Transcript
Page 1: Fall 2019 CRFS Meeting · Fort pache White R: Calva: No Data By as Fort Thomas Pima Fort Granl Globe Chrysotile: San Horseshoe US: 431.0 evelt 724.0 ' 'TOnto National Tonto Ck: 2048.0

US Army Corps of Engineers

BUILDING STRONG®

Fall 2019 CRFS Meeting

Van Crisostomo, PE

Chief, Reservoir Regulation Section

Los Angeles District

21 November 2019

Page 2: Fall 2019 CRFS Meeting · Fort pache White R: Calva: No Data By as Fort Thomas Pima Fort Granl Globe Chrysotile: San Horseshoe US: 431.0 evelt 724.0 ' 'TOnto National Tonto Ck: 2048.0

US Army Corps of Engineers

BUILDING STRONG®

Pertinent Stream Gages Upstream of Painted Rock Dam

Painted Rock Dam

Page 3: Fall 2019 CRFS Meeting · Fort pache White R: Calva: No Data By as Fort Thomas Pima Fort Granl Globe Chrysotile: San Horseshoe US: 431.0 evelt 724.0 ' 'TOnto National Tonto Ck: 2048.0

US Army Corps of Engineers

BUILDING STRONG®

Questionable data?Q = 28,000 cfs

Monsoonal Rain ActivityGenerated Runoff Upstream

Of Painted Rock Dam – 24 SEP 2019

General Overview Of Flow Upstream ofPainted Rock Dam

Apr-Nov 2019

Page 4: Fall 2019 CRFS Meeting · Fort pache White R: Calva: No Data By as Fort Thomas Pima Fort Granl Globe Chrysotile: San Horseshoe US: 431.0 evelt 724.0 ' 'TOnto National Tonto Ck: 2048.0

US Army Corps of Engineers

BUILDING STRONG®

Painted Rock Dam Elevation Data – Apr-Nov 2019Project Invert Elevation at 530.0 ft, NGVD29

Telemetry Data is 5 ft above Invert


Recommended