Phase 1 Works 26th July 2010 to 15th October 2010 – 12w Phase 5 Works 1st August 2011 to 26th August 2011 – 5w
Phase 2 Works 18th October 2010 to 17th December 2010 – 9w Phase 6 Works 25th June 2012 to 03rd August 2012 – 6w
Phase 3 Works 20th December 2010 to 18th March 2011 – 9w
Phase 4 Work 21st March 2011 to 29th July 2011 – 19w
2
UNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTSUNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTS
REV.10
11/06/2010
SSEI PHASE 126th July 2010 to 16th October 2010
ACCESS / EGRESS DURING PHASE 1 WORK
University to Have Personnel Available During Access & Egress of
Wagons