Updated 07/28/2015
Printed 02/11/2020 Page 1 of 3 Project No. 46137 – C, H, P, E
DESIGN AND CONSTRUCTION GROUP
THE GOVERNOR NELSON A. ROCKEFELLER
EMPIRE STATE PLAZA
ALBANY, NY 12242
ADDENDUM NO. 1 TO PROJECT NO. 46137
CONSTRUCTION, HVAC, PLUMBING AND ELECTRICAL WORK
PROVIDE NEW ADDITION
CLASSROOMS & OFFICE SPACES
BUILDING 118
RESIDENTIAL REHABILITATION UNIT
BEDFORD HILLS CORRECTIONAL FACILITY
247 HARRIS RD
BEDFORD HILLS, NY
February 11, 2020
NOTE:This Addendum forms a part of the Contract Documents. Insert it in the Project Manual.
Acknowledge receipt of this Addendum in the space provided on the Bid Form.
CONSTRUCTION SPECIFICATIONS
1. 111901 DETENTION EQUIPMENT
A. Delete Section 111901 in its entirety. Replace with the updated Section 111901 that
accompanies this addendum.
GENERAL DRAWINGS
2. Drawing No. G-001
A. INDEX OF DRAWINGS
1) Delete PLUMBING drawing sheet 55:
“P-105 SUB-GRADE PASSIVE DEPRESSURIZATION SYSTEM”
2) Add CONSTRUCTION drawing sheet 43A:
“P-105 SUB-GRADE PASSIVE DEPRESSURIZATION SYSTEM”
3) Add ELECTRICAL drawing sheet 47A:
“E-504 DETAILS”
B. KEY PLAN
1) Revised Key Plan Drawing No. AD-01.01 02/06/2020 accompanies this
Addendum.
ADDENDUM NO. 1 TO PROJECT NO. 46137
Created 05/19/2009
Edited and/or Printed 02/11/2020 Page 2 of 3 Project No. 46137 – C, H. P. E
CONSTRUCTION DRAWINGS
3. Drawing No. C-002:
A. STORAGE AND STAGING PLAN: Change note “CONTRACTOR STAGING AREA
WITH TEMPORARY BARRIER FENCE” to “CONTRACTOR STAGING AREA
WITH TEMPORARY SECURE FENCE”.
4. Drawing No. S-101:
A. Revise per Drawing No. AD-01.05 which accompanies this Addendum.
B. Delete Note: “4” PVC GAS COLLECTION PIPING PROVIDED BY P-CONTRACT”
Add Note: “4” PVC GAS COLLECTION PIPING”
5. Drawing No. S-301 – Details 1, 2, 3 and 7:
A. Delete Note: “4” PVC GAS COLLECTION PIPING PROVIDED BY P-CONTRACT”
Add Note: “4” PVC GAS COLLECTION PIPING”
6. Drawing No. A-103:
A. SYMBOLS LEGEND: Revise as follows:
1) Delete: SURFACE MOUNTED 24X48 LIGHT FIXTURE
Add: RECESSED 24X48 LIGHT FIXTURE
2) Delete: SURFACE MOUNTED 12X48 LIGHT FIXTURE
Add: RECESSED 12X48 LIGHT FIXTURE
7. Drawing No. A-402:
A. Detail 4/A-402 add General Note: “SCAN SLAB TO VERIFY LOCATIONS OF ALL
IN SLAB REINFORCEMENT AND CONDUITS”
8. Revised Drawing:
A. Drawing No. A-510, noted “REVISED DRAWING A-510 02/06/2020”, accompanies
this Addendum and supersedes the same numbered originally issued drawing.
9. Revised Drawing:
A. Drawing No. A-601, noted “REVISED DRAWING A-601 02/06/2020”, accompanies
this Addendum and supersedes the same numbered originally issued drawing.
10. Drawing No. A-602:
A. Revise per Drawing No. AD-01.06 which accompanies this Addendum.
11. Revised Drawing:
A. Drawing No. P-105, noted “REVISED DRAWING P-105 02/06/2020”, accompanies this
Addendum and supersedes the same numbered originally issued drawing.
B. P-105 is revised and is now included in the C-Contract scope of work.
ADDENDUM NO. 1 TO PROJECT NO. 46137
Created 05/19/2009
Edited and/or Printed 02/11/2020 Page 3 of 3 Project No. 46137 – C, H. P. E
PLUMBING DRAWINGS
12. Revised Drawing:
A. P-105 is revised and is removed from the P-Contract scope of work. P-105 is now
included in the C-Contract scope of work.
ELECTRICAL DRAWINGS
13. Drawing No. E-101:
A. Detail 2 / E-101 REFERENCE PHOTOS is revised for clarity with Drawing No’s.: AD-
01.02, AD-01.03 and AD-01.04 dated 02/06/2020 which accompanies this Addendum.
14. Drawing No. E-601:
A. Receptacle Tag Schedule: Add “General Note. 1: Provide 10 gauge security faceplates
for receptacles within corridors and classrooms.”
B. Switch Tag Schedule: Add “General Note. 1: Provide 10 gauge security faceplates for
switches within corridors and classrooms.”
15. Revised Drawing:
A. Drawing No. E-104, noted “REVISED DRAWING 02/10/2020” accompanies this
Addendum and supersedes the same numbered originally issued drawings.
16. Add Drawing:
A. New Drawing No. E-504 accompanies this Addendum and forms part of the Contract
Documents.
END OF ADDENDUM
Erik T. Deyoe, P.E.
Director, Division of Design
Design & Construction
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 1 Project No. 46137-C
SECTION 111901
DETENTION EQUIPMENT
PART 1 GENERAL
1.01 PRODUCTS PROVIDED BY OTHERS
A. Power Wiring to Control Consoles: Electrical Work Contract.
1.02 RELATED WORK SPECIFIED ELSEWHERE
A. Steel Doors And Frames: Section 081102.
B. Finish Hardware: Section 087100.
C. Security Glazing: Section 088853.
D. Construction Painting: Section 099101
E. Wiring For Detention Equipment Systems: Section 260506.
1.03 REFERENCES
A. Welding Standards: Structural Welding Code - Steel, AWS D1.1 or Structural
Welding Code - Sheet Steel, AWS D1.3, as applicable, by the American Welding
Society (AWS Codes).
B. Materials and Finishes Standards:
1. ANSI/BHMA A156.18-2016, American National Standard for Materials
and Finishes.
C. ASTM-American Society for Testing Materials:1. ASTM A1008/A1008M-2018 Standard Specification for Steel, Sheet,
Cold- Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low Alloy with Improved Formability, Solution Hardened, and Bake Hardenable.
2. ASTM A1011A/A1011M-2018a Standard Specification for Steel, Sheet and Strip, Carbon, Hot Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low Alloy with Improved Formability, and Ultra-High Strength.
3. ASTM A653/653M-2019a Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy Coated (Galvannealed) by the Hot Dip Process.
D. Conform to the requirements of the National Electric Code.
1.04 DEFINITIONS
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 2 Project No. 46137-C
A. Technical Advisor(s): Full time employee of the Company that manufactures
both electric and mechanical, detention equipment and systems, and detention
hardware and accessories, who is certified in writing by the Company to be
technically qualified in the design, installation, operation, and servicing of the
required products.
B. Benchmark: Detention door and frame assembly of each type that is constructed
on-site. Benchmarks are constructed to verify quality of materials and execution;
to review coordination between frames, doors, and hardware; to demonstrate the
relationship between partitions and frames; and to demonstrate compliance with
specified clearances and tolerances. Benchmarks are not samples. Unless
otherwise indicated, approved benchmarks establish the standard by which the
Work will be judged. The approved benchmark may be incorporated into the
work of this section
1.05 SUBMITTALS
A. Waiver of Submittals: The Waiver of Certain Submittal Requirements in
Section 013300 does not apply to this Section.
B. Submittal Packages: Submit the entire Quality Assurance Package prior to other
submittal packages. After Quality Assurance Package is approved, submit the
Detention Equipment Package, Detention Hardware Package, and the Power and
Control Wiring Package specified below at the same time.
C. Quality Assurance Package:
1. Equipment Manufacturer’s Qualifications:
a. Name, business address and telephone numbers of the
Equipment Manufacturer.
b. Names, addresses and telephone numbers of facility contacts of
5 similar projects where manufacturer’s detention equipment
and hardware has been in operation for a minimum of 3 years.
2. Equipment Installation Company Qualifications:
a. Name, business address and telephone numbers of the
installation company.
b. Provide a comprehensive history of the Installation Company.
c. Names, addresses and telephone numbers of facility contacts of
5 similar projects company has completed in past 3 years.
d. Current written certification from the detention equipment
manufacturer the company installing the Work has successfully
completed factory training and is qualified as a Detention
Equipment Contractor.
3. Equipment Installer’s Qualifications:
a. Name of person providing full time on-site supervision of the
installation and completion of Work of this section.
b. If the person providing full time on-site supervision changes
after submittal approval, submit the qualifications for the new
onsite supervisor.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 3 Project No. 46137-C
c. Names, addresses and telephone numbers of facility contacts of
5 similar projects this person has supervised in the past 3 years.
d. Current written certification from the detention equipment
manufacturer the person providing on-site supervision of the
Work has successfully completed training and is qualified in the
installation of the accepted detention products.
4. Power and Control Wiring Installation Company Qualification:
a. Name, address and telephone numbers of the installation
company.
b. Provide a comprehensive history of the Installation Company.
c. Names, addresses and facility contacts of 5 similar projects the
installation company has completed in the past 3 years.
5. Power and Control Wiring Installer’s Qualifications:
a. Name of person providing full time on-site supervision of the
installation and completion of the Work of this section.
b. If the person providing full time on-site supervision changes
after submittal approval, submit the qualifications for the new
onsite supervisor.
c. Names, addresses and telephone numbers of facility contacts of
5 similar projects this person has supervised in the past 3 years
6. Technical Advisor’s Qualifications:
a. Name, business address and telephone numbers of technical
advisor(s).
b. If the technical advisor(s) changes after submittal approval,
submit the qualifications for the new onsite supervisor.
c. Written certification from detention equipment and detention
hardware manufacturers that advisor is technically qualified in
design, installation and servicing of products.
D. Detention Equipment Package:
1. Shop Drawings: Show relationship of detention equipment with other
Work.
a. Complete detailed drawings for each style of door/gate required.
Include separate schedule for each. List materials required, and
technical data including size, and finish to ensure conformance
to specifications. Include details of all major components and
show accessories. Include parts list showing manufacturers’
names and part numbers for the complete installation.
b. Include details of lock mountings.
c. Indicate shop and field welds by standard AWS welding
symbols.
d. For doors/gates to be installed in existing openings, field
measure existing gate openings and other conditions, and
indicate existing information on shop drawings. Include date(s)
and name(s) of person(s) performing field verifications.
e. Complete detailed drawings for each console/panel required.
Indicate technical data, including size and finishes, to ensure
conformance to specifications. Show relationship of all required
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 4 Project No. 46137-C
components with respect to the console housing. Include parts
list showing manufacturers’ names and part numbers for the
complete installation.
1) Drawings shall be dimensioned showing location of
each item (switch, LED, nameplate, etc.) mounted to the
control console/panel top (faceplate) and cut-out
locations.
2) Include scale drawing showing location of all
components which are to be located within and in the
control console/panel.
2. Product Data: Current catalog sheets, specifications and installation
instructions for accessories. Identify each item and component.
E. Detention Hardware Package:
1. Hardware Schedule: Use a vertical schedule layout. Horizontal
hardware schedules are not acceptable
2. Preface the schedule with the following:
a. Door Index
b. List of Manufacturers
c. List and explanation of finishes
d. List and explanation of abbreviations.
e. Keying schedule, keying instructions and key code. Include the
type lock used for the individual openings.
3. For Each Opening Include the Following:
a. Material and dimensions of doors, frames and gates.
b. Location and Handing
c. Fire Rating.
d. Detention hardware required to complete the Work of this
Section.
4. Create detention hardware groups, each group consisting of similar
detention doors and detention hardware. Do not combine labeled and
non-labeled openings.
a. Arrange by Buildings if required, and in groups; each group
consisting of similar doors gates and hardware.
b. Include manufacturers’ names, catalog numbers, sizes and
finishes.
c. Product quantities are not checked for accuracy.
5. Under each group heading, list hardware items in detail required for
ordering. For each item Include:
a. Quantity (3 ea)
b. Type (3 ea Hinges)
c. Manufacturers’ Name (3 ea Hinges Brookfield)
d. Size and Catalog number (3 ea Hinges Brookfield I-8513)
e. Accessories and options (3 ea Hinges Brookfield I-8513 x
application “C”).
f. Finish (3 ea Hinges Brookfield I-8513 x application “C” x
US32D.
g. Fasteners (3 ea Hinges Brookfield I-8513 x application “C” x
US32D x Torx)
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 5 Project No. 46137-C
6. Product Data: Furnish 2 current Manufacturer’s Catalog sheets,
specifications, templates, and installation instructions for each item of
detention hardware required to complete Work of this Section. Identify
and highlight information pertaining specifically the items and
components submitted for this project.
F. Power and Control Wiring Package:
1. Shop Drawings:
a. Wiring Diagrams: Include wiring diagrams of the complete
system as proposed to be installed.
1) Standard diagrams will not be acceptable.
2) Wiring diagrams showing point-to-point connections to
electrical components specified, including power and
control wiring within the control console/panel.
3) Include in the diagrams connections between the
components (locking devices, locks, position switches,
etc.) affected and the control console/panel.
4) Include connections to the control console/panel.
2. Product Data:
a. Bill of Materials: Provide a Bill of Materials identifying each
system device or component proposed to be used for this system
as listed in PART 2 PRODUCTS of this section. The Bill of
Materials shall provide the following information:
1) Identify each item by name and model number.
2) Indicate the page number(s) in the Submittal Package
where information required for that item can be found.
3) Identify the appropriate specification section, Article
number, paragraph and subparagraph where that item is
listed in the project manual.
b. Current catalog sheets, specifications and installation
instructions for each system device or component proposed for
use as listed in PART 2 PRODUCTS of this section and as listed
in the Bill of Materials.
1) Catalog sheets shall be marked up by the contractor to
clearly identify exact what item is being submitted for
approval and marked up clearly indicating what options
the item will have to meet the contract requirements.
3. Detailed sequence of operations. Submit in a format similar to
Description of Completed System.
G. Contract Closeout Submittals:
1. Operation and Maintenance Data for Detention Equipment: In addition
to the electronic submission, deliver 3 hard copies of instructions for
operation, maintenance recommendations, and parts manuals covering
the installed products to the Director’s Representative.
2. Operation and Maintenance Data for Detention Hardware: In addition to
the electronic submission, deliver 3 hard copies of instructions,
maintenance, and parts manuals covering the installed products to the
Director’s Representative.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 6 Project No. 46137-C
3. Operation and Maintenance Data for Power and Control Wiring
Products:
a. In addition to the electronic submission deliver 3 hard copies of
instructions, maintenance recommendations, and parts manuals
covering each of the installed products to the Director’s
Representative.
b. Electronically and in hard copy furnish a comprehensive,
complete point-to-point wiring diagram of the entire system as
installed. Number all conductors, (numbers shall correspond to
numbered tags installed on each conductor) and show all
termination points.
4. Final Systems Testing Report and Certification of Proper Operation:
Submit electronically and deliver hard copy to the Director’s
Representative written certification from the detention equipment
manufacturer(s) that the detention equipment systems, the detention
locks, and the accessories are installed correctly and operating properly.
Certification to include name of person(s) performing the inspection,
date(s) performed, a listing of locations inspected, functions tested, and a
confirmation that all required corrections or adjustments have been
satisfactorily completed.
5. Spare components and maintenance kit.
1.06 TEMPLATES
A. After receipt of approved submittals, furnish current required templates to the
affected trades to enable the fabricators to make proper provision for hardware
without delaying job progress.
1.07 QUALITY ASSURANCE
A. Equipment Manufacturer’s Qualifications: The manufacturer of detention
hardware, detention equipment, and control consoles shall be regularly engaged
in the production of such products, shall have furnished such products for 5
similar projects that have been in operation for a minimum of 3 years, and is
subject to the Director’s approval.
B. Installation Company Qualifications: The Company installing the Work of this
Section shall hold current written certification as an approved Detention
Equipment Contractor from the approved Detention Equipment Manufacturer
and shall be experienced in detention equipment work, and shall have been
engaged in the assembly and installation of detention equipment for a minimum
of 3 years.
C. Installer’s Qualifications: The person(s) installing and providing full time on-site
supervision of the Work of this Section shall be experienced in detention
equipment work, shall hold current written certification from the Detention
Equipment Manufacturer that they have successfully completed training and are
qualified in the installation of the accepted detention products, and shall have
been engaged in the assembly and supervision of installation of detention
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 7 Project No. 46137-C
equipment for a minimum of 3 years.
D. Power and Control Wiring Installation Company Qualifications: The Company
installing the Work of this Section shall be experienced in control wiring for
detention work and shall have been engaged in the installation of detention
power and control wiring for a minimum of 3 years.
E. Power and Control Wiring Installer’s Qualifications: The electrician(s)
installing and providing full time on-site supervision of the power and control
wiring for and in cabinets, detention devices and equipment in this Section
including shop fabrication and field wiring shall be experienced in detention
wiring, shall have been engaged in wiring detention operating device systems,
control panels, and emergency release cabinets for a minimum of 3 years.
F. Technical Advisor: In addition to being present via teleconference for the Pre-
Installation Conference, upon request secure the services of a Technical Advisor
for a one site inspection for the following:
1. Render technical assistance to the Installer regarding installation
procedures of the detention equipment.
2. Familiarize the Director’s Representative with the aspects of proper
installation and operation of the detention equipment.
3. Answer questions which might arise.
4. Witness final systems test and certify with an affidavit that the system is
installed correctly and is operating properly.
G. Pre-Delivery Inspection: Before the detention equipment is scheduled to be
delivered to the site, and prior to the second door skin being attached to the
doors, the Director’s Representative will call a conference at the Detention Door
and Frame manufacturer’s warehouse for the purpose of inspecting the doors,
frames, and hardware; reviewing the Contract Documents, shop drawings,
approved submissions, and the requirements of the Work. The Physical Security
Consultant Designer, Consultant Designers, OGS Project Team Leader, Project
Manager, and in-house Physical Security Reviewers, OGS Engineer-in- Charge
shall attend. Other participants may be invited at the discretion of the Director.
H. Pre Delivery Control Cabinet, Control Console (Consolet), and/or control
Panel/Housing Inspections:
1. Before the control cabinet, control console, and/or control panel/housing
is delivered to the site, the Director’s Representative will call a
conference at the Control Cabinet, Control Console (Consolet) at the
manufacturer’s warehouse. The purpose of the inspection is to confirm
fabrication according to the approved shop drawing submittals and
conformance with applicable referenced Codes regarding materials,
methods, and workmanship. The Physical Security Design Consultant,
the OGS Physical and Electronic Security Reviewers, the Team Leader,
and the Project Manager shall attend. Other participants may be invited
at the discretion of the Director. Upon inspection and approval, the
control cabinet, control console, and/or control panel/housing assemblies
may be delivered to the Site for installation.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 8 Project No. 46137-C
I. Pre-Installation and Pre-Benchmark Installation Conference: Once the Detention
Equipment is delivered to the site and prior to the construction of the Benchmark
Installation, a meeting will be held at the site to review the requirements and
discuss the intent of the Benchmark. The meeting will be scheduled by the
Director’s Representative and conducted by the Physical Security Designer and
Reviewer. The OGS Physical Security Reviewer, OGS Team Leader, OGS
Project Manager, Contractor’s on -site Foreman, Detention equipment installers,
and Power and Control Wiring installer shall attend. Other participants may be
invited at the discretion of the Director.
J. Construction of Benchmark: Before installing portions of the Work requiring
benchmarks, install benchmarks for each form of construction required to
comply with the following requirements, using materials indicated for the
completed Work.
1. Install a detention door, frame, and hardware assembly of each type
specified in this section, in locations as directed, and include hinges,
locksets, closer, surface overhead stop and gaskets.
2. Notify the Director’s Representative in advance of dates and times when
benchmark will be constructed.
3. Install benchmark with supervisor oversight and workers who will be
employed during the construction of the Work.
4. Construct benchmarks using the exact materials, products, methods, and
workmanship that were approved for the Work.
5. Obtain Director’s Representative’s written approval of benchmarks
before proceeding with work.
6. Maintain benchmarks during construction in an undisturbed condition as
a standard for judging the completed Work.
7. Failure to maintain this standard of quality will be cause for rejection of
the Work.
8. Benchmark may be used in the Work unless otherwise indicated.
K. Galvanizing Stamp: Stamp galvanized items with name of the galvanizer, weight
of coating, and applicable ASTM number.
L. Uniformity of Detention Equipment Systems: Provide detention equipment
systems specified in this Section from the same manufacturer.
1. Provide Folger Adam detention equipment manufactured by
Southern Folger Detention Equipment Company.
M. Construction Verification: In order to confirm the products furnished complywith the specifications, the Director’s Representative will choose one door andframe, of each type, at random for examination. The examination will involvecutting the door and frame to expose the internal construction for inspection ofthe framing, reinforcements, welds, and other construction details. The selected doors and frames are in addition to the doors and frames identified in theContract Documents. The Contractor shall include an allowance in their detailedestimate for the initial destructive testing. Should deviations from the Contract
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 9 Project No. 46137-C
requirements be found, the Director’s Representative reserves the right to inspectadditional units to confirm compliance. The additional inspections andappropriate corrective measures shall be provided by the Contractor at no cost tothe State.
1.08 DELIVERY
A. Coordinate delivery of anchors and other accessories to be built into other Work,
to avoid delay. Furnish instructions and templates to the affected trades as
required for accurate location.
B. The manufacturer of the prison lock keys shall provide advance notification as
directed and ship all prison lock keys through the United States Postal Service or
United Parcel Service, direct from manufacturer to the facility, via Registered
Mail, Restricted Delivery, Return Receipt Requested.
C. Specific information regarding cut key delivery, including names and addresses,
and phone numbers will be provided to the successful low bidder at the initial
job meeting.
1.09 MAINTENANCE
A. Spare Components: Furnish a minimum of two of the following components,
except as specified otherwise. Furnish two units of each hand for handed items.
Store at the Site where directed:
1. Torsion Spring Deadbolt Cam Latch bolt.
2. Control Panels:
a. Four (4) momentary contact push-buttons.
b. Four (4) of each type of indicator lights.
c. Four (4) 2 amp circuit breakers.
d. 5 amp circuit breakers.
B. Maintenance Materials:
1. Hand Tool Maintenance Kit(s): Lockable steel tool box each containing
one set of all hand tools and fasteners necessary to perform preventative
maintenance and repairs of detention equipment, and locking system
devices. This list includes but is not limited to the following:
a. One complete Torx kit and driver.
b. Acceptable Manufacturers: Craftsman or Snap-On with lifetime
warranty.
c. Manufacturers recommended lubricants for three (3) years’
service.
d. This is not a complete list of required tools, but it is a
representation of the type needed for service and repair of the
devices.
PART 2 PRODUCTS
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 10 Project No. 46137-C
2.01 DETENTION EQUIPMENT COMPANIES
A. American Jail Products, LLC, 4 Van Buren St., Troy, NY 12180, (518) 271-
6560, www.americanjailproducts.com.
B. Hilti, Inc., P.O. Box 21148, Tulsa, OK 74121, (800) 879-8000,
www.us.hilti.com.
C. Allegion:
1. LCN, 121 W. Railroad Avenue P. O. Box 100, Princeton, IL 61356,
(877) 671-7011, www.lcnclosers.com.
2. Glynn-Johnson Door Control Hardware, 2720 Tobey Drive,
Indianapolis, IN 46219, (877) 671-7011, www.glynn-johnson.com.
D. JRS Company, Inc., P. O. Box 2035, Covina, CA 91722, (626) 967-2432,
www.jrscoinc.com.
E. Assa Abloy Door Accessories:
1. Markar Products Inc., 68 Ward Road, Lancaster, NY 14086-9779, (800)
866-1688, www.markar.com.
2. Rockwood Manufacturing, 300 Main St., Rockwood, PA. 15557,
(800) 458-2424, www.rockwoodmfg.com
F. Maximum Security Products Corporation, 3 Schoolhouse Lane, Waterford, NY
12188, (518) 233-1800, www.maximumsecuritycorp.com.
G. Powers Fasteners, Inc., 2 Powers Lane, Brewster, NY 10509, (914) 235-6300,
www.powers.com.
H. Protective Closures Company, 2150 Elmwood Ave., Buffalo, NY 14207, (888)
227-5847, www.caplugs.com.
I. R and S Corporation, 7021 La HWY 1 South, Addis, LA 70710 (225) 749-8001,
www.randscorp.com.
J. Southern Folger Detention Equipment Company, 4634 South Presa St., San
Antonio, TX 78223, (210) 533-1231, www.southernfolger.com.
K. Sentry Security Fasteners Inc., 8208 N. University St., Peoria, IL 61615, (309)
693-2800.
L. Stanley Works, 480 Myrtle St., New Britain, CT 06050, (800) 622-4393,
www.stanleyworks.com.
M. Tanner Bolt and Nut Corporation, 4302 Glenwood Road, Brooklyn, NY 11210,
(718) 43404500.
2.02 MATERIALS
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 11 Project No. 46137-C
A. Steel Plate: Open-hearth mild steel produced especially for detention use;
ASTM A 36.
B. Steel Tubing: Hot-formed, welded or seamless, structural tubing; ASTM A 501.
C. Miscellaneous Steel Shapes and Bars: ASTM A 36, unless otherwise specified
or indicated.
D. Steel Sheet:
1. Hot-Rolled Steel Sheets and Strip: Commercial quality carbon steel
pickled and oiled, complying with ASTM A 569 and ASTM A 568.
2. Cold-Rolled Steel Sheets: Commercial quality carbon steel, complying
with ASTM A 366 and ASTM A 568.
E. Stainless Steel: Type 304; ASTM A 666 for plate, sheet and strip; ASTM A 276
for bars and shapes; US32D (630) for hardware, No. 3 finish for sheet and strip,
unless otherwise specified or indicated.
F. Anchors:
1. For Solid Masonry and Concrete:
a. Internally Threaded Expansion Shield Anchors (For Lag Bolts):
FS FF-S-325, Group II, Type 1.
2. For Hollow Concrete Masonry:
a. Double Expansion Anchors: Dual expansion machine bolt
anchor suitable for hollow concrete masonry. Powers Fasteners,
Double Expansion Anchor or approved equal.
G. Fasteners:
1. Bolts and Nuts: ASTM A 307-12, Grade A, ASTM A563-07a.
a. Concealed Bolts: Standard common bolts with lock washers and
nuts.
b. Exposed Bolts: Torx center pin security head bolts, unless
otherwise specified.
c. Carriage Bolts:
1) Exposed bolts with lock washers and nuts for mounting
of control console to counter top.
2) Plain Washers: Round, general assembly grade carbon
steel.
3) Lock Washers: Helical spring type carbon steel.
d. Carbon Steel Fasteners: Zinc plated per ASTM B695 or ASTM
F2329.
e. Stainless Steel Fasteners: Type 304, ASTM F593-13a.
2. Machine Screws: ANSI/ASME B18.6.3, ASTM F 835-13.
a. Concealed Machine Screws: Torx center pin security head
screws, unless otherwise specified.
b. Exposed Machine Screws: Torx center pin security head
screws, unless otherwise noted.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 12 Project No. 46137-C
c. Alloy Steel Screws: Zinc plated per ASTM B695 or ASTM
F2329.
d. Stainless Steel Screws: Type 304, ASTM F879-12.
H. Paint:
1. Cold Galvanizing Compound: Single component, non-aerosol,
compound giving 93 percent pure zinc in dried film, and meeting
2. Ferrous and Galvanized Shop Primer: Zinc rich primer as manufactured
by or recommended by the finish paint manufacturer. Coordinate
submittals with Section 099101 certification requirements.
2.03 DETENTION HARDWARE
A. Manufacturers:
1. Detention Hinges: Southern Steel, Markar, and Stanley.
2. Locking Systems and Detention Hardware: Southern Folger Detention
Equipment Company.
3. Knob Pulls, Raised Pulls, Flush Pulls, Accessories: Southern Folger
Detention Equipment Company, Maximum Security Products, and
Bronze Craft.
4. Security Door Closer: LCN Door Closer Company:
a. Series 4200, factory adjusted to size 3, and field adjusted to the
size specified in the hardware set , through bolted.
B. General Notes:
1. At mortise locksets provide mortise strikes with dust box furnished by
the lock manufacturer.
2. Provide Deadlocks with bolt keepers with dust box.
3. Locate centerline of mechanical deadbolt and electric latchbolt 3’-2”
high from top of finished floor unless noted otherwise.
4. Where manual locks require escutcheons or cylinder shields, extend
cylinder shanks into escutcheons or cylinder shields.
5. Deadlocks: Use 1-1/4 inches extended bolt for stop side mounting.
6. Fill and grind smooth exposed ends of fasteners at lock mounting plate.
7. Locate centerline of Door Pull 4’-0” from top of finished floor unless
otherwise shown.
8. Maximum undercut of 5/8 inch on detention doors without thresholds
unless noted otherwise.a. Bottom (at threshold): 3/8 inch maximum to top of threshold.
9. Set thresholds in full bed of Type 3 Sealant.
10. Surface mount detention hinges unless otherwise specified.
a. Weld detention hinges as recommended by manufacturer to
allow hinges to function at rated capacities without inducing
hinge bind.
b. For detention hinges provide a minimum fillet weld size of 1/4
inch, continuous on three sides of each hinge leaf. Attach
ground to hinge leaf and jamb to prevent welding current from
being carried through the hinge barrel when welding hinges to
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 13 Project No. 46137-C
the jambs. Ensure weld interpass temperature of the hinge does
not exceed 225 degrees F.
c. Hinge leafs: Full sized, or one leaf is full size and the other one
is 1-1/2 inches minimum to centerline of barrel sized to fit
frame.
11. Single Wing Escutcheons: Use on electric jamb mounted locks, stair
doors, control room doors, and emergency release cabinets.
12. Where electrically operated hardware and monitoring is required provide
hardware enclosures, junction boxes and interconnections using UL
approved conduit, elbows, and connectors.
13. Provide sized overhead stops and closers according to manufacturer's
table of sizes unless non-sized or barrier-free closers are specified.
Verify with manufacturers, the special templates provided are
compatible with the 2-1/4 inch door thickness, 5 inch prison hinge
installation, and 3/4 inch stop height. Attach overhead stops and closers
to doors with through-bolts.
14. Use proper installation sequence e.g., install head gasketing first, then
install overhead stops and coordinators before surface mounted door
closers. Template door closers for maximum door swing allowed by
wall placement and jamb conditions. Where overhead stop prevents
door from swinging to wall, template closer to exceed degree of opening
allowed by overhead stop.
15. Provide molex plug connector for electric locks
16. Galvanize exterior assemblies, and assemblies exposed to wet areas,
shower rooms, etc.
C. Detention Hardware Groups:
Group A:
1. Institutional Hinge: 2 ea Southern Steel 204FMSS 4.5 x 4.5 torx x 630.
2. Institutional Electric Power Transfer Hinge: 1 ea Southern Steel 204E
4.5 x 4.5 x torx x 630.
3. Door Position Switch: 1 ea Southern Steel 220A-42.
4. Electric Institutional Mortise Lock: 1 ea Folger Adam SK both sides
D9349 non-fail safe x Folger Adam Mogul Cylinders x DIS x KLO x
918-D-S x US32D.
5. Gasketing at Head: 1 es Legacy 5924 MA x torx.
6. Security Door Closer: 1 ea LCN 4214 x TMS x SRI x AL.
7. Gasketing at Jambs: 1 set Legacy 5924 MA x torx.
8. Wall Bumper: 1 ea Rockwood No. 400, 401, or 402 x US26D.
9. Protection Plate: 1 ea Rockwood K1050 16” x 2” LDW stop side x
.050" x B4E x OHUCMS 6” oc x US32D.
INSTALLATION NOTES: Install Electric Hinge in middle position. Install
gasketing at head. Then install overhead stop over gasketing and fasten through
the gasketing. Then install closer and fasten through the gasketing. Do not cut
gasketing for overhead stop and at closer parallel arm shoe.
Description of Operation: See 2.05 A.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 14 Project No. 46137-C
Group B:
1. Continuous Hinges: 1 ea Markar FM300 x M91-003MM x HT x welded
End Pins x 83.125” OA x Torx.
2. Institutional Mortise Deadlock: 1 ea Folger Adam D9318 x 918DNL x
900 Box x US32D.
3. Raised Door Pull: 1 ea Folger Adam No. 2 x US26D.
4. Protection Plate: 1 ea Rockwood K1050 16” x 2” LDW stop side x
.050" x B4E x OHUCMS 6” oc x US32D.
5. Gasketing: 1 set Legacy 5926 MA x torx.
Group C:
1. Hinges: 3 ea Stanley BBK852, MSPK855, or Brookfield I-8510 series,
zinc plated.
2. Prison Deadlock: 1 ea Folger Adam No. 86 x lock mount x galvanized
case.
3. Escutcheon: 1 ea Folger Adam No. 1 x US32D.
4. Cylinder Shield: 1 ea Folger Adam No. US32D.
5. Raised Door Pulls: 2 ea Folger Adam No. 2 x US26D.
6. Gasketing at Head: 1 es Legacy 5924 MA x torx.
7. Surface Overhead Stop: 1 ea Glynn Johnson 81S-HD x SOC x TMS x
US32D.
8. Security Door Closer: 1 ea LCN 4214 x ST3456 x 5th screw hole
spacer/ TB(2-1/4") TMS x SRI x AL.
9. Protection Plate: 1 ea Rockwood 16” x 2” LDW stop side x .050 x B4E
x OHUCMS 6” oc x US32D.
10. Astragal: By door manufacturer.
11. Threshold: 1 ea Legacy 3556 MA x torx.
12. Gasketing at Jambs: 1 set Legacy 5924 MA x torx.
13. Door Bottom: 1 ea Legacy78918 CA x torx.
Installation Notes: Install gasketing at head. Then install overhead stop over
gasketing and fasten through the gasketing. Then install closer and fasten
through the gasketing. Do not cut gasketing for overhead stop and at closer
parallel arm shoe.
Group D:
1. Hinges: 3 ea Stanley BBK852, MSPK855, or Brookfield I-8510 series,
zinc plated
2. Electric Prison Lock- jamb mounted: 1 ea Folger Adam No. 56ELLNN
x latch bolt remains retracted until control console switch is set to
LOCK x indicator switches x lock mount x galvanized case.
3. Escutcheons: 1 ea Folger Adam No. 1 x US32D.
4. Cylinder Shield: 1 ea Folger Adam No. 2CS x US32D.
5. Rim Exit Device: Precision FL2114 x 4914K x 630 x torx.
6. Raised Door Pull: 1 ea Folger Adam No. 2 x US26D on push side only.
7. Door Position Switch: 1 ea Folger Adam No. 534 series x standard
housing.
8. Gasketing at Head: 1 ea Legacy 5924 MA x torx.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 15 Project No. 46137-C
9. Security Door Closer: 1 ea LCN 4216 x 5th screw hole spacer x TB(2-
1/4")/TMS x SRI x AL
10. Gasketing at Jambs: 1 set Legacy 5924 MA x torx..
11. Protection Plate: 1 ea Rockwood K1050 16” x 2” LDW stop side x
.050" x B4E x OHUCMS 6” oc x US32D.
12. Floor Stop: Rockwood 463RKW x 630.
13. Astragal: By door manufacturer.
Installation Notes: Install closer and fasten through the gasketing. Do not cut
gasketing at closer parallel arm shoe. See detail drawing for coordination of exit
device, pull and electric prison lock/strike location.
Description of Operation: See 2.05 A.
Group E:
1. Institutional Hinge: 2 ea Southern Steel 204FMSS 4.5 x 4.5 torx x 630.
2. Institutional Electric Power Transfer Hinge: 1 ea Southern Steel 204E
4.5 x 4.5 x torx x 630.
3. Door Position Switch: 1 ea Southern Steel 220A-42.
4. Electric Institutional Mortise Lock: 1 ea Folger Adam SK both sides
D9349 non-fail safe x Folger Adam Mogul Cylinders x DIS x KLO x
918-D-S x US32D.
5. Gasketing at Head: 1 es Legacy 5924 MA x torx.
6. Surface Overhead Stop: 1 ea Glynn Johnson 81S-HD x SOC x TMS x
US32D.
7. Security Door Closer: 1 ea LCN 4514T TMS x SRI x AL.
8. Gasketing at Jambs: 1 set Legacy 5924 MA x torx.
9. Protection Plate: 1 ea Rockwood K1050 16” x 2” LDW stop side x
.050" x B4E x OHUCMS 6” oc x US32D.
Installation Notes: Install Electric Hinge in middle position. Install gasketing at
head. Then install overhead stop over gasketing and fasten through the gasketing.
Do not cut gasketing for overhead stop.
Description of Operation: See 2.05 A.
2.04 FABRICATION AND MANUFACTURE
A. General:
1. Fabrication: Fabricate members straight, true, and free from dents,
buckle, twist, and rough/sharp edges. Where exposed in finished spaces,
fit joints to provide tight metal-to-metal fit. Make connections by
welding, or by equally secured and approved method that will rigidly
hold the members in position so that their full strength will be utilized;
use the approved detention equipment manufacturer’s standard shapes
and methods, unless otherwise specified or indicated. All exposed
framing gaps are to be filled flush with Type S-6 Sealant (unless noted
otherwise) prior to finish painting Reinforce, cut, drill and tap members
as required to receive hardware, removable glazing stops, and
accessories.
2. Welding: Welds shall show uniform section and deep penetration.
Grind welds smooth and clean spatter off so that surfaces are easily
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 16 Project No. 46137-C
cleaned. Unless noted otherwise, provide appropriate weld, 2 inches
long, 8 inches on center.
3. Surface mount hinges unless noted otherwise.
a. Weld detention hinges as recommended by manufacturer to
allow hinges to function at rated capacities without inducing
hinge bind.
b. For detention hinges provide a minimum fillet weld size of 1/4
inch, continuous on three sides of each hinge leaf. When
welding detention hinges, attach ground to prevent welding
current from being carried through the hinge barrel. Weld
interpass temperature of the hinge not to exceed 225 degrees F.
c. Hinge leafs: Full sized, or one leaf is full size and the other one
is 1-1/2 inches minimum to centerline of barrel sized to fit
frame.
4. Rivets and Riveting:
a. Rivets: 3/8 inch diameter, countersunk flush type, and spaced 4
to 6 inches on center as the nature of the Work requires.
Diameter of holes for rivets shall not exceed rivet diameter by
more than 1/16 inch. Holes not in true alignment shall be
reamed; drifting or gouging will not be permitted.
b. Riveting: Drive rivets down to completely fill holes. Replace
loose rivets and those with imperfect heads, or without firm
bearing on metal, with good rivets.
5. Bolting: Use only where indicated or approved, and only where nuts are
not accessible to inmates or exposed to public view. Draw nuts up tight
and batter threads, unless otherwise indicated.
6. Cutting and Drilling for Others: Cut, drill and tap the Work of this
Section as required to receive items provided under Related Contracts.
7. Prepare and reinforce doors to receive surface, mortised, and concealed
hardware.
a. 10 gage plate unless noted otherwise.
b. 2 x 2 x 3/16x10-1/2 inches steel tube for surface mounted pulls.
B. Galvanizing: Galvanize items specified or indicated to be galvanized.
1. Process: Hot-dip process. Comply with the following:
a. ASTM A 123 for plain and fabricated material, and assembled
products.
b. ASTM A 153 for iron and steel hardware.
C. Shop Painting:
1. Thoroughly clean all surfaces of ferrous metal, removing rust, scale, and
other deleterious material.
a. Galvanized Metal: Rinse in hot alkali or in an acid solution, and
then in clear water. When dry, repair final assembly welds and
abraded areas with a 2.0 mil thick dry film coating of cold
galvanizing compound applied in accordance with compound
manufacturer’s instructions.
2. Provide one of the two following options:
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 17 Project No. 46137-C
a. Apply shop primer and finish paint (see Section 099101 _____)
to all surfaces of ferrous metal, except as otherwise required for
moving parts and except for surfaces to be embedded in concrete
or masonry or to be field welded after fabrication in accordance
with the paint manufacturer’s instructions and at a rate to
provide a uniform minimum wet film thickness of 3.0 mils.
b. Apply powder-coat finish immediately after cleaning and
pretreating to all surfaces of ferrous metal, except as otherwise
required for moving parts and except for surfaces to be
embedded in concrete or masonry or to be field welded after
fabrication, to provide a minimum dry-film thickness of 1.0 mil
for topcoat.
1) Acceptable powder-coat finishes suppliers:
a) TCI Powder, 300 Martin Marietta
Drive.Americus, GA 31719, (800)-533-9067,
www.tcipowder.com.
b) Nortek Powder Coating, LLC, 5600 Success
Drive, Rome, NY 13440, (888) 667-8357,
www.nortekpowder.com.
c) Axalta Coating Systems, Two Commerce
Square, 2001 Market St., Suite 3600,
Philadelphia, PA 19103, (855) 629-2582,
axaltacs.com.
d) Interpon Powder Coatings, 150 Columbia Street,
Reading, PA 19601, (610) 685-7600,
www.interpon.us.
3. Apply shop primer in accordance with Section 099101 to inner surfaces
of hollow steel doors before insulation and second face panel is
installed.
4. Finish paint inside of control cabinets with manufacturer’s standard gray
enamel system.
D. Swinging Hollow Steel Doors: Flush type, 2-1/4 inches thick. Doors shall not
have more than 1/8 inch clearance from frame, unless otherwise indicated. On
doors without thresholds, bottom clearance to finish floor is 3/4 inch maximum,
maximum of 1/4 inch on doors having head and foot bolts.
1. Framing: Frame doors with 2 x 1 x 3/16 inches steel channels on all four
edges, four intermediate 2 x 1 x 3/16 inches steel channels extending
horizontally the full width of the door. Doors with a lock box shall have
a 1/2 x 2 inches steel flat bar on lock edge and steel channels on other
three edges. Locate two of the intermediate channels about 4 inches
above and below the centerline of the door, or at the top and bottom of
the lock box if required, and the other two half way between these and
the top and bottom of the door. Extend legs of perimeter channels
inward and miter at corners. Cope legs to fit intermediate channels. Set
channels at top, bottom and lock edge 1/8 inch back from edge of face
panels opposite stop side to allow for welding; set channel back at hinge
edge to receive leaves of mortised hinges. Fill out spaces above, below,
and between hinges with steel bar riveted to the channel. Reinforce for
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 18 Project No. 46137-C
full surface hinge application with 2 x 2 x 3/16 x 6 inch long steel tubes.
Weld junctions of all channels.
2. Insulation: Fully fill doors with non-combustible mineral wool fiber
materials having a minimum thermal resistance, R-value of 4.1 per inch,
unless otherwise indicated.
3. Face Panels: Weld 10 gage, single sheet steel panel on each door face.
Weld back of one panel to framing; plug weld the other panel to framing.
Make inner welds at least 1/2 inch long on alternate sides of channels
and spaced 6 inches oc. Plug welds shall have equivalent strength of
inner welds. Weld panel edges to the perimeter frame.
4. Observation Light: Frame opening with 2 x 1 x 3/16 inches steel
channels on all four sides. Cut face panels for light and weld panel
edges to frame. Unless otherwise indicated, weld to door 1/4 inch
continuous bent steel plate “Z” shaped stop to perimeter of opening,
drilled and tapped for fasteners, and provide 1-1/2 x 1-1/4 inches
continuous steel bar stop (LLV) attached with 5/16 inch diameter high
strength tamper resistant machine screws 4 inches on center maximum, 2
inches maximum from end on threat side of door.
5. Prepare and reinforce doors to receive surface, mortised, and concealed
hardware.
6. Lock Box: Frame pocket with 2 x 1 x 3/16 inches steel channels unless
otherwise indicated. Cut one face panel for lock box cover plate.
Fabricate cover plate of 1/8 inch thick steel sheet. Cover plate shall be
flush with face panel and attached to lock pocket framing with Torx
center pin security head machine screws. Weld filler plates in lock box
as required to receive lock.
a. Locate removable cover plate on the side of the door opposite
the threat side.
7. Galvanizing: Galvanize entire assembly of exterior doors and doors in
wet areas.
E. Structural Steel Door Frames: Fabricate of structural shapes and bars as
specified or indicated, square, true, uniform, and fully welded. Ship with
temporary spreader at bottom.
1. Stops: 1-1/2 x 3/4 inches steel bar, plug welded to frame on not more
than 8 inch centers.
2. Floor Anchors: Steel angle clip welded to back of frame at bottom of
each jamb. Prepare clips for anchorage to floor construction indicated.
3. Jamb Anchors: 2 x 1/4 inches steel strap anchors, not less than 8 inches
long and terminating with l inch bent end, welded to jambs. Anchors
shall be fixed for concrete walls and adjustable type for masonry walls.
Anchors, for exterior frames in concrete masonry unit construction, shall
extend into cells (cores) as indicated. Space anchors not exceeding 16
inches oc, with no less than 4 anchors per jamb.
4. In-Place Masonry Construction Jamb Anchors: 3/8 inch diameter Type
304 stainless steel button head machine bolts and expansion shields,
spaced not exceeding 16 inches oc, with not less than 4 anchors per
jamb.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 19 Project No. 46137-C
5. Prepare frames to receive and accommodate required hardware and other
items. Form slots in frames to serve as hardware strikes, unless
otherwise indicated. Weld 12 gage steel box closures on back of frame
where slots for hardware occur.
6. Lock Box: Prepare frame for Electric Prison Lock as indicated. Form
slots in frame for latchbolt and deadlock actuator. Coordinate with
manufacturer’s templates.
7. Door Position Indicator Switch: Prepare frame for Door Position
Indicator Switch. Coordinate with manufacturer’s templates. Weld 12
gage steel box closure on back of frame where cut out for hardware
occurs. Provide connectors for conduit connections as indicated.
8. Wiring Connection Between DPS and Lockbox: 3/4 inch diameter PVC,
Schedule 40 conduit. Fittings and accessories as recommended by the
conduit manufacturer for wall construction type. Provide pull string.
9. Galvanizing: Galvanize entire assembly of exterior door frames and
frames in wet areas.
F. Fire Rated Doors and Frames: Materials and general construction as specified
for swinging hollow steel doors and structural steel door frames.
1. Fire ratings up to three hours, tested in accordance with UL Bulletin No.
UL10C or NFPA 252.
2. Manufacturers: Maximum Security Products Corporation and American
Jail Products LLC.
3. Attach UL labels to hinge side of door, and to jamb of frame.
G. Shop Painting:
1. Thoroughly clean all surfaces of ferrous metal, removing rust, scale, and
other deleterious material.
a. Galvanized Metal: Rinse in hot alkali or in an acid solution, and
then in clear water. When dry, repair final assembly welds and
abraded areas with a 2.0 mil thick dry film coating of cold
galvanizing compound applied in accordance with compound
manufacturer’s instructions.
2. Provide one of the two following options:
a. Apply shop primer and finish paint (see Section 099101) to all
surfaces of ferrous metal, except as otherwise required for
moving parts and except for surfaces to be embedded in concrete
or masonry or to be field welded after fabrication in accordance
with the paint manufacturer’s instructions and at a rate to
provide a uniform minimum wet film thickness of 3.0 mils.
b. Apply powder-coat finish immediately after cleaning and
pretreating to all surfaces of ferrous metal, except as otherwise
required for moving parts and except for surfaces to be
embedded in concrete or masonry or to be field welded after
fabrication, to provide a minimum dry-film thickness of 1.0 mil
for topcoat.
1) Acceptable powder-coat finishes suppliers:
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 20 Project No. 46137-C
a) TCI Powder, 300 Martin Marietta
Drive.Americus, GA 31719, (800)-533-9067,
www.tcipowder.com.
b) Nortek Powder Coating, LLC, 5600 Success
Drive, Rome, NY 13440, (888) 667-8357,
www.nortekpowder.com.
c) Axalta Coating Systems, Two Commerce
Square, 2001 Market St., Suite 3600,
Philadelphia, PA 19103, (855) 629-2582,
axaltacs.com.
d) Interpon Powder Coatings, 150 Columbia Street,
Reading, PA 19601, (610) 685-7600,
www.interpon.us.
3. Apply shop primer (see Section 099101 3.03C) to all inner surfaces of
hollow steel doors before insulation and second face panel is installed.
2.05 ELECTRIC LOCKING SYSTEM FOR ELECTRIC PRISON LOCKS
A. Description of Completed System: Doors with Electric Institutional Mortise
Lock, and/or Electro-Mechanical Deadlatch, provided by this project, shall be
controlled and monitored from the Classroom Gate Control Consolet (CGCC)
located in the Control Room.. Provide all materials and work as required for the
doors to operate as follows:
1. Each door and door group with power-operated lock(s) shall be
controlled and monitored by a selector or push-button switch, and
indicator lights located on the designated Control Consolet.
a. Three Position Selector-Switch (Door 1X01A):
1) Lock shall automatically unlock when selector switch is
turned to the unlocked position and remain unlocked
unless specific action is taken at the control consolet to
enable lock to relock. Selector switch shall spring return
to center (O) position upon release of selector switch.
2) Lock shall automatically deadlock when control switch
is turned to the locked position and remain locked unless
specific action is taken at the control consolet to enable
lock to unlock. Selector switch shall spring return to
center (O) position upon release of selector switch.
b. Push-Button Switch (Doors 1D08B, 1D09B, 1D10B,1D05A,
1D06A): Depressing the push-button, the lock or lock groups
will unlock from the locked position and remain unlocked only
while pushbutton is depressed. Lock or lock groups will
automatically deadlock when door is closed. Both knobs, of
doors with knobs, are locked except when power is applied from
console. Key override operates latch bolts when knobs are
locked out.
b. Two control panel indicator lights per door and door group shall
monitor the status of each power-operated door’s door position
switch and lock.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 21 Project No. 46137-C
1) A “Green” indicator light shall illuminate when the door
or door group is completely closed and deadlocked.
2) A “Red” indicator light shall illuminate for all other
conditions.
2. Power-operated locks shall be operable by a manual key release
mechanism at the door.
3. Control console unlocks knobs both sides on the Folger Adam D9349
series (classroom entry doors). The knob, either side, must then be
turned to retract the latch bolt.
4. A power switch on the control consolet shall allow the attendant to
switch power on and off to the consolet.
a. When the power switches are in the “OFF” position, no
electrical power shall be available at the doors. All power to the
doors and locks shall be disconnected at the consolet.
b. In the “On” position, the key shall be non-removable until the
switch is returned to the “Off” position.
5. A lamp test push button on the gate control consolet shall allow the
attendant to test the status of all indicator lights. No other system shall
be affected.
6. A circuit breaker adjacent to each door’s control switch in the consolet
will provide protection of the door’s control circuit.
2.06 CONTROL CONSOLES (CONSOLETS)
A. Control Panels and Housings: Incorporated as the top of a control console, or as
the top of the housing.
1. General: Fabricate panels, of 11 gage stainless steel with holes to
receive switches, circuit breakers, and indicator lights. Fabricate
housings and fastening battens of 10 gage steel with hammer tone gray
finish. Each door and gate controlled by panel shall have a control
switch, circuit breaker, and two accessible and replaceable indicator
lights mounted in a horizontal line. A green light shall go on only when
the door is locked closed and the drop bar for sliding doors is in the
locked position. A red light shall show all other conditions of the door.
Identify each door or gate controlled from the panel.
a. Maintenance Wiring Diagram: Provide a representative point-
to-point diagram to show typical wiring patterns of the panel.
Mount inside panel cover.
b. Maintenance Power Cut-off Switch: Provide disconnect switch
in each control panel housing. Install in line with power
circuitry. This switch will completely cut power to the
individual panel.
2. Panels for Control Consoles and Housings: Panels shall form the top, be
inclined down from back to front between 20 and 30 degrees from
horizontal, and turn down at least one inch over front and sides. Panel
shall have a continuous stainless steel hinge at the back to allow it to
swing up for maintenance, and be secured at the front, sides, and battens.
Reinforce for security fasteners position. Provide a key operated control
switch, with a magnetic contactor, so that when the key is turned all
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 22 Project No. 46137-C
electric power to the panel is switched on or off. When the panel is
activated, key is non removable.
a. Wiring to console top mounted components shall be bundled
with slack in the bundled wiring to allow console top to be
opened without disconnecting the conductors from the console
top.
3. Panels with Controls for Non-Cell Doors: Arrange and locate controls
for non-cell doors as indicated.
4. Prop Rods: Provide a pair of interior door props with automatic cam
action to prevent accidental closing and to hold the panel in an open
position for maintenance purposes.
5. Mounting of Gate Control Consolet to Counter: Install carriage bolts
from the underside of counter top into the Consolet Base Section.
6. Provide adhesive backed 3.5 mil vinyl identification nameplates as
indicated on drawings. Height and length of nameplate as required.
Locate nameplate centered on its associated switch. Apply straight and
level and in accordance with manufacturer’s written instructions.
a. Color: White letters/numerals on black background.
b. Font: Helvetica Medium, 3/8” (minimum) high, all capitals.
c. Inscription on identification plate as indicated or directed.
B. Furnish a lamp test push button on each panel that will test status of all indicator
lights on the panel. None of the system operations shall be affected by the test.
2.07 ELECTRICAL COMPONENTS FOR ELECTRIC OPERATING AND LOCKING
SYSTEM AND ELECTRIC LOCKING SYSTEM
A. General:
1. Control panels: Suitable for connection to a 20 ampere, #12 AWG wire,
120 volt, single phase, 60 Hz dedicated circuit as indicated.
2. Electrical components for which Underwriters’ Laboratories, Inc. (UL)
provides product listing service, shall be listed and bear the listing mark.
3. Electrical components: Standard product of the detention equipment
manufacturer except for the qualifications that follow.
4. Utilize hard-wired relay logic in system design. No printed circuit board
style components will be allowed.
B. Circuit Breaker: A circuit breaker adjacent to each gate/door control switch on
the control panel will provide protection of the gate/door control circuit only.
AIRPAX Series PR11-62; or Potter & Brumfield W28 series, amperage as
indicated.
C. Control Panel Indicator Lights: Chicago Miniature Lighting, LLC 1091QM
SUPER-BRITE series LEDs. 1091QM1-24VDC(RED); 1091QM5-24VDC
(GREEN). Mount with push-on speed nut model SN0461.
D. Individual Swing Door Control Switch for Electric Locking Systems: Three
Position Selector Switch, Non-Illuminated: Allen-Bradley’s 800T series, or
Cutler-Hammer’s (Eaton) 10250T series switch, having:
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 23 Project No. 46137-C
1. Size: 30.5 mm diameter for insertion in 31mm keyed panel opening.
2. Legend Plate: “UNLOCK – O – LOCK”.
3. Operator Action: Spring return to Center (O) position from left
(UNLOCK) position, and right (LOCK) position.
4. Handle (Knob): Black Standard Knob with white insert.
5. Contact Blocks: Configuration and number of contact blocks as required
for the specified functions and operations.
E. Momentary Contact Push-Button Switch: Non-Illuminated, Allen-Bradley’s
800T series, or Cutler Hammer’s (Eaton) 10250T series switch, having:
1. Size: 30.5 mm diameter for insertion in 31mm keyed panel opening.
2. Legend Plate: “UNLOCK”.
3. Push-button: Black Flush Head, Black Flush Button, or Black Full
Guard.
4. Contact Blocks: Minimum of one contact block with 1 normally open
(N.O.) contact and 1 normally closed (N.C.) contact. Provide additional
contact blocks as required for the specified functions and operations.
F. Key Operated Control Panel Power Cut-off Switch: Two Position Selector
Switch: Allen-Bradley’s 800T series, or Cutler-Hammer’s (Eaton) 10250T series
switch, having:
1. Size: 30.5 mm diameter for insertion in 31mm keyed panel opening.
2. Legend Plate: “ON - OFF”.
3. Operator Action: Maintained position for both positions. Key is non
removable when switch is in “Power On” mode.
4. Handle (Knob): Keyed switch, furnish three keys for each switch.
a. All Power Cut-off switches shall be keyed individually and
unlike any other keyed switch.
5. Contact Blocks: Minimum of one contact block with 1 normally open
(N.O.) contact and 1 normally closed (N.C.) contact. Provide additional
contact blocks as required for the specified functions and operations.
G. Maintenance Power Cut-Off Switch: Gould Shawmut, Ultrasafe class J fuse
holder, Model No. US3J Series, DIN-rail installation.
H. Power Supply: 24 Volts, Silver Line Linear Power Supplies, model Type SLS;
or Sola Heviduty Model No. SDP-24-100. Output rating according to the control
panel requirements. Screw Terminal connections, temperature range 0 degrees C
to +50 degrees C, automatic current limiting, DC output adjustable 10%
minimum.
I. Contactors and Relays: ABB MDRC’s Modular DIN Rail Components.
J. Wiring Conductors: Provide wiring in accordance with Section 260505.
2.08 KEYING
SPECIFIC KEYING INSTRUCTIONS WILL BE PROVIDED TO THE SUCCESSFUL LOW BIDDER AT THE INITIAL JOB MEETING
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 24 Project No. 46137-C
A. Key locks individually, and furnish 7 cut keys per lockset. A keying schedule
will be furnished during submittal phase.
B. Key locks as directed and incorporate a keying schedule into the hardware
schedule for approval.
1. Key changes shall be different from changes previously used at this
Facility except as noted. Verification of existing key change records
shall include the identification of and coordination with multiple Facility
Identification Codes and related Cylinders (Key Ways) assigned to the
same facility address.
a. When multiple Facility Identification Codes and related
Cylinders (Key Ways) are identified at the same facility address,
the Contractor shall contact the Director’s Representative for
confirmation of which established coding system is to be
continued with.
2. Record key changes, to avoid future unintended duplication.
3. Furnish seven keys for each change, except as noted.
4. Furnish extended shank keys when required.
PART 3 EXECUTION
3.01 DETENTION EQUIPMENT INSTALLATION
A. Install the Work of this Section in its designed position, plumb, level, square,
straight, and true, and in accordance with the manufacturer’s approved shop
drawings.
B. Brace assembled fabrications until permanently secured in place to prevent
displacement or distortion of the members.
C. Comply with requirements of FABRICATION AND MANUFACTURE Article.
Touch-up abraded areas and areas of field welding as required, with compatible
primer and finish paint, or cold galvanizing compound.
1. For exposed galvanized items, touch-ups shall include the full width and
length of the face of steel in the area of abrasion and welds. Brush apply
cold galvanizing compound in accordance with ASTM A780
requirements to a 3.0 mil dry film thickness.
D. Use only rotary power drills where masonry or concrete is required to be drilled.
Drill holes to exact size required.
E. Perform welding in accordance with the AWS Codes.
F. Surface mount hinges unless noted otherwise.
a. Weld detention hinges as recommended by manufacturer to allow hinges
to function at rated capacities without inducing hinge bind.
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 25 Project No. 46137-C
b. For detention hinges provide a minimum fillet weld size of 1/4 inch,
continuous on three sides of each hinge leaf. When welding detention
hinges, attach ground to prevent welding current from being carried
through the hinge barrel. Weld interpass temperature of the hinge not to
exceed 225 degrees F.
c. Hinge leafs: Full sized, or one leaf is full size and the other one is 1-1/2
inches minimum to centerline of barrel sized to fit frame.
G. Side hinged doors and gates shall not be hinge bound, nor sprung, nor travel nor
drift more than 5 degrees of arc in either direction when placed in any stationary
position of its swing.
H. Neatly install and securely fasten hardware. Keep polished hardware and
handles free from scratches and defacement with temporary protective covers.
1. Installation Sequence: Use proper installation sequence e.g., install
overhead stops and coordinators before surface mounted door closers.
2. Template door closers for maximum door swing allowed by wall
placement and jamb conditions. Where overhead stop prevents door
from swinging to wall, template closer to exceed degree of opening
allowed by overhead stop. Verify with closer/overhead stop
manufacturers, the special templates provided are compatible with the
2-1/4 inch door thickness and 5 inch prison hinge installation.
3. Attach closers and overhead stops to doors with through-bolts.
3.02 WIRING FOR DETENTION EQUIPMENT
A. Electrical Work Contractor shall provide power wiring and raceway system from
the power source (circuit breakers in panelboard) to the control consoles.
B. Provide power wiring, control wiring, and raceway system from the control
consoles/cabinets etc. to the operating devices, appurtenances, and the detention
hardware.
3.03 CONDUCTOR INSTALLATION
A. Conductors (power wiring and control wiring) shall be continuous (no splices)
from each door and/or gate, device/lock location to their associated control
consoles/cabinets except as noted below.
1. At doors/gates and at cell run Emergency Control Cabinet locations
splices will be allowed through the use of plug-in connectors or terminal
blocks for connections to locks, motors, limit switches, and other electrical
components to facilitate removal and replacement of these items.
1. The use of common wiring (shared conductors) between multiple door and
or gate, device/lock locations for connections to their associated control
consoles/cabinets shall not be allowed.
B. Install wiring in raceways.
1. Wiring from door and/or gate, device/lock locations to their associated
control consoles/cabinets may be installed in common raceways. Do not
Revised 11/18/14
Edited and/or Printed 2/5/2020 111901 - 26 Project No. 46137-C
exceed the raceway’s conductor fill as allowed by the National Electric
Code.
C. Protect wiring in track boxes with wire trough or chase. Encase wiring in plastic
sheathing or rubber grommets when passing through metal components and near
moving parts.
3.04 FIELD QUALITY CONTROL
A. Testing Of Detention Equipment:
1. Preparation: Notify the Director’s Representative at least three working
days prior to the tests so arrangements can be made to have a Facility
Representative witness the tests.
a. Remove protective covering from view windows, mirrors,
hardware, etc.
2. Testing: Individually test each door or gate system, covering all
functions and features one at a time.
2. Test control panel(s) for each designed function.
3. Test each manual lock and each electric lock for ease of operation.
4. Supply all equipment necessary for system adjustment and testing.
B. Post installation Inspection For Detention Equipment: The Director’s
Representative will call for an inspection tour at the site. Attending will be the
Contractor, Technical Advisor, Control Wiring Installer and the Detention
Equipment Installer. Other participants may be invited at the discretion of the
Director. The Detention systems and hardware, both electric and mechanical,
and the accessories will be inspected for proper installation and operation. The
Technical Advisor will document the inspection identifying locations and
required corrections and adjustments. Provide copies of the report to the
Director’s Representative.
1. The Detention Equipment Installer shall perform all corrections or
adjustments found during the post installation inspection immediately
following the tour or as soon as practicable.
2. The Technical Advisor shall verify all corrections and adjustments have
been completed and certify with an affidavit (affidavits) that the system
is installed correctly and is operating properly. Forward certification(s)
to the Director’s Representative.
3.05 ADJUSTING
A. Adjust operative units and equipment to work freely and easily, ready for use.
Field lubricate operating and locking systems in accordance with the
manufacturer’s maintenance instructions. Adjust equipment when the
temperature is approximately 70 degrees F.
END OF SECTION
KEY PLAN
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
JUNCTION BOX,
REFER TO ADJACENT IMAGE
STORAGE BUILDING
(T.B.R.)
SURVEILLANCE CAMERA
(T.B.R.)
EXTERIOR LIGHT
(T.B.R.)
BRANCH CIRCUIT TO
STORAGE BUILDING
(T.B.R.)
SCALE:
REFERENCE PHOTOS
NTS
E-101
2
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
WIRELESS RADIO
ANTENNA
(E.R.E.)
SURVEILLANCE
CAMERA
(T.B.R.)
PHOTOCELL
(T.B.R.)
SCALE:
REFERENCE PHOTOS
NTS
E-101
2
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
4
JUNCTION BOX
(T.B.R.)
3
EXISTING SERVICE CONDUITS
(E.T.R.)
SCALE:
REFERENCE PHOTOS
NTS
E-101
2
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
W1W2
WINDOW TYPES
WINDOW SCHEDULE
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
DOOR SCHEDULE
MASONRY WALL LOCATIONS
TYPICAL
DOOR TYPES
F1
F
(FLUSH)
NV1
(NARROW VISION)
V
(VISION)
HG
(HALF GLASS)
FRAME TYPES
A-509
1
F2
C6 DETENTION
FRAME
HARDWARE MOUNTING HEIGHTS
DETENTION DOOR - TYPICAL
LITE KIT
DESIGN & CONSTRUCTION
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
COMPLIANCE STATEMENT:
46137 -
REVISED DRAWING A-601 02/06/2020
S
T
A
T
E
O
F
NE
W
Y
O
R
K
R
E
G
I
S
T
E
R
E
D A
R
C
H
I
T
E
C
T
T
R
A
V
I
S
C O
V
E
R
T
O
N
0
3
58
9
1
GENERAL NOTES:
DESIGN & CONSTRUCTION
Bernier, Carr & Associates, Engineers, Architects and Land Surveyors, P.C.
COMPLIANCE STATEMENT:
46137 -
L ICENSED PROFESS IONAL ENGIN
EER
091078
HOWA
RD J CABEZAS
STATE OF NEW YORK
REVISED DRAWING P-105 02/06/2020
LIGHTING PANEL
(E.T.R.)
POWER PANEL
(E.T.R.)
200A DISCONNECT
(E.T.R.)
8 CKT LOADCENTER
(E.T.R.)
JB
VOICE BLOCKS
(E.T.R.)
TC
TIMECLOCK
(E.T.R.)
CLASSROOM
1D08
CLASSROOM
1D09
CLASSROOM
1D10
CONFERENCE
1D11
OFFICE
1D12
OFFICE
1D13
CORRIDOR
NORTH
1DO1
HALL
STORAGE
1D03
ROOM
ELECTRIC
ROOM
MECHANICAL
1X02
ROOM
MECHANICAL
1D04
ROOM
ELECTRIC
1D02
PANEL 'PP1'
WAP
WAP
WAP
WAP
4
4
GENERAL DATA
CABLING RACEWAY
HOMERUN ROUTE
1
2
TYP.
+84
"4
4 4
4 4
DATA/WAP CABLING
VOICE CABLING
FOC TO BUILDING 114.
REFER TO SHEET E-503
FOR MORE INFORMATION.
FOC TO BUILDING 114.
REFER ALSO TO E-503
+84
"4
+84
"4
RESTROOM
INMATE 02
1D06
RESTROOM
INMATE 01
1D05
RESTROOM
STAFF
1D07
PANEL 'PP-EM'
UPS
4
9
AV
JL
8
10
A/V RACK
10
9
AV
JL
8
10
AV
JL
8
10
9
EER RACK
11
3
6
5
GENERAL NOTES:
1. REFER TO E-001 FOR ELECTRICAL LEGENDS, ABBREVIATIONS AND
GENERAL PROJECT NOTES.
2. REFER TO E-601 FOR PANEL SCHEDULE FOR CIRCUIT
CHARACTERISTICS.
3. REFER TO E-601 FOR BRANCH CIRCUIT SCHEDULE (BCS) FOR
CIRCUIT REQUIREMENTS.
KEY NOTES:
PROPOSED 4-POST DATA RACK. REFER TO SHEET E-503 FOR MORE
INFORMATION.
PROVIDE CAT 6 CABLE. REFER TO DATA DETAILS ON E-502 FOR
ADDITIONAL REQUIREMENTS.
DOOR CONTROL CONSOLE PROVIDED BY CONSTRUCTION
CONTRACT. COORDINATE WITH 'C' CONTRACT FOR FINAL
LOCATIONS PRIOR TO ROUGH-IN.
PROVIDE (3) 120V, 20A CIRCUITS FROM PANEL 'PP-EM' TO DOOR
CONTROL CONSOLE: (1) FOR CONTROL CONSOLE CONTROL
POWER, (2) FOR DOOR ELECTRIC LATCH POWER. THE CIRCUITS
ARE DESCRIBED AS FOLLOWS: (3) SETS OF (2)#12 G, 3/4"C
FROM PANEL 'PP-EM' TO MASTER CONSOLE LOCATIONS.
CONTROL WIRING, POWER WIRING & RACEWAYS FROM ELECTRIC
LOCK/DOOR POSITION SWITCHES (ONE PER DOOR) TO MASTER
DOOR CONTROL CONSOLE SHALL BE PROVIDED BY CONSTRUCTION
WORK CONTRACT.
COORDINATE FINAL LOCATION OF UPS REMOTE ALARM PANEL WITH
DIRECTOR'S REPRESENTATIVE PRIOR TO ROUGH-IN. PROVIDE
CONNECTION TO UPS PER MANUFACTURER'S RECOMMENDATIONS.
PROVIDE (3)#4 & #10G, 1"C
(3) HDMI CABLES, TYP.
PROVIDE (3) CAT5 E NANO SKEW CABLES PER CLASSROOM. ROUTE
TO A/V HEAD END, LOCATED IN ELECTRIC ROOM. LABEL &
TERMINATE IN RACK, TYP.
COORDINATE EXACT LOCATION WITH DIRECTOR'S
REPRESENTATIVE. PROVIDE 120V, 20A CIRCUIT TO PANEL PP-1.
PROVIDE (2) 120V, 20A CIRCUITS TO SERVE EER RACK. REFER TO
E-700 SERIES DRAWINGS FOR ADDITIONAL INFORMATION.
1
2
3
4
5
6
7
8
9
10
11
AVJ
L
AUDIO/VIDEO REMOTE JACK STATION. MOUNT (1) AT 2'-0" AFF & (1) AT
7'-0" AFF. 42" CLASSROOM MONITOR. MOUNT APPROXIMATELY 7'-0"
AFF. COORDINATE EXACT LOCATION WITH DIRECTOR'S
REPRESENTATIVE.
WALL-MOUNTED LOCK BOX CONTAINS THE FOLLOWING:
- BLU-RAY WITH REMOTE, TYP.
- USB (PC) REMOTE, TYP.
- MONITOR REMOTE, TYP.
COORDINATE EXACT LOCATION & MOUNTING HEIGHT WITH DIRECTOR'S
REPRESENTATIVE.
SCALE:
ELECTRICAL SINGLE LINE DIAGRAM
NOT TO SCALE
E109
3
PANEL
'LP-2A'
ETR
PANEL
'PP-EM'
60A
MLO
UPS
7
7
CIRCUIT SERVED
BREAKER
1
60 AMP FRAME
MLO
208/120 VOLT 3ϕ, 4W+G
10K AIC RMS SYM
CONTROL CONSOLE CONTROL POWER 20
PANEL PP-EM
AMP POLE
BREAKER
1
3
5
7
9
11
CIRCUIT SERVED
2
4
6
8
10
12
CIRCUIT
NUMBER
CIRCUIT
NUMBER
AMP POLE
120
120 120
120 120
1SPARE 20 SPARE120
1SPARE 20 SPARE120
1SPARE 20 SPARE120
JSE
GENERAL SCHEDULE NOTES:
1. PROVIDE SPARE BREAKERS AS INDICATED.
2. PROVIDE ARC FLASH WARNING LABEL PER SPECIFICATIONS.
3. PROVIDE TYPED PANEL DIRECTORY INDICATING LOADS SERVED.
4. REFER TO ELECTRICAL PLANS FOR GENERAL LOCATIONS OF EQUIPMENT.
5. PROVIDE ALL REQUIRED MOUNTING HARDWARE, BRACKETS, ACCESSORIES, ETC...
6. CONTRACTOR TO BALANCE PROPOSED PANEL LOAD ACROSS ALL PHASES EQUALLY.
7. VERIFY ALL CIRCUIT BREAKER REQUIREMENTS WITH EQUIPMENT MANUFACTURER. PROVIDE AS REQUIRED.
8. COORDINATE FINAL LABELING REQUIREMENTS WITH THE OWNER AND PROVIDE NAMEPLATE PER SPECIFICATIONS.
9. PROVIDE TOTAL NUMBER OF 1P SPACES AS INDICATED. PROVIDE BLOCK OFF PLATES FOR ALL SPACES WHICH ARE NOT UTILIZED.
10. REFER TO ELECTRICAL SINGLE LINE DIAGRAM, EQUIPMENT CONNECTION SCHEDULE & SPECIFICATIONS FOR ADDITIONAL INFORMATION/REQUIREMENTS.
CONTROL CONSOLE LATCH POWER
CONTROL CONSOLE LATCH POWER
SPARE
SPARE
SPARE
DESIGN & CONSTRUCTION
JADE STONE ENGINEERINGmechanical, electrical, plumbing
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
46137 - E
SCALE:
ELECTRICAL ENLARGED DATA PLAN
1/4" = 1'-0"
E-104
1
SCALE:
KEY PLAN
NTS
SCALE:
ELECTRICAL ENLARGED DATA PLAN
1/4" = 1'-0"
E-104
2
1
1
1
1
BLU-RAY
PLAYER
HDMI
VIDEO / AUDIO
MATRIX
INPUTS-OUTPUTS
CLASSROOMS
(TYP OF 3)
EXT
CAT5E
NANO
SKEW
A/V HEADEND EQUIPMENT
(PARTIAL SHOWN)
LOCATE IN ROOM B-005
EXT
DIST
AMP
H/E
COMPUTER LOCAL
BLU-RAY
AUDIO/VIDEO
HEAD END
BLU-RAY
HDMI
CLASSROOM
TV/MONITOR
HEADEND PC
USB
PORT
EXT
USB EXT.
LABEL "USB FROM
CLASSROOM
1-_____". (TYPICAL)
EXT
USB EXT
AUDIO
DIST
AMP
DIST
AMP
IN
ROOM
BLU-RAY
PLAYER
HDMI
SYMBOL:
LOCK BOX
PRESENTERS
PC REMOTE
RX
LOCATE ABOVE
PRESENTER
IN CEILING
CAT5E
NANO
SKEW
CAT5E
NANO
SKEW
PRESENTERS
PC REMOTE
TX
CLASSROOM
TV/BLU-RAY
REMOTES
LABEL "AV TO
CLASSROOM
1-_____". (TYPICAL)
PROVIDE RF DISTRIBUTION HEAD END DEVICES REQUIRED.
INSTALL IN EQUIPMENT RACK, AND INTEGRATE AS SHOWN. LOCATE
RACK IN ROOM B-005. REFER TO SPECIFICATION SECTION 274173.
STATION FOR INSTALLED CLASSROOM MONITOR:
ROUTE WIRING FROM HEAD END AND LOCAL DEVICES TO
RECESS WALL MOUNTED JACK PLATES. PROVIDE PANEL MOUNT HDMI
JACKS, CONNECTOR AND TERMINATE.
PROVIDE ETCHED LABELS ON PLATES IDENTIFYING
CONNECTED COMPONENTS. LOCATE 7' A.F.F.
STATION FOR PORTABLE CLASSROOM MONITOR:
PROVIDE DISTRIBUTION AMPLIFIERS AND ROUTE ADDITIONAL
CABLING TO 2' HIGH RECESS WALL MOUNTED OUTPUT
JACKPLATES IN CLASSROOMS. PROVIDE PANEL MOUNT HDMI JACKS,
CONNECTOR AND TERMINATE.PROVIDE ETCHED LABELS ON PLATES
IDENTIFYING CONNECTED COMPONENTS. LOCATE 2' A.F.F.
COMPUTER
LOCAL
BLU-RAY
AUDIO/VIDEO
HEAD END
BLU-RAY
SYMBOL:
REQUIREMENTS PER
CLASSROOM (TYPICAL
OF 3 ROOMS).
SCALER
BLU-RAY
PLAYER
RACK MOUNT
ADMIN COMPUTER
MONITOR
RACK MOUNT
ADMIN COMPUTER
MOUSE
SIGNAL
EXTENDERS
SIGNAL
EXTENDERS
SIGNAL
EXTENDERS
SIGNAL
EXTENDERS
SIGNAL
EXTENDERS
POWER STRIP
POWER STRIP
DISTRIBUTION
AMPS
DISTRIBUTION
AMPS
DISTRIBUTION
AMPS
RACK UPS
SPACE
SPACE
SPACE
SPACE
POWER STRIP
RACK MOUNT
COMPUTER
RACK MOUNT
COMPUTER
RACK MOUNT
COMPUTER
RACK MOUNT
COMPUTER
DATA
ROUTER
TO CLASSROOMS
MATRIX (PARTIAL)
RACK UPS
NOTES:
1. RACK LAYOUT SHOWN IS AN EXAMPLE.
SPECIFIC LAYOUT TO BE ADJUSTED FOR
EQUIPMENT PROVIDED IN ACCORDANCE WITH
A/V SPECIFICATION.
AVJ
2
3
1
AVJ
2
1
3
1
SCALE:
CLASSROOM A/V SYSTEM DETAILS
NTS
E-504
1
SCALE:
AVJ SYMBOL DETAILS
NTS
E-504
2
SCALE:
AV HEAD END RACK ELEVATION
NTS
E-504
3
DETAIL KEYNOTES:
AUDIO/ VIDEO CONNECTOR SHALL BE HDMI.1
DETAIL KEYNOTES:
HDMI
HDMI
BLU-RAY
PLAYER
HDMI
BLU-RAY
PLAYER
HDMI
HDMI
BLU-RAY
PLAYER
BLU-RAY
PLAYER
BLU-RAY
PLAYER
AUDIO/VIDEO
1
AUDIO/VIDEO
1
COMPUTER LOCAL
BLU-RAY
AUDIO/VIDEO
HEAD END
BLU-RAY
HDMI
HDMI
HDMI
DESIGN & CONSTRUCTION
JADE STONE ENGINEERINGmechanical, electrical, plumbing
Bernier, Carr & Associates,
Engineers, Architects and Land Surveyors, P.C.
46137 - E
AUDIO/VIDEO
HDMI
AUDIO/VIDEO
HDMI
AUDIO/VIDEO
HDMI
AUDIO/VIDEO
HDMI