
to enable local connections across and around the Pacific
Highway alignment. The bypass will provide travel time
savings for through and local traffic, and the transport
industry; improved road safety conditions for traffic,
pedestrians and cyclists using the existing highway
through Coffs Harbour; improved freight efficiency; and
improved accessibility to the Coffs Harbour CBD.
Planning
Coffs Harbour Station Refresh Package 2a
Coffs Harbour Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Colo Park Non-
powered Boating
Access, Colo
Colo West Maritime Construction of a non-powered boat launching facility at
Colo Park, Colo. This site is a destination on the
Hawkesbury Canoe and Kayak Trail.
Planning
Colongra Bay Boat
Ramp Car Park
Upgrade, Lake
Munmorah
Lake Munmorah Central Coast Maritime Upgrade parking. Planning
Combe Road Griffith Riverina Murray Road Seal unsealed section, realignment, shoulder widening,
delineation.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Commercial Road Boat
Ramp Improvements,
Murwillumbah
Murwillumbah North Coast Maritime Upgrade of the car park and stabilisation of the river
bank at the Commercial Road boat ramp, Murwillumbah.
Works include reprofiling of the river bank and car park
surface to better manage drainage at the site.
Planning
Coniston Interchange -
Commuter Parking
Coniston Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Connell Road Boat
Ramp Upgrade, Oyster
Bay
Oyster Bay South Maritime Planning
Cook Park cycleway Sans Souci Eastern City
District
Walking and Cycling Shared Path cycleway alongside Cook Park Completed
Coolamon Scenic
Drive
Mullumbimby North Coast Road Shoulder widening, CAMs, guideposts Completed
Coomal Avenue
cycleway
Davistown Central Coast Walking and Cycling Shared Path cycleway alongside Coomal Avenue Completed
Coomba Boating
Access Improvements,
Wallis Lake
Coomba Park Hunter Maritime Planning
Cootamundra Saleyards- Truckwash
Cootamundra Riverina Murray Freight To improve the existing truck wash facilities by increasing the size of the wash bay to cater for two B-doubles, improving the efficiency and capacity of the catchment and treatment of the effluent and generally improve access and truck turning movements via sealed access/egress from the facilities.
Planning
Coramba Road Karangi North Coast Road Install RRPMs, CAMS, roadside w-beam barrier, seal
shoulders and upgrade seal
Not Started
Corrimal Interchange -
Commuter Parking
Corrimal Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Corrimal Station Refresh Package 4a
Corrimal Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Country Rail Network
Maintenance Works -
Resleepering
Condobolin Central West &
Orana
Rail The Country Regional Network (CRN) is owned by
Transport for NSW and is operated and maintained by
our rail infrastructure manager, John Holland Rail, under
a 10-year contract that commenced in January 2012. The
CRN links broad areas of regional NSW to interstate and
metropolitan rail systems and in addition supports,
customers transporting coal, grain, cotton, minerals and
containerised freight to domestic and export markets.
In-Progress
Coward Street
cycleway
Mascot Eastern City
District
Walking and Cycling Shared Path cycleway alongside Coward Street Completed
Cowra Breakout
Track cycleway
Cowra Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Cowra Breakout
Track
Completed
Creek Reserve Road
cycleway
Boolaroo Hunter Walking and Cycling Shared Path cycleway alongside Creek Reserve
Road
Completed
Cremorne Point Wharf
- Wharf Upgrade
Program
Cremorne Point North District Maritime The new wharf includes a steel floating pontoon, a
covered concrete fixed entry platform and a covered
aluminium gangway connecting the entry platform to the
pontoon. The pontoon has a curved roof, glass panels
and new seating offering some protection from the
weather and improved amenity. The new wharf provides:
better protection from the wind, rain and sun; improved
safety for customers; mproved access for mobility
impaired customers and customers with prams; and
quicker and more efficient boarding and disembarking.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Croki Boat Ramp
Improvements
(Investigation)
Croki Hunter Maritime Construction of a new gravel boat ramp at Croki. Works
include the purchase and subdivision of land, site survey
and design, and construction of the new boat ramp and
car park.
Planning
Cromer Golf Club
cycleway
Narrabeen North District Walking and Cycling Shared Path cycleway alongside Cromer Golf Club Completed
Cronulla Interchange -
Commuter Parking
Cronulla South District Parking Conversion of existing staff car park to provide 12 extra
commuter car parking spaces.
Completed
Crookwell Bridge
Replacement – Bridges
for the Bush - Program
2
Binda South East &
Tablelands
Road The replacement bridge is a three span 39.37 metre long
pre-cast concrete plank bridge located approximately 15
metres downstream from the existing bridge. It was
designed and built to meet current bridge standards. The
new bridge provides one travel lane in each direction,
two metre shoulders to allow for cyclists, upgraded road
approaches, improved safety and improves the capacity
of the NSW freight network as it carries Higher Mass
Limit vehicles.
Completed
Cross Street
cycleway
Doonside Central City
District
Walking and Cycling Shared Path cycleway alongside Cross Street Completed
Croydon Interchange -
Transport Access
Program Upgrade
Croydon Eastern City
District
Interchange The upgrade will include three new lifts; a new station
concourse and pedestrian footbridge; improved shelter;
new bicycle racks; and upgrades to lighting and security
cameras. The upgrade will connect the new station
operations building at Paisley Road to a new station
entrance at Hennessy Street through a wider pedestrian
bridge, which will also have new stairs and three lifts to
access the station platforms. There will also be
interchange upgrades including additional kiss and ride
spaces and accessible parking spaces. Other facilities
include a new family accessible toilet and new weather
protection canopies along the pedestrian bridge, stairs
and lift landings.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Cudgegong River
cycleway
Mudgee Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Cudgegong River Completed
Culcairn Holbrook
Road
Morven Riverina Murray Road Widen and realign road, widen shoulders and clear zone
including tree removal & small land acquisition. NB
high pressure gas main close to road
Completed
Dangar Island
Commuter Access
Improvements
(Investigation),
Hawkesbury River
Brooklyn North Maritime Investigation into an improved commuter access facility
at Dangar Island.
Planning
Dapto Interchange -
Commuter Parking
Dapto Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Dapto Interchange -
Transport Access
Program Upgrade
Dapto Illawarra
Shoalhaven
Interchange The improvements to the transport interchange facilities
and access at Dapto Station included redesigning and
rebuilding the ramp on the eastern side of the station to
make it wheelchair accessible; installing clear signage, as
well as provide more bus route and timetable
information; providing new seating in the taxi and bus
zones; constructing a safer bus access road; improving
lighting in and around the station, bus interchange and
taxi zone; and upgrading footpaths around the station.
Completed
Dapto Station Refresh Package 1a
Dapto Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Dareton Boat Ramp
Car Park & Access
Road Upgrade
Dareton Far West Maritime Planning
Name Suburb Region/District Project Type Project Description Current
Status
Davy Robinson
Reserve Car Park &
Seawall Upgrade,
Moorebank
Moorebank South West Maritime Upgrade of the existing failed seawall and
reconfiguration and sealing of the car park at the Davy
Robinson Reserve boat ramp.
Planning
Dee Why / Warringah
Mall Interchanges -
Transport Access
Program Upgrade
Brookvale North District Interchange Dee Why / Warringah Mall bus interchange upgrades
that include accessibility, pedestrian and cyclist
improvements.
Completed
Deep Creek Boat Ramp
and Car Park Upgrade Nambucca
Heads
North Coast Maritime Upgrade of the Deep Creek boat ramp at Valla Beach.
Works include reconstruction of the existing damaged
single lane boat ramp with a new concrete ramp, access
improvements and protection to vegetation and
installation of new interpretive signage at the ramp.
Planning
Devils Pulpit - Pacific
Highway Upgrade
Jacky Bulbin Flat North Coast Road The 7.3 kilometre Devils Pulpit section of the Pacific
Highway has been upgraded. Key features of the upgrade
include four lane divided highway, improvements to
property access; construction of bridges over
Tabbimoble floodways; and overhead rope crossings for
glider and other animal species.
Completed
Digital Train Radio
System
Haymarket Eastern City
District
Rail A Digital Train Radio System (DTRS) is being installed
throughout the 1,455 kilometre electrified rail network
bounded by Kiama, Macarthur, Lithgow, Bondi Junction
and Wickham. The DTRS will ensure that train drivers,
train controllers, signallers and train guards on the
electrified rail network are able to communicate with
each other using the same system with the same
technology. Replacing the existing analogue train radio
system with DTRS will fulfil recommendations from the
Special Commission of Inquiry into the Waterfall Rail
Accident to provide a common platform of
communication for staff working on the railway.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Dignams Creek –
Princes Highway
Upgrade
Dignams Creek South East &
Tablelands
Road The Princes Highway at Dignams Creek, around 20km
south of Narooma, will be upgraded. Key features of the
upgrade include building a new section of highway to
current road design standards; building a new bridge
over Dignams Creek to replace the existing bridge;
relocating the intersection of Dignams Creek Road and
the Princes Highway; upgrading the existing southbound
overtaking lane; and revegetation of the existing Princes
Highway. Benefits of the upgrade include increased road
safety by improving road alignment; increased road
safety at the Dignams Creek Road intersection; reduced
vehicle carbon emissions by improving grades and
curves; improved travel times for motorists on the
Princes Highway and safer crossings for local animals.
In-Progress
Dinghy Storage Across
North Harbour
(Investigation)
Balgowlah North Maritime Provide formal dry storage for dinghies & kayaks.
Provide walkway and floating pontoon to provide public
access to North Harbour.
Planning
Dinghy Storage Across
the Gosford LGA Gosford Central Coast Maritime Installation of dinghy storage at key locations in Gosford
LGA.
Planning
Dinghy Storage Across
the Lake Macquarie
LGA
Lake Macquarie Central Coast Maritime To provide dinghy storage racks at three sites being,
Swansea, Balmoral and Marmong Point.
Planning
Dinghy Storage and
Launching Facility at
Pindimar/Bundabah,
Port Stephens
Port Stephens Hunter Maritime Installation of new dinghy launching and storage
facilities.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Doonside Station Refresh Package 4
Doonside Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Dora Street Morisset Hunter Road Install mid-block traffic signals south of existing zebra
crossing, remove zebra crossing
Not Started
Drummoyne Wharf -
Wharf Upgrade
Program
Drummoyne Eastern City
District
Maritime The new wharf comprises a steel floating pontoon, a
small concrete fixed entry platform and an aluminium
gangway connecting the entry platform to the pontoon.
The pontoon has a curved roof, glass panels and new
seating offering some protection from the weather and
improved amenity. Removal of the tidal steps provides
improved safety and accessibility as well as improving
efficiency. The new wharf provides improved protection
from the wind, rain and sun; safety for passengers;
access for passengers using mobility aids; access for
passengers with prams; and boarding and disembarking
efficiency.
Completed
Dubbo Rail Triangle
Upgrade
Dubbo Central West &
Orana
Rail Improving access for trains travelling to the north, south
and west of the state that use this busy central junction
point.
Completed
Duckmaloi Road Duckmaloi Central West and
Orana
Road Install shoulder from no shoulder, install curve alignment
markers & road narrow signage
Completed
Dungog Interchange -
Transport Access
Program Upgrade
Dungog Hunter Interchange Upgrading access ramps, including two new access
ramps, lighting upgrades to the existing pedestrian
walkway across the train tracks and CCTV surveillance.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Dunmore Bridge -
Bridges for the Bush -
Program 2
Woodville Hunter Road The structural capacity of Dunmore Bridge has been
upgraded to meet current load requirements and reduce
future maintenance costs. Key features include
reconstructing and upgrading of all three timber truss
spans, including new stress laminated timber decks and
traffic barriers; replacing the approach span and its
abutment, which included driving steel piles and
installing new concrete timber composite deck units;
upgrading the deck and traffic barriers at the lift span to
tie in with the upgraded truss spans; and upgrading the
road approaches and traffic barriers.
Completed
East Hills Interchange -
Commuter Parking
East Hills South District Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
East Richmond
Interchange -
Commuter Parking
Richmond Western City
District
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
East Wardell Boat
Ramp New Pontoon East Wardell North Coast Maritime Installation of a pontoon and walkway at the existing
boat ramp at East Wardell.
Planning
Eastwood Interchange -
Commuter Parking
Eastwood North District Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Eastwood Interchange -
Commuter Parking
Eastwood North District Parking New multi-storey car park on Rowe Street will include
230 new commuter spaces, and lighting and CCTV to
boost security.
In-Progress
Eastwood Station Refresh Package 2
Eastwood Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Edgecliff Interchange -
Transport Access
Program Upgrade
Edgecliff Eastern City
District
Interchange Improvements are planned to provide easier access to
public transport. Facilities being considered include lift
access to the platform, new ‘kiss and ride’ facilities with
seating and shelter and improved bus interchange
facilities.
Planning
Edward Street
cycleway
Moree New England
North West
Walking and Cycling Shared Path cycleway alongside Edward Street Completed
Elizabeth Drive
cycleway
Liverpool Western City
District
Walking and Cycling Shared Path cycleway alongside Elizabeth Drive Completed
Ellerton Drive
Extension
Karabar South East &
Tablelands
Road The extension would connect east Queanbeyan, where
the existing Ellerton Drive ends, with Karabar at the new
Edwin Land Parkway intersection with Old Cooma
Road. The 4.6km extension would provide an alternative
route around the central business district and connect
east and west Queanbeyan to the new southern
population growth areas. Queanbeyan’s population is
expected to grow to 56,000 by 2031 with Tralee and
Googong developments underway. The proposed
Ellerton Drive Extension would minimise the impact of
this expected population growth on traffic congestion.
Without the proposed extension increased congestion is
predicted along Cooma Street and across the Queens
Bridge. Project benefits include motorists avoiding up to
19 intersections and two sets of traffic lights; up to a
38% travel time saving compared to the existing route;
the route would avoid the 50km/h sections of
Queanbeyan central business district as well as school
zones; and reduced congestion in Queanbeyan.
Planning
Emigrant Creek
Boating Access
Improvements
(Investigation), West
Ballina
West Ballina North Coast Maritime Investigation study to assess the feasibility of dredging a
section of Emigrant Creek to provide improved access to
the commercial marine precinct on Smith Drive, Ballina.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Empire Bay Drive Empire Bay Central Coast Road Install roundabout Not Started
Endeavour Park Boat
Ramp Facility
Improvements, Taree
Taree Hunter Maritime Upgrade of the Endeavour Park boat ramp facility,
Taree. Works include extension of the existing boat
ramp, resealing the existing car park, and the
construction of a new amenities facility (to replace the
existing ageing toilet block).
Planning
Enfield Intermodal
Terminal
Greenacre Eastern City
District
Freight The Intermodal Logistics Centre (ILC) at Enfield is part
of a network of existing and planned intermodal terminal
facilities in Sydney. In doing so, it will mitigate the
growth in freight truck numbers on our roads.
Completed
Engadine interchange -
Commuter Parking
Engadine South District Parking A new 78 space commuter car park is being built along
the Princes Highway (southbound). Four accessible
parking spaces within the existing car park near the
station will be provided. Lighting and CCTV
surveillance is also being improved.
In-Progress
Epping Interchange -
Transport Access
Program Upgrade
Epping Central City
District
Interchange The improvements to the transport interchange facilities
at Epping Station included upgrading the footpath on the
western side of Beecroft Road (north of Epping Hotel);
upgrading road, pavement, kerb and guttering; and
installing a new bench seat at the existing bus stop on the
western side of Beecroft Road.
Completed
Epping Station Refresh Package 2
Epping Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Epping to Thornleigh
Third Track
Beecroft North District Rail The project involved the construction of six kilometres
of new and upgraded track within the rail corridor
between Epping and Thornleigh stations on the western
side of the existing tracks. The new (third) track
separates northbound freight from all-stops passenger
train movements along the steep incline between Epping
and Thornleigh. This will help provide additional
capacity for northbound (interstate container) freight
trains, particularly during the daytime when passenger
trains currently have priority. This project is part of the
Northern Sydney Freight Corridor Program, which is an
initiative to improve the capacity and reliability of
freight trains between Strathfield and Broadmeadow,
Newcastle. The program will increase capacity for
interstate container freight and remove the most serious
bottleneck on the East Coast interstate, which connects
Australia’s three largest cities (Melbourne, Sydney and
Brisbane).
Completed
Epping Town Centre
Road Upgrades
Epping Central City
District
Road Road and intersection upgrades in Epping Town Centre
are being planned to support the NSW Government's
Urban Activation Precinct Program. The road projects
aim to improve traffic flows and road safety and reduce
congestion. The projects include upgrading the Beecroft
Road and Carlingford Road intersection; and widening
Epping Road westbound between Blaxland Road and
Essex Street, including the upgrade of the intersection at
Epping Road and Essex Street. These projects aim to
improve traffic flow and road safety, and help reduce
traffic delays and congestion.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Erskine Park Link
Road
Eastern Creek Central City
District
Road The road upgrade provides a connection between Lenore
Lane at Erskine Park and Old Wallgrove Road at Eastern
Creek with a 3.1 kilometre four lane divided road;
provides a vital link between the Western Sydney
Employment Area and the M4 and M7 Motorways;
reinforces the Western Sydney Employment Area as a
significant employment hub; reduces industrial traffic on
the existing Erskine Park Road and adjoining local roads;
improves traffic flow in Western Sydney with direct
connections to and from the M7 Motorway; provides a
new shared cycle/pedestrian path; and reduces transport
costs for industry located in the Western Sydney
Employment Area.
Completed
Euston Reserve Boat
Ramp Pontoon, Euston Euston Far West Maritime Upgrade of the boat ramp facility at Euston Reserve.
Works include widening the existing single lane boat
ramp by 3m (on the upstream side) making it a two lane
ramp, installation of two 8m pontoon/gangway structures
(one each side of the boat ramp) and minor landscaping.
Planning
F6 Extension Kirrawee South District Road A study is being undertaken into developing a possible
link between the M1 Princes Motorway at Waterfall and
the Sydney Motorway Network. At present there is no
efficient connection between the M1 Princes Motorway
and Sydney’s broader motorway network from north to
south. Along the Princes Highway between Tom Ugly’s
Bridge and St Peters there are 42 sets of traffic lights and
a further 18 sets of lights between Tom Ugly’s Bridge
and Loftus. Congestion along this route is significant in
peak times. Similarly, motorists using The Grand Parade
also regularly experience heavy traffic through this busy
corridor.
Planning
Fairfield Interchange -
Commuter Parking
Fairfield Western City
District
Parking Construction of new commuter car park providing 57
commuter car parking spaces.
Completed
Fairfield Interchange -
Commuter Parking
Fairfield Western City
District
Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Fairfield Interchange -
Transport Access
Program Upgrade
Fairfield Western City
District
Interchange The improvements to the Fairfield transport interchange
included reconfiguring the bus interchange into the
commuter car park previously at the intersection of The
Crescent and Court Road; formalising the kiss and ride
zone on the westbound lane of The Crescent; relocating
the taxi rank to the eastbound lane at the western end of
The Crescent; aligning the exit point of the bus
interchange with the Smart Street intersection; relocating
the signalised pedestrian crossing and creating a new
zebra pedestrian crossing on The Crescent; relocating
timed and commuter parking on both sides of Fairfield
Station, including replacement car parking at Wilga
Street; improving the streetscape on The Crescent and
throughout the bus interchange, including new paving,
street furniture, landscaping and wayfinding signage;
extending the station forecourt to incorporate the historic
crane previously located in the bus interchange; and
upgrading CCTV camera surveillance.
Completed
Fairy Meadow
Interchange -
Commuter Parking
Fairy Meadow Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Fassifern Interchange -
Commuter Parking
Fassifern Hunter Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Fassifern Station Refresh Package 1a
Fassifern Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Faulks Reserve Boat
Ramp New Pontoon,
West Ballina
West Ballina North Coast Maritime Installation of a pontoon at the existing boat ramp at
Faulks Reserve, West Ballina. The project also includes
investigating car park improvements to improve vehicle
manouevring.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Federal Highway Bywong South East and
Tablelands
Road Vegetation clearing on Bungendore Road on approach to
Federal Highway for greater sight distance, Junction
lighting, Install concrete median at throat of Bungendore
Road and move hold line forward (treatment 26 used to
represent this), Install rumble bar
Completed
Federal Highway Wollogorang South East and
Tablelands
Road Provide appropriate super elevation Completed
Ferry Fleet
Replacement
Sydney Eastern City
District
Maritime The first stage of upgrading the fleet is an investment in
six new ferries, with the first vessel on the water in late
2016. The rest will be delivered progressively throughout
2017. The new ferries will service routes in the Inner
Harbour from Watsons Bay in the east to Cockatoo
Island in the west, and use new wharves such as
Barangaroo. The next stage in modernising the fleet as
part of an overall ferry fleet strategy is developing a new
style ferry for the Parramatta River. This work is
underway. The new Inner Harbour ferries will each carry
up to 400 passengers, and be designed to be easily
accessible for less mobile passengers and young families.
There will be 12 spaces for passengers using
wheelchairs. They will be spacious, with an open plan
layout, provide more seating and ensure rapid and safe
boarding. Features will include two wide walk-around
decks, bicycle and luggage storage areas, wi-fi access
and real time journey information.
In-Progress
Fingal Boat Harbour
Pontoon Upgrade,
Fingal Head
Fingal Head North Coast Maritime Replacement of the existing pontoon with a new pontoon
at the Fingal Boat Harbour boat ramp. The repositioned
new pontoon will provide disability access and assist
with Sailability.
Planning
Fishermans Reach Boat
Ramp Upgrade Fishermans
Reach
North Coast Maritime Upgrade of access to the Fishermans Reach boat ramp.
Works include the sealing the existing dirt access
approach to the ramp, the ramp manouevring area and
closure of the site's secondary access road.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Fishery Creek Boat
Ramp Pontoon
Upgrade, Ballina
West Ballina North Coast Maritime Installation of an additional pontoon and walkway to the
existing southern pontoon at Fishery Creek Boat Ramp,
Ballina.
Planning
Fitzgerald Bridge at
Aberdeen
Aberdeen Hunter Road The new bridge allows access for higher mass limit
vehicles between Muswellbrook and Tamworth, which
will increase productivity of road freight transport. Key
features include a new bridge and road approaches;
upgraded intersections of the New England Highway at
Blairemore Lane, Hall Street and the Aberdeen Bowling
Club entrance; the existing southbound heritage bridge
has been retained for pedestrians and cyclists; increased
flooding clearance; and a new concrete pathway under
the bridges to link the western side of the bridges to the
old southbound bridge for pedestrian and cyclist access.
Completed
Fixing Country Rail
Pilot Program
Condobolin Central West &
Orana
Freight Fixing Country Rail is a program to fund rail
infrastructure enhancement projects that eliminate
connectivity constraints on the NSW regional rail
network and reduce the cost to market for regional
businesses. It is designed to complement Fixing Country
Roads to build an efficient freight transport network in
regional NSW. Projects funded under Fixing Country
Rail could include sidings, passing loops, overtaking
lanes, and network enhancements that allow the use of
faster, longer and heavier trains.
In-Progress
Fixing Country Rail
Pilot Program -
Installation of a New
Turnout at the Centre
of Dunmore Loop at
Shellharbour
Dunmore Illawarra
Shoalhaven
Freight Additional line capacity and operating efficiency. Planning
Fixing Country Rail
Pilot Program -
Installation of a New
Turnout at Unanderra
Unanderra Illawarra
Shoalhaven
Freight Additional line capacity and operating efficiency. Planning
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Rail
Pilot Program - New
Crossing Loop near
Tarago
Tarago South East &
Tablelands
Freight Additional line capacity and will allow longer trains. Planning
Fixing Country Rail
Pilot Program - Rail
Siding Extension -
Barellan
Barellan Riverina - Murray Freight Reduced shunting and faster train loading. Projected
saving of $6 per tonne in freight costs to port.
In-Progress
Fixing Country Rail
Pilot Program - Rail
Siding Extension -
Burren Junction
Burren Junction Far West Freight Reduced shunting and faster train loading. Projected
saving of $6 per tonne in freight costs to port.
In-Progress
Fixing Country Rail
Pilot Program - Rail
Siding Extension -
Hillston
Hillston Riverina - Murray Freight Reduced shunting and faster train loading. Projected
saving of $6 per tonne in freight costs to port.
In-Progress
Fixing Country Rail
Pilot Program - Rail
Siding Upgrade at the
Canberra Railway
Freight Terminal
(Fyshwick)
Queanbeyan West South East &
Tablelands
Freight Restarts freight services between Canberra and Port
Botany.
Shifts export containers to rail (300 B-Doubles per
annum to start)
In-Progress
Fixing Country Rail
Pilot Program -
Reinstatement of a
2.8km Section of
Moree to Inverell
Railway Line
Gravesend New England North
West
Freight The project will shift 250,000 tonnes of grain and 6,400
cargo boxes of cotton and pulses from road to rail.
Projected savings of $25/tonne in freight costs from
Moree to Port of Newcastle.
In-Progress
Fixing Country Rail
Pilot Program -
Reinstatement of the
Maimuru to
Demondrille Railway
Line
Kingsvale South East &
Tablelands
Freight Will provide a connection to the Main South Line,
improving rail network access for grain producers,
mining and containerised transport industries. It will
result in cheaper and more efficient transport for
producers.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Rail
Pilot Program -
Reinstatement of the
Non-Operational Line
from West Tamworth
to Westdale
Taminda New England North
West
Freight Connecting a growing industrial precint to the rail
network.
Planning
Fixing Country Road
Round 1 - Abington
Creek Bridge
Abington New England North
West
Freight Abington Creek bridge is a vital link on an important
connection between the North West and New England
Highway. A new bridge would generate good economic
benefits and create a more reliable route for the livestock
industry.
In-Progress
Fixing Country Road
Round 1 - Accelerated
Timber Bridge
Replacement Program
Mellool Riverina - Murray Freight Replacement of the three bridges mentioned in the
application would lead to improved access to 12,000 Ha
of properties, and result in fewer vehicle trips by
allowing the use of higher productivity vehicles currently
not able to use the existing load limited bridges.
Completed
Fixing Country Road
Round 1 - Acres
Billabong Tilpa
Tilpa Far West Freight Acres Billabong Tilpa is an important access road for
local producers, but access is severely limited during
flood events. Upgrading the road to allow better passage
of flood waters will generate strong economic benefits,
assuming flood events every 6-10 years.
In-Progress
Fixing Country Road
Round 1 - Ardlethan
Grain Hub
Barellan Riverina - Murray Freight Project permits HML access to the Ardlethan Grain Hub
from the State and local road network and has the
potential to reduce heavy vehicle movements by up to
11%. This is a strategically important site that both
GrainCorp and Emerald Grain have made significant
recent investments in. Supports State Government
investment in siding extensions at the site to be
commissioned in the current financial year.
Completed
Fixing Country Road
Round 1 - Beaconsfield
and Sewell's Creek
Road Upgrade
Essington Central West &
Orana
Freight Project generates positive economic benefits and
facilitates the use of more environmentally friendly 23m
B-doubles rather than existing 19m B-doubles used to
transport logs on the route. Contrary to the EOI, Council
is now providing 10% co-funding for the project.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Bergen
Bridge Widening
Walcha New England North
West
Freight Would open up the section between Uralla and Walcha
to HML B-doubles and provide for a wider, safer bridge.
Project has significant sources of additional co-funding,
both from Council and, potentially, the Australian
Government.
In-Progress
Fixing Country Road
Round 1 - Boree Creek
Freight Link
Boree Creek Riverina - Murray Freight With a grain receival site in Lockhart closing, Boree
Creek will gain in importance. Upgrading road access
into the site will generate strong economic and
productivity gains for local grain producers. Although
council contribution is low, this upgrade benefits a large
number of producers in the region and neighbouring
Shires.
Completed
Fixing Country Road
Round 1 - Box Creek
Bridge Replacement at
Chainage 26.424 on
Pretty Pine Road
Barratta Riverina - Murray Freight Project generates a high BCR, primarily as a result of
improved access for heavy vehicles. This is particularly
important as Pretty Pine Road is used as a diversion
when there is an incident on the Sturt Highway. The
assumptions and claims in the application appear
reasonable and the project is supported by both industry
and council co-contributions.
In-Progress
Fixing Country Road
Round 1 -
Bulgandramine Timber
Bridge Replacement
Peak Hill Central West &
Orana
Freight Project generates strong economic and productivity
benefits by upgrading Narromine and Parkes Shire
Council’s last timber bridge. The project will provide
access to HML vehicles by removing the existing 10
tonne load restrictions on a route that is used extensively
by heavy vehicles (48% of AADT). This will remove the
need for HML vehicles to take a 50km round trip detour.
The project also potentially has significant co-funding
from the Australian Government.
In-Progress
Fixing Country Road
Round 1 - Burrangong
Creek Bridge
Young South East &
Tablelands
Freight Project generates positive economic and productivity
benefits by removing B-double restrictions on Bribbaree
Road and the associated 20km detour. The project will
enable B-double access from silos and farms to the
Olympic and Hume Highways and is potentially
supported by co-funding from the Federal Government.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Burrendong
Way Upgrade (incl
Dripstone Bridge)
Dripstone Central West &
Orana
Freight The Panel felt that a replacement of Dripstone Bridge
merits funding, as it will reduce travel distances for
livestock traffic using Burrendong Way and allow for
use of higher productivity vehicles as the existing bridge
has a 10 tonne load limit. The project generates a good
BCR and relies on a mix of cofounding from Federal,
State and Council sources.
In-Progress
Fixing Country Road
Round 1 - Carrs Creek
Bridge Replacement
Caloola Central West &
Orana
Freight A new bridge at Carrs Creek would create a more
productive East-West route livestock and other farm
produce. The project would allow the use of 25m B-
doubles on a route currently only suitable for 19m B-
doubles. This will result in a reduction in the number of
trips, which leads to a high BCR.
Completed
Fixing Country Road
Round 1 - Combaning
Road Upgrade
Junee Reefs Riverina - Murray Freight Project generates positive economic and productivity
benefits by enabling HML access on an important link
to, from and between the abattoir and feedlot. The
project will result in a 15km reduction in trip distance
and is supported by co-funding from Council. Benefits
would be realized as soon as the route opens.
Completed
Fixing Country Road
Round 1 - Croker
Grain, Marrar
Marrar Riverina - Murray Freight Project will generate strong economic benefits and
improved access into the Croker Grain hub and is
expected to reduce the number of freight movements into
the site. Project has an adequate BCR and Council and
industry are contributing a substantial amount to the road
upgrade.
In-Progress
Fixing Country Road
Round 1 - Culvert
repairs and
replacement, Pilliga Rd
Coonamble Central West &
Orana
Freight Project will generate strong economic benefits by
preventing significant detours caused by expected
failures of deteriorating culverts on a key freight
corridor. The project also includes a substantial council
contribution.
In-Progress
Fixing Country Road
Round 1 - Cumnock
S’s
Cumnock Central West &
Orana
Freight In combination with project 17 (Hanover Bridge), this
set of works generates significant economic, productivity
and safety benefits. Together it opens up a new and
shorter HML route to Manildra.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Cunningar
Road rehabilitation
5.5km to 7.25 km north
of MR84
Cunningar South East &
Tablelands
Freight Project generates good economic benefits and maintains
MR380's ability to support high productivity vehicles.
Contrary to the EOI, Council is now providing 7% co-
funding for the project.
Completed
Fixing Country Road
Round 1 - Deniliquin
Industrial Area Local
Road Upgrade
Deniliquin Riverina - Murray Freight Project generates strong economic benefits relating to
improved access for heavy vehicles to the Deniliquin
Industrial Area. Project supports the operation of an
abattoir that will recommence operations in January
2015 as well as other companies located in the precinct.
In-Progress
Fixing Country Road
Round 1 - Emerald
Grain
Tara Riverina - Murray Freight Project will generate strong economic benefits and
improved access into the Emerald Grain site for HML
vehicles transporting 80,000 tonnes of grain per year.
Project has a high BCR and Council is contributing a
substantial amount to the road upgrade.
Completed
Fixing Country Road
Round 1 - Euston
Prungle Access
Upgrade
Euston Far West Freight The project generates positive economic benefits relating
to improved access for heavy vehicles and local industry.
Although the project BCR is around 1.0, the project
includes a substantial council contribution.
Completed
Fixing Country Road
Round 1 - Forbes
Northern Heavy
Vehicle Route
Forbes Central West &
Orana
Freight The Forbes Northern Heavy Vehicle Route will generate
strong economic benefits by opening up a new road train
route and lead to travel time reductions for heavy
vehicles. The project has strong interdependencies with
upgrades being performed in Parkes Shire.
In-Progress
Fixing Country Road
Round 1 - Gobarralong
Bridge
Coolac Riverina - Murray Freight This Application is recommended for qualified funding
on the basis that it provides for strong economic benefits
and has significant sources of additional co-funding, both
from Council and, potentially, the Australian
Government. Replacement of the safety impaired and
load limited bridge will remove a constraint on an
approved B-double route.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 -
Greenethorpe –
Bumbaldrey Road
Upgrade
Bumbaldry Central West &
Orana
Freight Project would open up a significantly shorter B-double
route for 66,000t of freight and almost 4000 movements
annually. Council is making a substantial co-contribution
to a project that generates a high BCR.
In-Progress
Fixing Country Road
Round 1 - Gumble
Road Sealing
Gumble Central West &
Orana
Freight This application is recommended for funding as it seals
the last remaining section of Gumble Road, a gazetted B-
double and feeder route in Manildra from the North.
Although economic benefits vary depending on
assumptions made, the project would rely on 70% co-
funding from non-Fixing Country Roads sources and
deliver tangible safety benefits.
Completed
Fixing Country Road
Round 1 - Hanover
Bridge
Yeoval Central West &
Orana
Freight Replacing the Hanover Bridge, which is currently single
lane, with a two lane bridge on an improved alignment
will generate significant economic, productivity and
safety benefits. By opening up the route for HML
vehicles, access to milling and grain receival sites in
Manildra will be greatly improved.
In-Progress
Fixing Country Road
Round 1 - Hopefield
Road Bridge Widening
Balldale Riverina - Murray Freight While the BCA model generated a low BCR, the
Technical Panel felt that the project would generate
additional safety benefits that were not incorporated in
the BCR. This view was supported by six fatalities
occurring on the road over the past five years. The
project also has significant levels of co-contribution from
Council and Federal sources.
Completed
Fixing Country Road
Round 1 - Jones Road
& Boorga Road
Intersection Upgrade
Lake Wyangan Riverina - Murray Freight The project will aid the establishment of the Griffith
Northern Heavy Vehicle Bypass which will open up a
new HML Road Train route that will carry over 18,000
heavy vehicles per year. Council is contributing 50%
towards the project.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Lower
Bendoc Road
Pavement
Rehabilitation
Delegate South East &
Tablelands
Freight Project generates a high BCR, primarily as a result of
improved access for heavy vehicles. This project will
remove the need for Bombala Council to impose
limitations on the number of B-double movements on the
route, which is important especially in light of expected
additional forestry vehicle volumes on this route.
In-Progress
Fixing Country Road
Round 1 - Milvale
Road Upgrade
Milvale South East &
Tablelands
Freight An improvement of Milvale Road generates improved
travel times and positive economic benefits for over
100,000 heavy vehicle movements per annum. Project
relies on a good mix of Federal, State and Council
contribution.
Completed
Fixing Country Road
Round 1 - Mitchell
Highway &
Bunglegumbie Rd
Intersection Widening
Dubbo Central West &
Orana
Freight Project will generate economic, productivity and safety
benefits by removing one of two remaining impediments
for the bypass route to be approved for road train access.
By opening up the route for road trains, the productivity
of the Dubbo Regional Livestock Markets, Fletcher's
Intermodal Freight Centre and International Exports
(abattoir) will be greatly improved. The bypass route will
reduce average trip times by an estimated 11 minutes and
improve safety by removing road trains from the more
heavily trafficked roads in the centre of Dubbo.
In-Progress
Fixing Country Road
Round 1 - Mount
Lindesay Road
Upgrade (Kyogle)
Lindesay Creek North Coast Freight Project will generate significant economic, productivity
and safety benefits by completing the opening up of
Warwick to Mt Lindesay Highway and the Summerland
Way for B-doubles. Increased use of HPVs will increase
productivity as livestock is able to be loaded at a greater
density and the improved pavement will reduce damage
to vehicles and livestock. Complements a number of
other upgrades along Mt Lindsay Road. The Panel felt
that the State Government should develop a
comprehensive concept for upgrade of Mt Lindsay Road.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Mount
Lindesay Road
Upgrade (Tenterfield)
Koreelah New England North
West
Freight Project will generate significant productivity and safety
benefits by improving the quality of Mount Lindesay
Road. The project will result in a reduction in travel
distance for transport companies who currently avoid
using the road because of its condition. The upgrade is
expected to improve safety on a road that has had two
heavy vehicle incidents in the previous year. The
calculated BCR understates potential safety benefits. The
Panel also felt that the State government should develop
an overall concept for upgrading Mount Lindesay Road.
In-Progress
Fixing Country Road
Round 1 - MR240
Ardlethan / Coolamon
Road
Coolamon Riverina - Murray Freight The project generates positive economic benefits by
enabling HML vehicles to access a strategic freight route
connecting the Newell and Olympics Highways. The
resulting expected reduction in the number of trips leads
to a high BCR. The project also includes a significant
council contribution.
Completed
Fixing Country Road
Round 1 - Old
Cootamundra Road
Upgrade
Quandary Riverina - Murray Freight Project will generate significant economic, productivity
and safety benefits though an improvement of two parts
and intersections of Old Cootamundra Road in Temora.
This will lead to improved access and ability to use
higher productivity vehicles into two grain receival sites
to the Southeast of the town.
Completed
Fixing Country Road
Round 1 - Parsonage
Creek Bridge
Strengthening and
Widening
Lords Hill South East &
Tablelands
Freight This application is recommended for qualified funding
primarily due to the project’s strong economic and
productivity benefits relating to maintaining access for
heavy vehicles. The project also caters for the expected
growth in forestry volumes from the area.
In-Progress
Fixing Country Road
Round 1 - Phoenix
Street Intersection
Upgrades for B-Triple
Access to TRLX
Westdale New England North
West
Freight Project generates strong economic and productivity
benefits by removing the last two remaining restrictions
between TRLX and the State Highway network that
prohibit B-triple access. The project is supported by
RMS and has significant co-funding from Council and,
potentially, the Australian Government.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Replace Tin
Tot Bridge
Graman New England North
West
Freight Project generates strong economic benefits and has
significant sources of additional co-funding, both from
Council and, potentially, the Australian Government.
Main beneficiary will be within the livestock industry
which use the route to access cattle processing plants in
South East Queensland.
In-Progress
Fixing Country Road
Round 1 - Replacement
of Abercrombie River
Bridge
Paling Yards Central West &
Orana
Freight Project will generate significant economic benefits by
securing the most direct route between Oberon and
Goulburn to 19m B-doubles and opening up a new route
for 25m B-doubles. The project eliminates a 100km
detour during high river flows and supports the
development of a proposed wind farm.
In-Progress
Fixing Country Road
Round 1 - Replacement
of Allison Bridge
Coolah Central West &
Orana
Freight This Application is recommended for qualified funding
primarily due to the Project's strong economic benefits
relating to improved access for heavy vehicles and the
impact that this will have on local industry. Project will
enable HML access on Black Stump Way and result in a
35-64km distance saving for heavy vehicles.
In-Progress
Fixing Country Road
Round 1 - Reseal
Railway Street
saleyards access
Coonamble Central West &
Orana
Freight Project generates strong economic benefits relating to
improved access for heavy vehicles to the Coonamble
Saleyards and adjacent GrainCorp silos. Project supports
the operation of the proposed Coonamble abattoir as well
as other companies located in the area. The project also
includes a substantial council contribution.
Completed
Fixing Country Road
Round 1 - Rockvale
Road Upgrade, 1.6km
north of Boundary
Creek
Aberfoyle New England North
West
Freight By addressing the most problematic section on Rockvale
Road, project creates significant travel time reductions
for heavy vehicles in bad weather and a safer route for
all road users. Economic benefits of the project are
positive and Council is contributing 25% of the cost of
the project.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Sealing of
Bugilbone Road
between Burren
Junction and Pilliga
Burren Junction Far West Freight Project generates positive economic and productivity
benefits by increasing average speeds and improving the
reliability of a route that facilitates access to the major
saleyards and the proposed rail terminal at Burren
Junction. The project is also supported by a reasonable
council contribution. Project is supported by an
underlying strategy to seal and upgrade the entire route
between Coonabarabran and Mungundi.
Completed
Fixing Country Road
Round 1 - Southern
Cadia Access Route
Errowanbang Central West &
Orana
Freight This application is recommended for qualified funding
primarily due to the importance of a suitable B-Double
route servicing Cadia Valley mine and its future
development, the Central Tablelands Livestock
Exchange and forestry operations in the area. The
funding for the remaining sections of the route is already
allocated in Council’s 10 year forward budget.
In-Progress
Fixing Country Road
Round 1 - Starr's
Crossing Bridge
Replacement
Timor Hunter Freight Project generates strong economic and productivity
benefits by improving access to StoneCo Limestone
Quarry and cartage of livestock to the saleyards at Scone.
The project will provide access to heavy vehicles by
removing the existing 6 tonne load restrictions. The
project also has significant co-funding from industry,
Council and potentially, the Federal Government.
Completed
Fixing Country Road
Round 1 - Sutton's
Lane reconstruction
Cootamundra Riverina - Murray Freight Sealing Sutton's Lane would create a more productive
and reliable diversion route for overheight vehicles
travelling on the Olympic Highway as well as heavy
vehicles travelling to the local abattoir and saleyards.
The 30km increase in trip distance for over height
vehicles if Sutton's Lane were closed leads to a high
BCR.
Completed
Fixing Country Road
Round 1 - The Rock
Road Upgrade
The Rock Riverina - Murray Freight Project will generate strong economic benefits and
provide a direct route to the Emerald Grain facility at
The Rock. This is expected to save grain producers and
receival stations up to $7.50/tonne. Project has an
acceptable BCR and Council is contributing a substantial
amount to the road upgrade.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Tocal Road
Improvement Program
Bolwarra Heights Hunter Freight This application is recommended for qualified funding
primarily due to the significant Council contribution and
the project's solid economic and productivity benefits
relating to improved access for heavy vehicles, and the
positive impact this will have on local industry (in
particular the Martins Creek Quarry and regional
livestock markets). The road sees approximately 500
heavy vehicle movements per day.
Completed
Fixing Country Road
Round 1 - Tooloom
Bridge
Upper Tooloom New England North
West
Freight Project generates economic and productivity benefits by
upgrading Tenterfield Shire Council's only load limited
bridge. The project will provide access to heavy vehicles
by lifting the existing 15 tonne load restriction on the
bridge. This will remove the need for heavy vehicles to
take a 16km detour. The project also has significant co-
funding from Council.
In-Progress
Fixing Country Road
Round 1 - Trangie
Showground Road
upgrade to the
Robinson Grain
Storage terminal
Trangie Central West &
Orana
Freight Project will generate good economic, productivity and
safety benefits by improving the reliability of a key
stretch of road that provides the most direct link to the
Robinson Grain Storage Terminal which has an annual
throughput of up to 70,000t. The project will remove the
need for heavy vehicles to take a 33km detour when the
road is closed due to bad weather and is supported by a
reasonable co-contribution from industry and Council.
Completed
Fixing Country Road
Round 1 - Upgrade
Middle Trundle Road
Trundle Central West &
Orana
Freight Project will generate positive economic and productivity
benefits by improving the quality of a key stretch of road
that provides the most direct link to the Newell Highway,
Mugincoble Silos and Central West Livestock Exchange.
Moreover, the project will provide significant safety
benefits on a section of road that has recorded a number
of fatalities and injuries. The project will remove the
need for heavy vehicles to take an 8km longer but safer
alternative route and is supported by significant co-
contribution from Council and the Federal Government.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Upgrade of
Gundabloui Road north
of Collarenebri
Collarenebri Far West Freight Project generates economic and productivity benefits by
increasing average speeds and improving the reliability
of a route that facilitates access to the major saleyards
and the proposed rail terminals at Merrywinebone and
Burren Junction. The project is also supported by a
reasonable council contribution and previous work on
the route. Project is supported by an underlying strategy
to seal and upgrade the entire route between
Coonabarabran and Mungundi. Project BCR does not
take safety and non-freight benefits into account and as
such is expected to be higher.
Completed
Fixing Country Road
Round 1 - Upgrade of
Silo Road, Tocumwal
Tocumwal Riverina - Murray Freight Project will generate strong economic benefits and
improved access into the Tocumwal freight precinct
which handles 23,000 heavy vehicle movements
annually. Project has a high BCR and Council is
contributing a substantial amount to the road upgrade.
In-Progress
Fixing Country Road
Round 1 - Upper
Murray Industry
Access Project
Wantagong Riverina - Murray Freight Project opens up the entire length of Jingellic Road to B-
doubles. This is the shortest route between the Hume
Highway at Holbrook and Jingellic, Tumbarumba and
Corryong. The project generates significant vehicle
operating cost savings and is expected to lead to a
reduction in annual heavy vehicle movements, estimated
at7% or 1600 vehicles. Council is providing a substantial
contribution to the project and has provided detailed
costing information.
Completed
Fixing Country Road
Round 1 - Whitbarrow
Way
Nymagee Far West Freight Project will generate significant economic, productivity
and safety benefits by enabling heavy vehicles to use the
most direct route to and from the Hera Mine. The project
will provide additional safety benefits by improving
deteriorated pavement quality and is supported by co-
funding from industry and Council.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 1 - Widen and
Upgrade MR350 at
Gunningbland
Gunningbland Central West &
Orana
Freight Upgrades support the development of a Road Train route
to the Central West Livestock Exchange. Project
generates strong economic benefits by significantly
reducing maintenance costs and has significant sources
of additional co-funding from Council and, potentially,
the Australian Government.
Completed
Fixing Country Road
Round 1 - Widen
MR350 between
Trundle and Tullamore
Tullamore Central West &
Orana
Freight Improves access for Class 3 Road Trains and HML
vehicles, which have been denied access to this route.
Project generates strong economic benefits by
significantly reducing maintenance costs and has
significant sources of additional co-funding from
Council, RMS Repair Program and, potentially, the
Australian Government.
Completed
Fixing Country Road
Round 2 - Appleby
Lane Upgrade
Appleby New England North
West
Freight Upgrade and seal 5.8km of Appleby Lane between the
Oxley Highway (SH11) and Gidley-Appleby Road.
Upgrade the intersection of Appleby Lane and Gidley
Appleby Road, and upgrade the intersection of Appleby
Lane and Manilla Road (MR63) to facilitate access for
Restricted Access Vehicles (B-Doubles).
In-Progress
Fixing Country Road
Round 2 - Ardlethan
Grain Hub
Connectivity Project
Ardlethan Riverina - Murray Freight Realignment or Bygoo Rd to remove road constraints
and improve connectivity to the Ardlethan Grain Hub
from Newell Hwy, Burley Griffin Way and Tallimba
area to the north of Ardlethan. Works required include
acquiring of land, clearing of vegetation, culvert
upgrades, construction of new road alignment and
connection of surrounding roads.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Browns
Creek Road Upgrade
Browns Creek Central West &
Orana
Freight This project is for the pavement strengthening, widening,
and minor realignment of Browns Creek Road from
Millthorpe Road for a total of 7km to the entrance to
Australian Native Landscapes (ANL) Horticultural
Products Production Facility at Browns Creek. The
existing pavement is failing in a numerous places and not
able to handle the existing usage pattern for ANL. ANL
has recently been awarded additional contracts for the
collection of Green Waste from Council areas in the
Central West and Western Sydney. These are expected to
significantly increase the volumes of material being
brought into and out of the facility.
In-Progress
Fixing Country Road
Round 2 - Bull Plain
Road Upgrade
Coreen Riverina - Murray Freight Bull Plain Rd is a major secondary trunk route (north-
south) to Oaklands (in nearby Urana shire), and serves as
a collector road for grain transport traffic from local
farms. Over past years Council has sought to upgrade
Bull Plain Road between Riverina Highway and Emu
Park Rd (formerly Sanger Darcy Rd) to a higher standard
in recognition of its status as a collector road.
Improvements have included reconstruction of road,
stabilisation and widening of seal. A 1.4km section
remains to be upgraded, between CH28823and
CH30231. It is proposed to upgrade this section by
reconstructing the road, placement and compaction of
150mm crushed rock pavement and then placement of a
10mm primer seal to a width of 7m. In addition it is
proposed to upgrade drainage by constructing a new
culvert at CH29732 and reconstructing and upgrading
the existing culvert at CH28830.
In-Progress
Fixing Country Road
Round 2 - Bulli Creek
Bridge Replacement,
Comboyne Road
Byabarra North Coast Freight The replacement of an ageing single lane three span
timber bridge on Comboyne Road, 9.6km west of the
Oxley Highway, with a single span, two lane, pre-
stressed concrete deck girder bridge and associated road
works.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Cam Creek
Bridge Upgrade
Rangers Valley New England North
West
Freight Rangers Valley Road has a very important ‘last-mile’
freight function, providing all heavy vehicle access to
Rangers Valley feedlot, which is currently the sixth
largest feedlot in Australia at 33,500 head capacity.
Access to Rangers Valley feedlot comprises 14km travel
on local roads, all of which is a two-lane sealed road
except for the single lane Cam Creek bridge that is the
subject of this application. Glen Innes Severn Council
propose to widen the narrow Cam Creek Bridge on
Rangers Valley Road to become a two-lane bridge
structure with improved load capacity, and reconstruct
bridge approaches which are presently in very poor
condition.
In-Progress
Fixing Country Road
Round 2 - Cedar Party
Creek Bridge
Replacement - Stage 1
Investigation,
Feasibility & Design
Wingham Hunter Freight Stage 1 (investigation, feasibility and design of preferred
option) of a two stage project (stage 2 being
construction) for the replacement for the existing bridge
that has reached the end of its useful life and is
controlled by PBS weight limitations to prevent further
structural damage and flooding which cuts access to
Wingham in any event worse than 1 in 20 years (5%
AEP).The reason for splitting this project is to allow the
investigation and feasibility assessment of various
alignment options, including incorporation of a high
level overpass over the main northern rail line (currently
low level crossing).Stage 2 (construction) may be from
$5M to $15M depending on the BCR of various
alignments, however inclusion of the rail overpass may
bring other funding partners (Federal Government, State
Rail) to the table.
In-Progress
Fixing Country Road
Round 2 - Conargo
Road
Carrathool Riverina - Murray Freight We are seeking to widen, improve drainage and seal the
road. We are also seeking to strengthen the pavement at
the entrance to the cotton gin and grain storage site as the
road current receives close to 18,000 truck movements
and if the entrance area is not reinforced it will quickly
break away and cause additional maintenance costs for
the Council.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Cranky
Corner Road (South)
Bridge Upgrade
Stanhope Hunter Freight Cranky Corner Road (South) Bridge is located on
Cranky Corner Road, 2.5km from the Stanhope Road
and Cranky Corner Road (South) intersection. The
Bridge was extensively damaged by the April 2015
storms. Singleton Council has received Roads and
Maritime funds to repair the damage but no means to
upgrade the bridge. Improvements to the bridge will
expand freight opportunities in the Singleton Region.
The bridge upgrade will assist with improving safety and
allow heavier freight movement.
In-Progress
Fixing Country Road
Round 2 - Daysdale
Walbundrie Road
Floodway
Daysdale Riverina - Murray Freight Construction of 110m long x 8m wide x 150mm thick
reinforced concrete floodway from CH32100 to
CH32210. Floodway construction will ensure road can
remain serviceable during and immediately after flood
events. Previous experience is that flooding has washed
away sealed section of road. Due to location – traffic will
be required to make a 21.5km detour to head west. Road
repairs have taken up to 4-6 weeks to complete, requiring
area to dry out (proximate to Coreen Creek), subgrade
restabilisation, road reconstruction and reseal.
Construction of a concrete floodway minimises time
road is unserviceable due to flooding, as well as would
obviate requirement for reconstruction of road after a
flood event. Engineering cost estimate of upgrade:
$220,000
In-Progress
Fixing Country Road
Round 2 - Dicks Creek
Road Bridge
Replacement - Nanima
(Murrumbateman
Creek)
Nanima South East &
Tablelands
Freight Replacement of the existing single lane Dicks Creek
Road timber bridge over the Murrumbateman Creek,
which has a 5 tonne load limit, with a 2 lane concrete
bridge . The new bridge will have a load carry capacity
of 56 tonne and be capable to accommodate HML
vehicles
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Eunony
Bridge – Wagga
Wagga High
Productivity Freight
Route Upgrade
Bomen Riverina - Murray Freight Wagga Wagga City Council (WWCC) has identified
significant improvements to productivity and efficiency
will be achieved by upgrading existing road networks,
encompassing the Eunony Bridge and the adjoining road
network linking the Sturt Highway with the Bomen
Business Park (north of the city) and the Olympic
Highway. The existing network features a number of
known constraints and is both inefficient for high
productivity freight vehicles and unsafe for the general
public and regular traffic. The project is significant in
nature and has therefore been comprehensively
considered by WWCC in extensive consultation with
local industry and key stakeholders. Upgrading the
existing road network will remove a number of
productivity constraints and safety hazards, including the
Eunony Bridge GML limit, the Dampier Street/Byrnes
Road level crossing and sections of road not designed for
high productivity vehicles. In addition to realising short
term improvements to the existing road network, the
upgrade will generate long term benefits to the regional
economy by releasing industrial land for development
and creating the opportunity for the development of an
intermodal freight hub within the Bomen Business Park.
The consultation with industry and key stakeholders has
shaped and informed a long term solution to an
immediate problem. The scope of the project is
summarised in attachment ‘Road drawings’ and includes
the following:- Construction of a grade-separated
underpass of the Main Southern Railway Line (located
near the western point of East Bomen Road). - The
associated road works to allow the underpass
construction including a heavy vehicle intersection near
East Bomen Road. - The construction of a link road
connecting the existing Bomen Business Park to the
underpass running north from the Bomen Road
intersection of Dampier Street along the disused stock
rail sidings. - A heavy vehicle designed link between the
eastern side of the main rail line to the Olympic
Highway. - Reconstruction of Eunony Bridge to allow
for direct HML access into Bomen Business Park and
locations further north. For clarity, this project does not
include the proposed Riverina Intermodal Freight and
Logistics (RiFL) Hub and is a standalone project. Within
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 -
Eyre/Comstock and
Comstock//Patton
Street Intersection
Concrete Upgrade
Broken Hill Far West Freight Reconstruct Eyre/Comstock and Comstock/Patton St
with concrete pavement, to allow for heavier vehicle
freight movements including AB triples and B triples.
The road is a current route for Type 1 - A - Double Road
Trains and 25/26m B - Doubles. The current
intersections are sealed however the seal is breaking
severely due to heavy vehicle movements in particular
due to the shear forces of turning vehicles.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Federation
Street Road Upgrade
Gilgandra Central West &
Orana
Freight The Heavy Vehicle Bypass (HVB) of the Gilgandra
CBD comprises Federation Street (north of the Oxley
Hwy) and Hargraves Lane (south). The HVB is a vital
regional freight link and has a high percentage of heavy
vehicles (up to 23% based on 2013 traffic counts).
AADT on the road is in the order of 766 vpd. The HVB
links the Castlereagh Highway (B55) in the north, via the
Oxley Highway (B56), to the Newell Highway (A39) in
the south. Federation Street is the section between B55
and B56, and it crosses the Dubbo-Coonamble rail line.
Federation Street is approx. 2.3km in length, and is
mostly of a rural standard. The southern 600m in
Gilgandra township is of an urban standard with kerb
and gutter both sides, and residential properties fronting
the road. In the rural section, the pavement width is
narrow and generally in poor condition. Due to the sub-
standard and narrow pavement in the rural section, heavy
vehicles slow down and move to the shoulder to pass
(one wheel on/one wheel off). In wet weather, the
pavement edge and shoulders become boggy and
impassable. Council officers advise that after a rainfall
event of 25mm in 24 hours, Federation Street is closed to
heavy vehicle traffic and it is reopened again in 2 days.
Rainfall data for Gilgandra indicates that Federation
Street is closed to heavy vehicle traffic on average 18
days p.a. During closures, heavy vehicles detour via
Miller Street through the Gilgandra CBD, where there is
high local vehicle and pedestrian activity. This proposal
is to reconstruct and widen sub-standard sections of the
Federation Street pavement shoulders, and to top up and
reseal the existing road pavement to provide a road
construction of a suitable standard and width for the
expected increased heavy vehicle movements and loads.
It is proposed to construct the works in one stage. The
design road standard is:? 7m wide carriageway (2 x 3.5m
lanes)? 1.5m shoulders each side, of which 0.5m is
sealed (overall width of seal 8m)? Asphalt surface in
urban section; bitumen seal in rural section. Council is
seeking funding to undertake the construction, and will
contribute planning, design and other preconstruction
approvals.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Federation
Way Freight Link
Morundah Riverina - Murray Freight The project involves reconstruction, realignment and
widening 4.5 kilometres of Federation Way between
Urana and Morundah and reconstruction of culverts to
bring that section of road up to the same standard as
adjoining sections.
In-Progress
Fixing Country Road
Round 2 - Flags
Niangala Bridge
Replacement
Niangala New England North
West
Freight The current one lane timber bridge will be replaced with
a single lane yet wider concrete structure. The timber
bridge has two spans, with the centre piles located in a
stream. This is less environmentally friendly than a
single span bridge that completely spans the watercourse.
It is proposed that the replacement structure will be
single span, and will have no footprint within the
watercourse, allowing the water to flow unimpeded.
There will be no bypass track installed for the
construction of this bridge; residents will have to take a
lengthy detour. Environmental and site constraints will
not allow for a bypass track to be installed. The older
timber structure will be removed and completely
replaced by the new structure.
In-Progress
Fixing Country Road
Round 2 - Forest Road
Rail Bridge
Duplication
Orange Central West &
Orana
Freight The project intent is to duplicate the existing narrow dual
lane bridge with a new structure to increase the capacity
of the rail crossing to allow for legal and safe higher
productivity vehicle access and reduce likelihood of
traffic accidents. Work will also include the construction
of new road approaches and associated infrastructure
including provision for pedestrian and cyclists. It should
be noted that the existing structure is an asset that is
owned and maintained as part of the Country Rail
Network. The new bridge structure would be wholly
separate and it is envisaged that this would become a
Council asset. Council has well developed engineering
designs for the project developed in consultation with
John Holland Rail but subject to final approval.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Gresford
Road Bridge Upgrade
Mitchells Flat Hunter Freight Gresford Road is a “classified” Regional Road. Gresford
Road Bridge is located 0.59km from the intersection of
Gresford Road and Glendonbrook Road. It has been
closed since April 2015 storms. The western Bridge
abutment and western road approach on Gresford Road
were extensively damaged during April 2015 storms.
Stage 1 of the bridge and road work is about to
commence which will reinstate the bridge and road to its
original condition. Stage 2 of the bridge upgrade works,
which forms the basis of this funding submission is to
strengthen the bridge to enable HML access.
In-Progress
Fixing Country Road
Round 2 - Grubben
Road Upgrade
Henty Riverina - Murray Freight The proposed project provides for an upgrade of
Grubben Road to:- Extend all culverts;- Increase
pavement depth and width;- Seal the 11.5 kilometre
section between Woodend Fiveways Road and the Shire
boundary.
In-Progress
Fixing Country Road
Round 2 - Gundagai
Road/ Cowcumbla
Street reconstruction
Cootamundra Riverina - Murray Freight Upgrade intersection to cater for turning lanes for heavy
vehicles, widen and strengthen pavement in Cowcumbla
Street and replace low level causeway with box culverts.
In-Progress
Fixing Country Road
Round 2 - Gundy
Creek Bridge Upgrade
– Renshaw McGirr
Way
Walmer Central West &
Orana
Freight Replace a two lane timber bridge that is not currently
operational (due to load limits and safety considerations)
with a two lane concrete bridge with the capacity to
accommodate higher mass limit (HML) vehicles.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Jacks Bridge
Replacement
Dalmorton North Coast Freight Replacement of a two lane timber bridge with a concrete
pipe culvert. Old Glen Innes Road is an important link
for residents, livestock producers, and tourists between
Grafton and Glen Innes. The replacement of the bridge
will remove the safety risk to vehicles due to the poor
condition of the timber bridge and potential for collapse.
To mitigate the risk of leaving the bridge open to traffic
Council has delineated the approaches to the bridge so
that traffic is restricted to the centre of the bridge and
single lane traffic only and Council currently inspects the
bridge weekly. Replacing the bridge will eliminate the
additional 82.1km and 75 minutes that would be required
to use an alternative route from the locality at the bridge
of Dalmorton to the regional centre of Grafton. The
replacement culvert is to be constructed by one of the
Council bridge crews, ensuring that the funding received
for the project contributes to local employment.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Jerangle
Road Capital Upgrade
Stage2
Jerangle South East &
Tablelands
Freight Jerangle road is a major link and current 19m B-Double
route between the village of Bredbo in Cooma-Monaro
Shire and Captains Flat in Palerang Shire. The road
within Cooma-Monaro Shire Council is 59.3Km long, of
which 48.7Km is still Un-Sealed. Of the Un-Jerangle
road is a major link and the only current 19m B-Double
route between the village of Bredbo in Cooma-Monaro
Shire and Captains Flat in Palerang Shire. The road
within Cooma-Monaro Shire Council is 59.3Km long, of
which 48.7Km is still Un-Sealed. Of the Un-Sealed road,
the nominated sections have been identified as
presenting restrictions to Heavy Vehicle Access. The
sections are nominated in this project are; ? Section 1
(Jerangle) from Chainage 33.1 to Chainage 36.5
(3.4Km). ? Section 2 (Wild Cattle Flat) from Chainage
53.1 to Chainage 57.6 (4.5Km). The sections identified
in the application are the weakest links in this collector,
with narrow formations, and a pavement that fails
regularly, becoming impassable to trucks, the school bus,
and motorists when wet. The nominated sections have:•
Poor drainage and a narrow clearance which resulting
in:• Damage to HV from Overhanging Vegetation.•
Unsafe traction when driving during mid to heavy rain.•
Roads frequently becoming impassable due to bogs and
erosion.• Inadequate Formation and Pavement widths
raise safety issues with:• Passing or attempting to
overtake, heavy vehicles.• Passing width and sight
distance for the School Bus Service.• Increased accident
risk due to inadequate sight distances.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Kinghorn
Bridge Replacement
Pillar Valley North Coast Freight Clarence Valley Council proposes to replace the existing
timber Kinghorn Bridge with a concrete box culvert. The
existing bridge has been prioritised for replacement due
to its deteriorating condition and the considerable
ongoing expense involved in maintaining the bridge.
Replacement of the bridge will remove the safety risk to
vehicles due to the poor condition of the timber bridge
and potential for collapse. The replacement culvert is to
be constructed by one of the Council bridge crews,
ensuring that the funding received for the project
contributes to local employment.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Kolkilbertoo
Road joint application
Narrandera and Bland
Shire Council
Barellan Riverina - Murray Freight The planned works on Kolkilbertoo Road (Main Road 37
and Main Road 84 at Bland Shire, for this joint project
between Narrandera and Bland Shires is to include the
following: I) Widen shoulder to make a seal width of 7
meters over a length of 14 km. ii) Upgrade 1.9 km of
road length at the boundary between Bland and
Narrandera Shire, improve geometry, pavement strength
and alignment iii) Widen shoulder to make a seal width
of 7 meters over a length of 3.5km between the boundary
bend and first S curve.(See Attachment B - Schematic
sketch of proposed works Kolkilbertoo Road)Project
Details: Shoulder widening works:• Site clearing on
western side of road• Extension of 20 culverts of size
400 mm and 5 culverts of size 600 mm.• Prepare
subgrade and provide 200 mm of loose local gravel•
Compact material to gain 100 % Modified Dry Density•
Provide Otta seal on widened portion• Complete line
marking and install guideposts Improving geometry,
alignment at one curve:• Site clearing on both sides of
road • Use road mixer to pulverise existing narrow seal•
Provide additional gravel and reshape the road to meet
superelevation, width and pavement depth• Compact,
trim, Otta seal and complete line-marking Bland Shire
further plan to undertake additional works, widen the
road between the 2 bends from 6m to 7m, in 2016/17
subject to receiving additional government funding.
In-Progress
Fixing Country Road
Round 2 - Main Canal
Road
Coleambally Riverina - Murray Freight Main Canal Road is a Freight route linking Kidman Way
(south) and the Sturt Highway (to north), it is used by
agricultural and transport companies for movement of
freight. It can save 30-40 minutes on freight transport
route for a trucking company and save over 35 kms per
route using Main Canal Road, compared to alternative
routes. We are seeking to seal the last remaining 4 kms
of unsealed road.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Middlebrook
Bridge Replacement
Middle Brook Hunter Freight Replace a single lane timber bridge with a two lane
concrete bridge.
In-Progress
Fixing Country Road
Round 2 - Mihi Creek
Bridge Replacement
Mihi New England North
West
Freight Mihi Creek Bridge is located approximately 22km south-
east of Armidale on Enmore Road. The bridge is an old
narrow timber structure which requires traffic in one
direction to give way to oncoming vehicles. Due to the
poor condition of the structural members, the bridge
requires regular repair which can require the bridge to be
closed for extended periods up to three weeks. During
these times, traffic is detoured around the site via
Linfield Road and Mihi Road which are both narrow
gravel roads. The detour is 4.5km further in distance and
due to the low road standard, takes approximately 9
minutes longer in a truck. In addition, the existing
structure does not meet volumetric loading requirements.
Following recent load capacity testing of the structure, it
has been recommended that a load restriction of 30
tonnes for articulated vehicles and 16 tonnes for rigid
vehicles be placed on the bridge so that vehicles larger
than a dual axle rigid truck are required to use the detour.
It is proposed to upgrade the existing bridge by replacing
the timber superstructure with concrete elements to
enable greater load carrying capacity to suit HML
vehicles.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Mosquito
Creek Road
Intersection Widening
Pallamallawa New England North
West
Freight The project involves the widening of two sealed "T"
intersections and one sealed 90 degree bend on the north
eastern entrance into the village of Pallamallawa.
Increasing the width of the intersections and bend will
allow the introduction of larger restricted access AB-
triple vehicles that have a wider sweep path than the
current vehicle combinations. The works will include:
•Relocation of three power poles to allow for the
additional road widths. •Lengthening (extension) of two
culverts. •Replacing two culvert head walls that have
collapsed. •Additional road formation at intersections
and bend.
In-Progress
Fixing Country Road
Round 2 - MR 241
Murringo Road
Pavement Widening at
3.25-3.75km and 8-
8.9km West of Lachlan
Valley Way
Boorowa South East &
Tablelands
Freight This project involves strengthening and widening the
pavement to 2 x 4m sealed lanes to replace the failing
and narrow sections of pavement. Both proposed
sections of work will result in a 9m wide formation with
an 8m with the total length of works being 1.4 km.
Drainage works associated with formation will also be
undertaken at the same time.
In-Progress
Fixing Country Road
Round 2 - MR 380
Cunningar Road
Pavement
Rehabilitation and
Widening
Boorowa South East &
Tablelands
Freight Reconstruction of 5.75km of Cunningar Road to provide
a road that is suitable for B-Double and HML vehicle
use. The project will include widening, rehabilitation,
and strengthening of the existing road pavement to
provide a 10m wide pavement and 8m wide seal.
Ancillary works will include improvements to drainage,
delineation, and signage improvements.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Newell
Highway to Wirrinya
Heavy Vehicle Route
Upgrade
Wirrinya Central West &
Orana
Freight To enable the use of higher mass and productivity
vehicles, this project involves the upgrade and widening
of a local arterial road between the Newell Highway and
a large grain handling facility at Wirrinya. This facility
currently averages 50,000 tonnes of grain delivered by
road each year, which is then transported via rail. The
region also produces grain stored on farm, livestock and
is a consumer of large volumes of commodities such as
fertiliser and seed. The project involves 22.5 km’s of
road widening and pavement rehabilitation, curve
realignments, multiple intersection realignments and
improvements, the widening of culvert structures and
upgraded traffic facilities. The upgrades will enable the
use of higher mass and productivity vehicles on this
route.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Purvis Lane
Upgrading
Dubbo Central West &
Orana
Freight Purvis Lane is a local "east west" distributor road
providing access to the North Dubbo Industrial Precinct.
It provides access from the Newell Highway and
connects with Yarrandale Road, a "north south"
distributor which links to the Golden Highway. The
existing road, was constructed over 60 years ago
effectively as a local rural road servicing the abattoir
which is long closed and has been replaced by new
industries and businesses including pet food processing,
wool warehousing, truck and heavy plant sales and
service, mining equipment sales and servicing, steel
fabrication and concrete pre casting. The road provides
access from the Newell Highway to industries in
Yarrandale Road including Fletcher International
Exports abattoir and Fletcher Grain Intermodal Centre.
The shoulders have been sealed to widen the carriageway
over the past 30 years to cater for the increase in trucks
accessing the general area. The existing two lane road
with 7m seal width is to be upgraded to the proposed
standard of an "Industrial Distributor" road. Distributor
Roads are typically designed to allow truck access into
adjacent properties without interrupting traffic flow. This
is achieved by a 15.5 m wide formation comprising two
3.5 m wide travel lanes with 2m wide sealed shoulders
separated by a 4.5m wide centre turning lane. The traffic
flows on the Freightway are not intended to be
particularly high and therefore the combined flows of
local and truck traffic can be accommodated in two
traffic lanes. The upgrading of Purvis Lane over a length
of 1.22km (Merrygoen Rail Line to Yarrandale Road)
will upgrade the road to the standard of the proposed
Freightway Ring encircling the City of Dubbo. The
works will also include improvements to the stormwater
flow capacity of the table drains and crossover culverts.
The upgrade also include the installation of street
lighting to P4 lighting standard.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Realignment
of the Devil's Elbow
Corner
Merrill South East &
Tablelands
Freight The Devils Elbow Corner is a hairpin bend on MR52
North (Grabben Gullen Road) which runs from
Crookwell to Gunning and provides access for freight
vehicles to M31. The road is not open to 25m B-doubles
due to the corner’s alignment and steep decent
preventing safe interaction between freight vehicles,
school busses and general commuter traffic. The project
will realign the Devils Elbow Corner creating a safe and
productive alignment for Higher Productivity Vehicles.
The outputs for the project consist of:• 1.1km of New
Road (29.5km to 30.6km South of Crookwell)•
Acquisition of Land• Removal of Rock• New pavement
to acceptable, safe alignment standards for Higher
Productivity Vehicles• Line Marking• Signposting•
Additional Drains• Fencing
In-Progress
Fixing Country Road
Round 2 - Rebuilding
Taylors Bridge
Bucca North Coast Freight Coffs Harbour City Council proposes to rebuild Taylors
Bridge, a timber bridge on Coramba Forest Road, Bucca,
with a wider concrete bridge. The previous timber bridge
collapsed after being traversed by a high mass load
vehicle. Fortunately there were no injuries or fatalities
involved. The current bridge provided is a temporary
bridge that is not suitable for use in the medium to long
term. The current temporary bridge (as was the previous
bridge) is narrow at 3.5m wide, and dangerous. A 20kph
speed restriction is in place to slow vehicles to safely
pass on the bridge. There will also be considerable
ongoing expense incurred in keeping the temporary
bridge in a condition state suitable for heavy vehicle use
outside of the short term. The proposed new concrete
bridge will provide a permanent long term access
solution, removing the risk of future load restriction or
closure posed by the temporary bridge. The new bridge
proposed is 15m long by 7.6m wide.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 -
Reconstruction and
Sealing of Gundabloui
Road between
Collarenebri and
Mungindi- 6 km
segment
Collarenebri Far West Freight Reconstruction and sealing of a 6 km segment of RR457.
Unit rate of $250,000 per kilometre, inclusive of new
causeways and table drains.
In-Progress
Fixing Country Road
Round 2 - Replacement
of Brookers Bridge
(Timber Bridge with a
concrete bridge)
Mirannie Hunter Freight Brookers Bridge is a single lane timber bridge located on
Mirannie Road about 23.5km from the Gresford Road
intersection. It is the last timber bridge under the care
and control of Singleton Council. The bridge is the only
direct route for the local Mirannie cattle industry and
currently restricts the freight capability for Mirannie
cattle properties to the Singleton Regional Livestock
Markets. There are approximately 61 vehicle movements
per day across Brookers Bridge. Singleton Council
proposing to replace the timber bridge with a two lane
concrete bridge, resulting in increased load capacity.
Improvements to the higher mass limits will expand
freight opportunities in the Region. The upgrade will
assist with improving safety, minimising maintenance
costs and securing freight accessibility to a Region that is
vital to the local agricultural economy.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Romiaka
Channel Bridge
Replacement
Palmers Island North Coast Freight Clarence Valley Council proposes to replace the
Romiaka Channel Bridge to provide a wider concrete
bridge comprising 2 x 3.5m wide travel lanes, 1.2m wide
shoulders and a 2.0m wide footpath. The construction of
the approach embankments require considerable
earthworks, accounting for approximately a third of the
total project costs. The existing bridge is narrow at 7
metres wide with no shoulders and causes heavy
vehicles, including freight vehicles and buses, to have to
slow down or stop to pass safely on the bridge, adding
approximately 30 seconds to each trip. The replacement
bridge will be constructed on the north side of the
existing bridge. The existing bridge will remain open
during construction and will be demolished following the
traffic switch to the new bridge.
In-Progress
Fixing Country Road
Round 2 - Rosemeath
Road Widening and
Pavement
Strengthening
Bombala South East &
Tablelands
Freight Bombala Council needs to undertake pavement
strengthening and widening of approximately 1200
metres of Rosemeath Road, Bombala. This is a local
road however it is subject to significant heavy haulage of
forestry product from both local and interstate sources.
Bombala LGA is reliant upon the timber industry as one
of its key economic drivers.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Seal
Extension Wilga
Downs Road (SR26)
Byrock Far West Freight To undertake 200m of lineal excavation and remove
around 2160 cubic metres of gravel to vertically realign a
dangerous crest and then form, stabilise and seal 4km of
the Wilga Downs Road (SR26). This section of road has
been selected due to the dangerous crest where there is
limited visibility and it is a stretch of road which has a
high maintenance requirement on Council. Wilga Downs
Road is a priority road for Council due to the amount of
road train activity carting material from the Boral pit
located near Byrock. Wilga Downs Road is the shortest
access road from the pit to the sealed road at the Kidman
Way. This is the only blue metal (aggregate) pit in the
region and the only one that has been certified to a
standard where the material can be used in the mining
industry (one of the biggest users of the end product).
Primary users are local councils and the
concrete/shotcrete industry (batch plants, shotcrete in
mines etc.). There is one primary contractor that carts
concrete aggregate from the pit to serve the Cobar
region. Ballast for use along the railway lines is also
produced at this pit. Wilga Downs Road is in poor
condition due to a combination of the large amount of
trucks and road trains using the road, and the number of
causeways along it. The road is at the base of a set of
hills, with many short run-off areas. The section of road
selected for works under this grant is the highest
maintenance area along the road. Council has recently
spent $310,000 in 2013/2014 to extend the seal and a
further $430,000 was programmed for 2015/2016 on
further seal extension along this road in a bid to improve
access to the pit and reduce ongoing maintenance costs
for Council.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - South
Kempsey Village
Heavy Vehicle Bypass
South Kempsey North Coast Freight The project involves the construction of the unformed
section of South Street from the South Kempsey
Industrial Area through to Gowings Hill Road as well as
the strengthening and minor road widening of sections of
the existing road pavement on South Street. This will
establish a heavy vehicle bypass of the residential village
area in South Kempsey and direct heavy vehicles to an
existing intersection which has capacity to accommodate
larger vehicle turning movements on a HML approved
route. Under the present situation heavy vehicles
transporting quarry & rural/agricultural products from
approved industries in the Euroka, Dondingalong and
Pipers Creek areas are required to pass through the South
Kempsey urban area of Middleton Street before
accessing Macleay Valley Way and the Pacific Highway.
The current need to pass through the urban residential
areas surrounding Middleton Street causes a number of
issues including - delays to heavy vehicles movements,
greatly increased road safety risks, generates excessive
noise and causes significant road pavement deterioration.
This section of South Kempsey is also a low socio-
economic area that experiences a variety of social issues.
Disturbance caused by heavy vehicles through this area
increases the level of community tension, particularly
where truck movements conflict with school children
travelling to and from school or in the early morning/late
evening. It is proposed to bypass the urban area by
constructing the unformed section of South Street from
the South Kempsey Industrial Area to Gowings Hill
Road; an approximate length of 750m. There is an
existing road reserve along this route, which is largely
clear of vegetation. Pavement strengthening and
widening works are also proposed on the existing sealed
section of South Street in order to ensure that the existing
road pavement can accommodate the predicted increase
in heavy vehicle and passenger traffic. The bypass will
reduce the average travel time for heavy vehicles by
approximately 11% (refer Benefit Cost Analysis)
through providing a more direct route and avoiding
residential 50km/hr speed zones. With the current
demand for quarry products generated by the Pacific
Highway upgrade project this reduction would
substantially improve efficiency, reduce costs and
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Stage 1 -
Griffith Southern
Heavy Vehicle Bypass
Griffith Riverina - Murray Freight Construction of Stage 1 of the Griffith Heavy Vehicle
Bypass (GSHVB), a 5 leg rural roundabout at
intersection of Old Willbriggie Road, Kurrajong Avenue,
Watkins Avenue and Thorne Road which includes
realignment and construction of the approaches to the
intersection, adjustment of existing utilities and services
including electricity, street lighting, water supply and
drainage. (appendix 1)The Griffith Southern Heavy
Vehicle Bypass (GSHVB) consists of approximately
11.7kms in total length that provides a strategic alternate
heavy vehicle route around the south of Griffith’s built-
up environments. The entire route consists of the
widening and construction of existing roadways, the
construction of two (2) roundabouts at existing
intersections and realignment to two (2) existing
intersections. The entire GSHVB commences at the
intersection of Kidman Way (MR80) and Brown Road
and ends at the intersection of Kurrajong
Avenue/Irrigation Way (MR80)/Burley Griffith Way
(MR84). The project has been broken into stages to
provide a more realistic delivery of the project due to the
size and cost; while still maintaining a link with the
existing heavy vehicle routes in Griffith.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Tara-Betric
Road Bridge
Replacement
Pucawan Riverina - Murray Freight Tara-Betric Road Bridge requires replacement after
recent load rating assessment testing revealed that this
Bridges Load Rating is only 10T, making this route
inaccessible by heavy vehicles. This creates a detour of
13.16km round trip while forcing these heavy vehicles to
use local gravel roads as the alternate detour route. This
road links key networks including regional road MR398
Mary Gilmore Way and state road MR84 Burley Griffin
Way. Replacement of Tara-Bridge Road Bridge, will
include site establishment (including development of
sidetrack), demolishment of existing structure,
earthworks, construction of new bridge structure, final
pavement works and bitumen seal. Incorporated in the
project is 500m of approach re-alignment works on the
eastern side of the bridge including tie inn of intersection
with 2 small pipe culvert widenings. The new bridge
constructed will accommodate a minimum load rating of
90.5 tonnes and minimum axle loadings of 22.5 Tonnes
per axle.
In-Progress
Fixing Country Road
Round 2 - Tenterden
Road bridge
replacement
Tenterden New England North
West
Freight Replace the existing single lane timber bridge with a 2
lane concrete structure
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Tyrone
Bridge replacement
Eurobodalla South East &
Tablelands
Freight The project involves the replacement of the existing
Tyrone Bridge structure with a new concrete bridge at a
higher level to provide improved access and load
capacity. The existing bridge is only capable of T44
loading. The new bridge will be a concrete single lane
bridge designed to SM1600 loadings in accordance with
the AS5100 Bridge Code capable of handling higher
mass limit vehicles which currently cannot access the
area due to the load capabilities of the existing timber
bridge. The new bridge will have 5 x 16m spans with 3m
approach slabs at each end, a total length of 86m, with a
width of 5.50m giving a total deck area of 473 m2. The
bridge deck will be raised to a level similar to others
within the same catchment and will improve access for
the community. The new concrete bridge will be
constructed alongside the existing 9 span timber bridge.
New approach roads will be constructed to the new
bridge.
In-Progress
Fixing Country Road
Round 2 - Upgrade
Kiamma Creek Bridge
Crookwell South East &
Tablelands
Freight The Kiamma Creek Bridge is a 111 year old, low level,
timber bridge on MR 248E (Laggan Road) Crookwell. It
is a key access route between North East and South West
Upper Lachlan Shire. Outputs for this project include:•
A concrete culvert bridge• Realignment of the approach
road• Drainage improvements• Landscaping
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Upgrade
Middle Trundle Road
Bogan Gate Central West &
Orana
Freight This project will undertake further upgrades to Middle
Trundle Road to include the widen and seal of a further
3.0km of the remaining 17km of unsealed road. Middle
Trundle Road forms a significant local collector road for
Parkes LGA, allowing outlying villages Trundle and
Tullamore to access Parkes urban centre. The route is
unsealed for 17km of its 29km length - 4.5km of this will
be upgraded in Fixing Country Roads Round 1 projects
late 2016. Further upgrades to Middle Trundle Road will
provide at least a ten minute reduction in travel time
between Parkes and the villages of Trundle and
Tullamore, and adjacent LGAs. While the upgrade will
only reduce 8km off total travelling distance, it will
remove the need to travel through Bogan Gate which is
speed limited at 50km/h, adding considerable time to the
journey. This reduction in travel time of a return journey
saves 20 mins a day will create employment
opportunities within Parkes but will allow people to still
live and invest in Trundle which is important for the
economic growth of this small country town. This time
saving and improved HPV access provides a significant
improvement to accessing regional facilities such as
GrainCorp Silos, the Forbes Livestock Exchange and
Manildra Flour Mill. The upgrades will also help
alleviate a pinch point in the transport network allowing
increased access to the farm gate. The sealing of the road
may also allow for a relaxation on the current curfew
limiting access from 7:30-9:00am to 3:00-4:30pm school
days and travel during daylight hours only. The upgrade
of the Middle Trundle Road has been identified as a
community priority at community consultation
workshops held throughout the Shire since 2012.
Residents of Trundle and Tullamore in the north-west of
the Shire use this road as the shortest route into Parkes
for shops and services. As a result Council has
endeavoured to allocate resources and apply for funding
to complete the reseal. The benefits that this project
offer regionally have been acknowledged by the
CENTROC Road Freight Transport working group who
have collectively rated and included the project in the
Centroc Regional infrastructure Priority Matrix - Freight,
Logistics and Transport Tranche.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Upgrade of
Regional Tantawangalo
Road
Cathcart South East &
Tablelands
Freight The project will see improved transport links between
the Monaro Plains and the Bega Valley.• Increased
access for heavy haulage of forestry products from local
sources.• Enhancement of economic development within
the Bombala Council area.• Improved safety for heavy
vehicle operations, tourists and local farming enterprises.
The project will see pavement strengthening and
widening of approximately 500 metres of Tantawangalo
Road east of Cathcart. This road is a Regional Road and
is subject to significant heavy haulage of forestry product
from local sources. Approximately 100,000 tonnes of
pulpwood product per annum has been estimated by the
processor. The timber industry is one of the two key
economic drivers and employers for the region. Council's
freight and heavy vehicle transportation management is
compromised by the sub-standard existing pavement
which is affecting the carrying capacity of this road.
Council needs to ensure that the road has the capacity for
the freight task now and into the future. There is
increasing pressure upon Council by timber producers
and other heavy vehicle users of this road to ensure
transport efficiency and address road safety needs and
residential amenity for people living along this section of
road. This project targets a specific section of the
regional road network that has been identified as having
significant haulage tonnages and is already beginning to
show signs of stress and deterioration. The project
addresses several goals within the Bombala Council
Community Strategic Plan.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Upper
Murray Productivity
and Safety
Improvement Project -
Clarkes Hill
Maragle Riverina - Murray Freight Clarkes Hill is a 3.6km steep (10%) and narrow (<6m,
seal edge to seal edge) section of the Tooma Road
(RR628) linking the southern and northern parts of
Tumbarumba Shire. It currently acts as an impediment to
efficient heavy haulage transportation, and to industry
development. It also poses a major safety risk for all road
users. Although currently designated a B-Double route,
geotechnical investigations have found the current
pavement has 'five years or less' remaining life. This
application is predicated on the fact this section of road
will continue deteriorating and will lose its B-Double
status should investment not occur under this program. A
particular outcome of this project will be to improve
current access to plantation timber supplied from the
Maragle Valley. It also an opportunity to increase the
capacity and safety of road infrastructure supporting the
region's growing agricultural, livestock and tourism
industries. This project has been fully surveyed and
designed. A scope of works has been developed and
geotechnical survey completed. Works ready to be
undertaken include:-Widening & stabilisation of steep
earth/rock embankments-Drainage works-Road
reconstruction and widening-Guard railing & road
delineation-Resealing Please refer to attached project
plans and Gantt chart for further details.
In-Progress
Fixing Country Road
Round 2 - Urana
Lockhart Road
Causeway Upgrade
Brookong Riverina - Murray Freight The proposed project provides for:- Replacement of
existing aged culverts to HML- Replacement of existing
old concrete causeways with new culverts-
Reconstruction of 620m of pavement to suit new culverts
and upgrade pavement width and depth to suit HML
vehicles.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Road
Round 2 - Widening of
McHenrys Creek
Bridge, Henry Lawson
Way, Young
Young South East &
Tablelands
Freight It is proposed to: • construct a new bridge 5m wide on
the western side of the existing McHenrys Creek bridge
to provide one north bound traffic lane• change the
traffic arrangements on the existing McHenrys Creek
bridge to provide one south bound traffic lane; possibly
including resurfacing to correct the crossfall McHenrys
Creek Bridge on Henry Lawson Way is a reinforced
concrete bridge designed by the NSW Department of
Main Roads in 1936 and constructed in 1937. Consistent
with bridge designs at the time the deck width between
kerbs was constructed at ‘20 feet’ (6m) wide. A fatal
head-on accident between a truck and a passenger
vehicle at the bridge site in 2007 generated considerable
community reaction to the road safety issues at the
bridge identified as: • narrow lane width• inability of
heavy vehicles to cross the bridge without crossing the
centreline due to the alignment of the bridge approaches•
the mix of heavy vehicle, school buses and light vehicles
using the bridge (refer Young Witness January 21, 2008;
attached)Council engaged GHD to complete a Road
Safety Audit of The McHenrys Creek Bridge and
Approaches and this was completed in April 2011 (copy
attached). The photos provided in Appendix B of this
report further demonstrate the road safety issues
associated with this structure. In accordance with the
findings of the road safety audit, delineation and warning
signage has been improved; but improvements to the
geometry of the road approaches have been deferred
while Council investigates options for increasing the
bridge trafficable width. Council staff have been
consulting with the Roads and Maritime Services’ bridge
design and maintenance staff to determine possible
options for bridge widening. Advice received in June
2014 indicates that: • the existing bridge has theoretical
load capacity for Higher Mass Limit (HML in NSW)
vehicles; but this would be subject to detailed level three
structural assessment including coring to determine
actual concrete strength• typically widening of this type
of bridge is undertaken on one side only by the
construction of a new independent bridge; to allow future
replacement of the older bridge.(refer email dated 3 June
2014 attached Given the high level of community
concern regarding the safety of the existing bridge; as
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Country Roads Condobolin Central West &
Orana
Freight Fixing Country Roads is a program that provides
targeted funding to local councils to repair and upgrade
regional NSW roads. Its overall aim is to improve and
build efficient freight transport networks to reduce costs
for businesses. The program helps to fund projects that
better connect local and regional roads to state highways
and key freight hubs; such as silos, saleyards, rail heads,
supermarket distribution centres, industrial parks and
depots.
In-Progress
Fixing Cowra Saleyards Truck Wash
Cowra Central West and
Orana
Freight The project will update the existing truck wash, located at Cowra Saleyards, to a modern standard. The updated facility will meet all operating, legislative and compliance standards, and result in a facility that is more user-friendly for truck operators. This will be achieved by;- Upgrade of current lighting,- Installation of pumps to increase water delivery to hoses,- Installation of cameras for better security,- Increased concrete area in front of pump house to cater for wet weather,- Upgrade of effluent receivals for truck wash – increasing bio security and environmental compliance (including installation of pre-treatment lagoon),- Upgrade existing settlement ponds, - Installation of irrigation system to utilise waste water on holding paddocks; and- Upgrade of toilet and shower facility for use by transport operators.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Fixing Finley Truck Wash
Finley Riverina Murray Freight Completion of the upgraded truck wash at Finley will deliver a superior facility that will address all the issues that current users of the facility have brought to the attention of Council.The upgrade of the Finley truck wash will include paving Edwards road from it's intersection with Dales rd. to the facility exit ramp to replace the current dirt road and an expanded concrete apron within the site to allow for B doubles to be washed side by side at the same time. The lighting will be increased to cover the whole concrete stand allowing for trucks and trailers to be cleaned without having to be moved. A new and more powerful pumping system will be installed to provide high pressure water to the hoses and the drainage will be improved to cope with the higher flow. A new amenities block, accessed by the avdata key will have toilet and shower facilities.
Planning
Flemington
Interchange - Transport
Access Program
Upgrade
Homebush West Eastern City
District
Interchange Customer access to Flemington Station is being
improved. The project includes new lifts and stairs; a
new concourse overbridge and footbridge; a family
accessible toilet; a new kiss and ride area; and new bike
racks.
In-Progress
Flemington Station Refresh Package 2
Homebush West North Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Flo Clarke Park Jetty
Upgrade, Lawrence Lower
Southgate
North Coast Maritime Installation of a small jetty and pontoon on the
downstream side of the existing boatramp and relocation
of the fish cleaning tabe.
If funding permits also included is provision of a boat
wash down area and upgrade of the turning area to the
boat ramp.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Foreshore Beach
Groynes
Port Botany Eastern City
District
Freight This project addresses beach erosion and stabilise sand
movements with the construction of three groynes made
of fibre-reinforced plastic sheet piles and rock armour.
Also the groynes will help to enhance the natural
environment by protecting seagrass beds from any
further damage from sand inundation and to foster
natural growth.
Completed
Forster Harbour Boat
Ramp Facility
Improvements
Forster Hunter Maritime Installation of a pontoon at the existing boat ramp to
improve launch and retrieval of vessels. Also, expand,
realign and resurface existing car park to improve flow
of boat ramp traffic and allow for easier car-trailer
parking.
Planning
Forty Bends and
Hartley Valley Safety
Improvements
South Bowenfels Central West &
Orana
Road Safety upgrades and road improvements on the Great
Western Highway are being undertaken between Hartley
Valley and Forty Bends. Key features of the project
include improvements along the existing highway,
including changes to curves to make them safer; new
structure over Whites Creek to lessen risk of black ice
formation; five main intersection upgrades; bus bays
along the highway for safer access; more arrows and
reflective markers on the highway to provide clear
definition of lanes; and improved road surface.
In-Progress
Fourth Street
cycleway
Warragamba Western City
District
Walking and Cycling Shared Path cycleway alongside Fourth Street Completed
Foxground and Berry
Bypass - Princes
Highway Upgrade
Broughton Illawarra
Shoalhaven
Road The bypass will provide a four-lane highway (two lanes
in each direction) with median separation for 12.5
kilometres of the Princes Highway between Toolijooa
Road to just south of Andersons Lane. The upgrade
includes a bypass of the existing winding highway at
Foxground and a bypass of Berry with access ramps at
the north and south of the town.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Frederickton to Eungai
- Pacific Highway
Upgrade
Collombatti North Coast Road 26.5 kilometres of the Pacific Highway between
Frederickton interchange and Eungai Rail was upgraded.
The project included building 20 new bridges, a new
interchange at Stuarts Point Road and installing safe,
modern rest areas on both sides of the highway at
Clybucca.
Completed
Freemans Drive Freemans
Waterhole
Hunter Road Install median wire rope, including widening and
retaining walls on Freemans Drive, Freemans Waterhole
Completed
Freemans Reach Road Freemans Reach Western City Road High friction surface, shoulder widening, CAMs, w-
beam barrier, RRPMs and guideposts with reflectors
Completed
Freight Noise
Attenuation Program
Koolewong Central Coast Rail The program seeks to provide mitigation for the
properties most impacted by freight rail noise across the
Transport for NSW managed heavy rail network.
Treatments include upgraded windows and doors to
reduce internal noise levels and provide amenity,
particularly at night. The program will run for ten years
and will treat up to 200 homes each year. The program is
in its first year of implementation, with treatments
already being delivered at Koolewong, Emu Plains,
Wombarra and Jannali.
In-Progress
Gan Gan Road One Mile Hunter Road Curve alignment, Shoulder Widening, Guardrail,
intersection hold lines , sight distance and delineation
Completed
Garfield Road Upgrade Riverstone Central City
District
Road An upgrade of Garfield Road between Richmond Road
and Windsor Road is being planned. It includes a grade
separated rail crossing at Riverstone. The upgrade will
cater for the expected increase in population and
development of local employment hubs including Box
Hill, Riverstone West and Marsden Park industrial
precincts that will result in significantly more traffic in
the area.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Gateway to the South
Pinch Point Program
Gymea South District Road The Gateway to the South Pinch Points Program aims to
ease congestion and improve journey reliability on
Sydney’s key southern corridors. The program will
address critical pinch points along the A1, A3 and A6
routes south of the M5 Motorway which includes Princes
Highway, King Georges Road, Heathcote Road, The
Grand Parade, Stacey Street, New Illawarra Road and
Alfords Point Road. The program focuses on short to
medium term solutions to improve travel time and
reliability for all road traffic including buses and freight.
In-Progress
Gee Gee Bridge
Replacement - Bridges
for the Bush - Program
2
Wetuppa Riverina Murray Road Gee Gee Bridge over the Wakool River on the Swan Hill
to Deniliquin Road (also known as Noorong Road) was
built in 1929. It is a Dare type timber truss bridge and is
listed on the State Heritage Register. The bridge has a
single traffic lane and vehicles give way to oncoming
traffic. A new two-lane concrete bridge across the
Wakool River and floodplain is proposed adjacent to the
existing bridge, including realignment of about 1.4
kilometres of Noorong Road.
The plans include removal of the existing Gee Gee
Bridge and flood relief bridge, and providing a new rest
area. The new bridge will provide for higher mass
vehicles and reduce maitenance costs.
Planning
Gerringong - Princes
Highway Upgrade
Willow Vale Illawarra
Shoalhaven
Road The Princes Highway has been upgraded between Mount
Pleasant and Toolijooa Road. The upgrade provides 7.5
kilometres of upgraded highway and includes two new
interchanges with access to Gerringong and Gerroa.
Completed
Gerringong
Interchange -
Commuter Parking
Gerringong Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Gerringong
Interchange - Transport
Access Program
Upgrade
Gerringong Illawarra
Shoalhaven
Interchange The improvements to Gerringong Station included
regrading and widening the existing external ramp which
provides access to the platform, and provision of a new
DDA compliant car parking space.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Glenbrook interchange
- Commuter Parking
Glenbrook Western City
District
Parking Improvements at Glenbrook Station included a new
commuter car park providing 56 extra car parking
spaces; two accessible parking spaces close to the station
entrance; a safer pedestrian crossing and traffic island;
improved footpaths, wayfinding signage and security
fencing; safety improvements to the station entrance
including the installation of a new balustrade and non-
slip paint to the ramp; and improved lighting between the
station entrance and the new car park.
Completed
Glenbrook Station Refresh Package 3a
Glenbrook North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Glenfield Interchange -
Commuter Parking
Glenfield Western City
District
Parking Conversion of existing staff car park to provide five
extra commuter car parking spaces.
Completed
Glenfield Station Refresh Package 3
Glenfield South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Glenmore Parkway to
Jamison Road - The
Northern Road
Upgrade
Orchard Hills Western City
District
Road The Northern Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney airport at Badgerys Creek.
It would also improve safety, increase road capacity and
reduce congestion and travel times in the future. This
stage of The Northern Road Upgrade is four kilometres
between Glenmore Parkway, Glenmore Park and
Jamison Road, South Penrith. It is planned to generally
follow the existing road alignment. Key features include
widening The Northern Road to provide four lanes in
each direction (three general traffic lanes and a kerbside
bus lane); widening the road bridge over the M4
Motorway; installing new traffic lights and turning lanes
at some intersections; installing new traffic lights at the
Glenmore Parkway intersection (existing roundabout to
be removed); providing continuous bus lanes in each
direction; installing a central median; providing a new
shared path for pedestrians and cyclists on the western
side of the road and a new footpath on the eastern side of
the road; and installing new street lighting, drainage and
safety barriers.
In-Progress
Glennies Creek Bridge
Upgrade - Bridges for
the Bush - Program 2
Glennies Creek Hunter Road The Middle Falbrook Bridge, also known as Glennies
Creek Bridge is an old timber truss bridge built in 1904.
The work involves replacing and strengthening all bridge
components above the piers including the timber trusses,
deck, traffic barriers and approach spans. The road
approaches are also be upgraded as part of the work.
This will ensure the bridge meets current load standards
and is capable of carrying a 42.5 tonne semi-trailer or
equivalent without significantly affecting the appearance
of the bridge.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Gocup Road Upgrade Minjary Riverina - Murray Road Gocup Road is being upgraded from the Snowy
Mountains Highway at Tumut to the Hume Highway at
Gundagai. The upgrade work includes widening the
road, straightening curves, installing overtaking lanes
and wire rope and strengthening sections of the road
surface to withstand heavy loads.
In-Progress
Golden Highway Gungal Hunter Road Install roadside barrier both directions on the Golden
Highway, Gungal, Westwood Road to 500 metres north,
plus northbound barrier 1.5-2.5 kilometres south of
Westwood Road.
Completed
Golden Highway Warkworth Hunter Road Provide short CHR intersection Completed
Golden Highway Merriwa Hunter Road Install kerbside barrier for 2 curves Completed
Golden Highway Merriwa Hunter Road Upgrade crossings, improve blisters, trees removed for
improved visibility, improved traffic calming on
approach on Golden Highway, Merriwa at Bow Street.
Completed
Golden Highway Merriwa Hunter Road Upgrade crossings, improve blisters, trees removed for
improved visibility, improved traffic calming on
approach on Golden Highway, Merriwa at Bow Street.
Completed
Goldfields Way Old Junee Riverina Murray Road Shoulder widening and wire rope safety barrier Completed
Gordon Interchange -
Commuter Parking
Gordon North District Parking A new commuter car park and interchange on the
western side of Gordon Station, off Henry Street,
provides 214 commuter parking spaces (an increase of
135), including five accessible parking spaces. The car
park and interchange also includes bicycle racks,
motorcycle parking, bus stops, taxi zone, weather
protected waiting areas, lighting and CCTV cameras.
Completed
Gordon Interchange -
Commuter Parking
Gordon North District Parking The commuter car park on Werona Avenue was
upgraded providing an additional 30 commuter car
parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Gordon Park Boat
Ramp and Car Park
Upgrade, Nambucca
Heads
Nambucca
Heads
North Coast Maritime Upgrade of boat ramp facilities at Gordon Park,
Nambucca Heads. Works include the review of existing
masterplan, boat ramp improvements, new amenities,
access amendments (pedestrian and vehicular) and
parking changes.
Planning
Gordon Station Refresh Package 2
Gordon Riverina Murray Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Gosford Interchange -
Commuter Parking
Gosford Central Coast Parking Conversion of existing staff car park to provide 59 extra
commuter car parking spaces.
Completed
Gosford Interchange -
Commuter Parking
Gosford Central Coast Parking New commuter car park providing an extra 86 spaces
including new surfacing, line marking, lighting, CCTV
cameras and fencing.
Completed
Gosford Passing Loops Wyoming Central Coast Rail Two passing loops (northbound and southbound) were
constructed between Gosford and Narara Stations, to
allow freight trains to wait whilst passenger services
pass. This assists in improving freight access through
northern Sydney and the Central Coast, relieve a serious
bottleneck, create a more efficient freight rail network
and improve the reliability of passenger services on the
Main North Line. This project is part of the Northern
Sydney Freight Corridor Program, which is an initiative
to improve the capacity and reliability of freight trains
between Strathfield and Broadmeadow, Newcastle. The
program will increase capacity for interstate container
freight and remove the most serious bottleneck on the
East Coast interstate, which connects Australia’s three
largest cities (Melbourne, Sydney and Brisbane).
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Gosford Station Refresh Package 1a
Gosford Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Goulburn Ilford Road Sofala Central West and
Orana
Road Provide sealed shoulder one metre on the inside and 2.5
metres on the outside, improve horizontal alignment,
install a widened centre painted median, CAMs and non-
skid bitumen surface.
Completed
Goulburn Interchange -
Transport Access
Program Upgrade
Goulburn South East &
Tablelands
Interchange New cycle facilities and pedestrian crossing. Completed
Goulburn Mulwaree Truck Wash
Goulburn South East and
Tablelands
Freight Construction of a new purpose built 2 bay truck wash in Goulburn that will cater for clientel on a 24/7 basis, centrally located to Hume Highway for trucks travelling from Sydney to Canberra or Melbourne and local sale yards.
Planning
Goulburn Station Refresh Package 2a
Goulburn Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Goulburn Street Crookwell South East and
Tablelands
Road Construct a 2.5m wide shared cycleway along Goulburn
Street, Crookwell (135m).
Not Started
Governor Phillip Park
Boat Ramp Car Park
Upgrade, Windsor
Windsor West Maritime Upgrade of the existing car park at the Governor Phillip
Reserve boat ramp, Windsor. Upgrade works to cover
both car only and car/trailer parking.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Grafton - Additional
Crossing of the
Clarence River
South Grafton North Coast Road The additional crossing of the Clarence River is being
planned that will address short-term and long-term
transport needs. Key benefits of the project include
reducing the potential for road crashes and injuries on
the bridge and approaches including any intersections
and connecting roads; providing safe facilities for
pedestrians and cyclists; providing efficient access for a
second crossing of the Clarence River and for the State
road network; providing a traffic management network
which reduces delays between Grafton and South
Grafton in peak periods to an acceptable level of service
for 30 years after opening; providing adequate vertical
clearance for heavy vehicles; providing transport
solutions that complement existing and future land uses
and support development opportunities; provide
improved opportunities for economic and tourist
development for Grafton; providing for commercial
transport including B-doubles where required; providing
flood immunity for the bridge; and providing
navigational clearance from the additional crossing for
river users.
In-Progress
Grafton High School
Interchange - Transport
Access Program
Upgrade
Grafton North Coast Interchange The upgrade includes road resurfacing and new bus
signage near Grafton High School.
Completed
Grafton Interchange -
Transport Access
Program Upgrade
South Grafton North Coast Interchange The upgrade includes a new bus and taxi rank and the
installation of new signage.
Completed
Grafton Saleyard upgrade with 2 new B Double truck wash bays, ablutions & lighting
South Grafton North Coast Freight Demolish existing single body truck wash bay and sediment catching pitsInstall 2 new drive-through B double truck wash bays and sediment catching pitsInstall 2 unisex ablution facilities.Install LED lighting and pole for truck wash bays.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Grafton Station Refresh Package 2a
South Grafton Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Grant Street
cycleway
Broulee South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Grant Street Completed
Granville Interchange -
Transport Access
Program Upgrade
Granville Central City
District
Parking A new commuter car park on the corner of Rowell and
Cowper streets was constructed to provide 20 additional
commuter parking spaces in close proximity to Granville
Station. As part of this project, the Granville bus
interchange was upgraded and a new commuter car park
on Mary Street which provided 40 additional commuter
parking spaces. New public toilets, lighting, CCTV,
footpaths and landscaping were also provided.
Completed
Granville Station Refresh Package 1
Granville Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Great Western
Highway
Faulconbridge Western City Road CAMs and high friction seal Completed
Great Western
Highway cycleway
Marrangaroo Central West &
Orana
Walking and Cycling Bicycle Path cycleway alongside Great Western
Highway
Completed
Great Western
Highway cycleway
Werrington Western City
District
Walking and Cycling Shared Path cycleway alongside Great Western
Highway
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Great Western
Highway cycleway
Emu Plains Western City
District
Walking and Cycling Shared Path cycleway alongside Great Western
Highway
Completed
Great Western
Highway cycleway
Eastern Creek Central City
District
Walking and Cycling Shared Path cycleway alongside Great Western
Highway
Completed
Great Western
Highway cycleway
Kingswood Western City
District
Walking and Cycling Shared Path cycleway alongside Great Western
Highway
Completed
Green Valley Creek
cycleway
Canley Heights Western City
District
Walking and Cycling Shared Path cycleway alongside Green Valley
Creek
Completed
Greenwell Point
Sewage Pump-out
Facility (Investigation)
Greenwell Point Illawarra
Shoalhaven
Maritime Installation of a public sewage pump-out facility at
Greenwell Point. Project includes the replacement of an
existing timber wharf (at the end of its asset life) with a
new pontoon and the installation of the pump-out on the
pontoon.
Planning
Gresford Road Paterson Hunter Road Construct sealed shoulders and provide clearzone Completed
Greta Interchange -
Transport Access
Program Upgrade
Greta Hunter Interchange The improvements to Greta Station included redesigning
and rebuilding the existing ramps on both sides of the
station and the entrances to improve customer access.
Completed
Greys Beach Boat
Ramp Facility
Upgrade, North Nowra
North Nowra Illawarra
Shoalhaven
Maritime Upgrade of the Greys Beach boat ramp facility, North
Nowra. Works include: formalisation of the existing boat
ramp into a 3 lane ramp, installation of an additional
jetty/pontoon at the boat ramp and improvements to
car/trailer parking. Project also includes an investigation
study into the feasibility of a new boat ramp facility on
the south side of the Shoalhaven River at Nowra (East of
the bridge).
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Griffith Livestock Marketing Centre Truck Wash
Griffith Riverina Murray Freight Construction of a new two-bay public road train accessible truck wash-down facility at the existing Griffith Livestock Marketing Centre (GLMC) that will improve productivity and reduce effluent spill that cause road safety issues and the spread of noxious weeds and disease. The facility will also service a wide range of trucks and heavy machinery up to Road Train size that will benefit inter-regional and interstate freight networks and last mile connectivity to local commodity producers and processors.
Planning
Grose Vale Road Kurrajong Western City Road Install high friction, shoulder, RRPMs, guideposts Completed
Guanna Hill
Realignment
Belgravia Central West &
Orana
Road The proposed improvements at Goanna Hill, about 21
kilometres north of Orange, will upgrade and realign 7.2
kilometres of the Mitchell Highway towards Molong.
This work will improve safety, travel times and provide a
smoother road surface for road users. Key features of the
Guanna Hill realignment include construction of 7.2
kilometres of two-lane, two way rural road with a 100
km/h posted speed limit; provision of 3.5 metre wide
lanes and two metre wide sealed shoulders (one metre
when next to the overtaking lane); provision of a 1.6
kilometre eastbound overtaking lane at the southern end
of the road; and protected right turn bays at the
Strathmore Lane and Guanna Hill Lane intersections.
In-Progress
Guildford Station Refresh Package 4
Guildford Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Gunnedah - Second
Road Over Rail Bridge
- Bridges for the Bush -
Program 1
Gunnedah New England North
West
Road The second road over rail bridge would provide an
unrestricted Higher Mass Limit freight route through
Gunnedah and improve local traffic efficiency and road
safety. The new route replaces the existing New Street
level crossing which would be permanently closed as
part of this project. The new bridge would be built west
of the Gunnedah Maize Mill to link the Oxley Highway
with Warrabungle Street. In addition to building a new
bridge, the project scope contemplates an upgrade of the
Oxley Highway roundabout; new roundabout at the
intersection of Warrabungle and Conadilly Streets; new
intersection of Warrabungle and Barber Streets and a
shared path for cyclists and pedestrians.
In-Progress
Gunnedah Saleyards Truck Wash
Gunnedah New England
North West
Freight the provision of a supplemental 2 bay truck wash adjacent the existing facility to the west of the Gunnedah Saleyards on the Kamilaroi Highway.
Planning
Gwydir Highway
cycleway
Moree New England
North West
Walking and Cycling Shared Path cycleway alongside Gwydir Highway Completed
Gymea Station Refresh Package 1
Gymea Central Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Hamilton Interchange -
Transport Access
Program Upgrade
Hamilton Hunter Interchange The improvement to Hamilton Station included
redesigning and rebuilding the existing ramp from the
platform to the station entrance, off Beaumont Street,
and installation of new family accessible toilet facilities.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Hamilton Station Refresh Package 1a
Hamilton Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Hannell Street Wickham Hunter Road Install safety barrier kerbside (northbound) Completed
Hannell Street
cycleway
Maryville Hunter Walking and Cycling Shared Path cycleway alongside Hannell Street Completed
Hare Street cycleway Casino North Coast Walking and Cycling Shared Path cycleway alongside Hare Street Completed
Harris Park Interchange
- Transport Access
Program Upgrade
Harris Park Central City
District
Interchange Key features of the interchange upgrade include a new
lift, new stairs and ramps, a refresh of the station
concourse, new sheltered bicycle facilities and new
lighting and CCTV surveillance.
In-Progress
Hastings River
Recreational Boating
Facilities Study
(Investigation)
Fernbank Creek North Coast Maritime Funding for the investigation into a new or significantly
expanded recreational boating facility on the Hastings
River. The study is to include site analysis within the
study area, identification of boating sites suitable for
development, environmental impact assessments for
sites, concept development and community consultation.
Planning
Hawker Street Quirindi New England North
West
Road Design and construct a 2.5m wide concrete shared path
along Hawker Street, Quirindi between Waterford Street
and Cansdell Street.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Hawkesbury River Station Refresh Package 4a
Brooklyn Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Hazelbrook
Interchange -
Commuter Parking
Hazelbrook Western City
District
Parking The car park has been upgraded with new road
pavement, linemarking, drainage improvements, lighting
and landscaping to improve access and safety.
Completed
Hazelbrook Station Refresh Package 3a
Hazelbrook North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Head Street Forster Hunter Road Install pedestrian fencing at the southern end of the
Forster-Tuncurry bridge, redirect pedestrians to
pedestrian underpass.
Completed
Headlands Road
cycleway
Skennars Head North Coast Walking and Cycling Shared Path cycleway alongside Headlands Road Completed
Heathcote Interchange
- Transport Access
Program Upgrade
Heathcote South District Interchange Key features of the interchange upgrade include a new
overhead pedestrian footbridge with a new lift and stairs
(integrated with the existing footbridge over the Princes
Highway), new forecourts on both sides of the station, an
accessible toilet on the station platform, improvements to
commuter car parks, new kiss and ride areas and bike
facilities.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Heathcote Road,
Deadmans Creek
Bridge Upgrade
Holsworthy South District Road The bridge over Deadmans Creek has been replaced. The
new bridge provides improved road safety as a result of a
wider bridge; improvements to the vertical and
horizontal alignment of Heathcote Road and a reduced
likelihood of road crashes; improved driver visibility
resulting from widened road shoulders and median;
improve flood immunity at the creek crossing; lower on-
going bridge maintenance costs; improved storm water
and road drainage; enhanced road safety at the St George
Crescent intersection; and improved road alignment with
potential to upgrade to four lanes.
Completed
Heavy Duty Pavement
- Newell Highway,
Mungle Back Creek to
Boggabilla
Boggabilla New England North
West
Road Heavy duty pavement upgrades are being planned on the
Newell Highway, including a widened centreline,
between Mungle Back Creek and Boggabilla.
Planning
Helensburgh Station Refresh Package 2a
Helensburgh Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Henley Marine Drive
cycleway
Drummoyne Eastern City
District
Walking and Cycling Shared Path cycleway alongside Henley Marine
Drive
Completed
Henry Lawson Drive Picnic Point South Road Install 400m of 1.0m wide sealed shoulder adjacent to
the southbound lane on Henry Lawson Drive, between
200m and 600m south of The River Road. Install a 400m
long kerbside w-beam safety barrier adjacent to the
southbound lane on Henry Lawson Drive, betw
Not Started
Henry Lawson Drive
cycleway
Milperra South District Walking and Cycling Shared Path cycleway alongside Henry Lawson
Drive
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Henry Parry Drive Gosford Central Coast Road Install median barrier for curve between Georgiana Tce
and Margin St
Completed
Herbert Street Dulwich Hill Eastern City Road Install pedestrian refuge in Herbert Street with road
narrowing and footpath widening.
Completed
Hexham Passing Loop Hexham Hunter Rail Construction of a train facility to improving freight
access between the Lower Hunter, Sydney, and North
Coast of NSW.
Completed
Hilder Street
cycleway
Elderslie Western City
District
Walking and Cycling Shared Path cycleway alongside Hilder Street Completed
Hinchinbrook Creek
cycleway
Hinchinbrook Western City
District
Walking and Cycling Shared Path cycleway alongside Hinchinbrook
Creek
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Holbrook Bypass -
Hume Highway
Upgrade
Holbrook Riverina - Murray Road The 9 kilometre bypass was built to the west of Holbrook
to improve safety and transport efficiency. It runs from
four kilometres north of Holbrook where it deviates west
from the existing dual carriageways to cross Wagga
Wagga Road. The bypass features a four-lane divided
carriageway with a 110km/h speed limit; a full-diamond
northern interchange on Wagga Wagga Road with
northbound and southbound on and off load ramps; a
full-diamond southern interchange near the existing
Hume Highway with southbound and northbound on and
off load ramps; twin bridges over Culcairn Road; twin
bridges over Ten Mile Creek; landscape and urban
design treatments to minimise visual impact and provide
'gateway' treatments to Holbrook; and environmental
controls to minimise impacts on nearby waterways and
natural areas. The bypass removes many heavy vehicles
from residential and shopping areas of Holbrook;
improves pedestrian safety along the current Hume
Highway route through Holbrook; reduces traffic noise
for residents and businesses, particularly at night; and
provides travel time and fuel savings for vehicles moving
between Sydney and Melbourne.
Completed
Holman Bridge
Replacement - Bridges
for the bush - Progam 2
Gooloogong Central West and Orana
Road The new Gooloogong Bridge over the Lachlan river at
Gooloogong was opened to traffic in 2015, located about
one kilometre north of Gooloogong on Main Road 237 -
Nanima Road. This new bridge replaced the old Holman
Bridge which was a timber truss bridge built in 1904.
Completed
Holsworthy
Interchange -
Commuter Parking
Holsworthy Western City
District
Parking Conversion of existing staff car park to provide 12 extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Holsworthy
Interchange -
Commuter Parking
Holsworthy Western City
District
Parking The car park at Holsworthy Station has been extended to
provide 462 additional commuter spaces and 18 new
motorcycle spaces. The project included construction of
additional parking levels on both of the existing multi-
storey car parks, a new lift, extension of an existing lift,
and the installation of new lighting and CCTV security
cameras to improve commuter safety.
Completed
Holts Point Place Boat
Ramp New Pontoon,
Sylvania Waters
Taren Point South Maritime Repair/renewal or replacement of existing boat ramp and
installation of a pontoon.
Planning
Homebush Interchange
- Transport Access
Program Upgrade
Homebush Eastern City
District
Interchange The interchange upgrade includes new lifts, upgraded
stairs and footbridge, a new family accessible toilet, new
bus stops and shelters, kiss and ride and bike racks, new
lighting and CCTV cameras.
In-Progress
Hornsby Interchange -
Commuter Parking
Hornsby North District Parking Conversion of existing staff car park to provide 19 extra
commuter car parking spaces
Completed
Hornsby Interchange -
Commuter Parking
Hornsby North District Parking Commuter parking will be improved by providing 230
additional spaces. The existing at-grade car park on
George Street will be converted into a multi-storey
commuter car park.
Planning
Hornsby Station Refresh Package 2
Hornsby Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Horseshoe Lagoon
Boating Access
Improvements (Stage
1), Moama
Moama Riverina Murray Maritime Stage 1 in the upgrade of the Horseshoe Lagoon boating
precinct. Works include construction of a 45m timber
retaining wall with mooring points immediately
downstream of the Moama Wharf to provide short
term/overnight mooring capability. Works also include
re-decking a 220m section of the existing timber
boardwalk through Horseshoe Lagoon.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Horsley Road Horsley Park Western City Road Shoulder widening, superelevation and remove hazards
from clearzone
Completed
Hot Water Outlet Boat
Ramp Facility
(Investigation), San
Remo
San Remo Central Coast Maritime New boat ramp and car-trailer parking. Planning
Hughes Street Cabramatta Western City Road Upgrade the existing pedestrian refuge on Hughes Street
located mid-block between Hill Street and Gladstone
Street, Cabramatta. Includes the reconstruction of the
pedestrian refuge, associated kerb ramps, signs and line
marking.
Completed
Hume Highway
cycleway
Warwick Farm Western City
District
Walking and Cycling Shared Path cycleway alongside Hume Highway Completed
Hume Highway
cycleway
Liverpool Western City
District
Walking and Cycling Shared Path cycleway alongside Hume Highway Completed
Hunter Expressway Heddon Greta Hunter Road The Hunter Expressway is a four lane freeway link
between the M1 Pacific Motorway near Seahampton and
the New England Highway, west of Branxton. The new
expressway provides a new east-west connection
between Newcastle and the Lower Hunter and was
designed to accommodate long-term development and
growth in the Hunter region in the coming decades. Key
features include six grade-separated interchanges that
allow motorists to access the expressway; 40 kilometres
of dual carriageway freeway; and 52 bridges, including
almost 800 metres of high bridges through Sugarloaf
Range.
Completed
Hunter Orana fuel pipeline
Merriwa Hunter Freight Planning
Name Suburb Region/District Project Type Project Description Current
Status
Hunter River
Recreational Boating
Access Improvements
(Investigation)
Morpeth Hunter Maritime Planning
Huntleys Point Wharf -
Wharf Upgrade
Program
Henley North District Maritime Ferry wharf upgrade that includes improved access for
less mobile passengers and the construction of a covered
pontoon with wind protection and new seating. The
modern design provides easier and safer berthing for
ferries. Interchange improvements include a new
pathway and lift to the ferry wharf, a dedicated drop off
and pick up area, relocation of accessible parking spaces
closer to the ferry wharf and an upgrade of the turning
circle on Huntleys Point Road.
Completed
Hurstville Station Refresh Package 1
Hurstville Central West and Orana
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Huskisson Wharf
Upgrade Huskisson Illawarra
Shoalhaven
Maritime Redevelopment of the existing Huskisson wharves
facility. Works include: Installation of a new pontoon on
the eastern wharf (providing for disability access),
connection of the two wharves with new decking and
stairs on the western wharf, new footpath and associated
items along the wharves (piling, ladders, hand railing
etc).
Planning
Illawarra Highway
cycleway
Robertson South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Illawarra Highway Completed
Illumba Way
cycleway
Kelso Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Illumba Way Completed
Name Suburb Region/District Project Type Project Description Current
Status
Improved Boating
Access at Lake
Benanee
(Investigation), Euston
Euston Far West Maritime Funding for investigation and preliminary design for
boat launching facilities at Lake Benanee.
Planning
Improved Boating
Access at Lake
Jindabyne and Lake
Eucumbene
(Investigation)
Jindabyne South East and
Tablelands
Maritime Planning
Improved Boating
Access in Botany Bay
(Between the Cooks
River and the Georges
River)
Mascot Central Maritime Planning
Improved Boating
Access to Prospect
Creek at Lansvale
Reserve, Lansvale
Lansvale South West Maritime Planning
Improved Disabled
Boating Access at
McInherney Park, Port
Macquarie
Port Macquarie North Coast Maritime Installation of a permanent jetty and pontoon equipped
with personnel hoist to assist with the Sailability
program at McInherney Park, Port Macquarie.
Planning
Improved Non-
powered Boating
Access at Nambucca
Heads RSL Boat Ramp
Nambucca
Heads
North Coast Maritime Improvements to the boating facilities at the Nambucca
Heads RSL boat ramp. Works include boat ramp re-
surfacing, formalised boat wash down area and boat
holding area, improved wayfinding (signs, bollards,
lighting), landscaping/bank stabilsation.
Planning
Improved Non-
powered Boating
Access from Bridge
Reserve, Clarence
Town
Clarence Town Hunter Maritime Planning
Name Suburb Region/District Project Type Project Description Current
Status
Improved Non-
powered Boating
Access at Bennelong
Park, Putney
(Investigation)
Putney North Maritime Planning
Improved Non-
powered Boating
Access at Coffs Creek
Coffs Harbour North Coast Maritime The installation of a canoe launcher to improve disability
access for non-powered craft to Coffs Harbour Creek.
Planning
Improved Non-
powered Boating
Access at Dent Street,
Huskisson
Huskisson Illawarra
Shoalhaven
Maritime Non-powered boating access improvements to the
Currambene Creek at Dent Street, Huskisson. Works
include the provision of a facility for launching non-
powered craft and the upgrade of the existing informal
car park at the site.
Planning
Improved Non-
powered Boating
Access at Milson Park,
Kirribilli
(Investigation)
Kirribilli North Maritime Planning
Improved Non-
powered Boating
Access at Moonee
Creek
Moonee Beach North Coast Maritime Planning
Improved Non-
powered Boating
Access at Rose Bay
(Investigation)
Rose Bay Central Maritime Planning
Improved Non-
powered Boating
Access at the Edward
River Bridge,
Mathoura
Mathoura Riverina Murray Maritime Construction of a small boat ramp at the Edward River
Bridge campground (within the Murray Valley National
Park) for access to the Edward River by non-powered
vessels.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Improved Non-
powered Boating
Access at Wonga
Wetlands, Albury
Splitters Creek Riverina Murray Maritime Investigation study into the development of a non-
powered vessel launching facility at Wonga Wetlands.
The study will be to identify possible locations and
assess the feasibility, constraints and limitations of each
location.
Planning
Improved Non-
powered Boating
Access at Woolgoolga
Lake
Woolgoolga North Coast Maritime Planning
Improvements to the
Newell Highway at
Grong Grong
Grong Grong Riverina - Murray Road The project involves construction of a 2.4 kilometre long
section of highway with a 110km/h design speed to the
west of Grong Grong. The highway would remain two-
lane, with turning lanes at intersections to provide access
into Grong Grong. Key benefits include improved road
safety; improved safety for pedestrians and cyclists;
reduced cost of transporting goods on trucks; reduced
traffic noise in Grong Grong; consistent travel speeds;
reduced travel time; and provision for growth in freight
and other traffic that is forecast to occur over the next 20
years.
In-Progress
Industrial Drive Tighes Hill /
Mayfield East
Hunter Road Provide improved shoulders for cyclists on Industrial
Drive, Tighes Hill across the rail over-bridge near
Selwyn Street.
Not Started
Ingleburn Interchange -
Commuter Parking
Ingleburn Western City
District
Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Ingleburn Interchange -
Transport Access
Program Upgrade
Ingleburn Western City
District
Interchange The improvements to Ingleburn Station included three
new lifts; covered walkways from the lifts to the
platforms; reconfigured station entries; new customer
amenities; improvements to the bus stop and canopy; taxi
zone; lighting; new bicycle storage; accessible parking;
and formalised kiss and ride facilities.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Ingleburn Station Refresh Package 3
Ingleburn South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Inland Rail Freight Planning
Investigation into
Provision of Sewage
Pump-outs and
Mooring Facilities for
Houseboats Along the
Murray River
Bullatale Riverina Murray Maritime Planning
Iron Cove Creek
Bridge cycleway
Five Dock Eastern City
District
Walking and Cycling Shared Path cycleway alongside Iron Cove Creek
Bridge
Completed
Jack Renshaw Bridge
Underpass cycleway
Gilgandra Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Jack Renshaw
Bridge Underpass
Completed
Jack Renshaw Bridge
Underpass cycleway
Gilgandra Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Jack Renshaw
Bridge Underpass
Completed
Jackson Street Broadmeadow Hunter Road Install kerb extensions on all approaches, and centre
concrete median islands in Jackson Street.
Completed
James King Park Boat
Ramp Facility
Upgrade, Gol Gol
Gol Gol Far West Maritime Planning
Name Suburb Region/District Project Type Project Description Current
Status
Jane Street and Mulgoa
Road Infrastructure
Upgrade
Penrith Western City
District
Road The key features of the project include an additional lane
both north and southbound from Museum Drive to Union
Road increasing capacity for through traffic, while
providing capacity for vehicles turning left onto Mulgoa
Road from Jane Street and right onto the Great Western
Highway; a longer left turn lane along Mulgoa Road for
vehicles turning onto the Great Western Highway; an
upgrade of the Mulgoa Road and High Street intersection
to provide increased capacity; an upgrade of the T-
intersection of Jane Street with Castlereagh
Road/Mulgoa Road to provide increased capacity; and
widening the existing rail underpass to allow three lanes
in each direction on Castlereagh Road and extra lanes at
intersections.
Planning
Jannali Interchange -
Transport Access
Program Upgrade
Jannali South District Interchange Improvements to Jannali Station included redesigning
and rebuilding the current ramp on the western side of
the station and upgrading the footpath on the eastern side
of the station.
Completed
Jannali Interchange -
Transport Access
Program Upgrade
Jannali South District Interchange Accessibility is being improved at Jannali Station. Key
features of the project include two new lifts; a new
pedestrian bridge, stairs and canopies; a family
accessible toilet; undercover bicycle racks; improved
interchange areas; improvements to the Oxley Avenue
car park and footpath to the station; and upgrades to
lighting and CCTV surveillance.
In-Progress
Jannali Station Refresh Package 3
Jannali Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Jedda Road cycleway Prestons Western City
District
Walking and Cycling Shared Path cycleway alongside Jedda Road Completed
Name Suburb Region/District Project Type Project Description Current
Status
Jenolan Caves Road Hartley Central West and
Orana
Road Widen shoulder from 0.5 metres to 2.5 metres, install
non-skid seal, provide CAMs and curve advisory signs
Design Only
Completed
Jerilderie Truckwash Jerilderie Riverina Murray Freight Upgrade of existing pump infrastructure which will increased water pressure, improve water efficiencies and allow truck operators short timeframes in cleaning with livestock trailers. Widen the entrance to the truck wash to allow direct access from Newell Highway for Road trains and b-Doubles. Increasing turning circle and trailer parking area. Seal 500 metres of pavement.
Planning
Jerseyville Boat Ramp
New Pontoon Rainbow Reach North Coast Maritime Installation of a new pontoon at the Jerseyville boat
ramp. Works also include the removal of steel poles at
the ramp, river bank stabilsation, relocation of signage at
the boat ramp and the installation of new solar lighting at
the ramp.
Planning
Jervis Street
cycleway
Vincentia Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Jervis Street Completed
Jetty Upgrades at
Boonerah Point, Ski
Way Park and Burroo
Bay, Lake Illawarra
Yallah Illawarra
Shoalhaven
Maritime Refurbishment of the jetties at Boonerah Point, Ski Way
Park and Burroo Bay, Lake Illawarra. Works include:
repairs to worn planks, painting of jetties and the
replacement of safety ladders. Additionally, the approach
to the Burroo Bay jetty will be formalised.
Planning
John Street Cabramatta Western City Road Upgrade the existing pedestrian refuge on John Street
located mid-block between Hill Street and Gladstone
Street, Cabramatta. Includes the reconstruction of the
pedestrian refuge, associated kerb ramps, signs and line
marking.
Completed
Jones Street
cycleway
Moama Riverina - Murray Walking and Cycling Shared Path cycleway alongside Jones Street Completed
Junction Hill to
Grafton Off - Road
cycleway
Carrs Creek North Coast Walking and Cycling Shared Path cycleway alongside Summerland Way Completed
Name Suburb Region/District Project Type Project Description Current
Status
Kalua Drive Boat
Ramp Pontoon,
Chittaway Bay
Chittaway Bay Central Coast Maritime Construction of a new boat ramp, pontoon and car-trailer
parking at an existing informal boat ramp site.
Planning
Kamilaroi Highway Boggabri New England North
West
Road Provide sealed shoulders to 2.5 metres, CAMs and raised
reflective pavement markers
Design Only
Completed
Kanahooka Boat Ramp
Upgrade Kanahooka Illawarra
Shoalhaven
Maritime Upgrade of the existing boat ramp at Kanahooka.
Upgrade to include improved ramp surfacing (non-slip
surface), replacement of damaged concrete planks at the
toe of the ramp and upgrade of ramp surrounds.
Planning
Kanangra Drive Crangan Bay Central Coast Road Install wire rope safety barrier, shoulder widening,
resurfacing and delineation on Kanangra Drive, Crangan
Bay, a 4 kilometre length heading north west from the
Pacific Highway intersection.
Completed
Kapooka Bridge
Replacement and
Olympic Highway
Realignment - Bridges
to the Bush - Program
1
Lloyd Riverina - Murray Road The new four lane road-over-rail bridge on the Olympic
Highway at Kapooka includes realigning about 2.7
kilometres of the Olympic Highway and upgrading the
Olympic
Highway / Camp Access Road intersection. The upgrade
was undertaken to meet current network safety and
design standards, remove restrictions to traffic, improve
road safety, and provides increased clearance for trains
on the Sydney to Melbourne Rail Line to facilitate the
future construction of a second rail line and double
stacking of freight containers.
For more information, please visit:
http://www.rms.nsw.gov.au/projects/south-
western/kapooka/index.html
Completed
Karuah Boat Ramp
Facility Upgrade, Port
Stephens
Karuah Hunter Maritime Upgrade of the Karuah boat ramp facility. Works
include: extension of the boat ramp manouevring area,
upgrade and extension of the existing car park (to
accommodate up to 50 formalised car/trailer parking
spaces), improve pedestrian access to existing pontoons
at the ramp, and reconfiguration of pontoons to enhance
safety.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Katoomba Interchange
- Commuter Parking
Katoomba Western City
District
Parking Conversion of existing staff car park to provide eight
extra commuter car parking spaces.
Completed
Katoomba Station Refresh Package 1a
Katoomba Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Katoomba to Mount
Victoria Safety Works
Blackheath Western City
District
Road Safety improvements are being made along the Great
Western Highway between Katoomba and Mount
Victoria. The safety upgrades would cover about 14
kilometres, including through the townships of
Blackheath and Medlow Bath. The key objectives of the
project are to improve safety for all road users between
Mount Victoria and Katoomba including motorists,
cyclists and pedestrians; and to improve traffic efficiency
between Katoomba and Mount Victoria.
Planning
Keith Hall Boat Ramp
and Pontoon, Ballina Keith Hall North Coast Maritime Construction of a new boat ramp facility at Keith Hall,
including boat ramp, pontoon and car parking.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Kellyville - Memorial
Avenue Upgrade
Kellyville Central City
District
Road Memorial Avenue is being planned for an upgrade to a
four lane road to meet the future transport needs of
Sydney’s north west. Key features of the upgrade include
upgrading Memorial Avenue from a two lane to a four
lane divided road with a central median; introducing a
speed limit of 70km/h; providing a wide central median
to allow for future widening to six lanes, when required
in the future; providing landscaping in the median;
constructing pedestrian/cyclist paths on both sides of
Memorial Avenue; installing bus priority capability at
traffic lights and indented bus bays at Arnold Avenue
and Severn Vale Drive intersections; and providing
designated turning lanes and bicycle lanes at
intersections with traffic lights. Key beneifits of the
upgrade include increased road capacity to cater for
traffic growth; improved safety for motorists through the
installation of traffic lights and a central median to
separate traffic travelling in opposing directions;
improved safety for cyclists and pedestrians by providing
off-road shared paths; improved travel times between
Blacktown and Castle Hill; improved access and travel
times for road freight; improved bus accessibility at
traffic lights; and facilitating the development of the
Balmoral Road release area precinct.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Kelso - Great Western
Highway Upgrade
Kelso Central West &
Orana
Road The upgrade includes widening of the highway to
provide two travel lanes and shoulder/parking lanes on
both sides of the road; wider travel lanes and shoulders;
variable width concrete median; kerb and guttering;
paved pedestrian and cyclist pathways; replacement of
the existing bridge at Boyd Creek; drainage
improvements; upgraded intersections with traffic lights,
roundabouts and right turn bays; and improved
landscaping. The upgrade will improve road safety,
reduce congestion, improve road freight efficiency,
improve intersection arrangements, cater for the mix of
traffic, pedestrians and cyclists, and take account of the
area's current and likely future development.
In-Progress
Kempsey Bypass -
Pacific Highway
Upgrade
Verges Creek North Coast Road The 14.5 kilometre Kempsey bypass project was the first
part of the 40 kilometre Kempsey to Eungai project,
which extends from the existing dual carriageway south
of Kempsey to the existing dual carriageway at Eungai
Rail. The bypass includes a 3.2 kilometre long bridge
over the Macleay River and its floodplain.
Completed
Kendall Reserve Boat
Ramp Improvements,
Cundletown
Cundletown Hunter Maritime Planning
Kennedy Drive Boat
Ramp Car Park
Upgrade, Tweed Heads
Tweed Heads North Coast Maritime Improvements to the car park at the Kenndy Drive boat
ramp. Project to include redesign of the existing car park
to increase traffic functionality, improved storm water
management and resurfacing works.
Planning
Kennedy Drive
cycleway
Tweed Heads North Coast Walking and Cycling Shared Path cycleway alongside Kennedy Drive Completed
Kiama Boat Ramp Car
Park Upgrade, Kiama Kiama Illawarra
Shoalhaven
Maritime Upgrade of the car park at the Kiama Boat Ramp with
the formalisation of an additional 10 car/trailer parking
spaces and an additional 2 boat wash down areas.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Kiama Interchange -
Commuter Parking
Kiama Illawarra
Shoalhaven
Parking The new commuter car park is located on Bong Bong
Road, behind Kiama Mowers, approximately 100 metres
from Kiama Station. The car park provides 40 spaces
including an accessible parking space, security lighting
and CCTV surveillance.
Completed
Kiama Interchange -
Commuter Parking
Kiama Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide seven
extra commuter car parking spaces.
Completed
Kiama Station Refresh Package 4a
Kiama North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Kianinney Boat Ramp
Jetty Upgrade, Tathra Tathra South East and
Tablelands
Maritime Upgrade of the existing jetty at the Kianinney boat ramp,
Tathra. Works include: removal of the timber jetty
sections of the existing ad-hoc jetty at the boat ramp and
replacement with a new aluminium jetty.
Planning
Killara Interchange -
Commuter Parking
Killara North District Parking The commuter car park on Culworth Avenue provides
more than 80 new commuter car parking spaces;
accessible parking spaces and a new accessible
pedestrian ramp; improved lighting; line marking,
bollards and wheel stops; and minor landscaping
improvements including a widened driveway entry.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
King Georges Road to
Camden Valley Way -
M5 West Widening
Milperra South District Road The M5 West widening project includes one additional
lane in each direction on the M5 South West Motorway
for the majority of its length; a new operations
management control system, including up-to date travel
time information for drivers on variable message signs
situated on the motorway and surrounding arterial roads;
a new operations management control building situated
near the existing toll plaza at Hammondville; bridge and
underpass upgrades at Queen Street, Nuwarra Road and
De Meyrick Avenue; and six kilometres of new noise
walls, twelve kilometres of heightened noise walls and
individual noise treatments installed at more than 200
properties. Key benefits of the project include reduced
congestion on the motorway; supporting long term
residential and employment growth in Sydney's south-
west; improved access between key population hubs,
commercial and economic centres such as the Western
Sydney Employment Hub; increased capacity to service
Sydney's existing and future transport demands;
improved travel times for individuals and businesses;
improved traffic management with a new motorway
control centre at Hammondvill; and improved safety and
provide early warning alerts for drivers on the motorway
and arterial networks by providing additional variable
message signs.
Completed
Kings Cross Station Refresh Package 3
Potts Point Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Kings Hill Road Mulgoa Western City Road Install warning signs, curve advisory signs, shoulder,
CAMs, remove hazards from clear zone
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Kingswood
Interchange -
Commuter Parking
Kingswood Western City
District
Parking The commuter car park was upgraded and expanded on
the southern side of the station to provide approximately
23 additional spaces, a new entrance, improved traffic
flow, CCTV surveillance, lighting and a covered
footpath to the station. A new 'kiss and ride' and taxi
zone was also constructed on the southern side to make
passenger drop off in the new car park easier. Lighting
was added in the existing commuter car park on the
northern side to improve safety.
Completed
Kissing Point Road Dundas Central City Road Install 450M of Elsholz barrier on median from no
existing barrier. Install 150M of Elsholz barrier on
roadside from no existing barrier.
Completed
Kogarah Interchange -
Transport Access
Program Upgrade
Kogarah South District Interchange The station forecourt was redesigned and facilities
upgraded on surrounding roads, including changes to bus
stops, 'kiss and ride' facilities, taxi zones, a pedestrian
crossing and bicycle facilities.
Completed
Kogarah Station Refresh Package 1
Kogarah Central West and Orana
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Koolewong Boat Ramp
Facilities Upgrade,
Brisbane Water
Koolewong Central Coast Maritime Improvements to boating facilities at Koolewong
Foreshore Reserve, Koolewong. Works include
investigation/design and reconstruction of the existing
northern and southern boat ramps, installation of new
pontoons at the boat ramps and improvements
(reconfiguration/sealing) to the Reserve's car park.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Kooragang -
Duplication of Tourle
Street and Cormorant
Road
Kooragang Hunter Road Key features of the upgrade include: Key features
include duplicating 3.8 kilometres of the road between
Industrial Drive, Mayfield West and Egret Street,
Kooragang to provide two lanes in each direction; a new
two lane bridge on the western side of the existing
bridge; 2.5 metre shoulders along Cormorant Road to
cater for on-road cyclists; minimising impact on the
Long Pond by mainly widening the road on the southern
side of the existing Cormorant Road; maintaining access
to existing businesses along the corridor; and catering for
future industrial development on Kooragang Island next
to the existing road.
In-Progress
Kooringal Road
cycleway
East Wagga
Wagga
Riverina - Murray Walking and Cycling Shared Path cycleway alongside Kooringal Road Completed
Kundabung to
Kempsey - Pacific
Highway Upgrade
Kundabung North Coast Road The upgrade involves 14 kilometres of four lane divided
highway between Kundabung and Kempsey and includes
building an interchange at Kundabung Road, a new
intersection for local access roads, bus stops and new rest
areas at Barrys Creek. The project is part of the overall
Kempsey to Eungai upgrade.
In-Progress
Kurmond Road North Richmond Western City Road Install high friction, shoulders, CAMs, w-beam,
guideposts, RRPMs
completed
Kyalite Reserve Boat
Ramp Pontoon, Kyalite Kyalite Far West Maritime Installation of two 8m pontoon/gangway structures and
improved trailer parking and picnic amenities at the
Kyalite boat ramp.
Planning
Kyeemagh Boat Ramp
Facilities Upgrade,
Cooks River
Kyeemagh Central Maritime Reconstruction of the amenities block such that it is
compliant with the latest Australian Standards with
respect to accessibility and disabled access. Works
include 4 Toilets, 2 Disabled Toilets, 2 Showers for the
Public and an Amenities Room for Council Maintenance
Staff.
Planning
La Perouse Jetty
Reinstatement
(Investigation)
La Perouse Central Maritime Planning
Name Suburb Region/District Project Type Project Description Current
Status
Lachlan Valley Way Yass South East and
Tablelands
Road Improve horizontal alignment and provide appropriate
superelevation
Completed
Lachlan Valley Way Boorowa South East and
Tablelands
Road Shoulder widening, hazard removal and wire rope safety
barrier
Completed
Lachlan Valley Way Yass South East and
Tablelands
Road Safety Barrier on approaches to bridge Not Started
Laggers Point Boat
Ramp Upgrade, South
West Rocks
Arakoon North Coast Maritime Upgrade of the Laggers Point boat ramp facility. Works
include improvements to the boat ramp access road
(Quarry Road) to provide additional car/trailer parking,
enhanced traffic flow and safe pedestrian access.
Planning
Lake Conjola Entrance
Boat Ramp Upgrade &
Investigation into a
New Boat Ramp
Facility at Lake
Conjola
Lake Conjola Illawarra
Shoalhaven
Maritime Improvements to boating facilities at Lake Conjola.
Works include investigation and design into a new boat
ramp facility at Haviland Street, West Conjola, upgrade
of the existing dirt boat ramp to a new concrete ramp at
Aney Street, Conjola and provision of a floating
pontoon(s) near the Holiday Haven Park near the Lake
Entrance Launching Facility.
Planning
Lake Drive cycleway Narrandera Riverina - Murray Walking and Cycling Shared Path cycleway alongside Lake Drive Completed
Lake Forbes Bridge
cycleway
Forbes Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Lake Forbes
Bridge
Completed
Lake Forbes
cycleway
Forbes Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Lake Forbes Completed
Lake Forbes
cycleway
Forbes Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Lake Forbes Completed
Name Suburb Region/District Project Type Project Description Current
Status
Lake Talbot
Hydrological and Lake
Bed Mapping Study,
Narrandera
Narrandera Riverina Murray Maritime Funding to undertake a hydrological and lake bed
mapping study of Lake Talbot to inform long term
planning, management and sustainability of the Lake.
Study to include: silt testing, lake floor mapping, water
testing, vegetation assessment as well as consultation of
findings with stakeholders.
Planning
Lakemba Station Refresh Package 3
Lakemba Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Lamb Street
cycleway
Plumpton Central City
District
Walking and Cycling Shared Path cycleway alongside Lamb Street Completed
Lane Street cycleway Broken Hill Far West Walking and Cycling Road Shoulder cycleway alongside Lane Street Completed
Lanyon Drive
cycleway
Queanbeyan
West
South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Lanyon Drive Completed
Lawrence Road Southgate North Coast Road Improve vertical alignment and provide superelevation,
install shoulders CAMs and guideposts
Completed
Lawson Interchange -
Commuter Parking
Lawson Western City
District
Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Lawson Park
cycleway
Putta Bucca Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Lawson Park Completed
Ledger Road - Fox
Street cycleway
Holroyd Central City
District
Walking and Cycling Shared Path cycleway alongside Ledger Road - Fox
Street
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Lemon Tree Passage
Aquatic Infrastructure
Upgrade, Port Stephens
Port Stephens Hunter Maritime Improvements to boating facilities at Lemon Tree
Passage. Works include: construction of an additional
lane on the existing boat ramp (to become a 3 lane
ramp), installation of 2 modular pontoons on the boat
ramp, replacement of the existing wharf with a new
pontoon to house a sewage pump-out unit, and upgrade
of the car park at the site.
Planning
Lennox Head Boat
Ramp Upgrade Skennars Head North Coast Maritime Upgrade of the existing informal boat ramp and
provision of formalised car parking at the site.
Planning
Leumeah Interchange -
Commuter Parking
Leumeah Western City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Leumeah Station Refresh Package 4
Leumeah Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Leura Interchange -
Transport Access
Program Upgrade
Leura Western City
District
Interchange The upgrade includes new lift and stairs; a new canopy
over the lift, stairs and part of the platform; upgraded
toilet facilities; formalised taxi rank on Railway Parade;
an accessible path from the station to the taxi rank; new
kiss and ride zone; bicycle facilities; and improved
lighting and CCTV security surveillance.
In-Progress
Leura Station Refresh Package 3a
Leura Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing:
Amaroo Road,
Amaroo
Borenore Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Avondale Road,
Dapto
Avondale Illawarra Shoalhaven
Road Major level crossing upgrade Completed
Level Crossing: Baird
Street, Culcairn Culcairn Riverina Murray Road Major level crossing upgrade Planning
Level Crossing:
Bathampton Road,
Wimbledon
Wimbledon Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing: Beni
Street, Wongarbon Wongarbon Central West and
Orana
Road Major level crossing upgrade Planning
Level Crossing:
Bentley Road, Kyogle Cedar Point North Coast Road Major level crossing upgrade Planning
Level Crossing:
Blumer Avenue,
Griffith
Griffith Riverina Murray Road Major level crossing upgrade Completed
Level Crossing:
Boree Street,
Manildra
Manildra Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Bruxner Highway,
Casino
Casino North Coast Road Major level crossing upgrade Completed
Level Crossing:
Bulunbulun Road,
Breeza
Breeza New England North West
Road Major level crossing upgrade Planning
Level Crossing: Burley
Griffin Way - Yenda
Road, Yoogali /
Griffith
Yoogali Riverina Murray Road Major level crossing upgrade Planning
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing:
Burrington Road,
Moree
Moree New England North West
Road Major level crossing upgrade Completed
Level Crossing:
Canal Street, Leeton Leeton Riverina Murray Road Major level crossing upgrade Completed
Level Crossing:
Cemetery Lane,
Whittingham
Whittingham Hunter Road Major level crossing upgrade Completed
Level Crossing:
Clergate Lane, Clergate Clergate Central West and
Orana
Road Major level crossing upgrade Completed
Level Crossing:
Cobbora Road,
Wellington
Montefiores Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Colerenerbri Road,
Bellata
Bellata New England North West
Road Major level crossing upgrade Planning
Level Crossing:
Coopers Road,
Goobang Jtn
Parkes Central West and Orana
Road Major level crossing upgrade Planning
Level Crossing: Covan
Creek Road, Lake
Bathurst
Lake Bathurst South East and Tablelands
Road Major level crossing upgrade Planning
Level Crossing:
Dandaloo Road,
Narromine
Narromine Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Dudauman Street,
Stockinbingal
Stockinbingal Riverina Murray Road Major level crossing upgrade Completed
Level Crossing:
Ebert Street, Griffith Griffith Riverina Murray Road Major level crossing upgrade Completed
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing:
Eulomogo Road,
Dubbo
Dubbo Central West and Orana
Road Major level crossing upgrade Planning
Level Crossing:
Flagstone Street,
Cookamidgera
Cookamidgera Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing: Fry
Street, Grafton Grafton North Coast Road Major level crossing upgrade Completed
Level Crossing:
Gardiner Street,
Griffith
Yoogali Riverina Murray Road Major level crossing upgrade Planning
Level Crossing:
Goondah Road,
Bowning
Bowning South East and Tablelands
Road Major level crossing upgrade Completed
Level Crossing:
Gostwyck Road North,
Armidale
Armidale New England North West
Road Major level crossing upgrade Planning
Level Crossing:
Harefield Road,
Harefield
Harefield Riverina Murray Road Major level crossing upgrade Planning
Level Crossing:
Hoddle Street
(Illawarra Highway),
Robertson
Robertson South East and Tablelands
Road Major level crossing upgrade Completed
Level Crossing:
Hulbert Street,
Sawtell
Toormina North Coast Road Major level crossing upgrade Completed
Level Crossing:
Jerrawa Road, Jerrawa Jerrawa South East and
Tablelands
Road Major level crossing upgrade Planning
Level Crossing:
Kooringal Avenue,
Griffith
Griffith Riverina Murray Road Major level crossing upgrade Completed
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing: Lake
Street, Ganmain Ganmain Riverina Murray Road Major level crossing upgrade In Progress
Level Crossing:
Lansdowne Road,
Kundle Kundle
Kundle Kundle Hunter Road Major level crossing upgrade Completed
Level Crossing: Limbri
Road, Kootingal
(Limbri)
Kootingal New England North West
Road Major level crossing upgrade Planning
Level Crossing:
Mackays Road,
Coffs Harbour
Coffs Harbour North Coast Road Major level crossing upgrade Completed
Level Crossing:
Mangoola Road,
Mangoola
Denman Hunter Road Major level crossing upgrade Completed
Level Crossing:
Mangoola Road,
Ulan
Denman Hunter Road Major level crossing upgrade Completed
Level Crossing: Marrar
North Road, Marrar Marrar Riverina Murray Road Major level crossing upgrade In Progress
Level Crossing:
McAdam Street
(Rouchel Road),
Aberdeen
Aberdeen Hunter Road Major level crossing upgrade Planning
Level Crossing: Mid
Western Highway,
Goolgowi
Goolgowi Riverina Murray Road Major level crossing upgrade Completed
Level Crossing:
Middle Folbrook
Road, Nundah
Glennies Creek Hunter Road Major level crossing upgrade Completed
Level Crossing: Mills
Road, Towrang Towrang South East and
Tablelands
Road Major level crossing upgrade Planning
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing:
Mogriguy Road,
Mogriguy
Mogriguy Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Murrays Flat Road,
Towrang
Towrang South East and Tablelands
Road Major level crossing upgrade Planning
Level Crossing: Nash
Street, Parkes Parkes Central West and
Orana
Road Major level crossing upgrade Completed
Level Crossing:
Newell Highway,
Gilgandra
Gilgandra Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Philip Street,
Gloucester
Gloucester Hunter Road Major level crossing upgrade Completed
Level Crossing:
Primrose Street,
Wingham
Wingham Hunter Road Major level crossing upgrade Completed
Level Crossing: Rosler
Parade, Henty Henty Riverina Murray Road Major level crossing upgrade Planning
Level Crossing:
Rossglen Road,
Rossglen
Rossglen North Coast Road Major level crossing upgrade Completed
Level Crossing:
Sheep Wash Road,
Calwalla
Glenquarry South East and Tablelands
Road Major level crossing upgrade Completed
Level Crossing:
Sheraton Road,
Dubbo
Dubbo Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Summerland Way,
Koolkhan
Koolkhan North Coast Road Major level crossing upgrade Completed
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing:
Summerland Way,
Nammoona
Casino North Coast Road Major level crossing upgrade Completed
Level Crossing:
Summerland Way,
Wiangaree
Wiangaree North Coast Road Major level crossing upgrade Completed
Level Crossing:
Tapscott Road
(Dunavants), Moree
Moree New England North West
Road Major level crossing upgrade Completed
Level Crossing: The
Escort Way,
Borenore
Borenore Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing: Tilly
Willy Road,
Macksville
Macksville North Coast Road Major level crossing upgrade Completed
Level Crossing: Tip
Road, Dunmore Minnamurra Illawarra
Shoalhaven
Road Major level crossing upgrade Completed
Level Crossing:
Turanville Road, Togar Scone Hunter Road Major level crossing upgrade Planning
Level Crossing:
Tynans Road, Table
Top
Table Top Riverina Murray Road Major level crossing upgrade Completed
Level Crossing:
Victoria Street /
Mitchell Highway,
Dubbo
Dubbo Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Warral Road, Warral Warral New England
North West
Road Major level crossing upgrade Completed
Name Suburb Region/District Project Type Project Description Current
Status
Level Crossing:
Wheelers Lane,
Dubbo
Dubbo Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing: Whiley
Road, Spring Hill Spring Hill Central West and
Orana
Road Major level crossing upgrade Planning
Level Crossing:
Whitton Street,
Narrandera
Narrandera Riverina Murray Road Major level crossing upgrade Completed
Level Crossing:
Yarrandale Road,
Dubbo
Dubbo Central West and Orana
Road Major level crossing upgrade Completed
Level Crossing:
Yerong Street, The
Rock
The Rock Riverina Murray Road Major level crossing upgrade Completed
Lidcombe Station Refresh Package 1
Lidcombe Central West and Orana
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Lidcombe to Granville
Corridor Upgrade
Program
Auburn Central City
District
Rail The program involves works to upgrade rail
infrastructure in the Lidcombe to Granville rail corridor.
The program will improve network reliability and
capacity and provide more efficient and reliable access to
and from the maintenance and stabling facilities. Key
features of the program include installation of new and
renewal of existing turnouts; removal of redundant track;
upgrade of track from timber sleepers to concrete
sleepers and upgrade of track drainage; replacement of
overhead wiring and related structures; upgrade of
signalling, communications and control systems; and
new high voltage works to support the new signalling
system.
In-Progress
Limekilns Road Clear Creek Central West and
Orana
Road Shoulder widening, install roadside w-beam guardrail,
curve widening & superelevation correction at various
locations over 11km length
Completed
Lindfield Interchange -
Commuter Parking
Lindfield North District Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Lindfield Station Refresh Package 3
Lindfield Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Lions Park Boat Ramp
& Car Park Upgrade,
Corowa
Corowa Riverina Murray Maritime Upgrade of the Lions Park boat ramp facility at South
Corowa. Works include: replacement of the existing sub-
standard boat ramp with a new concrete single lane
ramp, sealing and formalisation of car/trailer
parking,sealing of the site access road and ramp
approach, and installation of a pontoon/jetty at the ramp.
Planning
Lions Park Boat Ramp
Upgrade, Gwandalan Gwandalan Central Coast Maritime This project is to repair and restore the toe of an existing
boat ramp which has a dangerous drop away caused by a
combination of natural erosion and prop wash.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Lions Park Boat Ramp
Upgrade, Toronto Toronto Hunter Maritime Upgrade of the Lions Park boat ramp facility at Toronto.
Works include reconstruction of the existing boat ramp,
formalisation of car/trailer parking and imrpovements to
the access road and boat ramp approach area.
Planning
Lismore Interchange -
Transport Access
Program Upgrade
South Lismore North Coast Interchange Extension of the existing bus shelter, lighting
improvements and new cycle facilities.
Completed
Lithgow Interchange -
Commuter Parking
Lithgow Central West &
Orana
Parking Conversion of existing staff car park to provide 18 extra
commuter car parking spaces.
Completed
Lithgow Interchange -
Transport Access
Program Upgrade
Lithgow Central West &
Orana
Interchange The upgrade includes improved footpaths, new cycle
facilities and road repairs along Railway Parade. New
steel canopies were installed on the station platform to
provide better protection for customers against rain and
sun exposure.
Completed
Lithgow Station Refresh Package 1a
Lithgow Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Liverpool -
Campbelltown Rail
Trail cycleway
Casula Western City
District
Walking and Cycling Shared Path cycleway alongside Liverpool -
Campbelltown Rail Trail
Completed
Liverpool Interchange -
Commuter Parking
Liverpool Western City
District
Parking Conversion of existing staff car park to provide 19 extra
commuter car parking spaces.
Completed
Liverpool Interchange -
Commuter Parking
Liverpool Western City
District
Parking The new commuter car park provides 84 car parking
spaces, motorcycle spaces, modern lighting and CCTV
cameras.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Livestock and Bitumen Truck Wash Project
Narrandera Riverina Murray Freight The project is the construction of a two bay manual truck wash facility at Narrandera comprising a bay for livestock trucks and a bay for road base trucks. The planned works have been modelled with two sites as possible locations. These are Red Hill Industrial Estate 1. Bitumen Truck Wash2. Livestock Truck Wash3. Bitumen solid trap4. Livestock wash solid trap5. Oil separator for Bitumen wash area6. Digestion system- Livestock wash(Shared)7. Wet weather storage damThe facility will be made available 24/7 via Avdata.
Planning
Livingstone Road Marrickville Eastern City Road Install 3 pedestrian refuges on Livingstone Road and Hill
Road, Marrickville.
Completed
Loftus Interchange -
Commuter Parking
Loftus South District Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Longworth Park Wharf
Upgrade, Karuah Karuah Hunter Maritime Upgrade of the existing wharf at Longworth Park,
Karuah. Works include the replacement of both lower
landing poles and substructure, and replacement of split
girders and deck boards on upper decking.
Planning
Lord Howe Island Boat
Ramp Upgrade and
Slipway
Lord Howe
Island
Far West Maritime Planning
Lower Hunter Freight
Corridor
Hamilton Hunter Rail The Lower Hunter Freight Rail Corridor will improve
journey time and reliability for regional and interstate
rail freight movements through the Newcastle region. It
will divert freight services from sensitive suburban areas
by providing a dedicated freight link that bypasses
Newcastle. It would also allow most freight trains to
avoid the Adamstown and Islington level crossings. This
provides urban amenity and liveability improvements by
reducing noise and road congestion in the Newcastle
region.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Lower Hunter Freight Corridor
Minmi Hunter Freight Planning
Lower River Road Tocumwal Riverina Murray Road Localised widening of curve on bridge approach,
delineation improvements
Completed
Lyons Road Drummoyne Eastern City Road Pedestrian protection at traffic lights Completed
M1 Pacific Motorway
Extension to Raymond
Terrace
Heatherbrae Hunter Road A future extension of the M1 Pacific Motorway is
planned to the Pacific Highway at Raymond Terrace.
The proposed upgrade includes 15 kilometres of dual
carriageway motorway with two lanes in each direction,
bypassing Hexham and Heatherbrae; interchanges at
Black Hill, Tarro, Tomago, and Raymond Terrace; a 2.6
kilometre bridge over Woodlands Close, the Main
Northern Railway, New England Highway and Hunter
River; minimum flood immunity along the new roadway
between Black Hill and Tomago for a one in 100 year
flood event; and minimum flood immunity along the new
roadway between Tomago and Raymond Terrace for a
one in 20 year event. Key benefits of the proposal
include improved connection between the M1 Pacific
Motorway and the Pacific Highway; improved traffic
flow for motorists and freight for more reliable travel
times; improved accessibility to the surrounding road
network; and improved safety for all road users.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
M1 Pacific Motorway
Tuggerah Interchange
Upgrade
Mardi Central Coast Road The project included upgrading the intersections of the
interchange ramps with Wyong Road and construction of
a new entry ramp for traffic wishing to travel northbound
on the motorway. Key features include a new roundabout
at the southbound entry/exit ramp intersection with
Wyong Road, new traffic lights at the northbound
entry/exit ramp intersection with Wyong Road, new
northbound freeway on ramp that loops under the
existing Wyong Road bridge, a new southbound exit
ramp arrangement to improve safety at Wyong Road and
a formal commuter car park.
Completed
M1 Princes Motorway
Improvements, Picton
Road to Bulli Tops
Cataract Illawarra
Shoalhaven
Road The M1 Princes Motorway between Picton Road and
Bulli Tops is currently two lanes in each direction. This
section of road carries about 37,000 vehicles a day, 15
per cent of which are heavy vehicles. Traffic numbers
will continue to increase along this route. Due to the
steepness of the road and the tight turns, heavy vehicles
travel slowly, which can lead to a large difference in
speeds between light and heavy vehicles. The project
would provide additional lanes and improve the curves.
This would increase the safety, capacity and efficiency
of the M1 Princes Motorway. It will also improve freight
efficiency, connectivity and productivity within the
Wollongong and Illawarra region, particularly between
Port Kembla and key regional industries.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
M12 Motorway Kemps Creek Western City
District
Road The new motorway would provide direct access to the
planned Western Sydney Airport at Badgerys Creek and
connect to Sydney’s motorway network. The proposal is
for an east-west motorway of about 15 - 17 kilometres
between the M7 Motorway and The Northern Road
which would provide increased road capacity and reduce
congestion and travel times in the future. It would also
improve the movement of freight in and through Western
Sydney and is expected to serve the Western Sydney
Priority Land Release Area and the Western Sydney
Employment Area. Key features include a motorway
built for up to six lanes with a central median to separate
opposing traffic flows; a grade separated interchange at
the planned Western Sydney Airport; a new at grade
connection to The Northern Road; a motorway-to-
motorway interchange at the M7 Motorway; and an off-
road shared path for pedestrians and cyclists.
Planning
M4 cycleway Merrylands Central City
District
Walking and Cycling Shared Path cycleway alongside M4 Completed
Name Suburb Region/District Project Type Project Description Current
Status
M4 Smart Motorway Minchinbury Central City
District
Road The M4 Smart Motorway project will introduce
intelligent technology, known as a Smart Motorway
system, to Sydney’s M4 Motorway between Pitt Street,
Mays Hill and Russell Street, Lapstone. The M4 Smart
Motorway will introduce a smarter way of travelling the
M4 by using real-time information, communication and
traffic management tools to provide motorists with a
safer, smoother and more reliable journey. Key features
include variable message signs on the motorway and
approach roads to inform drivers about expected travel
times and traffic conditions ahead, allowing drivers to
better plan their journey or choose an alternative route;
ramp signals on entry ramps to smooth traffic flow onto
the motorway and make merging safer and easier and
reduce the risk of drivers having to brake suddenly; lane
use signs to open and close lanes in response to
incidents; variable speed limit signs to vary speed limits
if there is heavy traffic, an incident or bad weather;
additional traffic sensors and CCTV cameras to
continually monitor traffic conditions; additional
emergency telephones and stopping bays to provide
drivers with improved safety when their vehicle breaks
down or if there is an emergency stop required;
improvements to 12 interchanges; and widening of the
motorway between the M7 Motorway and Roper Road
interchanges to four lanes in each direction to improve
traffic flow.
In-Progress
Macarthur Interchange
- Commuter Parking
Campbelltown Western City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Macarthur Road
cycleway
Spring Farm Western City
District
Walking and Cycling Shared Path cycleway alongside Macarthur Road Completed
Macquarie Fields
Interchange -
Commuter Parking
Macquarie Fields Western City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Macquarie Park Non-
powered Boating
Access , Windsor
Freemans Reach West Maritime Construction of a non-powered boating facility at
Macquarie Park, Windsor. Works include: construction
of a fixed jetty and launching facility, formalised access
pathway from the car park to the jetty, car park upgrade,
and associated landscaping.
Planning
Macquarie Park Station Refresh Package 2
Macquarie Park South East and Tablelands
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Macquarie University Station Refresh Package 2
Macquarie Park South East and Tablelands
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Main West Freight
Capacity
Enhancements -
Georges Plains Loop
Georges Plains Central West &
Orana
Rail The purpose of the Main West Capacity Enhancements
Program is to implement improvements to the Main
Western rail network that will allow the corridor to meet
the NSW Government’s projected demand for rail freight
and passenger transportation in the short and medium
term.
Planning
Main West Freight
Capacity
Enhancements - Rydal
Rydal Central West &
Orana
Rail The purpose of the Main West Capacity Enhancements
Program is to implement improvements to the Main
Western rail network that will allow the corridor to meet
the NSW Government’s projected demand for rail freight
and passenger transportation in the short and medium
term.
Planning
Maitland Interchange -
Commuter Parking
Maitland Hunter Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Maitland Interchange -
Transport Access
Program Upgrade
Maitland Hunter Interchange The interchange upgrade includes improvements to the
commuter car park, taxi zone, new drop off and pick up
area and cycle facilities.
In-Progress
Maitland Park
cycleway
Maitland Hunter Walking and Cycling Shared Path cycleway alongside Maitland Park Completed
Maitland Road Cessnock Hunter Road Install 2 lane roundabout Planning
Maitland Roundabout
Upgrades - New
England Highway
Maitland Hunter Road Two roundabouts are being upgraded on the New
England Highway at Church Street and High Street,
including building an eastbound overpass at the Church
Street roundabout. The railway station roundabout
upgrade involves building an eastbound overpass;
building a left turn slip lane from Cessnock Road onto
the New England Highway; removing the roundabout
entry from Walker Street; providing a u-turn bay on
Cessnock Road for access to the roundabout from
Walker Street; and realigning the westbound New
England Highway approach and departure to the
roundabout. The hospital roundabout upgrade involves
installing traffic signals at the northern end of Johnson
Street; removing the mid-block pedestrian lights 60
metres east of Johnson Street; building left turn slip lanes
into High Street and Bungaree Street; removing
vegetation from the roundabout; and providing
pedestrian paths, fencing and a crossing through the
median to the west of the roundabout. The key project
benefits include improved safety for road users,
increased traffic capacity through the roundabouts,
improved traffic flow and more reliable travel times, and
improved access for pedestrians and cyclists.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Maitland Station Refresh Package 2a
Maitland Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Majara Street
cycleway
Bungendore South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Majara Street Completed
Malabar Boat Ramp
Upgrade
(Investigation)
Malabar Central Maritime The proposal is to investigate options to improve the
condition and accessibility of the existing boat ramp at
Long Bay Malabar through a detailed investigation and
design report. The existing boat ramp is the only publicly
accessible coastal boat ramp on the southern side of
Sydney Harbour. The objective of the investigation is to
identify options for physical improvements to the
existing boat ramp and for minimising multi-user
conflict while providing an accessible boat ramp facility
that accommodates powered and passive craft and
swimmers and divers who now frequently use the area.
Planning
Mandagery River
cycleway
Manildra Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Mandagery River Completed
Manning Point Boat
Ramp Relocation
(Investigation)
Manning Point Hunter Maritime Feasibility study into the relocation of the boat ramp
facility at Manning Point (to an upstream location).
Construction of a new concrete boat ramp, on ramp
centre pontoon, and sealed car park to follow
investigation works (dependant on the outcome of the
feasibility study and community support).
Planning
Manning Street Tuncurry Hunter Road Ban right turn out of Point Rd, and resurfacing Completed
Name Suburb Region/District Project Type Project Description Current
Status
Mannus Lake Boat
Ramp extension,
Tumbarumba
Tumbarumba Riverina Murray Maritime Extension of the existing boat ramp at Mannus Lake. Planning
Mannus Lake Boat
Ramp Pontoon
Upgrade, Tumbarumba
Tumbarumba Riverina Murray Maritime Installation of a new pontoon at the Mannus Lake boat
ramp.
Planning
Marayong Interchange
- Commuter Parking
Marayong Central City
District
Parking New commuter car park along Railway Road and Harvey
Road will include more than 70 new commuter spaces,
fencing, lighting and CCTV to boost security.
In-Progress
Margaret Crescent
cycleway
Dubbo Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Margaret Crescent Completed
Marine Drive Wharf
and Pontoon Upgrade,
Tea Gardens East
Tea Gardens Hunter Maritime Resurface existing wharf surface and expand pontoon to
improve passenger accessibility. Install new passenger
waiting shelter, to provide protection from the elements
while waiting for a ferry.
Planning
Marine Esplanade
cycleway
Cronulla South District Walking and Cycling Shared Path cycleway alongside Marine Esplanade Completed
Marrickville
Interchange - Transport
Access Program
Upgrade
Marrickville Eastern City
District
Interchange Marrickville Station is being upgraded to improve access
for customers. The project includes two new lifts, a new
staircase and a new concourse; kiss and ride facilities for
convenient drop offs and pick ups; bicycle parking;
accessible parking; a new taxi rank; and a new family
accessible toilet.
Completed
Marrickville Road Marrickville Eastern City Road Installation of a pedestrian refuge in Railway Parade at
Marrickville in close proximity to Sydenham Railway
Station.
Not Started
Marrickville Station Refresh Package 4
Marrickville Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Martin Place Station Refresh Package 1
Sydney North Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Marulan Interchange -
Transport Access
Program Upgrade
Marulan South East &
Tablelands
Interchange Improvements to Marulan Station included an accessible
ramp and footpath from Platform 1 to the existing
pedestrian level crossing, an accessible ramp and
footpath leading to Platform 2, new balustrade and hand
rails, and improved safety including tactile surfacing,
lighting and CCTV surveillance cameras.
Completed
Mattys Flat Boat Ramp
and Car Park
Improvements, South
West Rocks
South West
Rocks
North Coast Maritime Improvements to the Mattys Flat boat ramp facilty.
Works include: levelling the sides of the ramp to
minimise drop off, installation of guide posts on the
outer edges of boat ramp lanes, ramp lane marking and
installation of solar lights at the ramp, wharf and boat
wash down area.
Planning
Mcburney Road Cabramatta Western City Road Upgrade the existing pedestrian refuge on McBurney
Road located mid-block between Hill Street and
Gladstone Street, Cabramatta. Includes the
reconstruction of the pedestrian refuge, associated kerb
ramps, signs and line marking.
Completed
McLachlan Park
Boating Facilities
Improvements,
Maclean
Maclean North Coast Maritime Repalcement of the existing pontoon and provisions of
amenities.
Planning
McMahons Point
Wharf - Wharf
Upgrade Program
Mcmahons Point North District Maritime The wharf upgrade aims to provide easier access to the
wharf, better weather protection, additional seating, more
safety features as well as quicker and more efficient
boarding and disembarking.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Mcmahons Point
Wharf Interchange -
Transport Access
Program Upgrade
Mcmahons Point North District Interchange Interchange upgrade at wharf that includes installation of
new cycle facilities.
Completed
Meadowbank Station Refresh Package 4
Meadowbank Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Meadowbank Wharf -
Wharf Upgrade
Program
Meadowbank North District Maritime The upgraded wharf is made up of a floating pontoon,
aluminium gangway and concrete bridge connecting to
the existing wharf entry structure which has been
refurbished. The pontoon, bridge and gangway have
curved roofs to shelter customers from the weather.
Glass weather protection panels and new seating provide
improved comfort and amenity. The upgraded
interchange includes, new footpaths and ramps, bicycle
racks and updated kiss and ride and accessible parking
areas. The upgraded wharf and interchange provides
better protection from wind, rain and sun; improved
seating and waiting areas; improved safety for
customers; quicker and more efficient ferry boarding and
disembarking; improved access for mobility impaired
customers and customers with prams; improved
pedestrian access; efficient interchanges with other
modes of transport; and effective wayfinding signage
and lighting.
Completed
Medcalf Street Warners Bay Hunter Road Install right turn bay into Ruswell Ave Completed
Merrylands
Interchange -
Commuter Parking
Merrylands Central City
District
Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Merrylands
Interchange -
Commuter Parking
Merrylands Central City
District
Parking New commuter car park with around 125 spaces. In-Progress
Merrylands Station Refresh Package 3
Merrylands Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Mersey Road to
Glenmore Parkway -
The Northern Road
Upgrade
Luddenham Western City
District
Road The Northern Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney airport at Badgerys Creek.
It would also improve safety, increase road capacity and
reduce congestion and travel times in the future. This
stage of The Northern Road Upgrade is 16 kilometres
between Mersey Road, Bringelly and Glenmore
Parkway, Glenmore Park. Key features include diverting
The Northern Road to the east of Luddenham, close to
the planned Western Sydney airport site boundary;
widening from two lanes to a six lane divided road (two
general traffic lanes and a kerbside bus lane in each
direction), with a wide median to allow for an additional
lane in each direction if required in the future; providing
kerbside bus lanes, bus priority lanes at traffic lights and
indented bus bays, where required; providing a
continuous bypass to access the Luddenham town centre;
installing new traffic lights and turning lanes at some
intersections; providing a new shared path for
pedestrians and cyclists on the western side of the road
and a new footpath on the eastern side of the road;
installing new street lighting, particularly at
intersections; providing for a future connection with the
proposed M12 Motorway; and upgrading drainage.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Middle Street Kingsford Eastern City Road Upgrade from give-way to stop sign and move stop lines
forward using kerb extensions
Completed
Milsons Point Station Refresh Package 2
Milsons Point South East and Tablelands
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Milsons Point Wharf
Expansion
Milsons Point North District Maritime The capacity of Milsons Point Wharf is being increased,
providing a second platform to enable two ferries to
berth at the same time. The upgrade will mean more
frequent, reliable services for ferry customers and
improved boarding and disembarking times during peak
periods.
Planning
Milsons Point Wharf
Interchange - Transport
Access Program
Upgrade
Milsons Point North District Interchange Improvements to Milsons Point Wharf Interchange
included a 'kiss and ride' upgrade, footpath regrading and
a new bus shelter.
Completed
Minnamurra
Billabong cycleway
Jamberoo Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Minnamurra
Billabong
Completed
Minto Interchange -
Commuter Parking
Minto Western City
District
Parking Conversion of existing staff car park to provide seven
extra commuter car parking spaces.
Completed
Minto Station Refresh Package 3
Minto Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Miranda Station Refresh Package 4
Miranda Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Mittagong Interchange
- Transport Access
Program Upgrade
Mittagong South East &
Tablelands
Interchange Improvements at Mittagong Station included
construction of a new accessible ramp to Platform 1, new
footpath and kerb ramp, formalised ‘kiss and ride’ and
bus stop zones, improvements to the existing accessible
parking space, new balustrade, fencing and hand rail to
match existing building architecture, new bike rack for
eight bikes, improved safety features including tactile
surfacing, lighting and CCTV surveillance cameras, and
minor landscaping.
Completed
Mittagong Station Refresh Package 4a
Mittagong North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Moama Beach Boating
Access Improvements,
Moama
Moama Riverina Murray Maritime Improvements to access and separation of activities at
Moama Beach. Access works include: upgrade the site
access road from a single lane to a two lane road,
formalisation of car parking and a vehicle turnaround
area, and uprade to the pedestrian pathway from the
Moama CBD to the beach. Water-based works include:
construction of a river bank retaining wall, construction
of a river bank retaining wall, construction of a disability
access ramp to the beach from the Reserve's picnic areas,
and the installation of a pontoon for short term berthing
and passive vessel launching.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Mogareeka Boat Ramp
Facility Upgrade Mogareeka South East and
Tablelands
Maritime Upgrade of the Mogareeka boat ramp facility. Works
include replacement of the existing boat ramp with a new
two lane concrete ramp, enlargement and reconfiguration
of the existing site access, car park and ramp approach,
and upgrade of lighting at the site.
Planning
Mona Vale Road Terry Hills North Road The widening of the eastbound shoulder of Mona Vale
Road, Terry Hills for approximately 90 metres at the
approach to the intersection with Forest Way so as to
provide sufficient width for cyclists. The cycle lane will
be delineated for the length of the
Completed
Mona Vale Road
Upgrade - Stage 1
Mona Vale North District Road The upgrade involved widening Mona Vale Road to two
lanes westbound from Foley Street through the
Ponderosa Parade roundabout and to two lanes
eastbound through the roundabout. The work provides a
safe opportunity for cars to pass heavy vehicles before
the steep grade to the west of the Mona Vale
Road/Ponderosa Parade roundabout.
Completed
Mona Vale Road
Upgrade - Stage 2
Ingleside North District Road The upgrade of 3.2 kilometres of Mona Vale Road is
being planned between Manor Road/Lane Cove Road,
Ingleside and Foley Street, Mona Vale from a two lane
undivided road (one lane in each direction) to a four lane
divided road (two lanes in each direction). Mona Vale
Road East currently experiences congestion as a result of
the steep grade and limited safe vehicle overtaking
opportunities which increases travel times. The proposed
road upgrade for Mona Vale Road East would provide
additional lanes for climbing and descending to improve
travel time in both directions; widened shoulders and
median separation to improve safety; 80km/h speed limit
between Mona Vale and Belrose once the road upgrades
for both Mona Vale Road East and Mona Vale Road
West are completed; facilities for cyclists and
pedestrians; and bus priority measures.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Mona Vale Road
Upgrade - Stage 3
Ingleside North District Road 3.2 kilometres of Mona Vale Road between McCarrs
Creek Road and Powder Works Road from a two lane
undivided road (one lane in each direction) to a four lane
divided road (two lanes in each direction). Mona Vale
Road West currently experiences congestion in peak
periods and requires upgrading to increase capacity and
reduce travel times. The proposed road upgrade for
Mona Vale Road West would provide additional lanes
for climbing and descending to improve travel time in
both directions; widened lanes and shoulders and median
separation to improve safety; 80km/h speed limit
between Mona Vale and Belrose once the road upgrades
for both Mona Vale Road East and Mona Vale Road
West are completed; and facilities for cyclists,
pedestrians and recreational horse riders.
Planning
Monaro Highway and
Kosciuszko Road –
overtaking lanes and
safety improvements
Chakola South East &
Tablelands
Road The project will improve road safety and traffic
efficiency for road users in the Snowy Mountains region
by providing an additional westbound lane on
Kosciuszko Road from Barry Way to Alpine Way;
providing additional overtaking lanes on Monaro
Highway and Kosciuszko Road (locations to be
determined); and carrying out additional road safety
improvements at other sections along both roads.
In-Progress
Moorebank Access
Roads and Intermodal
Terminal
Holsworthy Western City
District
Rail The Moorebank intermodal freight precinct will enable
freight to make part of its journey by rail. The freight
precinct will handle import-export (IMEX) and interstate
shipping containers, and include warehousing for
temporary onsite storage. It will provide direct access to
Port Botany via the Southern Sydney Freight Line,
which will connect to the terminal at the southern end of
the precinct. It will be a single development comprising
Moorebank Intermodal Company’s and the Sydney
Intermodal Terminal Alliance’s adjoining sites. The
facilities will be open access, enabling any rail or road
operator to use the IMEX or interstate terminals to
provide freight transport services.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Moree Saleyards Truck Wash
Moree New England
North West
Freight The Project scope will upgrade the existing truck wash by duplicating and extending the existing washdown slab, retaining the existing back-in / drive-out access and include a truck waiting / layover area on the approach and bitumen surfacing immediately prior to the washdown slab. It also includes:• Dual lanes• 25 metre length to suit the target user vehicle • 5 metre lane width to suit the target user vehicle• Walkway / splash over slabs each side• Water supply buffer storage tanks• High flow hoses on reels accessible from each lane and associated • Compressed air hose on reel accessible from each lane and associated compressor • New control shed• Avdata control box• Lighting• Security video camera• Mud pit adjacent to the washdown slab• Secondary storage/mud settling tank• Oil separator• Weed separator• Sludge drying beds• Effluent discharge pump well pumping to existing lagoons• Associated pipework
Planning
Moree Town Centre
Bypass - Stage 2
Moree New England North
West
Road Key features of Stage 2 of the Moree Town Centre
Bypass include providing a new 1.8 kilometre, 60km/h
route through east Moree between Gosport Street and the
railway line and allowing Gosport Street to remain as a
service road; the current signalised T-intersection of
Stage 1 of the bypass and the Gwydir Highway has been
upgraded to a four way signalised intersection;
upgrading the intersection with Bullus Drive and Frome
Street at the southern end of the bypass; provision for
pedestrians and cyclists; and significant urban design
features and landscaping.
Completed
Morisset Interchange -
Commuter Parking
Morisset Hunter Parking Conversion of existing staff car park to provide five
extra commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Morisset Station Refresh Package 1a
Morisset Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Mortdale Station Refresh Package 3
Mortdale Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Mosman Bay Wharf -
Wharf Upgrade
Program
Mosman North District Maritime The new wharf incorporates the existing waterside
building, a new longer aluminium gangway and a
refurbished pontoon. The gangway and pontoon has a
curved roof, glass panels and new seating. The new
wharf provides improved protection from the wind, rain
and sun; improved safety for passengers; improved
access for passengers using mobility aids; improved
access for passengers with prams; and boarding and
disembarking efficiency.
Completed
Moss Vale Interchange
- Commuter Parking
Moss Vale South East &
Tablelands
Parking The Moss Vale commuter car park is located at the
corner of Argyle Street and Dalys Way, approximately
200 metres from Moss Vale Station. The car park
provides 56 spaces and includes security lighting and
CCTV surveillance. Two additional accessible parking
spaces were also provided near the station entrance as
part of this project. Other improvements include the
upgrading of existing bicycle racks, improved lighting on
Dalys Way and a new pedestrian crossing to the car park
on Dalys Way.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Moss Vale Interchange
- Commuter Parking
Moss Vale South East &
Tablelands
Parking Conversion of existing staff car park to provide 15 extra
commuter car parking spaces.
Completed
Moss Vale Road Beaumont Illawarra
Shoalhaven
Road Upgrade signage along the route: fluoro signs, correct
existing signage
Completed
Moss Vale Station Refresh Package 2a
Moss Vale Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Mount Druitt
Interchange -
Commuter Parking
Mount Druitt Central City
District
Parking New multi-storey commuter car park located at the
north-east of Mount Druitt Station provides 220
commuter car parking spaces. The car park includes stair
and lift access between floors, security lighting and
CCTV surveillance.
Completed
Mount Druitt
Interchange -
Commuter Parking
Mount Druitt Central City
District
Parking Conversion of existing staff car park to provide 7 extra
commuter car parking spaces.
Completed
Mount Lindesay Road Legume New England North
West
Road Shoulder widening & superelevation correction Completed
Mount Victoria
Interchange -
Commuter Parking
Mount Victoria Western City
District
Parking Conversion of existing staff car park to provide 25
commuter car parking spaces, including two accessible
parking spaces. The project also included upgrades to the
carpark surface and line-marking as well as
improvements to lighting and fencing.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Mount Victoria Station Refresh Package 2a
Mount Victoria Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Mulgoa Road /
Castlereagh Road
Corridor Upgrade
Penrith Western City
District
Road Planning is being undertaken for the 6.5 kilometre
upgrade and widening of Mulgoa Road / Castlereagh
Road between Glenmore Parkway, Glenmore Park and
Andrews Road, Penrith to support current and future
traffic demands and expected growth in the area. The key
benefits of the upgrade include managing congestion and
delays along Mulgoa Road / Castlereagh Road during
morning and afternoon peak periods; reduced travel
times and lower transport costs; improved road safety for
all users; supporting residential and employment growth
and providing reliable network performance to support
economic growth and productivity by providing road
capacity for predicted 2036 traffic volumes; improved
access for public transport; improving freight efficiency;
providing safe and effective pedestrian and cycling
infrastructure; and improved urban design and visual
aspects of the road corridor.
Planning
Mulgoa Road
cycleway
Penrith Western City
District
Walking and Cycling Shared Path cycleway alongside Mulgoa Road Completed
Mulgoa Road
cycleway
Penrith Western City
District
Walking and Cycling Shared Path cycleway alongside Mulgoa Road Completed
Mulgoa Road
cycleway
Jamisontown Western City
District
Walking and Cycling Shared Path cycleway alongside Mulgoa Road Completed
Name Suburb Region/District Project Type Project Description Current
Status
Mulgrave Interchange -
Transport Access
Program Upgrade
Mulgrave Western City
District
Interchange Improvements to accessibility at Mulgrave Station
included the construction of a new accessible ramp, and
improved safety through the installation of additional
CCTV surveillance cameras and lighting.
Completed
Mungabareena Reserve
Boat Ramp Lighting
Improvements, Albury
East Albury Riverina Murray Maritime Installation of solar lighting at the recently upgraded
Mungabareena Reserve boat ramp. New lighting will
allow greater use of the boat ramp at dawn and dusk.
Planning
Murray Riverside
Precinct Development
(Planning), Albury
Albury Riverina Murray Maritime Stage 2 in the development of the Murray River
Riverside Precinct. This stage involves the development
of preliminary designs for public infrastructure at the site
(including recreational boating infrastructure).
Planning
Museum Interchange -
Transport Access
Program Upgrade
Sydney Eastern City
District
Interchange Museum Station is being upgraded to improve access for
customers. The project includes a new lift connecting the
entry of the station on the corner of Elizabeth and
Liverpool streets and the underground station concourse;
two new lifts connecting the station concourse with the
platforms; an accessible ramp at the station entrance; a
new family accessible toilet; and refurbishment of the
toilets within the concourse.
Completed
Museum Station Refresh Package 3
Sydney Eastern City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Muswellbrook Bypass -
New England Highway
Muswellbrook Hunter Road A future bypass of Muswellbrook is being planned. The
bypass would have significant benefits including
removing conflicts between local traffic and through
traffic in the Muswellbrook town centre; removing heavy
vehicle traffic away from the town centre and nearby
residential areas; reducing traffic noise levels in the
town; and improving travel times on the New England
Highway.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Nambucca Heads to
Urunga - Pacific
Highway Upgrade
Urunga North Coast Road The Pacific Highway was upgraded to a four lane
divided carriageway between Nambucca Heads, just
south of the railway line and the existing waterfall Way
interchange at Raleigh. Key features include a four lane
divided carriageway with safe driving conditions for
speeds of 110 km/h; no direct property access to or from
the highway; grade-separated interchanges at Waterfall
Way at Raleigh, Ballards Road, south of Urunga, and
Nambucca Heads; a continuous local road between
Nambucca Heads combining new roads and the existing
Pacific Highway; a rest area for light and heavy vehicles
at the Nambucca Heads interchange; a new bridge over
the Kalang River at Urunga; and floodplain bridges and
culverts across sections of the Kalang floodplain. Key
benefits of the upgrade include improved road safety;
uninterrupted highway traffic flow; and easy access on
and off the highway for local traffic.
Completed
Narara Station Refresh Package 2a
Narara South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Narara to Lisarow -
Pacific Highway and
Manns Road Upgrade
between Narara Creek
and Parsons Road
Niagara Park Central Coast Road An upgrade of the Pacific Highway and Manns Road
between Narara Creek Road at Narara and Parsons Road
at Lisarow is being planned. The proposed upgrade
involves widening the Pacific Highway and Manns Road
to provide two lanes in each direction to improve traffic
flow and safety for all road users. Key benefits of
upgrade include improved traffic flow on the Pacific
Highway and Manns Road, improved safety for all road
users and a improved pedestrian and cycle network.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Narellan Road Upgrade
- Stage 1
Campbelltown Western City
District
Road Narellan Road is a key road transport corridor servicing
south western Sydney. Traffic is predicted to grow in this
area due to residential and commercial development in
Western Sydney. Stage 1 covers 1.6 kilometres between
the M31 Hume Motorway, and the TAFE/Western
Sydney University access road, Campbelltown. Key
features of Stage 1 include the upgrade of Narellan Road
to a six lane divided road with three lanes in each
direction and a central median from the M31 Hume
Motorway to the TAFE/Western Sydney University
campus; new traffic lights at the Narellan Road and M31
Hume Motorway interchange; widened southbound exit
and loop ramp from one lane to three; a shared
pedestrian and cyclist path on the southern side of
Narellan Road (will connect to new pedestrian bridge as
part of the Narellan Road Upgrade Stage 2); an extra
right turn lane into the TAFE/Western Sydney
University campus for eastbound traffic and extension of
the right turn bay by about 180 metres; upgraded
TAFE/Western Sydney University roundabout from a
single lane to dual lanes; two left turn lanes and an extra
right turn lane onto Narellan Road from the
TAFE/Western Sydney University; new Incident
Response Facility at the south east corner of the M31
Hume Motorway interchange, which will provide
immediate response to any accidents on the M31 Hume
Motorway and surrounding areas; and new bus bays to
improve safety and access for commuters.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Narellan Road Upgrade
- Stage 2
Currans Hill Western City
District
Road Narellan Road is a key road transport corridor servicing
south western Sydney. Traffic is predicted to grow in this
area due to residential and commercial development in
Western Sydney. Stage 2 covers 5.2 kilometres from the
M31 Hume Motorway to Camden Valley Way and from
the TAFE/Western Sydney University access road to
Blaxland Road, Campbelltown. Key features of Stage 2
include widening Narellan Road to a six lane divided
road, generally three lanes in each direction with a
central median; upgrading the M31 Hume Motorway
interchange and widening the northern bridge over the
motorway for additional lanes; building a pedestrian
bridge to provide a shared path over the M31 Hume
Motorway on the southern side of Narellan Road;
installing new traffic lights with pedestrian crossings at
Kenny Hill Road; installing a three metre wide off-road
share pedestrian/cyclists path; extending the southbound
merge lane onto the M31 Hume Motorway by about 500
metres; constructing a Heavy Vehicle Inspection Bay on
the westbound carriageway between Botanical Gardens
and Hume Motorway Interchange; and ten intersection
improvements between Camden Valley Way, Camden
and Blaxland Road, Campbelltown.
In-Progress
Narromine Truck Wash
Narromine Central West and
Orana
Freight To provide a 24 hour 7 day facility for the wash down of stock crates and also to trap and prevent the spread of seeds from noxious weeds.To provide a system which will prevent oils and suspended solids from entering the environment.
Planning
Narwee Interchange -
Transport Access
Program Upgrade
Narwee South District Interchange Accessibility at Narwee Station is being improved and
will include new stairs and a new lift; new canopies for
weather protection; refurbishment of the heritage
platform building to include new toilet facilities;
improvements to bicycle facilities and interchange areas;
new wayfinding signage; and upgrades to lighting and
CCTV surveillance.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Nelson Bay Road Anna Bay Hunter Road The installation of 950 metres of roadside wire rope
barrier on three sections of Nelson Bay Road, Anna Bay
Completed
Nepean River Bridge
cycleway
Camden Western City
District
Walking and Cycling Shared Path cycleway alongside Nepean River
Bridge
Completed
Neutral Bay Wharf -
Wharf Upgrade
Program
Neutral Bay North District Maritime Construction of a new 30 metre jetty and a new pontoon.
The jetty is fully covered, including side protection from
wind and rain for commuters. Disabled access is
provided by using a system of ramps.
Completed
New Dubbo Bridge Dubbo Central West &
Orana
Road A new bridge across the Macquarie River is being
planned. A new bridge would improve freight efficiency
on the Newell Highway, reduce traffic congestion and
provide an alternative route during flooding events and
maintenance work on existing bridges.
Planning
New Engalnd
Highway cycleway
Tarro Hunter Walking and Cycling Road Shoulder cycleway alongside New Engalnd
Highway
Completed
New England Highway Murrurundi Hunter Road Install kerbside barrier at selected locations along the
length
Completed
New England Highway Whittingham Hunter Road Upgrade uncontrolled intersection to provide channelised
right turns
Completed
New England Highway Whittingham Hunter Road Upgrade uncontrolled intersection to provide channelised
right turns
Completed
Name Suburb Region/District Project Type Project Description Current
Status
New England Highway
and rail bridge upgrade
at Gowrie Gates
Gowrie Hunter Road The rail bridge is being upgraded to provide increased
horizontal clearance to accommodate two travel lanes
with wide sealed shoulders and facilities for pedestrians
and cyclists. Key features of the upgrade include a new
rail bridge over the New England Highway providing a
minimum 5.3 metre vertical clearance; rebuilding and
widening about 260 metres of the New England
Highway to provide two 3.5 metre lanes; providing three
metre shoulders along the highway through this section
to bring the road up to current road safety standards; and
relaying up to 200 metres of rail track.
Planning
New England Highway
Bypass of Scone and
Town Centre Rail
Bridge
Scone Hunter Road Key features of the upgrade include a two lane highway
bypass to the west of Scone, which would pass through
the Scone Golf Course and bridge over the rail line south
of town, Kingdon Street and Liverpool Street; access to
and from the bypass to the north and south of town and
midway at St Aubins Street which would provide for all
turning movements; and a road over rail bridge. Key
benefits of the upgrade include Key benefits of the
upgrade include improved traffic flow and amenity for
local traffic; improved travel times for freight and long
distance traffic; and improved safety for all road users.
The Town Centre Bridge component is being reviewed.
In-Progress
New England
Highway cycleway
Tenterfield New England
North West
Walking and Cycling Shared Path cycleway alongside New England
Highway
Completed
Name Suburb Region/District Project Type Project Description Current
Status
New England Highway
Upgrade between
Belford and the Golden
Highway
Whittingham Hunter Road The New England Highway between Belford and the
Golden Highway is being upgraded to provide two travel
lanes in each direction and a flyover for vehicles turning
right from the Golden Highway towards Maitland and
Newcastle. The proposed upgrade would increase
capacity and connectivity of the New England Highway
and Golden Highway for the efficient and reliable
movement of freight; improve safety at the New England
Highway and Golden Highway intersection by reducing
the risk of crashes, particularly for motorists turning
right from the Golden Highway; increase capacity at the
New England Highway and Golden Highway
intersection to cater for the predicted increase in traffic
movements due to future growth in the Hunter; and
allow for access to existing and future adjoining land
uses.
Planning
New Intercity Fleet Haymarket Eastern City
District
Rail The new intercity fleet will replace the trains carrying
customers from Sydney to the Central Coast, Newcastle,
the Blue Mountains and the South Coast. The new
double deck trains will give long distance customers a
more comfortable travelling experience. The trains will
be safe, comfortable, accessible and provide an
appealing environment for customers during longer
journeys with features including wider seats with arm
rests and more space; charging stations for mobile
devices for each seat; cup holders and tray tables; two by
two seating on upper and lower levels; dedicated space
for luggage, prams, bicycles and wheelchairs; accessible
toilets; digital screens and announcements; CCTV and
passenger intercoms; and modern air conditioning. The
new trains will come into service progressively, with the
first trains anticipated to be delivered in 2019.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
New Pontoons at
McLeans Beach Boat
Ramp & Lawson
Syphon Boat Ramp,
Deniliquin
Deniliquin Riverina Murray Maritime Planning
New Street cycleway Ulladulla Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside New Street Completed
Newcastle Light Rail Newcastle Hunter Light Rail Newcastle Light Rail is an important new transport
initiative that will transform the city centre. It will
strengthen connections between the city and the
waterfront, create new jobs, provide more public space
and amenity, and deliver more public transport –
activating Hunter and Scott streets and bringing people
back into the city centre. Introducing light rail in the city
centre will transform the way Newcastle functions. It
will help connect the main activity precincts and reunite
the city centre with the harbour – helping create a world-
class harbourfront city. Light rail will deliver safe,
frequent transport for Newcastle and help to revitalise
the city centre. Newcastle Light Rail is 2.7 kilometres of
light rail track from the new transport interchange at
Wickham to Pacific Park. There will be six stops along
the way, starting at the transport interchange,
Honeysuckle (near Hunter Street TAFE), Civic, Crown
Street, Market Street and Pacific Park. This high capacity
transport system will help cut city centre congestion and
provide a frequent, reliable and comfortable travel option
through the city centre.
In-Progress
Newell Highway Marsden Riverina Murray Road Wire rope safety barrier, traversable batters, audiotactiles Completed
Newell Highway
cycleway
Coonabarabran Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Newell Highway Completed
Name Suburb Region/District Project Type Project Description Current
Status
Newell Highway
cycleway
Coonabarabran Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Newell Highway Completed
Newell Highway,
Overtaking Lanes
Boggabilla New England North
West
Road Five overtaking lanes on the Newell Highway have been
constructed. The locations are: north and southbound
overtaking lanes 79-82 kilometres north of Moree
(Girahween – completed June 2014); northbound
overtaking lane 70 kilometres north of Gilgandra (Tap
Hill – completed June 2015); southbound overtaking
lane 15 kilometres north of Parkes (Telescope Straight –
completed April 2015); and northbound overtaking lane
10 kilometres south of Narrandera.
Completed
Newtown Interchange -
Transport Access
Program Upgrade
Newtown Eastern City
District
Interchange Newtown Station was upgraded to make train travel
more comfortable, safe and convenient for customers.
The upgrade included a centrally located concourse, new
covered walkways, a new lift, upgraded toilet and retail
premises, new platform canopies and improved CCTV,
lighting, signage, tactile tiles and bike racks.
Completed
Newtown Station Refresh Package 2
Newtown Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Nimbin Road Blakebrook North Coast Road Install guardrail, CAMs and guideposts Not Started
Nimbin Road Coffee Camp North Coast Road Install guardrail, CAMs and guideposts Not Started
Name Suburb Region/District Project Type Project Description Current
Status
Normanhurst
Interchange - Transport
Access Program
Upgrade
Normanhurst North District Interchange Improvements to the transport interchange facilities at
Normanhurst Station included upgrading of road
pavement and kerb and gutter at bus stops on Denman
Parade; upgrading of footpaths; providing new bike
racks; and installing new blisters at the existing
pedestrian crossing on Denman Parade to improve
pedestrian safety.
Completed
North Arm Cove New
Boat Ramp and Jetty
(Investigation), Port
Stephens
Port Stephens Hunter Maritime Planning
North Stockton Boat
Ramp Facility Upgrade Stockton Hunter Maritime Upgrade of the North Stockton boat ramp facility. Works
include: sealing and formalisation of the site's car park
(providing 42 car/trailer spaces, 16 car only parking
spaces and 1 disabled car park space), demolition of the
existing amenities block and replacement with a new
amenities facility, installation of a new fish cleaning
table and other site improvements (signage, rubbish bins,
landscaping).
Planning
North Strathfield
Interchange - Transport
Access Program
Upgrade
North Strathfield Eastern City
District
Interchange The North Strathfield transport interchange was
upgraded to include new shelter over a pedestrian
walkway, new and formalised 'kiss and ride' zones,
bicycle racks, a new pedestrian access ramp, upgrade of
bicycle facilities and upgrade of footpaths.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
North Strathfield Rail
Underpass
Concord West Eastern City
District
Rail The North Strathfield Rail Underpass involved the
construction of a rail underpass at North Strathfield, and
a new aerial concourse at Concord West Station,
including four new lifts and platform upgrades. The
underpass and associated tracks improve network
reliability for freight and passenger trains by removing
the need for freight trains to cross over the existing
tracks on the Main North Line. This project is part of the
Northern Sydney Freight Corridor Program, which is an
initiative to improve the capacity and reliability of
freight trains between Strathfield and Broadmeadow,
Newcastle. The program will increase capacity for
interstate container freight and remove the most serious
bottleneck on the East Coast interstate, which connects
Australia’s three largest cities (Melbourne, Sydney and
Brisbane).
Completed
North Strathfield Station Refresh Package 4
North Strathfield Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
North Sydney Station Refresh Package 2
North Sydney Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
North Wollongong Station Refresh Package 1a
North
Wollongong Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
NorthConnex, M1 to
M2 Motorway Link
Thornleigh North District Road NorthConnex is a nine kilometre tunnel that will link the
M1 Pacific Motorway at Wahroonga to the Hills M2
Motorway at West Pennant Hills, removing around 5,000
trucks off Pennant Hills Road. Key features of
NorthConnex include twin motorway tunnels with a
three lane capacity for future traffic growth; a northern
interchange connecting the M1 Pacific Motorway, the
Pacific Highway and Pennant Hills Road; a northern
ventilation outlet and support facilities located within
and immediately adjacent to the existing M1 Motorway
corridor; a southern interchange connecting with Pennant
Hills Road and the M2 Motorway; a motorway control
centre, ventilation outlet and support facilities located
near the southern interchange; integration on the M2
Motorway to provide an extra 3.5 kilometre lane, as well
as on and off-ramps, and bridge widening works from
Pennant Hills Road to the Windsor Road interchange; on
and off-ramps linking the tunnel and the existing M1
Pacific Motorway, north of Edgeworth David Avenue
and the M2 Motorway at Pennant Hills Road; and tunnel
support facilities to provide air intake systems,
emergency smoke extraction outlets and substations.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Northern Beaches B-
Line
Dee Why North District Bus The B-Line is an integrated program of service and
infrastructure improvements. The B-Line will provide
more frequent and reliable bus services for customers
travelling between the Northern Beaches and the Sydney
CBD. The program includes roadworks including new
bus lanes, bus bays, minor lane widening and other road
improvements to support bus services; nine modern B-
Line stops at Mona Vale, Warriewood, Narrabeen,
Collaroy, Dee Why, Brookvale, Manly Vale, Spit
Junction (Mosman) and Neutral Bay including real-time
passenger information and improved facilities for
customers; six new commuter car parks at Mona Vale,
Warriewood, Narrabeen, Dee Why, Brookvale and
Manly Vale providing around 900 spaces, as well as
bicycle parking, to encourage customers to park and ride;
works to ensure integrated pedestrian and bicycle links to
commuter car parks and B-Line stops; modifications to
the bus network to provide for a turn-up-and-go B-Line
service with an average five minute wait for the bus
during the day; and a new B-Line double decker bus fleet
for improved on-board capacity and comfort.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Northern Beaches
Hospital Road
Upgrades
Frenchs Forest North District Road Roads around the new Northern Beaches Hospital are
being upgraded. Key features include widening Frenchs
Forest Road from two to four lanes between Forest Way
and Allambie Road, including new traffic lights with
signalised pedestrian crossings at key intersections;
widening and upgrading the intersection of Frenchs
Forest Road with Wakehurst Parkway wich will allow a
right turn from Wakehurst Parkway into French Forest
Road West to access the new hospital; widening and
intersection upgrades along sections of Forest Way
between Warringah Road and south of Adams Street,
including a right turn bay for traffic turning from Forest
Way into Naree Road; providing an additional four lanes
on Warringah Road within a separated underpass for
about 1.3 kilometres below the intersections of Forest
Way, Hilmer Street and Wakehurst Parkway; and two
new shared bridges across Warringah Road near Forest
Way and Hilmer Street and new shared paths and
footpaths on sections of Warringah Road, Wakehurst
Parkway, Forest Way, Aquatic Drive and Allambie
Road.
In-Progress
Northern Sydney Freight Corridor
Eastwood North District Freight Planning
Name Suburb Region/District Project Type Project Description Current
Status
NRLX Truck Wash Upgrade
Casino North Coast Freight The proposed project is to upgrade the current facility and allow 24 hour access to the amenities. The current facility has two truck wash bays, using recycled water at both. An additional truck wash bay is to be added, able to facilitate B-Double Trucks and Trailers. The new bay would have both recycled and town water, allowing for cabins to be washed, as well as the trailers. Lighting will be replaced with LED Lighting and a Water Meter added. Some road works and tree removal will be necessary. AVDATA technology that is used on site for measurement and invoicing will require upgrading. Inclusions:- Replacing 2 light poles and installation of 1 new pole to service the new bay- Supply 3 500w LED floodlights- Upgrade overhead power network- Washbay construction and concrete and bitumen seal works- Replace guardrail and install 10 heavy duty bollards- Water connection to town water supply to provide option of recycled or town water- Extra AVDATA port for new B Double wash bay- Tree removal and replacement program- Provision of rubbish collection service- Install of door to amenities block and installation of access board from AVDATA to provide amenities access to truckwash users
Planning
Oak Flats Interchange -
Commuter Parking
Oak Flats Illawarra
Shoalhaven
Parking The Oak Flats commuter car park project involved the
construction of an additional 230 parking spaces, new
lighting, landscaping and fencing.
Completed
Oak Flats Interchange -
Commuter Parking
Oak Flats Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Oatley Bay Boat Ramp
Facility Upgrade,
Georges River
Hurstville Grove South Maritime Upgrade of the Oatley Bay boat ramp facility. Works
include: resurfacing, side kerbing and line marking of the
existing 3 lane boat ramp; installation of a new pontoon
(9m x 3m) and gangway (16m) facility (which includes a
pontoon-to-boat wheelchair crane) providing disability
access; and the development of a Site Management Plan
to assess future facility upgrades (including new toilets,
wash down areas and car/trailer parking).
Planning
Oatley Interchange -
Transport Access
Program Upgrade
Oatley South District Interchange Oatley Station is being upgraded to improve access for
customers. The project includes new lift and stair access
to Oatley Parade, Mulga Road and the station platforms
and new station forecourts on both Oatley Parade and
Mulga Road with landscaping to suit the current features;
a new pedestrian footbridge providing access from the
new Oatley Parade and Mulga Road forecourts;
installation of an accessible toilet on the station platform;
canopy extensions to provide weather protection for
customers on the station platform; interchange upgrades
including reconfiguration of kiss and ride, accessible
parking, taxi and bus stops locations, additional cycle
storage, lighting, CCTV surveillance cameras and new
wayfinding signage; and construction of a commuter car
park with 100 spaces.
In-Progress
Ocean Street Woollahra Eastern City Road Reconstruction of existing pedestrian refuge island on
Ocean Street, Woollahra.
Completed
O'Connell Road Oberon Central West and
Orana
Road Shoulder widening to 1m shoulder, correct
superelevation, improve vertical alignment, improve
horizontal alignment (from R215m to R350M), install
incremental traversible clearzones and upgrade seal to
non-skid surface. To be delivered in conjunction wit
Completed
O'Connell Road O'Connell Central West and
Orana
Road Community consultation and completion of REF to
investigate construction of a shared path and a cyclist
and pedestrian bridge connecting OÔÇÖConnell village
to OÔÇÖConnell Public School.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
O'Connell Street
cycleway
Parramatta Central City
District
Walking and Cycling Shared Path cycleway alongside O'Connell Street Completed
Off-water Boat Storage
Improvement at Little
Manly
Manly North Maritime Provide formal dry storage for all types of boats
including dinghies & kayaks - to include appropriate
boat wash down facilities.
Planning
Ogden Street Public
Jetty Upgrade, Tea
Gardens
Tea Gardens Hunter Maritime Installation of a new jetty south of existing to increase
public boating in this area.
Planning
Old Brewery Road
Boat Ramp Pontoon
Upgrade, Narrandera
Narrandera Riverina Murray Maritime Upgrade of the existing pontoon at the Old Brewery Flat
boat ramp to allow access to the pontoon under all river
conditions.
Planning
Old Ferry Road
Reserve Boating
Access Improvements,
Illawong
Illawong South Maritime Construction of a small craft low impact boating facility
at Old Ferry Road Reserve, Illawong. Boating related
works include: the construction of a fixed jetty for small
boat pick up and drop off, construction of a kayak/canoe
launching ramp, car park upgrade and associated access
pathways.
Planning
Old Punt Road Boat
Ramp Car Park
Upgrade, North
Batemans Bay
North Batemans
Bay
South East and
Tablelands
Maritime Upgrade (sealing, formalisation, drainage) of the existing
car park at the Old Punt Road boat ramp, Batemans Bay.
Car park to accommodate up to 11 car/trailer parking
spaces and 14 car only parking spaces.
In Progress
Name Suburb Region/District Project Type Project Description Current
Status
Old Wallgrove Road
Upgrade
Eastern Creek Central City
District
Road The 1.5 kilometre upgrade of Old Wallgrove Road will
provide a vital east-west link connection for the Western
Sydney Employment Area. Key features of the project
include widening to two lanes in each direction between
Roberts Road and Southridge Street with a central
median to allow for three lanes in the future; widening to
three lanes in each direction between Southridge Street
and the M7 Motorway and Wallgrove Road
interchanges; building a 400 metre link road with two
lanes in each direction from Quarry Road to connect to
Wallgrove Road and the northbound on and off ramps to
the M7; providing bus stops near each intersection on
Old Wallgrove Road and installing traffic lights that give
priority to buses; providing a shared path for pedestrians
and cyclists from the Erskine Park Link Road to the
shared pathway on the M7 Motorway; upgrading
intersections to help reduce congestion during peak
periods; and upgrading one kilometre of Wallgrove Road
to provide additional turning and through lanes at the
Old Wallgrove Road and new link road intersections.
Key benefits of the project include a vital east-west link
connection for the Western Sydney Employment Area;
improved access to the M4 and M7 Motorways;
increased road capacity; improved safety for motorists
with a central median to separate opposing traffic flows;
more reliable travel times when future development
occurs; and improved access and safety for pedestrians
and cyclists through an off-road shared path.
In-Progress
Olympic Highway Young South East and
Tablelands
Road Shoulder widening and wire rope safety barrier Completed
Olympic Highway Cowra Central West and
Orana
Road Install shoulder from no shoulder and install full width
clearzone
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Orange Station Refresh Package 4a
Orange North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Orara Way Kremnos North Coast Road Improve vertical alignment and provide superelevation,
install shoulders CAMs and guideposts
Completed
Orphan School Creek
cycleway
Canley Heights Western City
District
Walking and Cycling Shared Path cycleway alongside Orphan School
Creek
Completed
Osmond Reserve
cycleway
Swansea Hunter Walking and Cycling Shared Path cycleway alongside Osmond Reserve Completed
Otford Interchange -
Commuter Parking
Otford Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide five
extra commuter car parking spaces.
Completed
Ourimbah Interchange
- Transport Access
Program Upgrade
Ourimbah Central Coast Interchange The improvements to Ourimbah Station included the
construction of two small ramps at the station building
doorways on Platform 2 and the installation of new
handrails and tactile indicators.
Completed
Ourimbah Station Refresh Package 3a
Ourimbah Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Outer Sydney Orbital
Corridor Preservation
Glenmore Park Western City
District
Road A suitable corridor for the Outer Sydney Orbital is being
investigated to provide a north – south connection for a
future motorway, freight rail and where practical a
passenger rail line. Corridor preservation is a process to
identify and preserve an area of land for future transport
use. A preserved corridor provides certainty for
communities, businesses and land owners and reduces
the cost of providing infrastructure in the long term.
Ultimately the corridor will provide increased capacity
for the road network to improve accessibility to housing
and employment opportunities in Western Sydney. The
corridor is also expected to provide for a future freight
rail connection from Port Kembla to the T2 South Line,
to the T1 Western Line and the Northern Line.
Planning
Owen Bridges Reserve
Boat Ramp Upgrade,
Mulwala
Mulwala Riverina Murray Maritime Upgrade of the Owen Bridges Reserve boat ramp facility
at Mulwala. Works include: upgrade/reconstruction of
the existing boat ramp, installation of a new pontoon,
improvements to the site car park and investigation into
the upgrade of the site's toilet facility.
Planning
Oxford Street Darlinghurst Eastern City Road Install four left turn red arrow protection at the
intersection of Oxford Street and Crown Street
Completed
Oxley Highway -
Tangaratta Creek
bridge replacement
Wallamore New England North
West
Road Road realignment and a new bridge located just west of
the existing bridge. The new bridge is wider and delivers
a safer road for commuters, and improves efficiency and
productivity for businesses which use the Oxley
Highway to transport freight.
Completed
Oxley Highway -
Wrights Road to
Pacific Highway, Port
Macquarie
Thrumster North Coast Road Six kilometres of the Oxley Highway was upgraded
between Wrights Road and the Pacific Highway. Key
features of the upgrade include six kilometres of dual
carriageway, bridge over the current Oxley Highway
near Philip Charley Drive, two dedicated fauna
underpasses, works at five intersections, provision for
on-road cycling, landscaping and noise attenuation. The
ugrade provides improved road safety, improved traffic
efficiency, and supports economic development.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Oxley Highway to
Kempsey - Pacific
Highway Upgrade
Cooperabung North Coast Road 37 kilometres of the Pacific Highway is being upgraded
to four lane divided highway from north of the Oxley
Highway to south of Kempsey. Key features of the
project include 37.8 kilometres of four lane divided road,
with a wide median, to allow for a future upgrade to six
lanes when required; access at interchanges; a bypass of
Telegraph Point; interchanges at Sancrox, Yarrabee
Road and Kundabung Road; an overpass at Bill Hill
Road; new major bridge structures for the Hastings River
and Wilson River crossings, and the crossing of the
North Coast Railway Line to the north of the Wilson
River; smaller bridges for a number of creek crossings;
north and southbound rest areas for light and heavy
vehicles in the vicinity of Mingaletta Road; and sections
of the existing highway maintained and used as a service
road for local traffic. Key benefits of the project include
improved highway safety, reduced travel times and
improved travel efficiency; reduced greenhouse gas
emissions and fuel consumption; and improved local
access.
In-Progress
Oxley Highway to
Kundabung - Pacific
Highway Upgrade
The Hatch North Coast Road The upgrade involves 23 kilometres of four lane divided
highway between the Oxley Highway and Kundabung. It
includes major bridge crossings of the Hastiings and
Wilsons Rivers, a bypass of Telegraph Point and
interchanges at three locations. The project is part of the
overall Kempsey to Eungai upgrade.
In-Progress
Oxley Park Boat Ramp
Upgrade, Chinderah Chinderah North Coast Maritime Upgrade of the Oxley Park boat ramp at Chinderah to
improve access to the Tweed River. Works include
dredging the embayment the boat ramp is located in to
provide increased depths when launching at low water.
The toe of the boat ramp will also be upgraded.
Planning
Pacific Highway Ferodale Hunter Road Install median and kerbside safety barrier at crash
clusters
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Pacific Highway Koorainghat Hunter Road Install sections of northbound kerbside and median
barrier
Completed
Pacific Highway Glenthorne Hunter Road Install kerbside safety barrier (southbound) Completed
Pacific Highway Jewells Hunter Road Install traffic signals Design Only
Completed
Pacific Highway Artarmon North Road Install a high level non-skid surface on the dual left-turn
lanes eastbound on-ramp at the signalised intersection of
Pacific Highway and Gore Hill Freeway
Completed
Pacific Highway
cycleway
Swansea Hunter Walking and Cycling Shared Path cycleway alongside Pacific Highway Completed
Pacific Highway
cycleway
Coffs Harbour North Coast Walking and Cycling Shared Path cycleway alongside Pacific Highway Completed
Pacific Highway
cycleway
Nambucca
Heads
North Coast Walking and Cycling Shared Path cycleway alongside Pacific Highway Completed
Pacific Highway
cycleway
Merewether Hunter Walking and Cycling Shared Path cycleway alongside Pacific Highway Completed
Name Suburb Region/District Project Type Project Description Current
Status
Pacific Highway
upgrade between
Ourimbah Street and
Parsons Road, Lisarow
Lisarow Central Coast Road The upgrade of the Pacific Highway is being planned
between Ourimbah Street and Parsons Road at Lisarow.
The proposed upgrade involves widening the highway to
provide two lanes in each direction to improve traffic
flow and safety for all road users. Key features of the
upgrade include two lanes in each direction on the
Pacific Highway; a new bridge over the rail line,
replacing the existing narrow bridge near Railway
Crescent; new traffic lights at the Railway Crescent and
Tuggerah Street (formerly Macdonalds Road)
intersections with the Pacific Highway; upgrading the
existing traffic lights at The Ridgeway; improved
pedestrian and cycle paths along and across the highway;
and improved access to the parking area at Lisarow
Railway Station. Key benefits of the upgrade include
improved traffic flow and more consistent travel times
on the Pacific Highway; improved access to connecting
roads; improved safety for all road users; and improved
pedestrian and cycle network.
Planning
Pacific Highway
upgrade between
Ourimbah Street,
Lisarow and Glen
Road, Ourimbah
Ourimbah Central Coast Road The upgrade involves widening the highway to provide
two lanes in each direction to improve traffic flow and
safety. The upgrade includes two lanes in each direction
on the Pacific Highway; new traffic lights with
pedestrian crossing facilities at the Ourimbah Street,
Teralba Street and Walmsley Road intersections; a
shared pedestrian and cycle path on the western side of
the highway; and new bridges over Cut Rock Creek. The
upgrade will improve traffic flow and travel times for
around 29,000 motorists travelling this 1.6 kilometre
section of highway each day. It will also improve safety
for motorists, pedestrians and road users.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Pacific Highway
Upgrade through
Wyong Town Centre
Wyong Central Coast Road An upgrade of the Pacific Highway is planned through
the Wyong town centre to provide two lanes in each
direction between Johnson Road at Tuggerah and Cutler
Drive at Wyong. The upgrade would improve traffic
flow, travel times and safety for all road users as well as
provide for possible future changes to the public
transport network.
Planning
Pacific Motorway Killingworth Hunter Road Install median wire rope safety barrier (northbound) Completed
Pacific Motorway Wyee Central Coast Road Install kerbside and median barrier (southbound) Completed
Pacific Palms
Recreational Club
Boating Facilities
Improvement, Wallis
Lake
Wallis Lake Hunter Maritime Replacement of existing jetty surface and installation of
a new pontoon to improve launch and retrival of boats.
Works also includes the formalisation of existing car
park to improve flow of boat ramp and alllow for boat
trailer parking.
Planning
Padstow Interchange -
Commuter Parking
Padstow South District Parking The multi-storey car park, located at 10-14 Padstow
Parade, Padstow, provides 100 additional commuter
parking spaces, lift and stair access, motorcycle parking
spaces, bicycle racks, lighting and CCTV cameras.
Short-term parking and family accessible toilets have
also been provided at the car park site and are managed
by Bankstown City Council.
Completed
Paine Street Maroubra Eastern City Road Install a single lane roundabout Completed
Name Suburb Region/District Project Type Project Description Current
Status
Panania Interchange -
Transport Access
Program Upgrade
Panania South District Interchange Accessibility at Panania Station is being improved for
people with disabilities, limited mobility, parents with
prams, and tourists with luggage. The proposed
improvements at Panania Station include three new lifts
and stairs; a new pedestrian bridge; new canopies for
weather protection; refurbishment of the heritage
platform building to include new toilet facilities;
improvements to the bicycle facilities and interchanges
areas; new wayfinding signage; and improvements to
lighting and CCTV surveillance.
In-Progress
Paradise Beach Dinghy
Storage, Clareville Avalon Beach North Maritime Installation of additional storage racks for dinghies and
other passive watercraft at Paradise Beach, Clareville to
address a high demand for storage at this location.
Planning
Park Street cycleway Glenbrook Western City
District
Walking and Cycling Shared Path cycleway alongside Park Street Completed
Parker Street Penrith Western City Road Install pedestrian median fence and install footpath &
pedestrian leg
Completed
Parkes Eugowra Road Eugowra Central West and
Orana
Road Install roadside wire rope around curve Completed
Parkes Interchange -
Transport Access
Program Upgrade
Parkes Central West &
Orana
Interchange Interchange upgrade includes a new taxi zone, traffic
island and footpaths.
Completed
Paroo Road Holgate Central Coast Road Install roadside w-beam barrier, resurfacing, CAMs,
advisory signs
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Parramatta Light Rail Parramatta Central City
District
Light Rail Along a 22-kilometre corridor, the network will connect
Parramatta’s CBD to the key hubs of Sydney Olympic
Park, Westmead Hospital, Western Sydney University
and Strathfield. The spine of the preferred route runs
from Westmead to Strathfield via Parramatta CBD, and
incorporating Camellia and Sydney Olympic Park. A
light rail line will also branch to Carlingford, replacing
the existing heavy rail shuttle. It will provide a frequent
and reliable transport mode for growing and emerging
precincts by bringing businesses, destinations and
employers closer to their suppliers, visitors, employees
and customers.
Planning
Parramatta Station Refresh Package 1
Parramatta North Coast Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Parramatta Valley
cycleway
Rydalmere Central City
District
Walking and Cycling Shared Path cycleway alongside Parramatta Valley Completed
Parramatta Valley
cycleway
Parramatta Central City
District
Walking and Cycling Shared Path cycleway alongside Parramatta Valley Completed
Parramatta Valley
cycleway
Parramatta Central City
District
Walking and Cycling Shared Path cycleway alongside Parramatta Valley Completed
Parramatta Wharf -
Wharf Upgrade
Program
Parramatta Central City
District
Maritime The wharf upgrade aims to provide easier access to the
wharf, better weather protection, additional seating, more
safety features as well as quicker and more efficient
boarding and disembarking.
Planning
Parriwi Road
cycleway
Mosman North District Walking and Cycling Mixed Traffic cycleway alongside Parriwi Road Completed
Name Suburb Region/District Project Type Project Description Current
Status
Parsley Bay Boating
Infrastructure
Improvements
(Investigation),
Brooklyn
Brooklyn North Maritime Development of a strategic plan to improve boating
infrastructure at Parsley Bay, Brooklyn.
Planning
Parsley Bay Dinghy
Storage, Brooklyn Brooklyn North Maritime Investigation into the provision of dinghy storage at
Parsley Bay, Brooklyn.
Planning
Peachtree Creek
Bridge cycleway
Penrith Western City
District
Walking and Cycling Shared Path cycleway alongside Peachtree Creek
Bridge
Completed
Pendle Hill Interchange
- Commuter Parking
Pendle Hill Central City
District
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Pendle Hill Interchange
- Commuter Parking
Pendle Hill Central City
District
Parking Planning is underway to improve commuter parking by
providing around 125 additional spaces on Civic
Avenue.
In-Progress
Pendle Hill Interchange
- Transport Access
Program Upgrade
Pendle Hill Central City
District
Interchange Pendle Hill Station is being upgraded to improve access
for customers. The upgrade includes four new lifts, a
new station concourse and footbridge, new stairs and
platform canopies, and a family accessible toilet. As part
of this upgrade, the existing station footbridge will be
partially demolished including the complete removal of
the existing ramps to Joyce Street and Wentworth
Avenue.
In-Progress
Pennant Hills
Interchange - Transport
Access Program
Upgrade
Pennant Hills North District Interchange Improvements to the transport interchange facilities at
Pennant Hills Station included upgrading uneven
footpath areas at Railway Street, Yarrara Road and
Ramsay Road; reconstructing uneven road pavement in
Railway Street and at the intersection of Ramsay Road
and Pennicook Lane; converting the existing staff car
park for commuter use, including an upgrade to comply
with accessibility standards; and new signage for 'kiss
and ride' areas on Yarrara Road and Ramsay Road.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Pennant Hills Station Refresh Package 4
Pennant Hills Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Penrith Interchange -
Commuter Parking
Penrith Western City
District
Parking Conversion of existing staff car park to provide 153 extra
commuter car parking spaces.
Completed
Penrith Interchange -
Commuter Parking
Penrith Western City
District
Parking A new commuter car park is being built at Penrith
Station to provide around 350 additional commuter
spaces. The project will include extending the existing
multi-storey car park to replace the existing at-grade car
park, a new lift, stairs and lighting and CCTV upgrades.
In-Progress
Penrith Interchange -
Transport Access
Program Upgrade
Penrith Western City
District
Interchange Facilities at Penrith Station are being upgraded to
provide a better customer experience and increase
capacity for future growth in the region. The upgrade
will include a new station concourse, new stairs and
canopies, new accessible amenities and an improved
interchange area.
In-Progress
Penrith Station Refresh Package 1
Penrith Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Penshurts Station Refresh Package 3
Penshurst North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Peter Brock Drive to
Mersey Road - The
Northern Road
Upgrade
Bringelly Western City
District
Road The Northern Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney airport at Badgerys Creek.
It would also improve safety, increase road capacity and
reduce congestion and travel times in the future. This
stage of The Northern Road Upgrade is 11.5 kilometres
between Peter Brock Drive, Oran Park and Mersey Road,
Bringelly, including the intersection of The Northern
Road and Bringelly Road which will be built as a grade
separated interchange. Key features include widening
from a generally two lane to a four lane, divided road
with a 4 metre wide shoulder and wide central median
allowing for widening to six lanes, if required in the
future; a grade separated intersection at Bringelly Road
to the east of Bringelly Village shops and the existing
intersection with Bringelly Road/Greendale Road; a
speed limit of 80km/h; a three metre wide shared
pedestrian/cyclist path on the eastern side; adjustments to
public facilities such as gas, electricity, water, and
telecom services along the route; designated turning
lanes and bicycle and pedestrian crossing provisions at
traffic lights; upgrade and/or tie in with local roads
where required; bus priority lanes at traffic lights and
indented bus bays; temporary U-turn facilities at some
future precinct link roads; nine intersections to be
upgraded with new traffic lights; and the existing bridge
over Thompson Creek will be replaced for southbound
traffic and a new bridge will be constructed for
northbound traffic.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Petersham Station Refresh Package 4
Petersham Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Picnic Point Boat
Ramp & Car Park
Upgrade, Mathoura
Mathoura Riverina Murray Maritime Stage 1 of the upgrade to the Picnic Point boat ramp at
Mathoura. Works include: sealing and formalising the
existing car/trailer parking area and boat ramp
manouevring area, erosion stabilisation to the river bank
around the existing boat ramp and pontoon to include
mooring points for short term berthing of vessels,
construction of site access pathways and new
picnic/recreation facilities at the site.
Planning
Picton Interchange -
Commuter Parking
Picton Western City
District
Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Picton Interchange -
Transport Access
Program Upgrade
Picton Western City
District
Interchange Improvements to the transport interchange facilities at
Picton Station included upgrading the footpath pavement
on the northern side of Station Street, installing a new
refuge island on Station Street, installing a new
pedestrian footpath for the southern side of Station
Street, installing a pedestrian safety fence along the
northern side of the Prince Street road bridge (over the
railway line) and installing new way-finding signage.
Completed
Picton Road Safety
Improvements
Cordeaux Illawarra
Shoalhaven
Road The improvements were designed to reduce the number
and severity of the most common types of crashes on the
road and make it a safer and more reliable transport link
for the 15,000 motorists who use it every day. During the
program of work 6.5 kilometres of new guardrail and
10.8 kilometres of concrete or wire rope median have
been installed; the amount of overtaking opportunities in
both directions has been increased by 1.5 kilometres; and
two dangerous curves have been realigned.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Pinch Points Program
and Clearways
Program
Parramatta Central City
District
Road The Pinch Point Program aims to reduce traffic delays,
manage congestion and improve travel times on Sydney's
major roads, particularly during weekday peak periods.
Projects to help ease congestion at pinch points include
widening small sections of road or intersection;
lengthening turn bays; adding extra turn bays or turning
lanes; replacing heavily used roundabouts with traffic
signals; and installing closed circuit television cameras
and electronic message signs to help manage traffic and
provide real-time traffic information to motorists to help
them make informed travel decisions.
In-Progress
Pinnacle Road Canobolas Central West and
Orana
Road Clearzone improvement, skid resistance reseal and
CAMS on 90 degree curve
Completed
Pitts Lane cycleway Putta Bucca Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Pitts Lane Completed
Pittwater Road
cycleway
North Narrabeen North District Walking and Cycling Shared Path cycleway alongside Pittwater Road Completed
Plantation Point
Parade cycleway
Vincentia Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Plantation Point
Parade
Completed
Plantation Point
Parade cycleway
Vincentia Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Plantation Point
Parade
Completed
Pleasure Point Jetty
Upgrade, Georges
River
Pleasure Point South West Maritime Installation of a new jetty and pontoon facility at
Pleasure Point. Works include the demolishion and
replacement of the existing dilapidated jetty with a new
timber jetty and the installation of a new gangway and
pontoon off the jetty.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Point Clare Station Refresh Package 4a
Point Clare North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Point Road Boat Ramp
Upgrade, Tuncurry Tuncurry Hunter Maritime Works include replacement of existing jetty, expansion
of existing pontoon at boat ramp, improve definition
within existing car park to improve flow of boat ramp
and allow for easier boat trailer parking, installation of
dinghy storage facility, improve dinghy launching ability
on exisiting gravel ramp and improve lighting on site.
Planning
Port Botany Expansion
– Third Terminal
including Grade
Separation
Port Botany Eastern City
District
Freight Port Botany Expansion Project – the design,
construction, procurement and contracting Terminal 3
operation to Hutchison Port Holdings. Includes Penrhyn
Rd grade separation. Operations commenced in 2014.
Completed
Port Kembla Boat
Ramp New Pontoon &
Car Park Upgrade
Port Kembla Illawarra
Shoalhaven
Maritime Planning
Port Kembla
Interchange -
Commuter Parking
Port Kembla Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Port Macquarie
Interchange - Transport
Access Program
Upgrade
Port Macquarie North Coast Interchange Improvements to the footpath and road surface. Completed
Prairiewood
Interchange -
Commuter Parking
Bossley Park Western City
District
Parking A new commuter car park providing 50 new spaces. In-Progress
Princes Highway Dalmeny South East and
Tablelands
Road Widen shoulder, improvements to the horizontal and
vertical alignment of the Princes Highway, Dalmeny
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Princes Highway
cycleway
Bulli Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
West
Wollongong
Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
Kembla Grange Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
Ulladulla Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
Albion Park
Rail
Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
Brownsville Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
Kembla Grange Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Princes Highway
cycleway
Burrill Lake Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Princes Highway Completed
Pritchard Street Mt Pritchard Western City Road Install a single lane roundabout Completed
Prospect Highway
cycleway
Prospect Central City
District
Walking and Cycling Shared Path cycleway alongside Prospect Highway Completed
Name Suburb Region/District Project Type Project Description Current
Status
Prospect Highway
Upgrade
Blacktown Central City
District
Road The planned upgrade of 3.6 kilometres of the Prospect
Highway, between Reservoir Road at Prospect and St
Martins Crescent at Blacktown, will reduce congestion
and meet future traffic demand on this road corridor. Key
features of the upgrade include upgrading from an
undivided two lane road to a four lane divided road;
duplicating the bridges over the M4 Motorway and the
Great Western Highway; a new two way link road
between the Great Western Highway and the Prospect
Highway, with traffic lights at either end of the new
road; providing new traffic lights at Stoddart Road, M4
Motorway eastbound entry and exit ramps and Reservoir
Road; changing access arrangements on some local
connecting roads; upgrading of the existing shared path
on the western side of the Prospect Highway between the
M4 Motorway and Blacktown Road; and installing
kerbside bus lanes between Lancelot Street and north of
St Martins Crescent.
Planning
Provision of Amenities
at Pickering Point &
Seaforth Jetties
Middle Harbour North Maritime Provide additional facilities in the form of potable water,
lighting & waste disposal and recycling facilities at
Sangrado Street & Gurney Crescent.
Planning
Provision of Sewage
Pump-out facilities in
Botany Bay
(Investigation)
Botany Bay South Maritime Planning
Punchbowl Station Refresh Package 4
Punchbowl Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Pymble Station Refresh Package 3
Pymble North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Pyrmont Bay Wharf -
Wharf Upgrade
Program
Sydney Eastern City
District
Maritime The new wharf is connected to the existing timber
boardwalk and includes a new covered steel floating
pontoon, small concrete fixed bridge and an aluminium
gangway connecting the bridge to the pontoon. The
pontoon has a curved zinc roof, glass panels and new
seating offering some protection from the weather and
improved amenity. The new wharf provides better
protection from the wind, rain and sun, improved access
for mobility impaired customers and customers with
prams, improved safety for customers, and quicker and
more efficient boarding and disembarking.
Completed
Quakers Hill
Interchange -
Commuter Parking
Quakers Hill Central City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Quakers Hill
Interchange - Transport
Access Program
Upgrade
Quakers Hill Central City
District
Interchange The interchange upgrade included new drop off and pick
up zones, reconfiguration of car parking and relocation
of a bus stop.
Completed
Quakers Hill Park
cycleway
Quakers Hill Central City
District
Walking and Cycling Shared Path cycleway alongside Quakers Hill Park Completed
Quakers Hill
Parkway cycleway
Quakers Hill Central City
District
Walking and Cycling Shared Path cycleway alongside Quakers Hill
Parkway
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Quakers Hill Station Refresh Package 4
Quakers Hill Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Quirindi Truck Wash Replacement
Quirindi New England
North West
Freight The scope includes construction of a new single wash bay sized to cater for B-doubles, an effluent treatment facility utilising existing storage dams on-site and a turning loop from the existing road access point.Replacement of the existing Quirindi truck wash that is at the end of its useful life and on a site to that is to be redeveloped. The proposed replacement will be sized to cater for B-doubles and prominent signage is proposed on trucking routes to allow easy identification of the facility. The proposed facility will also include a treatment facility to comply with EPA requirements, which the current facility does not have.
Planning
Rail Operations Centre Alexandria Eastern City
District
Rail The new Rail Operations Centre will minimise delays
and ensure when incidents do occur on the Sydney
Trains rail network, customers receive better and faster
information. The centre will modernise how Sydney’s
rail network is controlled by incorporating dozens of
different systems into a single location and changing our
approach to managing trains. Customers will benefit
from faster communication of the updated train timetable
after an incident; faster resolution of incidents,
minimising customer delay times; and more accurate,
timely, relevant and consistent information during
delays.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Railway Parade Granville Central City Road Removal of filter right turn to provide a fully controlled
right turn for westbound traffic on Railway Parade and
installation of missing pedestrian phases on Railway
Parade & Bold Street.
Completed
Railway Parade
cycleway
Leura Western City
District
Walking and Cycling Shared Path cycleway alongside Railway Parade Completed
Railway Terrace Merrylands Central City Road Convert the existing median island to a refuge island on
Railway Terrace between Sutherland Road and
Merrylands Road, Merrylands. Includes road widening
and street lighting infrastructure.
Completed
Rankin Park to
Jesmond - Newcastle
Inner City Bypass
New Lambton
Heights
Hunter Road The Rankin Park to Jesmond section of the Newcastle
Inner City Bypass would provide traffic relief to the
surrounding road network, in particular the existing route
of Lookout Road, Croudace Street and Newcastle Road.
The project would involve building a 3.4 kilometre four-
lane divided road with a northern interchange at
Newcastle Road; a southern interchange at Lookout
Road; a half interchange providing access to John Hunter
Hospital to/from the north; three structures provided
along the bypass to improve connectivity in the bushland
for people and animals; and off-road provisions for
pedestrians and cyclists including a footbridge over
Newcastle Road at Jesmond Park.
Planning
Redfern Interchange -
Transport Access
Program Upgrade
Eveleigh Eastern City
District
Interchange Redfern Station was upgraded to improve access for
customers. The project included a new lift to platforms 6
and 7, a new section of canopy providing sheltered
access to the lift, and new CCTV, lighting and fencing
around the lift area.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Redfern Station Refresh Package 1
Eveleigh Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Regional Freight Rail
Sidings Extensions
Condobolin Central West &
Orana
Rail A program of upgrades to lengthen sidings to allow
faster loading and passing loops to allow longer trains to
operate more efficiently on the grain rail network.
In-Progress
Remembrance
Driveway cycleway
Tahmoor Western City
District
Walking and Cycling Shared Path cycleway alongside Remembrance
Driveway
Completed
Reservoir Road
cycleway
Prospect Central City
District
Walking and Cycling Shared Path cycleway alongside Reservoir Road Completed
Revesby Beach
Pontoon Replacement,
Georges River National
Park
Revesby
Heights
South Maritime Installation of a new pontoon to replace the existing
pontoon (that is in poor condition) at Revesby Beach.
Planning
Rhodes Interchange -
Commuter Parking
Rhodes Eastern City
District
Parking Conversion of existing staff car park to provide three
extra commuter car parking spaces.
Completed
Rhodes Station Refresh Package 2
Rhodes Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Rhodes Wharf - Wharf
Upgrade Program
Rhodes Eastern City
District
Maritime The proposed new wharf will be fully accessible and
include weather protection, seating, safety features as
well efficient boarding and disembarking.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Richardson Road Campvale Hunter Road Improve roundabout deflection, install safety barrier
kerbside on north eastern corner of roundabout
Completed
Richmond Interchange
- Commuter Parking
Richmond Western City
District
Parking Conversion of existing staff car park to commuter car
park to provide 59 additional commuter car parking
spaces.
Completed
Richmond Intersection
Improvements
North Richmond Western City
District
Road The intersection upgrades will reduce congestion on the
Kurrajong Road, March Street and Bells Line of Road
approaches to Richmond Bridge. The upgrades are being
undertaken at the following intersections: Kurrajong
Road and Old Kurrajong Road, Richmond; March Street
and Bosworth Street, Richmond; and Bells Line of Road
and Grose Vale Road, North Richmond.
In-Progress
Richmond Road Penrith Western City Road Install seagull, MIST and upgrade to stop Completed
Richmond Road
cycleway
Blacktown Central City
District
Walking and Cycling Shared Path cycleway alongside Richmond Road Completed
Name Suburb Region/District Project Type Project Description Current
Status
Richmond Road
Upgrade - Stage 1
Colebee Central City
District
Road Richmond Road is being progressively upgraded from a
two lane road north of Bells Creek Bridge, Colebee to
the South Creek floodplain. The upgrade would see
Richmond Road widened to a four lane road with
provision for six lanes in the future. Stage 1 of the
upgrade is between Bells Creek, and to the north of
Townson Road, Marsden Park. Key features include an
upgrade from two to a four lane divided road with a
landscaped central median with provision for widening
to six lanes in the future; a speed limit of 80km/h; a three
metre wide off-road shared pedestrian/cyclist path on the
western side of the road with provision made on the
eastern side of the road in the future; new traffic lights at
Townson Road and at the new intersection for Colebee
and the Sydney business Park; closure of Hollinsworth
Road with access via an extended Townson Road; bus
priority capability at traffic lights; and designated turning
lanes, and bicycle and pedestrian crossing provisions at
traffic lights.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Richmond Road
Upgrade - Stage 2
Marsden Park Central City
District
Road Richmond Road is being progressively upgraded from a
two lane road north of Bells Creek Bridge, Colebee to
the South Creek floodplain. The upgrade would see
Richmond Road widened to a four lane road with
provision for six lanes in the future. Stage 2 of the
upgrade is between Townson Road and 900 metres north
of Garfield Road West. Key features include upgrading
the road to a four-lane divided road with a landscaped
central median with provision for widening to six lanes
in the future; an 80km/h speed limit; two metre wide
shoulders; a three metre wide, off-road shared
pedestrian/cyclist path on the western side of the road
with provision for another shared path on the eastern side
of the road in the future; new traffic lights at Quarry
Road and South Street; new traffic lights at Vine Street
West/Pius Lane; realignment and upgrade of the Garfield
Road West intersection; provision of a new set of traffic
lights to enable right turns onto Garfield Road West from
the service road; bus priority capability at traffic lights
and indented bus bays on each side of Richmond Road;
and designated turning lanes, and bicycle and pedestrian
crossings at traffic lights.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Richmond Road
Upgrade - Stage 3
Marsden Park Central City
District
Road Richmond Road is being progressively upgraded from a
two lane road north of Bells Creek Bridge, Colebee to
the South Creek floodplain. The upgrade would see
Richmond Road widened to a four lane road with
provision for six lanes in the future. Stage 3 of the
upgrade is between north of Grange Avenue to the South
Creek floodplain. Key features include an upgrade from
two to a four lane divided road with a landscaped central
median with provision for widening to six lanes in the
future; a speed limit of 80km/h; a three metre wide off-
road shared pedestrian/cyclist path on the western side of
the road with provision made on the eastern side of the
road in the future; bus priority capability at traffic lights;
designated turning lanes, and bicycle and pedestrian
crossing provisions at traffic lights; and provision of a
new intersection with traffic lights, approximately one
kilometre north of Garfield Road West that will provide
access to Marsden Park Precinct.
Completed
River Forest Road to
Mongarlowe River -
Kings Highway
Upgrade
Northangera South East &
Tablelands
Road 4.1 kilometres of Kings Highway will be realigned to
improve safety between River Forest Road and the
Mongarlowe River, south east of Braidwood. As part of
this work a number of trees will be removed to make
room for the new alignment which will include an
overtaking lane and widening the shoulders on the side
of the road. Guard rail will also be installed as part of
this work.
In-Progress
River Road cycleway Shoalhaven
Heads
Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside River Road Completed
River Road West
cycleway
Longueville North District Walking and Cycling Shared Path cycleway alongside River Road West Completed
Name Suburb Region/District Project Type Project Description Current
Status
River Street Ballina North Coast Road Extend 2 to 4 lane transition westwards from current
location at Tweed St intersection to midblock between
Tweed St & Brunswick St. Construct concrete median in
River St to prevent right turns at Tweed St and provide
protected right turn lanes at Brunswi
Completed
Riverina Highway Corowa Riverina Murray Road Install intersecion lighting Completed
Riverina Highway Albury Riverina Murray Road Close Olive Street intersection with median and provide
right turn phases for eastbound and westbound traffic at
Kiewa and David Streets
Completed
Riverina Highway
cycleway
Thurgoona Riverina - Murray Walking and Cycling Shared Path cycleway alongside Riverina Highway Completed
Riverina Highway
cycleway
Thurgoona Riverina - Murray Walking and Cycling Shared Path cycleway alongside Riverina Highway Completed
Riverina Highway
Upgrade, East of
Albury
Thurgoona Riverina - Murray Road The work will improve road safety on the Riverina
Highway between Sandy Creek and Bethanga Bridge
and includes widening the road between Sandy Creek
and Bethanga Bridge; improving rough sections of road;
retaining the 80km/h speed limit between Sandy Creek
and Bethanga Bridge; upgrading signposting; widening
culverts; and installing guardrail. This work will provide
consistent travelling conditions from Albury to Bethanga
Bridge and improve safety by increasing the lane and
shoulder widths.
In-Progress
Riverside Park New
Wharf and Pontoon,
Kempsey
Kempsey North Coast Maritime Construction of a wharf and floating pontoon facility and
access pathway at the Riverside Park, Kempsey.
Planning
Riverstone Interchange
- Commuter Parking
Riverstone Central City
District
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Riverstone Interchange
- Transport Access
Program Upgrade
Riverstone Central City
District
Interchange Improvements to accessibility at Riverstone Station
included regrading the internal ramp near the ticket
office and construction of a new ramp between the
platform and Garfield Road.
Completed
Rockdale Interchange -
Commuter Parking
Rockdale Eastern City
District
Parking The existing Geeves Lane commuter car park was
upgraded and extended to provide an additional 24
parking spaces. Three new accessible parking spaces
were constructed and two existing accessible parking
spaces were upgraded as part of this work.
Completed
Rockdale Interchange -
Commuter Parking
Rockdale Eastern City
District
Parking Conversion of existing staff car park to provide 26 extra
commuter car parking spaces.
Completed
Rocks Ferry Reserve
New Pontoon,
Wauchope
Wauchope North Coast Maritime Installation of a new pontoonat the Rocks Ferry Reserve
boat ramp, Wauchope.
Planning
Rocky Waterholes Boat
Ramp Access Road
Upgrade & New Toilet
Facility, Narrandera
Narrandera Riverina Murray Maritime Upgrade of the Rocky Waterholes boat ramp facility,
Narrandera. Works include sealing the 500m boat ramp
access road (Stage 1) and the installation of a new toilet
facility and water tank at the boat ramp (Stage 2).
Planning
Rooty Hill Interchange
- Transport Access
Program Upgrade
Rooty Hill Central City
District
Interchange Improvements are planned to improve commuter parking
and provide easier access to public transport. Facilities
being considered include a new footbridge, lifts and a
new commuter park.
Planning
Rooty Hill Station Refresh Package 4
Rooty Hill Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Rose Bay Wharf -
Wharf Upgrade
Program
Rose Bay Eastern City
District
Maritime Upgrade includes access improvements; a new bus
shelter near the ferry wharf; new accessible pedestrian
crossing; lighting modifications; footpath improvements
and additional signage.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Roseville Station Refresh Package 4
Roseville South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Rowland Reserve Boat
Ramp Facility
Upgrade, Bayview
Bayview North Maritime Upgrade of 2 boat ramps, installation of 2 pontoons and
upgrade to car-trailer parking.
Planning
Russell Street Quirindi New England North
West
Road Design and construct a 2.5m wide concrete shared path
from Fitzroy Street, Quirindi starting at Kennedy Street
to the Quirindi Racecourse main entrance via Blairmont
Street, Russell Street, the Quirindi Cemetry entrance,
Dewhurst Street and East Street .
Completed
Rydalmere Wharf -
Wharf Upgrade
Program
Rydalmere Central City
District
Maritime The wharf upgrade aims to provide easier access to the
wharf, better weather protection, additional seating, more
safety features as well as quicker and more efficient
boarding and disembarking.
Planning
Sage Street cycleway Gordon North District Walking and Cycling Mixed Traffic cycleway alongside Sage Street Completed
Salamander Bay Wharf
Upgrade, Port Stephens Port Stephens Hunter Maritime Upgrade of the Salamander Bay wharf. Works include
replacement of baffle boards and lower landing
substructure, and replacement of decking and girders on
the upper deck.
Planning
Sanctuary Point Boat
Ramp Facility
Upgrade, St Georges
Basin
St Georges
Basin
Illawarra
Shoalhaven
Maritime Upgrade of the Greys Beach boat ramp facility, North
Nowra. Works include: formalisation of the existing boat
ramp into a 3 lane ramp, installation of an additional
jetty/pontoon at the boat ramp and improvements to
car/trailer parking. Project also includes an investigation
study into the feasibility of a new boat ramp facility on
the south side of the Shoalhaven River at Nowra (East of
the bridge).
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Sanoni Avenue Sans Souci Eastern City Road Widen existing off road pedestrian /cycleway from 2.1 to
3.0 metres at Cook Park Sans Souci between Sanoni
Avenue and Vanston Parade.
Completed
Sapphire to
Woolgoolga - Pacific
Highway Upgrade
Moonee Beach North Coast Road The project provided a four-lane divided highway
extending approximately 25 kilometres from Campbell
Close, Sapphire, to Arrawarra Beach Road, Arrawarra,
including a bypass of Woolgoolga.
Completed
Schofields Interchange
- Commuter Parking
Schofields Central City
District
Parking Conversion of existing staff car park to provide six extra
commuter car parking spaces.
Completed
Schofields Road
Upgrade and Extension
- Stage 1
The Ponds Central City
District
Road Schofields Road is being upgraded to become a major
east-west connection between Windsor Road and
Richmond Road. It will link the Rouse Hill and Marsden
Park town centres and help to better meet the future
transport needs of the North West Priority Land Release
Area. Stage 1 of the upgrade is between Windsor Road
and Tallawong Road. Key features include upgrading the
road from a two lane to a four-lane, divided road with
provision for widening to six lanes in the future; a speed
limit of 60km/h; three new signalised intersections at
The Ponds Boulevard/Terry Road, Cudgegong Road and
Tallawong Road/Ridgeline Drive; realignment of
Tallawong Road to match up with Ridgeline Drive;
realignment of Cudgegong Road to accommodate
Sydney Metro Northwest; twin bridges over Second
Ponds Creek; designated turning lanes at the signalised
intersections; bus priority measures at traffic lights and
one indented bus bay east of Cudgegong Road; an off-
road, shared path on both sides of the corridor; and new
street lighting.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Schofields Road
Upgrade and Extension
- Stage 2
Schofields Central City
District
Road Schofields Road is being upgraded to become a major
east-west connection between Windsor Road and
Richmond Road. It will link the Rouse Hill and Marsden
Park town centres and help to better meet the future
transport needs of the North West Priority Land Release
Area. Stage 2 of the upgrade is between Tallawong Road
and Veron Road. Key features include upgrading the
road from a two lane to a four-lane, divided road with
provision for widening to six lanes if required in the
future; extending Schofields Road from Railway Terrace
to Veron Road; trees and plants to provide a tree-lined
transit boulevard; new traffic lights at five intersections
along Schofields Road; left-in / left-out access to the
Schofields Precinct between Bridge Street and Veron
Road and also at Schofields Farm Road; temporary U-
turn facilities until the surrounding precincts and local
road network have been sufficiently developed; two twin
bridges at First Ponds Creek and the Eastern Creek
tributary near Railway Terrace; a retained connection to
the new Schofields Station western car park via a new
bridge overpass at Bridge Street; an underpass crossing
of the Richmond rail line; designated turning lanes; off-
road, shared paths for cyclists and pedestrians on the
southern side of the road and making provisions for a
future shared path on the northern side of the road; bus
priority measures at intersection approaches; bus stops at
and in between signalised intersections; improved flood
immunity; and an initial speed limit of 70 km/h reducing
to 60 km/h in the future, as traffic increases.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Schofields Road
Upgrade and Extension
- Stage 3
Schofields Central City
District
Road Schofields Road is being upgraded to become a major
east-west connection between Windsor Road and
Richmond Road. It will link the Rouse Hill and Marsden
Park town centres and help to better meet the future
transport needs of the North West Priority Land Release
Area. Stage 3 of the upgrade is between Veron Road and
Richmond Road. Key features include providing a four-
lane, divided road with a wide central median that would
allow widening to six lanes if required in the future;
extending Schofields Road from Veron Road across
Eastern Creek to Carnarvon Road; extending of
Schofields Road from Carnarvon Road to Richmond
Road using the existing South Street alignment;
constructing a tree-lined transit boulevard; installing new
traffic lights at Carnarvon Road and at a future Fermoy
Road extension intersection; constructing twin bridges
over Eastern Creek and Bells Creek; constructing
designated turning lanes and temporary U-turn facilities
until the surrounding precincts and local road network
have been sufficiently developed; constructing off-road,
shared paths for cyclists and pedestrians on both sides of
the road; installing signalised crossings for pedestrians
and cyclists at all intersections; constructing indented
bus bays and bus priority measures at intersections; and
improving flood immunity.
In-Progress
Scone Interchange -
Transport Access
Program Upgrade
Scone Hunter Interchange The improvements to Scone Station included resurfacing
and re-levelling the footpath and line-marking the
accessible car parking space.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Scone Regional Livestock Truck Wash Effluent Management System
Scone Hunter Freight The scope of this project is to improve the effluent management of the Scone Regional Livestock Selling Centre truck wash facility.The deliverables are to construct a:1. livestock truck effluent disposal facility 2.solidis separator to process manure into a dry product3. Install a reticulation systemThe effluent disposal facility is a grid receptor that trucks drive over and empty waste from the on-board effluent capture tanks. The effluent will go from the receptor area into the truck wash sump. The grill receptor will enable the discharge of single and b-double truck effluent tanks. The effluent will be captured and gravity fed to the truck wash sump. There will be a wash down system under the grills to wash away any excess manure that collects on the grills.The effluent separator is a solids separate unit which processes the solid manure waste into a dry product. All the effluent from the truck wash sump will be processed through the separator. The separator produces dry manure for composting and waste water for irrigation or in the process of manufacturing compost.The reticulation system will utilise captured rainwater to use within the effluent management system.
Planning
Scylla Bay Boating
Facilities Upgrade,
Como
Como South Maritime Upgrade of the boat ramp facility at Scylla Bay, Como.
Works include: upgrade of the existing boat ramp,
replacement of the old exisitng jetty with a new jetty and
pontoon facility, and upgrade of car parking at the site.
Planning
Seaham Boat Ramp
Upgrade, Williams
River
Seaham Hunter Maritime Upgrade of the Seaham boat ramp facility. Works
include Boat ramp and associated facility upgrade. Work
includes regrading the existing boat ramp, formalisation
of the car park and installation of a non-powered craft
launching facility.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Sepoy Knob Boat
Ramp Extension,
Copeton Waters
Holiday Park (Copeton
Dam)
Bundarra New England
North West
Maritime Extension of the Sepoy Knob boat ramp at Copeton Dam
to improve boating access at low water levels.
In Progress
Seven Hills
Interchange -
Commuter Parking
Seven Hills Central City
District
Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces
Completed
Sextonville Road
cycleway
Casino North Coast Walking and Cycling Shared Path cycleway alongside Sextonville Road Completed
Shelley Beach Boat
Ramp and Car Park
Upgrade, Nambucca
Heads
Nambucca
Heads
North Coast Maritime Improvements to the Shelley Beach boat ramp facility,
Nambucca Heads. Works include re-surfacing of the boat
ramp, renewal of the existing toilet block facility,
formalisation of the boat preparation area and
stormwater management at the site.
Planning
Shellharbour Boat
Harbour Boat Ramp
Upgrade & New Jetty
Shellharbour Illawarra
Shoalhaven
Maritime Planning
Shellharbour Junction
Interchange - Transport
Access Program
Dunmore Illawarra
Shoalhaven
Interchange New station, transport interchange and commuter car
park including new infrastructure: two platforms and a
station building, CCTV surveillance, lighting, lifts, stairs
and a footbridge between platforms; a car park with 105
parking spaces including four accessible spaces; an
interchange with two bus bays; four kiss-and-ride spaces,
a taxi zone and bicycle racks; and a pedestrian and cycle
pathway connecting to Haddin Road, Flinders.
Completed
Shellharbour Road Warilla Illawarra
Shoalhaven
Road Install pedestrian fencing on existing median Completed
Shores Drive
cycleway
Yamba North Coast Walking and Cycling Shared Path cycleway alongside Shores Drive Completed
Name Suburb Region/District Project Type Project Description Current
Status
Shortland to Sandgate -
Newcastle Inner City
Bypass
Shortland Hunter Road The Shortland to Sandgate project is a 1.8 kilometre
four-lane divided carriageway road which forms part of
the Newcastle Inner City Bypass between Shortland and
Sandgate. The road passes underneath Sandgate Road at
Shortland, bridge over Deepbridge Creek and the Main
Northern Railway line, runs past the western side of
Sandgate Cemetery and joins the Pacific Highway at
Sandgate. The project also includes five new bridges,
including twin bridges over the Main Northern Railway
Line, and an interchange at Sandgate Road for access
onto the bypass. The newly built intersection of the
bypass and the Pacific Highway helps reduce traffic
delays on the Pacific Highway with motorists now able
to use both the bypass and Wallsend Road intersections.
Completed
Silver City and Cobb
Highway Sealing
Broken Hill Far West Road Improvement works were undertaken at three locations.
Widening and resurfacing work was undertaken on the
Silver City Highway about 46 kilometres south of
Broken Hill. Safety has been improved by widening and
smoothing the road surface and also involved
strengthening the road to accommodate B triples and
mining trucks. Improvement work was also undertaken
on a 9.8 kilometre length of the Silver City Highway
south of Packsaddle and involved surfacing an unsealed
section of road which was often closed following wet
weather. The work has reduced the amount of closures
and provides improved access between Broken Hill and
Packsaddle in all weather conditions. A section of the
Cobb Highway about 105 kilometres north of Ivanhoe
was also sealed to improve safety and reduce closures
during wet weather.
Completed
Singleton - New
England Highway
Bypass
Singleton Hunter Road An assessment of route options is being undertaken to
select a preferred route for the bypass. The bypass would
address current congestion and future traffic demands at
this pinch point, as well as improve safety and travel
times and reduce heavy vehicle traffic through Singleton.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Singleton Interchange -
Transport Access
Program Upgrade
Singleton Hunter Interchange Improvements to Singleton Station included improved
ramp access.
Completed
Singleton Regional Livestock Market Truck Wash
Clydesdale Hunter Freight 1. Concrete Works around the dumping bay 2. Increasing washing bays from one to two 3. Steel structure around the washing bays 4. Median wall construction5. Lighting systems improvement
Planning
Sir Bertram Stevens
Drive
Royal National
Park
South Road Delineation and signs. Police enforcement bays (these
will also provide a wide shoulder for motorists)
Not Started
Smalls Creek
cycleway
Kellyville Central City
District
Walking and Cycling Shared Path cycleway alongside Smalls Creek Completed
Smiths Lake Boating
Access Improvements Smiths Lake Hunter Maritime Replacement and expansion of existing boat ramp and
improve car park at John Debert Reserve. Decommission
informal boat ramp at Patsys Flat Road and replace with
dinghy launching and storage area. Create dinghy
launching and storage area at Eagle Nest Parade.
Planning
Snowy Mountains
Highway
Gundagai Riverina Murray Road Shoulder widening, WRSB Completed
Snowy Mountains
Highway
Tumut Riverina Murray Road Provide appropriate superelevation and shape correction Completed
Snowy Mountains
Highway
Kosciuszko
National Park
South East and
Tablelands
Road Widen shoulder on curves, install guardrail (with rubrail)
and install rubrail on existing guardrail
Not Started
South Creek Road
cycleway
Wheeler Heights North District Walking and Cycling Shared Path cycleway alongside South Creek Road Completed
Name Suburb Region/District Project Type Project Description Current
Status
South Nowra - Princes
Highway Upgrade
South Nowra Illawarra
Shoalhaven
Road Key features of the upgrade include enhanced travel
efficiency for through traffic with the provision of three
lanes on the eastern side of the highway between Quinns
Lane and Warra Warra Road; a 2.5 metre wide shared
footpath / cycleway on the eastern side of the highway
between McKay Street and Warra Warra Road for
cyclists and pedestrians; an on road cycle facility south
of Warra Warra Road; pedestrian activated traffic lights
on the Princes Highway at the Park Road cul-de-sac;
changes to Nowra Hill Road to a left in, left out
intersection; relocation of the existing BTU Road
intersection to approximately 400 metres north of its
original location. The new intersection has been
reconstructed to allow all turning movements;
reconstruction of the Forest Road intersection to allow
all turning movements; a dual lane roundabout at the
junction with Hillcrest Avenue; a heavy vehicle
inspection area to the south of Hillcrest Avenue; and
improvements to the existing service road between
Quinns Lane and Central Avenue to a two lane road on
the western side of the highway for improved road safety
and accessibility. Key benefits of the project include
consistent four lane travel conditions on the Princes
Highway between Bomaderry and Jervis Bay Road;
improved road safety by reducing conflicts between
through traffic and local traffic accessing business
premises; improved road safety by providing a central
median, along with more opportunities to safely overtake
slower vehicles; improved travel times for motorists;
improved access to many business properties; and
improved safety and facilities for pedestrians and
cyclists.
Completed
South Street
cycleway
Gymea South District Walking and Cycling Shared Path cycleway alongside South Street Completed
Name Suburb Region/District Project Type Project Description Current
Status
South West Rail Link Leppington Western City
District
Rail The South West Rail Link extends for 11.4 kilometres
from Leppington to Glenfield via Edmondson Park. Key
features include an upgraded Glenfield Station, two
brand new stations and interchanges at Edmondson Park
and Leppington, and 1,250 customer parking spaces. The
new line will help create new communities and act as a
catalyst for economic development, regional growth and
job creation.
Completed
South West Rail Link
Extension Corridor
Leppington Western City
District
Rail Western Sydney’s future transport needs are being
planned by preserving an additional public transport
corridor in Sydney’s South West to help people to access
jobs and services in the future. The extension corridor is
proposed to connect Leppington Station to Bringelly and
then head in two directions: north to the T1 Western Line
near St Marys; and south to Narellan. Extension of the
corridor further south to the existing T2 South Line is
also being considered. A number of core stations are
proposed in the existing and planned centres of
Rossmore, Bringelly, North Bringelly, Oran Park and
Narellan. A station is also proposed at Badgerys Creek to
serve the Western Sydney Airport. The corridor allows
for additional stations if required. The transport corridor
for the South West Rail Link extension would ensure a
dedicated corridor is available to deliver public transport
infrastructure for Greater Western Sydney when it is
needed; create north-south transport connection, helping
people to access jobs and services and contribute to the
growth of liveable communities in the area; provide
access to the Western Sydney airport at Badgerys Creek
in the longer term, as demand increases; ensure new
town centres are designed and planned around public
transport; provide greater certainty to stakeholders, local
government, businesses, and the wider community; and
reduce the cost of delivering transport infrastructure in
the future.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Southern Mooring
Bollard
The Rocks Eastern City
District
Freight Some cruise ships berthing at the OPT currently extend
beyond the end of the wharf and require the use of
special anchors in Campbells Cove, which were installed
as a temporary solution to allow for the safe berthing of
such cruise vessels. Campbells Cove is currently used by
tall ships, super yachts, water taxis and other smaller
vessels. The use of these anchors hinders access to
Campbells Cove. When cruise ships berthed extend
beyond the end of the wharf, this restricts ship to wharf
access and decreases providoring capacity. The Wharf
Extension Project has improved ship berthing safety and
reliability and allows more efficient servicing of vessels.
Completed
Southern Sydney
Freight Line
Macquarie Fields Western City
District
Rail The Southern Sydney Freight Line provides a dedicated
freight line for a distance of 36 kilometres between
Sefton and Macarthur in southern Sydney. It provides a
third track in the rail corridor specifically for freight
services, allowing passenger and freight services to
operate independently. Key benefits include separating
passenger rail from freight rail to reduce freight transit
times, increasing freight and passenger capacity and
encouraging a shift in freight from trucks to rail.
Completed
Spenser Street Boat
Ramp Jetty Upgrade,
Iluka
Iluka North Coast Maritime The proposed works include:
Provision of a pontoon on the southern side of the
existing boat ramp, modification or removal of the jetty
located on the northern side of the existing boat ramp,
construction of general pathways connecting
infrastructure.
Planning
Spit Road Mosman North Road Install pedestrian fencing on shared path to western side
of Spit Bridge, Mosman.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Sportsmans Creek
Bridge Replacement -
Bridges for the Bush -
Program 2
Lower Southgate
North Coast Road The existing Sportsmans Creek Bridge is located at the
southern approach to Lawrence on Bridge Street, which
connects to Grafton-Lawrence Road. Due to its geometry
and design limitations, the existing bridge was unable to
be safely or cost-effectively serviced and upgraded to
cater for future requirements of surrounding agricultural
industries, local traffic and pedestrian access. A new
concrete bridge is being built to improve traffic
efficiency for heavy and light vehicles, provide for
pedestrian access.
In-Progress
Springwood
Interchange -
Commuter Parking
Springwood Western City
District
Parking Conversion of existing staff car park to provide 23 extra
commuter car parking spaces. The conversion also
includes installation of better lighting, new CCTV
surveillance and handrails for the stairs leading to the
station.
Completed
Springwood Station Refresh Package 1
Springwood Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
St James Station Refresh Package 3
Sydney North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
St Leonards Station Refresh Package 1
St Leonards Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
St Marys Station Refresh Package 3
North St Marys North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Stacey Street Bankstown South Road Close intersection with median Completed
Stanhope Parkway
cycleway
Stanhope
Gardens
Central City
District
Walking and Cycling Shared Path cycleway alongside Stanhope Parkway Completed
Stanley Park
cycleway
Bowral South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Stanley Park Completed
Stanmore Station Refresh Package 3
Stanmore North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Stanwell Park
Interchange -
Commuter Parking
Stanwell Park Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Station Street Waratah Hunter Road Install Escholtz median barrier with pedestrian fencing
on top around curve
Completed
Stenhouse Drive Mount Annan Western City Road Redesign and upgrade of a combined wombat / children's
crossing with enhanced kerb extensions at Mount Annan
Public School on Stenhouse Drive, Mount Annan.
Completed
Stewart Avenue Hamilton South Hunter Road Ban right turns in/out of Kemp Street on the eastern side,
provide right turn facilities out of Parkway Ave (eastern
side)
Construction
Strathfield Interchange
- Transport Access
Program Upgrade
Strathfield Eastern City
District
Interchange Improvements delivered to reduce congestion and
improve customer thoroughfare through the concourse
area included removal of retail kiosks, relocation of
public information displays, installation of a handrail
around the central columns and lighting and new tiling
where the kiosks were removed.
Completed
Strathfield Station Refresh Package 1
Strathfield Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Stroud Hill Road Stroud Hill Hunter Road Widen shoulder, correct superelevation and install
CAMS
Completed
Stuart Island Boating
Facilities
Improvements (Stage
2), Nambucca Heads
Nambucca
Heads
North Coast Maritime Upgrade of the Stuart Island boat ramp facility. Works
include modifications to the island's entry road, parking
upgrade, new public amenities, community shelter and
access improvements.
Planning
Sturt Highway Collingullie -
Gillenbah
Riverina Murray Road Install audio tactile line marking on centre and edge lines
on 69 kilometres of the Sturt Highway between
Collingullie and Gillenbah.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Summer Hill Station Refresh Package 3
Summer Hill North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Sunshine Park Boat
Ramp New Pontoon,
Sunshine
Sunshine Hunter Maritime Installation of a pontoon and gangway facility adjacent
to the boat ramp at Sunshine Reserve. Works also
include the formalisation of an access pathway between
the new pontoon and fish cleaning table at the site.
Planning
Sussex Inlet Boating
Facilities
Improvements
Sussex Inlet Illawarra
Shoalhaven
Maritime Reconstruction of the car park at the Lakehaven Drive
boat ramp, Sussex Inlet. Works include pavement
reconstruction, grading, drainage and line marking the
car park.
Planning
Sutherland Interchange
- Commuter Parking
Sutherland South District Parking The multi-storey car park, constructed on the corner of
Robertson and Oxford Streets Sutherland, provides 388
commuter parking spaces, lift and stair access, accessible
parking spaces, lighting and CCTV cameras. The ground
floor of the car park also features 84 spaces for use of
members of Club on East (formerly Sutherland United
Services Club).
Completed
Sutherland Interchange
- Commuter Parking
Sutherland South District Parking Conversion of existing staff car park to provide 17 extra
commuter car parking spaces, including one accessible
parking space.
Completed
Sutherland Interchange
- Transport Access
Program Upgrade
Sutherland South District Interchange Installation of new station lifts to Platform 1 at
Sutherland Station.
Completed
Sutherland Interchange
- Transport Access
Program Upgrade
Sutherland South District Interchange The upgrade provides increased bus capacity, alleviates
some existing traffic congestion and provides a safer
environment for pedestrians around Sutherland Station.
Completed
Swager Place
cycleway
Canley Heights Western City
District
Walking and Cycling Shared Path cycleway alongside Swager Place Completed
Name Suburb Region/District Project Type Project Description Current
Status
Swamp Road
cycleway
Jamberoo Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Swamp Road Completed
Swamp Road
cycleway
Jamberoo Illawarra
Shoalhaven
Walking and Cycling Shared Path cycleway alongside Swamp Road Completed
Swifts Creek Boat
Ramp Way Finding
Signage, Mathoura
Mathoura Riverina Murray Maritime Installation of signage directing boaters to the boat ramp
at Swifts Creek in the Murray Valley National Park.
Signage to be installed at the main entry points to the
Park (off the Cobb Highway) and throughout the Park.
Planning
Sydenham Interchange
- Transport Access
Program Upgrade
Sydenham Eastern City
District
Interchange Sydenham Station was upgraded to make train travel
more accessible for customers. Improvements included a
new elevated concourse and station entrance with new
ticketing facilities; retail space; a staff office and public
and family accessible toilets; four new lifts to the
platform and concourse; expansion of the station
forecourt area to include new bicycle storage facilities;
and new staircases to access platforms.
Completed
Sydney City Centre
Bus Plan
Sydney Eastern City
District
Bus In October 2015 a new Sydney CBD bus network was
introduced with new priority routes along Elizabeth,
Castlereagh, Park, Druitt, Clarence and York streets. As
part of these changes, and to coincide with major
construction of the new light rail, buses stopped using
George Street. The new network has reduced the number
of buses caught in peak hour traffic which help maintain
bus journey time reliability.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Sydney City Centre
Capacity Improvement
Plan
Sydney Eastern City
District
Road Changes to road infrastructure in the city aim to keep
traffic moving into, from and through the CBD to
support the introduction of light rail and changes to bus
infrastructure. The Sydney City Centre Capacity
Improvement Plan comprises a package of 17 road
infrastructure projects within the CBD, from Broadway
to Circular Quay. The program supports the
implementation of other Sydney City Centre Access
Strategy initiatives by prioritising vehicle movements
along particular corridors and at identified intersections.
The changes include modifying and realigning traffic
lanes, introducing changes to kerbside uses, adjusting
kerbs, and modifying or removing some on-street
parking.
In-Progress
Sydney Gateway (St
Peters to Sydney
Airport and Port
Botany)
St Peters Eastern City
District
Road Sydney Gateway will provide a high-quality, high-
capacity connection between the airport and port precinct
and the St Peters Interchange.
Planning
Sydney Metro City and
Southwest
Haymarket Eastern City
District
Rail Sydney Metro City and Southwest will extend metro rail
from Sydney’s booming North West region, beneath
Sydney Harbour, through new underground CBD
stations and beyond to Bankstown. The project includes
seven new modern metro stations at Crows Nest,
Victoria Cross, Barangaroo, Martin Place, Pitt Street,
Central and Waterloo that will be fully accessible for
people with a disability, prams and children, including
level access between platforms and trains. The existing
Bankstown Line between Bankstown and Sydenham will
be upgraded and converted to metro standards,
increasing services from eight an hour in the peak to 15
new metro trains every hour with real time information
at metro stations and on board trains.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Sydney Metro
Northwest
Rouse Hill Central City
District
Rail Sydney Metro Northwest is delivering eight new railway
stations and 4000 commuter car parking spaces to
Sydney’s growing North West. Trains will run every
four minutes in the peak, with 15 trains an hour. Sydney
Metro Northwest is the first stage of Sydney Metro and
will be the first fully-automated metro rail system in
Australia. Sydney Metro Northwest will deliver, for the
first time, a reliable public transport service to a region
which has the highest car ownership levels per household
in NSW. Over the coming decades, an extra 200,000
people will move into Sydney’s North West, taking its
population above 600,000, or twice the size of Canberra.
In-Progress
Sydney Motorways
Real Time Travel
Information
Eastern Creek Central City
District
Road Real-time information technology provides motorway
road users with real travel time information to monitor
travel flow and make informed decisions to deliver
improved journey outcomes. Typical travel time
messages will include upcoming exits with estimated
times. Real-time information uses electronic variable
message signage (VMS) to display the estimated length
of time it should take to reach upcoming motorway exits,
based on current traffic flow conditions. Real-time is
updated regularly to provide motorists with accurate and
timely information, for example real-time information on
the M4 Motorway is updated every three minutes. Real-
time information is currently provided on the Eastern
Distributor, Lane Cove Tunnel, Gore Hill and Warringah
Freeways, M1 Pacific Motorway, M2 Hills Motorway,
M4 Western Motorway, M5 East Motorway, M5 South-
West Motorway and M7 Westlink Motorway.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Sydney Olympic Park
Wharf - Wharf
Upgrade Program
Sydney Olympic
Park
Central City
District
Maritime The new wharf is connected to the existing covered
wharf structure and includes a new steel floating
pontoon, small concrete fixed bridge and an aluminium
gangway connecting the bridge to the pontoon. The new
structures are covered. The pontoon has a curved zinc
roof, glass panels and new seating offering some
protection from the weather and improved amenity. The
new wharf provides better protection from the wind, rain
and sun; improved safety for customers; improved access
for mobility impaired customers and customers with
prams; and quicker and more efficient boarding and
disembarking.
Completed
T.H. Halton Park Boat
Ramp Upgrade,
Croudace Bay
Eleebana Hunter Maritime Installation of a new pontoon adjacent to the existing
boat ramp at T.H. Halton Park, Eleebana (Lake
Macquarie). Works also include the construction of an
access pathway between the car park and the new
pontoon.
Planning
Tabulam Bridge
Replacement - Bridges
for the Bush - Program
2
Tabulam New England North West
Road The old Tabulam Bridge over the Clarence River at
Tabulam is part of the Bruxner Highway. It is a State
heritage listed structure and has an overall length of
about 300 metres, comprising 13 timber approach spans
and five composite timber/steel de Burgh truss central
spans. The overall width between kerbs is 4.6 metres,
accommodating only single lane traffic. The new
Tabulam Bridge is being built to improve freight
productivity and reduce maintenance costs.
In-Progress
Tahlee Wharf Upgrade
(Investigation), Port
Stephens
Tahlee Hunter Maritime Planning
Tahmoor Interchange -
Transport Access
Program Upgrade
Tahmoor Western City
District
Interchange Work was undertaken to provide easier access to public
transport, including construction of new accessible
ramps to both platforms, construction of four new
accessible parking spaces and improved safety features
including lighting and CCTV surveillance cameras.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Tamworth Station Refresh Package 4a
Tamworth North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Tangerine Street Fairfield East Western City Road Upgrade of existing marked pedestrian crossing located
on Tangerine Street between Hercules Street and Loftus
Street to a raised marked pedestrian crossing. Includes
the removal of existing marked pedestrian crossing
(zebra), associated signs, kerb ramps
Completed
Taree Station Refresh Package 2a
Taree South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Taylor Park Reserve
cycleway
Queanbeyan
East
South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Taylor Park
Reserve
Completed
Taylors Beach Wharf
Replacement, Port
Stephens
Port Stephens Hunter Maritime Upgrade of the existing wharf at Taylors Beach. Works
include the demolition of the existing wharf and rock
groyne and replacement with a new structure.
Planning
Tea Gardens/Hawks
Nest Foreshore
Redevelopment Master
Plan
Tea Gardens Hunter Maritime Development of foreshore master plan to direct and
schedule improvements to public boating infrastructure
in the coming years.
Foreshore master plan will also address feasibility of
and identify locations for a futureharbour/marina in
Myall River.
Planning
Telarah Interchange -
Commuter Parking
Telarah Hunter Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Telarah Station Refresh Package 4a
Telarah North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Tench Reserve Boat
Ramp Facility
Upgrade, Penrith
Jamisontown West Maritime Planning
Tenterfield Heavy
Vehicle Bypass - New
England Highway
Tenterfield New England North
West
Road A heavy vehicle bypass at Tenterfield is being planned.
The existing highway passes through Tenterfield's
central business district, causing traffic and safety issues
from the mix of heavy vehicle and through traffic with
local trips and pedestrian activity. The bypass would
improve road safety; improve road transport
productivity, efficiency and reliability of travel;
minimise the impact on the natural, cultural and built
environment; provide sustainable economic outcomes for
the local community; minimise social impact on the local
community; and provide value for money.
Planning
Tenterfield Livestock Selling Centre – Truck Wash Installation
Tenterfield New England
North West
Freight Scoping, design and construction of a hardstand access road, truck wash, including AvData and effluent disposal system to Australian Design and EPA Standards
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Termeil Creek -
Princes Highway
Upgrade
Termeil Illawarra
Shoalhaven
Road The upgrade provides a new, straighter 1.6 kilometre
stretch of the Princes Highway and will improve safety
for the more than 7,000 local commuters, freight and
tourist motorists using the road daily. The project also
features a new Termeil Creek Bridge that is 5.3 metres
wider and 26 metres longer than the previous bridge and
is capable of withstanding a one in 100 year flood event.
Key benefits of the project include improved road safety,
safer access for adjacent residents, improved road
geometry and alignment; reduced travel times for traffic
on the Princes Highway with the upgrade constructed to
a 100km/h standard, minimised impact on ecologically
significant habitats and improved creek crossing.
Completed
Terrigal Haven Ocean
Boat Ramp Upgrade Terrigal Central Coast Maritime Upgrade of the Terrigal Haven boat ramp. Works
include: Reprofiling of the boat ramp, installation of boat
access platforms, installation of beach access steps,
removal of seabed debris around the boat ramp and
ancillary works.
Planning
The Avenue Granville Central City Road Install a refuge island on The Avenue north of Daniel
Street, Granville. The project includes construction of a
refuge island with an additional street lighting and
upgrading of the existing street lighting infrastructure.
Completed
The Bucketts Way Stroud Hunter Road Traversable clear zones, widen shoulders Completed
The Coast Road
cycleway
Skennars Head North Coast Walking and Cycling Shared Path cycleway alongside The Coast Road Completed
The Entrance Road Bateau Bay Central Coast Road Install median barrier on northern side of roundabout Completed
The Escort Way Orange Central West and
Orana
Road Sealed shoulder, widened painted median and wire rope
barrier
Design Only
Completed
Name Suburb Region/District Project Type Project Description Current
Status
The Esplanade Warners Bay Hunter Road Remove hazards from clearzone south/east bound
(trees/utility poles), extend median barrier west towards
Alley St
Completed
The Esplanade Speers Point Hunter Road Install median Elscholz barrier with pedestrian fencing
on top, resurfacing
Design Only
Completed
The Esplanade Boat
Ramp Car Park
Upgrade, Swansea
Lake Macquarie Hunter Maritime Upgrade of the car park at the James L Boyd Reserve
boat ramp, Swansea. Works include: formalising (sealing
and line marking) car and trailer parking spaces, and
improvements to the boat ramp manouevring area, access
road, boat rigging and wash down area and dinghy
storage at the site.
Planning
The Horsley Drive
Upgrade
Horsley Park Western City
District
Road Key features of the upgrade include widening and
upgrading The Horsley Drive between the M7 Motorway
and Cowpasture Road to a four lane divided road with a
wide median to allow for six lanes when required;
upgrading the Ferrers Road intersection, Cowpasture
Road north intersection, Cowpasture Road roundabout
and The Horsley Drive eastern approach at the M7
Motorway interchange and Wallgrove Road intersection;
providing an off road shared path for pedestrians and
cyclists that connects to the existing M7 Motorway and
Western Sydney Parkland cycleways; and reserving two
corridors of land, one to the north of The Horsley Drive
between Wallgrove Road and Wallworth Road, and one
east of Cowpasture Road north, to allow for future
upgrade work. Key benefits of the upgrade include
increased road capacity; more reliable travel times;
improved road safety; an improved east-west connection
between the Broader Western Sydney Employment Area
(WSEA), the M7 Motorway and the Wetherill
Park/Smithfield Industrial area; improved access to the
Western Sydney Parklands; improved freight access and
efficiency; improved public transport and improved
landscaping.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
The Northern Road and
Bringelly Road
Interchange - The
Northern Road
Upgrade
Bringelly Western City
District
Road The Northern Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney airport at Badgerys Creek.
It would also improve safety, increase road capacity and
reduce congestion and travel times in the future. The
intersection of The Northern Road and Bringelly Road,
Bringelly is being upgraded to a grade separated
interchange. Key features of the upgrade include an
interchange (underpass) to separate vehicles on The
Northern Road and Bringelly Road to allow for better
traffic flow, with The Northern Road running under
Bringelly Road; widening The Northern Road and
Bringelly Road from two to four lanes with a wide
central median to allow for six lanes in the future;
installing new on and off ramps between Bringelly Road
and The Northern Road, and turning lanes and traffic
lights with pedestrian crossings on Bringelly Road; a
new connection from Robinson Road to The Northern
Road on a new section of Belmore Road; an off-road
shared path for pedestrians and cyclists; and changes to
access for some properties along The Northern Road,
Bringelly Road and Robinson Road.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
The Old Northern Road
to Peter Brock Drive -
The Northern Upgrade
Harrington Park Western City
District
Road The Northern Road Upgrade will deliver new and
upgraded roads to support integrated transport in the
region and capitalise on the economic benefits from
developing a Western Sydney airport at Badgerys Creek.
It would also improve safety, increase road capacity and
reduce congestion and travel times in the future. This
stage of The Northern Road Upgrade is 3.3 kilometres
between The Old Northern Road, Narellan and Peter
Brock Drive, Oran Park. Key features include Key
features include widening The Northern Road to a four
lane divided road with a wide central median and
kerbside bus lane in each direction; a 80km/h speed
limit; a three metre wide off-road shared pedestrian and
cyclist path; designated turning lanes; three intersection
upgrades with traffic lights at Porrende Street, Hillside
Drive and Cobbity Road; two new bridges over Narellan
Creek for northbound and southbound traffic; and
bicycle and pedestrian crossings at traffic lights.
In-Progress
The Putty Road Howes Valley Hunter Road Undertake delineation improvements and shoulder
widening on the outside of curves (where feasible) on the
Putty Road, Howes Valley
Completed
The Putty Road Howes Valley Hunter Road Undertake delineation improvements and shoulder
widening on the outside of curves (where feasible) on the
Putty Road, Howes Valley.
Completed
The Putty Road Howes Valley Hunter Road Install median safety barrier over several curves on the
Putty Road, Howes Valley.
Completed
The Putty Road Putty Hunter Road Shoulder widening and delineation on Putty Rd - 1km
south to 700m north of Putty Valley Road
Completed
The Putty Road Colo Heights Western City Road Delineation and signs Completed
Thirroul Interchange -
Commuter Parking
Thirroul Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide seven
extra commuter car parking spaces.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Thirroul Interchange -
Commuter Parking
Thirroul Illawarra
Shoalhaven
Parking A new commuter car park was constructed on Church
Street to provide 151 commuter parking spaces near
Thirroul Station. The car park also features security
lighting and CCTV surveillance cameras.
Completed
Thirroul Station Refresh Package 1a
Thirroul Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Thomas Humphries
Reserve Boat Ramp
Car Park Upgrade,
Swansea
Swansea Hunter Maritime Upgrade of car/trailer parking at the Thomas Humphreys
Reserve boat ramp. Works include formalisation of 33
car/trailer parking spaces, overflow parking and access
roads at the site.
Planning
Thompson Street Jetty
Upgrade, Iron Cove Drummoyne Central Maritime Planning
Thornleigh Interchange
- Commuter Parking
Thornleigh North District Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Thornton Station Refresh Package 4a
Thornton Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Thunderbolt Drive
cycleway
Raby Western City
District
Walking and Cycling Shared Path cycleway alongside Thunderbolt Drive Completed
Name Suburb Region/District Project Type Project Description Current
Status
Tintenbar to
Ewingsdale - Pacific
Highway Upgrade
Newrybar North Coast Road The Tintenbar to Ewingsdale section of the Pacific
Highway upgrade is about 17 kilometres in length
starting at the northern end of the Ballina bypass at Ross
Lane and extending to the Ewingsdale interchange. Key
features of the upgrade include interchanges for
motorists to safely enter and exit the highway; a four
lane divided road, with a wide median allowing for the
future addition of a third lane in each direction when
required; a motorway standard highway with a 110 km/h
speed limit and no access for traffic between
interchanges; and separated local traffic and highway
traffic by providing a continuous alternative local road
link between Tintenbar and Ewingsdale for school buses
and motorists who do not wish to use the upgraded
highway.
Completed
Tom Ugly's Bridge
Boat Ramp Upgrade &
New Pontoon, Sylvania
Sylvania South Maritime Upgrade of the Tom Ugly's Bridge boat ramp facility.
Works include: demolition of the existing timber wharf
and replacement with a new pontoon and general repairs
to the boat ramp, seawall and footapths at the site.
Planning
Tomago Boat Ramp
Facility Upgrade,
Hunter River
Tomago Hunter Maritime Upgrade of the Tomago boat ramp facility. Works
include sealing and formalising the car park and
installation of an on-ramp pontoon.
Planning
Tomakin Boat Ramp
Upgrade Tomakin South East and
Tablelands
Maritime Upgrade of the boat ramp at Kingston Place, Tomakin.
Works include: Replacement of the exisiting sub-
standard boat ramp with a new single lane concrete ramp
(Stage 1) and formalisation of the existing car park and
upgrade of lighting at the site (Stage 2).
In Progress
Tonkin Park Boat
Ramp Upgrade,
Cronulla
Cronulla South Maritime Upgrade of the boat ramp at Tonkin Oval, Cronulla.
Works include reconstruction of the existing single lane
concrete boat ramp, the installation of a new pontoon or
jetty adjacent to the boat ramp and improvements to
car/trailer parking at the site.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Tooleybuc Bridge
Replacement - Bridges
for the Bush - Program
2
Tooleybuc Riverina Murray Road Roads and Maritime Services, in partnership with
VicRoads, has funding to plan for a future Murray River
bridge on the Mallee Highway at Tooleybuc. The yellow
option, a high level bridge downstream of the existing
bridge, has been identified as the preferred option. The
project is part of the NSW Government's Bridges for the
Bush initiative, which aims to improve freight
productivity in regional areas.
Planning
Tooma Road Jagumba Riverina Murray Road VAS Curve Warning Sign Completed
Toongabbie
Interchange - Transport
Access Program
Upgrade
Toongabbie Central City
District
Interchange Accessibility at Toongabbie Station is being improved
for people with disabilities, limited mobility, parents
with prams, and tourists with luggage. The
improvements at Toongabbie Station include new stairs
and new lifts; new canopies for weather protection;
improvements to bicycle facilities and interchange areas;
new wayfinding signage; three new family accessible
toilets; and improved lighting and CCTV security
surveillance.
In-Progress
Trewilga - Newell
Highway Realignment
Trewilga Central West &
Orana
Road The project involves a new 3.2 kilometre alignment,
widening of traffic lanes and shoulders, providing a
northbound overtaking lane, a truck parking area and a
bus turning area. The project aims to improve the safety
of the highway along this section.
In-Progress
Truck Wash Facility Upgrade at the Cooma Livestock Selling Centre
Cooma South East and
Tablelands
Freight Upgrade and expansion of Truck Wash facilities at the Cooma Livestock Selling Centre. The scope will include:* Construction of 2 new B-Double Truck Wash Bays, including associated earthworks,* Construction of new drying beds, and oil / water separator* Installation of new auxiliary equipment (water break tank, 2 pump sets)* Installation Service Lines, including water supply, drainage and electrical works* Project Management, Project consultation and Project commissioning.(See attached Project Management Plan)
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Truck Wash- Molong Molong Central West and
Orana
Freight The project comprises of the construction of a single bay covered truck wash and effluent disposal pit. A treatment system is included in the construction including a three bed solids trap and dosing and aeration tanks before disposal into the Molong STP. The wash will include contingencies to upgrade to a double bay in the future. The solids trap is a concrete construction utilising screens and gravity to allow the setting of solids in each bed. From a sump, the effluent is than discharged to the secondary treatment, bioreactor system consisting of a series of poly tanks. Concept drawings are attached in supporting documentation.
Planning
Tuggerah Interchange -
Commuter Parking
Tuggerah Central Coast Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Tuggerah Station Refresh Package 1a
Tuggerah Riverina Murray Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Tuggerah to Doyalson -
M1 Pacific Motorway
Widening
Jilliby Central Coast Road The M1 Pacific Motorway is being upgraded between
the Tuggerah and Doyalson interchanges to improve
traffic flow and safety. The upgrade involves widening
the motorway to provide three lanes in each direction
and rebuilding the roadway to provide a smoother and
more durable surface. The upgrade includes widening a
12 kilometre section of the motorway to provide three
lanes in each direction between Wyong Road at
Tuggerah and the Doyalson Link Road; rebuilding a nine
kilometre section of the motorway between Wyong
River and the Doyalson interchange to improve the road
surface; improving road drainage for greater wet weather
safety; and providing safety and capacity improvements
to key motorway interchanges at Warnervale and
Doyalson. Key benefits include increased traffic capacity
along the motorway, more reliable travel times,
improved road safety and a smoother road surface.
In-Progress
Tulladunna Bridge
Replacement - Bridges
for the Bush - Program
1
Wee Waa New England North
West
Road The new bridge provides access for trucks with no height
or width restrictions, improved safety for motorists and
lower bridge maintenance costs. The replacement of this
bridge will remove the only remaining bridge on the
Kamilaroi Highway that cannot take heavy vehicles
allowed to carry an increased maximum weight. Trucks
currently excluded because of the height restrictions of
the current bridge will be able to access the region with a
saving up to two hours in time.
Completed
Tumbarumba Road Carabost Riverina Murray Road Shoulder widening, RRPM's, audio tactile edge line Completed
Tumbulgum Boat
Ramp New Pontoon,
Tumbulgum
Tumbulgum North Coast Maritime Replacement of existing old timber jetty with a new
floating pontoon at the Tumbulgum boat ramp.
Planning
Tuntable Falls Road Nimbin North Coast Road Improve horizontal alignment, install shoulders and w-
beam barrier
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Turramurra Station Refresh Package 2
Turramurra Central City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Turrella Street Turrella Eastern City Road MIST treatments in Nelson and Loftus, remove sight
distance restriction at Nelson, separate through and
parking lanes in Turrella Street. Install RRPMs.
Completed
Turton Street
cycleway
New Lambton Hunter Walking and Cycling Shared Path cycleway alongside Turton Street Completed
Tweed River Canoe
Launch Facility,
Byangum
Byangum North Coast Maritime Provision of a safe and convenient canoe launch facility
(low level jetty) for access to the Tweed River at
Byangum (Col Wiley Park).
Planning
Ulladulla Harbour
Northern Boat Ramp
New Pontoon
(Investigation)
Ulladulla Illawarra
Shoalhaven
Maritime Construction of a low level jetty to assist with vessel
launch/retrieval at the Ulladulla Harbour northern boat
ramp. Improvements to this boat ramp facility will
reduce demand at the Harbour's sourthern boat ramp.
Planning
Unanderra Interchange
- Commuter Parking
Unanderra Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide two extra
commuter car parking spaces.
Completed
Unanderra Interchange
- Transport Access
Program Upgrade
Unanderra Illawarra
Shoalhaven
Interchange Improvements included remediation of the existing
station platform, reinstating CCTV, lighting, draining
and maintenance to the existing pedestrian footbridge.
Completed
Unanderra Station Refresh Package 4a
Unanderra South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
University Drive Callaghan Hunter Road Install mastarms Completed
Upper Clarence River
Sewage Pump-out
Facility (Investigation)
Woodford
Island
North Coast Maritime Planning
Urban Roads Pinch
Point Program
Parramatta Central City
District
Road Congestion will be eased and traffic flows will be
improved on 32 of Sydney’s busiest road corridors over
the next 10 years. These corridors include Cumberland
Highway, Parramatta Road, Old Windsor Road, The
Kingsway, Campbelltown Road and Hoxton Park Road.
Projects to help ease congestion at pinch points include
widening small sections of road or intersection;
lengthening turn bays; adding extra turn bays or turning
lanes; replacing heavily used roundabouts with traffic
signals; and installing closed circuit television cameras
and electronic message signs to help manage traffic and
provide real-time traffic information to motorists to help
them make informed travel decisions.
In-Progress
Valentine Crescent
Jetty Upgrade
(Investigation),
Valentine
Valentine Hunter Maritime Upgrade of the existing Valentine Crescent jetty with the
installation of a new pontoon and gangway (off the end
of the jetty) allowing for short term berthing of boats.
Planning
Vantage Crescent
cycleway
Kellyville Central City
District
Walking and Cycling Shared Path cycleway alongside Vantage Crescent Completed
Victoria Avenue
cycleway
Castle Hill Central City
District
Walking and Cycling Shared Path cycleway alongside Victoria Avenue Completed
Victoria Road Parramatta Central City Road Upgrade seal to high friction seal at the intersection -
25m on the northbound right turn lanes and 60m east on
the eastbound lanes.
Completed
Victoria Road Ryde North Road Upgrade seal to high friction surface on both east and
westbound carriageways. Extend existing westbound F-
type barrier by 20m
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Victoria St Station Refresh Package 2a
East Maitland South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Victoria Street
cycleway
Howlong Riverina - Murray Walking and Cycling Shared Path cycleway alongside Victoria Street Completed
Victoria Street
Interchange - Transport
Access Program
Upgrade
East Maitland Hunter Interchange Improvements are planned to provide easier access to
public transport. Facilities being considered include new
lifts and canopies, a family accessible toilet, installation
of accessible parking and taxi bays on both sides of the
station, footpath improvements, lighting and CCTV.
In-Progress
Villawood Interchange
- Commuter Parking
Villawood Western City
District
Parking Extension of Villawood Station car park to provide 37
additional commuter parking spaces and the installation
of additional lighting, CCTV cameras, line marking and
fencing.
Completed
Wagga Wagga Station Refresh Package 4a
Turvey Park South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Waitara Station Refresh Package 3
Waitara North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Wakaden Street
cycleway
Griffith Riverina - Murray Walking and Cycling Shared Path cycleway alongside Wakaden Street Completed
Walcha Truck Wash Bay Upgrade
Walcha New England
North West
Freight Installation of Avdata key systemInclusion of basic shower and toilet amenitiesUpgrade the existing concrete wash bay - widening and lengtheningConstruction of a passenger side footpathReplacement and lengthening of steel walkwayRelocation of pump houseConstruction of concrete solid trapsConstruction of drying bedInstallation of effluent treatment systemsInstallation of additional lightingSecurity fencing around solid traps and drying bedsRefurbishment of existing holding damConstruction of new effluent dump point to suit all vehicles
Planning
Walgett Saleyards Truck Wash Upgrade
Walgett Far West Freight Installation of containerised unit truck wash and electronic water billing system at Walgett saleyards.
Planning
Walla Avenue Griffith Riverina Murray Road Install single lane roundabout Completed
Wallarah Road
cycleway
Kanwal Central Coast Walking and Cycling Shared Path cycleway alongside Wallarah Road Completed
Wallarobba
Interchange - Transport
Access Program
Upgrade
Wallarobba Hunter Interchange Improvements to Wallarobba Station included
construction of a new accessible ramp; an accessible
parking space with footpath leading to the ramp; and
upgraded safety features including lighting and CCTV
surveillance cameras.
Completed
Wallgrove Road
cycleway
Eastern Creek Central City
District
Walking and Cycling Shared Path cycleway alongside Wallgrove Road Completed
Name Suburb Region/District Project Type Project Description Current
Status
Wallsend to
Broadmeadow,
Newcastle Link Road /
Thomas Street /
Newcastle Road
Upgrade
Wallsend Hunter Road Six intersections between the M1 Pacific Motorway and
Newcastle were upgraded in anticipation of increased
traffic as a result of the Hunter Expressway. Work
included the replacement of roundabouts with traffic
signals and providing additional lanes.
Completed
Walters Road Berala Central City Road Install a single lane roundabout Completed
Waratah Station Refresh Package 4a
Waratah South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Warialda Truck Wash/ Effluent Disposal Facility
Warialda New England
North West
Freight Construction of new intersection with HW12 Gwydir Highway, new access road to truck wash/ effluent dump facility, truck wash pads and pits, associated pressure washers effluent collection pits and pumps. Connection of electricity and construction of rising main to existing sewerage main for effluent supernatant.
Planning
Warnervale Link Road
- Pacific Highway,
Watanobbi and Sparks
Road, Warnervale
Watanobbi Central Coast Road A future road is being planned between the roundabout
at the Pacific Highway and Britannia Drive at Watanobbi
and Sparks Road at Warnervale to improve traffic flow
and connectivity. Key benefits of a future road would
include improved connectivity, traffic flow and travel
times for motorists; improved pedestrian and cyclist
access; and improved safety for all road users.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Warnervale Station Refresh Package 2a
Warnervale South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Warnervale Town
Centre - Sparks Road
Woongarrah Central Coast Road Key features of the upgrade include a new intersection
for the new Warnervale town centre to provide safe
access for all road users; increased capacity on Sparks
Road with two lanes in each direction between
Minnesota Road and the new Warnervale town centre
intersection to reduce congestion and allow for future
growth; two right turn lanes into Mary MacKillop Drive
at the Minnesota Road intersection to ease congestion in
peak periods; provision of street lighting on Sparks Road
between Minnesota Road and the new Warnervale town
centre intersection to improve safety; new shared cyclist
and pedestrian path between Minnesota Road and the
new Warnervale town centre intersection to provide for
cyclists; and provision of on-road cycle lanes in both
directions on Sparks Road.
Completed
Warrali Avenue
cycleway
Wilcannia Far West Walking and Cycling Shared Path cycleway alongside Warrali Avenue Completed
Name Suburb Region/District Project Type Project Description Current
Status
Warrell Creek to
Nambucca Heads -
Pacific Highway
Upgrade
Macksville North Coast Road The Pacific Highway is being upgraded to a four lane
divided carriageway between the Allgomera deviation,
south of Warrell Creek and Nambucca Heads, just south
of the railway line. Key features include a four lane
divided carriageway with safe driving conditions for
speeds of 110 km/h; no direct property access to or from
the highway; grade-separated interchanges at South
Macksville at Bald Hill Road and Warrell Creek at
Browns Crossing Road; a continuous local road between
Warrell Creek and Nambucca Heads combining new
roads and the existing Pacific Highway; a rest area for
light and heavy vehicles at the Nambucca Heads
interchange; new bridges over Warrell Creek and the
Nambucca River at Macksville; and floodplain bridges
and culverts across sections of the Gumma floodplain.
Key benefits of the upgrade include improved road
safety; uninterrupted highway traffic flow; and easy
access on and off the highway for local traffic.
In-Progress
Warwick Farm
Interchange -
Commuter Parking
Warwick Farm Western City
District
Parking Conversion of existing staff car park to provide five
extra commuter car parking spaces.
Completed
Washington Drive Boat
Ramp Upgrade, Bonnet
Bay
Bonnet Bay South Maritime Upgrade of the Washington Drive boat ramp, Bonnet
Bay. Works include: minor repairs to the existing boat
ramp, installation of a pontoon adjacent to the ramp and
improvements to the existing car park at the site.
Planning
Waterfall Interchange -
Commuter Parking
Waterfall South District Parking Conversion of existing staff car park to provide eight
extra commuter car parking spaces.
Completed
Waterfall Interchange -
Transport Access
Program Upgrade
Waterfall South District Interchange Improvements to Waterfall Station included a new
concourse with level access to the Kooraban Street
overbridge, a new lift from the concourse to the station
platform, weather protection canopies on the station
platform, resurfaced Kooraban Street overbridge
footpath, raised station platform level, accessible toilets
on the station platform level, new 'kiss and ride' facility,
and upgrading the existing bicycle storage facilities.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Waterfall Way Bellingen North Coast Road A range of projects on Waterfall Way are being
undertaken including planning investigations and work
in the following sections: Connells Creek to East
Fernmount improvements; delivery of Bellingen Main
Street plan (stages one and two); and road upgrades
seven kilometres west of Ebor and east of Armidale.
Recently completed projects on the Waterfall Way
include Sweedmans Lane improvements, St Helena to
Four Mile Bridge upgrade, installation of two vehicle
activated speed devices, speed zone reviews between
Thora and Dorrigo, development of the Bellingen Main
Street project and landslip repair and realignment work
at Nut Farm and Weeping Jenny.
In-Progress
Waterfall Way Wollomombi New England North
West
Road Shoulder widening, guard fencing and remove hazards
from clearzones
Completed
Waterhen Park Boating
Facilities
Improvements
(Investigation), Nerong
Nerong Hunter Maritime Development of a plan to direct and schedule
improvements to public boating infrastructure in the
future.
Planning
Watson Street
cycleway
Molong Central West &
Orana
Walking and Cycling Shared Path cycleway alongside Watson Street Completed
Wauchope Interchange
- Transport Access
Program Upgrade
Wauchope North Coast Interchange Improvements to the transport interchange at Wauchope
include new footpaths and a waiting area.
Completed
Wentworth Falls
Interchange - Transport
Access Program
Upgrade
Wentworth Falls Western City
District
Interchange Wentworth Falls Station is being upgraded to improve
access for customers. The project includes three new
lifts; weather protection canopies along the existing
footbridge, stairs and entrance areas; improved station
facilities including accessible toilets and waiting areas;
improved station forecourts with bicycle storage
facilities; extension of the Railway Parade car park to
provide formal kiss and ride and turning space; and new
kiss and ride on Station Street.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
Wentworth Falls Station Refresh Package 1a
Wentworth Falls New England North West
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Wentworthville
Interchange - Transport
Access Program
Upgrade
Wentworthville Central City
District
Interchange Wentworthville Station is being upgraded to improve
access for customers. The project includes four new lifts
and stairs with canopies; a new concourse area; a family
accessible toilet; refurbishments of the existing
footbridge; and pedestrian access and transport
interchange improvements.
In-Progress
Wentworthville Station Refresh Package 4
Wentworthville Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Werrington Arterial
Road, M4 Motorway to
Great Western
Highway
Claremont
Meadows
Western City
District
Road Kent Road and Gipps Street, Claremont Meadows is
being upgraded to form the new Werrington Arterial
Road. Key features include widening Gipps Street and
Kent Road to four lanes between the M4 Motorway and
the Great Western Highway; new eastbound entry and
westbound exit ramps with traffic lights for the M4
Motorway; three intersection upgrades with traffic lights
at Caddens Road/Kent Road, Fowler Street/Gipps Street
and Sunflower Drive (north)/Gipps Street; a three metre
wide off-road shared path for pedestrians and cyclists,
including a new bridge over the M4 Motorway; bicycle
and pedestrian crossings at traffic lights; six bus bays on
both sides of Gipps Street and Kent Road; posted vehicle
speeds of 70km/h south of Caddens Road; new line
marking on the Kent Road Bridge to create two
northbound lanes and one southbound lane; two metre
wide shoulders; and noise wall on the western side of
Gipps Street between Caddens Road and the Great
Western Highway. The key benefits of the project are
improved access to the M4 Motorway, increased road
capacity; improved safety for motorists; more reliable
travel times; and improved access and safety for
pedestrians and cyclists through an off-road shared path.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
West Gosford to
Narara – Manns Road
between Stockyard
Place, West Gosford
and Narara Creek
Road, Narara
West Gosford Central Coast Road A future upgrade of Manns Road between Stockyard
Place, West Gosford and Narara Creek Road, Narara is
being planned to improve traffic flow and safety. The
proposal would investigate widening the road to provide
two lanes in each direction, separated by a central
median; replacing the narrow bridge near Nells Road;
installing traffic lights where required to improve access
to major connecting roads; restricting access to some
minor roads; providing pedestrian and cyclist facilities;
and improvements to drainage. Key benefits of a future
upgrade would include improved traffic flow and travel
times for motorists, improved access to major connecting
roads, improved pedestrian and cyclist access, and
improved safety for all road users.
Planning
West Kempsey
Racecourse
Interchange - Transport
Access Program
Upgrade
West Kempsey North Coast Interchange Provision of new footpaths. Completed
West Kempsey School
Interchange - Transport
Access Program
Upgrade
West Kempsey North Coast Interchange Improvements to four waiting areas at St Paul's College. Completed
West Pennant Hills
(Oakes Road) -
Commuter Parking
West Pennant
Hills
Central City
District
Parking Commuter car park providing up to 275 spaces. Planning
West Ryde Interchange
- Commuter Parking
West Ryde North District Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
West Ryde Station Refresh Package 3
West Ryde North Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
West Wyalong Heavy
Vehicle Alternative
Route
West Wyalong Riverina - Murray Road The West Wyalong heavy vehicle alternative route is
being upgraded to improve safety and meet the demands
of the increasing amount of freight being carried on the
Newell Highway. The key benefits of the upgrade to the
community include reduced conflict between local traffic
and heavy vehicles; improved safety at intersections for
turning vehicles; improved freight capacity; and no
through traffic on Green Street and Old Hospital Road.
In-Progress
WestConnex - Stage
1A - M4 Widening
(Parramatta to
Homebush)
Lidcombe Central City
District
Road Stage 1A of WestConnex involves upgrading the
existing M4 Western Motorway to four lanes in each
direction between Church Street, Parramatta and
Homebush Bay Drive, Homebush, providing an extra
lane for motorists using this section of the motorway and
helping to alleviate congestion around the James Ruse
Drive ramps. Key work includes widening of the
motorway in the existing corridor between Junction
Street, Silverwater (about 1.4 kilometres west of the
Silverwater Road exit) and Homebush Bay Drive,
Homebush; new access from Hill Road, Sydney Olympic
Park to the M4 eastbound; a new access ramp for
southbound Homebush Bay Drive motorists to access the
M4 westbound, helping alleviate congestion and
removing the need for a right hand turn at traffic lights; a
new elevated road on the southern side of the M4
between Church Street, Parramatta and Wentworth
Street, Granville; and a new bridge between Wentworth
Street, Granville and Junction Street, Silverwater.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
WestConnex - Stage
1B - M4 East
(Homebush to
Haberfield)
Burwood Eastern City
District
Road Stage 1B of WestConnex involves extending the M4
Motorway in tunnels between Homebush and Haberfield
via Concord, and includes provision for the future
connection to M4 – M5 Link. The M4 East will reduce
congestion at the end of the M4, saving travel time for
motorists and removing cars and freight traffic from
local streets. Some key benefits of the M4 East project
include connecting to the existing M4 Motorway
westbound at Concord Road; improving access to the
existing M4 at Homebush Bay Drive, increasing
reliability for through traffic; removing an estimated
3,000 trucks each day from Parramatta Road; providing
new, wider footpaths, street landscaping and other
surface road improvements for local residents at
Patterson Street, Concord and Wattle Street, Haberfield;
improving access via interchanges at Concord Road
Concord, Parramatta Road, Ashfield and to City West
Link, Haberfield; and including ramps on Wattle Street
for a proposed M4-M5 Link.
In-Progress
WestConnex - Stage 2 -
King Georges Road
Interchange Upgrade
(Beverly Hills)
Beverly Hills South District Road The King Georges Road interchange upgrade will
increase capacity on the King Georges Road on and off
ramps to the M5 Motorway, relieving one of Sydney’s
worst bottlenecks. The upgrade connects to the widened
M5 South West Motorway, which now has three lanes
each way, west of Penshurst Road. The upgrade also
makes provision for the future connection to the New
M5.
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
WestConnex - Stage 2 -
New M5 (Beverly Hills
to St Peters)
Arncliffe Eastern City
District
Road The New M5 will link to the upgraded King Georges
Road Interchange on the existing M5 East Motorway at
Beverly Hills and run via twin tunnels to St Peters. The
New M5 tunnels will more than double the capacity of
the M5 East corridor, improving travel times and
reliability for the 100,000 motorists which use this key
route every day. Key features of the New M5 will
include around nine kilometres of new motorway
tunnels, line marked for two traffic lanes in each
direction, and capable of accommodating up to three
lanes in the future, if required; widening and realigning
the existing M5 East Motorway just east of King
Georges Road; a new interchange at St Peters; enhanced
and upgraded local streets near St Peters Interchange;
around 14 kilometres of new and upgraded shared,
pedestrian and cycle paths, including new bridges across
Alexandra Canal and Campbell Road, St Peters; a land
bridge linking Sydney Park with new public open space
at the St Peters Interchange; tunnels that will be taller,
wider and less steep than the existing M5 East resulting
in a smoother ride for motorists, reducing emissions and
improving air quality outcomes. The New M5 will
improve connections across Sydney for businesses,
freight vehicles, buses and commuters, providing relief
to hundreds of thousands of road users struggling in
traffic every day; support development and growth in
south west Sydney and link this booming area of Sydney
to the Global Economic Corridor around Sydney Airport,
Port Botany and the south Sydney area; reduce traffic on
the M5 East, improving travel speeds for heavy vehicles
travelling to and from Sydney Airport and Port Botany,
and boosting productivity; and provide new opportunities
for continued urban growth and renewal in Sydney’s
south west, taking into account the needs of growing
populations at Erskineville (Ashmore Estate urban
renewal) and Mascot (Mascot station urban renewal).
In-Progress
Name Suburb Region/District Project Type Project Description Current
Status
WestConnex - Stage 3 -
M4-M5 Link
(Haberfield to St
Peters)
Forest Lodge Eastern City
District
Road The M4-M5 Link will connect the extended M4
Motorway at Haberfield with the New M5 in St Peters,
easing congestion on Victoria Road and City West Link
and improving local connections across the inner west.
The M4-M5 Link will ease congestion on local roads
allowing for increased use by pedestrians, cyclists and
public transport; connect the neighbourhoods of
Annandale and Rozelle and provide a green link between
Bicentennial Park and Easton Park; future-proof
Sydney’s transport network by allowing for connections
to the proposed Western Harbour Tunnel and Beaches
Link; improve travel time and reliability for bus services,
business, personal, trade and freight journeys; reduce car
and heavy vehicle traffic on key major roads across the
inner west; and provide improved access to the Bays
Precinct for local vehicles, pedestrians and cyclists.
Planning
Western Harbour
Tunnel and Beaches
Link
Mcmahons Point North District Road Planning and development activities are being carried
out by Roads and Maritime Services to inform a final
business case for the Western Harbour Tunnel and
Beaches Link. This would deliver another Sydney
Harbour road crossing and link WestConnex at Rozelle
with the Gore Hill or Warringah freeways as well as
provide a connection to Sydney’s Northern Beaches.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Western Sydney
Airport
Luddenham Western City
District
Interchange On 15 April 2014 the Australian Government announced
that Commonwealth-owned land at Badgerys Creek will
be the site for a second Sydney airport. Western Sydney
Airport would cater for ongoing growth in demand for
air travel, particularly in the rapidly expanding Western
Sydney region, as well as providing additional aviation
capacity in the Sydney region more broadly. An airport
in Western Sydney would also provide long term
economic and employment opportunities in the
surrounding
area and accelerate the development of critical
infrastructure and urban development. The airport is
planned to be operational by the mid-2020s and would
service both domestic and international markets.
Development would be staged in line with ongoing
growth in aviation demand.
For more information, please visit:
http://westernsydneyairport.gov.au/
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Western Sydney
Airport Fuel Pipeline
Badgerys Creek Western City
District
Road The preservation of a fuel pipeline corridor to the
planned Western Sydney Airport is listed as a high-
priority project for near term delivery in the Australian
Infrastructure Plan released in February 2016. Western
Sydney is at the heart of a surge in Sydney’s population
and economic activity. This growth will drive an
increase in road use by commercial and private vehicles,
and will raise demand for transport fuel. Western Sydney
Airport is expected to commence operation by 2025.
Once operations ramp up, the airport will require 43 B-
double tanker aviation fuel deliveries per day, which
would add to congestion on Sydney’s urban road
network. The reliance on fuel transportation by heavy
vehicles could also generate congestion problems at the
airport site, contribute to delay costs along key freight
corridors, and increase safety risks for road users. A fuel
pipeline system is being proposed to help address some
of these issues. While not required when operations at
Western Sydney Airport commence, the identification
and protection of a corridor will ensure that a route for
the pipeline is available when required to connect the
airport to the Port Botany fuel pipeline network and
connected import terminals.
Planning
Western Sydney
Freight Line
Horsley Park Western City
District
Rail Western Sydney is a major destination for freight
journeys, particularly for those coming in from Port
Botany and also Port Jackson. The most recent additions
to the motorway network have assisted in the freight task
to this area. However, rail infrastructure (particularly
dedicated rail infrastructure) does not service this area
well. Without investment in this area, it is unlikely that
the targeted rail freight modal share will be met. We will
continue to work with the Australian Government to
identify further opportunities to advance this corridor
and look to protecting the corridor to ensure its viability
into the future.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Western Sydney fuel pipeline
Mascot Central District Freight Planning
Western Sydney
Intermodal Terminal
Kemps Creek Western City
District
Road Western Sydney is a major destination for freight
journeys, particularly for those coming in from Port
Botany and also Port Jackson. The most recent additions
to the motorway network have assisted in the freight task
to this area. However, rail infrastructure (particularly
dedicated rail infrastructure) does not service this area
well. Without investment in this area, it is unlikely that
the targeted rail freight modal share will be met. We will
continue to work with the Australian Government to
identify further opportunities to advance this corridor
and look to protecting the corridor to ensure its viability
into the future.
Planning
Western Sydney Rail
Upgrade
Parramatta Central City
District
Rail The program will improve the current network and
provide additional and faster services for the T1 Western
Line including Penrith and Parramatta. The
improvements include additional track, signalling and
power supply upgrades to enable more express trains into
the CBD, and technology that will allow more trains per
hour to travel on the Western Line.
In-Progress
Westmead Interchange
- Commuter Parking
Westmead Central City
District
Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Westport Park Boat
Ramp Upgrade, Port
Macquarie
Port Macquarie North Coast Maritime Stage 2 in the upgrade of the Westport Park boat ramp
facilty, Port Macquarie. Works include widening the
existing boat ramp (from a 2 lane ramp to a 4 lane ramp),
the installation of a second on-ramp modular pontoon,
and formalisation of car/trailer parking.
Planning
Wharf Reserve Boat
Ramp Facility
Upgrade, Clarence
Town
Clarence Town Hunter Maritime Planning
Name Suburb Region/District Project Type Project Description Current
Status
Wharf Road Melrose Park Central City Road Install a refuge island in Hope Street west of Wharf
Road, Melrose Park. The project includes construction of
a refuge island with new street lighting and
reconstruction of kerb and gutter.
Completed
Wharf Road
cycleway
North Batemans
Bay
South East &
Tablelands
Walking and Cycling Shared Path cycleway alongside Wharf Road Completed
White Bay Cruise
Terminal
Balmain Eastern City
District
Freight Sydney has long been the only port in Australia with two
cruise facilities but this new terminal demonstrates the
NSW Government’s commitment to investing in key
infrastructure to meet the huge growth in cruise demand
in our city.
Completed
Wilfred Barrett Drive The Entrance Central Coast Road Kerbside barrier on the north western corner of the
roundabout, traffic calming at the roundabout
Completed
Wilson Drive Hilltop South East and
Tablelands
Road Construct a 2.5m wide off road shared pathway with
pedestrian refuge and kerb ramps along Wilson Drive,
Hilltop (250m).
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Windsor Bridge
Replacement
Windsor Western City
District
Road Key features of the project include a new bridge with
two lanes 35 metres downstream of the existing Windsor
Bridge; new approach roads and intersections to connect
the new bridge to the existing road network; new traffic
lights with pedestrian facilities at the intersection of
Bridge Street and George Street; modifications to local
roads and access arrangements, including changes to the
Macquarie Park access road and reconnection of The
Terrace; a new dual lane roundabout at the intersection
of Wilberforce Street and Freemans Reach Road;
pedestrian and cyclist facilities, including a shared path
for access to and across the new bridge; removal and
backfill of the existing bridge approach roads; removal
of the existing bridge once the new bridge is operational;
and landscaping and urban design work, including within
the Thompson Square parkland area and adjacent to the
northern intersection of Wilberforce Road, Freemans
Reach Road and the Macquarie Park access road. Key
benefits of the project include improved safety for
motorists, pedestrians and cyclists from a new, reliable
bridge; improved traffic flow from a bridge that allows
two-way heavy vehicle traffic and shoulders for vehicle
breakdowns; upgrading an essential local and regional
road link across the Hawkesbury River at Windsor;
improved traffic efficiency by installing traffic lights at
the intersection of Bridge and George Streets and a new
dual-lane roundabout at Freemans Reach Road and
Wilberforce Road; a new bridge that can cope with
higher levels of flooding; better access for pedestrians
and cyclists from a three metre wide shared pedestrian
and cycle path that provides safe, efficient connections to
Thompson Square and surrounds; reduced road footprint
within the Thompson Square heritage precinct; and a
unified open space in Thompson Square increasing the
usable area in the square by more than 500 square metres
with direct access to the river.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Windsor Interchange -
Commuter Parking
Windsor Western City
District
Parking Conversion of existing staff car park to provide four
extra commuter car parking spaces.
Completed
Windsor Interchange -
Transport Access
Program Upgrade
Windsor Western City
District
Interchange Windsor Station was upgraded to make train travel from
this station more accessible for customers. Features
included a new station building, reconfiguration and
refurbishment of the existing station building,
reconstruction of the platform, replacement of awnings,
upgrade of the public address, CCTV and lighting
systems.
Completed
Windsor Road to Lane
Cove Road - M2
Motorway Upgrade
Macquarie Park North District Road The upgrade delivered new west facing Windsor Road
on and off-ramps; an additional eastbound lane from
Windsor Road to Pennant Hills Road; an additional
eastbound lane from Pennant Hills Rd through the M2
Tunnel to Lane Cove Road; a new Christie Road
eastbound on-ramp; a new Herring Road westbound off-
ramp; additional westbound lane from Beecroft Road to
Pennant Hills Road; widened road between Lane Cove
Road and Beecroft Road to reinstate the 3.5 metre traffic
lanes and 2.5 metre breakdown shoulder for cyclists; and
Norfolk Tunnel widened in both directions. Key benefits
of the upgrade include reduced congestion during
morning and afternoon peak periods; new access points
to Sydney's growing residential and business precincts;
restoration of a 100km/h speed limit along the motorway
from Lane Cove Road to Beecroft Road; new entry/exit
points to create opportunities for additional public
transport services and facilities; increased capacity to
accommodate planned future residential and business
growth; and an estimated 12 per cent reduction in travel
time for bus commuters, with a five minute travel time
saving expected between Seven Hills and Macquarie
Park.
Completed
Wine Country Drive Pokolbin Hunter Road Install roundabout Completed
Name Suburb Region/District Project Type Project Description Current
Status
Wine Country Drive Rothbury Hunter Road Install median safety barrier Completed
Wine Country Drive
cycleway
Nulkaba Hunter Walking and Cycling Road Shoulder cycleway alongside Wine Country
Drive
Completed
Wisemans Ferry Boat
Ramp Facility Upgrade Wisemans Ferry North Maritime Upgrade of the boat ramp and car park at Wisemans
Ferry. Works include: replacement of the existing single
lane ramp with a new two lane concrete ramp,
improved/expanded car parking and improvements to
vehicle access at the site.
Planning
Wisemans Ferry Public
Wharf New Pontoon Wisemans Ferry North Maritime Construction of a new pontoon at the Wisemans Ferry
public wharf.
Planning
Wisemans Ferry Road Maroota Central City Road Shoulder, curve advisory signs and cams Completed
Wisemans Ferry Road Cattai Central City Road Shoulder, curve advisory signs and cams Completed
Wollombi Road Broke Hunter Road Speed reductions, roadside w-beam barriers, line
marking, signage
Completed
Wollongong
Interchange -
Commuter Parking
Wollongong Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide 40 extra
commuter car parking spaces.
Completed
Wollongong Station Refresh Package 1
Wollongong Illawarra Shoalhaven
Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Woodburn Evans
Head Road cycleway
Evans Head North Coast Walking and Cycling Shared Path cycleway alongside Woodburn Evans
Head Road
Completed
Woodford to
Hazelbrook - Great
Western Highway
Upgrade
Woodford Western City
District
Road The upgrade included widening and straightening of a
3.4 kilometre section of the highway to cater for
increased traffic volumes and provide improved road
safety; protected turning centre bays at Clear View
Parade, Park Road and Woodford Avenue; new full-size
bus bays to improve access for bus commuters; and a
new pedestrian bridge.
Completed
Woodstock Avenue
cycleway
Rooty Hill Central City
District
Walking and Cycling Shared Path cycleway alongside Woodstock
Avenue
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Woolgoolga to Ballina
- Pacific Highway
Upgrade
Maclean North Coast Road Key features of the upgrade include duplication of 155
kilometres of the Pacific Highway to a motorway
standard (Class M) or arterial road (Class A), with two
lanes in each direction and room to add a third lane if
required in the future; grade-separated interchanges at
Range Road, Glenugie, Tyndale, Maclean, Yamba /
Harwood, Woombah (Iluka Road), Woodburn,
Broadwater and Wardell; bypasses of South Grafton,
Ulmarra, Woodburn, Broadwater and Wardell; about 40
bridges over rivers, creeks and floodplains, including
major bridges crossing the Clarence and Richmond
Rivers; bridges over and under the highway to maintain
access to local roads that cross the highway; access roads
to maintain connections to existing local roads and
properties; structures designed to encourage animals over
and under the upgraded highway where it crosses key
animal habitat or wildlife corridors; rest areas located at
Pine Brush (Tucabia) and north of Mororo Road; and a
heavy vehicle checking station near Halfway Creek.
When complete, the upgrade will reduce overall length
from 180 kilometres to 167 kilometres, saving about 13
kilometres in travel distance; allow for a higher posted
speed limit of up to 110 km/h; reduce travel time from
130 minutes to about 105 minutes, saving 25 minutes;
reduce crash rates by an expected 27 per cent due to
divided carriageways; and improve travel reliability
through better flood immunity, fewer incidents and more
readily available alternative routes.
In-Progress
Woollamia Boat Ramp
New Pontoon and Car
Park Upgrade
Woollamia Illawarra
Shoalhaven
Maritime Improvements to boating infrastructure at the Woollamia
boat ramp precinct. Works will be staged to include:
Stage 1 - the preparation of a masterplan to inform
improved water access (new pontoon); improved car
parking and associated utilities at the boating precinct.
Stage 2 to be the construction of identified works in the
masterplan.
Planning
Name Suburb Region/District Project Type Project Description Current
Status
Woonona Interchange -
Commuter Parking
Woonona Illawarra
Shoalhaven
Parking Conversion of existing staff car park to provide one extra
commuter car parking space.
Completed
Woonona Station Refresh Package 4a
Woonona South Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Woy Woy Interchange
- Commuter Parking
Woy Woy Central Coast Parking The new multi-storey commuter car park above the
existing Deepwater Plaza car park provides 300
commuter car parking spaces. The new car park includes
17 accessible spaces, lighting, and CCTV surveillance.
Completed
Woy Woy Interchange
- Commuter Parking
Woy Woy Central Coast Parking Conversion of existing staff car park to provide 24 extra
commuter car parking spaces
Completed
Woy Woy Station Refresh Package 1a
Woy Woy Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Wyee Station Refresh Package 3a
Wyee Western City Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Wynyard Station
Upgrade
Sydney Eastern City
District
Interchange Wynyard Station is being upgraded to create a new
gateway to Barangaroo and Sydney’s financial district.
Key features include new fixtures and finishes, such as
lighting, tiling and painting; widened paid concourse and
additional ticket gates; reduced clutter on the concourse
and platforms; upgraded existing and new platform stairs
to improve pedestrian circulation and reduce queuing;
new wayfinding and signage to make it easier for
customers to move in and around the station; improving
operational reliability through upgraded services and
removal of redundant services; and renovated back of
house areas, including new and relocated Station
Manager’s office. The upgrade will enhance customer
comfort and safety and improve service efficiency. The
project will achieve this by improving amenity to create
a new gateway for Sydney’s financial district and
western CBD; increasing capacity for future passenger
demand and network growth; improving pedestrian flow,
making it easier for customers to move in and around the
station; reducing clutter on the platforms, making it
easier and safer to board and alight from trains and
improving punctuality of services and improving
connectivity between Pitt and George Streets through to
the western CBD and waterfront.
In-Progress
Wyong Interchange -
Commuter Parking
Wyong Central Coast Parking Conversion of existing staff car park to provide nine
extra commuter car parking spaces.
Completed
Wyong River Boat
Ramp Facility
(Investigation), South
Tacoma
Tacoma South Central Coast Maritime Investigate a new boat ramp, parking and jetty/pontoon. Planning
Wyong Road Killarney Vale Central Coast Road Improve sight distance by removing vegetation Completed
Name Suburb Region/District Project Type Project Description Current
Status
Wyong Road & Pacific
Highway upgrade at
Tuggerah
Tuggerah Central Coast Road The upgrade involves replacing the existing roundabout
with traffic lights to improve traffic flow and safety. The
upgrade will ease congestion and improve traffic flow
along the Pacific Highway and Wyong Road for more
reliable travel times during peak periods. It includes
three lanes in each direction on Wyong Road; three right
turn lanes from the Pacific Highway to Wyong Road (to
the M1 Pacific Motorway); two right turn lanes from
Wyong Road to the Pacific Highway (to Wyong); two
left turn lanes from Wyong Road to the Pacific Highway
(to Wyong); building a new bridge beside the existing
railway overbridge to accommodate eastbound traffic;
and extending the existing pedestrian/cycle underpass.
In-Progress
Wyong Road
Intersection Upgrade at
Enterprise Drive
Berkeley Vale Central Coast Road Key features of the upgrade include provision of bus
jump lanes at the traffic lights for both directions on
Wyong Road to assist public transport; double right turn
lanes from Enterprise Drive into Wyong Road; single left
turn lane from Wyong Road into Enterprise Drive;
double left turn lanes from Enterprise Drive into Wyong
Road; double right turn lanes from Wyong Road into
Enterprise Drive; double right turn lanes from Chittaway
Road into Wyong Road; and cyclists would be catered
for with provision for a shared pedestrian cycleway on
both sides of Wyong Road. Key benefits of the upgrades
include improved traffic flow on Wyong Road, improved
safety for all road users and an improved pedestrian and
cycle network.
Completed
Name Suburb Region/District Project Type Project Description Current
Status
Wyong Road
Intersection Upgrades
at Tumbi Road and
Mingara Drive
Tumbi Umbi Central Coast Road The upgrades involve replacing the existing roundabouts
with traffic lights to improve traffic flow and safety,
while catering for future traffic growth. Key features of
the Tumbi Road intersection upgrade include double
right turn lanes from Wyong Road into Tumbi Road;
double left turn lanes (westbound) from Tumbi Road into
Wyong Road; single right turn lane (eastbound) from
Tumbi Road into Wyong Road; provision for left in and
left out traffic movements at Watson Avenue for
eastbound traffic on Wyong Road; provision for a
signalised right turn traffic movement into Watson
Avenue for westbound traffic on Wyong Road; and
provision for a signalised right turn traffic movement
(westbound) from Watson Avenue into Wyong Road for
buses only. Key features of the Mingara Drive
intersection upgrade include three lanes (westbound) on
Wyong Road, with a left turn lane into Mingara Drive
and a single right turn lane into Tumbi Creek Road;
single right turn lanes into both Mingara Drive and
Tumbi Creek Road; double left turn lanes (eastbound)
out of Tumbi Creek Road; and removal of the existing
pedestrian mid-block traffic lights west of Mingara
Drive. Key benefits of the upgrades include improved
traffic flow on Wyong Road, improved safety for all road
users and an improved pedestrian and cycle network.
In-Progress
Wyong Station Refresh Package 1a
Wyong Hunter Rail The Station Refresh Program, within the Customer
Experience Improvement Programs seeks to fulfil the
needs of the customer by investing in improvements to
the customer facilities and amebience at stations. The
eight elements of scope are: Bird Proofing, Cleaning,
Painting/Painting Stripping, LED Lighting, Toilet
refurbishments, Landscaping, Station Precient repairs
and Kit of Parts upgrade (Seats, Bins and Bubblers)
Completed
Wyrallah Road Tucki Tucki North Coast Road Install shoulders from no shoulders and new CAMs Completed
Name Suburb Region/District Project Type Project Description Current
Status
Yamba Boating Access
Improvements Yamba North Coast Maritime Comprises 3 projects:
1) Yamba Road Boat Ramp Upgrade ($180,000 and
completion 23/12/16)
2) Hickey Island Boat Ramp ($150,000 and completion
23/12/16)
3) Witonga Drive Boat Ramp Upgrade ($70,000 and
completion 23/12/16)
Planning
Yamba Road
cycleway
Yamba North Coast Walking and Cycling Shared Path cycleway alongside Yamba Road Completed
Yass Junction
Interchange -
Commuter Parking
Yass South East &
Tablelands
Parking A new commuter car park on Lead Street provides 34 car
parking spaces for customers including four accessible
car parking spaces and a bicycle rack.
Completed
Yass Junction
Interchange - Transport
Access Program
Upgrade
Yass South East &
Tablelands
Interchange Improvements to Yass Junction Station included a new
accessible ramp to platform 2 and the ticket office, new
accessible parking spaces and improved safety features
including lighting.
Completed
Future Projects Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Parramatta T-Way to T-Way link Central City Bus Parramatta T-Way to T-Way Link 0-10yrs For
Investigation
Improved bus connections between
South West Sydney and Illawarra
Western City Bus Improved bus connections between South West
Sydney and Illawarra
0-10yrs For
Investigation
Improved bus services between north
of Parramatta and centres to the south
of Parramatta
Central City Bus Improved bus services between north of Parramatta
and centres to the south of Parramatta as a result of
linking Liverpool – Parramatta T-Way with
Northwest T-Way
0-10yrs For
Investigation
Infrastructure to support rapid bus
connections between WSA-Badgerys
Creek Aerotropolis and Penrith,
Liverpool, Blacktown and
Campbelltown-Macarthur(for priority
planning)
Western City Bus Infrastructure to support rapid bus connections
between WSA-Badgerys Creek Aerotropolis and
Penrith, Liverpool, Blacktown and Campbelltown-
Macarthur
0-10yrs For
Investigation
Northern Beaches B-Line North Bus Northern Beaches B-Line 0-10yrs Committed
Bus Priority Infrastructure program All Bus Bus Priority Infrastructure Program 0-10yrs Committed
New and replacement buses All Bus New and replacement buses 0-10yrs Committed
Trial of on-demand bus services on
selected local bus routes to provide
more convenience and choice for
customers while improving the
efficiency of the transport network
All Bus Trial of on-demand bus services on selected local
bus routes to provide more convenience and choice
for customers while improving the efficiency of
the transport network
0-10yrs Committed
Improved bus connections between
WSA-Badgerys Creek Aerotropolis
and Penrith, Liverpool and
Campbelltown-Macarthur(for priority
planning)
Western City Bus Improved bus connections between WSA-
Badgerys Creek Aerotropolis and Penrith,
Liverpool and Campbelltown-Macarthur
0-10yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Parramatta to Bankstown to
Hurstville / Kogarah rapid bus link
Central City Bus Parramatta to Bankstown to Hurstville / Kogarah
rapid bus link
0-10yrs For
Investigation
Green Square to La Perouse rapid bus
link
Eastern City Bus Green Square to La Perouse rapid bus link 0-10yrs For
Investigation
Eastern Suburbs to Inner West rapid
bus links: Randwick to Sydney
University to The Bays Precinct;
Maroubra Junction to Sydney Airport
to Marrickville
Eastern City Bus Eastern Suburbs to Inner West rapid bus links:
Randwick to Sydney University to The Bays
Precinct; Maroubra Junction to Sydney Airport to
Marrickville
0-10yrs For
Investigation
Improved bus services between
Northern Beaches and Chatswood
North Bus Improved bus services between Northern Beaches
and Chatswood
0-10yrs For
Investigation
Bus Head Start Program All Bus Bus Head Start Program 0-10yrs For
Investigation
Bus priority access program for
centres
All Bus Sydney-wide projects/programs: Bus priority
access program for centres
0-10yrs For
Investigation
Bus priority infrastructure to support
new services
All Bus Sydney-wide projects/programs: Bus priority
infrastructure to support new services
0-10yrs For
Investigation
Bus Headstart for Central Coast Central Coast Bus Growth Centre Buses for the Central Coast. New
routes implemented to support new homes as they
are built.
0-10yrs For investigation
Central Coast Rapid Bus package Central Coast Bus Implementation of programs to prioritise access for
buses over private vehicles in our Global Gateway
and Satellite Cities.
0-10yrs For investigation
Newcastle Rapid Bus Package Hunter Bus Implementation of programs to prioritise access for
buses over private vehicles in our Global Gateway
and Satellite Cities.
0-10yrs For investigation
Bus headstart for Newcastle Hunter Bus Growth Centre Buses. New routes implemented to
support new homes as they are built.
0-10yrs For investigation
Bus headstart for Wollongong Illawarra
Shoalhaven
Bus Growth Centre Buses. New routes implemented to
support new homes as they are built.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Wollongong Rapid Bus package Illawarra
Shoalhaven
Bus Implementation of programs to prioritise access for
buses over private vehicles in our Global Gateway
and Satellite Cities.
0-10yrs For investigation
Duplication of Port Botany freight rail line (in collaboration with the Commonwealth)
Eastern City Freight Duplication of Port Botany freight rail line 0-10yrs For
Investigation
Southern Sydney Freight Line
improvements (in collaboration with
the Commonwealth)
Western City Freight Supporting freight with upgrades to the Southern
Sydney Freight Line
0-10yrs For
Investigation
Northern Sydney Freight Corridor
Stage 2
North Freight Northern Sydney Freight Corridor Stage 2 0-10yrs For
Investigation
Additional capacity on Southern Sydney Freight Line (in collaboration with the Commonwealth)
Western City Freight Additional capacity on Southern Sydney Freight
Line to support growth in traffic
10-20yrs For
Investigation
Western Sydney Fuel Pipeline (for
priority planning in collaboration
with the Commonwealth)
Western City Freight Protect corridors for a future Western Sydney Fuel
Pipeline
0-10yrs For
Investigation
Port Botany Precinct Planning Eastern City Freight Port Botany Precinct Planning 0-10yrs For
Investigation
Freight Separation All Freight Investigation to separate freight from other traffic
on strategic road and rail corridors
20+yrs For
Investigation
Moorebank Intermodal (a
Commonwealth initiative)
Central City Freight Moorebank Intermodal Terminal 0-10yrs Committed
Maldon-Dombarton freight rail link Western City Freight Maldon-Dombarton freight rail link 10-20yrs For
Investigation
Last mile freight policy All Freight Development and implementation of Last Mile
Freight Policy in collaboration with industry to
encourage more freight movements in centres to
take place outside of normal business hours
0-10yrs For
Investigation
Western Sydney Freight Line Western City Freight Western Sydney Freight Line 10-20yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Moss Vale to Unanderra and
Coniston Junction rail improvements
in collaboration with ARTC
Illawarra
Shoalhaven, South
East and
Tablelands
Freight Upgrade to the Moss Vale to Unanderra Line in the
Southern Highlands to address rail freight pinch
points
0-10yrs For investigation
Port Efficiency, Access and
Integration Package*
North Coast,
Hunter, Illawarra
Shoalhaven, South
East and
Tablelands
Freight Road and rail projects to improve port access,
efficiency, and integration
0-10yrs For investigation
Inland Rail (Federally funded) Riverina Murray,
Central West and
Orana, New
England North
West
Freight The Inland Rail will provide an enhanced freight
link between Queensland and Southern Australia,
including Adelaide and Perth (via Parkes), and
enable freight travelling from Brisbane to
Melbourne to bypass the busy Sydney network.
The planned route is about 1,700 kilometres
between Melbourne and Brisbane of which 1,047
kilometres is in NSW. It will require 475
kilometres of upgrades to existing tracks and 399
kilometres of new tracks in NSW.
0-10yrs For investigation
Fixing Country Rail program
continuation
State-wide Freight Projects funded under Fixing Country Rail could
include sidings, passing loops, the reopening of
non-operational sections and network
enhancements that allow the use of faster, longer
and heavier trains.
0-10yrs For investigation
Heavy vehicle rest areas* State-wide Freight Program to continue building heavy vehicle rest
areas across relevant areas of the road network
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Lower Hunter Freight Corridor Hunter Freight Lower Hunter Freight Corridor which will enable a
future dedicated freight rail line to be constructed
between Fassifern and Hexham; bypassing
Newcastle while improving regional and interstate
links.
10-20yrs For investigation
Main Northern Line - improvements
to address pinch points
Hunter, New
England North
West
Freight Upgrade to the Northern Line in the Upper Hunter
to address rail freight pinch points
10-20yrs For investigation
Main South Freight Rail Capacity Enhancements in collaboration with ARTC
Riverina Murray Freight Main South rail amplification/duplication between Junee and Victorian Border to allow for double stacking of containers on Inland Rail alignment track. Bridge upgrades to increase height (7.1m from track) upgrades
10-20yrs For investigation
New rail alignment of North Coast
Line between Newcastle and Stroud
Road - investigation corridor
Hunter, North
Coast
Freight Creating a more direct rail connection between the
Lower Hunter Freight corridor at Hexham to
Stroud Road.
20+yrs For investigation
Newell Highway Heavy Vehicle
Pavement Upgrades (Planning)
Central West and
Orana
Freight Newell Highway corridor improvements 0-10yrs Committed
Road Freight Safety and Productivity All Freight Road Freight Safety and Productivity 0-10yrs Committed
Fixing Country Rail Pilot Program All Freight Funding rail infrastructure enhancement projects
that eliminate connectivity constraints on the NSW
regional rail network.
0-10yrs Committed
Lower Hunter Freight Corridor
Protection
Hunter Freight Lower Hunter Freight Corridor which will enable a
future dedicated freight rail line to be constructed
between Fassifern and Hexham; bypassing
Newcastle while improving regional and interstate
links.
0-10yrs Committed
Convenient interchanges All Interchange More convenient interchanges to encourage public
transport use. This includes making interchanges
more attractive and providing more services, such
as shops
0-10yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Improve access to train stations and
ferry wharves
All Interchange Improve access to train stations and ferry wharves 0-10yrs Committed
Transport Access Program (TAP) All Interchange Accessibility upgrades to stations, stops and
wharves
0-10yrs Committed
Metropolitan Interchanges Program All Interchange Sydney-wide projects/programs: Metropolitan
Interchange Program
0-10yrs For
Investigation
Regional Interchange program
(ongoing)
State-wide Interchange Upgrade major interchanges to encourage PT use
by providing accessible, easy to use, safe and
secure interchanges between
coach/cars/parking/taxis & ride share/local
buses/rail.
0-10yrs For investigation
Transport Access Program All Interchange Providing a better experience for public transport
customers by delivering accessible, secure and
integrated transport infrastructure.
0-10yrs Committed
Light rail to Bays Precinct Eastern City Light Rail -extension of Inner West Light Rail to Bays
Precinct - Inner West Light Rail: loop via The
Bays Precinct
10-20yrs For
Investigation
Light rail extension to Maroubra
Junction
Eastern City Light Rail Light rail extension to Maroubra Junction 10-20yrs For
Investigation
Parramatta Light Rail Stage 2(subject
to Final Business Case)
Central City Light Rail Parramatta Light Rail Stage 2 0-10yrs Committed
Parramatta Light Rail Stage 1 Central City Light Rail Parramatta Light Rail Stage 1 (Westmead to
Carlingford)
0-10yrs Committed
CBD & South East Light Rail Eastern City Light Rail CBD and South East Light Rail 0-10yrs Committed
Parramatta Light Rail extensions Central City Light Rail Possible future extensions of Parramatta Light Rail 10-20yrs For
Investigation
Newcastle Light Rail network
extension
Hunter Light Rail Extension of the Newcastle Light Rail network 0-10yrs For investigation
Extension of light rail from Gold
Coast Airport to Tweed Heads
North Coast Light Rail Extension of the current Gold Coast Light rail
project to Tweed Heads. This would connect
northern NSW to the Gold Coast Airport.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Investigate extension of light rail
from Canberra to Queanbeyan
South East and
Tablelands
Light Rail Extension of the Canberra Light Rail network to
Queanbeyan
0-10yrs For investigation
Newcastle Light Rail All Light Rail Delivering a new light rail for Newcastle City
centre
0-10yrs Committed
Implement Transport for NSW
related actions arising from the Cruise
Development Plan
Eastern City Maritime The Cruise Development Plan will manage the
cruise industry development in the short, medium
and long-term. Transport for NSW will investigate
options to facilitate better connections to cruise
terminals.
0-10yrs For
Investigation
Newcastle Cruise Terminal Hunter Maritime To provide home porting facilities and position
Newcastle as an international cruise destination. A
new cruise terminal building of approximately
3,000m2. A dedicated car park and improved
accessibility.
0-10yrs Committed
Newcastle Ferry Network extension Hunter Maritime To extend ferry services between Stockton and
Queens Wharf to Wickham. This will facilitate
interchange with heavy rail services.
10-20yrs For investigation
Maritime Safety Program State-wide Maritime Delivery of the NSW Regional Boating Plans 0-10yrs Committed
Coffs Harbour/Yamba cruise
terminal/ infrastructure development
North Coast Maritime To provide home porting facilities and associated
transport access connections to position Coffs
Harbour / Yamba as an international cruise
destination.
10-20yrs For investigation
Eden cruise terminal development South East and
Tablelands
Maritime Eden Wharf Extension project to cater for cruise
ships docking at Eden
0-10yrs Committed
Mobility as a Service (MaaS)
implementation
All Planning and
Policy
Implementation of Mobility as a Service (Maas)
model in collaboration with industry, whereby
private operators can sell integrated end-to-end
journeys to customers that include multiple
transport modes
0-10yrs For
Investigation
Trial of artificial intelligence
applications
All Planning and
Policy
Trial of artificial intelligence applications to
improve network management and/or customer
service
0-10yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Greater Sydney Parking Guideline All Planning and
Policy
Development and implementation of a Greater
Sydney Parking Guideline in collaboration with
local government. The key principle will be
ensuring parking availability takes into account the
level of access by public transport.
0-10yrs For
Investigation
Implementation of the movement and
place framework
All Planning and
Policy
Implementation of Movement and Place
Framework for planning, designing and operating
roads in collaboration with local government. The
key principle will be to balance the efficient
movement of people and goods with supporting the
liveability of places on our road network
0-10yrs For
Investigation
Road space allocation policy All Planning and
Policy
Development and implementation of Road Space
Allocation Policy. The key principle will be to
prioritise the efficient throughput of people and
goods on movement corridors, requiring more
priority for higher productivity vehicles such as
buses and shared vehicles.
0-10yrs For
Investigation
Expansion of Travel Choices Program. All Planning and
Policy
Expansion of Travel Choices to other congested corridors and centres. This program encourages customers to change when or how they travel, consistent with their journey objectives, in a way that enables us to better use the current transport capacity
0-10yrs Committed
State Infrastructure Multi Modal Corridor Program
All Planning and
Policy Delivering cycling routes within state owned assets
0-10yrs For
Investigation
Precinct Improvement Program All Planning and
Policy Provide bicycle parking at interchanges and partner with developers to provide cycling end of trip facilities within precincts
0-10yrs For
Investigation
Consideration of initiatives to further
incentivise more customers to travel
in off-peak periods
All Planning and
Policy
Consideration of initiatives to further incentivise
more customers to travel in off-peak periods
0-10yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Protection of corridors for future train
and road links
Western City Planning and
Policy
Corridor protections for future motorway and train
links
0-10yrs For
Investigation
Centres-Placemaking Enhancement
Package
All Planning and
Policy
Sydney-wide projects/programs: Centres -
Placemaking Enhancement Package
0-10yrs For
Investigation
Pinch Point Program All Planning and
Policy
Sydney wide projects/programs: Pinch Point Program 0-10yrs Committed
Central Coast Precinct Plan Central Coast Planning and
Policy
Plan and deliver improved access to/from/within
key precincts within the Central Coast by all
modes
0-10yrs For investigation
Greater Newcastle Precinct Plan Hunter Planning and
Policy
Plan and deliver improved access to/from/within
key precincts within Greater Newcastle by all
modes
0-10yrs For investigation
Wollongong Precinct Plan Illawarra
Shoalhaven
Planning and
Policy
Plan and deliver improved access to/from/within
key precincts within Wollongong by all modes
0-10yrs For investigation
Regional Airports Program* State-wide Planning and
Policy
Support Regional Airports through landside
improvements
0-10yrs For investigation
Regional centre in town access
improvement program*
State-wide Planning and
Policy
Program to improve in town access and amenity in
regional cities and centres. For example, certain
centres only have one state highway access which
can cause serious impediments to access when
disruption occurs
0-10yrs For investigation
Regional Parking Guidelines* State-wide Planning and
Policy
Deliver and implement a regional parking
guidelines across Regional NSW.
0-10yrs For investigation
WSA-Badgerys Creek Aerotropolis-
Parramatta train link (for priority
planning in collaboration with the
Commonwealth)
Western City Rail The WSA-Parramatta train link will reduce journey
times between these centres and mean each of the
three cities are connected by turn-up-and-go train
services. The extension of the north-south train
link in the Western Parkland City will support
population growth to the south of Western Sydney
Airport–Badgerys Creek Aerotropolis
0-10yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Suburban passenger train services
extended south of Macarthur
Western City Rail Suburban passenger train services extended south
of Macarthur to support urban growth
0-10yrs For
Investigation
North-south train link in Western City
(St Marys– WSA-Badgerys Creek
Aerotropolis) - for priority planning
in collaboration with the
Commonwealth
Western City Rail North-south train link in Western Parkland City (St
Marys to WSA-Badgerys Creek Aerotropolis)
0-10yrs For
Investigation
Sydney Metro West (subject to Final
Business Case)
Central City Rail Sydney Metro West 0-10yrs Committed
Sydney Metro Northwest Central City Rail Sydney Metro Northwest 0-10yrs Committed
Passenger train improvements south
of Macarthur
Western City Rail Suburban passenger train services extended south
of Macarthur to support urban growth
0-10yrs For
Investigation
Sydney Metro City & Southwest Central City Rail Sydney Metro City and Southwest 0-10yrs Committed
Sydney Growth Trains (part of More
Trains, More Services program)
All Rail Investment in the ‘More Trains, More Services’
program includes for 24 brand new air-conditioned
suburban trains and extra services across the train
network.
0-10yrs Committed
New Intercity Trains All Rail New Intercity Trains 0-10yrs Committed
Ferry Fleet Replacement Program All Rail Ferry Fleet Replacement Program 0-10yrs Committed
Corridor protection for higher speed
connections to regional areas
All Rail Corridor protection for Higher Speed connections
to regional areas north and south of Greater
Sydney
10-20yrs For
Investigation
Train improvements on T1, T2, T4
and T5 lines, including rollout of
Advanced Train Control System
All Rail Capacity and reliability improvements to T1
Western, Northern and North Shore Lines, T2
Airport, Inner West and South Lines, T4 Eastern
Suburbs and Illawara Line, and T5 Cumberland
Line, including Advanced Train Control System
deployment
0-10yrs For
Investigation
Upgrade to Blue Mountains Line Western City Rail Upgrade of Blue Mountains Line 0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
North-south train link in Western
Parkland City (WSA-Badgerys Creek
Aerotropolis – Campbelltown-
Macarthur) - for priority planning in
collaboration with the
Commonwealth
Western City Rail North-south train link in Western Parkland City
(WSA-Badgerys Creek Aerotropolis to
Campbelltown-Macarthur)
0-10yrs For
Investigation
Leppington to WSA-Badgerys Creek
Aerotropolis train link - for priority
planning in collaboration with the
Commonwealth
Western City Rail Leppington to WSA-Badgerys Creek Aerotropolis
train link
0-10yrs For
Investigation
North-south train link in Western City
(St Marys-Cudgegong Road) - for
priority planning in collaboration
with the Commonwealth
Western City Rail North-south train link in Western Parkland City (St
Marys to Cudgegong Road)
0-10yrs For
Investigation
Sydney Metro City and Southwest
extension to Liverpool
Western City Rail Sydney Metro City & Southwest extension to
Liverpool
20+yrs For
Investigation
Mass transit/ train link to South East South Rail Mass transit/ train link to South East 10-20yrs For
Investigation
Upgrades to Main West Line Central West and
Orana
Rail Upgraded rail infrastructure on the major railway
between Parkes and the Blue Mountains within the
Central West and Orana region for freight and
passengers.
0-10yrs For investigation
Regional rail maintenance facilities Central West and
Orana
Rail A new rail maintenance facility to support the
replacement of the entire regional train fleet
0-10yrs Committed
Sydney-Central Coast-Newcastle rail
Improvement
Hunter Rail A program of operational, fleet and targeted fixed
infrastructure improvements (for example, new
deviations to eliminate curvatures and flatten
grades). This would include a new rail crossing of
the Hawkesbury River
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Sydney-Wollongong Rail
Improvement
Illawarra
Shoalhaven
Rail A program of operational, fleet and targeted fixed
infrastructure improvements (for example, new
deviations to eliminate curvatures and flatten
grades). This would include a new rail crossing
through the Illawarra Escarpment
0-10yrs For investigation
New Intercity Fleet Hunter, Central
Coast, Illawarra
Shoalhaven,
Central West and
Orana, South East
and Tablelands
Rail A new fleet of long distance, intercity trains from
Sydney to the Central Coast, Newcastle, the Blue
Mountains and the South Coast.
0-10yrs Committed
Sydney-Canberra Rail Improvement South East and
Tablelands
Rail A program of operational, fleet and targeted fixed
infrastructure improvements (for example, new
deviations to eliminate curvatures and flatten
grades).
0-10yrs For investigation
Rail Network Optimisation Program* State-wide Rail Program to decommission smaller stations in the
regional train network and provide accessible Point
to Point connections to major interchanges (hub
and spoke delivery).
0-10yrs For investigation
Electrification of intercity to Bathurst Central West and
Orana
Rail Extension of the electrified Intercity Rail network
to Bathurst from Lithgow
10-20yrs For investigation
Electrification of intercity to
Bomaderry/Nowra
Illawarra
Shoalhaven
Rail Extension of the electrified Intercity Rail network
to Bomaderry from Kiama
10-20yrs For investigation
Electrification of intercity to
Goulburn
South East and
Tablelands
Rail Extension of the electrified Intercity Rail network
to Goulburn from Macarthur
10-20yrs For investigation
Corridor Preservation for Higher
Speed Connections
State-wide Rail Confirm and begin the preservation of a corridor,
based on the corridor set out in the Australian
Government’s High Speed Rail Study Phase 2, for
a high speed rail link between Melbourne, Sydney
and Brisbane.
10-20yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Diesel Fleet, Xplorer, Endeavour
Replacement Program
State-wide Rail A new regional NSW fleet will replace the ageing
XPT, XPLORER and Endeavour trains for
passengers who travel between Sydney, Canberra,
Melbourne, Brisbane and major regional centres. A
new maintenance facility for these trains will also
be built in regional NSW at Dubbo.
0-10yrs Committed
Electrification of the Hunter Line to
Telarah
Hunter Rail Extension of the electrified Intercity Rail network
to Telarah from Broadmeadow
20+yrs For investigation
Higher Speed Connections (east
coast)
State-wide Rail Deliver a high speed transport connection along
the East Coast of NSW (traversing Greater
Sydney)
20+yrs For investigation
Foreshore road upgrade All Road Capacity upgrades to Foreshore Road at Port
Botany and investigation of truck only lanes in the
Port Precinct
0-10yrs For
Investigation
Bells Line of Road improvements Western City Road Bells Line of Road improvements 0-10yrs For
Investigation
WSA-Badgerys Creek Aerotropolis
CAV zone
Western City Road WSA-Badgerys Creek Aerotropolis CAV zone 0-10yrs For
Investigation
WSA-Badgerys Creek Aerotropolis
inner and outer ring roads
Western City Road WSA Outer and Inner Ring Roads 20+yrs For
Investigation
Improved road network management
system
All Road Implementation of improved road network
management system to enable live monitoring of
network performance across all modes that use our
roads
0-10yrs For
Investigation
Western Sydney Infrastructure Plan
(M12 motorway)
Western City Road Western Sydney Infrastructure Plan (M12
motorway)
0-10yrs For
Investigation
Western Harbour Tunnel and Beaches
Link (subject to Final Business Case)
Eastern City Road Western Harbour Tunnel and Beaches Link 0-10yrs Committed
Northern Beaches Hospital road
upgrade
North Road Northern Beaches Hospital road upgrade 0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Sydney Airport road upgrades Eastern City Road Sydney Airport road upgrades 0-10yrs Committed
WestConnex Eastern City Road WestConnex 0-10yrs Committed
NorthConnex Central City Road NorthConnex 0-10yrs Committed
Western Sydney Infrastructure Plan
(in collaboration with the
Commonwealth)
Western City Road Western Sydney Infrastructure Plan 0-10yrs Committed
Western Sydney Growth Roads
Program
Western City Road Western Sydney Growth Roads Program 0-10yrs Committed
Parramatta outer ring road Central City Road The Parramatta Outer Ring road will provide a
bypass of Parramatta for customers travelling from
the west to centres north of Greater Parramatta.
10-20yrs For
Investigation
F6 President Ave, Kogarah to Loftus
(for immediate detailed planning)
South Road This section of the F6 will link President Ave,
Kogarah to Loftus
0-10yrs For
Investigation
Heathcote Road improvements South Road A6 improvements – M5 to M1 0-10yrs For
Investigation
Appin and Picton Road
improvements
Western City Road Appin and Picton Road improvements 0-10yrs For
Investigation
M5 motorway extension from
Liverpool to Outer Sydney Orbital
Western City Road M5 motorway extension from Liverpool to Outer
Sydney Orbital
20+yrs For
Investigation
Outer Sydney Orbital (motorway and
freight rail) from Great Western
Highway and Western Line to WSA-
Badgerys Creek Aerotropolis
Western City Road The Outer Sydney Orbital motorway will
ultimately provide an outer bypass of Greater
Sydney, connecting the Central Coast, Western
Parkland City and Illawarra. The first stage will
connect the Great Western Highway near St Marys
with WSA-Badgerys Creek Aerotropolis.
10-20yrs For
Investigation
Bells Line of Road-Castlereagh
Connection
Western City Road Bells Line of Road-Castlereagh Connection 20+yrs For
Investigation
F6 - WestConnex to President Ave,
Kogarah (subject to Final Business
Case)
South Road The proposed F6 will link WestConnex with the
A1 at President Ave, Kogarah
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Central City strategic road corridor (NorthConnex to Southern Sydney)
Central City Road Central City strategic road corridor 20+yrs For
Investigation
Investment in smart roads All Road Sydney-wide projects/programs: Investment in
smart roads
0-10yrs For
Investigation
Address long term capacity constraints to Port Botany and South East
Eastern City Road Address long term capacity constraints to Port Botany and South East
20+yrs For
Investigation
Outer Sydney Orbital (motorway and
freight rail) from Great Western
Highway and Western Line to Central
Coast
Western City Road Outer Sydney Orbital (motorway and freight rail)
from Great Western Highway and Western Line to
Central Coast
20+yrs For
Investigation
Outer Sydney Orbital (motorway and
freight rail) from WSA-Badgerys
Creek Aerotropolis to M31 Hume
Motorway and South Line
Western City Road Outer Sydney Orbital (motorway and freight rail)
from WSA-Badgerys Creek Aerotropolis to M31
Hume Motorway and South Line
20+yrs For
Investigation
Outer Sydney Orbital (motorway)
from M31 Hume Motorway to
Illawarra
Western City Road Outer Sydney Orbital (motorway) from M31 Hume
Motorway to Illawarra
20+yrs For
Investigation
Parramatta inner ring road
(improvements to existing surface
roads)
Central City Road Parramatta inner ring road 0-10yrs For
Investigation
M4 Smart Motorways All Road Rollout of Smart Motorways on the M4 0-10yrs Committed
M1 Motorway improvements
(Hawkesbury River - Mt White)
Central Coast Road Upgrading of the M1 Motorway between
Hawkesbury River and Mount White to improve
safety and facilitate the increase in speed
restriction from 90km/hr to 110km/hr.
0-10yrs For investigation
M1 - Newcastle SMART Motorway Central Coast,
Hunter
Road The M1 Newcastle Smart Motorway project will
introduce intelligent technology, known as a
motorway management system. This includes
variable speed limits, dynamic message signs and -
where appropriate - ramp meters to meter traffic
flows
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Golden Highway improvements Central West and
Orana
Road Upgrade the Golden Highway through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
0-10yrs For investigation
Mt Victoria to Orange road corridor
improvements to achieve travel time
savings and road safety outcomes
Central West and
Orana
Road Upgrade of the Great Western and Mitchell
Highways between the western end of the Blue
Mountains at Mount Victoria, to better connect and
support the regional cities and centres of Lithgow,
Bathurst and Orange. Upgrade will include safety
measures identified from Safe System design
principles for corridor planning (including ATLM,
wide centreline, median barriers and 2+1 treatment
where appropriate).
0-10yrs For investigation
Henry Parkes Way improvements Central West and
Orana
Road Upgrade Henry Parkes Way through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
0-10yrs For investigation
Integration of New England and
Golden Highways at Maitland.
Hunter Road Duplication of New England Highway at Belford
between the Hunter Expressway and Golden
Highway.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
M1 Pacific Motorway extension to
Raymond Terrace
Hunter Road 15 kilometres of dual carriageway motorway with
two lanes in each direction, bypassing Hexham and
Heatherbrae
0-10yrs For investigation
The Lakes Way Corridor
Improvements
Hunter Road Upgrade the Lakes Way through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
0-10yrs For investigation
Princes Highway Nowra Bridge
replacement
Illawarra
Shoalhaven
Road A new bridge that will improve conditions on the
Princes Highway over the Shoalhaven River at
Nowra. As well as a new bridge, the project will
look at improving congestion at the intersections at
Illaroo Road, Bolong Road and Bridge Road /
Pleasant Way.
0-10yrs For investigation
Picton Rd/Appin Rd Improvements Illawarra
Shoalhaven
Road Capacity improvements to Appin and Picton Road
to support additional freight, public transport and
private vehicle journeys. In collaboration with
local council, upgrades to also focus on supporting
liveability of centres that roads pass through, as
well as safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate).
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Nelson Bay road improvements -
Fern Bay to Williamtown
Hunter Road Nelson Bay Road is the main arterial link connecting Newcastle to Williamtown and the Tomaree Peninsula. Improvements will include safety measures identified from Safe System design principles for corridor planning (including ATLM, wide centreline, median barriers and 2+1 treatment where appropriate).
0-10yrs Committed
New England Highway
Improvements
New England
North West
Road Upgrade the New England Highway between
Werris Creek and Armidale through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
0-10yrs For investigation
New England Highway
Improvements (Armidale to border)
New England
North West
Road Upgrading of the New England Highway between
Armidale and The Queensland border, including
safety measures identified from Safe System
design principles for corridor planning (including
ATLM, wide centreline, median barriers and 2+1
treatment where appropriate).
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Oxley Highway Improvements New England
North West, North
Coast
Road Upgrade the Oxley Highway between Tamworth
and Port Macquarie. Improvements will focus on
intersections and bridge approach barriers, flood
immunity, improve road alignment and overtaking
opportunities, as well as safety measures identified
from Safe System design principles for corridor
planning (including ATLM, wide centreline,
median barriers and 2+1 treatment where
appropriate). Will also investigate improvements
for cyclist connectivity and better pedestrian
facilities. Also includes ongoing maintenance to
slope stability on the mountain between Walcha
and Wauchope.
0-10yrs For investigation
Silver City Highway sealing missing
links
Far West Road Sealing of the remaining sections of the Silver City
Highway
0-10yrs For investigation
Cobb Highway sealing missing links Far West, Riverina
Murray
Road Sealing of the remaining sections of the Cobb
Highway
0-10yrs For investigation
Kidman Way sealing missing links Far West, Riverina
Murray
Road Sealing of the remaining sections of The Kidman
Way
0-10yrs For investigation
Waterfall Way corridor
improvements
North Coast Road Upgrading Waterfall Way between the Pacific
Highway and the New England Highway.
Widening sealed shoulders and lane widths on a
priority basis. Implementing identified clear zone
and safety measures identified from Safe System
design principles for corridor planning (including
ATLM, wide centreline, median barriers and 2+1
treatment where appropriate). Planning for minor
realignment between the Pacific Highway and
Bellingen including accommodating for active
transport users to promote safe connections.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Bruxner Highway Improvements
(Lismore-Ballina)
North Coast Road Improvements to the Bruxner Highway between
Lismore and Ballina, including safety measures
identified from Safe System design principles for
corridor planning (including ATLM, wide
centreline, median barriers and 2+1 treatment
where appropriate).
0-10yrs For investigation
Gwydir Highway Improvements North Coast, New
England North
West
Road Upgrade the Gwydir Highway through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
0-10yrs For investigation
Murray River Bridges Program Riverina Murray Road The upgrading and replacement of key bridges
across the Murray River to connect communities
and facilitate the movement of freight.
0-10yrs For investigation
Sturt Highway improvements Riverina Murray Road Upgrade the Sturt Highway through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works.
0-10yrs For investigation
Kidman Way improvements Riverina Murray Road Corridor improvements to deliver greater journey
time savings and road safety outcomes.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Newell Highway Improvements (in
addition to those committed)
Riverina Murray,
Central West and
Orana, New
England North
West
Road Upgrade the remaining sections of the Newell
Highway Corridor. This would include a series of
measures from as large as town bypasses, lane and
seal widening with clear zone works, safety
measures identified from Safe System design
principles for corridor planning (including ATLM,
wide centreline, median barriers and 2+1 treatment
where appropriate), intersection improvements at
highly traffic locations, flood immunity works and
asset maintenance works.
0-10yrs For investigation
M31 Hume SMART motorway South East and
Tablelands
Road The M31 Hume Smart Motorway project will
introduce intelligent technology, known as a
motorway management system. This includes
variable speed limits, dynamic message signs and -
where appropriate - ramp meters to meter traffic
flows
0-10yrs For investigation
Kings Highway improvements South East and
Tablelands
Road Upgrade the Kings Highway through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Hume Highway Improvements South East and
Tablelands
Road Upgrade the Hume Highway Corridor to improve
safety and efficiency to cater for growing
passenger demand, including implementation of
safety measures identified from Safe System
design principles for corridor planning (including
ATLM, wide centreline, median barriers and 2+1
treatment where appropriate).
0-10yrs For investigation
Snowy Mountains Highway
improvements
South East and
Tablelands
Road Upgrade the Snowy Mountains Highway from
Cooma to Bega through a series of measures such
as lane and seal widening with clear zone works,
safety measures identified from Safe System
design principles for corridor planning (including
ATLM, wide centreline, median barriers and 2+1
treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works.
0-10yrs For investigation
Monaro Highway improvements South East and
Tablelands
Road Upgrade the Monaro Highway from Canberra to
Cooma through a series of measures such as lane
and seal widening with clear zone works, safety
measures identified from Safe System design
principles for corridor planning (including ATLM,
wide centreline, median barriers and 2+1 treatment
where appropriate), intersection improvements at
highly traffic locations, flood immunity works and
asset maintenance works.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Lachlan Valley Way improvements South East and
Tablelands,
Central West and
Orana
Road Upgrade the Lachlan Valley Way through a series
of measures such as lane and seal widening with
clear zone works, safety measures identified from
Safe System design principles for corridor
planning (including ATLM, wide centreline,
median barriers and 2+1 treatment where
appropriate), intersection improvements at highly
traffic locations, flood immunity works and asset
maintenance works.
0-10yrs For investigation
Fixing Country Roads program
continuation
State-wide Road The program helps to fund projects that better
connect local and regional roads to state highways
and key freight hubs; such as silos, saleyards, rail
heads, supermarket distribution centres, industrial
parks and depots.
0-10yrs For investigation
Bridge upgrades - Bridges for the
Bush continuation
State-wide Road Upgrades of various bridges in regional NSW,
including the Bridges for the Bush program; and
local road bridges
0-10yrs For investigation
Programs to ensure CAV/AV
readiness
State-wide Road Infrastructure to support CAV/AV on NSW roads. 0-10yrs For investigation
Self drive car share accessibility
package
State-wide Road Provide car sharing areas around the regions
(similar to GoGet stations). Roll out to include
mobile app for customers to book vehicles
0-10yrs For investigation
Resilience Package* State-wide Road Improving immunity for Flood prone regional
roads.
0-10yrs For investigation
Rural roads network enhancements
program, including Safe Systems
Infrastructure Program*
State-wide Road Program of works across the state to deliver
network enhancements and improvements e.g.
overtaking lanes, shoulder widening, clear zones,
curve realignment, intersection improvements, etc.
Program of road safety initiatives to reduce road
fatalities and serious injuries across NSW.
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Sealing Country Roads Program continuation
State-wide Road Program of works to progressively seal unsealed roads in regional NSW
0-10yrs For investigation
Slopes and culverts condition
program*
State-wide Road Program of works to progressively
address/improve the conditions of slopes and
culverts in the network
0-10yrs For investigation
Roadside facilities for AV and CAVs State-wide Road Develop rest areas and other roadside facilities that
would be required when Automated Vehicles, and
Connected and Autonomous Vehicles come online
0-10yrs For investigation
Service Centres along state
highways*
State-wide Road Construction of on/off ramps, land leasing etc. 0-10yrs For investigation
Last Mile Productivity Program* State-wide Road Package of works that will focus on improving first
and last mile connectivity and efficiency for freight
network
0-10yrs For investigation
Town Bypasses identification of
future need
State-wide Road Construction of town bypasses to divert heavy
vehicle freight movements and other through
traffic away from town centres to improve traffic,
safety, and urban amenity. Includes Coffs Harbour,
towns along the Princes Highway etc. List of
prioritised town bypasses will be developed in
consultation with local communities (LTTMP)
0-10yrs For investigation
Barrier Highway improvements
(Dubbo-Broken Hill)
Central West and
Orana, Far West
Road Upgrade the Barrier Highway through a series of
measures such as lane and seal widening with clear
zone works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
10-20yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Castlereagh Highway Improvements
(Mudgee-Lithgow)
Central West and
Orana
Road Upgrade the Castlereagh Highway through a series
of measures such as lane and seal widening with
clear zone works, safety measures identified from
Safe System design principles for corridor
planning (including ATLM, wide centreline,
median barriers and 2+1 treatment where
appropriate), intersection improvements at highly
traffic locations, flood immunity works and asset
maintenance works
10-20yrs For investigation
Nelson Bay Road improvements -
Williamtown to Bobs Farm
Hunter Road Upgrade Nelson Bay Road between Williamtown and the Tomaree Peninsula, including safety measures identified from Safe System design principles for corridor planning (including ATLM, wide centreline, median barriers and 2+1 treatment where appropriate).
10-20yrs For investigation
Mount Ousley Bypass Illawarra
Shoalhaven
Road Develop a long term high capacity road solution
for the crossing of the Illawarra Escarpment
10-20yrs For investigation
Kamilaroi Highway Improvements New England
North West, Far
West
Road Upgrade the Kamilaroi Highway between Narrabri
and Werris Creek through a series of measures
such as lane and seal widening with clear zone
works, safety measures identified from Safe
System design principles for corridor planning
(including ATLM, wide centreline, median barriers
and 2+1 treatment where appropriate), intersection
improvements at highly traffic locations, flood
immunity works and asset maintenance works
10-20yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Summerland Way Improvements
(Grafton-Lismore)
North Coast Road Upgrading of the Summerland Way which works
operates as a key freight link for the timber, cattle
farming and meat manufacturing industries.
Measures would be investigated such as lane and
seal widening with clear zone works, safety
measures identified from Safe System design
principles for corridor planning (including ATLM,
wide centreline, median barriers and 2+1 treatment
where appropriate), intersection improvements at
highly traffic locations, flood immunity works and
asset maintenance works
10-20yrs For investigation
Outer Metro Roads Program Illawarra
Shoalhaven,
Central Coast,
Hunter
Road Program to improve the local road network in
Newcastle, Wollongong and Central Coast
10-20yrs For investigation
Tomago Road Improvements -
Pacific Highway to Williamtown
Hunter Road Upgrade Tomago Road between the pacific
Highway and Newcastle Airport at Williamtown.
10-20yrs For investigation
Gwydir Highway Improvements
(Inland)
New England
North West
Road Upgrade the Gwydir Highway between Moree and
Glen Innes through a series of measures such as
lane and seal widening with clear zone works,
improving safety measures (including at level
crossings), additional overtaking lanes and
intersection improvements at highly traffic
locations, flood immunity works and asset
maintenance works
10-20yrs For investigation
Duplication of New England
Highway Muswellbrook to Scone
Hunter Road Duplication of New England Highway between
Muswellbrook and Scone
20+yrs For investigation
Barton Highway duplication South East and
Tablelands
Road Duplication of the Barton Highway between
Canberra and the Hume Motorway
20+yrs For investigation
Woolgoolga to Ballina (State and
Federal Funded)
North Coast Road Pacific Highway upgrade works 0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Warrell Creek to Nambucca Heads
(State and Federal Funded)
North Coast Road Pacific Highway upgrade works 0-10yrs Committed
Oxley Highway to Kundabung (State
and Federal Funded)
New England
North West
Road Pacific Highway upgrade works 0-10yrs Committed
Foxground and Berry Bypass,
Toolijooa Road to South Berry -
Princes Highway
South East and
Tablelands
Road It will provide a four-lane highway (two lanes in
each direction) with median separation for 12.5
kilometres of the Princes Highway between
Toolijooa Road and just south of Andersons Lane.
0-10yrs Committed
Pacific Motorway Widening and
Reconstruction, Wyong Road to
Doyalson Link Road (State and
Federal Funded)
Central Coast Road The upgrade involves widening the motorway to
provide three lanes in each direction and rebuilding
the roadway to provide a smoother and more
durable surface.
0-10yrs Committed
Summerland Way, Additional
Clarence River Crossing (Grafton
Bridge)
North Coast Road Project involves building an additional 525 metre
bridge 70 metres downstream from the existing
road and rail bridge. The project also includes
upgrading parts of the road network in Grafton and
South Grafton to connect the new bridge to the
existing road network.
0-10yrs Committed
Kundabung to Kempsey (State and
Federal Funded)
North Coast Road Pacific Highway upgrade works 0-10yrs Committed
Forty Bends and Hartley Valley
Safety Improvements (State and
Federal Funded)
Central West and
Orana, Far West
Road Safety upgrades and road improvements on the
Great Western Highway between Hartley Valley
and Forty Bends
0-10yrs Committed
Golden Highway Safety and
Productivity Works (State and
Federal Funded)
Hunter Road Upgrades on the Golden Highway between the
Upper Hunter and Dubbo, to improve safety,
traffic efficiency, network reliability and freight
access
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Pacific Motorway Widening, Kariong
Interchange to Somersby Interchange
(State and Federal Funded)
Central Coast Road Roads and Maritime Services is upgrading the M1
Pacific Motorway between the Kariong and
Somersby interchanges to improve traffic flow and
safety. The upgrade involves widening the
motorway and upgrading three of the four ramps at
the Kariong interchange.
0-10yrs Committed
Cormorant Road, Industrial Drive to
Stockton Bridge (State and Federal
Funded)
Hunter Road Upgrade of Cormorant Road along the Newcastle
Port Precinct on Kooragang Island
0-10yrs Committed
Pacific Highway, Wyong Road
Intersection Upgrade
Central Coast Road The upgrade involves replacing the existing
roundabout with traffic lights to improve traffic
flow and safety.
0-10yrs Committed
Gocup Road Upgrade Riverina Murray Road Upgrade of Gocup road to deliver improvements
between Tumut and Gundagai
0-10yrs Committed
Pacific Highway, Ourimbah Street to
Glen Road
Central Coast Road he upgrade involves widening the highway to
provide two lanes in each direction to improve
traffic flow and safety.
0-10yrs Committed
Burrill Lake Bridge Replacement Illawarra
Shoalhaven
Road Replacing existing bridge 0-10yrs Committed
Oxley Highway Safety and
Realignment Works (Planning)
New England
North West
Road The NSW Government is funding the delivery of
vital road improvements along the Oxley Highway.
This important work stems from the Oxley
Highway Route Safety Review and the Oxley
Highway corridor strategy.
0-10yrs Committed
Bruxner Highway, Replacement
Bridge over Clarence River
North Coast Road The new Tabulam Bridge is being built as part of
the Bridges for the Bush program, a NSW
Government initiative to improve freight
productivity and reduce maintenance costs by
replacing or upgrading timber bridges.
0-10yrs Committed
Dignams Creek Realignment South East and
Tablelands
Road Upgrade of the Princes Highway at Dignams
Creek, around 20km south of Narooma.
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Mitchell Highway, Guanna Hill
Realignment
Central West and
Orana
Road Upgrade and realign 7.2 kilometres of the Mitchell
Highway near Molong. This work will improve
safety, travel times and provide a smoother road
surface for road users.
0-10yrs Committed
Wyong Road, Mingara Drive to
Tumbi Road Upgrade
Central Coast Road The upgrades involve replacing the existing
roundabouts with traffic lights to improve traffic
flow and safety, while catering for future traffic
growth.
0-10yrs Committed
Newell Highway, Trewilga
Realignment
Central West and
Orana
Road Upgrade and realign 6.5 kilometres of the Newell
Highway north of Parkes.
0-10yrs Committed
Sportsmans Creek Replacement
Bridge
North Coast Road Construction of new bridge over Sportsmans Creek
at Lawrence.
0-10yrs Committed
Hunter Pinch Points Hunter Road Pinch Point Programs aim to reduce traffic delays,
manage congestion and improve travel times
0-10yrs Committed
Newell Highway, Grong Grong
Realignment
Riverina Murray Road Moving the Newell Highway west of Grong Grong
to improve freight efficiency and road safety
0-10yrs Committed
Newell Highway, West Wyalong
Heavy Vehicle Bypass
Riverina Murray Road upgrading the West Wyalong heavy vehicle
alternative route to improve safety and meet the
demands of the increasing amount of freight being
carried on the Newell Highway.
0-10yrs Committed
Kings Highway, River Forest Road
Realignment
South East and
Tablelands
Road Realign the highway between River Forest Road
and the Mongarlowe River
0-10yrs Committed
Road Safety All Road Program to deliver road safety projects as per draft
Road Safety Plan across Regional NSW.
0-10yrs Committed
Albion Park Rail Bypass (Planning
and Preconstruction)
Illawarra
Shoalhaven
Road Future extension of the M1 Princes Motorway
between Yallah and Oak Flats to bypass Albion
Park Rail. The bypass would complete the 'missing
link' for a high standard road between Sydney and
Bomaderry.
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
New England Highway, Scone
Bypass (State and Federal Funded)
Hunter Road New England Highway bypass of Scone to
improve traffic flow, travel times and safety for
road users
0-10yrs Committed
Newell Highway, Parkes Bypass
(Planning)
Central West and
Orana
Road Planning for the potential Newell Highway
upgrade at Parkes as part of the $500 million
Newell Highway upgrade program.
0-10yrs Committed
Newell Highway, Mungle Back
Creek to Boggabilla Heavy Duty
Pavement (State and Federal Funded)
New England
North West
Road Upgrade of the Newell Highway between Mungle
Back Creek and Boggabilla. This will improve
safety for motorists and reduce future maintenance
requirements.
0-10yrs Committed
Manns Road, Central Coast Highway
to Narara Creek Road (Planning)
Central Coast Road future upgrade of Manns Road between Stockyard
Place, West Gosford and Narara Creek Road,
Narara to improve traffic flow and safety.
0-10yrs Committed
New England Highway, Bolivia Hill
Upgrade (State and Federal Funded)
New England
North West
Road Upgrade of the New England Highway at Bolivia
Hill
0-10yrs Committed
Batemans Bay Bridge (planning) South East and
Tablelands
Road New bridge over the Clyde river 0-10yrs Committed
Coffs Harbour Bypass North Coast Road Coffs Harbour Bypass (Planning) (State and
Federal Funded)
0-10yrs Committed
Kosciuszko Road Overtaking Lanes
and Safety Improvements
South East and
Tablelands
Road new overtaking lanes and improve safety on
Monaro Highway and Kosciuszko Road.
0-10yrs Committed
Newell Highway, New Dubbo Bridge
(Planning)
Central West and
Orana
Road Newell Highway corridor improvements 0-10yrs Committed
Warnervale Link Road, Albert
Warner Drive to Pacific Highway
(Planning)
Central Coast Road planning a future road between the roundabout at
the Pacific Highway and Britannia Drive at
Watanobbi and Sparks Road at Warnervale to
improve traffic flow and connectivity.
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Nowra Bridge over Shoalhaven River (Planning) (State and Federal Funded) subject to final business case and Federal funding
Illawarra
Shoalhaven
Road Planning is underway for a new bridge that will improve conditions on the Princes Highway over the Shoalhaven River at Nowra. As well as a new bridge, the project will look at improving congestion at the intersections at Illaroo Road, Bolong Road and Bridge Road / Pleasant Way.
0-10yrs Committed
New England Highway, Gowrie
Gates, Widen Rail Underpass
New England
North West
Road upgrade of the Singleton railway underpass. The
widened underpass would improve road and rail
freight access through the Hunter Valley.
0-10yrs Committed
Princes Motorway Improvements,
Bulli Tops to Picton Road (Planning)
(State and Federal Funded)
Illawarra
Shoalhaven
Road The project would provide additional lanes in both
directions and improve the curves. This would
increase the safety, capacity and efficiency of the
M1 Princes Motorway.
0-10yrs Committed
Newell Highway Overtaking Lanes New England
North West
Road Newell Highway corridor improvements 0-10yrs Committed
Program 2: Timber Truss Bridge
Replacements and Upgrades
All Road Replacement of six heritage timber truss
bridges (to HML standard) and upgrade of six
heritage timber truss bridges to provide ongoing
safe service levels.
0-10yrs Committed
Pacific Highway, Parsons Road to
Ourimbah Street (Planning)
Central Coast Road The proposed upgrade involves widening the
highway to provide two lanes in each direction to
improve traffic flow and safety for all road users.
0-10yrs Committed
Berry to Bomaderry Upgrade South East and
Tablelands
Road The upgrade will provide about 10.5 kilometres of
four-lane highway with median separation between
Mullers Lane, Berry and Cambewarra Road,
Bomaderry.
0-10yrs Committed
Oxley Highway, Gunnedah Bridge
over Rail
New England
North West
Road developing the design for a second road over rail
bridge in Gunnedah to improve local traffic
efficiency and road safety.
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Cobb Highway, New Bridge at
Echuca - Moama
Riverina Murray Road New cross border bridge at Echuca 0-10yrs Committed
Main Road 54 (Goulburn to Bathurst)
Initial Sealing
South East and
Tablelands
Road Sealing project 0-10yrs Committed
Barton Highway Improvements (State
and Federal Funded)
South East and
Tablelands
Road The upgrade will ease congestion, improve driver
safety and boost freight productivity.
0-10yrs Committed
Pacific Highway and Manns Road,
Narara Creek Road to Parsons Road
(Planning)
Central Coast Road planning for the proposed Pacific Highway and
Manns Road upgrade between Narara Creek Road,
Narara and Parsons Road, Lisarow to improve
traffic flow and road user safety.
0-10yrs Committed
Newell Highway, Improvements
through Coonabarabran (Planning)
Central West and
Orana
Road Newell Highway corridor improvements 0-10yrs Committed
Hume Highway Heavy Duty
Pavement (State and Federal Funded)
South East and
Tablelands
Road Heavy duty pavement 0-10yrs Committed
New England Highway, Belford to
Golden Highway Upgrade (Planning)
New England
North West
Road upgrade the New England Highway between
Belford and the Golden Highway to provide two
travel lanes in each direction and a flyover for
vehicles turning right from the Golden Highway
towards Maitland and Newcastle.
0-10yrs Committed
Pacific Highway, Wyong Town
Centre (Planning)
Central Coast Road Roads and Maritime is planning to upgrade the
Pacific Highway through the Wyong town centre
to provide two lanes in each direction between
Johnson Road at Tuggerah and Cutler Drive at
Wyong.
0-10yrs Committed
Newcastle Inner City Bypass, Rankin
Park to Jesmond
Hunter Road The Newcastle Inner City Bypass (Highway 23)
between the Pacific Highway at Bennetts Green
and the Pacific Highway at Sandgate provides an
orbital road linking Newcastle's radial road
network.
0-10yrs Committed
New England Highway,
Muswellbrook Bypass (Planning)
Hunter Road planning for a future bypass of Muswellbrook. 0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Empire Bay Drive, The Scenic Road and Cochrone Street Intersection Upgrade
Central Coast Road The proposal aims to reduce congestion, and improve traffic flow and travel times for the 25,000 motorists travelling along Empire Bay Drive between Kerta Road and Avoca Drive each day.
0-10yrs Committed
Princes Motorway, Interchange at
Base of Mount Ousley (Planning)
Illawarra
Shoalhaven
Road planning for an interchange on the M1 Princes
Motorway at the base of Mount Ousley.
0-10yrs Committed
Queanbeyan Bypass (Ellerton Drive
Extension) (State, Federal and Local
Government Funded)
South East and
Tablelands
Road The project will extend Ellerton Drive to connect
Queanbeyan East with Karabar at the Edwin Land
Parkway intersection with Old Cooma Road. The
project also involves an upgrade of the existing
Ellerton Drive.
0-10yrs Committed
Program 3: Bridges for the Bush All Road The Bridges for the Bush initiative will enhance
freight productivity in country NSW. It is an
investment in critical infrastructure to remove a
number of significant freight pinch points or
bottlenecks on the state road network and to
improve the safety and reliability of some old
bridge structures.
0-10yrs Committed
Monaro Highway Overtaking Lanes
and Safety Improvements
South East and
Tablelands
Road build new overtaking lanes and improve safety on
Monaro Highway and Kosciuszko Road
0-10yrs Committed
New England Highway, Singleton
Bypass (Planning)
Hunter Road a future New England Highway bypass of
Singleton.
0-10yrs Committed
Kings Highway, Replacement Clyde
River Bridge
South East and
Tablelands
Road replacement of bridge on Clyde river 0-10yrs Committed
Silver City and Cobb Highway Seal
Extension
Far West Road program of work to further seal and upgrade the
Cobb and Silver City Highways to improve freight
access and safety for motorists.
0-10yrs Committed
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Higher frequency public transport
services
All Transit Introduction of higher frequency public transport
services on selected corridors, including new metro
lines, key train lines and bus routes. Introduction of
higher frequency transport services across Greater
Sydney:
- Turn-up-and-go services (<5 minute frequencies)
on city-city and centre-centre corridors
- High frequency (<10 mins) or on-demand
services on CBD mass transit and local corridors
0-10yrs For
Investigation
Victoria Road public transport
improvements
Central City Transit Victoria Road public transport improvements 0-10yrs For
Investigation
Introduction of higher frequency public transport services on selected corridors
All Transit Introduction of higher frequency public transport
services on selected corridors, including new metro
lines, key train lines and bus routes
0-10yrs Committed
Parramatta to Kogarah train/ mass
transit link
Central City Transit Parramatta to Kogarah mass transit/ train link 10-20yrs For
Investigation
Parramatta to Epping mass transit/ train link
Central City Transit Parramatta to Epping mass transit/ train link 10-20yrs For
Investigation
Harbour CBD to Green Square mass
transit link: Botany Road
Eastern City Transit Harbour CBD to Green Square mass transit link:
Botany Road
0-10yrs For
Investigation
Extension of South East mass transit/
train link to Miranda
South Transit Extension of South East mass transit/ train link to
Miranda
20+yrs For
Investigation
Parramatta Road public transport
improvements
Eastern City Transit Parramatta Road public transport improvements 0-10yrs For
Investigation
Parramatta to Norwest mass transit/
train link
Central City Transit Parramatta-Norwest mass transit/ train link 20+yrs For
Investigation
Regional point to point booking
system
State-wide Transit Investment to support implementation of electronic
ticketing and online adaptive booking systems
0-10yrs For investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Roll out Demand Responsive services State-wide Transit Program to make flexible transport available in all
regions
0-10yrs For investigation
Cycling and pedestrian infrastructure Western City Walking and
Cycling
Cycling and pedestrian infrastructure 0-10yrs Committed
Innovative walking and cycling
initiatives
All Walking and
Cycling
Development and testing of new approaches to
encourage walking and cycling, especially for
school age children
0-10yrs For
Investigation
Priority Cycleway links in Western City Western City Walking and
Cycling Priority Cycleway links connecting Liverpool, Blacktown and Penrith, including the Nepean River Green Bridge
0-10yrs Committed
Priority Cycleway links in Central City Central City Walking and
Cycling Priority Cycleway links to Greater Parramatta and Sydney Olympic Park including through Carlingford and Parramatta North.
0-10yrs Committed
Priority Cycleway links in Eastern City Eastern City Walking and
Cycling Priority Cycleway links near the Harbour CBD including the Inner West Greenway and Sydney Harbour Bridge cycleway connections.
0-10yrs Committed
Council partnership program to improve local walking and cycling connections.
All Walking and
Cycling Council partnership program to improve local walking and cycling connections.
0-10yrs Committed
Inner Sydney Regional Bike Network Eastern City Walking and
Cycling Inner Sydney Regional Bike Network within 10km of the Harbour CBD
0-10yrs For
Investigation
Safe Cycleway network Central City Walking and
Cycling Safe cycleway network within 10km of Parramatta
0-10yrs For
Investigation
Sutherland to CronullaActive Transport Link
South Walking and
Cycling Sutherland to Cronulla Active Transport Link 0-10yrs For
Investigation
Name Region/District Project
Type
Project Description Future
Timeframe
Future
Status
Safe cycleway network Western City Walking and
Cycling Safe cycleway network within 10km of Greater Penrith, Liverpool, Campbelltown-Macarthur and WSA-Badgerys Creek Aerotropolis
10-20yrs For
Investigation
Cycling improvements around
metropolitan and strategic centres and
on the Principal Bicycle Network
All Walking and
Cycling
Walking and cycling improvements around
Metropolitan City Centres / Clusters and Strategic
Centres and on the Principal Bicycle Network
0-10yrs For
Investigation
Walking improvements around
metropolitan and strategic centres
All Walking and
Cycling
Walking and cycling improvements around
Metropolitan City Centres / Clusters and Strategic
Centres and on the Principal Bicycle Network.
Council partnership program to improve local
walking and cycling connections
0-10yrs For
Investigation
Walking programs State-wide Walking and
Cycling
Completion of Newcastle, Wollongong and Central
Coast 10 km pedestrian network, Completion of 2
km radius catchment investments for regional
centres. Will include safety measures identified
from Safe System design principles for corridor
planning (including traffic calming and pedestrian
priority measures).
0-10yrs For investigation
Cycling programs State-wide Walking and
Cycling
Completion of Sydney, Parramatta, Western
Sydney Airport, Newcastle 10 km cycling
network, 5 km radius of district and regional
centres. Will include safety measures identified
from Safe System design principles for corridor
planning (including traffic calming measures).
0-10yrs For investigation