7/30/2019 Oncor - Custom Commercial Standard Offer Program
1/70
CUSTOM COMMERCIAL
STANDARD OFFER
PROGRAM
SECTION 1 OF 5
2013 Program Manual and Contract Documents
November 2012
7/30/2019 Oncor - Custom Commercial Standard Offer Program
2/70
Table of Contents1 INTRODUCTION ...................................................................................................................................1
1.1 BACKGROUND ..........................................................................................................................2
1.1.1 Glossary .................................................................................................................................2
1.2 PROGRAM GOALS....................................................................................................................2
1.3 ELIGIBILITY ................................................................................................................................2
1.3.1 Service Provider Eligibility ...................................................................................................2
1.3.2 Project Eligibility....................................................................................................................3
1.3.3 Measure Eligibility.................................................................................................................4
1.4 INCENTIVE BUDGETS AND PRICING...................................................................................7
1.4.1 Available Budgets .................................................................................................................7
1.4.2 Prices ......................................................................................................................................7
1.4.3 Incentive Limitations .............................................................................................................8
1.4.4 Payments ...............................................................................................................................9
1.4.5 Special Incentive Cases .................................................................................................... 11
2 PARTICIPATION PROCESS ....................................................................................................... 12
2.1 ENERGY EFFICIENCY PROGRAM MANAGEMENT........................................................ 12
2.2 CUSTOM COMMERCIAL STANDARD OFFER PROGRAM PARTICIPATION........... 12
2.3 PROJ ECT PHASES ................................................................................................................ 13
2.3.1 Program Addendum.......................................................................................................... 15
2.3.2 Initial Application (IA)......................................................................................................... 15
2.3.3 Final Application (FA) ........................................................................................................ 16
2.3.4 Deposit Forfeit.................................................................................................................... 17
2.3.5 Additional Deposit.............................................................................................................. 18
2.3.6 Pre-installation Inspection................................................................................................. 18
2.3.7 Contract Addendum........................................................................................................... 19
2.3.8 Installation Notice (IN)....................................................................................................... 19
2.3.9 Post-installation Inspection............................................................................................... 20
2.3.10 Measurement and Verification (M&V) ............................................................................ 20
2.3.11 Savings Report (SR).......................................................................................................... 22
2013 Custom Commercial Standard Offer Program
7/30/2019 Oncor - Custom Commercial Standard Offer Program
3/70
7/30/2019 Oncor - Custom Commercial Standard Offer Program
4/70
Section 1 Chapter 1 Introduction
CCSOP 1 INTRODUCTION
Oncor is a regulated electric transmission and distribution service provider that serves 10million customers across Texas. Using cutting edge technology, more than 3,000 employees
work to safely maintain reliable electric delivery service with the largest distribution andtransmission system in Texas; made up of approximately 118,000 miles of lines and morethan 3 million meters across the state.
But Oncor delivers more than just electricity. Each day, Oncor helps Texans meet thechallenge of rethinking energy use for greater efficiency, cost savings and positiveenvironmental impact. For more than 100 years, weve built a reputation as a company thatcares about our communities, whether it involves supporting the environment, promotingsafety or teaching school children about electricity.
Oncor is owned by a limited number of investors, including a majority owner, Energy FutureHoldings Corp. It is managed by a board of directors, which is comprised of a majority of
independent directors.
Welcome to the Oncor Custom Commercial Standard Offer Program (CCSOP) for 2013 (the
Program). This Program pays incentives to energy efficiency service providers (including
equipment distributors, contractors, Retail Electric Providers, energy service companies, and
customers) for new or retrofit projects. Eligible projects for the Program require
measurement and verification, can span multiple Program years, or have incentives that
exceed $300,000. Measurement and verification projects must have a $10,000 minimum
incentive. Only commercial customers can participate in this Program. Solar Photovoltaic
project must spans multiple Program years or require measurement and verification. In
general, to participate in the Program, Service Providers undergo an application process
including going online to the Energy Efficiency Program Management (EEPM) Solution,
signing the Amended and Restated Texas Energy Efficiency Market Agreement (Umbrella
Agreement), and then entering into a Program Addendum for the Custom
Commercial Standard Offer Program with Oncor. The Umbrella Agreement allows the
Service Provider to obtain access to the programs Oncor has set up on EEPM. Under the
terms of the Custom Commercial Standard Offer Program Addendum, the Service Provider
agrees to participate in the Program and deliver demand and energy savings to an eligible
Oncor customer via the installation of eligible energy efficiency measures at that customer
site. To receive incentive payments, the Service Provider must demonstrate the
demand and energy savings delivered by the installed equipment by performing simplified
or comprehensive measurement and verification (M&V) activities, or for projects that exceed$300,000 in incentives by utilizing the deemed savings approved for the Program.
This Program Manual consists of five Sections. The first Section provides a general
introduction to the Program, including an overview of Program features and background
information on Oncors energy efficiency initiatives. All Program information, including
2013 Custom Commercial Standard Offer Program 1
7/30/2019 Oncor - Custom Commercial Standard Offer Program
5/70
Section 1 Chapter 1 Introduction
application materials, is available via the Internet at the Oncor website,
https://www.oncoreepm.com.Oncor will accept applications starting December 3, 2012.
1.1 BACKGROUND
The Program was developed to comply with state energy efficiency goals. The Texas
Legislature passed Senate Bill 7 (SB7) in 1999, which restructured the states electric utility
industry. Several revisions to the terms of the original law have been enacted over the
years. Several changes to the Public Utility Commission of Texas (PUCT) rules governing
utility energy efficiency programs became effective December 1, 2010 (see PUCT Docket
No. 37623 for changes to Substantive Rule 25.181). One of these changes was to increase
the utilitys goal from 25% to 30% of the annual growth in demand of residential and
commercial customers for 2013 through savings achieved by energy efficiency programs.
1.1.1 Glossary
Certain capitalized terms used herein are defined in Oncors Technical Resource Manual for
Energy Efficiency Projects (the TRM), which reference herein. For Glossary term see
Section 2 of the TRM.
1.2 PROGRAM GOALS
The main goal of the Program is to reduce summer peak demand in the Oncor service
area and reach the demand and energy reduction goals established by the Public
Utility Commission of Texas (PUCT) regulations (see PUCT Substantive Rule25.181). Additional Program objectives are to:
Encourage private sector delivery of energy efficiency products and services.
Achieve customer energy and cost savings.
Create a simple and streamlined Program process to stimulate strong Program
participation by Service Providers.
1.3 ELIGIBILITY
1.3.1 Service Provider Eligibility
Any entity meeting the participation requirements that installs eligible energy
efficiency measures at a facility with nonresidential electric service provided by
2013 Custom Commercial Standard Offer Program 2
http://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/7/30/2019 Oncor - Custom Commercial Standard Offer Program
6/70
Section 1 Chapter 1 Introduction
Oncor is eligible to participate in the Program as a Service Provider. Eligible Service
Providers include:
National or local energy service companies (ESCOs).
National or local companies that provide energy-related services (e.g.,
contracting) or products (e.g., lighting and HVAC equipment).
Retail Electric Providers (REPs).
Individual customers with metered electrical demand exceeding 50 kW that
implement energy efficiency measures in their own facilities.
To ensure that the Program incentive budget is allocated to Projects that are likely to
meet with success, all Service Providers will be required to demonstrate a
commitment to fulfilling Program objectives and competency in completing the
proposed Project. Service Providers will be required to submit the following
information as part of the application process:
A description of the Service Provider firm, including relevant experience, areas of
expertise, and references.
1.3.2 Project Eligibility
A Project (Project or Projects) is defined by a set of proposed or installed
measures and estimated demand and energy savings included in a single
application (IA) as set forth in Section 2, Chapter 1 of this Program Manual.Comprehensive Projects that include a range of measure types are encouraged. All
Projects must meet the following requirements:
Each Project must be over $300,000 in incentive or require Measurement and
Verification (M&V) or span multiple Program years. All other Projects must be
submitted in the Basic Commercial Standard Offer Program.
One Project may involve the installation of measures at more than one customer
site, so long as the customers and sites are similar. For example, installation of
measures at a chain of grocery stores may include more than one customer, but
may constitute a single Project. Combining similar measures/sites into a single
Project reduces administrative costs for performing due-diligence review of
applications.
Peak demand savings must be determined for the peak demand period with
exceptions approved by the Program Manager. M&V of demand and energy
savings may continue for up to 12 months and carry into the following year.
2013 Custom Commercial Standard Offer Program 3
7/30/2019 Oncor - Custom Commercial Standard Offer Program
7/70
Section 1 Chapter 1 Introduction
A work plan that covers the design, implementation, operation, and management
of the Project may be required.
A performance security deposit of 5% of a Projects estimated incentive payment
will be required.
1.3.3 Measure Eligibility
The Program does not specify eligible measures in order to provide Service
Providers flexibility in packaging services. A Service Provider may propose the
inclusion of any measure in its Project that meets the following requirements:
Measure must produce savings through an increase in energy efficiency or a
substitution of another energy source for electricity supplied through the
transmission and distribution grid.
Measure must produce a measurable and verifiable electric demandreduction during the peak summer period or must reduce electricity
consumption. Fuel-switching measures must reduce peak electric demand, and
there must be a decrease in net British Thermal Units (BTU) use.
Measure may be installed in retrofit or new construction applications.
Measure must exceed min imum equipment standards.
The following measures are excluded from consideration in the Program:
Measures that involve plug loads (loads which plug into a standard wall or flooroutlet).
Measures that involve self-generation or cogeneration, except for renewable
technologies.
Measures that rely on changes in customer behavior and require no capital
investment.
Measures that achieve savings through equipment maintenance,
commissioning, or operational changes, without an equipment efficiency
upgrade.
Measures that result in negative environmental or health effects.
Measures that receive an incentive through any other energy efficiency
program offered by Oncor.
2013 Custom Commercial Standard Offer Program 4
7/30/2019 Oncor - Custom Commercial Standard Offer Program
8/70
Section 1 Chapter 1 Introduction
Project incentives will be paid only for energy and demand savings directly related to
end-use equipment installed under the Project. Savings due to interactive effects
between lighting measures and space-cooling equipment (in cases where lighting
measures have been installed in a cooled space) will be eligible for payment based
on a stipulated value only. Interactive effects between other end-use equipment will
not be eligible for Program incentive payments.
Table 1.1 provides examples of eligible and ineligible measures. Oncor will consider
any measures that are not listed in Table 1.1 for Program eligibility on a case-by-
case basis.
Table 1.1: Examples of eligible and ineligible measures and projects
Eligible Measures or Projects Ineligible Measures or Projects
Commercial Cooling and
Ventilation
Constant air volume (CAV)
to variable air volume (VAV)
conversion
Chiller replacement
Packaged cooling unit
replacement
Fan and pump motor
efficiency upgrades
Fan and pump variable
speed dr ive (VSD)
installations
Thermal storage projects
Commercial Lighting
High-efficiency lighting thatreplaces less-efficient
lighting
Lighting controls to reduce
operating hours (in
conjunction with lighting
CFLs wi thout hard-wired
ballasts
Any screw-in lamp
Cogeneration and self-
generation projects, except
renewable technologies
Electric equipment with
decoupled self-generation
Fuel switching to electric
Load reductions caused by
building vacancies, decreased
product ion, or other changes
in occupant characteristics or
behavior
Measures that decrease
building plug loads, such as
green plugs or computer
inactivity time-out controls
Energy-efficient gas-only
measures
Load shift ing, except thermal
storage
2013 Custom Commercial Standard Offer Program 5
7/30/2019 Oncor - Custom Commercial Standard Offer Program
9/70
7/30/2019 Oncor - Custom Commercial Standard Offer Program
10/70
Section 1 Chapter 1 Introduction
Table 1.2: Baseline equipment efficiency standards
Equipment Type Appl icable Basel ine Standard
Cooling ASHRAE 90.1 1999 (baseline for retrofits)
ICEE 2009 except Heat Pump and DX
and chillers which are PUCT Docket
based.
Lighting Oncor Electric Delivery Standard Lighting
Wattage Table (based on 1992 EPACT)
New construction based on ICEE 2009
Motors ASHRAE 90.1 2004
1.4 INCENTIVE BUDGETS AND PRICING
1.4.1 Available Budgets
Oncor has assigned an incentive budget for the Program of approximately
$4,000,000 for the 2013 Program year, which budget may be increased or
decreased by Oncor at any time in its sole discretion.
1.4.2 Prices
There is no universal price for demand or energy reduction. Each measure will havea set base $/kW demand and $/kWh energy reduction per year. Incentives for each
measure will be calculated using a base $/kW/year for the measure, times the years
of Expected Useful Life (EUL) of the measure, times a net present value calculation,
times a geographic multiplier. See Table 1.3 for measure incentives. These include
use of the aforementioned variables. All Program adjustments are applicable.
Energy and demand savings eligible for incentives must either be calculated using
pre-approved deemed (stipulated) savings or determined through simplified M&V
procedures or a detailed M&V plan.
Table 1.3 Incentives by measures
2013 Custom Commercial Standard Offer Program 7
7/30/2019 Oncor - Custom Commercial Standard Offer Program
11/70
Section 1 Chapter 1 Introduction
Descrip tion $/kW $/kWh
Air Compressor E9 $ 187.46 $ 0.0577
Biomass E11 $ 187.65 $ 0.0626
Chillers* $ 336.90 $ 0.1011
Controls E13 $ 187.46 $ 0.0577
DC UPS E21 $ 180.25 $ 0.0505DC Virtualization E20 $ 103.25 $ 0.0289
DX Air Conditioners & Heat Pumps* $ 285.30 $ 0.0856
Geothermal E3 $ 375.90 $ 0.1128
Injection Molding E15 $ 187.72 $ 0.0570
Lighting: High Intensity Discharge (HID) $ 209.22 $ 0.0571
Lighting: Light Emitting Diode (LED) $ 209.22 $ 0.0571
Lighting: Linear Fluorescent $ 209.22 $ 0.0571
Lighting: Modular CFL and CCFL Fixtures $ 217.58 $ 0.0593
Lighting: Replace T12 NonElectronic $ 133.76 $ 0.0365
Lighting: Screw, all Types $ $ Motors E2 $ 247.52 $ 0.0762
Solar PV E12 $ 538.79 $ 0.4077
Thermal Storage E10 $ 336.90 $ 0.1011
VFD for VAV Air Handler $ 247.26 $ 0.0761
Wind Generation $ 180.50 $ 0.0505
Window Film E4 $ 180.50 $ 0.0505
Other As Needed Case By Case Case By Case
* Additional Funds for Early Replacement
Qualifying Chillers, DX units and Heat Pump units are further explained in Section5.3.10 and 5.3.12 of the TRM.
This table will be expanded as additional measures are added.
1.4.3 Incentive Limitations
Maximum Service Provider incentives
To ensure that incentives are available to multiple Service Providers, no Service
Provider or its affiliates may reserve nor receive more than an aggregate total of20% of the incentive budget in a given budget year.
2013 Custom Commercial Standard Offer Program 8
7/30/2019 Oncor - Custom Commercial Standard Offer Program
12/70
Section 1 Chapter 1 Introduction
Geographic adjustments
In order to promote energy efficiency activities in all areas of the service territory
there will be an additional 15% payment for all work, except Solar Photovoltaic,
calculated on a site basis, outside the seven-county metroplex area. The metroplex
area counties include Dallas, Tarrant, Rockwall, Denton, Collin, J ohnson, and Ellis.
Net present value
The calculation will use a discount rate of 8.14% and an inflation rate of 2%.
Cost of Project
Incentives will also be limited to a percentage of the capital cost of the Project. In no
case will Oncor pay incentives in an amount that exceeds 50% of the capital cost (as
determined by Oncor, in its sole discretion, based on information supplied by Service
Provider and such other information Oncor may elect to use) of the Project (i.e.,Oncor will pay incentives equal to a maximum of 50% of Project capital cost).
Adjustments will be across all measures.
Documentation of cost
The Service Provider may be required to provide Oncor with a breakdown of the
capital cost of the Project. This will include a copy of the customers invoice or
contract. This may be requested at the Initial Application at Oncors discretion.
Controls measures
Controls measures utilizing the E13 controls measure file will be excluded from the
project capacity factor and limited to a maximum of 10,000,000 kWh per project to
be incented.
1.4.4 Payments
Oncor will pay the Service Provider in two installments: the installation payment
and the performance payment. After each Project is installed and Oncor verifies
installation, the Service Provider will receive an initial payment of 40% of the total
estimated Project incentive payment available at the Installation Notice payment or
40% of the Contract Addendum, whichever is less. This initial installation payment
will be calculated as follows:
2013 Custom Commercial Standard Offer Program 9
7/30/2019 Oncor - Custom Commercial Standard Offer Program
13/70
Section 1 Chapter 1 Introduction
Equation 1.1:
Installation payment
($) =
0.4 [(Estimated peak kW incentive) + (Estimated annual
kWh incentive)]
All M&V activities must be completed, documented, and accepted before the ServiceProvider will receive the remaining incentive payment, based on the verified savings.
This performance payment will be the difference between the Installation Notice
payment and the total final incentive amount and will be calculated as follows:
Equation 1.2:
Performance payment
($) =[(Verified peak kW incentive) + (Verified annual kWh
savings incentive)] Installation payment
If the performance payment calculation results in a negative number, then the
Service Provider must repay such amount to Oncor.
Under no circumstances will Oncor make a total incentive payment that is more than
100% of the total estimated incentive payment specified in the Contract Addendum.
If, however, M&V activities indicate that the measured savings are less than the
estimated savings, the total incentive payment will be based on the measured
savings.
Equation 1.3:
Performance payment ($) + Installation payment ($) Contract Addendum ($)
Completion Timetable
In order to better budget funds, at the time of the Contract Addendum preparation
(FA Approval) the Service Provider must give an estimated completion date.
Deposits
Service Providers must submit performance security deposits equal to 5% of Project
incentive estimates included in the Initial Application (IA). Deposits must besubmitted with the IA. See 2.3.4 and 2.3.5 for additional information.
2013 Custom Commercial Standard Offer Program 10
7/30/2019 Oncor - Custom Commercial Standard Offer Program
14/70
Section 1 Chapter 1 Introduction
1.4.5 Special Incentive Cases
Projects involving fuel switching (i.e., electric chillers to gas or absorption chillers)
shall be eligible for incentive payments based on the electric demand savings only.
Refer to the M&V Guidelines in the Technical Resource Manual to determine how to
calculate fuel switching demand savings. As mentioned earlier, fuel switching to
electric is not an eligible measure in the Program.
2013 Custom Commercial Standard Offer Program 11
7/30/2019 Oncor - Custom Commercial Standard Offer Program
15/70
Section 1 Chapter 2 Participation Process
CCSOP 2 PARTICIPATION PROCESS
This chapter provides information on participating in the Program including the
Program process, required submittals, milestones, and performance securitydeposits. Oncor will open the online system on December 3, 2012. On December
17, 2012 at 10:00 a.m. CST the immediate submission of Projects will be allowed.
Oncor will continue to allow submissions until the budget is exhausted, and after
that, additional Projects will be waitlisted. Projects entered in the 2012 Commercial
Standard Offer Program (CSOP) and not accepted will need to be re-entered for the
2013 Custom Commercial Standard Offer Program if eligible. Projects submitted in
previous CSOP years and not completed will need to remain in the Program year
and guidelines in which they were originally submitted. This process is handled in
the Custom Commercial Standard Offer Program.
2.1 ENERGY EFFICIENCY PROGRAM MANAGEMENT
Service Providers must first be accepted into the EEPM Solution to be eligible to
participate in the Custom Commercial Standard Offer Program. This will include
completing the Umbrella Agreement, and receiving approval of said contract. The
next step is to complete the Service Provider profile in EEPM with the required
information and documents. This includes such things as the Affidavit of Affiliation
and insurance accords. Once the Umbrella Agreement is approved and the
Program opens you will be ready to begin the application process to be able toparticipate in CCSOP. That process will allow you to apply but does not guarantee
acceptance into CCSOP. This can be accomplished athttps://www.oncoreepm.com.
2.2 CUSTOM COMMERCIAL STANDARD OFFER PROGRAM
PARTICIPATION
Participation in the Custom Commercial Standard Offer Program involves phases
shown in Section 2.3.
You must submit and sign a Program Addendum before going on to the Project
Phases
2013 Custom Commercial Standard Offer Program 12
http://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/7/30/2019 Oncor - Custom Commercial Standard Offer Program
16/70
Section 1 Chapter 2 Participation Process
2.3 PROJECT PHASES
1. Submit an Initial Application (IA) in order for Oncor to screen the potential
Project for feasibility and tentatively reserve incentive funding.
2. Prepare and submit a Final Application (FA).
3. Install the Project, and submit an Installation Notice (IN) to receive an initial
incentive payment.
4. Conduct M&V activities, and submit a Savings Report (SR) in order to
receive the final energy and demand savings incentive payment.
A discussion of the requirements of each phase can be found below. Figure 2.1
shows a flowchart of the process. Shaded boxes with bold borders denote required
submittals by the Service Provider.
2013 Custom Commercial Standard Offer Program 13
7/30/2019 Oncor - Custom Commercial Standard Offer Program
17/70
Section 1 Chapter 2 Participation Process
Figure 2.1 Custom Commercial Standard Offer Process
Oncor Electric Delivery Service Provider
Complete Umbrella andProgram Contract, identify
projects, and negotiate withCustomer
IA approval or rejection Submit Initial Applic ation (IA)
If IA approved, reserve funding
(Typically within 20working days)
Finalize measures andprepare M&V plan
FA approval or rejection
(Typically within 45 days)
Send Standard Contract
Adden du m
Submit Final Applic ation (FA)(Due within 60 days of IA approval)
Sign & return Standard Contract Addendum (Due to Oncor within 15 days of receipt of Contract)
Install project
IN approval o r rejection
(Typically within 30 days of approval of invoice)
(Typically within 30 days)
Submit Installation Notice (IN)
On approval m ake installation payment (~ 40%) Conduct M&V activities
SR approval o r rejection Submit Savings Report (SR)(Due after completion of M&Vactivities (up to 12 months))
(Typically within 30 days of approval of invoice)
On approval make performance payment (~ 60%)
2013 Custom Commercial Standard Offer Program 14
7/30/2019 Oncor - Custom Commercial Standard Offer Program
18/70
Section 1 Chapter 2 Participation Process
2.3.1 Program Addendum
The Service Provider must enter into the Program Addendum with Oncor in order to
participate in the Program. Program Addendums are terminable by Oncor at will, as
well as for other events of default by Service Provider. This allows Service Providersto avoid resubmitting a new Program Addendum each year; however, it does require
the Service Provider to submit updated documentation for each year of the Program
Addendum, using the Program online application, and Service Provider is required to
enroll and be accepted by Oncor each Project year. It is solely the responsibility of
the Service Provider to make Oncor aware of changes in the documentation and to
provide hard copies of such documentation. Failure to provide documentation may
be a breach of the Program Addendum which can be grounds for termination of the
Program Addendum with the Service Provider.
The Program Addendum does not in any way guarantee the Service Providerfunds for any year of the Program. The Program Addendum does not in any
way obligate Oncor to offer the Program.
The terms of the Program Addendum will be standard for all Service Providers and
are nonnegotiable unless unique circumstances merit and require, in the sole
discretion of Oncor, revision. In the event of any conflict between the descriptions
and the Program Addendum, the terms of the Program Addendum prevail.
2.3.2 Initial Application (IA)
The IA is a required submittal for all Projects and requires the following:
The identification of the host Oncor customer site(s) with ESI ID. This also
applies to new construction. The permanent ESI ID must be entered into the
system within four months of the meter being set for new construction to qualify.
A description of the proposed set of energy efficiency measures, demand and
energy savings, and incentive payment estimate.
A brief work plan presenting Project design, M&V approach, implementation, andanticipated Project timeline.
A signed IA Agreement.
A signed Host Customer Agreement and Service Provider Agreement
2013 Custom Commercial Standard Offer Program 15
7/30/2019 Oncor - Custom Commercial Standard Offer Program
19/70
Section 1 Chapter 2 Participation Process
A performance security deposit equal to 5% of the incentive estimate included
with the IA. The deposit is refundable for Projects provided they meet at least
80% of their IA dollar request in the Final Application and they meet 75% of their
contracted demand savings goal in the Savings Report within 60 days after the
completion date specified in the Program Addendum.
IAs will be reviewed on a first-come, first-served basis until all incentive funding hasbeen committed. Oncor reviews the IA for both participant and measure eligibility. If
an IA is accepted, Oncor reserves funds for the applicant, who is then referred to as
a Service Provider. Once notified of acceptance, the Service Provider proceeds to
develop a more detailed description of the Project. This information will be submitted
in the Final Application (FA) phase. A typical review cycle for an IA is 20 working
days. If the IA is rejected, the performance security deposit will be immediately
returned to the Service Provider.
2.3.3 Final Application (FA)
Service Providers must complete a FA to participate in the Program. This
application describes the proposed measures, Project sites, estimated demand and
energy savings, and estimated incentive payments based on a detailed engineering
study and site audit. The FA requires the following:
Detailed information about the host customer site(s) and customer contact
information.
The existing and proposed retrofit equipment inventories, including equipment
counts, equipment efficiencies, and equipment nameplate data.
Building occupancy and equipment operating schedules.
Engineering calculations estimating energy and demand savings based on the
efficiency of the proposed equipment compared to that of new, minimum-
standard efficiency equipment.
A proposed Project-specific M&V plan describing how the Service Provider will
measure and verify energy and demand savings, the methods for calculating
actual savings, and a schedule for conducting and reporting on M&V activities.In some cases, pre-installation M&V activities may be required to accurately
estimate savings.
A revised work plan for Project design, implementation, operation, and
management, including the anticipated Project timeline.
2013 Custom Commercial Standard Offer Program 16
7/30/2019 Oncor - Custom Commercial Standard Offer Program
20/70
Section 1 Chapter 2 Participation Process
As part of the FA review, which is up to a 45-day process, Oncor will review the
feasibility of the proposed measures, the accuracy of the savings estimates, and the
comprehensiveness of the M&V plan. Oncor may request clarification of, or additional
information about, any item in the FA. Service Providers will have 10 working days
to respond to such requests. If the clarification or additional information is not
forthcoming, Oncor may choose to discontinue its evaluation of the FA andretain the performance security deposit. Also, the FA must contain at least 80%
of the IA incentive or a portion of the deposit will be forfeited.
FA Incentive DollarsIF < 0.80 Then the amount forfeited at the FA is:
IA Incentive Dollars
FA Incentive Dollars1 *Deposit
IA Incentive Dollars
The FA must be submitted within 60 days of the date of the IA acceptance in order
to hold reserved funding. Failure to submit the FA by the 60-day deadline may
result in loss of reserved funding and forfeiture of the performance security
deposit. Service Providers who do not meet the 60-day deadline may resubmit an
IA with a new deposit for the same Project, subject to availability of funds or the
existence of a Project waitlist.
If FA incentive estimates differ from the incentive funds reserved in the IA, the FA
savings and incentive estimates will take precedence over the IA, as the FA shouldinclude a more detailed and accurate estimate of demand and energy savings.
Where FA estimates are lower than those approved in the IA, the reserved
incentives will be adjusted down accordingly, and excess incentive funds returned to
the remaining Program incentive budget. In some cases FA estimates may be
higher than approved in the IA. In cases where all incentive funds have been
reserved and Projects are waitlisted, the Project will be limited to the funds reserved
in the IA.
2.3.4 Deposit Forfeit
If the Final Application does not contain at least 80% of the Initial Application
incentive estimate, that percentage of the deposit will be forfeited; for example, if the
FA has only 70% of the IA kW then 30% of the deposit will be forfeited. Any and all
funds not forfeited here will be forfeited in the Savings Report if at least 75% of the
contracted kW is not verified in the Savings Report.
2013 Custom Commercial Standard Offer Program 17
7/30/2019 Oncor - Custom Commercial Standard Offer Program
21/70
Section 1 Chapter 2 Participation Process
2.3.5 Additional Deposit
If the incentive value of the Final Application exceeds the Initial Application by 20%
an additional deposit will be required to reserve the additional funds.
2.3.6 Pre-installation Inspection
In addition to the application review discussed above, Oncor may conduct a pre-
installation inspection of the Project site at its own discretion as part of the FA review
process. The purpose of the inspection is to verify the baseline conditions
documented in the application and the feasibility of installing the proposed
equipment. Oncor will contact the Service Provider and complete the inspection
after receipt of a complete FA. The pre-installation inspection requires the presence
of at least one Service Provider representative who is familiar with the Project and
the facility so that all parties can identify any discrepancies simultaneously. The
inspection will verify the following information:
The accuracy of the equipment survey. For most measures, the accuracy of the
equipment quantity and nameplate information is verified. For lighting measures,
the requirement for acceptance is that the total error of the installed demand of
the sample must be within 5% of the total demand submitted on the survey
form.
The M&V plan is appropriate for the measures, and the necessary M&V activities
are being performed.
All existing equipment listed in the FA is still in place and operational.
New equipment installation, or old equipment demolition, has not begun.
When electrical measurements are necessary, the representative(s) will be required
to perform any necessary disruptions in equipment operation, the opening of any
electrical connection boxes, or the connection of current and power transducers. If
the inspection cannot be completed in a timely manner because the
representative(s) is unfamiliar with the facility or Project, the Project site will fail the
inspection.
If a Project site fails an inspection, Oncor, at its discretion, may cancel the
Project, retain the performance security deposit, and release the reserved
incentive funds or conduct additional inspections at the Service Providers
expense. Payment of the cost for additional inspections is due with the
signed contract. If the proposed equipment has been installed before the pre-
2013 Custom Commercial Standard Offer Program 18
7/30/2019 Oncor - Custom Commercial Standard Offer Program
22/70
Section 1 Chapter 2 Participation Process
installation inspection and the baseline conditions cannot be verified, Oncor
may cancel the Project, retain the performance security deposit, and release
the reserved incentive funds.
2.3.7 Contract Addendum
Once the FA is approved the Service Provider will be required to sign a ContractAddendum stipulating expected demand and energy savings and the reserved
incentive for the Project as well as time required for completion of either the
Installation Notice or the Savings Report, depending on the makeup of the Project.
2.3.8 Installation Notice (IN)
After Project installation, Service Providers must submit an IN. The IN updates any
information proposed in the FA that has now been finalized after completion of the
Project. The IN typically includes the following information:
Updated information about the host customer site(s) and updated Service
Provider or customer contact information.
The demolished and installed retrofit equipment inventories, including equipment
counts, equipment efficiencies, and equipment nameplate data or other
documents required to establish the efficiency of the measures and/or Project.
Updated building occupancy and equipment operating schedules.
Updated engineering calculations estimating energy and demand savings based
on the efficiency of the actual installed equipment compared to that of new,
minimum-standard efficiency equipment.
A final Project-specific M&V plan describing how the Service Provider will
measure and verify energy and demand savings, the methods for calculating
actual savings, and a schedule for conducting and reporting on M&V activities.
A certification, signed by the Service Provider and Host Customer, verifying that
the energy efficiency measures described in the IN have been completed.
The IN is due based on meeting the dates the Service Provider provided in theContract Addendum.
A typical review cycle for an IN, including the post-installation inspection, is 30 days.
An approved IN will serve as the invoice for the first incentive paymentthe
installation payment. This payment is 40% of the incentive estimate approved in the
IN. The installation payment is typically made within 30 days following IN approval.
2013 Custom Commercial Standard Offer Program 19
7/30/2019 Oncor - Custom Commercial Standard Offer Program
23/70
Section 1 Chapter 2 Participation Process
2.3.9 Post-installation Inspection
Oncor will contact the Service Provider and conduct a post-installation inspection of
the Project site after receipt of a complete IN. The post-installation inspection
requires the presence of at least one Service Provider representative who is familiar
with the Project and the facility. The inspection shall verify that:
The equipment specified in the IA has been installed and is operating as
described in the approved IN. For most measures, the accuracy of the
equipment quantity and nameplate information is verified. For lighting measures,
the requirement for acceptance is that the total error of the installed demand of
the sample must be within 5% of the total demand submitted on the survey
form.
The M&V plan is being followed in accordance with the approved FA.
When electrical measurements are necessary, the Service Providers
representative(s) will be required to perform any necessary disruptions in equipment
operation, the opening of any electrical connection boxes, or the connection of
current and power transducers. If the inspection cannot be completed in a timely
manner because the Service Providers representative(s) is unfamiliar with the
facility or Project, the Project site will fail the inspection.
If a Project site fails an inspection, Oncor may, at its discretion, cancel the Project,
retain the performance security deposit, decline to make any payments to the
Service Provider and release the reserved incentive funds, or conduct additional
inspections at the Service Providers expense, due prior to the approval of the IN.
This inspection, however, does not constitute Oncors warranty that the work has
been done correctly and does not constitute an agreement to indemnify Service
Provider against any third-party claim.
2.3.10 Measurement and Verification (M&V)
In order for a Project to be accepted, a detailed savings estimate and a viable M&V
plan must be submitted. Service Providers are responsible for conducting all M&V
activities for the Project. However, Oncor will work with the Service Provider to
facilitate M&V planning as necessary and assist Service Providers in identifying
M&V options appropriate to their specific Project.
M&V procedures will vary in detail and rigor depending on the measures installed.
For each installed measure, the chosen procedures will depend upon the
predictability of equipment operation, the availability of evaluation data from previous
2013 Custom Commercial Standard Offer Program 20
7/30/2019 Oncor - Custom Commercial Standard Offer Program
24/70
Section 1 Chapter 2 Participation Process
Programs, and the benefits of the chosen M&V approach relative to its cost. Oncor
has developed recommended M&V guidelines for several common measures.
These procedures may be classified according to three distinct approaches that
represent increasing levels of detail and rigor:
Deemed (or stipulated) savings: Savings values are stipulated based on
engineering calculations using typical equipment characteristics and operating
schedules developed for particular applications, without on-site testing or
metering. This approach is designed for use with lighting efficiency and lighting
with controls Projects.
Simple M&V: Savings values are based on engineering calculations using
typical equipment characteristics and operating schedules developed for
particular applications, with some short-term testing or simple long-term
metering. For example, chiller energy and demand savings can be determined
using the simple approach by comparing rated efficiencies of high-efficiency
equipment to standard equipment and using kW spot-metering and simple long-
term kWh metering.
Full M&V: Savings are estimated using a more detailed method than in the
deemed savings or simple M&V approaches through the application of metering,
billing or regression analysis, or computer simulation. These methods will need
to be developed in accordance with the 2012 International Performance
Measurement and Verification Protocol (IPMVP), which represents the starting
point for standard industry practice. More information about the IPMVP may be
found on the Internet at www.ipmvp.org. An application of the IPMVP adapted
for use with this Program is presented as part of this Program Manual and is
available on the Program website.
The time required to complete M&V activities will range from less than a month to 12
months, depending on the approach chosen. Table 2.1 summarizes the available
M&V guidelines in this Program Manual for common measures.
Table 2.1: M&V approaches and guidelines
M&V Energy Efficiency M&V ApproachGuideline Measure
1 Lighting efficiency Deemed or Simple (depending onbuilding type)
2 Lighting efficiency and Deemed or Simple (depending oncontrols building type)
3 Cooling equipment retrofits Deemed, Simple, or Full (depending onapplication)
2013 Custom Commercial Standard Offer Program 21
http://www.ipmvp.org/http://www.ipmvp.org/http://www.ipmvp.org/7/30/2019 Oncor - Custom Commercial Standard Offer Program
25/70
Section 1 Chapter 2 Participation Process
4 Motor retrofit s Simple or Full (depending onapplication)
5 ENERGY STAR Roofs Deemed
6 Air Compressors Simple or Full (depending onapplication)
7 Thermal Storage Full
8 Bio Mass Full
9 Controls Deemed, Simple, or Full (depending onapplication)
10 Solar Water Heating Full
11 Injection Molding Simple, or Full (depending onapplication)
12 Wind Generation Full
13 Other Simple, or Full (depending onapplication)
14 Data Center Virtualization Deemed, Simple, or Full (depending onapplication)
15 Data Center UPS Simple, or Full (depending onapplication)
16 Variable Frequency Drives Deemedfor Variable Air Volume
Air Handlers
2.3.11 Savings Report (SR)
After all M&V activities are complete, the Service Provider will submit aSR documenting the Projects measured and verified demand and energy savings.
An approved SR will serve as the invoice for the final incentive paymentthe
performance payment. This payment is based on the Projects verified savings
minus the amount paid in the installation payment. The total incentive payment
(installation payment plus performance payment) cannot exceed the incentive
payment stated in the FA. The performance payment is typically made within
30 days following SR approval. After the SR is approved, the remaining
performance security deposit (funds not forfeited in the FA stage) shall be
refunded provided that 75% of the contract demand savings (kW) goal was metwithin the required deadline and the Service Provider has complied with Program
requirements.
For Projects eligible to use deemed savings M&V the full incentive payment will be
made after IN approval and a correct signed SR has been received.
2013 Custom Commercial Standard Offer Program 22
7/30/2019 Oncor - Custom Commercial Standard Offer Program
26/70
Section 1 Chapter 2 Participation Process
2.3.12 Submittals
Oncor must receive both an electronic version and a hard copy version of
all required submittals. Electronic application submittals will be performed through
Oncors interactive submittal process on the EEPM Solution at:
https://www.oncoreepm.com/commprogram.aspx
Some portions of the applications, including lighting and motor equipment inventory
forms and supporting information such as savings calculations, analysis files,
and raw meter data, will be uploaded into the online application. Oncor must
receive hard copies and the performance security deposit within 10 business days
of receipt of the electronic submittal. Hard copies should include all application
materials, excluding lengthy support documents such as equipment inventories,
savings calculations, and raw collected data. Table 2.2 summarizes the addresses
for application submittals.
Table 2.2: Addresses for electronic and hard copysubmittals
Submittal type Mechanism Address or location
Electronic Applications Interactive website https://www.oncoreepm.com
Supporting Documents
(inventory forms, raw data)Interactive website https://www.oncoreepm.com
Hard Copies and
Performance Security
Deposit
(excluding lengthy support
documents)
U.S. mail or ground
courier
Mr. J ohn Hanel or Mr. Ron Haskovec
Oncor
1616 Woodall Rodgers Frwy
Suite 5M-024 or 5M-021
Dallas, TX 75201
2.4 CONTRACTUAL PROVISIONS
Service Provider acknowledges that it received this Program Manual prior to
submission of any IA. Service Provider warrants and represents that its
participation in the Program has at all times been in material compliance with the
2013 Custom Commercial Standard Offer Program 23
http://www.oncoreepm.com/commprogram.aspxhttp://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/commprogram.aspx7/30/2019 Oncor - Custom Commercial Standard Offer Program
27/70
Section 1 Chapter 2 Participation Process
procedures and conditions set forth in this Program Manual and that any failure to
comply therewith may be treated as a breach of the Umbrella Agreement
notwithstanding the fact that such failure occurred prior to the execution of the
Program Addendum. Service Provider also acknowledges that it meets or exceeds
all of the qualifications required to participate in the Program as described in this
Program Manual and that material failure to meet the qualifications therein may betreated as a breach of the Umbrella Agreement.
Service Provider warrants and represents it and its affiliates have not requested
Program funds totaling more than an aggregate amount of 20% of the Program
budget and that the Affiliate Affidavit is true and correct.
2.4.1 Acknowledgement of Program Requirements
By executing the Program Addendum, the Service Provider warrants and represents
that it is aware of and complies with all of the provisions of the Umbrella
Agreement, any Program Addendum to the Umbrella Agreement, this Manual, any
Contract Addendums, and any amendments or supplements to such documents
(collectively, the Contract Documents). The Service Provider also warrants and
represents that it meets or exceeds all of the following qualifications required by
Oncor for participation in the Program:
Possesses and can demonstrate experience in implementing similar
projects;
Can produce evidence of a good credit rating, unless self-sponsoring;
Can produce evidence of financial strength and capability through financial
statements, unless self-sponsoring;
Can produce evidence of possession of all applicable licenses required
under state law and local building codes;
Can produce evidence of possession of all building permits required by
governing jurisdictions;
Has produced the proof of insurance required by Section 2.4.3 of thisChapter 2 of this Program Manual, unless self-sponsoring.
Warrants and represents that each Project meets all applicable federal,
state, and local laws and regulatory requirements, and also warrants and
represents as follows:
2013 Custom Commercial Standard Offer Program 24
7/30/2019 Oncor - Custom Commercial Standard Offer Program
28/70
Section 1 Chapter 2 Participation Process
Each Project will result in a reduction in energy consumption and/or peak
demand, and a reduction in energy and/or demand costs for the end-use
customer.
Each Project will result in consistent and predictable energy or peak
demand savings over the Expected Useful Life (EUL).
Each Project application will disclose all potential adverse environmental
or health effects associated with the energy efficiency measures to be
installed, if any.
Each Project includes appropriate and adequate measurement,
verification, and reporting procedures.
Each Project does not achieve demand reduction by eliminating an
existing function or shutting down a facility or operation, or result inbuilding vacancies or the relocation of existing operations to locations
outside of the facility or area served by Oncor.
Measures installed pursuant to each Project would not have been installed
if not for the Project or would have been installed later and/or with a lower
efficiency.
Each Project does not result in negative environmental or health effects,
including effects that result from improper disposal of equipment and
materials.
Each Project does not involve the installation of self-generation or
cogeneration equipment but may involve renewable DSM technologies.
2.4.2 Audits and Records
Contractor shall maintain its books in accordance with generally acceptable
accounting principles and all other records related to its performance under this
Agreement. For three (3) years following payment of the final invoice, Company will
have the right to examine, reproduce, and audit these books and records, at anyreasonable time, to the extent company deems necessary to verify the accuracy and
reasonableness of invoices, contractors performance of the Work or contactors
compliance with this Agreement. In the event a company audit discloses a
discrepancy between invoices and the books and records, contractor agrees to
promptly refund any overpayment by company.
2013 Custom Commercial Standard Offer Program 25
7/30/2019 Oncor - Custom Commercial Standard Offer Program
29/70
Section 1 Chapter 2 Participation Process
2.4.3 Insurance
See the Insurance requirements in the Technical Resource Manual.
2.4.4 Amendment and Termination
Oncor may terminate any or all CCSOP Program Addendums or Umbrella Agreement in
whole or in part, at any time, at its sole discretion, by providing written notice of termination
to Service Provider. The notice of termination will specify the effective date of any
termination, and that the CCSOP Program Addendum or Umbrella Agreement is terminated
in its entirety. Termination may result from unacceptable performance, either during current
or past CCSOP Programs. Please review the CCSOP Program Addendum and Umbrella
Agreement for additional details.
Service Provider will finish any Project already commenced which cannot be discontinued
without breaching the Host Customer Agreement. Oncor will have no obligations with
respect to any contractual obligations entered into between Host Customer and Service
Provider after Service Providers receipt of Oncors notice of termination.
In the event a Standard Offer Program is terminated, Oncor's only liability will be to pay
Service Provider the unpaid balance due Service Provider for that portion of the Project
already commenced and which cannot be discontinued without breaching the Host Customer
Agreement.
Oncor may, in its sole discretion, refuse to allow a Service Provider to participate in the
Custom Commercial Standard Offer Program for any reason, including based on prior
Program participation or participation in other programs.
2.4.5 Force Majeure
Should either Party be rendered unable, either wholly or in part, by an event of Force
Majeure, to fulfill its obligations under the Umbrella Agreement (including the
Program Addendum), this Program Manual or any other Contract Document, the
obligation of the Party so rendered, that is affected by the event of Force Majeure,
will be suspended only during the continuance of that inability. The Party so
affected will give written notice of the existence, extent, and nature of the Force
Majeure to the other Party within forty-eight (48) hours after the occurrence of theevent. The Party so affected will use its best efforts to remedy its inability as soon as
possible and will provide the other Party with prompt notice when it is able to resume
the performance of its obligations. Failure to give notice will result in the continuance
of the affected Party's obligation regardless of the extent of any existing Force
Majeure.
2013 Custom Commercial Standard Offer Program 26
7/30/2019 Oncor - Custom Commercial Standard Offer Program
30/70
Section 1 Chapter 2 Participation Process
The term "Force Majeure" as used in this Agreement will mean acts of God (except
as excluded herein), strikes, lockouts, or other commercial disturbances, acts of
public enemies, terrorists, wars, blockades, insurrections, riots, epidemics,
earthquakes, fires, priority allocations of pipe or other materials or orders, restraints
or prohibitions by any court, board, department, commission, or agency of the United
States or of any state, any arrests and restraints, civil disturbances, explosions, andinability despite reasonable diligence to obtain materials essential to this Agreement.
Rain, snow, ice, or other adverse weather conditions will not be considered events of
Force Majeure.
The term Force Majeure does not include: events or circumstances that affect the
costs of installing the measures but do not prevent performance, including, but not
limited to, requirements, actions, or failures to act on the part of governmental
authorities (including the adoption or change in any rule, regulation, or
environmental constraint lawfully imposed by federal, state, or local governmental
bodies); changes in market conditions; and events or conditions attributable tonormal wear and tear or flaws randomly experienced in materials and equipment
and their assembly and operation, unless such events and conditions are caused by
an occurrence which would fit the definition of Force Majeure.
In no event will any Force Majeure extend this Agreement beyond its stated term.
2.4.6 Independent Contractor
Service Provider will act as and be deemed to be an independent contractor. Service
Provider will not act as, nor be deemed to be, an agent or employee of Oncor.
Service Provider will have the sole right to control and directly supervise the method,
manner, and details of the Project, providing it is in accordance with the Contract
Documents.
2.4.7 Indemnity
Service Provider will indemnify Oncor against certain damage or losses resulting
from Service Providers participation in the Program. Please see the Umbrella
Agreement for additional detail regarding Service Providers indemnity obligations.
2.4.8 Miscellaneous
The Service Provider will not assign, transfer, or otherwise dispose of any of its
obligations or duties without the prior written approval of Oncor. Any assignment or
transfer made without the express written approval of Oncor will be null and void.2013 Custom Commercial Standard Offer Program 27
7/30/2019 Oncor - Custom Commercial Standard Offer Program
31/70
Section 1 Chapter 2 Participation Process
The rights and remedies provided by this Program Manual and the Umbrella
Agreement are cumulative and the use of any one right or remedy by either Partyshall not preclude or waive its right to use any or all remedies. Said rights andremedies are given in addition to any other rights the Parties may have by law,statute, ordinance, or otherwise. No waiver by the Parties hereto of any default orbreach of any term, condition, or covenant of the Contract Documents shall be
deemed to be a waiver of any other breach of the same or any other term, condition,or covenant contained herein.
The Contract Documents constitute the entire agreement between the Parties with
respect to the subject matter hereof, and there are no express or implied warranties
or representations upon which any Party may rely beyond those set forth therein.
The execution of the Umbrella Agreement and any Program Addendum supersedes
all previous agreements, discussions, communications, and correspondence with
respect to such documents respective subject matter.
In the event any provision of the Contract Documents is held to be void, unlawful, or
otherwise unenforceable, that provision will be severed from the remainder of the
Agreement and replaced automatically by a provision containing terms as nearly like
the void, unlawful, or unenforceable provision as possible; and the Contract
Documents, as so modified, will continue to be in full force and effect.
The Contract Documents will be governed by, construed, and enforced in
accordance with the laws of the state of Texas. The Parties agree that the proper
venue and jurisdiction for any cause of action not within the jurisdiction of the Public
Utility Commission of Texas relating to the Agreement will be in Tarrant County,
Texas.
Service Provider shall not use Oncors corporate name, trademark, trade name,
logo, identity, or any affiliation to solicit Customers for participation in the Project,
without Oncors prior written consent. Use of Oncors name in the Customer and
Service Provider Agreement and Customer Certificate as required by this Agreement
does not constitute solicitation of Customers.
2.5 ADDITIONAL INFORMATION
2.5.1 Confidentiality
The Program is subject to oversight by the Public Utility Commission of Texas
(PUCT). The PUCT may request a copy of any Program materials that Oncor
receives. Sensitive company and Project information submitted by the Service
2013 Custom Commercial Standard Offer Program 28
7/30/2019 Oncor - Custom Commercial Standard Offer Program
32/70
Section 1 Chapter 2 Participation Process
Provider to Oncor, such as financial statements, will be treated confidentially to the
fullest extent possible and will not be provided directly to outside parties other than
the PUCT. Oncor will have no liability to any Service Provider or other party as a
result of public disclosure of any information submitted by the Service Provider in
connection with the Program.
2.5.2 Participation Costs
Oncor will not reimburse any Service Provider for any costs incurred by participating
in the Program, including any costs related to preparing any application or submittal
or reviewing the Program Addendum.
2.5.3 Submission of False Information
Oncor reserves the right to discontinue its evaluation of all submittals and retain theperformance security deposit from any Service Provider that submits false,
misleading, or incorrect information. This will include the changing of any shaded
areas in the inventory forms that will affect the savings and/or incentive calculations.
2.5.4 Program Website
The Program website at https://www.oncoreepm.com/commprogram.aspx will serve
as the primary source for all updated Program information and materials. The
website will include:
Information describing the Program design and requirements.
Contact information to receive more information about the Program.
Status updates on Program funding available and committed.
Interactive submittal forms and tools.
Downloadable Program procedures, M&V guidelines, and submittal forms.
2.5.5 Program Promotion and Outreach
Oncor will conduct outreach for this Program by providing complete Program
information and application materials and instructions on the Internet at
https://www.oncoreepm.com/commprogram.aspx. Oncor will also conduct workshops
with potential Program participants to explain the Program parameters, rules, and
procedures.
2013 Custom Commercial Standard Offer Program 29
http://www.oncoreepm.com/commprogram.aspxhttp://www.oncoreepm.com/commprogram.aspxhttp://www.oncoreepm.com/commprogram.aspxhttp://www.oncoreepm.com/commprogram.aspxhttp://www.oncoreepm.com/commprogram.aspx7/30/2019 Oncor - Custom Commercial Standard Offer Program
33/70
Section 1 Chapter 2 Participation Process
2.5.6 Seminars for Service Providers
Oncor may choose to sponsor procedural and M&V seminars for Service Providers
to help them comply with Program requirements. Seminars may include subjects
such as using the interactive submittal tools, completing equipment inventories,
proper use of deemed savings, lighting M&V, and other simplified M&V approaches.These seminars are an opportunity to train several participants at once and help
both Oncor and the Service Providers make more efficient use of time and
administrative budgets.
2013 Custom Commercial Standard Offer Program 30
7/30/2019 Oncor - Custom Commercial Standard Offer Program
34/70
CUSTOM COMMERCIALSTANDARD OFFER PROGRAM
SECTION 2 OF 5ENROLLMENT PROCESS
2013 Program Manual and Contract Documents
November 2012
7/30/2019 Oncor - Custom Commercial Standard Offer Program
35/70
Table of Contents1 CCSOP 1 INITIAL APPLICATION (IA) .................................................................................... 31
1.1 OVERVIEW ..................................................................................................................... 311.2 SERVICE PROVIDER SIGNUP ...................................................................................... 311.3 SECTIONS OF THE INITIAL APPLICATION.................................................................. 32
1.3.1 SERVICE PROVIDER INFORMATION .......................................................... 321.3.2 CUSTOMER INFORMATION ......................................................................... 331.3.3 PROJECT INFORMATION ..................................................... ........................ 331.3.4 PERFORMANCE SECURITY DEPOSIT ........................................................ 331.3.5 CONDITIONS.................................................................................................. 34
1.4 SUBMITTING THE INITIAL APPLICATION .................................................................... 341.4.1 ELECTRONIC SUBMITTAL.......................................... .................................. 341.4.2 HARD COPY SUBMITTAL.............................................................................. 34
2 CCSOP 2 FINAL APPLICATION (FA) .................................................................................. 352.1 OVERVIEW ..................................................................................................................... 352.2 SECTIONS OF THE FINAL APPLICATION.................................................................... 35
2.2.1 PROJECT SUMMARY .................................................................................... 352.2.2 PROJECT SAVINGS ESTIMATES ................................................................. 36
2.2.3 PROPOSED MEASUREMENT AND VERIFICATION PLAN ......................... 362.2.4 SITE PROFILES ............................................................................................. 372.2.5 HOST CUSTOMER AGREEMENT..... ............................................................ 372.2.6 EQUIPMENT INVENTORY FORMS............................................................... 372.2.7 CONDITIONS.................................................................................................. 38
2.3 SUBMITTING THE FINAL APPLICATION ...................................................................... 392.3.1 ELECTRONIC SUBMITTAL.......................................... ................ .................. 392.3.2 HARD COPY SUBMITTAL.......... .................................................................... 39
3 CCSOP 3 CONTRACT TERMS............................................................................................. 40
4 CCSOP 4 INSTALLATION NOTICE (IN) .............................................................................. 414.1 OVERVIEW ....................................................................................................................... 414.2 SECTIONS OF THE INSTALLATION NOTICE ................................................................ 41
4.2.1 PROJECT SUMMARY ......................................................................................... 414.2.2 UPDATED PROJECT SAVINGS ESTIMATES .................................................... 414.2.3 FINAL MEASUREMENT AND VERIFICATION PLAN...... ................................... 424.2.4 UPDATED CUSTOMER SITE PROFILES........................................................... 424.2.5 CUSTOMER CERTIFICATION ............................................................................ 424.2.6 UPDATED EQUIPMENT INVENTORY FORMS.................................................. 424.2.7 CONDITIONS .......................... ............................................................................. 42
4.3 SUBMITTING THE INSTALLATION NOTICE ................................................................. 434.3.1 ELECTRONIC SUBMITTAL ................................................................................. 434.3.2 HARD COPY SUBMITTAL.............................................................................. ..... 43
5 CCSOP 5 SAVINGS REPORT (SR)) ....................................... ............................................. 445.1 OVERVIEW ...................................................................................................................... 445.2 SECTIONS OF THE SAVINGS REPORT ....................................................................... 44
5.2.1 PROJECT/SERVICE PROVIDER INFORMATION.............................................. 445.2.2 VERIFIED PROJECT SAVINGS .......................................................................... 445.2.3 SUPPORTING DATA AND CALCULATIONS...................................................... 445.2.4 SERVICE PROVIDER SIGNATURE.................................................................... 45
5.3 SUBMITTING THE SAVINGS REPORT ......................................................................... 455.3.1 ELECTRONIC SUBMITTAL ................................................................................ 455.3.2 HARD COPY SUBMITTAL.................................................................................. 45
6 CCSOP 6 APPENDIX ............................................................................................................... 46APPENDIX A................................................................................................................................ IAPPENDIX B.............................................................................................................................. IIIAPPENDIX C.............................................................................................................................. VAPPENDIX D...........................................................................................................................VIII
2013 Custom Commercial Standard Offer Program
7/30/2019 Oncor - Custom Commercial Standard Offer Program
36/70
APPENDIX E.............................................................................................................................. X
This section includes descriptions and samples of enrollment materials developed by Oncorfor participants in the 2013 Custom Commercial Standard Offer Program.
The enrollment forms included in this section are examples and may vary from the
interactive versions found on the Program website at https://www.oncoreepm.com. With theexception of some equipment inventories, all of the basic enrollment and applicationmaterials are completed online using the interactive tools located on the Program website.
2013 Custom Commercial Standard Offer Program
http://www.oncoreepm.com/http://www.oncoreepm.com/7/30/2019 Oncor - Custom Commercial Standard Offer Program
37/70
Section 2 - Chapter 1 - Initial Application (IA)
CCSOP 1 INITIAL APPLICATION (IA)
1.1 OVERVIEW
A Service Providers first formal step, after completing the Energy Efficiency ProgramManagement EEPM Solution signup, for participating in the Oncor Custom CommercialStandard Offer Program is the submission of a Program Addendum (ProgramAddendum) to the Amended and Restated Texas Energy Efficiency Market Agreement(Umbrella Agreement), as well as an Initial Application (IA) for each Project toOncor. The Program Addendum is required to be submitted only once, which will beupon the Service Providers initial participation in the Program. By submittingthe IA, the applicant is requesting that Oncor review the IA and, if it is approved,reserve funding for the Service Provider.
IAs will be reviewed on a first-come, first-served basis until all incentive funding has
been committed. Oncor reviews the IA for both participant and Project eligibility. Oncormay reject an IA for any reason in its sole discretion. If an IA is accepted, Oncorreserves funds for the applicant, who is then referred to as a Service Provider. Oncenotified of acceptance, the Service Provider proceeds to develop a more detaileddescription of the Project. This detailed description will be submitted in the FinalApplication (FA) phase. A typical review cycle for an IA is 20 working days.
The IA includes several sections to be filled out by the Service Provider. Theinformation required in these sections should be submitted to Oncor in both electronicand hard copy.
1.2 SERVICE PROVIDER SIGNUPThe Service Provider signs up online by providing basic contact information athttps://www.oncoreepm.com. Also, the following must be provided:
Description of the Service Provider firm, including relevant experience, areas ofexpertise, and total number of employees. Description must include references andmay also include customer affidavits or other evidence of Service Provider'scompetency from previous Projects.
Basic description of the relevant experience of the Project team members who willbe responsible for the design, installation, operation, and maintenance of the
Project. This may consist of resumes and should demonstrate the Service Providerteams expertise and technical depth.
The Service Providers Taxpayer Identification Number so that Oncor can properlyaccount for any incentive payments to the Service Provider in the future.
For customers that self-sponsor their Project, the following will be required:
The Service Providers Taxpayer Identification Number so that Oncor canproperly account for any incentive payments to the Service Provider in the future.
2013 Custom Commercial Standard Offer Program 31
http://www.oncoreepm.com/http://www.oncoreepm.com/7/30/2019 Oncor - Custom Commercial Standard Offer Program
38/70
Section 2 - Chapter 1 - Initial Application (IA)
1.3 SECTIONS OF THE INITIAL APPLICATION
The IA is composed of the following sections:
Service Provider Information
Customer Information
Project Information
Performance Security Deposit
IA Agreement
The information required in each section is described further below. Hard copies anddeposit are required within 10 working days of the online electronic submission.
1.3.1 SERVICE PROVIDER INFORMATION
This section includes information that the Service Provider should submit to Oncoralong with its first IA. The information is required of all Service Providers and need only
be submitted once. All subsequent IAs submitted under the Program may simply referto the information submitted in the first IA, unless there has been a material change inthe information. Information in this section will be submitted in hard copy only andincludes the following:
Evidence that Service Provider and subcontractors possess all applicable licensesand permits.
A brief management plan that covers the design, implementation, and operation ofthe Project. The plan should include key staff, expected management lines ofauthority and responsibility, expected staffing levels, and utilization ofsubcontractors.
2013 Custom Commercial Standard Offer Program 32
7/30/2019 Oncor - Custom Commercial Standard Offer Program
39/70
Section 2 - Chapter 1 - Initial Application (IA)
1.3.2 CUSTOMER INFORMATION
This section requests information about the Service Providers customers and theProject sites at which the Service Provider proposes to perform work to receiveincentives from Oncor. If the Project involves multiple sites and if exact information
about each customer site is known at the time the IA is submitted, Service Providersshould complete a separate Customer Site Information table for each site. If customerinformation is not yet known, the Service Provider should include as much informationas possible about the expected number of customer sites and a general description ofthe types of sites anticipated to be included in the Project. The type of informationrequested may include the following:
Customer company name
Site address
Site contact name, phone number, and fax number
Building type, operating schedule, and floor area Cooling system description
Oncor Distribution account number (ESIID). (An example of an ESI ID is10443720001234567. In the example, 44372 must be the third thru seventhdigits. 17699 is also eligible. The last seven digits are then reportable.)
This information will be submitted through both the online application and in hard copy.
1.3.3 PROJECT INFORMATION
This section requests basic information about the scope of the proposed Project. The
type of information requested includes the following:
Basic description of the Project.
List of proposed energy efficiency measures.
Expected demand and energy savings.
Preliminary savings calculations, including assumptions and formulas, to support theamount of incentive payment requested from Oncor.
Documentation as to the capital cost of the Project.
Additional supporting documentation as necessary.
This information will be submitted both through the online application and in hard copy.Any information needed to support the Project description and savings calculations(e.g., analysis spreadsheets) may be submitted with the hard copy of the IA and alsoelectronically atwww.oncoreepm.com.
1.3.4 PERFORMANCE SECURITY DEPOSIT
2013 Custom Commercial Standard Offer Program 33
http://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/http://www.oncoreepm.com/7/30/2019 Oncor - Custom Commercial Standard Offer Program
40/70
Section 2 - Chapter 1 - Initial Application (IA)
A performance security deposit must be included as part of the hard copy submittal ofthe IA. Deposits are equal to 5% of the incentive estimate requested in the IA. Thedeposit is generally refundable for Projects that meet at least 80% of their InitialApplication in the contract and 75% of their contracted kW savings goal by the requireddeadline in the Savings Report. The deposit must be provided by the Service Providerand not the end-use customer. The Service Provider will forfeit the deposit if it withdrawsthe IA after it has been reviewed and approved by Oncor. Also, an additional depositmay be required if the Final Application incentive exceeds the IA by 20%.
1.3.5 CONDITIONS
Service Provider agrees and understands that the incentive funds estimated in theService Providers IA are not reserved until Oncor has received from the ServiceProvider all information related to the IA that is required under the Program guidelinesand Oncor has approved the IA.
Service Provider agrees that it will forfeit, and Oncor will retain, the performancesecurity deposit if the Service Provider withdraws the IA after it has been approved by
Oncor. Service Provider agrees that if it does not submit a complete FA within 60 daysafter Oncors approval of the IA, then Oncor may, in its sole discretion, cancel the IA,retain the performance security deposit, and release the incentive funds reserved for theapplicable Project.
1.4 SUBMITTING THE INITIAL APPLICATION
1.4.1 ELECTRONIC SUBMITTAL
Electronic submittal of IAs will be performed through Oncors interactive online submittalforms.
1.4.2 HARD COPY SUBMITTAL
Oncor must receive hard copies and performance security deposits within 10 businessdays after receipt of the electronic submittal of the IA. Hard copies should include allapplication materials excluding lengthy support documents. Hard copy submittalsshould be mailed to the following address:
Oncor 2013 Custom Commerc ial SOP1616 Woodall Rodgers Suite 5M-024
Dallas, TX 75202Attn: J ohn Hanel/Ron Haskovec
Performance security deposit checks accompanying the IA submittal should be madeout to Oncor.
2013 Custom Commercial Standard Offer Program 34
7/30/2019 Oncor - Custom Commercial Standard Offer Program
41/70
Section 2 Chapter 2 Final Application (FA)
CCSOP 2 FINAL APPLICATION (FA)
2.1 OVERVIEW
The Service Provider is required to submit a Final Application (FA) within 60 days after
the date Oncor approves the IA in order to participate in the Program. In the FA, theService Provider provides a more detailed description of the proposed Project, includingmore precise descriptions of the Projects energy efficiency measures, customer sites,and expected energy savings. In addition, the Service Provider is required to submit ameasurement and verification (M&V) plan for the Project if deemed savings are notused on all measures. The following sections provide guidance on the completion ofthe FA.
No construction on the measures included in the FA may begin until the FA has beenreviewed and approved by Oncor, including on-site inspections of old equipment. If thebaseline equipment affected by the Project is removed before Oncor has approved theProject, the FA will be rejected.
The FA review typically takes up to 30 days. Once the FA for a Project has beenapproved by Oncor, Service Provider agrees to use all reasonable efforts to implementthe Project without undue delay and otherwise in accordance with the terms of theContract Documents. Measures shall be designed, constructed, and installed in a goodand workmanlike manner only with materials and equipment of appropriate quality, and,in any event, in accordance with Prudent Electrical Practices.
2.2 SECTIONS OF THE FINAL APPLICATION
The FA is composed of the following sections:
Project Summary
Project Savings Estimates
Proposed M&V Plan
Site Profiles
Host Customer Agreement
Equipment Inventory Forms
The information required in each section is described further below.
2.2.1 PROJECT SUMMARY
This section requires information concerning the Service Provider. It also includes asummary of the proposed energy efficiency measures, installation start and completiondates, and any additional information necessary to help describe the scope of theProject. This information will be generated from the information in the online applicationand will be submitted online and in hard copy. A separate document may be requiredfor the full Project description.
2013 Custom Commercial Standard Offer Program 35
7/30/2019 Oncor - Custom Commercial Standard Offer Program
42/70
Section 2 Chapter 2 Final Application (FA)
2.2.2 PROJECT SAVINGS ESTIMATES
This section requests revised savings estimates from the IA. The savings estimatesmust be substantiated with a list of methods, assumptions, or formulas used to derivethe demand and energy savings of each measure. Service Provider must provideelectronic and hard copy output of savings calculations, or any computer simulations or
analysis used to estimate savings. Savings calculations should be consistent with theM&V approach planned for the measure and follow the procedures outlined below.
This information will be generated from the information in the online application and willbe submitted online and in hard copy. Any information used to support the Projectsavings calculations (e.g., analysis spreadsheets and simulation files) must besubmitted with the hard copy of the FA and also electronically athttps://www.oncoreepm.com.
2.2.3 PROPOSED MEASUREMENT AND VERIFICATION PLAN
This section requires a detailed description of the proposed M&V plan to be used for the
Project. In general, it is recommended that the Service Provider use the M&VGuidelines described in Section 3 or 4 of this Program Manual, as applicable. However,the Service Provider may elect to develop an alternative approach. The alternativemust be described in detail, and is subject to the approval of Oncor. In general, theM&V plan should address the following items:
1. Project Site: Describe the Project site and the Project. Include information on howthe Project saves energy and demand and what key variables affect the savings.
2. M&V Approach: Describe the M&V approach to be used (Oncor guidelines may beused or the Service Provider may define it