Indiana Municipal Power Agency
CONSIDERATIONSFOR
JOINT OWNERSHIP OF
POWER GENERATION FACILITIES
Indiana Municipal Power Agency
POWER GENERATION PROJECT LIFECYCLE
• Decision to participate and participation negotiations
• Development period
• Construction and ongoing operations
Indiana Municipal Power Agency
Decision To Participate And Participation Negotiations
• Know the technology• Evaluate the lead partner and define
their role• Sanity Check-Likelihood of project
completion• Evaluate the makeup of the other
participants• Determine your level of participation
Indiana Municipal Power Agency
Decision To Participate And Participation Negotiations
• Due diligence investigation of design
• Relationships with other partners and with lead partner
• Rights to future additions of generation
• Resource diversity strategy
Indiana Municipal Power Agency
Development Period
• Development period costs• EPC contract negotiation• Pricing changes between participation
and development phases• Methods to monitor progress of project• Proactive approach to public relations
Indiana Municipal Power Agency
Development Period
• Environmental permitting hurdles• Recordkeeping from day one• Cancellation penalties• Protection of confidential
information• Insurance decision (Contractor or
owner provided)
Indiana Municipal Power Agency
Construction And Ongoing Operations
• Level of representation and monitoring during construction
• Backup power supply plans for the non-firm resource
• Capital and O&M budget monitoring, invoice review and audits
Indiana Municipal Power Agency
Construction And Ongoing Operations
• Emission allowances allocation and air quality systems performance
• Capital cost exposure due to changing environmental regulations
• A&G cost increase exposure and control