DAM ALLIED WORKS
DATA:For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio : 50 :30 : 20
Fine aggregate : 0.40 cum. Cement : 247 kg Super plasticizer : 0.75 ltr
For 1 cum plum CC :- Coarse aggregates : 0.765 cum Blending ratio : 50 :30 : 20
Fine aggregate : 0.34 cum. Super plasticizer : 0.65 ltr
Cement : 210 kg.
Plums of size 150 to 80 mm : 0.24 cum
Wastage : 1 % for cement and 2 % for coarse / fine aggregates & plums.
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 40 mm down CA.
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.
Cycle time for batching / mixing / unloading 1 mix :
Batching 40-20 mm CA ( 0.091 ) cum : 3.50 min
Batching 20-10 mm & 10 mm below CA parellel activity : ---
Batching fine aggregate parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 minMixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 min
Cycle time for batching / mixing / unloading 1 mix : 5.00 min
No. of mixes per day with 50 min / hr working ( 50 x 8 / 5 ) : 80 mixes
Output of CC for 80 mixes ( 80 x 50 / 247 ) say : 16.20 cum
Quantity of plum concrete for sinking 15 % plums ( 16.20 / 0.85 ) : 19.00 cum
Qty of plums ( solid volume ) in plum concrete ( 19.00 x 0.15 ) : 2.85 cum
Consider 19.00 cum plum concrete for rate analysis.
1. Requirement of materials:
Cement for mix with 1 % wastage ( 19 x 210 x 1.01 ) : 4030 kg
Cement for incidental works @ 3 kg / cum ( 19 x 3 ) : 57 kg
Coarse aggregate 40-20 mm size range ( 19 x 0.765 x 0.5 x 1.02 ) : 7.45 cum
Coarse aggregate 20-10 mm size range ( 19 x 0.765 x 0.3 x 1.02 ) : 4.45 cum
Coarse aggregate 10-4.75 mm size ( 19 x 0.765 x 0.2 x 1.02 ) : 2.95 cum
Qty of plums ( loose volume) with 2 % wastage ( 19 x 0.24 x 1.02 ) : 4.65 cum
Fine aggregate ( 19 x 0.34 x 1.02 ) : 6.60 cum
Super plasticiser ( 19 x 0.65 x 1.02 ) : 12.6 ltrs
2. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.
Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
3. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in smaller lifts.
Requirement of shuttering for plain concrete works is assumed at 1 sqm / cum of concrete.
Shuttering @ 1.00 sqm per cum of concrete ( 19 x 1 ) : 19.00 sqm
Scaffolding / supports etc @ 15 percent of cost of shuttering.
4. Requirement of workforce ( other than machinery crew ) :Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 40-20 mm CA Heavy mazdoors : 3 Nos.
Batching 20-10 mm & 10 mm below CA Heavy mazdoors : 3 Nos.
Batching fine aggregate Heavy mazdoors : 3 Nos.
Batching cement Heavy mazdoors : 2 Nos.
Remixing and conveying concrete Heavy mazdoors : 4 Nos.
Light mazdoors : 16 Nos.
Conveying plums Heavy mazdoors : 1 Nos.
60
8/13/2019 Data Rates-Dam Works-Part 4
2/21
DAM ALLIED WORKS
Light mazdoors : 2 Nos.
Laying concrete and plums Mason : 1 No.
Heavy mazdoors : 4 Nos.
Washing / cleaning / curing etc Light mazdoors : 1 No.
Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17
Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.
5. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.
6. Use rate of materials :
Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07
RATE ANALYSIS UNIT : 19.00 cum
A. MATERIALS:Sl No Unit Amount
in Rs.
1 Cement for mix with 1 % wastage kg 4030.00 4.00 16120.00
Cement for incidentals @ 3 kg/cum PC kg 57.00 4.00 228.00
2 Coarse aggregate 40-20 mm cum 7.45 381.00 2838.45
Coarse aggregate 20-10 mm cum 4.45 520.00 2314.00
Coarse aggregate 10 mm below cum 2.95 669.00 1973.55
3 Plums of size 150 to 80 mm cum 4.65 240.00 1116.00
4 Fine aggregate ( screened ) cum 6.60 199.00 1313.40
5 Super Plasticizer ltr 12.60 75.00 945.00
6 Use rate of shuttering for 40 uses sqm 19.00 151.07 2870.24
7 Scaffolding @ 15 % of shuttering 430.54
Total Rs: 30149.18
Add for small Tools and Plants @ 1% Rs: 301.49
Add for Contractor's Profit @ 10% Rs: 3014.92
Add for Contractor's Overheads @ 5% Rs: 1507.46
Add Royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add Royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 34973.04
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 10 hp pump ( ele ) Hour 1.00 5.00 5.00
Fuel / Energy charges Hour 1.00 50.00 50.003 Needle vibrator 60 mm dia ( ele ) Hour 8.00 8.00 64.00
Fuel / Energy charges Hour 8.00 8.00 64.00
4 Sundries LS 1.00 30.00 30.00
Total Rs: 717.00
Add for small Tools and Plants @ 1% Rs: 7.17
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 34.40
Add for Contractor's Overheads @ 5% Rs: 35.85
Total hire charges of Machinery : Rs: 794.42
Perticulars
Description Quantity Rate
Quantity
in Rs.
Rate
in Rs.
61
8/13/2019 Data Rates-Dam Works-Part 4
3/21
DAM ALLIED WORKS
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Concrete mixer Hour 8.00 75.10 600.80
2 Crew for Pump Hour 1.00 26.90 26.90
3 Crew for Needle vibrator Hour 8.00 53.30 426.40
4 Mason Class-I Day 1.00 159.00 159.00
5 Maistry Day 1.00 141.50 141.50
6 Heavy mazdoor
for batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 9.00 132.00 1188.00
for loading mortar pans Day 4.00 132.00 528.00
for loading plums Day 1.00 132.00 132.00
for laying concrete and plums Day 4.00 132.00 528.00
7 Light mazdoorfor conveying concrete Day 16.00 130.50 2088.00
for conveying plums Day 2.00 130.50 261.00
for cleaning / washing / curing Day 1.00 130.50 130.50
8 Labour for shuttering sqm 19.00 33.17 630.14
Labour for scaffolding @ 15 % 189.04
Total Rs: 7297.28
Add for small Tools and Plants @ 1% Rs: 72.97
Add for Contractor's Profit @ 10% Rs: 729.73
Add for hidden cost on Labour @ 15% Rs: 1094.59
Add for additional hidden cost on Labour @ 5% Rs: 364.86
Add for Contractor's Overheads @ 5% Rs: 364.86
Total cost of Labour : Rs: 9924.29
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 34973.04
B. Hire charges of Machinery Rs: 794.42
C. Cost of Labour Rs: 9924.29
Total Rs: 45691.76
Add for enabling works @ 1.40% Rs: 639.68
46331.44
Add for 1 km rehandling / initial lead including loading / unloading:
Cement 4087 kg @ Rs: 129.10 / tonne Rs: 527.63
C A and plums 19.5 cum @ Rs: 121.90 / cum Rs: 2377.05
Fine aggregates 6.6 cum @ Rs: 84.90 / cum Rs: 560.34
Total cost for 19.00 cum Rs: 49796.46
Rate per cum Rs: 2621.00
Rate approved per cum Rs: 2621.00
SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 18
ITEM: Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down sizeapproved, clean, hard, graded
aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
Description Quantity Rate
in Rs.
TOTAL Rs:
62
8/13/2019 Data Rates-Dam Works-Part 4
4/21
DAM ALLIED WORKS
for plain concreteworks with initial lead upto 1 km and all lifts. ( Cement content 220 kg /
cum with use of super plasticiser )
DATA:For 1 cum CC :- Coarse aggregates : 0.90 cum. Blending ratio : 50 :30 : 20
Fine aggregate : 0.40 cum. Cement : 220 kg Super plasticizer : 0.70 ltr
Wastage : 1 % for cement and 2 % for coarse & fine aggregates.
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 40 mm down CA.
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.
Cycle time for batching / mixing / unloading 1 mix :
Batching 40-20 mm CA ( 0.102 cum ) : 4.00 min
Batching 20-10 mm & 10 mm below CA parellel activity : ---
Batching fine aggregate parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 min
Mixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 minCycle time for batching / mixing / unloading 1 mix : 5.50 min
No. of mixes per day with 50 min / hr working ( 50 x 8 / 5.5 ) : 73 mixes
Output of CC for 73 mixes ( 73 x 50 / 220 ) say : 16.60 cum
Consider 16.60 cum concrete for rate analysis.
1. Requirement of materials:
Cement for mix with 1 % wastage ( 16.6 x 220 x 1.01 ) : 3689 kg
Cement for incidental works @ 3 kg / cum ( 16.6 x 3 ) : 50 kg
Coarse aggregate 40-20 mm size range ( 16.6 x 0.9 x 0.5 x 1.02 ) : 7.60 cum
Coarse aggregate 20-10 mm size range ( 16.6 x 0.9 x 0.3 x 1.02 ) : 4.55 cum
Coarse aggregate 10-4.75 mm size ( 16.6 x 0.9 x 0.2 x 1.02 ) : 3.05 cum
Fine aggregate ( 16.6 x 0.4 x 1.02 ) : 6.75 cum
Super plasticiser ( 16.6 x 0.7 x 1.02 ) : 11.90 ltrs
2. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.
Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
3. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in smaller lifts.
Requirement of shuttering for concrete works is assumed at 1 sqm / cum of concrete.
Shuttering @ 1.00 sqm per cum of concrete ( 16.6 x 1 ) : 16.60 sqm
Scaffolding / supports etc @ 15 percent of cost of shuttering.
4. Requirement of workforce ( other than machinery crew ) :
Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 40-20 mm CA Heavy mazdoors : 3 Nos.
Batching 20-10 mm & 10 mm below CA Heavy mazdoors : 3 Nos.
Batching fine aggregate Heavy mazdoors : 3 Nos.
Batching cement Heavy mazdoors : 2 Nos.Remixing and conveying concrete Heavy mazdoors : 4 Nos.
Light mazdoors : 17 Nos.
Laying concrete Mason : 1 No.
Heavy mazdoors : 3 Nos.
Washing / cleaning / curing etc Light mazdoors : 1 No.
Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17
Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.
63
8/13/2019 Data Rates-Dam Works-Part 4
5/21
DAM ALLIED WORKS
5. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.
6. Use rate of materials :
Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07
RATE ANALYSIS UNIT : 16.60 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Cement for mix with 1% wastage kg 3689.00 4.00 14756.00
Cement for incidentals @ 3 kg/ cum kg 50.00 4.00 200.00
2 Coarse aggregate 40-20 mm cum 7.60 381.00 2895.60
Coarse aggregate 20-10 mm cum 4.55 520.00 2366.00
Coarse aggregate 10 mm below cum 3.05 669.00 2040.45
3 Fine aggregate ( screened ) cum 6.75 199.00 1343.25
4 Super plasticizer ltr 11.90 75.00 892.50
5 Use rate of shuttering sqm 16.60 151.07 2507.68 6 Use rate of scaffolding @ 15 % 376.15
Total Rs: 27377.64
Add for small Tools and Plants @ 1% Rs: 273.78
Add for Contractor's Profit @ 10% Rs: 2737.76
Add for Contractor's Overheads @ 5% Rs: 1368.88
Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 31758.06
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 10 hp pump ( ele ) Hour 1.00 5.00 5.00
Fuel / Energy charges Hour 1.00 50.00 50.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 7.00 56.00
Fuel / Energy charges Hour 8.00 5.00 40.00
Total Rs: 655.00
Add for small Tools and Plants @ 1% Rs: 6.55
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 29.00
Add for Contractor's Overheads @ 5% Rs: 32.75
Total hire charges of Machinery : Rs: 723.30
C. LABOUR:
Sl No Unit Amount
in Rs.1 Crew for Concrete mixer Hour 8.00 75.10 600.80
2 Crew for Pump Hour 1.00 26.90 26.90
3 Crew for Needle vibrator Hour 8.00 53.30 426.40
4 Mason Class-I Day 1.00 159.00 159.00
Contd
Description
Description
Perticulars
in Rs.
Quantity Rate
in Rs.
Quantity Rate
Quantity Rate
in Rs.
64
8/13/2019 Data Rates-Dam Works-Part 4
6/21
DAM ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
5 Heavy mazdoor
for batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 9.00 132.00 1188.00
for loading mortar pans Day 4.00 132.00 528.00
for laying Day 3.00 132.00 396.00
6 Light mazdoor
for conveying concrete Day 17.00 130.50 2218.50
for cleaning / washing / curing Day 1.00 130.50 130.50
7 Labour cost of shuttering sqm 16.60 33.17 550.54
8 Labour cost of scaffolding @ 15 % 82.58
Total Rs: 6575.22
Add for small Tools and Plants @ 1% Rs: 65.75
Add for Contractor's Profit @ 10% Rs: 657.52
Add for hidden cost on Labour @ 15% Rs: 986.28Add for additional hidden cost on labour @ 5% Rs: 328.76
Add for Contractor's Overheads @ 5% Rs: 328.76
Total cost of Labour : Rs: 8942.30
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 31758.06
B. Hire charges of Machinery Rs: 723.30
C. Cost of Labour Rs: 8942.30
Total Rs: 41423.66
Add for enabling works @ 1.40% Rs: 579.93
42003.59
Add for 1 km rehandling / initial lead including loading / unloading:
Cement 3739 kg @ Rs: 129.10 / tonne Rs: 482.70
Coarse aggregates 15.2 cum @ Rs: 121.90 / cum Rs: 1852.88Fine aggregates 6.75 cum @ Rs: 84.90 / cum Rs: 573.08
Total cost for 16.60 cum Rs: 44912.25
Rate per cum Rs: 2706.00
Rate approved per cum Rs: 2706.00
SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 19
ITEM: Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded
aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
for plain concreteworks with initiallead upto 1 km and all lifts. ( Cement content : 290 kg /
cum with use of super plasticiser )
DATA:For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35
Fine aggregate : 0.45 cum. Super plasticizer : 0.90 ltr
Cement : 290 kg.
Wastage : 1 % for cement and 2 % for coarse & fine aggregates.
Description Quantity Rate
in Rs.
TOTAL Rs:
65
8/13/2019 Data Rates-Dam Works-Part 4
7/21
DAM ALLIED WORKS
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.
Cycle time for batching / mixing / unloading 1 mix :
Batching 20-10 mm CA ( 0.089 cum ) : 3.50 min
Batching 10 mm below CA parellel activity : ---
Batching fine aggregate parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 min
Mixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 min
Cycle time for batching / mixing / unloading 1 mix : 5.00 min
No. of mixes per day with 50 min / hr working ( 50 x 8 / 5 ) : 80 mixes
Output of CC for 80 mixes ( 80 x 50 / 290 ) say : 13.80 cum
Consider 13.80 cum concrete for rate analysis.
1. Requirement of materials:
Cement for mix with 1 % wastage ( 13.8 x 290 x 1.01 ) : 4042 kg
Cement for incidental works @ 3 kg / cum ( 13.8 x 3 ) : 42 kg
Coarse aggregate 20-10 mm size range ( 13.8 x 0.8 x 0.65 x 1.02 ) : 7.30 cum
Coarse aggregate 10-4.75 mm size ( 13.8 x 0.8 x 0.35 x 1.02 ) : 3.95 cumFine aggregate ( 13.8 x 0.45 x 1.02 ) : 6.35 cum
Super plasticiser ( 13.8 x 0.9 x 1.02 ) : 12.70 ltrs
2. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.
Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
3. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in smaller lifts.
Requirement of shuttering for concrete works is assumed at 1 sqm / cum of concrete.
Shuttering @ 1.00 sqm per cum of concrete ( 13.8 x 1 ) : 13.80 sqm
Scaffolding / supports etc @ 15 percent of cost of shuttering.
4. Requirement of workforce ( other than machinery crew ) :
Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 20-10 mm CA Heavy mazdoors : 3 Nos.
Batching 10 mm below CA Heavy mazdoors : 2 Nos.
Batching fine aggregate Heavy mazdoors : 3 Nos.
Batching cement Heavy mazdoors : 2 Nos.
Remixing and conveying concrete Heavy mazdoors : 4 Nos.
Light mazdoors : 14 Nos.
Laying concrete Mason : 1 No.
Heavy mazdoors : 3 Nos.
Washing / cleaning / curing etc Light mazdoors : 1 No.
Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17
Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.
5. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.6. Use rate of materials :
Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07
66
8/13/2019 Data Rates-Dam Works-Part 4
8/21
DAM ALLIED WORKS
RATE ANALYSIS UNIT : 13.80 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Cement for mix with 1% wastage kg 4042.00 4.00 16168.00
Cement for incidentals @ 3 kg/ cum kg 42.00 4.00 168.00
2 Coarse aggregate 20-10 mm cum 7.30 520.00 3796.00
Coarse aggregate 10 mm below cum 3.95 669.00 2642.55
3 Fine aggregate ( screened ) cum 6.35 199.00 1263.65
4 Super plasticiser ltr 12.70 75.00 952.50
5 Use rate of shuttering sqm 13.80 151.07 2084.70
6 Use rate of scaffolding @ 15 % 312.71
Total Rs: 27388.11
Add for small Tools and Plants @ 1% Rs: 273.88
Add for Contractor's Profit @ 10% Rs: 2738.81
Add for Contractor's Overheads @ 5% Rs: 1369.41
Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 31770.20
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 10 hp pump ( ele ) Hour 1.00 5.00 5.00
Fuel / Energy charges Hour 1.00 50.00 50.00
3 Needle vibrator 40 mm dia ( ele ) Hour 8.00 7.00 56.00
Fuel / Energy charges Hour 8.00 5.00 40.00
Total Rs: 655.00
Add for small Tools and Plants @ 1% Rs: 6.55
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 29.00
Add for Contractor's Overheads @ 5% Rs: 32.75
Total hire charges of Machinery : Rs: 723.30
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Concrete mixer Hour 8.00 75.10 600.80
2 Crew for Pump Hour 1.00 26.90 26.90
3 Crew for Needle vibrator Hour 8.00 53.30 426.40
4 Mason Class-I Day 1.00 159.00 159.00
5 Heavy mazdoor
for batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 8.00 132.00 1056.00
for loading mortar pans Day 4.00 132.00 528.00
for laying Day 3.00 132.00 396.006 Light mazdoor
for conveying concrete Day 14.00 130.50 1827.00
Contd
Description
Perticulars
Description Quantity Rate
Quantity
in Rs.
Quantity Rate
in Rs.
Rate
in Rs.
67
8/13/2019 Data Rates-Dam Works-Part 4
9/21
DAM ALLIED WORKS
C. LABOUR ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
for cleaning / washing / curing Day 1.00 130.50 130.50
7 Labour cost of shuttering sqm 13.80 33.17 457.68
8 Labour cost of scaffolding @ 15 % 68.65
Total Rs: 5944.93
Add for small Tools and Plants @ 1% Rs: 59.45
Add for Contractor's Profit @ 10% Rs: 594.49
Add for hidden cost on Labour @ 15% Rs: 891.74
Add for additional hidden cost on labour @ 5% Rs: 297.25
Add for Contractor's Overheads @ 5% Rs: 297.25
Total cost of Labour : Rs: 8085.10
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 31770.20
B. Hire charges of Machinery Rs: 723.30
C. Cost of Labour Rs: 8085.10
TOTAL Rs: 40578.60
Add for enabling works @ 1.40% Rs: 568.10Total Rs: 41146.71
Add for 1 km rehandling / initial lead including loading / unloading:
Cement 4084 kg @ Rs: 129.10 / tonne Rs: 527.24
Coarse aggregates 10.95 cum @ Rs: 121.90 / cum Rs: 1334.81
Fine aggregates 6.35 cum @ Rs: 84.90 / cum Rs: 539.12
Total cost for 13.80 cum Rs: 43547.87
Rate per cum Rs: 3156.00
Rate approved per cum Rs: 3156.00
SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 20
ITEM: Providing and laying insitu vibrated M-20( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded
aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
for RCC works of spillway bridge, blockout concretingand such other similar structures with
conjested reinforcement areas with initial lead upto 1 km and all lifts. ( Cement content :
330 kg / cum with use of super plasticiser ).
DATA:For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35
Fine aggregate : 0.45 cum. Cement : 330 kg Super plasticizer : 1.00 ltr
Wastage : 1 % for cement and 2 % for coarse & fine aggregates.
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA & FA.
Cycle time for batching / mixing / unloading 1 mix :
Batching 20-10 mm CA ( 0.079 cum ) : 3.00 min
Batching 10 mm below CA parellel activity : ---Batching fine aggregate parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 min
Description Quantity Rate
in Rs.
68
8/13/2019 Data Rates-Dam Works-Part 4
10/21
DAM ALLIED WORKS
Mixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 min
Cycle time for batching / mixing / unloading 1 mix : 4.50 min
No. of mixes per day with 50 min / hr working ( 50 x 8 / 4.5 ) : 89 mixes
Output of CC for 89 mixes ( 89 x 50 / 330 ) say : 13.50 cum
Consider 13.50 cum concrete for rate analysis.
1. Requirement of materials:
Cement for mix with 1 % wastage ( 13.5 x 330 x 1.01 ) : 4500 kg
Cement for incidental works @ 3 kg / cum ( 13.8 x 3 ) : 41 kg
Coarse aggregate 20-10 mm size range ( 13.5 x 0.8 x 0.65 x 1.02 ) : 7.15 cum
Coarse aggregate 10-4.75 mm size ( 13.5 x 0.8 x 0.35 x 1.02 ) : 3.85 cum
Fine aggregate ( 13.5 x 0.45 x 1.02 ) : 6.20 cum
Super plasticiser ( 13.5 x 1.0 x 1.02 ) : 13.80 ltrs
2. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.
Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
3. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in smaller lifts.
Requirement of shuttering for bridge concrete works is assumed at 4 sqm / cum of concrete.
Shuttering @ 4 sqm per cum of concrete ( 13.5 x 4 ) : 54 sqmScaffolding / supports etc @ 100 percent of cost of shuttering.
4. Requirement of workforce ( other than machinery crew ) :
Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 20-10 mm CA Heavy mazdoors : 3 Nos.
Batching 10 mm below CA Heavy mazdoors : 2 Nos.
Batching fine aggregate Heavy mazdoors : 3 Nos.
Batching cement Heavy mazdoors : 2 Nos.
Remixing and conveying concrete Heavy mazdoors : 4 Nos.
Light mazdoors : 14 Nos.
Laying concrete Mason : 1 No.
Heavy mazdoors : 3 Nos.
Washing / cleaning / curing etc Light mazdoors : 1 No.
Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17
Labour charges for erecting & dismantling scaffolding @ 100 % of cost labour for shuttering.
5. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.
6. Use rate of materials :
Use rate of normal shutter per sqm for 30 uses ( Annexure-A Item : 13 ) Rs: 186.42
RATE ANALYSIS UNIT : 13.50 cum
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Cement for mix with 1% wastage kg 4500.00 4.00 18000.00
Cement for incidentals @ 3 kg/ cum kg 41.00 4.00 164.00
2 Coarse aggregate 20-10 mm cum 7.15 520.00 3718.00
Coarse aggregate 10 mm below cum 3.85 669.00 2575.65Contd
A. MATERIALS ( Contd ) :
Sl No Unit Amount
Perticulars Quantity Rate
in Rs.
Perticulars Quantity Rate
69
8/13/2019 Data Rates-Dam Works-Part 4
11/21
DAM ALLIED WORKS
in Rs.
Contd
3 Fine aggregate ( screened ) cum 6.20 199.00 1233.80
4 Super plasticiser ltr 13.80 75.00 1035.00
5 Use rate of shuttering sqm 54.00 186.42 10066.70
6 Scaffolding @ 100 % of shuttering 10066.70
Total Rs: 46859.84
Add for small Tools and Plants @ 1% Rs: 468.60
Add for Contractor's Profit @ 10% Rs: 4685.98
Add for Contractor's Overheads @ 5% Rs: 2342.99
Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 54357.42
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 10 hp pump ( ele ) Hour 1.00 5.00 5.00
Fuel / Energy charges Hour 1.00 50.00 50.003 Needle vibrator 40 mm dia ( ele ) Hour 8.00 7.00 56.00
Fuel / Energy charges Hour 8.00 5.00 40.00
Total Rs: 655.00
Add for small Tools and Plants @ 1% Rs: 6.55
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 29.00
Add for Contractor's Overheads @ 5% Rs: 32.75
Total hire charges of Machinery : Rs: 723.30
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Concrete mixer Hour 8.00 75.10 600.80
2 Crew for Pump Hour 1.00 26.90 26.90
3 Crew for Needle vibrator Hour 8.00 53.30 426.40
4 Mason Class-I Day 1.00 159.00 159.00
5 Heavy mazdoor
for batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 8.00 132.00 1056.00
for loading mortar pans Day 4.00 132.00 528.00
for laying Day 3.00 132.00 396.00
6 Light mazdoor
for conveying concrete Day 14.00 130.50 1827.00
for cleaning/ washing/ curing Day 1.00 130.50 130.50
7 Labour cost of shuttering sqm 54.00 33.17 1790.91
8 Labour cost of scaffolding @ 100 % 1790.91
Total Rs: 9000.42
Contd
C. LABOUR ( Contd ) :
Sl No Unit Amount
in Rs.
Description
Description Quantity Rate
in Rs.
Quantity Rate
in Rs.
in Rs.
Description Quantity Rate
in Rs.
70
8/13/2019 Data Rates-Dam Works-Part 4
12/21
DAM ALLIED WORKS
Contd
Add for small Tools and Plants @ 1% Rs: 90.00
Add for Contractor's Profit @ 10% Rs: 900.04
Add for hidden cost on Labour @ 15% Rs: 1350.06
Add for additional hidden cost on labour @ 5% Rs: 450.02
Add for Contractor's Overheads @ 5% Rs: 450.02
Total cost of Labour : Rs: 12240.57
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 54357.42
B. Hire charges of Machinery Rs: 723.30
C. Cost of Labour Rs: 12240.57
TOTAL Rs: 67321.29
Add for enabling works @ 1.40% Rs: 942.50
Total Rs: 68263.79
Add for 1 km rehandling / initial lead including loading / unloading:
Cement 4541 kg @ Rs: 129.10 / tonne Rs: 586.24
Coarse aggregates 11.0 cum @ Rs: 121.90 / cum Rs: 1340.90
Fine aggregates 6.2 cum @ Rs: 84.90 / cum Rs: 526.38
Total cost for 13.50 cum Rs: 70717.31
Rate per cum Rs: 5238.00Rate approved per cum Rs: 5238.00
SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 21
ITEM: Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23 cm diameter
central hole using cement and 20 mm downapproved, clean, hard, graded coarse aggregates
in 1 : 3.50 proportion by volume including cost of all materials, machinery, labour, formwork,
curing etc., complete with initial lead upto 1 km and all lifts.
DATA:Area of concrete for body drain ( 0.685 x 0.685 - 0.7857 x 0.23 x 0.23 ) : 0.428 sqm
For 1 cum porous CC : Coarse aggregate : 1.00 cum Blending ratio : 65 : 35
Cement : 408 kg.
Wastage : 1 % for cement and 2 % for aggregate.
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA
Cycle time for batching / mixing / unloading 1 mix :
Batching 20-10 mm CA ( 0.080 cum ) : 3.00 min
Batching 10 mm below CA parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 min
Mixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 min
Cycle time for batching / mixing / unloading 1 mix : 4.50 min
No. of mixes per day with 50 min / hr working ( 50 x 8 / 4.5 ) : 89 mixes
Output of CC for 89 mixes ( 89 x 50 / 408 ) say : 10.90 cum
Generally, body drain is formed by casting porous concrete blocks of convenient height in the
casting yard and the blocks after curing are shifted to body drain location as concrete / masonry
work progresses for the dam block.
Assuming 2 % wastage of CC during casting of blocks the quantity of concrete required per
metre height of body drain will be ( 0.428 x 1.02 ) : 0.436 cum
71
8/13/2019 Data Rates-Dam Works-Part 4
13/21
DAM ALLIED WORKS
Length of body drain for 1 day output of mixer ( 10.9 / 0.436 ) : 25.00 m
Consider 25 m porous concrete body drain for analysis.
1. Requirement of materials:
Cement for mix with 1 % wastage ( 10.9 x 408 x 1.01 ) : 4492 kg
Coarse aggregate 20-10 mm size range ( 10.9 x 1.0 x 0.65 x 1.02 ) : 7.20 cum
Coarse aggregate 10-4.75 mm size ( 10.9 x 1.0 x 0.35 x 1.02 ) : 3.90 cum
2. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of porous concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
3. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in moulds.
Requirement of shuttering for 1 m height ( 4 x 0.685 + 3.14 x 0.23 ) say : 3.46 sqm
Shuttering for 25 m height of drain ( 25 x 3.5 ) : 86.50 sqm
4. Requirement of workforce ( other than machinery crew ) :
Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 20-10 mm CA Heavy mazdoors : 3 Nos.
Batching 10 mm below CA Heavy mazdoors : 2 Nos.
Batching cement Heavy mazdoors : 2 Nos.
Remixing and conveying concrete Heavy mazdoors : 4 Nos.
Light mazdoors : 11 Nos.
Shuttering for blocks Fitter shuttering : 1 No.Laying concrete for blocks Mason : 1 No.
Heavy mazdoors : 1 No.
Washing / cleaning / curing etc Light mazdoors : 1 No.
Conveying blocks to body drain location Heavy mazdoors : 2 Nos.
5. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.
6. Use rate of materials :
Consider 100 uses of moulds.
Cost of shuttering per sqm as per data in Item-13 @ Rs: 3535.51
Use rate of shutter per sqm for 100 uses 3535.51 / 100 Rs: 35.36
Add for shutter oil 0.2 ltr / sqm @ Rs: 25.00 / ltr Rs: 5.00
Use rate of shutter per sqm for 100 uses Rs: 40.36
RATE ANALYSIS UNIT : 25.00 Rm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Cement with 1% wastage kg 4492.00 4.00 17968.00
2 Coarse aggregate 20-10 mm cum 7.20 520.00 3744.00
3 Coarse aggregate 10-4.75 mm cum 3.90 669.00 2609.10
4 Use rate of shuttering sqm 86.50 40.36 3490.71
Total Rs: 27811.81
Add for small Tools and Plants @ 1% Rs: 278.12
Add for Contractor's Profit @ 10% Rs: 2781.18
Contd
A. MATERIALS ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
Add for Contractor's Overheads @ 5% Rs: 1390.59
Quantity Rate
in Rs.
Perticulars
Perticulars
Quantity Rate
in Rs.
72
8/13/2019 Data Rates-Dam Works-Part 4
14/21
DAM ALLIED WORKS
Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 32261.70
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 10 hp pump ( ele ) Hour 1.00 5.00 5.00
Fuel / Energy charges Hour 1.00 50.00 50.00
Total Rs: 559.00
Add for small Tools and Plants @ 1% Rs: 5.59
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 25.00
Add for Contractor's Overheads @ 5% Rs: 27.95
Total hire charges of Machinery : Rs: 617.54
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Concrete mixer Hour 8.00 75.10 600.802 Crew for Pump Hour 1.00 26.90 26.90
3 Mason Class-I Day 1.00 159.00 159.00
4 Heavy mazdoor
for batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 5.00 132.00 660.00
for loading mortar pans Day 2.00 132.00 264.00
for laying & packing concrete Day 3.00 132.00 396.00
for shifting blocks to site Day 2.00 132.00 264.00
5 Light mazdoor
for conveying concrete Day 11.00 130.50 1435.50
6 Fitter shuttering Day 1.00 148.50 148.50
Total Rs: 4222.70
Add for small Tools and Plants @ 1% Rs: 42.23
Add for Contractor's Profit @ 10% Rs: 422.27
Add for hidden cost on Labour @ 15% Rs: 633.41
Add for additional hidden cost on labour @ 5% Rs: 211.14
Add for Contractor's Overheads @ 5% Rs: 211.14
Total cost of Labour : Rs: 5742.87
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 32261.70
B. Hire charges of Machinery Rs: 617.54
C. Cost of Labour Rs: 5742.87
TOTAL Rs: 38622.12
Add for enabling works @ 1.40% Rs: 540.71
Total Rs: 39162.83
Add for 1 km rehandling / initial lead including loading / unloading:
Cement 4492 kg @ Rs: 129.10 / tonne Rs: 579.92
Coarse aggregates11.10 cum @ Rs: 121.90 / cum Rs: 1353.09
Total cost for 25.00 Rm Rs: 41095.83
Description
Description
in Rs.
Quantity Rate
in Rs.
Quantity Rate
73
8/13/2019 Data Rates-Dam Works-Part 4
15/21
DAM ALLIED WORKS
Rate per Rm Rs: 1644.00
Rate approved per Rm Rs: 1644.00
SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 22.a
ITEM: Providing and laying insitu vibrated M-20( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded
aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
for RCC solid parapetconsisting of 350 x 200 mm kerb, 350 x 350 x 1000 mm pillars spaced
approximately at 3.35 m c / c, 125 mm thick wall 800 mm height with 125 mm thick and 350
mm wide coping slab for wall and 125 mm thick 400 x 400 mm coping for pillars with top edges
of kerb and coping chamferred / rounded as directed etc., complete ( excluding cost of providing
and placing reinforcement steel and gate ) with initiallead upto 1 km and all lifts. ( Cement
content 330 kg / cum with use of super plasticiser )
DATA:Consider one spillway bridge span of 18 m.
Consider solid parapet for rate analysis for one span.
Consider 0.9 wide opening for approach to pier top hoist platform on d / s side.
0.35 mGate 3.00 m 0.125 m
0.8 m
0.20 m
SKETCH SHOWING COMPONENTS OF RCC SOLID PARAPET
Length of kerb on u /s and d / s ( 18.00 + 18.00 ) : 36.00 m
Length of parapet ( 18.00 + 18.00 - 0.90 ) : 35.10 m
Number of pillars for 3.35 m c / c spacing : 12 Nos
Number of wall panels of size 3.00 x 0.80 x 0.125 m : 10 Nos
Number of wall panels of size 0.45 x 0.80 x 0.125 m (on u/s only) : 2 Nos
Length of coping for wall panels ( 3 x 10 + 2 x 0.45 ) : 30.90 m
Number of coping slabs for pillers : 12 Nos
For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35
Fine aggregate : 0.45 cum. Cement : 330 kg Super plasticiser : 1.00 ltr.
Wastage : 1 % for cement and 2 % for coarse & fine aggregates.
1. Quantity of concrete per span :
For kerb ( 36 x 0.35 x 0.20 ) : 2.52 cum
For pillars ( 12 x 1 x 0.35 x 0.35 ) : 1.47 cum
For wall panels ( 10 x 3 x 0.80 x 0.125 + 2 x 0.45 x 0.80 x 0.125 ) : 3.09 cum
For wall coping ( 10 x 3 x 0.35 x 0.125 + 2 x 0.45 x 0.35 x 0.125 ) : 1.35 cum
For pillar coping ( 12 x 0.40 x 0.40 x 0.125 ) : 0.24 cum
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.
74
8/13/2019 Data Rates-Dam Works-Part 4
16/21
DAM ALLIED WORKS
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA
Cycle time for batching / mixing / unloading 1 mix :
Batching 20-10 mm CA ( 0.079 cum ) : 3.00 min
Batching 10 mm below CA parellel activity : ---
Batching fine aggregate parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 min
Mixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 min
Cycle time for batching / mixing / unloading 1 mix : 4.50 min
Construction of parapet involves laying of concrete in three stages namely ( i ) kerb, ( ii ) pillars
and wall panels and ( iii ) coping. While concrete laying cycle can be matched with production
cycle for kerb and coping, the laying cycle will be very slow for pillars and wall panels in view of
thin sections with reinforcement. Considering the laying time for pillars and wall panels at twice
the production time the average cycle time will be about 1.5 times the production cycle time.
Average cycle time for laying concrete ( 4.50 x 1.5 ) : 6.75 min
No. of mixes per day with 50 min / hr working ( 50 x 8 / 6.75 ) : 59 mixes
Output of CC for 59 mixes ( 59 x 50 / 330 ) : 8.9 cum
As the computed daily output of 8.9 cum is close to one span quantity of 8.7 cum consider the
daily output at 8.7 cum for rate analysis.
2. Requirement of materials:Cement for mix with 1 % wastage ( 8.7 x 330 x 1.01 ) : 2900 kg
Cement for incidental works @ 5 kg / cum ( 8.7 x 5 ) : 43.5 kg
Coarse aggregate 20-10 mm size range ( 8.7 x 0.8 x 0.65 x 1.02 ) : 4.60 cum
Coarse aggregate 10-4.75 mm size ( 8.7 x 0.8 x 0.35 x 1.02 ) : 2.50 cum
Fine aggregate ( 8.7 x 0.45 x 1.02 ) : 4.00 cum
Super plasticiser ( 8.7 x 1.0 x 1.02 ) : 8.90 ltrs
3. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.
Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
4. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in smaller lifts.
Shuttering for kerb x 18 x 0.20 + 4 x 0.35 x 0.20 ) : 14.68 sqm
For pillars x 2 x 0.55 x 1 + 2 x 0.15 x 1 ) : 13.50 sqm
For wall panels ( 10x2x3x0.80 + 2x2x0.45x0.80 + 2x0.15x0.80 ) : 49.68 sqm
For wall coping( 0.45 x 3 x 10 + 0.45 x 0.45 x 2 + 2 x 0.35 x 0.15 ) : 14.01 sqm
For pillar coping ( 12 x 4 x 0.35 x 0.15 ) : 2.52 sqm
Total ( say ) : 95.00 sqm
Scaffolding / supports assumed at 15 percent of cost of shuttering.
5. Requirement of workforce ( other than machinery crew ) :
Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 20-10 mm CA Heavy mazdoors : 2 Nos.
Batching 10 mm below CA Heavy mazdoors : 2 Nos.
Batching fine aggregate Heavy mazdoors : 2 Nos.
Batching cement Heavy mazdoors : 2 Nos.
Remixing and conveying concrete Heavy mazdoors : 2 Nos.
Light mazdoors : 9 Nos.
Laying concrete Mason Class-I : 2 Nos.
Heavy mazdoors : 2 Nos.
Washing / cleaning / curing etc Light mazdoors : 2 Nos.
75
8/13/2019 Data Rates-Dam Works-Part 4
17/21
DAM ALLIED WORKS
Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17
Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.
6. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.
7. Use rate of materials :
Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07
RATE ANALYSIS UNIT : 36.00 Rm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Cement with 1% wastage for mix kg 2900.00 4.00 11600.00
Cenent for incidentals @ 5 kg / cum kg 43.50 4.00 174.00
2 Coarse aggregate 20-10 mm cum 4.60 520.00 2392.00
Coarse aggregate 10-4.75 mm cum 2.50 669.00 1672.50
3 Fine aggregate ( screened ) cum 4.00 199.00 796.00
4 Super plasticiser ltr 8.90 75.00 667.50
5 Use rate of shuttering sqm 95.00 151.07 14351.20
6 Scaffolding @ 15 % of shuttering 2152.68
7 Sundries LS 2.00 30.00 60.00
Total Rs: 33865.88Add for small Tools and Plants @ 1% Rs: 338.66
Add for Contractor's Profit @ 10% Rs: 3386.59
Add for Contractor's Overheads @ 5% Rs: 1693.29
Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 39284.42
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 Needle vibrator 40 mm ( ele ) Hour 8.00 7.00 56.00
Fuel / Energy charges Hour 8.00 5.00 40.00
3 10 hp pump ( ele ) Hour 0.50 5.00 2.50
Fuel / Energy charges Hour 0.50 50.00 25.00
Total Rs: 627.50
Add for small Tools and Plants @ 1% Rs: 6.28
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 26.50
Add for Contractor's Overheads @ 5% Rs: 31.38
Total hire charges of Machinery : Rs: 691.65
C. LABOUR:Sl No Unit Amount
in Rs.
1 Crew for Concrete mixer Hour 8.00 75.10 600.80
2 Crew for Pump Hour 0.50 26.90 13.45
3 Crew for Vibrator Hour 8.00 53.30 426.40
4 Mason Class-I Day 2.00 159.00 318.00
5 Maistry Day 1.00 141.50 141.50
6 Heavy mazdoor
Description
Description
Perticulars
in Rs.
Quantity Rate
in Rs.
Quantity Rate
Quantity Rate
in Rs.
76
8/13/2019 Data Rates-Dam Works-Part 4
18/21
DAM ALLIED WORKS
for batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 6.00 132.00 792.00
for loading mortar pans Day 2.00 132.00 264.00
for laying & packing concrete Day 2.00 132.00 264.00
7 Light mazdoor
for conveying concrete Day 9.00 130.50 1174.50
for curing & miscellaneous Day 2.00 130.50 261.00
8 Labour for shuttering sqm 95.00 33.17 3150.68
9 Labour for scaffolding @ 15 % 472.60
Total Rs: 8146.93
Add for small Tools and Plants @ 1% Rs: 81.47
Add for Contractor's Profit @ 10% Rs: 814.69
Add for hidden cost on Labour @ 15% Rs: 1222.04
Add for additional hidden cost on labour @ 5% Rs: 407.35
Add for Contractor's Overheads @ 5% Rs: 407.35
Total cost of Labour : Rs: 11079.82
ABSTRACT:
A. Cost of Materials including royalty charges Rs: 39284.42
B. Hire charges of Machinery Rs: 691.65
C. Cost of Labour Rs: 11079.82TOTAL Rs: 51055.89
Add for enabling works @ 1.40% Rs: 714.78
Total Rs: 51770.67
Add for 1 km rehandling / initial lead including loading / unloading:
Cement 2943.5 kg @ Rs: 129.10 / tonne Rs: 380.01
Coarse aggregates 7.10 cum @ Rs: 121.90 / cum Rs: 865.49
Fine aggregate 4.00 cum @ Rs: 84.90 / cum Rs: 339.60
Total cost for 36.00 Rm Rs: 53016.17
Rate per Rm Rs: 1473.00
Rate approved per Rm Rs: 1473.00
SECTION: DAM AND ALLIED WORKS. YEAR : 2010-11 ITEM No: 22.b
ITEM: Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down sizeapproved, clean, hard, graded
aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
for RCC ornamental parapetconsisting of 350 x 200 mm kerb, 350 x 350 x 1000 mm pillars
spaced approximately at 3.5 m apart, 150 x 125 mm posts 600 mm height approximately 316
mm c/c with 125 mm thick and 350 mm wide coping slab for posts and pillars with top edges of
kerb and coping chamferred or rounded as directed etc., complete ( excluding cost of providing
and placing reinforcement steel and gate ) with initial lead upto 1 km and all lifts. ( Cementcontent : 330 kg / cum with use of super plasticiser )
DATA:Consider one spillway bridge span of 18 m.
Consider ornamental parapet for rate analysis for one span.
Consider 0.9 wide opening for approach to pier top hoist platform on d / s side.
0.35 m
Gate 3.00 m 0.125 m
77
8/13/2019 Data Rates-Dam Works-Part 4
19/21
DAM ALLIED WORKS
0.8 m
0.20 m
SKETCH SHOWING COMPONENTS OF RCC ORNAMENTAL PARAPET
Length of kerb on u / s and d / s ( 18.00 + 18.00 ) : 36.00 m
Length of parapet ( 18.00 + 18.00 - 0.90 ) : 35.10 m
Number of pillars for 3.35 m c / c spacing : 12 Nos
Number of wall panels of size 3.00 x 0.80 x 0.125 m : 10 Nos
Number of wall panels of size 0.45 x 0.80 x 0.125 m ( on u/s only ) : 2 Nos
Length of coping for wall panels ( 3 x 10 + 2 x 0.45 ) : 30.90 m
Number of coping slabs for pillers : 12 Nos
For 1 cum CC :- Coarse aggregates : 0.80 cum. Blending ratio : 65 :35
Fine aggregate : 0.45 cum. Cement : 330 kg Super plasticiser : 1.00 ltr Wastage : 1 % for cement and 2 % for coarse & fine aggregates.
1. Quantity of concrete per span :
For kerb ( 36 x 0.35 x 0.20 ) : 2.52 cum
For pillars ( 12 x 1 x 0.35 x 0.35 ) : 1.47 cum
For wall panels ( 10 x 3 x 0.80 x 0.125 + 2 x 0.45 x 0.80 x 0.125 ) : 3.09 cum
For wall coping ( 10 x 3 x 0.35 x 0.125 + 2 x 0.45 x 0.35 x 0.125 ) : 1.35 cum
For pillar coping ( 12 x 0.40 x 0.40 x 0.125 ) : 0.24 cum
Total : 8.70 cum
Less openings in wall panels ( 10x 9x 0.60x 0.166x 0.125) : 1.12 cum
Total ( say ) : 7.60 cum
Consider 300 / 200 ltr capacity mixer and 50 kg cement per mix for use of 20 mm down CA.
Equivalent volume batching using 0.3 x 0.3 x 0.3 m size boxes assumed for batching CA
Cycle time for batching / mixing / unloading 1 mix :
Batching 20-10 mm CA ( 0.079 cum ) : 3.00 min
Batching 10 mm below CA parellel activity : ---
Batching fine aggregate parellel activity : ---
Batching cement parellel activity : ---
Loading mixer drum & miscellaneous : 1.00 min
Mixing and unloading parellel activity : ---
Add for possible delays in any of the activity : 0.50 min
Cycle time for batching / mixing / unloading 1 mix : 4.50 minConstruction of parapet involves laying of concrete in three stages namely ( i ) kerb, ( ii ) pillars
and wall panels and ( iii ) coping. While concrete laying cycle can be matched with production
cycle for kerb and coping, the laying cycle will be very slow for pillars and wall panels in view of
thin sections with reinforcement. For ornamental parapet the laying cycle time will be more than
solid parapet in view of openings in wall panels. Considering the laying cycle time for pillars and
wall panels with openings 3 times the production cycle time the average cycle time will be about
1.8 times the production cycle time.
Average cycle time for laying concrete ( 4.50 x 1.8 ) : 8.10 min
78
8/13/2019 Data Rates-Dam Works-Part 4
20/21
DAM ALLIED WORKS
No. of mixes per day with 50 min / hr working ( 50 x 8 / 8.1 ) say : 50 mixes
Output of CC for 50 mixes ( 50 x 50 / 330 ) : 7.6 cum
As the computed daily output of 7.60 cum also matches with the one span parapet quantity of
7.60 cum consider the daily output at 7.60 cum for rate analysis.
2. Requirement of materials:
Cement for mix with 1 % wastage ( 7.6 x 330 x 1.01 ) : 2533 kg
Cement for incidental works @ 5 kg / cum ( 7.6 x 5 ) : 38 kg
Coarse aggregate 20-10 mm size range ( 7.6 x 0.8 x 0.65 x 1.02 ) : 4.05 cum
Coarse aggregate 10-4.75 mm size ( 7.6 x 0.8 x 0.35 x 1.02 ) : 2.20 cum
Fine aggregate ( 7.6 x 0.45 x 1.02 ) : 3.50 cum
Super plasticiser ( 7.6 x 1.0 x 1.02 ) : 7.75 ltrs
3. Requirement of machinery :
Deploy 300 / 200 ltr capacity concrete mixer for 8 hours for production of concrete.
Deploy 1 Needle vibrater 40 mm dia for 8 hours for vibrating concrete.
Deploy 1 Pump 10 hp for 1 hour for water required for concrete mixing / curing / cleaning etc.
4. Formwork & scaffolding :
Consider normal shuttering as concrete is laid in smaller lifts.
Shuttering for kerb x 18 x 0.20 + 4 x 0.35 x 0.20 ) : 14.68 sqm
For pillars (12x 2x 0.55x1 + 2x 0.15x1) : 13.50 sqm
For wall panels ( 10x2x3x0.80 + 2x2x0.45x0.80 + 2x0.15x0.80 ) : 49.68 sqm
For openings ( 10x 2x 2 x 9 x 0.125 x 0.6 ) : 20.00 sqmFor wall coping( 0.45 x 3 x 10 + 0.45 x 0.45 x 2 + 2 x 0.35 x 0.15 ) : 14.01 sqm
For pillar coping ( 12 x 4 x 0.35 x 0.15 ) : 2.52 sqm
Total ( say ) : 115.00 sqm
Scaffolding / supports assumed at 15 percent of cost of shuttering.
5. Requirement of workforce ( other than machinery crew ) :
Consider batching of materials and conveyance & laying of concrete by manual labour.
Batching 20-10 mm CA Heavy mazdoors : 2 Nos.
Batching 10 mm below CA Heavy mazdoors : 2 Nos.
Batching fine aggregate Heavy mazdoors : 2 Nos.
Batching cement Heavy mazdoors : 2 Nos.
Remixing and conveying concrete Heavy mazdoors : 2 Nos.
Light mazdoors : 8 Nos.
Laying concrete Mason Class-I : 2 Nos.
Heavy mazdoors : 2 Nos.
Washing / cleaning / curing etc Light mazdoors : 2 Nos.
Labour charges for normal shuttering / sqm ( Annexure-B Item :13 ) @ Rs: 33.17
Labour charges for erecting & dismantling scaffolding @ 15 % of cost labour for shuttering.
6. Rehandling / Initial lead for materials:
1 km rehandling lead for cement and 1 km initial lead for other materials considered.
7. Use rate of materials :
Use rate of normal shutter per sqm ( Annexure-A Item : 13 ) @ Rs: 151.07
RATE ANALYSIS UNIT : 36.00 Rm
A. MATERIALS:
Sl No Unit Amount
in Rs.
1 Cement with 1% wastage for mix kg 2533.00 4.00 10132.00
Cenent for incidentals @ 5 kg / cum kg 38.00 4.00 152.00
2 Coarse aggregate 20-10 mm cum 4.05 520.00 2106.00
Perticulars Quantity Rate
in Rs.
79
8/13/2019 Data Rates-Dam Works-Part 4
21/21
DAM ALLIED WORKS
Coarse aggregate 10-4.75 mm cum 2.20 669.00 1471.80
3 Fine aggregate ( screened ) cum 3.50 199.00 696.50
4 Super plasticiser ltr 7.75 75.00 581.25
5 Use rate of shuttering sqm 115.00 151.07 17372.50
6 Scaffolding @ 15 % of shuttering 2605.88
7 Sundries LS 2.50 30.00 75.00
Total Rs: 35192.93
Add for small Tools and Plants @ 1% Rs: 351.93
Add for Contractor's Profit @ 10% Rs: 3519.29
Add for Contractor's Overheads @ 5% Rs: 1759.65
Add royalty charges on CA @ ( Included in material rate ) Rs: 0.00
Add royalty charges on FA @ ( Included in material rate ) Rs: 0.00
Total cost of Materials : Rs: 40823.80
B. MACHINERY:
Sl No Unit Amount
in Rs.
1 Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 38.00 304.00
Fuel / Energy charges Hour 8.00 25.00 200.00
2 Needle vibrator 40 mm ( ele ) Hour 8.00 7.00 56.00
Fuel / Energy charges Hour 8.00 5.00 40.003 10 hp pump ( ele ) Hour 0.50 5.00 2.50
Fuel / Energy charges Hour 0.50 50.00 25.00
Total Rs: 627.50
Add for small Tools and Plants @ 1% Rs: 6.28
Add for Contractor's Profit on DPOL / Energy @ 10% Rs: 26.50
Add for Contractor's Overheads @ 5% Rs: 31.38
Total hire charges of Machinery : Rs: 691.65
C. LABOUR:
Sl No Unit Amount
in Rs.
1 Crew for Concrete mixer Hour 8.00 75.10 600.80
2 Crew for Pump Hour 0.50 26.90 13.45
3 Crew for Vibrator Hour 8.00 53.30 426.40
4 Mason Class-I Day 2.00 159.00 318.00
5 Maistry Day 1.00 141.50 141.50
Contd
C. LABOUR ( Contd ) :
Sl No Unit Amount
in Rs.
Contd
6 Heavy mazdoorfor batching cement ( cement handling ) Day 2.00 134.00 268.00
for batching other materials Day 6.00 132.00 792.00
for loading mortar pans Day 2.00 132.00 264.00
for laying & packing concrete Day 2.00 132.00 264.00
7 Light mazdoor
for conveying concrete Day 8.00 130.50 1044.00
for curing & miscellaneous Day 2.00 130.50 261.00
8 Labour for shuttering sqm 115.00 33.17 3813.98