Transcript
  • COMPANY CONTRACTOR

    Shell Iraq Petroleum Development B.V. CPP Petroleum Pipeline Bureau

    INFIELD PIPELINE WORKS FOR FCP, MAJNOON OIL FIELD PROJECT (SIPD-143)

    ITP For Method Statement For Pipeline Welding

    Project Infield Pipeline Works for FCP, Majnoon Oil Field Project

    Originating Company China Petroleum Pipeline Bureau (Iraq)

    Document Title ITP For Method Statement for Pipeline Welding

    Document Number FCPG-00000-CPP143-00-QA-5733-00010

    Document Revision 006

    Document Status IFA-Issued for Approval

    Document Type QA5733-Inspection Plan

    Originator/Author CPP

    Security Classification Restricted

    Authorizer Zhou Xiaoqiu

    Issue Date 24-June-12

  • INFIELD PIPELINE WORKS FOR FCP MAJNOON OIL FIELD PROJECT

    (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 3 of 16

    Revision History

    Rev# Date of Issue

    Transmittal No. Status Description Author Authoriser

    000 21-Feb-12 CPP143-PIUL-2002C-0051-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    001 28-Feb-12 CPP143-PIUL-2002C-0068-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    002 06-Mar-12 CPP143-PIUL-2002C-0073-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    003 15-Apr-12 CPP143-PIUL-2002C-0153-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    004 20-Apr-12 CPP143-PIUL-2002C-0159-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    005 13-May-12 CPP143-PIUL-2002C-0177-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    006 24-June-12 CPP143-PIUL-2002C-0220-TX IFA-Issued for Approval CPP Zhou Xiaoqiu

    Rev # Reason for Issue/Change

    000 First draft issued for Approval

    001 Issued for Approval(COMPANY comments incorporated)

    002 Issued for Approval(COMPANY comments incorporated)

    003 Issued for Approval(COMPANY comments incorporated)

    004 Issued for Approval(COMPANY comments incorporated)

    005 Issued for Approval(COMPANY comments incorporated)

    006 Issued for Approval(Check point and WELD BOX have been revised)

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 4 of 16

    Content

    1. INSPECTION AND TEST PLAN..................................................................................................................... 5

    2. CONSTRUCTION REPORT ......................................................................................................................... 12

  • INFIELD PIPELINE WORKS FOR FCP MAJNOON OIL FIELD PROJECT

    (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 5 of 16

    1. INSPECTION AND TEST PLAN

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    DEFINITION OF INSPECTION AND TEST PLAN SYMBOLS

    H - HOLD: A point beyond which work shall not proceed without formal approval by appropriate inspectorate. Achievement of H points shall be notified to COMPANY.

    W - WITNESS: A point beyond which work may proceed without formal documented approval by any of the inspectorate. Achievement of W points shall be notified to COMPANY.

    S - SURVEILLANCE: A point where CONSORTIUM and others may carry out surveillance of work in progress and documentation associated on an unscheduled basis, with no notification required by any

    party and without amendment to the scheduled production programme.

    R - REVIEW: The documents are to be submitted to the appropriate inspectorate for review by COMPANY. Note that where a document is subject to COMPANY approval, work shall not proceed until the

    COMPANYs approval is given.

    C - CERTIFICATION: Specific and appropriate certification documentation is to be included in the document package.

    REMARKS

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 6 of 16

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    Item No.

    Inspection Activity & Specific Check Point Area

    Reference Document Acceptance Criteria,

    Code & Standard Verifying Record

    Contractor ICMT

    1.0

    1.1

    1.2

    1.3

    1.4

    1.5

    1.6

    1.7

    General

    Method statement review for final approval.

    HSE Requirements for PPE and certified lifting

    equipments.

    Equipment Status for type range calibration earth

    clamp contact point in pipe line.

    Pipe inspection for pipe identification, physical and

    physical damage, manufacturing stamp.

    Electrode Control for class batch No.

    Electrode Tracing by marking batch No against

    welding

    Pipe tracing by pipe no heat no and length. Transfer

    the ID prior to cutting.

    FCPG-00000-CPP143-00-BA-5537-00001 Method statement for pipeline welding

    ISO 13847:2000 Petroleum and natural gas industries-Pipeline transportation systems-Welding of pipelines DEP 61.40.20.30-GEN Welding of pipelines and related facilities

    FORM-QA-5733-00010-01

    Daily Welding Report

    FORM-QA-5733-00010-02

    Pipe Log Book

    FORM-QA-5733-00010-03

    Weld Box

    H

    W/C

    W

    W/C

    W/C

    W

    W/H

    H

    R

    S

    C/S

    S

    C/S

    C/S

    Definitions of Symbols: H - Hold Point W - Witness Point S - Surveillance R - Review C Certification

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 7 of 16

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    Item No.

    Inspection Activity & Specific Check Point Area

    Reference Document Acceptance

    Criteria, Code & Standard

    Verifying Record

    Contractor/TPI ICMT

    2.0

    2.1

    2.2

    2.3

    2.4

    2.5

    2.6

    2.7

    Welder Qualification

    Welding Procedure Status for final approval

    Pre-weld preparations by bevel dimensions ,clamp

    type, root gap , alignment, mismatch with in 3mm

    Welding Control by weather protection like wind

    shield, welding parameters as per WPS, ensure

    finishing by removal of slag grind high points and file

    out under cuts.

    Visual Inspection for marking and good workmanship

    of root, cap, profile, surface discontinuities.

    Mechanical Test

    NDT 100% for RT for butt welds.

    Welder approval in WQT records with qualification,

    status, welder certificates, and cards

    FCPG-00000-CPP143-00-BA-5537-00001 Method statement for pipeline welding WPS

    ISO 13847:2000 Petroleum and natural gas industries-Pipeline transportation systems-Welding of pipelines DEP 61.40.20.30-GEN Welding of pipelines and related facilities

    FORM-QA-6050-0001-01 Welder Qualification Test Record

    FORM-QA-6050-0001-02 WQT Visual Inspection Report FORM-QA-6050-0001-03 Welder Qualification Test Certificate

    FORM-QA-5733-00010-04

    NDT REQUEST FORM-BA-6070-0003-01 RT Report

    H/W

    H/W

    H/W

    H/W

    H/W

    H/W

    C/R

    H

    S

    S

    S

    S/C

    S/C

    S/C

    Definitions of Symbols: H - Hold Point W - Witness Point S - Surveillance R - Review C Certification

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 8 of 16

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    Item No.

    Inspection Activity & Specific Check Point Area

    Reference Document

    Acceptance Criteria, Code & Standard

    Verifying Record

    Contractor ICMT

    3.0

    3.1

    3.2

    3.3

    3.4

    3.5

    3.6

    3.7

    3.8

    3.9

    3.10

    3.11

    Pipeline Welding

    Pipe size, type and quality. Check quality of welding

    product and handle, storage, oven and issue

    Verifying welding procedure

    Verifying welder qualification

    Line up joint clean

    Check line up clearance, high-low of spiral seam or/and long

    seam

    Check preheat temperature

    Check welding environment in accordance with

    requirement

    Check length of Fixed welding, weld identification

    Visual inspection for each pass

    Ensure avoiding foreign matter into pipeline (add flange)

    Job site inspection ensure ROW without any electrode

    heads, etc

    Transfer of heat NO. & color coding where applicable on

    piping to be cut.

    FCPG-00000-CPP143-00-BA-5537-00001 Method statement for pipeline welding

    WPS & PQR

    WQR

    ISO 13847:2000 Petroleum and natural gas industries-Pipeline transportation systems-Welding of pipelines DEP 61.40.20.30-GEN Welding of pipelines and related facilities

    FORM-QA-5733-00010-01

    Daily Welding Report

    FORM-QA-5733-00010-02

    Pipe Log Book

    FORM-QA-5733-00010-03

    Weld Box

    W/S

    S/R

    S/C

    W

    W

    W

    W

    W

    W

    W

    W

    S

    S

    S

    S

    S

    S

    S

    S

    S

    S

    S

    Definitions of Symbols: H - Hold Point W - Witness Point S - Surveillance R - Review C Certification

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 9 of 16

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    Item No.

    Inspection Activity & Specific Check Point Area

    Reference Document Acceptance Criteria,

    Code & Standard Verifying Record

    Contractor ICMT

    4.0

    4.1

    4.2

    4.3

    4.4

    4.5

    4.6

    4.7

    4.8

    4.9

    Tie-in

    Trench is clear of debris and water. The inside of

    adjoining pipes is clear from foreign material.

    Both ends of adjoining pipes are beveled as per WPS

    joint design, and the surface are clean within 100mm

    distance from the ends

    Bell hole for Tie-in is adequate for Tie-in welding

    operation, and as per specifications.

    Ensure that adjoining pipes are stress free before

    welding.

    Offset of adjoining pipes is divided equally around the

    pipes, and within specified tolerance.

    Tie-in welding is performed by qualified welders with

    approved WPS.

    Visual inspection to the final weld is acceptable.

    Tie-in weld is passed by radiographic testing.

    Tie-in weld is passed by ultrasonic testing.

    FCPG-00000-CPP143-00-BA-5537-00001 Method statement for pipeline welding

    FCPG-00000-CPP143-

    00-BA-6070-00013

    Tie-In Procedure

    WPS & PQR

    ISO 13847:2000 Petroleum and natural gas industries-Pipeline transportation systems -Welding of pipelines DEP 61.40.20.30-GEN Welding of pipelines and related facilities FCPG-00000-CPP143-00-QA-6050-00011 RT Procedure FCPG-00000-CPP143-00-QA-6050-00012 UT Procedure

    FORM-QA-5733-00010-01

    Daily Welding Report

    FORM-QA-5733-00010-02

    Pipe Log Book

    FORM-QA-5733-00010-03

    Weld Box

    FORM-QA-5733-00010-04

    NDT REQUEST

    FORM-QA-5733-00010-05

    TIE-IN CHECK LIST

    W

    W

    W/S

    W

    W

    W/R

    W

    R/C

    R/C

    S

    S

    S/R

    S

    S

    S

    S/R

    R

    R

    Definitions of Symbols: H - Hold Point W - Witness Point S - Surveillance R - Review C Certification

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 10 of 16

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    Item No.

    Inspection Activity & Specific Check Point Area

    Reference Document Acceptance Criteria,

    Code & Standard Verifying Record

    Contractor ICMT

    5.0

    5.1

    5.2

    5.3

    5.4

    5.5

    5.6

    5.7

    5.8

    5.9

    Pipe weld repair and cut out

    Pipe size, type and defects at Field Visual

    inspection for each pass

    Defect inspection; check the thickness after the

    removal arc strikes, surface imperfections, damages

    to pipe materials or fittings.

    Check for the weld repair by liquid penetrate

    technique

    Check the cut out for min 500 mm lengths.

    Dress the ground area to ensure smooth transition

    with surrounding surface.

    Welding as per approved WPS

    Verifying welder qualification

    Line up joint clean

    Check preheat temperature

    FCPG-00000-CPP143-00-BA-5537-00001 Method statement for pipeline welding

    FCPG-00000-CPP143-00-BA-6064-00001

    Pipe Weld Repair and

    Cut Out Procedure

    FCPG-00000-

    CPP143-00-QA-6050-

    00009 PT Procedure

    WPS &PQR

    ISO 13847:2000 Petroleum and natural gas industries-Pipeline transportation systems-Welding of pipelines DEP 61.40.20.30-GEN Welding of pipelines and related facilities

    FORM-QA-5733-00010-01

    Daily Welding Report

    FORM-QA-5733-00006-02

    Weld Repair Log

    W

    W

    R

    W

    W

    W/S

    S/R

    W

    W

    S/R

    S/R

    R

    S

    S

    S

    S

    S

    S

    Definitions of Symbols: H - Hold Point W - Witness Point S - Surveillance R - Review C Certification

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 11 of 16

    INFIELD PIPELINE WORS FOR FCP, MAJNOON OIL

    ITP FOR METHOD STATEMENT FOR PIPELINE WELDING

    Item No.

    Inspection Activity & Specific Check Point Area

    Reference Document Acceptance Criteria,

    Code & Standard Verifying Record

    Contractor ICMT

    6.0

    6.1

    6.2

    6.3

    6.4

    6.5

    Pipeline welding NDT

    Non-destructive test inspecting technician

    shall be experienced and competent with

    qualification certificate.

    Inspect RT films and inspection reports

    Inspect MT equipment and inspection reports

    Inspect PT liquid and inspection reports.

    Inspect UT equipment and inspection reports.

    FCPG-00000-CPP143-00-BA-5537-00001 Method statement for pipeline welding FCPG-00000-CPP143-00-QA-6050-00011 RT Procedure FCPG-00000-CPP143-00-QA-6050-00010 MT Procedure FCPG-00000-CPP143-00-QA-6050-00009 PT Procedure FCPG-00000-CPP143-00-QA-6050-00012

    UT Procedure

    ISO 13847:2000 Petroleum and natural gas industries-Pipeline transportation systems-Welding of pipelines DEP 61.40.20.30-GEN Welding of pipelines and related facilities

    FORM-QA-6050-00011-01

    RT Report

    FORM-QA-6050-00010-01

    MT Report

    FORM-QA-6050-00009-01

    PT Report

    FORM-QA-6050-00012-01

    UT Report

    S/R

    W

    S/R

    S/R

    S/R

    R

    S/R

    S/R

    S/R

    S/R

    Definitions of Symbols: H - Hold Point W - Witness Point S - Surveillance R - Review C Certification

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 12 of 16

    2. CONSTRUCTION REPORT NO. FORM-QA-5733-00010-01

    Daily Welding Report Report No. Line No. Date: Sheet of

    Pipe NO.

    Heat No.

    Pipe Material

    Diameter (Inch)

    W.T. (mm)

    Joint No. WPS NO.

    Fit-up

    Pre-heat

    ()

    Welders Visual Inspection

    Remarks Root Hot Fill1 Fill2 Fill3 Cap

    Contractor ICMT

    Name

    Signature

    Date

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 13 of 16

    NO. FORM-QA-5733-00010-02

    Pipe Log Book

    Pipe NO.

    Heat No.

    Length(m)

    Diameter W.T. (mm)

    Joint No.

    Welding Date

    WPS NO.

    Welders Welding Report

    No

    RT Reports

    Root Hot Fill1 Fill2 Fill3 Cap Date Results Report 1

    No. Report 2

    No.

  • INFIELD PIPELINE WORKS FOR FCP MAJNOON OIL FIELD PROJECT

    (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 14 of 16

    NO. FORM-QA-5733-00010-03

    WELD BOX

    WELD NO.

    WPS NO.

    L R

    PIPE NO.

    HEAT NO.

    R

    H

    F

    C

    VT

    DATE

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 15 of 16

    NO. FORM-QA-5733-00010-04

    NDT REQUEST Report NO.: Line No.: Drawing No.: Date: Sheet: of

    S.N. Weld NO. DIA X THICK WPS

    NO.

    REQUEST FOR Welders REMARKS

    RT UT PT MT

    Contractor ICMT

    Name

    Signature

    Date

  • INFIELD PIPELINE WORKS FOR FCP

    MAJNOON OIL FIELD PROJECT (SIPD-143)

    Document No.: FCPG-00000-CPP143-00-QA-5733-00010 Page 16 of 16

    NO. FORM-QA-5733-00010-05

    TIE-IN CHECK LIST Report No.:

    Line No.:

    Date:

    QC CHECK POINTS YES/NO

    1. Trench is clear of debris and water.

    2. The inside of adjoining pipes is clear from foreign material.

    3. Both ends of adjoining pipes are beveled as per WPS joint design, and the surface are clean within 100mm distance from the ends

    4. Bell hole for Tie-in is adequate for Tie-in welding operation, and as per specifications.

    5. Pipes to be joined are free from any mechanical damages; pup piece length is more than 2.0 meter if used.

    6. Weather conditions are suitable for tie-in welding, ambient temperature shall not be less than 10C .

    7. The weld seams of the adjoining pipes are offset as per specification.

    8. Ensure that adjoining pipes are stress free before welding.

    9. Offset of adjoining pipes is divided equally around the pipes, and within specified tolerance.

    10. Tie-in welding is performed by qualified welders with approved WPS.

    11. Visual inspection to the final weldment is acceptable.

    12. Tie-in weldment is passed by radiographic testing.

    REMARKS

    APPROVALS CONTRACTOR ICMT

    Name

    Signature

    Date


Recommended