OPNFV Plugfest Planning
Dovetail Project1/29/2016
• Plugfest: An industry event allowing companies and implementers an opportunity to test interoperability of products/projects being developed according to a common plan (i.e. a standard).• A plugfest event tends to be unique, where companies are at the same site
with similar resources / goals.• Testing scope and plans should take advantage of this opportunity, to provide
value to attendees beyond the testing they might undertake on their own outside of a plugfest.
Plugfest Definition
• OPNVF Turn-up• Target Participants: Hardware Suppliers, Integrators, Installation Development Team(s)• Testing Scope: Validation of installation process on different hardware platforms and
configurations.• SDN Integration:
• Target Participants: SDN Controllers• Testing Scope: Validation of SDN controller integration, coupled with install process testing above.
• VNF Applications:• Target Participants: VNF suppliers• Testing Scope: Provide underlying infrastructure and resources to help application provider verify
the life cycle management on the OPNFV platform. Testing of the application is outside of the scope of this event.• Note, this work item is a lower priority for the first plugfest, with active marketing aimed at the first two work
items. The infrastructure for this work item would be provided by the
Proposed Scope – May 2016
• Agree to the proposed scopes, document these scopes on the Etherpad or Wiki and plugfest webpage.• Finalize the “Rules of Engagement” for the plugfest.• Create a plugfest event webpage and registration portal.• Create marketing plan for the plugfest.• Create project area, repository, or Etherpad to “hold” the test plan for
the plugfest.• Need to develop process for review / acceptance of test cases within the test
plan.
Next Steps
2016 2016
Today
Jan Feb Mar Apr May
Rules of engagement completedFeb 12
Plugfest website posted, registration site opened (Linux Foundation)Feb 29
Initial press releaseMar 2
Test plan frozenApr 22
Plugfest beginsMay 9
Conclusion press release May 19
Publish plugfest reportMay 27
Test Plan DevelopmentFeb 15 - Apr 22
Logisitics Development (i.e. shipping/travel info, etc.)Jan 29 - Mar 11
Project Timline