Page 1: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 1/8

HomeDisclaimer

Construction Method Statements

Plumbing

Piping

Electrical

HVAC

Duct Works

HVAC PipingTesting & Commissioning

Pump Installation

Method Statement Template

Inspection ChecklistsRequest A Method Statement

Health & Safety

Sample Forms & Formats

Flushing Procedure For Chilled Water System ChemicalTreatment

Tweet

Like

0

Email

Share

Listen to musicSearch

Page 2: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 2/8

Tweet 0

Like 0

This method statement describes the methodology and

procedure for flushing of chilled water system and to ensure

that all concerned persons are familiar with the sequence of

activities, utilization of resources, and execution of the worksin compliance with applicable Safety and Quality

Procedures, and Project Documents and Specification.

Scope of Works

This method statement is intended to outline the activities and

the methods used in cleaning and flushing of chilled water

system and its chemical treatment. All activities will be

carried out in accordance with the contract details and in full

compliance to the project specifications. All work within therights-of-way of the standards and specifications will be

done in compliance with requirements issued by authorities.

Required Tools/Equipment

Tool box

Tool kitMeters/gauges

Power ToolsTemporary pump

HVAC Air Conditioning

www.siemens.com/climate-control

Climate Control by Siemens - Save up to60 percent of consumed energy

0 Email Share

Page 3: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 3/8

Chilled Water Flushing Procedure

Preparation: The following preparation checks / works shall be carried out prior to commencement of flushing

and cleaning of chilled water system.

Check and ensure the system is hydro-statically pressure tested and verify test certificate.Check the provision of air vents at location as per approved drawings.

Check and ensure sufficient quantities of chemicals are available as per requirement.Place warning signs and warning tape as required.

Arrangements for draining the flushed water to be made before starting the flushing process. Drain shouldbe connected to main drainage line or as directed by authorities.

Flushing & Cleaning Steps

Cleaning With Fresh Water

Fill the system with clean water and drain the water after 30 minutes of circulation. The water quality will be as

per approved parameters.

Refill the system with clean water and run the chilled water pump for 2 hours. Take samples to check the quality

Page 4: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 4/8

of water as per applicable requirements in the contract.

Open the drain valves in the main lines and drain the water completely.

Clean the strainers

During the above flushing process the drain valves shall be kept open while the pump is running, until the waterappears clean.

Close all the drain valves

Cleaning With Cleaning Chemical

Desired water quality should be achieved before adding the chemical.

Refill the system with clean water and add cleaning chemical in required quantities as per Specialistsupplier’s instructions i.e. 1Kg per cubic meter of system volume.

Once the cleaning process is started, samples of solution shall be collected from various parts of the

system to ensure the chemical solution has reached all parts of the system.

Run the pump and circulate the water (with chemicals added) for a minimum period of 24 hours as perspecialist supplier’s recommendations.

Samples to be taken and tested in 3rd party laboratory. The water quality must be achieved as per therequirements agreed in the contract or as applicable

Specialist contractor shall collect samples and conduct tests until satisfactory results are obtained as

required which is a condition when no increase in iron level is observed and a level of iron less than 1ppmis achieved and the water is clear, colourless and odourless.

After the cleaning process is completed as described above the cleaning solution shall be flushed out.

Addition of Corrosion & Scale Inhibitors

The entire system is re-filled with fresh and clean water and treated with corrosion and scale inhibiting treatment

chemical at the rate of 3Kg per cubic meter of the system volume or as applicable depending upon the chemical

concentration. After 24 hours of circulation samples are taken to ensure the concentration levels i.e. 800-100ppm as NaNo2

Biological Control

Biological control chemical, shall be dosed at the agreed rate per cubic meter using the manual dosing pot. This is

a shock dosing which shall be done after every three months.

Inspection

The inspection request shall be raised for consultant to witness the flushing and cleaning process at differentstages and results shall be noted on checklists.

Page 5: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 5/8

Tags: Chemical Treatment of chw piping, chw piping cleaning, Flushing Procedure For Chilled Water System

◀ METHOD STATEMENT FOR CONCRETE SAMPLING AND TESTINGSample Forms & Checklists For HVAC Installation Testing & Commissioning ▶

Search Search

Like Us To Support Us

Electrical Installation

www.siemens.ae/green-buildings

Siemens Green Buildings - Save up to 60percent of consumed energy!

Page 6: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 6/8

Methodstatementhq

Like

One person likes Methodstatementhq.

Facebook social plugin

Other Method Statements

Testing & Commissioning Of Fire Suppression System

August 20th, 2013

The scope of method statements covers the planning, preparation, and conduct of fire

suppression sys[...]

Welding Method Statement

August 13th, 2013

There are many different welding processes, but the most commonly used in the construction

industry [...]

Installation Of Reinforcement Steel Bars For Footing, Strap Beam, Raft, Slab & All

Structural Concrete - Steel Fixing

August 13th, 2013

The purpose of this method statement is to lay down the systematic procedures for the various

activi[...]

Method Statement For Installation Testing & Commissioning Of BMS Building

Management System

August 1st, 2013

Scope of Work This method statement is applicable for Installation, Testing & Commissioning

of [...]

Page 7: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 7/8

Chilled Water Balancing For HVAC System Method Statement

July 31st, 2013

The aim of chilled water balancing is to apply a disciplined procedure of adjustment to water

flow r[...]

Method Statement For Air Balancing Of HVAC System FCU AHU Exhaust Fans &

Pressurization Unit

July 31st, 2013

Air Balancing Method Statement Air Balancing For Fan Coil Units Check that all automatic

contro[...]

Inspection Checklists / Forms For Electrical Works Installation Testing &

Commissioning

July 31st, 2013

Below are the links for downloading the sample inspection and testing check sheets and forms

which y[...]

Sample Forms & Checklists For HVAC Installation Testing & Commissioning

July 31st, 2013

You can download the sample forms and checklists for different activities which you can then

customi[...]

METHOD STATEMENT FOR CONCRETE SAMPLING AND TESTING

July 29th, 2013

This method statement is applicable for collecting samples for concrete before and during

concrete p[...]

METHOD STATEMENT FOR TESTING & COMMISSIONING OF

PRESSURIZATION UNIT

July 29th, 2013

The purpose of this procedure is to define the step by step method to implement the correctpractice[...]

Page 8: Flushing Procedure for Chilled Water System Chemical Treatment  Method Statement HQ

8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ

methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 8/8

Most Visited Tags

AC Ducting Method Statement blank performa blank proforma BMS Testing Procedure Building Management System BMS

Construction Method Statements Drainage Piping Installation Electrical Method Statements for GI Box Installation GI Conduit In The Wall

hvac HVAC Duct Work Installation Method Statement HVAC System Procedure installation Installation of GI Conduits &

Accessories method Method Of Statement Method Statement Method Statement

For Drainage Piping method statement for drainage works Method Statement For GI Box & Conduit Installation method statement forInstallation Method Statement For PVC Conduit Installation In Concrete Slab Method Statement Template MST MST For

BMS MST For Conduiting Work of Piping Installation Procedure pressure pumps PVC uPVC Underground Above Ground Piping Risk

Assessment sample check list sample checksheet Sample Format Electrical SOP statement swms template test

Testing & Commissioning Testing & Commissioning Method Statement water

HomePrivacy Policy

Disclaimer

Copyright © 2011 - 2012 MethodStatementHQ.Com. All Rights Reserved.


Recommended