Agenda
C Ramp-Current Restriction
A Ramp-Starting tonight
B Ramp-Starting November + 2-lane closure
Summary
2
LOCATION
3
A
BC
I-84: MP 0.00 – 0.56
I-5: MP 301.45 – 301.92
During Design – Daytime lane restrictions
4
Current Pour status
5
C Ramp Pinch point
6
C Ramp Pinch point
7
C Ramp Pinch point
8
C Ramp – Outside of the pinch point
9
A Ramp
10
Existing Pinch Point-Removed from Contract
11
A Ramp – Pinch Point during Construction
12
B Ramp
13
B Ramp
14
B Ramp
15
Stakeholder Forum SupportProject supported. Yes or No?