CAPT Mike BelcherPMA26011 February [email protected]
Aviation Support Equipment
2
Outline
PMA260 Overview Roadmap for Automatic Test Equipment
– Mainframe CASS Update– USMC RTCASS Status– Legacy ATE TPS Offload Status– Legacy ATE Retirement Plan– Direct to CASS TPS Development– CASS TPS Rework Process– Next Generation CASS – eCASS
Common Ground Support Equipment– SE Prioritization Process– Current Deliveries– Near Term Deliveries
Other Initiatives– RCM, RTOC, Right Sizing the Inventory, PEMAs, Protrack/Pinpoint
Questions
3
PMA260 Overview
Provide cost effective aviation common support equipment in support of fleet operations and maintenance activities. Fund requirements for replenishment of peculiar support equipment (PSE) for out of production weapon systems
Scope: – 2,482 total different end items of Aviation Support Equipment – 157 funded programs across the FYDP– 124 current contracts in place– Current Designated Programs:
• 1 ACAT II = Consolidated Automated Support System (CASS) • 4 ACAT IVM
- Hydraulic Power Supply System- Land Based Mid Range Tow Tractor- Legacy Automatic Test Equipment Offload to CASS- eCASS
• 49 Abbreviated Acquisition Programs (AAPs)
4
PMA260 Overview (con’t)
Additional responsibilities – Provide SE leadership role for the Naval Aviation Enterprise– DoD Executive Directorate for Automatic Test Systems– Member of the Joint Panel for Aviation Support Equipment
(JPAVSE) committee // Aviation Common Systems (ACS)//Joint Aeronautical Logistics Commanders (JALC)
– Manage AUTOSERD & SERMIS (SEMS)– Designated as an USD(AT&L) Reduction of Total Ownership Cost
(RTOC) Special Interest Program– USMC Maritime Pre-Positioning Ship Program
OPNAV Sponsors– CDR Richard Dorn – N881C5– LCDR Louis Goncalves – N881C3– Major John McDermott – N881C4
5
SecretaryCarla Alvino (GS7)
PMA260SPrincipal Deputy PMDennis Albrecht (GS15)
(PMA260A)
AVIATION SE PM/ DIR, ATS EDCAPT Mike Belcher, USN
(PMA260)
Program Office Competency
RolesDEPUTY PM FOR ATS Systems
Asst. Dir. for ATS ED Bill Ross (GM15)
(PMA260D)Gov’t 164.1 MIL 14.5 CSS 57.3
Deputy PM for CASS CDR Bob Stailey, USN
(PMA 260DA)BFMMichelle Fore (AIR-7.8)Gov’t- 3, Mil-0, CSS- 0
ContractsJack Murtagh (NAWC 2.5.2)
Gov’t-2 Mil-1 CSS-0
LegalBrenda Dowdle (AIR-11.0)
Gov’t-1 Mil-0 CSS-0
Cost Estimating
Engineering & TestMike Flynn AIR-4.0
Gov’t-2.25 Mil-0 CSS-0
Fleet Support Team
LogisticsMark Dobson (AIR-6.0)
LCDR Rick Braunbeck, USN Gov’t-3 Mil-1 CSS-1
Test & Eval Rep
AIRFRAMES & PROPULSION/SEKen Sands (GS14)
(PMA260C2)Gov’t-73 MIL-1.6 CSS-9.3
ARMAMENT, AC WIRING, VIB, WEPS CONT SEBill Englehart (GS 14)
(PMA260C1)Gov’t-62.0 MIL3.6 CSS-7.4
AIRCRAFT WIRING/Corrosion ControlJay Losee (GS13)
(PMA260C12)Gov’t-11.9 MIL-.5 CSS-1.7
Airframes & Electrical CSE
Greg Bauer (GS13)(PMA260C23)
Gov’t-18.0 MIL-.5 CSS-1.9
ARMAMENT/ Weapon Cont CSE
LCDR Tilley, USN(PMA260C11)
Gov’t 21.7 MIL1.4 CSS 2.7
PROPULSION CSEMike Kopan (GS13)
(PMA260C22)Gov’t-35.9 MIL-0 CSS-4.0
Hydraulics, Cryogenics & RCM
LCDR Jim Gault, USN(PMA260C21)
Gov’t-19.1 MIL1.1 CSS-3.4
EW/COM/NAV CSE LT Bittle, USN(PMA260C13 )
Gov’t-27.4 MIL1.7 CSS-3.0
ASST FOR ATEPLANNING PM
Pat Weaver (GS14)(PMA260D3)
Gov’t 24.1 MIL 1.8 CSS 10.5
TPS Phase II PMKevin Dusch (GS13)
(PMA260D22)Gov’t 6.9 MIL 0 CSS .7
PHASE II OFFLOAD TEAM PM
Bob Augustine (GS14)(PMA260D2)
Gov’t 16.6 MIL 2 CSS5.7
SE InstallsAVCM Frank KadiUSN (PMA260E11)
Gov’t 2.6 MIL 3 CSS 0
NCSO/AMMRLShawn Durand (GS13)
(PMA260E1)Gov’t 17.7 MIL 3 CSS 2
MPF/MALSP/NALMEB
Vacant(PMA260E12)
Gov’t 0 MIL 3 CSS 0
PMA260IPT Structure
DEPUTY FOR FLEET INTERFACE
Bill Fennimore (GS14)(PMA260E)
Gov’t 25.3 MIL 9.0 CSS 2.0
DEPUTY FOR CSEDavid Sutherland (GS15)
(PMA260C)Gov’t-153.3 MIL-5.2 CSS-27.9
Acquisition/PMDennis Albrecht
Gov’t- 2, Mil- 0, CSS- 1
CASS PRODN PMChris Giggey (GS14)
(PMA260D3)Gov’t 79.4 MIL10.7 CSS22
RT CASS PRODN PM Maj. Rick Jayroe USMC
(PMA260D32)Gov’t42.7 MIL4.8 CSS10.6
eCASS DIPTCDR Carl Nolte, USN
(PMA260D )Gov’t 10.6 MIL2.8 CSS 9.1
eCASSJeff Llewelyn (GS13 )
Gov’t 4.9 MIL0 CSS 2.2
CASSLT Ronnie Harper, USN
(PMA260D33)Gov’t 17.4 MIL1 CSS .8
6
7
Replacing Legacy ATE with CASS
APM-469 RSTSAN/USM247 VASTAAM-60 EOSTSAN/USM470(v)2 TMVAN/USM614 ESTSAN/USM403 HATSAN/USM470v(1) ATSAN/USM604 EETS AN/APM446 RSTSAN/AWM23 RFTS AN/AWM23 LFTS AN/AWM23 C&D TS AN/AWM23 CTS AN/ASM-686 IATSAN/USM484 HTSAN/USM629 EOTS (F/A-18)AN/USM467 RADCOMAN/USM429 CAT IIIDAN/USM458 NEWTS OJ-615 EA-6B HPOJ-510 DTB APM457 S-3 AN/ASM-608 IMUTSA/E24T-205 Electrical Test SetAN/ARM-146 Decoder TS GACT/GRAD
$3.8B Reduced Total Ownership Costs
NECs - 41Tech Pubs - 624Personnel - 105Space - 2,700 ft2
Spares -30,000
NECs - 5Tech Pubs - 4 disksPersonnel - 54Space -1,900 ft2
Spares -3,800
Offload not Complete
8
Mainframe CASS Status
In Sustainment Phase - Oldest stations now 18 years old (planned 20-year life cycle)
Seven Year PBL awarded to LMSTS in November 2008– Support covered until November 2015
Vendor support commitment through 2015– USN will need to support longer– Block I stations being salvaged already – Block II/III in 2016/2017
Major changes in process– Developing a replacement for CNI assets with greater capability –
CNIAS– USN having battery problems – life limited solution in work
Will begin to replace mainframe CASS with:– RTCASS in 2009– eCASS in 2015
CASS Fleet Support Review (FSR) scheduled 5-7 May in VA Beach
9
CASSPerformance Based Logistics
New PBL Starting FY - 2009– CSP closed out after 8 successful years– PBL is essentially identical to CSP – Prime Contractor
• Lockheed Martin – Simulation Training & Support Division
– Period is 5 yrs with two 1 yr options
24 hour LOCKHEED MARTINTurnaround on BROAD ARROWS
1010
Communications/Navigation/IFF Ancillary Set (CNIAS)
Developing a new and improved CASS ancillary for CNI function– Will eliminate CNI MF CASS configuration by 2018 (with USN
JTIDS sundown) Includes real-time Link 16, IFF, TACAN test capability Includes improved MIDS-LVT and CIT TPSs
– Improved MIDS TPS will now require CNIAS assets– Expandable via software for future JTRS waveforms
Will be an ancillary to MF CASS RF, RTCASS, and the future eCASS
Development schedule (CNIAS and TPSs) – August 2007 to August 2010
CNIAS production - August 2010 to August 2011
11
Dielectric Fluid Conditioning System DFCS Fielding Status
SITE S/N Installation DateCVN-65 Enterprise (Estimated Decommission - Dec '12)
DDU014Jun-09
CVN-68 Nimitz DDU019 Mar-09CVN-69 IKE DDU003 InstalledCVN-70 Vinson DDU006 Jul-09CVN-71 Roosevelt DDU023 5/10/2010 ON CRUISECVN-72 Lincoln DDU021 Apr-09CVN-73 GW DDU022 Feb-09CVN-74 Stennis DDU002 InstalledCVN-75 Truman DDU015 Jan-09CVN-76 Reagan DDU004 Mar-09CVN-77 Bush DDU017 Jun-09AIMD Whidbey #1 DDU020 InstalledAIMD Whidbey #2 DDU009 InstalledAIMD NAF Washington DDU011 Feb-09MALS-12 DDU007 InstalledMALS-14 # 1 DDU013 InstalledMALS-14 # 2 DDU010 InstalledMALS-14 # 3 DDU016 InstalledELU #1 DDU008 InstalledELU C DDU018 InstalledCNATTU Whidbey DDU012 TBD
EA-6B FSTDDU001 Allowed to Remain @
DRS For Spare Testing
EA-6B DEPOTDDU005 At DRS for low Vac
issue
DFCS DEPLOYMENT SITES
12
Reconfigurable Transportable CASSRTCASS
Double Wide to Single Wide
HYB
RFto RT
V-22F/A-18AV-8BEA-6BH-1
CASSHigh Power Rack
+
13
RTCASS STATUS
Acquisition Objective: 160 USMC only Currently in production Initial Operational Capability (IOC) is dependant upon
TPS conversion and will be accomplished by T/M/S – MALS-14: EA-6B/AV-8B estimated IOC 1 April 09– MALS-28/29: V-22 estimated IOC 1 May 09– MALS-31: F/A-18 estimated IOC 1 July 09
Contractor Logistics Support contract with Boeing RT-High Power configuration (RTCASS + CASS HP
Rack) under integration by Boeing, estimated fielding mid-FY10
14
UUT
TPSTypical CVNOTPS
Inventory
F/A-18: 39E-2C: 29
EA-6B: 25MH-60: 13HH-60: 1
Common: 5
TMS Specific Operational Test Program Sets (OTPS)
PMA260 manages the CASS program TMS PMAs manage their own specific OTPS that provide
the:– Hardware interface between the CASS station and the Unit
Under Test (WRA/SRA)– Software test program for the Unit Under Test
PHASE I
ATE AIRCRAFT
APM-469 RSTS S-3 Removed from I-Level AN/USM-247 VAST S-3, F-14
E-2Removed from I-Level
AAM-60 (v)6 EOSTS S-3 Removed from I-Level;P-3 using (v)2 version
AN/USM-614 ESTS EA-6B, SH-60, S-3
Removed from I-Level;2 left at NADEP
AN/USM-403 HATS S-3 Removed from I-Level APM-457 TTS
HPOCS-3 Removed from I-Level
AN/USM-604 EETS AV-8B Removed from I-Level;1 left at CNATTU;2 left at NADEP
AN/APM-446 RSTS F/A-18, AV-8B
9 Remain at I-Level
AN/USM-629 EOTS F/A-18 8 Remain at I-Level
OJ-615/ALM TTS EA-6B 7 Remain at I-Level AN/USM-470(V)1
ATS F/A-18 Removed from I-Level
AN/AWM-23 RFTS F-14 Removed from I-Level AN/AWM-23 LFTS F-14 Removed from I-Level AN/AWM-23 C&DTS F-14 Removed from I-Level AN/AWM-23 CTS F-14 Removed from I-Level
Legacy ATE TPS Offload StatusPHASE II
ATE AIRCRAFT
AN/USM-484 HTS EA-6B F/A-18SH-60
AN/USM-467 RADCOM EA-6BE-2C
SH-60
AN/USM-429 CATIIID EA-6B E-2CAN/USM-470(V)2 TMV SH-60AN/USM-458 NEWTS AV-8B, F/A-18OJ-510/ALM DTB EA-6B
PHASE IIIATE AIRCRAFT
AN/ASM-686 Lot 1 IATS F/A-18AN/ASM-686 Lot 2 IATS F/A-18AN/ASM-608 IMUTS VariousA/E24T-205 GACT/GRAD
ActuatorsE-2C, EA-6B, C-2
AN/ARM-146A AN/ARA-63 VariousAN/ASM-167 & TS-2454A
AS/APC EA-6B
CAT IIID/HTS Orphans OTPS-22 EA-6BARM-200 (Marine only)
IATS Various
TPS effort completed CASS TPSs being deliveredTPS development in-process
16
Legacy ATE Retirement
Anticipated completion of removal of I-Level stations:
– TMV FY 09– DTB FY 10– IMUTS FY 10 – ARM-146 FY 10– NEWTS FY 11– RADCOM FY 11– IATS FY 12– CAT IIID FY 12– HTS FY 12
17
Emerging Platform CASS TPS Efforts(Direct to CASS)
Platform Lot OTPS I Level/Depot IOCV-22 1 9 OTPSs I Fielding
2 7 OTPSs I 3 Fielding4 In DEV
3 4 OTPSs I In DEV4 TBD Depot TBD
Platform OTPS I Level/Depot IOCAA-1Z/UH-1Y AWIRT/CWIRT I May 2010
MC/HIADC I Oct 2011FCC I TBDMFD/DFD I TBD
MH-60R ACFS I Sep 2012MMR I Jul 2013Acoustic Processor I Sep 2013TCOL I May 2014
MH-60R/S ESM I Dec 2010MTS I Dec 2011MTS(TV) I Sep 2012
18
Fleet - Initiate OTPS Repair IAW maintenance plan - Exhaust all local repair capability - Request NATEC Tech Assist info:TYCOM, WING, AIG - NATEC advices initiation of EI for design defects or rework candidate based on HW failure complexity - Fleet submits EI, if FST unable to restore full operational capability because of HW failure complexity EI advices Rework candidate - Fleet activity requests TYCOM for rework\repair\replace
TYCOM/SECA - TYCOM consult with PMA260\SEFAC to validate and prioritize SEFAC depot induction on a case by case basis- Reply to Fleet Activity with disposition instructions
SEFAC - Inducts\reworks and returns to TYCOM OTPH HW RFU
Dependent on H/W condition
CASS OTPS Depot Rework Process
19
Mainframe CASS Modernization
(Procured 1990 – 2003)
(Procured 2003 – 2011)
(Procure 2015 - 2021)
Mainframe CASS(Hybrid – RF – CNI – HP – EO)
RTCASS
(2004 – 2008 demo)
[160+ ]
[ 553 ]
[ 2 prototypes ]
ARGCS ACTD
[368 ]
eCASS(notional)
(tech demo)
20
– eCASS – Mainframe CASS Modernization
In 2015, early CASS stations will be 25 years old– Must address obsolescence while inserting technology to satisfy
emerging weapon system test requirements & reduce Total Ownership Costs
– Fewer stations required
Mainframe CASS Modernization called “eCASS” – a new test system
Leverage RTCASS, ARGCS ACTD and other test technology developments
TPSs will be transportable among eCASS, RTCASS and Mainframe CASS
Now 2015
21
The eCASS Challenge
Mainframe
RTCASS
eCASS
TPS
22
Common Ground Support
20
23
SE Budget Procurement Prioritization Process
May MayAug Nov Feb Aug
SECAs SolicitFleet Data Call
SECAs RQMT
Conference
SECAs/FleetActivities
ReallocateInventories
to filldeficits
Procurement PlanningNAVAIR
ProcurementPrioritizationConference
PrioritizeSECA
RQMTs
OPNAVApprovesPrioritiesAcrossFYDP
OPNAVLTRN881
Events
Activities
24
Current CGSE Deliveries
New SE Item Legacy SE Replaced Delivery StatusA/S32A-45 Mid Range Tow Tractor
A/S32A-30A SE and A/S32A-42 Mid Range Tow Tractors
1,000 (out of 1,249) tractors delivered thru 02/09
A/M27T-14 (Electric) and A/M27T-15 (Diesel) Hydraulic Power Supplies A/M27T-11 Purifier
A/M27T-5/5A & 7/7A Power Supplies
176 Diesel, 98 Electric, and 150 Purifiers delivered thru 02/09
Mobile Frequency Converter MMG-1A Mobile Motor Generator IOC – Dec 08; 30 units delivered to date
Jet Engine Test Instrumentation (JETI)
Instrumentation package being installed in T-1, T-6, T-10 and T-36 engine test cells. Supports testing of F414, F404, J52, F405 & F402 engines
22 of 32 systems installed including 11 CV/CVNs
25
Current CGSE Deliveries
New SE Item Legacy SE Replaced Delivery StatusAN/AWM-103 Stores Management Subassembly Test Set (SMSTS)
Replaces obsolete AWM-92, -96A, -98, - 100, -101, ASM-464, A/E-24T-216, TS3519, and MK432 Mod 6 to allow for checkout of weapons release and control interfaces prior to weapons loading.
Deliveries of all 777 units to be complete by October 2009.ECP in work to support emerging AV-8B Litening Pod, MH-60 Torpedo, and P-3C Harpoon & Maverick requirements.
TTU-597E Fuel Control Test Set
Replaces TTU-378A/E and A/E24T-159 for O-level testing and troubleshooting of aircraft fuel quantity probes and indicators.
Deliveries complete for EA-6B, E-2, C-2, and H-60 applications.Integration efforts against remaining aircraft to be completed 1st quarter FY09 with deliveries to follow.
LALS III Loader Replaces the GFK-21/E32K-7 LALS II Loader. Provides improved tensioner and Aircraft Interface Unit to improve system operation and reliability. Existing LALS II Loaders will be upgraded to LALS III configuration via ECP.
ECP kits currently being delivered to Kitting facility.New LALS III units to be delivered SEP 2008 through 2011
AECTS Depot SEC 5804 OEM produced five production lots, this ECP will make all of the units one configuration. Additionally, it will mitigate the risk associated with the long run times of the F/A 18 GCUs by incorporating an oil mist reduction system.
Depot installs started May of 2007 and are expected to be completed by October 2009. Total fleet inventory 62, units installed to date 25.
26
Current DeliveriesA/S32A-45 Mid Range Tow Tractor
Inventory objective: 1,248– Quantities delivered to date: 1,000– Deliveries complete: Projected 07/09
Legacy Inventory replaced: 848
Legacy Inventory replaced: 584
A/S32A-45 Mid Range Tow TractorA/S32A-30A SE Tow Tractor
A/S32A-42 Mid Range Tow Tractor
27
Current Deliveries A/M27T-14 (Electric) & A/M27T-15 (Diesel)
Hydraulic Power Supplies A/M27T-11 Purifier
Legacy Inventory replaced: 685
A/M27T-7ElectricA/M27T-14 Electric
A/M27T-15 Diesel
A/M37M-11Purifier A/M27T-5
Diesel
SE Designator>> T14 T15 M11Inventory objective: 258 750 240Quantities delivered to date:
98 176 150
Deliveries complete: 12/11 04/11 10/09
Legacy Inventory replaced: 275
28
Current DeliveriesMobile Frequency Converter
Inventory objective: 335– Quantities delivered to date: 30– Deliveries complete: 12/11
Legacy Inventory replaced: 343
MMG-1A Mobile Frequency Converter
A/M24M-5 Static Frequency Converter (SFC)
29
Current DeliveriesJet Engine Test Instrumentation (JETI)
Inventory objective: 32– Quantities delivered to date: 22– Deliveries complete: 10/10
Legacy Inventory replaced: one for onetest cell upgrade
Landbased: A/F32T-10A/F32T-6AA/M37T-23
Shipboard: A/W37T-1
30
Current Deliveries
AN/AWM-103Stores ManagementSubsystem Test Set
Inventory objective: 777Qty deliver to date: 777
Legacy inventory replaced:AWM-92 50
AWM-96 149AWM-98 28AWM-100 14AWM-101 70
ASM-464 174A/E-24T-216 243TS-3519 201
MK432 MOD4/6 15
TOTAL 944
LALS III LoaderInventory deficit : 75Qty deliver to date: 10Legacy LALS II inventory to be upgraded: 268
TTU-597EFuel Control Test SetInventory objective : 604Qty deliver to date: 378Legacy inventory replaced:TTU-378 A/E (GULL) 630A/E24T-159 (BOEING) 45
31
Current DeliveriesAECTS Depot SEC 5804
Inventory objective: 62– Units updated to date: 25– EST Deliveries complete: 10/09
Depot installs started May of 2007
A/F37T-21 Aircraft Engine Component Test Stand (AECTS)
A/F37T-21 Aircraft Engine Component Test Stand (AECTS)
32
Near-Term CGSE Deliveries
New SE Item Legacy SE Replaced Delivery StatusParts Washers Sink Large Aqueous Solvent
Replaces various units divisions to be installed: Sink: 400, 500 & 600 Large Aqueous: 500 & 900 Solvent: 500
Sink IOC: 2nd QTR FY00Large Aqueous IOC: 2nd
QTR FY09 Solvent IOC: 2nd QTR FY10
A/F27T-10 Hydraulic Component Test Stand SEC 5701
Replace obsolete components (monitor, computer, printer, keyboard, software, hard drive)
Depot field team installation began Nov 07
Aircraft Fluid Servicing Units PON-6 & HSU-1Separate servicing units for transmission, engine oil, hydraulic fluid and rotor fluid
IOC: Feb 09
Large Landbased Air Conditioner
A/M32C-17 Diesel Air Conditioner in support of C130, P-3, P-8 and E-2C/D aircraft
IOC – 4th QTR FY09
Computed Radiography Digitizes radiographic images of inspected components. Replaces wet method development of radiography film.
IOC – 3rd QTR FY10
Shaft Engine Test Instrumentation (SETI)
Instrumentation package being installed in T24 and T16 engine test cells. Supports testing of T-700 and T-64 engines
IOC – 2nd QTR FY10
Hydraulic Tube Bender A/E27M-9 Tube BenderCL215 Bench Mounted Tube Bender
IOC – 4th QTR FY09
Portable Oxygen Regulator Test Set (PORTS)
Replaces the Oxygen Component Test Stand “Green Monster”
IOC – 4th QTR FY09
33
Near Term CSE Deliveries
PORTSInventory objective : 113Projected delivery start: 09/09One for one replacement for LegacyOxygen Comp Test Stand
Hydraulic Tube BenderInventory objective : 46Projected delivery start: 09/09
Computed RadiographyInventory objective : 75Delivery start date: 04/10Legacy inventory replaced:75 Wet Film Processors
ShipBoardShoreBased
34
Near Term DeliveriesLarge Landbased Air Conditioner
Inventory objective: 166– Deliveries begin: IOC 09/09– Deliveries complete: 08/11
Legacy Inventory replaced: 310
A/M32C-17 Diesel
A/M32C-23
35
Near Term DeliveriesShaft Engine Test Instrumentation (SETI)
Inventory objective: 21– Quantities delivered to date: 0– Deliveries start: 02/10
Legacy Inventory replaced: 33
Mobile: A/E37T-24(V)2A/E37T-24(V)5
Indoor: A/F37T-16(V)2A/F37T-16(V)3
36
Near-Term DeliveriesAircraft Fluid Servicing Units
HSU-1
Inventory objective: – 920 Engine oil– 1040 Hydraulic fluid– 551 Transmission Fluid– 67 Aircraft Tail Rotor Fill Unit– Deliveries start: 02/09
PON-6
Legacy Inventory replaced:
PON-6: 1,384HSU-1: 1,342
37
New SE Item Program StatusHandheld Aircraft Wire Tester (HAWT) Full Rate Production Decision planned for 2nd quarter
FY09.Automatic Wire Test Set (AWTS) Full Rate Production Decision planned for 3rd quarter
FY09.Fiber Optic Test Set (FOTS) and Fiber Optic Repair Set (FORS)
Full Rate Production Decisions Planned for FY10.
Common Video Borescope Set (CVBS) Production contract scheduled for 1st quarter FY09 with Full Rate Production Decision planned for 1st quarter FY10.
AN/USM-715 Rocket Pod Test Set Full Rate Production Decision planned for 1st quarter FY09.
AN/USM-713 Signal Generator Test Set Full Rate Production Decision planned for 1st quarter FY09.
AN/ARM-206 I-Level TACAN Test Set (ITATS) Navy developmental testing scheduled for 2nd quarter of FY09. Full Rate production Decision to follow successful completion of testing.
AN/USM-708 CNI/RF Avionics Flightline Tester (CRAFT) Full Rate Production Decision planned for the end of FY09.
Handheld Radar Simulator Full Rate Production Decision planned for 1st quarter FY11.
TS-4543/G Precipitation Static (P-Static) Diagnostic Test Set
Full Rate Production Decision planned for 1st quarter FY09.
Turboprop Test Instrumentation (TPTI) Currently in the design and development phase with IOC planned for 2nd quarter FY11.
Next Generation Software Loader IOC in 1st quarter FY11.Shipboard Tow Tractor Contract award scheduled for 1st quarter FY09 with Full
Rate Production Decision planned for 3rd quarter FY10.Shipboard HELO Handler Contract award scheduled for 1st quarter FY09 with Full
Rate Production Decision planned for 4th quarter FY10.A/M32K-10 Munitions Trailer Extensive testing program to start 1st quarter FY09 with
Full Rate Production Decision planned for 1st quarter FY10.
On-Going CGSE Modernization Efforts
38
Other PMA260 Initiatives
NAN-3/-4/-4ANitrogen Servicing
Unit
A/S32A-37A/C Tow Tractor
A/M32C-17Mobile Air
Conditioning Unit
MMG-1AMobile Electric
Power Plant
NC-10B/CA/S32A-108
Mobile Electric Power Plants
A/S48M-2 & 3Manlift
(Diesel & Electric)
A/M32C-21 Mobile
Air Conditioning
Aircraft Maintenance
Platforms
A/S32A-31AA/C Tow Tractor
AircraftJacks
A/S32A-30AA/C Tow Tractor
A/S32A-42A/C Tow Tractor
A/U26U-1Oxygen Servicing
Cart
MSU 200NAVAir Start Unit
Annual Cost Avoidance Projection of 36 RCM analyses completed through FY 04 (Implemented by FY 07) = $34.98MAnnual Cost Avoidance Actual of RCM analyses completed by FY 04 (Implemented by FY 07) = $30.4M
Note: -Cost savings typically experienced ~2 Yrs after completion of RCM Analysis due to implementation in Fleet.
TS4508/U ADTS
A/E37T-17 T56 AETS
A/S32K-1DSATS Loader
A/S32M-14Pettibone
A/S37A-3 Shipboard MEPP
PMU-55E Hydraulic Fill Unit
CASS Airflow Sensor System / Battery Backup /
MOV’s / GPI / DTU
A/M27T-5 & 7Hydraulic Servicing
Unit (Diesel & Electric)
A/S32A-32 Spotting Dolly
CSE RCM AnalysisCSE RCM Analysis
$3.7$3
.95
$16.46 $18.91
$30.41
$27.59
$5.3
$14.2
$5.71
$14.31
$34.98
$32.35
$25.91
$9.18
$8.2
$16.34
40
Circuit Card Testing
ProTrack: GPETE; fielded ship and shore PinPoint: will be designated as special test
equipment at shore FRCs– Establishing logistics, training, and support thru supply
system– Identifying deficits that need to be filled– Establishing uniform test routine development procedures– Depot routines developed to date: H-60(7), F/A-18(7),
EA-6B(14), V-22(3)– 17 new F/A-18 and E-2C routines funded for FY09
(Depot/I Level) via PMA260 RTOC Initiative
Support Equipment Status
HuntronProTrack
DiagnoSYSPinPoint
41
Aviation Support EquipmentReduction of Total Ownership
(RTOC) Initiatives
USD (AT&L) designated PMA260 ASE and RTOC special Interest Program (SIP) based upon current Fleet O&S cost reduction efforts/programs
RTOC SIP status allows PMA260 to submit requests for follow-on OSD funded RTOC Initiatives– Four initiatives approved FY04 -> FY07
• AV-8B depot GCU SCA support on CASS• A/W37T-1 engine test system upgrade• F/A-18 DECU depot support on CASS• CASS TPS optimization (run time reduction) for selected
H-60/F/A-18/AV-8B TPS
42
FY09 OSD ApprovedRTOC Initiatives
Upgrade NOAP Spectrometers to a common hardware and software baseline eliminating multiple configurations, individual logistics tails, and resolving obsolescence issues
Approved funding: $400K (FY09 $200K/FY10 $200K)
Develop intermediate maintenance test procedures for 17 high failure and cost SRAs using fielded circuit card testers
Approved funding : $630K (FY09)
Navy Oil Analysis Program Spectrometer Upgrade
F/A-18 & E-2C Shop Replaceable Assy Test Routines (ProTrack/PinPoint)
43
Reducing the CGSE Footprint
I-LevelTACAN
Test Sets
• AN/ARM-155• AN/ARM-156• 972(V)-1• DTS-200
AN/ARM-206I-Level TACAN
Test Set (ITATS)4 1
60% Inventory Reduction
O-LevelCNI
Test Sets
AN/ARM-206I-Level TACAN
Test Set (ITATS)7 1
59% Inventory Reduction
• SM-511• SM-511A• ID-1956• AN/ASM-663• AN/ARM-201• AN/UKM-7• AN/APM-480A
O-LevelEW
Test SetsAN/USM-713
Signal GeneratorTest Set
(All other a/c not supported by JSECST)
4 2 8% Inventory Reduction• AN/USM-482• AN/USM482A• AN/USM-406• AN/USM-638
AN/USM-670JSECST
(F/A-18, EA-6B, AV-8B, & E-2)
44
Reducing the CGSE Footprint
O-LevelWeaponsRelease &
ControlTest Sets
AN/AWM-103Stores Management
Subassembly Test Set9 1
57% Inventory Reduction
• AN/AWM-92• AN/AWM-96A• AN/AWM-98• AN/AWM-100• AN/AWM-101• AN/ASM-464• A/E-24T-216• TS-3519• MK-432 Mod 4/6
O & I LevelBorescope
Sets
CommonVideo Borescope
Set (CVBS)>8 1
>13% Inventory Reduction
• 1998AS100-1• 2023AS100-1• 3353AS100-1• 3354AS100-1• 3355AS100-1• 3356AS100-1• 3358AS100-1• Additional PSE Borescope Sets
45
Completed Carrier SE inventory allowance Reductions
Carrier Vessel Support Equipment Productive Ratio Initiative
• CVN SE allowance reductions implemented with CNAF concurrence based upon fleet utilization rates• O&S Cost savings of 938K per year, CV fleet wide (AVDLR, AFM, MHRS)• 107 End Items removed from each Aircraft Carrier• 975 square feet footprint reduction per carrier
S/ENAVAIR Recommended / CNAF ApprovedTotal Reduced per CVSquare Feet
AIR
CO
ND
ITION
ER
01-208-8705
JENN
Y T-6 01-159-4744
HSU
-1 01-088-4611
TMU
-70 LOX C
AR
T 00-158-0657
HLU
-196/E Battery
Charger
01-494-5201
NA
N C
AR
T A/M
26U-4/A
01-517-9308
T20/3FH
01-064-2889
T20/2FH
00-102-8441
T30-1VH5
00-516-2017
T10-1VH4
00-516-2019
T20/1VH5
00-865-7838
NET-4/3000 EN
GIN
E TR
AILER
00-123-8073
BO
MB
HO
IST (HLU
196) 01-447-4628
BO
MB
HO
IST (HLU
288) 01-161-8623
AD
U-400/E W
EAPO
NS
SKID
00-143-8788
MH
U-191 W
EPS SKID
01-244-3449
TOW
BA
R 15 FT
01-155-2670
2 2 2 3 4 10 5 0 5 9 4 12 8 14 0 250 40
1 2 1 3 1 10 4 5 5 9 1 3 4 4 2 66 2072 3 1 53 30 60 24 30 30 54 60 4 0 4 30 495 20
46
Portable Electronic Maintenance Aid (PEMA) Management
PEMA management transitioning from AIR-6.8 to PMA260– All future PEMA procurements will be managed as stand
alone program of record by PMA260– PEMA procurement budget established in FY10 for stand
alone program of Record– PEMAs will be identified/documented/tracked as
‘O’ Level Support Equipment via the IMRL• USN programs identified in POR include F/A-18(A-G), H-60,
E-6B, UAV’s• USMC programs (funding TBD) include
F/A-18, C130J, MV-22, AV-8B, AH-1Z, UH-1Y• Units to be replenished on a 3/4 year cycle
47
Summary
PMA260 is committed to:– Modernizing Common Support Equipment,
including CASS– Mitigating obsolescence– Making our CSE better for the operator– Removing Legacy ATE – Right sizing the SE inventory
48
PMA260 Points of Contacts
CAPT Belcher Aviation SE Prog Mgr [email protected] Albrecht Principal Deputy PM [email protected] Sutherland Deputy PM for CSE [email protected] Fennimore Deputy for Fleet Interface [email protected] Ross Deputy PM for ATS [email protected] Bob Stailey CASS Officer [email protected] Giggey CASS/eCASS IPT Lead [email protected] Llewellyn CASS EO Team Lead [email protected] Ronnie Harper CASS Team Lead [email protected] Scott LevkulichDeputy eCASS Team Lead [email protected] Sands Cryo/Hyd CGSE Team Lead [email protected] Kevin Tilley Arm Hand Wep CGSE [email protected] Rick Jayroe RTCASS Team Lead [email protected] Rick Braunbeck CASS APML [email protected] Kevin Bittle CNI/Inst CGSE Team Lead [email protected]
49
This presentation is available atwww.amdo.org