Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Jun. 2014 Till Now.
Client : SIEMENS
Owner : First Natagaz Power Corporation Client – Owner
Company : NEM Energy Egypt.
Project : San Gabriel Power Planet Project
------------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Mar. 2014 Till Now.
Client : SIEMENS
Owner : Saudi Aramco Client – Owner
Company : NEM Energy Egypt.
Project : Jazan Power Island Project
------------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Jan. 2014 Up to Mar. 2014
Client : SIEMENS
Owner : PT. Pelayanan Listrik Nasional Batam Client – Owner
Company : NEM Energy Egypt.
Project : Tanjung Uncang CCPP 120MW Project
------------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Des. 2013 Up to Jan. 2014
Client : SIEMENS
Owner : Alinta Energy Client – Owner
Company : NEM Energy Egypt.
Project : Pinjarra Project
------------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Sep. 2013 Up to Nov. 2013
Client : SIEMENS
Owner : Panda Energy International Client – Owner
Company : NEM Energy Egypt.
Project : Temple II Power Planets
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Mar. 2013 Up to Nov. 2013
Client : SIEMENS
Owner : ENARSA, Energia Argentina S.A. Client – Owner
Company : NEM Energy Egypt.
Project : Brigadier Lopez and Ensenada de Barragan Power Planets
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Oct. 2012 Up to Sep 2013.
Client : SIEMENS
Owner : Panda Energy International Client – Owner
Company : NEM Energy Egypt.
Project : Temple & Sherman Power Planets
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : QA/QC Document Coordinator – System Administrator Company
Inclusive Dates : Aug. 2012 Up to Sep. 2013
Client : SIEMENS
Owner : Saudi Electricity Company Client – Owner
Company : NEM Energy Egypt.
Project : PP10 CCGT Power Planet
----------------------------------------------------------------------------------------------------------------------------------------------------------
I’m Join the Team for Preparing the QC Manual to meet the applicable requirements of the ASME Boiler and Pressure Vessels Code Section I, ASME B31.1, in addition to the client "contractor" requirement for Manufacture and Field assembly of Power Boilers parts and Pressure piping to be stamped with "S", "PP", "R" and "U" Stamp.
Position : Document Control Coordinator (DCC)
ASME [S] Stamp: of Manufacturing and Assembly Power Boilers.
ASME [PP] Stamp: of Manufacturing and Assembly Pressure Piping.
ASME [R] Stamp: of Repair and Alteration.
ASME [U] Stamp: of Manufacturing and Assembly Pressure Vessels. ----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : July. 2012 Up to Aug. 2012
Client : DEAGREMONT SA.
Owner : Ministry of Housing, Utilities & Urban Development EGYPT Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : EAST WASTEWATER TREATMENT PLANT (EWTP) – Scope: Fabric. & Erec.
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : May. 2012 Up to July. 2012
Client : International Oil Services ( IOS )
Owner : Halliburton Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Silo Tank (3 Units) – Scope: Fabrication
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Apr. 2012 Up to May. 2012
Client : International Oil Services ( IOS )
Owner : Halliburton Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Liquid Tanks ( 6 Units ) Scope: Fabrication
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Mar. 2012 Up to Apr. 2012
Client & Owner : Solvay International Chemical Group
Company : Project Services Company (Amreia Fabrication Workshop) Client
& Owner Project : Maintenance Of SHAHRAZAD Project
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Jan. 2012 Up to Mar.2012
Client : International Oil Services ( IOS )
Owner : Halliburton Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Liquid Tanks ( 6 Units ) & Cutting Boxes ( 65 Box )
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Oct. 2011 Up to Nov. 2011
Client : PWT
Owner : Kafr El-Dawar Power Station Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Kafr El-Dawar Power Station ( Tank )
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Jul. 2011 Up to Sep.2011
Client : International Oil Services ( IOS )
Owner : Halliburton Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Silo Tank (2 Units)
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Jun. 2011 Until Now
Client : Egyptian Maintenance Company (EMC)
Owner : Egyptian LNG (ELNG) Client - Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : West Heat Recovery Unit ( WHRU )
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : May. 2011 Up to Jun.2011
Client : International Oil Services ( IOS )
Owner : Halliburton Client – Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Silo Tank (3 Units)
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Mar. 2010 Up to Apr.2011
Client : DSD Ferrometalco.
Owner : ANSALDO CALDAIE S.p.A. Client - Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : Abu Qir Thermal Power Plant
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Jan. 2010 up to Feb. 2010
Client : DEAGREMONT SA.
Owner : Ministry of Housing, Utilities & Urban Development EGYPT Client - Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : EAST WASTEWATER TREATMENT PLANT (EWTP)
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Planning & Progress Follow up (Planning Dept.) Company
Inclusive Dates : Nov. 2009 up Des. 2009
Client & Owner : ASF - Arab Steel Fabrication Company.
Client - Owner
Company : Project Services Company (Amreia Fabrication Workshop)
Project : EL SEWEDY Cement – Scope: Fabrication
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Document Control Coordinator (DCC) Company
Inclusive Dates : Feb. 2009 up to Oct 2009
Client : NEM B.V.
Owner : PGESCO. Client - Owner
Company : Al- HASHEMIAH Contracting Company (Amreia Fabrication Workshop)
Project : Sidi-Krir & El-Atf Power Plant (750 MW) Combined Cycle Project-Egypt
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Document Control Coordinator (DCC) Company
Inclusive Dates : Oct. 2008 up to Feb 2009
Client : NEM B.V.
Owner : General Electric. GE Client - Owner
Company : Al- HASHEMIAH Contracting Company (Amreia Fabrication Workshop)
Project : Besos V Power Plant (750 MW) Combined Cycle Project– Spain
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Document Control Coordinator (DCC) Company
Inclusive Dates : July 2008 up to Oct. 2008
Client : NEM B.V.
Owner : General Electric. GE Client - Owner
Company : Al- HASHEMIAH Contracting Company (Amreia Fabrication Workshop)
Project : Kerawalabityia Power Plant (750 MW) Combined Cycle Proj.– Sri Lanka
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Document Control Coordinator (DCC) Company
Inclusive Dates : March 2008 up to July 2008
Client : NEM B.V.
Owner : General Electric. GE Client - Owner
Company : Al-HASHEMIAH Contracting Company (Amreia Fabrication Workshop)
Project : Darling Downs Combined Cycle Power Plant – Australia.
----------------------------------------------------------------------------------------------------------------------------------------------------------
I’m Join the Team for Preparing the QC Manual to meet the applicable requirements of the ASME Boiler and Pressure Vessels Code Section I, ASME B31.1, in addition to the client "contractor" requirement for Manufacture and Field assembly of Power Boilers parts and Pressure piping to be stamped with "S" and "PP" Stamp.
Position : Document Control Coordinator (DCC)
ASME [S] Stamp: of Manufacturing and Assembly of Power Boilers.
ASME [PP] Stamp: of Fabrication and Assembly of Pressure Piping. ----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Workshop Traveler Inspector. (Technical Office Dept.) Company
Inclusive Dates : Aug 2007 up to March 2008
Client : NEM
Owner : MESIAEED Combined. Client - Owner
Company : Al-HASHEMIAH Contracting Company (Amreia Fabrication Workshop)
Project : MESIAEED Combined Cycle Power Plant – Qatar.
----------------------------------------------------------------------------------------------------------------------------------------------------------
Position : Document Controller Company
Inclusive Dates : Oct. 2006 up to Aug. 2007
Client : UHDE
Owner : MOPCO Petroleum. Client - Owner
Company : IEMSA Company ( Damietta Site Workshop )
Project : Fertilizer
----------------------------------------------------------------------------------------------------------------------------------------------------------
Responsibilities at work: Perform a production plan / schedule for project.
Estimate the manpower distribution.
Monitoring the project productivity.
Taking corrective actions to meet the schedule.
Prepare all Computer programs need to control and follow-up the project.
Related Course:
Completed One NDT Method Liquid Penetrant Testing ( PT ) - ( Level 2 ) Cert. PT
Completed One NDT Method Magnetic Particle Testing ( MT ) - ( Level 2 ) Cert. MT
Unrelated Course:
Completed The Programming Course Certificate
Superiority Certificates:
Position : Planner Experience Certificate From PSC(Project Services Company) Certificate
Certificates:
Prepared to get the Microsoft Office Specialist (MOS, MOSE and MOM) ver. 2010
As soon as possible
Skills:
Language
Arabic : Mother Language
English : Very Good ( Write – Read – Spoke )
Computer
Very Good with any Operating System.
Very Good with Microsoft Office – Old Versions and 2010.
(Analysis, Design and Programming Database in Microsoft Access)
Capable to work on Primavera Project Planner – v 3.1 & v 6.0
Capable to work For Creating Databases with (SQL Server 2005 and MS-Access all Versions)
Capable to work For Designing The Programs with (Visual Studio v.2008 and v.2010)
Capable to work on Web Site Languages (HTML 4.0, X-HTML and CSS)
Other Things
Can work individual or with team.
Ability to work for a long period.
Capable to work under stress and accepted new experts.
Easily communication with Co-Workers and Partner.
My Own Programs
Creating Program For Controlling projects Related 4 Departments (ver.1)
( Tech. Office – Quality Control – Material Control – Planning) in AL HASHEMIAH Company
Creating Program For Controlling projects Planning Department in PSC Company
Creating Human Resourcing Program For Following Manpower in PSC Company
Creating Program For Controlling projects Related 4 Departments (ver.2)
( Tech. Office – Quality Control – Material Control – Planning) in NEM ENERGY EGYPT Company