GEOTHERMAL POWER PLANT DEVELOPMENT IN INDONESIA
Presented at:
“Forum for East Asia-Latin America Cooperation”
November 13th, 2012
Tokyo, Japan
DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION
MINISTRY OF ENERGY AND MINERAL RESOURCES
by:
Jarman Directorate General of New, Renewable Energy and Energy Conservation
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
I. Background
II. Geothermal Policy
III. Geothermal Program
IV. Geothermal Development
V. Investment Opportunities
OUTLINE
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
I. Background
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
BACKGROUND
Geothermal is a thermal energy that naturally formed beneath the earth's surface;
Geothermal energy is a green energy because it produces lower green house gasses (GHG) than fossil fuel. In addition, when managed properly, geothermal is also consider as a renewable energy;
Geothermal energy is site specific, can not be stored, and also can not be transported;
Implementation of geothermal activity in line with the mandate of the Law 1945;
Geothermal utilization are in forms of direct and indirect use;
Authority for geothermal management distributed to Minister, The Governor, and/or Regent/Mayor in accordance with their authority.
Constraints and Barriers:
Pricing Electricity price from geothermal energy still considers has not reached its economical value;
Land-use Issues Geological Agency has been identified that more than 70% of geothermal areas are partially or completely overlapping with forestry areas (conservation forest, protected forest and production forest)
Direktorat Jenderal
EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi
Kementerian Energi dan Sumber Daya Mineral
2011
Oil 20 %
Gas 30 %
Coal 33 %
NRE 17 %
Oil 23,7 %
Gas 19,7 %
Coal 30,7 %
NRE 25,9 %
Gov. Reg.
NO. 5/2006
NEP Draft
By NEC
Note:
NRE = New and Renewable Energy
NEP = National Energy Policy
NEC = National Energy Council
Oil 49,7 %
Gas 20,1 %
Coal 24,5 %
NRE 5,7 %
2025
CURRENT ENERGY CONDITION
BACKGROUND
1. Electrification ratio in 2011 is 72,95%;
2. Energy consumption growth is 7% per year,
which not balance with energy suppy;
3. The dependence on fossil energy is high,
but the energy reserve is limited;
4. Fossil subsidy is increasing;
5. The utilization of renewable energy and
implementation of energy conservation
has not been optimized;
6. Link with environmental issue:
a. Climate change mitigation;
b. Clean energy initiative:
National commitment to reduce emission
by 26% in 2020;
7. Funding for energy development is limited
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
Source : Geological Survey, MEMR(2011)
Already Developed
Ready to Developad
Detail Survey
Preliminary Survey
Note:
RESOURCES (MWe)
% RESERVE (MWe)
%
Speculative Hypothetical
45.17%
Possible Probable Proven
54.83% 8.231 4.964 12.909 823 2.288
13.195 16.020
29.215
GEOTHERMAL POTENTIAL
BACKGROUND
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
II. Geothermal Policy
Direktorat Jenderal
EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi
Kementerian Energi dan Sumber Daya Mineral
Policy Directions:
• The paradigm of national energy management is shifting from Supply Side Management to demand side management Management;
• Supply Side Management on fossil focused energy sources;
• Demand Side Management focused on optimizing energy efficiency and new renewable energy sources;
• The Law No. 30/2007 on Electricity, emphasis on diversification and energy conservation.
Opportunities:
• Environmental issues and sustainable development;
• A paradigmatic shifting in the management of the national energy;
• Indonesia has huge of renewable energy potential;
• High potential for energy savings.
GEOTHERMAL POLICY
Direktorat Jenderal
EBTKE Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi
Kementerian Energi dan Sumber Daya Mineral
9
GEOTHERMAL POLICY
1. Revision of Law 27/2003 on Geothermal:
GoI is revising the law 27/2003 on Geothermal, law 5/1990 on Conservation of Natural Resources, and law 41/1999 on Forestry.
2. MoU Between MEMR – Minister of Forestry
MEMR and Minister of Forestry have signed MoU regarding the acceleration of geothermal utilization permit within production forest, protected forest, and conservation forest .
3. Feed-in Tariff:
Feed-in Tariff is a Government policy to set the price of electricity from geothermal power plant which is final and can not be negotiated by PT. PLN
4. Funding incentives : • Government guarantee on the feasibility of PT. PLN; • “Geothermal Fund" for geothermal exploration; • Green Banking Program.
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
III.Geothermal Program
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
Development 2010 2011 2012 2013 2014 2015
Geothermal Development
1. Added Capacity (MW) 37 115 3 375 1.797
2. Installed Capacity (MW) 1.189 1.226 1.341 1.344 1.719 3.516
GEOTHERMAL PROGRAM POWER PLANT DEVELOPMENT 2010 – 2015
Note:
- Capacity Factor of Geothermal Power Plant = 90%
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
No Geothermal Working Area (GWA) Location Potential Capacity
(MW)
1 Gn. Talang West Sumatera 36
2 Songa Wayaua North Maluku 140
3 Danau Ranau Lampung & South
Sumatera 210
4 Mataloko East Nusa Tenggara 63
5 Gn. Endut Banten 80
6 Way Ratai Lampung 105
7 Candi Umbul Telomoyo Central Java 72
8 Simbolon Samosir North Sumatera 155
9 Bora Pulu Central Sulawesi 123
10 Gn. Lawu Central Java 195
GEOTHERMAL WORKING AREA FOR TENDER
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
PRELIMINARY SURVEY ASSIGNMENT’S AREA 2012
No Geothermal Working Area (GWA) District/ City Province
1 Gn. Hamiding West Halmahera, North Halmahera North Maluku
2 Pentadio Gorontalo, Bone Bolango, Gorontalo
City' Gorontalo
3 Graho Nyabu Merangin, Kerinci, Muko-Muko Jambi and Bengkulu
4 Gn. Wilis Ponorogo, Madiun, Nganjuk, Kediri,
Tulungagung, Trenggalek East Java
5 Gn. Geureudong Central Aceh, Bener Meriah, North
Aceh Nanggroe Aceh Darussalam
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
IV.Geothermal Development
©2012
Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
15
ACEH 2 WKP
Jaboi: 70 MW
Seulawah Agam: 130 MW
NORTH SUMATERA 5 WKP
Sibayak – Sinabung: 130 MW
Sibual – Buali: 750 MW
Sipaholon Ria-ria: 75 MW
Sorik Marapi: 200 MW
Simbolon Samosir : 155 MW
JAMBI 1 WKP
Sungai Penuh: 70 MW
SOUTH SUMATERA 3 WKP
Lumut Balai: 250 MW
Rantau Dedap: 106 MW
Danau Ranau: 210 MW
BANTEN 2 WKP
Kaldera Danau Banten: 115 MW
G. Endut: 80 MW
WEST SUMATERA 4 WKP
Bukit Kili: 83 MW
Gn Talang: 35 MW
Liki Pinangawan: 400 MW
Bonjol: 200 MW
BENGKULU 2 WKP
Tmbg Sawah-Hululais: 873 MW
Kepahiang: 180 MW
LAMPUNG 4 WKP
Gn.Rajabasa: 91 MW
Suoh Sekincau: 230 MW
Waypanas – Ulubelu: 556 MW
Danau Ranau: 210 MW
Way Ratai :105 MW
WEST JAVA 10 WKP
Ciater - Tgkban Perahu: 60 MW
Cibeureum–Parabakti: 485 MW
Cibuni: 140 MW
Cisolok Cisukarame: 45 MW
Gn. Tampomas: 50 MW
Gn. Tgkuban Perahu: 100 MW
Kamojang-Darajat: 1465 MW
Karaha Cakrabuana: 725 MW
Pangalengan: 1106 MW
G. Ciremai: 150 MW
CENTRAL JAVA 5 WKP
Baturaden: 175 MW
Dataran Tinggi Dieng: 780 MW
Guci: 79 MW
Gn. Ungaran: 100 MW
Umbul Telomoyo : 120 MW
EAST JAVA 3 WKP
Blawan – Ijen: 270 MW
Gn. Iyang Argopuro: 295 MW
Telaga Ngebel: 120 MW
Gn. Lawu: 195 MW
BALI 1 WKP
Tabanan: 276 MW
WEST NUSA
TENGGARA 2 WKP
Hu'u Daha: 65 MW
Sembalun: 100 MW
EAST NUSA TENGGARA 5 WKP
Atadei: 40 MW
Sokoria: 30 MW
Ulumbu: 199 MW
Mataloko: 63 MW
Oka Ile Ange: 40 MW
MALUKU 1 WKP
Tulehu: 100 MW
NORTH MALUKU 2 WKP
Jailolo: 75 MW
Songa Wayaua: 140 MW
NORTH SULAWESI 2 WKP
Kotamobagu: 410 MW
Lahendong-Tompaso: 358 MW
GORONTALO 1 WKP
Suwawa: 110 MW
CENTRAL SULAWESI 2 WKP
Marana: 35 MW
Bora Pulu : 152 MW
Total : 58 GWA
Distribution of GWA
GEOTHERMAL DEVELOPMENT
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
Presidential Regulation No. 04/2010 on Assignment to PT. PLN to Accelerate Power Plant Development Using Renewable Energy, Coal and Gas
MEMR Regulation No. 01/2012 as revised in Ministerial Regulation No. 15/2010 on Projects List of Power Plant Accelerated Development using Renewable Energy, Coal and Gas as well as Related Transmission
Target for Geothermal Power Plant Development on Crash Program 10.000 MW Phase II
Existing field (on Production Phase) : 465 MW
Existing field (not on Production Phase) : 1535 MW
New Geothermal Working Area : 2925 MW
Total of Geothermal Development 4925 MW
GEOTHERMAL DEVELOPMENT TARGET
(2010 - 2014)
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
V. Investment Opportunities
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
The development of 4,925 MW electricity from Geothermal in Second Phase Crash Program 10,000 MW up to the year 2014 requires more than US$ 14,000 millions for the investment.
The development plan of 12,000 MW Geothermal Power Plant up to the year 2025, international supports are needed.
Foreign ownership in Geothermal Business is allowed up to 95 %;
Access to Potential Geothermal Resources for Investors: - Preliminary Survey Assignment - Participate in the geothermal business through GWAs tendering mechanism
Other business opportunities in geothermal sector: Geothermal direct use;
Low temperature geothermal potential;
Small scale power plant;
CER under CDM Scheme;
Services company to support the core business of geothermal.
INVESTMENT OPPORTUNITIES
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
Go Green Indonesia ! green energy, future energy
Jalan Jenderal Gatot Subroto, Kav. 49 Jakarta 12950; Telp: 021-52904235; 5250575; Faks: 021-25529106; 25529212
Email: [email protected] ; [email protected]
MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA
DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY, AND ENERGY CONSERVATION
Thank You
www.ebtke.esdm.go.id
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
No. Geothermal Working
Area/ Location License Holder Developer Power Plant
Installed
Capacity
(MW)
1 Sibayak – Sinabung,
NORTH SUMATERA
PT. Pertamina Geothermal
Energy (PGE)
PT. Pertamina Geothermal
Energy (PGE) Sibayak 12
2 Cibeureum – Parabakti,
WEST JAVA
PT. Pertamina Geothermal
Energy (PGE)
KOB - Chevron Geothermal
Salak, Ltd (CGS) Salak 377
3 Pangalengan,
WEST JAVA
PT. Pertamina Geothermal
Energy (PGE)
KOB - Star Energy
Geothermal Wayang
Windu, Ltd (SEGWWL)
Wayang
Windu 227
4 Kamojang – Darajat,
WEST JAVA
PT. Pertamina Geothermal
Energy (PGE)
PT. Pertamina Geothermal
Energy (PGE) Kamojang 200
5 Kamojang – Darajat,
WEST JAVA
PT. Pertamina Geothermal
Energy (PGE)
KOB - Chevron Geothermal
Indonesia, Ltd (CGI) Darajat 270
6 Dataran Tinggi Dieng,
CENTRAL JAVA
PT. Pertamina Geothermal
Energy (PGE) PT. Geo Dipa Energi (GDE) Dieng 60
7 Lahendong – Tompaso,
NORTH SULAWESI
PT. Pertamina Geothermal
Energy (PGE)
PT. Pertamina Geothermal
Energy (PGE) Lahendong 80
8 Ulubelu,
LAMPUNG
PT. Pertamina Geothermal
Energy (PGE)
PT. Pertamina Geothermal
Energy (PGE) Ulubelu 55
1.281 20
INSTALLED GEOTHERMAL POWER PLANT CAPACITY 2012
©2012
Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
MEMR
Prov.
Govmt.
Corporation
PLN
WKP
Determination Pre-Survey WKP
Tendering
IUP
Issuance
Electricity
Price
Rep
ort o
f
Ten
derin
g
Pro
cess
Geo
therm
al
Po
tential
Potential
Map Survey
APBN
Survey
APBD
Prov.
Other
Parties
Assignment
Evaluation WKP Report WKP-N
WKP-P
WKP-K
(S3-N)
(S3-P)
(S3-K)
IUP-N
IUP-P
IUP-K
(S4-N)
(S4-P)
(S4-K)
Tender Winner
GEOTHERMAL VALUE CHAIN
(S-1) (S-2) (S-3) (S-4) (S-5)
PPA
(S-6)
Assignment
Exp
loratio
n
(S-7)
Exp
lora
tio
n
(Current Regulations)
(S-0)
BUSINESS STADIUM (S-X)
Survey
APBD
Kab./
Kota
Local
Govmt.
(Regent/
City)
© DJEBTKE – KESDM 2012
Units
Potential/
Stadium Exp
loitatio
n
FS Production/
Utilization
(S-8) (S-9) (S-10)
FS
Exp
loit
atio
n
Pro
du
ctio
n/
Uti
lizat
ion
Tender Winner
Tender Winner
Report
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
Road Map of Geothermal Development 2006 – 2025
Current Condition
2006
852 MW
(Produksi)
2008 2012 2016 2020
2000 MW 3442 MW 4600 MW 6000 MW 9500 MW
(Target)
1148 MW
Existing WKP
1442 MW
Existing WKP
1158 MW
Existing WKP
+ New WKP
1400 MW
New WKP
3500 MW
New WKP
2025
1.281 MW
(based on Presidential Decree No. 5/2006 on National Energy Policy)
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
GEOTHERMAL POWER PLANT PROJECTS INCLUDED IN CRASH PROGRAM PHASE II (Based on MEMR Regulaton No. 01/2012)
NO.GEOTHERMAL POWER
PLANT PROJECTSTATUS PROVINCE
ESTIMATION
OF CAPACITY
(MW)
1 Sungai Penuh Existing WKP Jambi 2x55
2 Hululais Existing WKP Bengkulu 2x55
3 Kotamobagu 1 and 2 Existing WKP North Sulawesi 2x20
4 Kotamobagu 3 and 4 Existing WKP North Sulawesi 2x20
5 Sembalun Open Area West Nusa Tenggara 2x10
6 Tulehu Existing WKP Maluku 2x10
7 Tangkuban Perahu I New WKP West Java 2x55
8 Kamojang 5 and 6 Existing WKP West Java 1 x30 1 x60
9 Ijen New WKP East Java 2x55
10 Iyang Argopuro Existing WKP East Java 1 x55
11 Ngebel New WKP East Java 3x55
12 Gunung Endut New WKP Banten 1 x55
13 Rawa Dano New WKP Banten 1 x 110
14 Cibuni Existing WKP West Java 1 x 10
15 Cisolok-Cisukarame New WKP West Java 1 x50
16 Karaha Bodas Existing WKP West Java 1 x30 2x55
17 Patuha Existing WKP West Java 3x60
18 Tampomas New WKP West Java 1 x45
19 Tangkuban Perahu II Existing WKP West Java 2x30
20 Wayang Windu Unit 3 and 4 Existing WKP West Java 2x 110
21 Gunung Ciremai New WKP West Java 2 x 55
22 Baturaden New WKP Central Java 2x 110
23 Dieng Existing WKP Central Java 1 x55 1 x60
24 Guci New WKP Central Java 1 x55
25 Ungaran New WKP Central Java 1 x55
26 Seulawah Agam New WKP Aceh 1X55
NO.GEOTHERMAL POWER
PLANT PROJECTSTATUS PROVINCE
ESTIMATION
OF CAPACITY
(MW)
27 Jaboi New WKP Aceh 2x5
28 Sarulla 1 Existing WKP North Sumatera 3x 110
29 Sarulla 2 Existing WKP North Sumatera 2x55
30 Umbul Telumoyo New WKP Central Java 1 x55
31 Simbolon Samosir Open Area North Sumatera 2x55
32 Sipoholon Ria-Ria New WKP North Sumatera 1 x55
33 Sorik Marapi New WKP North Sumatera 240 (Total)
34 Muaralaboh New WKP West Sumatera 2x 110
35 Bonjol New WKP West Sumatera 3x55
36 Lumut Balai Existing WKP South Sumatera 4x55
37 Rantau Dadap New WKP South Sumatera 2x110
38 Rajabasa New WKP Lampung 2x110
39 Ulubelu 3 and 4 Existing WKP Lampung 2x55
40 Suoh Sekincau New WKP Lampung 4x55
41 Wai Ratai Open Area Lampung 1 x55
42 Danau Ranau New WKP Lampung 2x55
43 Lahendong 5 dan 6 Existing WKP North Sulawesi 2x20
44 Bora Open Area Central Sulawesi 1 x5
45 Marana/Masaingi New WKP Central Sulawesi 2x10
46 Hu'u New WKP West Nusa Tenggara 2x10
47 Atadei New WKP East Nusa Tenggara 2 x2,5
48 Sokoria New WKP East Nusa Tenggara 3x5
49 Mataloko New WKP East Nusa Tenggara 1 x5
50 Jailolo New WKP North Maluku 2x5
51 Songa Wayaua New WKP North Maluku 1 x5
TOTAL PLANNED INSTALLED CAPACITY 4925
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
President Decree No 45/1991, No 49/1991, and No 23/1992
Business structure based on JOC and ESC 34% of Net Operating Income (NOI), that had included all kinds of taxes and retribution, except personal tax. Project Management : Under Pertamina (JOC) and PLN (ESC) Project Type:
Total (Integrated) Project Partial Project
Law No. 27/2003
Business structure in the form of Permit: Geothermal Mining Permit Enterprise Permit for Electricity
Obligation to pay for taxes and royalty Project Management : Under Permit Holder Project Type: Total (Integrated) Project GWA holder will be granted as generally plan
operation
Implementation of Geothermal Policies
Existing GWA New GWA
24
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
1. Law No. 27/2003 on Geothermal
2. Government Regulation (GR) No. 59/2007 on Geothermal Business Activities, as amanded in GR No. 70/2010
3. GR No. 62/2008 jo. GR No. 1/2007 on Income Tax Facilities for Investment in Certain Business Areas and / or in Specific Regions
4. GR No. 9/2012 on Types And Tariffs On Non-tax State Revenue Applicable to The Ministry Of Energy And Mineral Resources
5. Presidential Regulation No. 04/2010 on Assignment to PT. PLN (Persero) to Accelerate The Development of Power Plant from Renewable Energy, Coal and Gas
6. Ministry Regulation (MR) of Minister Energy And Mineral Resources
1) MR No. 11/2008 on the Procedure for Determination Geothermal Working Area
2) MR No. 02/2009 on Guidelines for Geothermal Preliminary Survey Assignment (as amendment of MR. 05/2007)
3) MR No. 11/2009 on Guidelines for Implementation of Geothermal Business , jo. MR No. 18/2012
GEOTHERMAL REGULATION
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
4) MR No. 01/2012 on Revision of MR No. 15/2010 on The List of Power Plant Acceleration Projects Using Renewable Energy, Coal, and Gas and Related Transmission
5) MR No. 22/2012 on Assignment to PT PLN (Persero) to Purchase Electricity from Geothermal Power Plant and Geothermal Power Purchase Benchmark Price by PT PLN (Persero)
7. Ministry Regulation of Minister of Finance
1) No. 139/PMK.011/2011 on Procedures for Granting Business-Feasibility Guarantee to PT PLN (Persero) for The Development or Renewable Energy, Coal and Gas-Fueled Power Plants Through Cooperation With The Independent Power Producers
2) No. 03/PMK.011/2012 on Procedures for the Management and Accountability Geothermal Facility Fund
..Continue
Direktorat Jenderal
EBTKE Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
No Area
Price (cent US$/kWh)
High Voltage
Medium Voltage
1 Sumatera 10 11,5
2 Java, Madura and Bali 11 12,5
3 South Sulawesi, West Sulawesi, and
Southeast Sulawesi
12 13,5
4 North Sulawesi, Central Sulawesi, and
Gorontalo
13 14,5
5 West Nusa Tenggara, and East Nusa
Tenggara
15 16,5
6 Maluku and Papua 17 18,5
GEOTHERMAL FEED-IN TARIFF
©2012
Ministry of Energy and Mineral Resources
Directorate General of New Renewable Energy and Energy Conservation
The Feed-in Tariffs mechanism will be applied to :
a. geothermal license holders (IUP holder) after the issuance of Minister Regulation No. 22/2012;
b. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who already have Power Purchase Agreement (PPA), which will increase power plant capacity on the existing agreement (PPA);
c. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who will extend their expired PPA;
d. mining right holders, license holder or concession holder that existed before the enactment of Law No. 27 Year 2003 on Geothermal who already have PPA, for both who have produced or not yet produced electricity or steam, as long as all parties involved agree upon the amendment on sales price of electricity or steam; or
e. IUP holder who will undertake PPA, as long as agreed by the parties involved and allowed by PPA to be agreed by the parties.
Feed in Tariff Mechanism