8/2/2019 Mass and Haul
1/17
Problem:
Determine the total volume of earth to be excavated up to elevation 0.
10m 10m
10m
10m
6 8 5
0-315
11 10 6
I II
III IV
8/2/2019 Mass and Haul
2/17
Mass and Haul DiagramMass and Haul Diagram
HAUL
: product of earth excavated and the distance it was transported to form an
embankment or to be disposed as waste.
unit: meter station (metric) = 1 m3 to be transported
FREE HAUL DISTANCE (FHD)
: fixed distance within which the hauling of material is not paid for but it isassumed to be included in the cost of excavation.
OVERHAUL (OH)
: product of volume in excess of the free haul mass and the length of overhaul
in which payment is already required.
LENGTH OF OVERHAUL (LOH)
: distance between the center of gravity of mass excavation beyond the free
haul mass and the center of gravity of the resulting embankment.
8/2/2019 Mass and Haul
3/17
LENGTH OF ECONOMICAL HAUL
: distance within which it is economical to haul materials than to throw them
as waste.
WASTE
: excavated earth to be thrown away and not to be used as filling materials.
BORROW
: the excavated materials obtained from borrow pits located beyond the limits
of the road when the excavation for the roadway is not sufficient to formembankments.
Mass and Haul DiagramMass and Haul Diagram
8/2/2019 Mass and Haul
4/17
Vcut=VfillVcut=Vfill
FHD FHD
xLxR xL xR
FGL
cg cg
cgcg
NGL
wasteOHM=Vcut
FHM
borrow
FHM OHM waste
LEH LEH
Profile DiagramProfile Diagram
8/2/2019 Mass and Haul
5/17
Problem:
Here under shows a table of quantities of earthworks of a
portion of a proposed national road to be constructed toconnect some provinces in the Philippines. The length of thefree haul distance is specified to be 50m long. It is requiredto determine the stationing limits of free haul distance so asnot to include in the computation of overhaul.
Station Cut (m2) Fill (m2)2+000 60
+020 35+040 20+060 10
+080 0 0
2+100 15+120 60
+140 100
8/2/2019 Mass and Haul
6/17
2+140
2+000
2+080
Station Cut (m2) Fill (m2)2+000 60
+020 35
+040 20+060 10+080 0 02+100 15+120 60
+140 100
60
3520
10
15y2
60 100
y1
FHD = 50m
8/2/2019 Mass and Haul
7/17
1
2
3
4
1
8/2/2019 Mass and Haul
8/17
sta2+060
sta1+760s
ta1+460
Problem:
The cross-sectional area of sta 1+460 is 40m2 in fill, at sta 2+060 is
60m2 in cut. The free haul distance is 50m. The cost of borrow isPhP4.00/m3 while the cost of excavation is PhP3.50/m3. Cost of haulis PhP0.20 per meter-station. Balancing point is at sta 1+760.Assume the ground surface to be sloping upward uniformly up tostation 1+760 and then with a slightly steeper slope to sta 2+060.
60
40
y1y3
y2
y4
300 300
xRxL
x 50-x
FHD=50mz
400-z
LEH=450m
8/2/2019 Mass and Haul
9/17
Find the following:
a.Sta limits of FHDb.Sta limits of LEHc.Length ofOverhauld.Overhaule.Cost of Haul
f.Cost of Wasteg.Cost of Borrow
1
2
3
8/2/2019 Mass and Haul
10/17
8/2/2019 Mass and Haul
11/17
8/2/2019 Mass and Haul
12/17
8/2/2019 Mass and Haul
13/17
Properties of a Mass DiagramProperties of a Mass Diagram
1. Grade point on the profile corresponds to a max ormin point on the mass diagram.
2. Ascending line denotes cut or excavation anddescending line denotes fill or embankment.
3. The difference in length between any two verticalordinates of the mass diagram is the volumebetween the stations at which the ordinates wereerected.
4. Between any points, where the curve is intersectedby a horizontal line, excavation equals embankment.
5. In the mass diagram, a loop that forms a peakindicates a haul forward and a loop that forms a sagindicates a haul backward.
8/2/2019 Mass and Haul
14/17
8/2/2019 Mass and Haul
15/17
Problem:
The following data represents
a single summit massdiagram of a proposedexpansion of the TolosaExpressway.
Free Haul Distance = 50m
Limit of Economical Haul =400mMass Ordinate of Initial Limitof the Free Haul = +910m3
Mass Ordinate of the initialLimit of Economical Haul =+350
1.Compute the volume ofwaste in m3.2.Compute the volume ofoverhaul in m3.3.Compute the volume of
borrow in m3.
Station Volumes
Cut Fill
10+000 +200
10+040 +100
10+080 +150
10+120 +140
10+160 +110
10+200 +190
10+240 +5010+280 -40
10+320 -120
10+360 -90
10+400 -80
10+440 -200
10+480 -22010+520 -110
10+560 -320
10+600 -280
8/2/2019 Mass and Haul
16/17
Station Volumes Mass
Ordinate
Cut Fill
10+000 +200 +20010+040 +100 +300
10+080 +150 +450
10+120 +140 +590
10+160 +110 +700
10+200 +190 +890
10+240 +50 +940
10+280 -40 +900
10+320 -120 +780
10+360 -90 +690
10+400 -80 +610
10+440 -200 +41010+480 -220 +190
10+520 -110 +80
10+560 -320 -240
10+600 -280 -520
8/2/2019 Mass and Haul
17/17
1. Volume of wasteVolume of Waste = 350 200Volume of Waste = 150 m3
2. Overhaul VolumeOverhaul Volume = 910 350Overhaul Volume = 560 m3
3. Volume of Borrow
Volume of Borrow = 350 + 520Volume of Borrow = 870 m3