ELI-NP Team, March 5, 2013
2006 – ELI on ESFRI Roadmap
ELI-PP 2007-2010 (FP7) ELI-Beamlines (Czech Republic) ELI-Attoseconds (Hungary) ELI-Nuclear Physics (Romania)
ELI-DC (Delivery Consortium): 2010, Legal entity: April 2013 Czech Republic, Hungary, Romania, Italy, Germany
2
Extreme Light Infrastructure
ELI-NP
NUCLEARTandem accelerators
Cyclotronsγ – Irradiator
Advanced DetectorsBiophysics
Environmental PhysicsRadioisotopes
ring rail/road
BUCHAREST
Bucharest-MagureleNational Physics Institutes
LasersPlasma
OptoelectronicsMaterial Physics
Theoretical PhysicsParticle Physics
ELI-NP
Large equipments:• High power laser system, 2 x 10PW maximum power• Gamma beam, high intensity, tunable energy up to 20MeV, produced by Compton scattering of a laser beam on a 700 MeV electron beam produced by a warm LINAC
Buildings: 33000sqm total
Experiments: • 8 experimental areas, Interaction chambers, Beam transportation
• 8 auxiliary laboratories
4
ELI-Nuclear Physics
ELI-NPMain buildings Lasers
Gamma
Experiments
Laboratories
ELI-Nuclear PhysicsLarge equipments:
• High power laser system, 2 x 10PW maximum power
Thales Optronique SA and SC Thales System Romania
• Gamma beam, high intensity, up to 20MeV, produced by Compton scattering of a laser beam on a 700 MeV electron beam produced by a warm LINAC
EUROGAMMAS (Italy, France, UK, Danemark, Sweden)
Scientific program: • Nuclear Physics experiments to characterize laser – target int.• Photonuclear reactions• Exotic Nuclear Physics and astrophysics • Applied Research
6
Financial aspects
Implementation by EU Structural Funds:• Project Approval: 18.09.2012, Contract with MA: 12.12. 2012
Building 66 M€ Staff 34 M€ Large Equipment 120 M€ Scientific equipment 49 M€ Others 24 M€ Total 293 M€
• EC contribution: 243 M€• National contribution: 50 + 63 + 5 + 4 = 122 M€• Duration/phasing: 2 phases (2012-2015/2014-2017)• 1st phase EC approval : 180 M€
8
White Book (Scientific Case)
Feasibility Study
Preparation of the Application
E.C. Evaluation & Approval
Building - Preparation
Building - Construction
Major Eqp. - Tender
Major Eqp.– Constr, Install
Experimental set-ups
Recruitment
2010 2011 2012 2013 2014 2015
Project implementation
2017
Human Resources
0
50
100
150
200
250
2011 2012 2013 2014 2015 2016 2017 2018
Technical Staff (18)
Eng. Staff (18)PhD students (50)
Jr. researchers (107)
Senior researchers (20)
Head of Res. Activities (5)2013 2014 2015 2016 2017 2018 2019
August 23, 2013
10
August 23, 2013June 14, 2013
September 25, 2013 February 2014
GOVERNMENT OF ROMANIA Structural Instruments2007-2013
EUROPEAN UNION
Infos: http://www.eli-np.ro
March 2014
Management Team
Dir.: N.V. Zamfir
Deputy : Gh. C-DSci. Dir: Sydney GalesTechnical Dir.: C. IvanFinancial: Al. PopescuLegal &HR: R. Stoicea