Integration of Oracle E-Business Suite with Oracle Utilities Work and Asset ManagementSession: CON5590September 29, 2014Marriott Marquis - Golden Gate C1/C2
2
Introductions About NEORSD About AST Product Definitions Project Background Integration Lessons Learned Questions
Agenda
3
Donice Bell – Program Manager, NEORSD
Prakash Chhatwani – Senior Practice Director,
AST Corporation
Introductions
4
Our Mission Our History Oracle Platform To serve our customers by leading
effective wastewater and storm water management that protects the health and environment of our region while enhancing quality of life
Created in 1972 (1979 - NEORSD)
Role
• Responsible for planning, financing, constructing, operating and controlling wastewater treatment and disposal facilities, major interceptor sewers and other water pollution control facilities within its service area
Governance
• Board of Trustees
• Financials
• Core - Human Resource
• Advanced Benefits
• iRecruitment
• Self Service
• Purchasing
• iProcurement
• Inventory
• Order Management
• Sourcing
• iSupplier
• Oracle Database 11g
• SOA/BPEL
About NEORSD
National Environment Achievement Award2009 - 2013
Excellence in Management2003, 2007
Supplier Diversity2009
Middle MarketSenior Management2012, 2013
5
Our Services Oracle Partnership Oracle Specialized E-Business Suite
Business Intelligence
EPM-Hyperion
Middleware
CRM
Managed Services
Education / Oracle University
Project Advisory Services
Oracle Platinum Partner
Pillar Partner
• SOA
• Business Intelligence
• Hyperion
Oracle University Approved Education Center
Oracle University Reseller
Oracle Accelerator Implementer
Oracle Managed Cloud Services Implementer
Small Business Strategy Council
EBS Financial Management
EBS Human Capital Management
EBS Supply Chain Management
BI Applications
BI Foundation
Service Oriented Architecture
Application Development Framework 11g
Hyperion Planning 11
Database 11g
Public Sector
3 Time Oracle Excellence Award Winner 2011 Inc. Top Small Company Workplaces
2012-2013 Inc. 5000 Fastest Growing Companies
2012 Best & Brightest Companies to Work For
6
Oracle EBS: Oracle E-Business Suite (R12) Upgrade
Oracle Supply Chain Management Implementation• Six (6) Modules
Oracle Fusion Middleware• SOA and BPEL
Oracle Integration Pack (JSK)
Product Definitions
7
As Is:• Oracle EBS used for FIN and HRMS only• Oracle WAM used for all SCM, Work Orders & Asset Mgt
To Be / Goal: Move Supply Chain functionality from WAM to EBS• Oracle EBS used for SCM (Procurement & Inventory) along with
Financials and HRMS• Oracle WAM used for Work Orders & Asset Mgt only
Business Driver: Need for Asset Costing in WAM (increase operational efficiencies)• Material & Services purchased for work orders• Inventory Items used for work orders
Project Background
8
Pre-Built Integration Packs (PIPs)• Set of pre-built integrations - ‘plug & play’ interface code• Offered in 2 models based on pre-established,
standardized business flowso EBS to WAM model (SCM in EBS) – chosen modelo WAM to EBS model (SCM in WAM)
Integration driven by SOA and BPEL• All mapping, error handling and scheduling of interface
records handled using BPEL processes All records created/interfaced using standard APIs (in
both systems)
Overview of Integration
9
Integration Flow
10
Integration Features
11
Purchase Requisition Integration Purchase Order Integration Receipts Integration Invoice and Payments Integration Material Request Integration Stock Transaction Integration Vendor Integration Accounts Integration Employee and Employee Wages Integration Catalog Integration Store Room Integration Checkout Integration
Integration Points
12
Planning & Approach• Identify: Integration Points, Business Flows,
System of Record for Key Components (Items, Suppliers, Employees, etc.)
• ‘As Is’ documentation (up-to-date)• ‘Familiarization’ - Spend the time to learn the
business flows delivered (as early as possible)• Not really an ‘Out of the Box’ solution• GAPs should be identified (as early as possible)
Lessons Learned
13
Technology Impact• Don’t underestimate time & resources based on the concept of
‘plug & play’• Technology is advanced and can speed up the process but it
doesn’t replace the need foro Timeline – ensure adequate time is provided to:
– Build test environments– Identify GAPs– Test and disposition GAPs
o Resources - skillset and knowledge of the technical components and products
– Technical resources – SOA– Functional resources – Oracle EBS/Oracle WAM– Subject Matter Experts – Business Flows
Lessons Learned
14
Testing• Plan for multiple test iterations• Include unit tests, system integration tests and
even performance tests• Involve business and end users early on in the
testing process• Provide for time between testing iterations to
make decisions and updates• Test complete business flows between WAM and
EBS for exception handling
Lessons Learned
15
Q&A