Download pdf - Mass and Haul

Transcript
  • 8/2/2019 Mass and Haul

    1/17

    Problem:

    Determine the total volume of earth to be excavated up to elevation 0.

    10m 10m

    10m

    10m

    6 8 5

    0-315

    11 10 6

    I II

    III IV

  • 8/2/2019 Mass and Haul

    2/17

    Mass and Haul DiagramMass and Haul Diagram

    HAUL

    : product of earth excavated and the distance it was transported to form an

    embankment or to be disposed as waste.

    unit: meter station (metric) = 1 m3 to be transported

    FREE HAUL DISTANCE (FHD)

    : fixed distance within which the hauling of material is not paid for but it isassumed to be included in the cost of excavation.

    OVERHAUL (OH)

    : product of volume in excess of the free haul mass and the length of overhaul

    in which payment is already required.

    LENGTH OF OVERHAUL (LOH)

    : distance between the center of gravity of mass excavation beyond the free

    haul mass and the center of gravity of the resulting embankment.

  • 8/2/2019 Mass and Haul

    3/17

    LENGTH OF ECONOMICAL HAUL

    : distance within which it is economical to haul materials than to throw them

    as waste.

    WASTE

    : excavated earth to be thrown away and not to be used as filling materials.

    BORROW

    : the excavated materials obtained from borrow pits located beyond the limits

    of the road when the excavation for the roadway is not sufficient to formembankments.

    Mass and Haul DiagramMass and Haul Diagram

  • 8/2/2019 Mass and Haul

    4/17

    Vcut=VfillVcut=Vfill

    FHD FHD

    xLxR xL xR

    FGL

    cg cg

    cgcg

    NGL

    wasteOHM=Vcut

    FHM

    borrow

    FHM OHM waste

    LEH LEH

    Profile DiagramProfile Diagram

  • 8/2/2019 Mass and Haul

    5/17

    Problem:

    Here under shows a table of quantities of earthworks of a

    portion of a proposed national road to be constructed toconnect some provinces in the Philippines. The length of thefree haul distance is specified to be 50m long. It is requiredto determine the stationing limits of free haul distance so asnot to include in the computation of overhaul.

    Station Cut (m2) Fill (m2)2+000 60

    +020 35+040 20+060 10

    +080 0 0

    2+100 15+120 60

    +140 100

  • 8/2/2019 Mass and Haul

    6/17

    2+140

    2+000

    2+080

    Station Cut (m2) Fill (m2)2+000 60

    +020 35

    +040 20+060 10+080 0 02+100 15+120 60

    +140 100

    60

    3520

    10

    15y2

    60 100

    y1

    FHD = 50m

  • 8/2/2019 Mass and Haul

    7/17

    1

    2

    3

    4

    1

  • 8/2/2019 Mass and Haul

    8/17

    sta2+060

    sta1+760s

    ta1+460

    Problem:

    The cross-sectional area of sta 1+460 is 40m2 in fill, at sta 2+060 is

    60m2 in cut. The free haul distance is 50m. The cost of borrow isPhP4.00/m3 while the cost of excavation is PhP3.50/m3. Cost of haulis PhP0.20 per meter-station. Balancing point is at sta 1+760.Assume the ground surface to be sloping upward uniformly up tostation 1+760 and then with a slightly steeper slope to sta 2+060.

    60

    40

    y1y3

    y2

    y4

    300 300

    xRxL

    x 50-x

    FHD=50mz

    400-z

    LEH=450m

  • 8/2/2019 Mass and Haul

    9/17

    Find the following:

    a.Sta limits of FHDb.Sta limits of LEHc.Length ofOverhauld.Overhaule.Cost of Haul

    f.Cost of Wasteg.Cost of Borrow

    1

    2

    3

  • 8/2/2019 Mass and Haul

    10/17

  • 8/2/2019 Mass and Haul

    11/17

  • 8/2/2019 Mass and Haul

    12/17

  • 8/2/2019 Mass and Haul

    13/17

    Properties of a Mass DiagramProperties of a Mass Diagram

    1. Grade point on the profile corresponds to a max ormin point on the mass diagram.

    2. Ascending line denotes cut or excavation anddescending line denotes fill or embankment.

    3. The difference in length between any two verticalordinates of the mass diagram is the volumebetween the stations at which the ordinates wereerected.

    4. Between any points, where the curve is intersectedby a horizontal line, excavation equals embankment.

    5. In the mass diagram, a loop that forms a peakindicates a haul forward and a loop that forms a sagindicates a haul backward.

  • 8/2/2019 Mass and Haul

    14/17

  • 8/2/2019 Mass and Haul

    15/17

    Problem:

    The following data represents

    a single summit massdiagram of a proposedexpansion of the TolosaExpressway.

    Free Haul Distance = 50m

    Limit of Economical Haul =400mMass Ordinate of Initial Limitof the Free Haul = +910m3

    Mass Ordinate of the initialLimit of Economical Haul =+350

    1.Compute the volume ofwaste in m3.2.Compute the volume ofoverhaul in m3.3.Compute the volume of

    borrow in m3.

    Station Volumes

    Cut Fill

    10+000 +200

    10+040 +100

    10+080 +150

    10+120 +140

    10+160 +110

    10+200 +190

    10+240 +5010+280 -40

    10+320 -120

    10+360 -90

    10+400 -80

    10+440 -200

    10+480 -22010+520 -110

    10+560 -320

    10+600 -280

  • 8/2/2019 Mass and Haul

    16/17

    Station Volumes Mass

    Ordinate

    Cut Fill

    10+000 +200 +20010+040 +100 +300

    10+080 +150 +450

    10+120 +140 +590

    10+160 +110 +700

    10+200 +190 +890

    10+240 +50 +940

    10+280 -40 +900

    10+320 -120 +780

    10+360 -90 +690

    10+400 -80 +610

    10+440 -200 +41010+480 -220 +190

    10+520 -110 +80

    10+560 -320 -240

    10+600 -280 -520

  • 8/2/2019 Mass and Haul

    17/17

    1. Volume of wasteVolume of Waste = 350 200Volume of Waste = 150 m3

    2. Overhaul VolumeOverhaul Volume = 910 350Overhaul Volume = 560 m3

    3. Volume of Borrow

    Volume of Borrow = 350 + 520Volume of Borrow = 870 m3


Recommended