Page 1: Data Center Best Practice and Architecture

Data CenterBest Practices and Architecture

for the California State University

Author(s): DCBPA Task ForceDate: OctAug 127, 2009Status: DRAFTVersion: 0.34.11

Page 2: Data Center Best Practice and Architecture

The content of this document is the result of the collaborative work of the Data Center Best Practice and Architecture (DCBPA) Task Force established under the Systems Technology Alliance committee within the California State University.

Team members who directly contributed to the content of this document are listed below.

Samuel G. Scalise, Sonoma, Chair of the STA and the DCBPA Task Force

Don Lopez, Sonoma

Jim Michael, Fresno

Wayne Veres, San Marcos

Mike Marcinkevicz, Fullerton

Richard Walls, San Luis Obispo

David Drivdahl, Pomona

Ramiro Diaz-Granados, San Bernardino

Don Baker, San Jose

Victor Vanleer, San Jose

Dustin Mollo, Sonoma

David Stein, PlanNet Consulting

Mark Berg, PlanNet Consulting

Michel Davidoff, Chancellor’s Office

2

Page 3: Data Center Best Practice and Architecture

Table of Contents

1. Introduction................................................................................................................................41.1. Purpose...............................................................................................................................41.2. Context................................................................................................................................41.3. Audience.............................................................................................................................51.4. Development Process.........................................................................................................51.5. Principles and Properties....................................................................................................5

2. Framework/Reference Model.....................................................................................................73. Best Practice Components.........................................................................................................15

3.1. Standards..........................................................................................................................153.2. Hardware Platforms..........................................................................................................153.3. Software............................................................................................................................173.4. Delivery Systems...............................................................................................................183.5. Disaster Recovery.............................................................................................................233.6. Total Enterprise Virtualization..........................................................................................293.7. Management Disciplines..................................................................................................32

3

Page 4: Data Center Best Practice and Architecture

1. Introduction

1.1. Purpose

As society and institutions of higher education increasingly benefit from technology and collaboration, the importance of identifying mutually best practices and architecture makes this document vital to the behind-the-scenes infrastructure of the university. Key drivers behind the gathering and assimilation of this collection are:

Many campuses want to know what the others are doing so they can draw from a knowledge base of successful initiatives and lessons learned. Having a head start in thinking through operational practices and effective architectures--as well as narrowing vendor selection for hardware, software and services--creates efficiencies in time and cost.

Campuses are impacted financially and data center capital and operating expenses need to be curbed. For many, current growth trends are unsustainable with limited square footage to address the demand for more servers and storage without implementing new technologies to virtualize and consolidate.

Efficiencies in power and cooling need to be achieved in order to address green initiatives and reduction in carbon footprint. They are also expected to translate into real cost savings in an energy-conscious economy. Environmentally sound practices are increasingly the mandate and could result in measurable controls on higher energy consumers.

Creating uniformity across the federation of campuses allows for consolidation of certain systems, reciprocal agreements between campuses to serve as tertiary backup locations, and opt-in subscription to services hosted at campuses with capacity to support other campuses, such as the C-cubed initiative.

1.2. Context

This document is a collection of Best Practices and Architecture for California State University Data Centers. It identifies practices and architecture associated with the provision and operation of mission-critical production-quality servers in a multi-campus university environment. The scope focuses on the physical hardware of servers, their operating systems, essential related applications (such as virtualization, backup systems and log monitoring tools), the physical environment required to maintain these systems, and the operational practices required to meet the needs of the faculty, students, and staff. Data centers that adopt these practices and architecture should be able to house any end-user service – from Learning Management Systems, to calendaring tools, to file-sharing.

This work represents the collective experience and knowledge of data center experts from the 23 campuses and the chancellor’s office of the California State University system. It is coordinated by the Systems Technology Alliance, whose charge is to advise the Information Technology Advisory Committee

4

mberg, 08/12/09,
Reference other ITAC initiatives, as appropriate
Page 5: Data Center Best Practice and Architecture

(made up of campus Chief Information Officers and key Chancellor’s Office personnel) on matters relating to servers (i.e., computers which provide a service for other computers connected via a network) and server applications.

This is a dynamic, living document that can be used to guide planning to enable collaborative systems, funding, procurement, and interoperability among the campuses and with vendors.

This document does not prescribe services used by end-users, such as Learning Management Systems nor Document Management Systems. As those services and applications are identified by end-users such as faculty and administrators, this document will describe the data center best practices and architecture needed to support such applications.

Campuses are not required to adopt the practices and architecture elucidated in this document. There may be extenuating circumstances that require alternative architectures and practices. However, it is hoped that these alternatives are documented in this process.

It is not the goal to describe a single solution, but rather the range of best solutions that meet the diverse needs of diverse campuses.

1.3. Audience

This information is intended to be reviewed by key stakeholders who have material knowledge of data center facilities and service offerings from business, technical, operational, and financial perspectives.

1.4. Development Process

The process for creating and updating these best Practices and Architecture (P&A) is to identify the most relevant P&A, inventory existing CSU P&A for key aspects of data center operations, identify current industry trends, and document those P&A which best meet the needs of the CSU. This will include information about related training and costs, so that campuses can adopt these P&A with a full understanding of the costs and required expertise.

The work of creating this document will be conducted by members of the Systems Technology Alliance appointed by the campus Chief Information Officers, by members of the Chancellors Office Technology Infrastructure Services group, and by contracted vendors.

1.5. Principles and Properties

In deciding which Practices and Architecture should be adopted, it is important to have a set of criteria that reflect the unique needs, values, and goals of the organization. These Principles and Properties include:

Cost-effectiveness

5

Page 6: Data Center Best Practice and Architecture

Long-term viability Flexibility to support a range of services Security of the systems and data Reliable and dependable uptime Environmental compatibility Redundancy High availability Performance Training Communication

Additionally, the architecture should emphasize criteria that are standards-based. The CSU will implement standards-based solutions in preference to proprietary solutions where this does not compromise the functional implementation.

The CSU seeks to adhere to standard ITIL practices and workflows where practical. Systems and solutions described herein should relate to corresponding ITIL and service management principles.

6

Page 7: Data Center Best Practice and Architecture

2. Framework/Reference Model

The framework is used to describe the components and management processes that lead to a holistic data center design. Data centers are as much about the services offered as they are the equipment and space contained in them. Taken together, these elements should constitute a reference model for a specific CSU campus implementation.

2.1. Standards2.1.1. ITIL

The Information Technology Infrastructure Library is a set of concepts around managing services and operations. The model was developed by the UK Office of Government Commerce and has been refined and adopted internationally. The ITIL version 2 framework for Service Support breaks out several management disciplines that are incorporated in this CSU reference architecture (see Section 2.7).

ITIL version 3 has reworked the framework into a collection of five volumes that describe

Service Strategy Service Design Service Transition Service Operation Continual Service Improvement

2.1.2. ASHRAE

The American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) releases updated standards and guidelines for industry consideration in building design. They include recommended and allowable environment envelopes, such as temperature, relative humidity, and altitude for spaces housing datacomm equipment. The purpose of the recommended envelope is to give guidance to data center operators on maintaining high reliability and also operating their data centers in the most energy efficient manner.

2.1.3. Uptime Institute

The Uptime Institute addresses architectural, security, electrical, mechanical, and telecommunications design considerations. See Section 2.4.1.1 for specific information on tiering standards as applied to data centers.

2.1.4. ISO/IEC 20000

An effective resource to draw upon as part of one of the ISO IT management standards are the ISO 20000-1 and ISO 20000-2 processes. ISO 20000-1 promotes the adoption of

7

mberg, 08/12/09,
This section (Reference Model) is meant to define terms, show the high-level relationships, reflect a baseline architecture, and reference external documents from other initiatives and reference architectures.This same outline is developed in Section 3 (Components) where each topic is given a more thorough “deep dive” treatment; including best practices.
Page 8: Data Center Best Practice and Architecture

an integrated process approach to effectively deliver managed services to meet the business and customer requirements. It comprises ten sections: Scope; Terms & Definitions; Planning and Implementing Service Management; Requirements for a Management System; Planning & Implementing New or Changed Services; Service Delivery Process; Relationship Processes; Control Processes; Resolution Processes; and Release Process. ISO 20000-2 is a 'code of practice', and describes the best practices for service management within the scope of ISO20000-1. It comprises nine sections: Scope; Terms & Definitions; The Management System; Planning & Implementing Service Management; Service Delivery Processes; Relationship Processes; Resolution Processes; Control Processes; Release Management Processes.

Together, this set of ISO standards is the first global standard for IT service management, and is fully compatible and supportive of the ITIL framework.

2.2. Hardware Platforms2.2.1. Servers

Types

Rack-mounted Servers – provide the foundation for any data center’s compute infrastructure. The most common are 1U and 2U: these form factors compose what is known as the volume market. The high-end market, geared towards high-performance computing (HPC) or applications that need more input/output (I/O) and /or storage is composed of 4U to 6U rack-mounted servers. The primary distinction between volume market and high-end servers is the I/O and storage capabilities.

Blade Servers –are defined by the removal of many components – PSUs, network interface cards (NICS) and storage adapters from the server itself. These components are grouped together as part of the blade chassis and shared by all the blades. The chassis is the piece of equipment that all of the blade servers “plug” into. The blade servers themselves contain processors, memory and a hard drive or two. One of the primary caveats to selecting the blade server option is the potential for future blade/chassis compatibility. Most IHVs do not guarantee blade/chassis beyond two generations or five years. Another potential caveat is the high initial investment in blade technology because of additional costs associated with the chassis.

Towers – There are two primary reasons for using tower servers…price and remote locations. Towers offer the least expensive entrance into the server platform market. Towers have the ability to be placed outside the confines of a data center. This feature can be useful for locating an additional Domain Name Server (DSN) or backup server in a remote office for redundancy purposes.

8

Page 9: Data Center Best Practice and Architecture

Principles

1. Application requirements – Applications such as databases, backup servers and other high I/O requirements are better suited HPC rack-mounted servers. Applications such as web servers and MTAs work well in a volume-market rack-mounted environment or even in a virtual server environment. These applications allow servers to be easily added and removed to meet spikes in capacity demand. The need to have servers that are physically located at different sites for redundancy or ease of administration can be met by tower servers, especially if they are low demand applications. Applications with high I/O requirements perform better with 1U or 2U rack-mounted servers rather than blade servers because stand alone servers have a dedicated I/O interface rather than a common one found on the chassis of a blade server.

2. Software support – can determine the platform an application lives on. Some vendors refuse to support virtual servers making VMs unsuitable if support is a key requirement. Multiple instances of an application is not supported by some software, requiring the application to run on a large single server rather than multiple smaller servers.

3. Storage – requirements can vary from a few gigabytes to accommodate the operating system, application and state data for application servers to terabytes to support large database servers. Applications requiring large amounts of storage should be SAN attached using fiber channel or iSCSI. Fiber offers greater reliability and performance but a higher skill lever from SAN Admins. Support for faster speeds in iSCSI is and improved reliability is making it more attractive. Direct Attached Storage (DAS) is still prevalent because it is less costly and easier to manage than SAN storage. Rack-mounted 4U to 6U servers have the space to house a large number of disk drives and make suitable DAS servers.

4. Consolidation – projects can result in several applications being combined onto a single server or virtualization. Care must be taken when combining applications to ensure they are compatible with each other and vendor support can be maintained. Virtualization accomplishes consolidation by allowing each application think it’s running on its own server. The benefits of consolidation include reduced power and space requirements and fewer servers to manage.

5. Energy efficiency – starts with proper cooling design, server utilization management and power management. Replacing old servers with newer energy efficient ones reduces energy use and cooling requirements and may be eligible for rebates which allow them to pay for themselves.

6. Improved management – Many data centers contain “best of breed” technology. They contain server platforms and other devices from many

9

Page 10: Data Center Best Practice and Architecture

different vendors. Servers may be from vendor A, storage from vendor B and network from vendor C. This complicates troubleshooting and leads to finger pointing. Reducing the number of vendors produces standardization and is more likely to allow a single management interface for all platforms.

7. Business growth/New services – As student enrollment grows and the number of services to support them increases, the data center’s capacity to run its applications and store its data increases. This is the most common reason for buying new server platforms. IT administrators must use a variety of gauges to anticipate this need and respond in time.

2.2.1.1. Server VirtualizationPrinciples

1. Reliability and availability—An implementation of server virtualization should provide increased reliability of servers and services by providing for server failover in the event of a hardware loss of service as well as high-availability by ensuring that access to shared services like network and disk are fault-tolerant and balanced by load.

2. Reuse—Server virtualization should allow better utilization of hardware and resources by provisioning multiple services and operating environments on the same hardware. Care must be taken to ensure that hardware is operating within limits of its capacity. Effective capacity planning becomes especially important.

3. Consumability—Server virtualization should allow us to provide quickly available server instances, using technologies such as cloning and templating when appropriate.

4. Agility—Server virtualization should allow us to improve organizational efficiency by provisioning servers and services faster by allowing for rapid deployment of instances using cloning and templates.

5. Administration—Server virtualization will improve administration by having a single, secure, easy-to-access interface to all virtual servers.

2.2.2. Storage2.2.2.1. SAN – Storage Area Network

2.2.2.1.1. Fiber Channel2.2.2.1.2. iSCSI

1. Benefits1.1. Reduced costs: By leveraging existing network components

(network interface cards [NICs], switches, etc.) as a storage fabric, iSCSI increases the return on investment (ROI) made for data center network communications and potentially saves

10

Page 11: Data Center Best Practice and Architecture

capital investments required to create a separate storage network. For example, iSCSI host bus adapters (HBAs) are 30-40% less expensive than Fibre Channel HBAs. Also, in some cases, 1 Gigabit Ethernet (GbE) switches are 50% less than comparable Fibre Channel switches.

Organizations employ qualified network administrator(s) or trained personnel to manage network operations. Being a network protocol, iSCSI leverages existing network administration knowledge bases, obviating the need for additional staff and educational training to manage a different storage network.

1.2. Improved options for DR: One of iSCSI's greatest strengths is its ability to travel long distances using IP wide area networks (WANs). Offsite data replication plays a key part in disaster recovery plans by preserving company data at a co-location that is protected by distance from a disaster affecting the original data center. Using a SAN router (iSCSI to Fibre Channel gateway device) and a target array that supports standard storage protocols (like Fibre Channel), iSCSI can replicate data from a local target array to a remote iSCSI target array, eliminating the need for costly Fibre Channel SAN infrastructure at the remote site.

iSCSI-based tiered storage solutions such as backup-to-disk (B2D) and near-line storage have become popular disaster recovery options. Using iSCSI in conjunction with Serial Advanced Technology Attachment (SATA) disk farms, B2D applications inexpensively back up, restore, and search data at rapid speeds.

1.3. Boot from SAN: As operating system (OS) images migrate to network storage, boot from SAN (BfS) becomes a reality, allowing chameleon-like servers to change application personalities based on business needs, while removing ties to Fibre Channel HBAs previously required for SAN connectivity (would still require hardware initiator).

2. Components2.1. Initiators

11

Page 12: Data Center Best Practice and Architecture

2.1.1.Software Initiators: While software initiators offer cost-effective SAN connectivity, there are some issues to consider. The first is host resource consumption versus performance. An iSCSI initiator runs within the input/output (I/O) stack of the operating system, utilizing the host memory space and CPU for iSCSI protocol processing. By leveraging the host, an iSCSI initiator can outperform almost any hardware-based initiator. However, as more iSCSI packets are sent or received by the initiator, more memory and CPU bandwidth is consumed, leaving less for applications. Obviously, the amount of resource consumption is highly dependent on the host CPU, NIC, and initiator implementation, but resource consumption could be problematic in certain scenarios. Software iSCSI initiators can consume additional resource bandwidth that could be partitioned for supplemental virtual machines.

2.1.2.Hardware Initiators: iSCSI HBAs simplify boot-from-SAN (BfS). Because an iSCSI HBA is a combination NIC and initiator, it does not require assistance to boot from the SAN, unlike software initiator counterparts. By discovering a bootable target LUN during system power-on self test (POST), an iSCSI HBA can enable an OS to boot an iSCSI target like any DAS or Fibre Channel SAN-connected system. In terms of resource utilization, an iSCSI HBA offloads both TCP and iSCSI protocol processing, saving host CPU cycles and memory. In certain scenarios, like server virtualization, an iSCSI HBA may be the only choice where CPU processing power is consequential.

2.2. Targets2.2.1.Software Targets: Any standard server can be used as a

software target storage array but should be deployed as a stand-alone application. A software target can capitalize platform resources, leaving little room for additional applications.

2.2.2.Hardware Targets: Many of the iSCSI disk array platforms are built using the same storage platform as their Fibre Channel cousin. Thus, many iSCSI storage arrays are similar, if not identical, to Fibre Channel arrays in terms of reliability, scalability, performance, and management. Other than the controller interface, the remaining product features are almost identical.

12

Page 13: Data Center Best Practice and Architecture

2.3. Tape Libraries2.3.1.Tape libraries should be capable of being iSCSI target

devices, however broad adoption and support in this category hasn’t been seen and remains a territory served by native Fiber Channel connectivity.

2.4. Gateways and Routers2.4.1.iSCSI to Fibre Channel gateways and routers play a vital

role in two ways. First, these devices increase return on invested capital made in Fibre Channel SANs by extending connectivity to “Ethernet islands” where devices that were previously unable to reach the Fibre Channel SAN can tunnel through using a router or gateway. Secondly, iSCSI routers and gateways enable Fibre Channel to iSCSI migration. SAN migration is a gradual process. Replacing a large investment in Fibre Channel SANs at one time is not a cost reality. As IT administrators carefully migrate from one interconnect to another, iSCSI gateways and routers afford IT administrators the luxury of time and money. One note of caution: It's important to know the port speeds and amount of traffic passing through a gateway or router. These devices can become potential bottlenecks if too much traffic from one network is aggregated into another. For example, some router products offer eight 1 GbE ports and only two 4 Gb Fibre Channel ports. While total throughput is the same, careful attention must be made to ensure traffic is evenly distributed across ports.

Any x86 server can act as an iSCSI to Fibre Channel gateway. Using a Fibre Channel HBA and iSCSI target software, any x86 server can present LUNs from a Fibre Channel SAN as an iSCSI target. Once again, this is not a turnkey solution—especially for large SANs—and caution should be exercised to prevent performance bottlenecks. However, this configuration can be cost-effective for small environments and connectivity to a single Fibre Channel target or small SAN.

2.5. Internet Storage Name Service (iSNS)2.5.1.Voracious storage consumption, combined with lower-

cost SAN devices, has stimulated SAN growth beyond what administrators can manage without help. iSCSI exacerbates this problem by proliferating iSCSI initiators

13

Page 14: Data Center Best Practice and Architecture

and low-cost target devices throughout a boundless IP network. Thus, a discovery and configuration service, like iSNS is a must for large SAN configurations. Although other discovery services exist for iSCSI SANs, such as Service Location Protocol (SLP), iSNS is emerging as the most widely accepted solution.

3. Security4. Multi-path support

1.1.1.1.[2.2.2.2.] NAS – Network Attached Storage1.1.1.2.[2.2.2.3.] DAS – Direct Attached Storage1.1.1.3.[2.2.2.4.] Storage Virtualization

1.2.[2.3.] Software1.2.1.[2.3.1.] Operating Systems

An Operating System (commonly abbreviated to either OS or O/S) is an interface between hardware and user; an OS is responsible for the management and coordination of activities and the sharing of the resources of the computer. The operating system acts as a host for computing applications that are run on the machine. As a host, one of the purposes of an operating system is to handle the details of the operation of the hardware. This relieves application programs from having to manage these details and makes it easier to write applications.

1.2.2.[2.3.2.] MiddlewareMiddleware is computer software that connects software components or applications. The software consists of a set of services that allows multiple processes running on one or more machines to interact across a network. This technology evolved to provide for interoperability in support of the move to coherent distributed architectures, which are used most often to support and simplify complex, distributed applications. It includes web servers, application servers, and similar tools that support application development and delivery. Middleware is especially integral to modern information technology based on XML, SOAP, Web services, and service-oriented architecture.

1.2.2.1.[2.3.2.1.] Identity ManagementIdentity management or ID management is a broad administrative area that deals with identifying individuals in a system (such as a country, a network or an organization) and controlling the access to the resources in that system by placing restrictions on the established identities.

1.2.3.[2.3.3.] DatabasesA database is an integrated collection of logically related records or files which consolidates records previously stored in separate files into a common pool of data records that provides data for many applications. A database is a collection of information that is organized so that it can easily be accessed, managed, and updated. In one view, databases can be classified according to types of content: bibliographic, full-text, numeric, and images. The structure is achieved by organizing the data according to a database model. The model that is most commonly used today is the relational model. Other models such as the hierarchical model and the network model use a more explicit representation of relationships.

14

Page 15: Data Center Best Practice and Architecture

1.2.4.[2.3.4.] Core/Enabling Applications1.2.4.1.[2.3.4.1.] Email

Electronic mail, often abbreviated as email or e-mail, is a method of exchanging digital messages, designed primarily for human use. E-mail systems are based on a store-and-forward model in which e-mail computer server systems accept, forward, deliver and store messages on behalf of users, who only need to connect to the e-mail infrastructure, typically an e-mail server, with a network-enabled device (e.g., a personal computer) for the duration of message submission or retrieval.

1.2.4.1.1.[2.3.4.1.1.] Spam FilteringE-mail spam, also known as junk e-mail, is a subset of spam that involves nearly identical messages sent to numerous recipients by e-mail. Spam filtering comes with a large set of rules which are applied to determine whether an email is spam or not. Most rules are based on regular expressions that are matched against the body or header fields of the message, but Spam vendors also employ a number of other spam-fighting techniques including header and text analysis, Bayesian filtering, DNS blocklists, and collaborative filtering databases.

1.2.4.2.[2.3.4.2.] Web ServicesA Web Service (also Webservice) is defined by the W3C as "a software system designed to support interoperable machine-to-machine interaction over a network. It has an interface described in a machine-processable format (specifically WSDL). Other systems interact with the Web service in a manner prescribed by its description using SOAP-messages, typically conveyed using HTTP with an XML serialization in conjunction with other Web-related standards."

1.2.4.3.[2.3.4.3.] CalendaringiCalendar is a computer file format which allows internet users to send meeting requests and tasks to other internet users, via email, or sharing files with an .ics extension. Recipients of the iCalendar data file (with supporting software, such as an email client or calendar application) can respond to the sender easily or counter propose another meeting date/time. iCalendar is used and supported by a large number of products. iCalendar data is usually sent with traditional email.

1.2.4.4.[2.3.4.4.] DNSDomain Name Services enable the use of canonical names, (rather then IP addresses) in addressing network resources. To provide a highly available network, DNS servers should be placed in an Enabling Services Network Infrastructure Model (see section 12.7.5 ). DNS services must also be highly available.

1.2.4.5.[2.3.4.5.] DHCPDynamic Host Configuration Protocol is used to manage the allocation of IP addresses. To provide a highly available network, DHCP servers should be placed in an Enabling Services Network Infrastructure Model (see section 12.7.5). DHCP services must also be highly available.

1.2.4.6.[2.3.4.6.] Syslogsyslog is a standard for forwarding log messages in an IP network. The term "syslog" is often used for both the actual syslog protocol, as well as the application or library sending syslog messages. Syslog is essential to capturing system messages generated from network devices.  Devices provide a wide range of messages, including changes to device configurations, device errors, and hardware component failures.

1.2.4.7.[2.3.4.7.] Desktop VirtualizationDesktop virtualization (or Virtual Desktop Infrastructure) is a server-centric computing model that borrows from the traditional thin-client model but is designed to give system administrators and end-users the best of both worlds: the ability to host and centrally manage desktop virtual machines in the data center while giving end users a full PC

15

mberg, 08/12/09,
Remove NTA reference
mberg, 08/12/09,
Remove NTA reference
Page 16: Data Center Best Practice and Architecture

desktop experience. The user experience is intended to be identical to that of a standard PC, but from a thin client device or similar, from the same office or remotely.

1.2.4.8.[2.3.4.8.] Application VirtualizationApplication virtualization is an umbrella term that describes software technologies that improve portability, manageability and compatibility of applications by encapsulating them from the underlying operating system on which they are executed. A fully virtualized application is not installed in the traditional sense, although it is still executed as if it is. The application is fooled at runtime into believing that it is directly interfacing with the original operating system and all the resources managed by it, when in reality it is not. Application virtualization differs from operating system virtualization in that in the latter case, the whole operating system is virtualized rather than only specific applications.

1.2.5.[2.3.5.] Third Party Applications1.2.5.1.[2.3.5.1.] LMS

A learning management system (LMS) is software for delivering, tracking and managing training/education. LMSs range from systems for managing training and educational records to software for distributing courses over the Internet and offering features for online collaboration.

1.2.5.2.[2.3.5.2.] CMSThe mission of the Common Management Systems (CMS) is to provide efficient, effective and high quality service to the students, faculty and staff of the 23-campus California State University System (CSU) and the Office of the Chancellor.

Utilizing a best practices approach, CMS supports human resources, financials and student services administration functions with a common suite of Oracle Enterprise applications in a shared data center, with a supported data warehouse infrastructure.

1.2.5.3.[2.3.5.3.] Help Desk/TicketingHelp desks are now fundamental and key aspects of good business service and operation. Through the help desk, problems are reported, managed and then appropriately resolved in a timely manner. Help desks can provide users the ability to ask questions and receive effective answers. Moreover, help desks can help the organization run smoothly and improve the quality of the support it offers to the users.

Traditional - Help desks have been traditionally used as call centers. Telephone support was the main medium used until the advent of Internet.

Internet - The advent of the Internet has provided the opportunity for potential and existing customers to communicate with suppliers directly and to review and buy their services online. Customers can email their problems without being put on hold over the phone. One of the largest advantages Internet help desks have over call centers are that it is available 24/7.

1.3.[2.4.] Delivery Systems1.3.1.[2.4.1.] Facilities

1.3.1.1.[2.4.1.1.] Tiering Standards

The industry standard for measuring data center availability is the tiering metric developed by The Uptime Institute and addresses architectural, security, electrical, mechanical, and telecommunications design considerations. The higher the tier, the higher the availability. Tier descriptions include information like raised floor heights, watts per square foot, and points of failure. “Need,” or “N,” indicates the level of

16

mberg, 08/12/09,
Sonoma uses CMS as top-level system for other systems that feed info to and from, including data warehousing. APIs to cashiering, parking systems, for example. Also used for authenticating users.
mberg, 08/12/09,
Architecturally, there are some common interactions that need to be described; nightly feeds from CMS to LMS for student rosters, identity management systems, TurnItIn.com,
Page 17: Data Center Best Practice and Architecture

redundant components for each tier with N representing only the necessary system need. Construction cost per square foot is also provided and varies greatly from tier to tier with Tier 3 costs double that of Tier 1.

Tier 1 – Basic: 99.671% Availability

Susceptible to disruptions from both planned and unplanned activity Single path for power and cooling distribution, no redundant components (N) May or may not have a raised floor, UPS, or generator Typically takes 3 months to implement Annual downtime of 28.8 hours Must be shut down completely to perform preventative maintenance

Tier 2 – Redundant Components: 99.741% Availability

Less susceptible to disruption from both planned and unplanned activity Single path for power and cooling distribution, includes redundant components

(N+1) Includes raised floor, UPS, and generator Typically takes 3 to 6 months to implement Annual downtime of 22.0 hours Maintenance of power path and other parts of the infrastructure require a

processing shutdown

Tier 3 – Concurrently Maintainable: 99.982% Availability

Enables planned activity without disrupting computer hardware operation, but unplanned events will still cause disruption

Multiple power and cooling distribution paths but with only one path active, includes redundant components (N+1)

Includes raised floor and sufficient capacity and distribution to carry load on one path while performing maintenance on the other

Typically takes 15 to 20 months to implement Annual downtime of 1.6 hours

Tier 4 – Fault Tolerant: 99.995% Availability

Planned activity does not disrupt critical load and data center can sustain at least one worst-case unplanned event with no critical load impact

Multiple active power and cooling distribution paths, includes redundant components (2 (N+1), i.e. 2 UPS each with N+1 redundancy)

Typically takes 15 to 20 months to implement Annual downtime of 0.4 hours

17

Page 18: Data Center Best Practice and Architecture

Trying to achieve availability above Tier 4 presents a level of complexity that some believe presents diminishing returns. EYP, which manages HP’s data center design practice, says their empirical data shows no additional uptime from the considerable cost of trying to further reduce downtime from 0.4 hours due to the human element that gets introduced in managing the complexities of the many redundant systems.

1.3.1.2.[2.4.1.2.] Spatial Guidelines and Capacities

1. Locale: A primary consideration in data center design is understanding the importance of location. In addition to the obvious criteria of adjacency to business operations and technical support resources, consideration for cost factors such as utilities, networking and real estate are prime. Exposure to natural disaster is also a key component. Power is generally the largest cost factor over time, which has prompted organizations to increasingly consider remote data centers in low utility cost areas. Addressing remote control operations and network latency become essential considerations.

2. Zoned space: Data centers should be block designed with specific tiering levels in mind so that sections of the space can be operated at high density with supporting infrastructure while other sections can be supported with minimal infrastructure. Each zone should have capacity for future growth within that tier.

3. Raised floor: A typical design approach for data centers is to use raised floor for air flow management and cable conveyance. Consideration must be given for air flow volume, which dictates the height of the floor, as well as weight loading. Raised floor structures must also be grounded.

4. Rack rows and density: Equipment racks and cabinets should be arranged in rows that provide for logical grouping of equipment types, ease of distribution for power and network, and provide for air flow management, either through perforated floor tiles or direct ducting.

1.3.1.3.[2.4.1.3.] Electrical Systems

Generators: Can be natural gas or petroleum/diesel fuel type. For higher tier designs, are deployed in an N+1 configuration to account for load.

UPS: Can be rack-based or large room-based systems. Must be configured for load and runtime considerations. Asset management systems should track the lifecycle of batteries for proactive service and replacement.

PDUs: Power distribution units provide receptacles from circuits on the data center power system, usually from the UPS. Intelligent PDUs are able to provide management systems information about power consumption at the rack or even device level. Some PDUs are able to be remotely managed to allow for power cycling of equipment at the receptacle level, which aids in remote operation of servers where a power cycle is required to reboot a hung system.

18

Page 19: Data Center Best Practice and Architecture

Dual A-B cording: In-rack PDUs should make multiple circuits available so that redundant power supplies (designated A and B) for devices can be corded to separate circuits. Some A-B cording strategies call for both circuits to be on UPS while others call for one power supply to be on house power while the other is on UPS. Each is a function of resilience and availability.

1.3.1.4.[2.4.1.4.] HVAC Systems

CRAC units: Computer Room Air Conditioners are specifically designed to provide cooling with humidification for data centers. They are typically tied to power systems that can maintain cooling independent of the power distribution to the rest of the building.

Hot/Cold Aisle Containment: Arranging equipment racks in rows that allow for the supply of cold air to the front of racks and exhaust of hot air at the rear. Adjacent rows would have opposite airflow to provide only one set of supply or exhaust ducts. Some very dense rack configurations may require the use of chimney exhaust above the racks to channel hot air away from the cold air supply. The key design component is to not allow hot air exhaust to mix with cold air supply and diminish its overall effectiveness. Containment is achieved through enclosed cabinet panels, end of row wall or panel structures, or plastic sheet curtains.

Economizers: Directs ambient outside air in cooler climates to supplement cooling to the data center.

1.3.1.5.[2.4.1.5.] Fire Protection & Life Safety

Fire suppression systems are essential for providing life safety protection for occupants of a data center and to protecting the equipment. Design of systems should give priority to human life over equipment, which factors in the decision of certain gas suppression systems.

Pre-action: Describes a water sprinkler design that allows for the water pipes serving sprinkler heads within a data center to be free from water until such point that a triggering mechanism allows water to enter the pipes. This is meant to mitigate damage from incidental leakage or spraying water from ruptured water lines normally under pressure.

VESDA: Very Early Smoke Detection Apparatus allows for pre-action or gas suppression systems to have a human interrupt and intervention at initial thresholds before ultimately triggering on higher thresholds. The system operates by using lasers to evaluate continuous air samples for very low levels of smoke.

19

Page 20: Data Center Best Practice and Architecture

Halon: Oxygen displacing gas suppression system that is generally no longer used in current data center design due to risk to personnel in the occupied space.

FM-200: Gas suppression system that quickly rushes the FM-200 gas to the confined data center space that must be kept air tight for effectiveness. It is a popular replacement for halon gas since it can be implemented without having to replace deployment infrastructure. A purge system is usually required to exhaust and contain the gas after deployment so it does not enter the atmosphere.

Novec1230: Gas suppression system that is stored as a liquid at room temperature and allows for more efficient use of space over inert gas systems. Also a popular halon gas alternative.

Inergen: A gas suppression system that does not require a purge system or air tight facility since it is non-toxic and can enter the atmosphere without environmental concerns. Requires larger footprint for more tanks and is a more expensive gas to use and replace.

1.3.1.6.[2.4.1.6.] Access Control

Part of a good physical security plan includes access controls which allow you to determine who has access to your Data Center and when. Metal keys can provide a high level of security, but they do not provide an audit trail, and don't allow you to limit access based on times and/or days. Intrusion systems (aka, alarm systems) can sometimes allow for this kind of control in a facility where it is not possible to migrate to an electronic lock system.

Most new Data Centers constructed today include some sort electronic locking system. These can take the form of simple, offline keypad locks, to highly complex systems that include access portals (aka, man traps) and anti-tailgating systems. Electronic lock systems allow the flexability to issue and revoke access instantaneously, or nearly so, depending on the product. Online systems (sometimes refered to as hardwired systems) consist of an access control panel that connects to a set of doors and readers of various types using wiring run through the building. Offline systems consist of locks that have a reader integrated into the lock, a battery and all of the electronics to make access determinations. Updates to these sorts of locks are usually done through some sort of hand-held device that is plugged into the lock.

There are two fairly common reader technologies in use today. One is magnetic stripe based. These systems usually read data encoded on tracks two or three. While the technology is mature and stable, it has a few weaknesses. The data on the cards can be easily duplicated with equipment easily purchased on the Internet. The magnetic stripe can wear out or become erased if it gets close to a magnetic field. One option to improving the security of magnetic swipe installations is the use of a dual-validation

20

Page 21: Data Center Best Practice and Architecture

reader, where after swiping your card, the user must enter a PIN code before the lock will open.

The other common access token in use today is the proximity card, also called a RFID card. These cards have an integrated circuit (IC), capacitor and wire coil inside of them. When the coil is placed near a reader, the energy field emitted by the reader produces a charge in the capacitor, which powers the IC. Once powered, the IC transmits it's information to the reader and the reader or control panel that it communicates with, determines if you should gain access.

Beyond access control, the other big advantage to electronic locking systems is their ability to provide an audit trail. The system will keep track of all credentials presented to the reader, and the resulting outcome of that presentation - access was either granted or denied. Complex access control systems will even allow you to do things such as implement a two-man rule, where two people must present authorized credentials before a lock will open, or anti-passback.

Anti-passback systems require a user to present credentials to both enter or exit a given space. Obviously, locking someone into a room would be a life safety issue, so usually, some sort of alarm is sounded on egress if proper credentials were not presented. Anti-passback also allows you to track where individuals are at any given time, because the system knows that they presented credentials to exit a space.

1.3.1.7.[2.4.1.7.] Commissioning

Commissioning is essential to have validation of the design, verification of load capacities, and testing of failover mechanisms. A commissioning agent can identify design flaws, single-points of failure, and inconsistencies in the build-out from the original design. Normally a commissioning agent would be independent from the design or build team.

A commissioning agent will inspect for such things as proper wiring, pipe sizes, weight loads, chiller and pump capacities, electrical distribution panels and switch gear. They will test battery run times, UPS and generator step loads, and air conditioning. They will simulate load with resistive coils to generate heat and UPS draw and go through a play-book of what-if scenarios to test all aspects of redundant systems.

1.3.2.[2.4.2.] Load Balancing/High Availability1.3.3.[2.4.3.] Connectivity

1.3.3.1.[2.4.3.1.] Network

Network components in the data center—such as Layer 3 backbone switches, WAN edge routers, perimeter firewalls, and wireless access points—are described in the ITRP2 Network Baseline Standard Architecture and Design document, developed by the

21

Page 22: Data Center Best Practice and Architecture

Network Technology Alliance, sister committee to the Systems Technology Alliance. Latest versions of the standard can be located at http://nta.calstate.edu/ITRP2.shtml.

Increasingly, boundaries are blurring between systems and networks. Virtualization is causing an abstraction of traditional networking components and moving them into software and the hypervisor layer. Virtual switches

Considerations beyond “common services”

The following components have elements of network enabling services but are also systems-oriented and may be managed by the systems or applications groups.

1. DNS

For privacy and security reasons, many large enterprises choose to make only a limited subset of their systems “visible” to external parties on the public Internet. This can be accomplished by creating a separate Domain Name System (DNS) server with entries for these systems, and locating it where it can be readily accessible by any external user on the Internet (e.g., locating it in a DMZ LAN behind external firewalls to the public Internet). Other DNS servers containing records for internally accessible enterprise resources may be provided as “infrastructure servers” hidden behind additional firewalls in “trusted” zones in the data center. This division of responsibility permits the DNS server with records for externally visible enterprise systems to be exposed to the public Internet, while reducing the security exposure of DNS servers containing the records of internal enterprise systems.

2. E-Mail (MTA only)

For security reasons, large enterprises may choose to distribute e-mail functionality across different types of e-mail servers. A message transfer agent (MTA) server that only forwards Simple Mail Transfer Protocol (SMTP) traffic (i.e., no mailboxes are contained within it) can be located where it is readily accessible to other enterprise e-mail servers on the Internet. For example, it can be located in a DMZ LAN behind external firewalls to the public Internet). Other e-mail servers containing user agent (UA) mailboxes for enterprise users may be provided as “infrastructure servers” located behind additional firewalls in “trusted” zones in the data center. This division of responsibility permits the “external” MTA server to communicate with any other e-mail server on the public Internet, but reduces the security exposure of “internal” UA e-mail servers.

3. Voice Media Gateway

22

mberg, 08/12/09,
Standards for these services should be developed collaboratively with the NTA.
Page 23: Data Center Best Practice and Architecture

The data center site media gateway will include analog or digital voice ports for access to the local PSTN, possibly including integrated services digital network (ISDN) ports.

With Ethernet IP phones, the VoIP gateway is used for data center site phone users to gain local dial access to the PSTN. The VoIP media gateway converts voice calls between packetized IP voice traffic on a data center site network and local circuit-switched telephone service. With this configuration, the VoIP media gateway operates under the control of a call control server located at the data center site, or out in the ISP public network as part of an “IP Centrex” or “virtual PBX” service. However, network operators/carriers increasingly are providing a SIP trunking interface between their IP networks and the PSTN; this will permit enterprises to send VoIP calls across IP WANs to communicate with PSTN devices without the need for a voice media gateway or direct PSTN interface. Instead, data center site voice calls can be routed through the site’s WAN edge IP routers and data network access links.

4. Ethernet L2 Virtual Switch

In a virtual server environment, the hypervisor manages L2 connections from virtual hosts to the NIC(s) of the physical server.

A hypervisor plug-in module may be available to allow the switching characteristics to emulate a specific type of L2 switch so that it can be managed apart from the hypervisor and incorporated into the enterprise NMS.

5. Top-of-Rack Fabric Switches

As a method of consolidating and aggregating connections from dense rack configurations in the data center, top-of-rack switching has emerged as a way to provide both Ethernet and Fiber Channel connectivity in one platform. Generally, these devices connect to end-of-row switches that, optimally, can manage all downstream devices as one switching fabric. The benefits are a modularized approach to server and storage networks, reduced cross connects and better cable management.

1.3.3.1.1.[2.4.3.1.1.] Network Virtualization

1.3.3.1.2.[2.4.3.1.2.] Structured Cabling

23

mberg, 08/12/09,
Added as a result of the announcement of the virtual switch at our Cisco briefing.
Page 24: Data Center Best Practice and Architecture

The CSU has developed a set of standards for infrastructure planning that should serve as a starting place for designing cabling systems and other utilities serving the data center. These Telecommunications Infrastructure Planning (TIP) standards can be referenced at the following link: http://www.calstate.edu/cpdc/ae/gsf/TIP_Guidelines/

There is also a NTA working group specific to networking that regards cabling infrastructure, known as the Infrastructure Physical Plant Working Group (IPPWG). Information about the working group can be found at the following link: http://nta.calstate.edu/NTA_working_groups/IPP/

The approach to structured cabling in a data center differs from other aspects of building wiring due to the following issues:

Managing higher densities, particularly fiber optics Cable management, especially with regard to moves, adds and changes Heat control, for which cable management plays a role

The following are components of structured cabling design in the data center:

1. Cable types: Cabling may be copper (shielded or unshielded) or fiber optic (single mode or multi mode).

2. Cabling pathways: usually a combination of raised floor access and overhead cable tray. Cables under raised floor should be in channels that protect them from adjacent systems, such as power and fire suppression.

3. Fiber ducts: fiber optic cabling has specific stress and bend radius requirements to protect the transmission of light and duct systems designed for fiber takes into account the proper routing and storage of strands, pigtails and patchcords among the distribution frames and splice cabinets.

4. Fiber connector types: usually MT-RJ, LC, SC or ST. The use of modular fiber “cassettes” and trunk cables allows for higher densities and the benefit of factory terminations rather than terminations in the field, which can be time-consuming and subject to higher dB loss.

5. Cable management:

2.4.4 Operations

Information Technology (IT) operations refers to the day-to-day management of an IT infrastructure. An IT operation incorporates all the work required to keep a system running smoothly. This process typically includes the introduction and control of small changes to the system, such as mailbox moves and hardware upgrades, but it does not affect the overall system design. Operational support includes systems monitoring, network monitoring, problem determination, problem reporting, problem escalation, operating system upgrades, change control, version

24

mberg, 08/12/09,
Finish this section
Page 25: Data Center Best Practice and Architecture

management, backup and recovery, capacity planning, performance tuning and system programming.

The mission of data center operations is to provide the highest possible quality of central computing support for the campus community and to maximize availability central computing systems.

Data center operations services include:

Help Desk Support Network Management Data Center Management Server Management Application Management Database Administration Web Infrastructure Management Systems Integration Business Continuity Planning Disaster Recovery Planning Email Administration

2.4.4.1 Staffing

Staffing is the process of acquiring, deploying, and retaining a workforce of sufficient quantity and quality maximize the organizational effectiveness of the data center.

2.4.4.2 Training

Training is not simply a support function, but a strategic element in achieving an organization’s objectives.

IT Training Management Processes and Sample Practices

Management Processes Sample Practices

Align IT training with business goals. Enlist executive-level champions.

Involve critical stakeholders.

Identify and assess IT training needs. Document competencies/skills

25

mberg, 08/12/09,
Include references to benchmarks and classifications
Page 26: Data Center Best Practice and Architecture

required for each job description.

Perform a gap analysis to determine needed training.

Allocate IT training resources. Use an investment process to select and manage training projects.

Provide resources for management training, e.g., leadership and project management.

Design and deliver IT training. Give trainees choice among different training delivery methods.

Build courses using reusable components.

Evaluate/demonstrate the value of IT training.

Collect information on how job performance is affected by training.

Assess evaluation results in terms of business impact

2.4.4.3 Monitoring

Monitoring is a critical element of data center asset management and covers a wide spectrum of issues such as system availability, system performance levels, component serviceability and timely detection of system operational or security problems such as disk capacity exceeding defined thresholds or system binary files being modified, etc.

2.4.4.4 Automation

Automation of routine data center tasks reduces staffing headcount by using tools such as automated tape backup systems that auto load magnetic media from tape libraries sending backup status and exception reports to data center staff. The potential for automating routine tasks is limitless. Automation increases reliability and frees staff from routine tasks so that continuous improvement of operations can occur.

2.4.4.5 Console Management

26

mberg, 08/12/09,
Other examples of automation can involve provisioning of VMs and storage
mberg, 08/12/09,
Provide some examples of systems that can be monitored.In best practice section , drop in sample graphs of info from systems such as Nagios or HP OpenView, Big BrotherIn a discussion of monitoring, also make mention of the actions that follow from monitoring, whether prescriptive escalations or automation or distributed notifications, etc.
Page 27: Data Center Best Practice and Architecture

To the extent possible console management should integrate the management of heterogeneous systems using orchestration or a common management console.

2.4.4.6 Remote Operations

Lights out operations are facilitated by effective remote operations tools. This leverages the economy of scales enjoyed by managing multiple remote production data centers from a single location that may be dynamically assigned in manner such as “follow the sun.”

1.3.4.[2.4.5.] Accounting1.3.4.1.[2.4.5.1.] Auditing

The CSU publishes findings and campus responses to information security audits. Reports can be found at the following site: http://www.calstate.edu/audit/audit_reports/information_security/index.shtml

1.4.[2.5.] Disaster Recovery1.4.1.[2.5.1.] Relationship to overall campus strategy for Business Continuity

Campuses should already have a business continuity plan, which typically includes a business impact analysis (BIA) to monetize the effects of interrupted processes and system outages. Deducing a maximum allowable downtime through this exercise will inform service and operational level agreements, as well as establish recovery time and point objectives, discussed in section 2.7.4.1 Backup and Recovery.

1.4.2.[2.5.2.] Relationship to CSU Remote Backup – DR initiative

ITAC has sponsored an initiative to explore business continuity and disaster recovery partnerships between CSU campuses. [Charter document?] Several campuses have teamed to develop documents and procedures and their workproduct is posted at http://drp.sharepointsite.net/itacdrp/default.aspx.

Examples of operational considerations, memorandums of understanding, and network diagrams are given in Section 3.5.4.2

1.4.3.[2.5.3.] Infrastructure considerations1.4.3.1.[2.5.3.1.] Site availability

Disaster recovery planning should account for short-, medium-, and long-term disaster and disruption scenarios, including impact and accessibility to the data center. Consideration should be given to location, size, capacity, and utilities necessary to recover the level of service required by the critical business functions. Attention should be given to structural, mechanical, electrical, plumbing and control systems and should also include planning for workspace, telephones, workstations, network connectivity, etc.

27

mberg, 08/12/09,
Architecturally, this usually involves dedicated NICs and IP address assignments, which has some implications for system management.
mberg, 08/12/09,
Should this section also mention anything about contention with remote access and IP-based KVMs?
Page 28: Data Center Best Practice and Architecture

Alternate sites could be geographically diverse locations on the same campus, locations on other campuses (perhaps as part of a reciprocal agreement between campuses to recover each other’s basic operations), or commercially available co-location facilities described in Section 2.5.3.2.

When determining an alternate site, management should consider scalability, in the event a long-term disaster becomes a reality. The plan should include logistical procedures for accessing backup data as well as moving personnel to the recovery location.

1.4.3.2.[2.5.3.2.] Co-location

One method of accomplishing business continuity objectives through redundancy with geographic diversity is to use a co-location scenario, either through a reciprocal agreement with another campus or a commercial provider. The following are typical types of collocation arrangements:

Real estate investment trusts (REITs): REITs offer leased shared data center facilities in a business model that leverages tax laws to offer savings to customers.

Network-neutral co-location: Network-neutral co-location providers offer leased rack space, power, and cooling with the added service of peer-to-peer network cross-connection.

Co-location within hosting center: Hosting centers may offer co-location as a basic service with the ability to upgrade to various levels of managed hosting.

Unmanaged hosted services: Hosting centers may offer a form of semi-co-location wherein the hosting provider owns and maintains the server hardware for the customer, but doesn't manage the operating system or applications/services that run on that hardware.

Principles for co-location selection criteria1. Business process includes or provides an e-commerce solution2. Business process does not contain applications and services that were

developed and are maintained in-house3. Business process does not predominantly include internal infrastructure or

support services that are not web-based4. Business process contain predominantly commodity and horizontal applications

and services (such as email and database systems)5. Business process requires geographically distant locations for disaster recovery

or business continuity6. Co-location facility meets level of reliability objective (Tier I, II, III, or IV) at less

cost than retrofitting or building new campus data centers7. Access to particular IT staff skills and bandwidth of the current IT staffers8. Level of SLA matches the campus requirements, including those for disaster

recovery9. Co-location provider can accommodate regulatory auditing and reporting for

the business process10. Current data center facilities have run out of space, power, or cooling

28

Page 29: Data Center Best Practice and Architecture

[concepts from Burton Group article, “Host, Co-Lo, or Do-It-Yourself?”]

1.4.4.[2.5.4.] Operational considerations1.4.4.1.[2.5.4.1.] Recovery Time Objectives and Recovery Point Objectives discussed in

2.7.4.1 (Backup and Recovery1.5.[2.6.] Total Enterprise Virtualization1.6.[2.7.] Management Disciplines

1.6.1.[2.7.1.] Service Management

IT service management is the integrated set of activities required to ensure the cost and quality of IT services valued by the customer. It is the management of customer-valued IT capabilities through effective processes, organization, information and technology, including:

Aligning IT with business objectives Managing IT services and solutions throughout their lifecycles Service management processes like those described in ITIL, ISO/IEC 20000,

or IBM’s Process Reference Model for IT.

1.6.1.1.[2.7.1.1.] Service Catalog

An IT Service Catalog defines the services that an IT organization is delivering to the business users and serves to align the business requirements with IT capabilities, communicate IT services to the business community, plan demand for these services, and orchestrate the delivery of these services across the functionally distributed (and, oftentimes, multi-sourced) IT organization. An effective Service Catalog also segments the customers who may access the catalog - whether end users or business unit executives - and provides different content based on function, roles, needs, locations, and entitlements.

The most important requirement for any Service Catalog is that it should be business-oriented, with services articulated in business terms. In following this principle, the Service Catalog can provide a vehicle for communicating and marketing IT services to both business decision-makers and end users.

The ITIL framework distinguishes between these groups as "customers" (the business executives who fund the IT budget) and "users" (the consumers of day-to-day IT service deliverables). The satisfaction of both customers and users is equally important, yet it's important to recognize that these are two very distinct and different audiences.

To be successful, the IT Service Catalog must be focused on addressing the unique requirements for each of these business segments. Depending on the audience, they will require a very different view into the Service Catalog. IT organizations should consider a two-pronged approach to creating an actionable Service Catalog:

The executive-level, service portfolio view of the Service Catalog used by business unit executives to understand how IT's portfolio of service offerings

29

mberg, 08/12/09,
From Jim Michael: Internal cloud computing would probably span aspects of almost all of this framework and external cloud computing could have a similar placement, but I expect that security, compliance and other issues might define the scope of appropriate use for external cloud computing.
Page 30: Data Center Best Practice and Architecture

map to business unit needs. This is referred to in this article as the "service portfolio."

The employee-centric, request-oriented view of the Service Catalog that is used by end users (and even other IT staff members) to browse for the services required and submit requests for IT services. For the purposes of this article, this view is referred to as a "service request catalog."

As described above, a Service Request Catalog should look like consumer catalogs, with easy-to-understand descriptions and an intuitive store-front interface for browsing available service offerings. This customer-focused approach helps ensure that the Service Request Catalog is adopted by end users. The Service Portfolio provides the basis for a balanced, business-level discussion on service quality and cost trade-offs with business decision-makers.

To that end, service catalogs should extend beyond a mere list of services offered and can be used to facilitate:

IT best practices, captured as Service Catalog templates Operational Level Agreements, Service Level Agreements (aligning internal

& external customer expectations) Hierarchical and modular service models Catalogs of supporting and underlying infrastructures and dependencies

(including direct links into the CMDB) Demand management and capacity planning Service request, configuration, validation, and approval processes Workflow-driven provisioning of services Key performance indicator (KPI)-based reporting and compliance auditing

1.6.1.2.[2.7.1.2.] Service Level Agreements

The existence of a quality service level agreement is of fundamental importance for any service or product delivery of any importance. It essentially defines the formal relationship between the supplier and the recipient, and is NOT an area for short-cutting. This is an area which too often is not given sufficient attention. This can lead to serious problems with the relationship, and indeed, serious issues with respect to the service itself and potentially the business itself.

It will embrace all key issues, and typically will define and/or cover: The services to be delivered Performance, Tracking and Reporting Mechanisms Problem Management Procedures Dispute Resolution Procedures The Recipient's Duties and Responsibilities Security Legislative Compliance Intellectual Property and Confidential Information Issues Agreement Termination

30

mberg, 08/12/09,
Should this be part of the Best Practice section that describes different and effective ways of presenting the information?
Page 31: Data Center Best Practice and Architecture

1.6.2.[2.7.2.] Project Management

An organization’s ability to effectively manage projects allows it to adapt to changes and succeed in activities such as system conversions, infrastructure upgrades and system maintenance. A project management system should employ well-defined and proven techniques for managing projects at all stages, including:

Initiation Planning Execution Control Close-out

Project monitoring will include:

Target completion dates – realistically set for each task or phase to improve project control.

Project status updates – measured against original targets to assess time and cost overruns.

Stakeholders and IT staff should collaborate on defining project requirements, budget, resources, critical success factors, and risk assessment, as well as a transition plan from the implementation team to the operational team.

1.6.3.[2.7.3.] Change Management

Change Management addresses routine maintenance and periodic modification of hardware, software and related documentation. It is a core component of a functional ITIL process as well. Functions associated with change management are:

1. Major modifications: significant functional changes to an existing system, or converting to or implementing a new system; usually involves detailed file mapping, rigorous testing, and training.

2. Routine modifications: changes to applications or operating systems to improve performance, correct problems or enhance security; usually not of the magnitude of major modifications and can be performed in the normal course of business.

3. Emergency modifications: periodically needed to correct software problems or restore operations quickly. Change procedures should be similar to routine modifications but include abbreviated change request, evaluation and approval procedures to allow for expedited action. Controls should be designed so that management completes detailed evaluation and documentation as soon as possible after implementation.

4. Patch management: similar to routine modifications, but relating to externally developed software.

31

Page 32: Data Center Best Practice and Architecture

5. Library controls: provide ways to manage the movement of programs and files between collections of information, typically segregated by the type of stored information, such as for development, test and production.

6. Utility controls: restricts the use of programs used for file maintenance, debugging, and management of storage and operating systems.

7. Documentation maintenance: identifies document authoring, approving and formatting requirements and establishes primary document custodians. Effective documentation allows administrators to maintain and update systems efficiently and to identify and correct programming defects, and also provides end users access to operations manuals.

8. Communication plan: change standards should include communication procedures that ensure management notifies affected parties of changes. An oversight or change control committee can help clarify requirements and make departments or divisions aware of pending changes.

[concepts from FFIEC Development and Acquisition handbook]

1.6.4.[2.7.4.] Configuration Management

Configuration Management is the process of creating and maintaining an up to date record of all components of the infrastructure.

1. Functions associated with Configuration Management are:

Planning Identification Control Status Accounting Verification and Audit

2. Configuration Management Database (CMDB) - A database that contains details about the attributes and history of each Configuration Item and details of the important relationships between CI’s. The information held may be in a variety of formats, textual, diagrammatic, photographic, etc.; effectively a data map of the physical reality of IT Infrastructure.

3. Configuration Item - Any component of an IT Infrastructure which is (or is to be) under the control of Configuration Management.

4. The lowest level CI is normally the smallest unit that will be changed independently of other components. CI’s may vary widely in complexity, size and type, from an entire service (including all its hardware, software, documentation, etc.) to a single program module or a minor hardware component.

1.6.5.[2.7.5.] Data Management1.6.5.1.[2.7.5.1.] Backup and Recovery

32

mberg, 08/12/09,
Consider using FFIEC document on Sharepoint to draw best practice concepts
Page 33: Data Center Best Practice and Architecture

Concepts

1. Recovery Time Objective, or RTO, is the duration of time in which a set of data, a server, business process etc. must be restored by. For example, a highly visible server such as a campus' main web server may need to be up and running again in a matter of seconds, as the business impact if that service is down is high. Conversely, a server with low visibility, such as a server used in software QA, may have a RTO of a few hours.

2. Recovery Point Objective, or RPO, is the acceptable amount of data loss a business can tolerate, measured in time. In other words, this is the point in time before a data loss event occurred, at which data may be successfully recovered. For less critical systems, it may be acceptable to recover to the most recent backup taken at the end of the business day, whereas highly critical systems may have a RPO of an hour or only a few minutes. RPO and RTO go hand-in-hand in developing your data protection plan.

3. Deduplication:

a. Source deduplication - Source deduplication means that the deduplication work is done up-front by the client being backed up.

b. Target deduplication - Target deduplication is where the deduplication processing is done by the backup appliance and/or server. There tend to be two forms of target deduplication: in-line and post-process.

i. In-line deduplication devices decide whether or not they have seen the data before writing it out to disk.

ii. Post-process deduplication devices write all of the data to disk, and then at some later point, analyze that data to find duplicate blocks.

4. Backup types

a. Full backups - Full backups are a backup of a device that includes all data required to restore that device to the point in time at which the backup was performed.

b. Incremental backups - Incremental backups backup the changed data set since the last full backup of the system was performed. There does not seem to be any industry standards when you compare one vendor's style of incremental to another. In fact, some vendors include multiple styles of incrementals that a backup administrator may choose from.

i. A cumulative incremental backup is a style of incremental backup where the data set contains all data changed since the last full backup.

33

Page 34: Data Center Best Practice and Architecture

ii. A differential incremental backup is a style of incremental backup where the data set contains all data changed since the previous backup, whether it be a full or another differential incremental.

5. Tape Media - There are many tape formats to choose from when looking at tape backup purchases. They range from open-standards (many vendors sell compatible drives) to single-vendor or legacy technologies.

a. DLT - Digital Linear Tape, or DLT, was originally developed by Digital Equipment Corporation in 1984. The technology was later purchased by Quantum in 1994. Quantum licenses the technology to other manufacturers, as well as manufacturing their own drives.

b. LTO - Linear Tape Open, or LTO, is a tape technology developed by a consortium of companies in order to compete with proprietary tape formats in use at the time.

c. DAT/DDS - Digital Data Store, or DDS, is a tape technology that evolved from Digital Audio Tape, or DAT technology.

d. AIT - Advanced Intelligent Tape, or AIT, is a tape technology developed by Sony in the late 1990's.

e. STK/IBM - StorageTek and IBM have created several proprietary tape formats that are usually found in large, mainframe environments.

Methods

1. Disk-to-Tape (D2T)- Disk-to-tape is what most system administrators think of when they think of backups, as it has been the most common backup method in the past. The data typically moves from the client machine through some backup server to an attached tape drive. Writing data to tape is typically faster than reading the data from the tape.

2. Disk-to-Disk (D2D) - With the dramatic drop in hard drive prices over the recent years, disk-to-disk methods and technologies have become more popular. The big advantage they have over the traditional tape method, is speed in both the writing and reading of data. Some options available in the disk-to-disk technology space:

a. VTL - Virtual Tape Libraries, or VTLs, are a class of disk-to-disk backup devices where a disk array and software appear as a tape library to your backup software.

b. Standard disk array - Many enterprise backup software packages available today support writing data to attached disk devices instead of a tape drive. One advantage to this method is that you don't have to purchase a special device in order to gain the speed benefits of disk-to-disk technology.

34

mberg, 08/12/09,
For best practices: Be sure to stick with the same vendor for all drive types Be sure to understand backward compatibility issues with drive typesNot adviseable to mix drive types in library chassisShould select vendor solution that is open with respect to tape manufacturers; no warranty issues if going off platform or mixing manufacturers
Page 35: Data Center Best Practice and Architecture

3. Disk-to-Disk-to-Tape (D2D2T) - Disk-to-disk-to-tape is a combination of the previous two methods. This practice combines the best of both worlds - speed benefits from using disk as your backup target, and tape's value in long-term and off-site storage practices. Many specialized D2D appliances have some support for pushing their images off to tape. Backup applications that support disk targets, also tend to support migrating their images to tape at a later date.

4. Snapshots - A snapshot is a copy of a set of files and directories as they were at a particular moment in time. On a server operating system, the snapshot is usually taken by either the logical volume manager (LVM) or the file system driver. File system snapshots tend to be more space-efficient than their LVM counterpart. Most storage arrays come with some sort of snapshot capabilities either as base features, or as licenseable add-ons.

5. VM images – In a virtualized environment, backup agents may be installed on the virtual host and file level backups invoked in a conventional method. Backing up each virtual instance as a file at the hypervisor level is another consideration. A prime consideration in architecting backup strategies in a virtual environment is the use of a proxy server or intermediate staging server to handle snapshots of active systems. Such proxies allow for the virtual host instance to be staged for backup without having to quiesce or reboot the VM. Depending on the platform and the OS, it may also be possible to achieve file-level restores within the VM while backing up the entire VM as a file.

6. Replication

a. On-site - On-site replication is useful if you are trying to protect against device failure. You would typically purchase identical storage arrays and then configure them to mirror the data between them. This does not, however, protect against some sort of disaster that takes out your entire data center.

b. Off-site - Off-site implies that you are replicating your data to a similar device located away from your campus. Technically, off-site could mean something as simple as a different building on your campus, but generally this term implies some geo-diversity to the configuration.

c. Synchronous vs. Asynchronous - Synchronous replication guarantees zero data-loss by performing atomic writes. In other words, the data is written to the arrays that are part of the replication configuration, or none of them. A write request is not considered complete until acknowledged by all storage arrays. Depending on your application and the distance between your local and remote arrays, synchronous replication can cause performance impacts, since the application may wait until it has been informed by the OS that the write is complete. Asynchronous replication gets around this by acknowledging the write as soon as the local storage array has written the data. Asynchronous replication may increase performance, but it can contribute to data loss

35

Page 36: Data Center Best Practice and Architecture

if the local array fails before the remote array has received all data updates.

d. In-band vs. Out-of-band - In-band replication refers to replication capabilities built into the storage device. Out-of-band can be accomplished with an appliance, software installed on a server or "in the network", usually in the form of a module or licensed feature installed into a storage router or switch.

7. Tape Rotation and Aging Strategies

a. Grandfather, father, son - From Wikipedia: "Grandfather-father-son backup refers to the most common rotation scheme for rotating backup media. Originally designed for tape backup, it works well for any hierarchical backup strategy. The basic method is to define three sets of backups, such as daily, weekly and monthly. The daily, or son, backups are rotated on a daily basis with one graduating to father status each week. The weekly or father backups are rotated on a weekly basis with one graduating to grandfather status each month."

b. Offsite vaults - Vaulting, or moving media from on-site to an off-site storage facility, is usually done with some sort of full backup. The media sent off-site can either be the original copy or a duplicate, but it is common to have at least one copy of the media being sent rather than sending your only copy. The amount of time it takes to retrieve a given piece of media should be taken into consideration when calculating and planning for your RTO.

c. Retention policies: The CSU maintains a website with links and resources to help campuses comply with requirements contained in Executive Order 1031, the CSU Records/Information Retention and Disposition Schedules. The objective of the executive order is to ensure compliance with legal and regulatory requirements while implementing appropriate operational best practices. The site is located at http://www.calstate.edu/recordsretention.

8. Tape library: A tape library is a device which usually holds multiple tapes, multiple tape drives and has a robot to move tapes between the various slots and drives. A library can help automate the process of switching tapes so that an administrator doesn't have to spend several hours every week changing out tapes in the backup system. A large tape library can also allow you to consolidate various media formats in use in an environment into a single device (ie, mixing DLT and LTO tapes and drives).

9. Disk Backup appliances/arrays: some vendor backup solutions may implement the use of a dedicated storage appliance or array that is optimized for their particular backup scheme. In the case of incorporating deduplication into the backup

36

Page 37: Data Center Best Practice and Architecture

platform, a dedicated appliance may be involved for handling the indexing of the bit-level data.

1.6.5.2.[2.7.5.2.] Archiving

1.6.5.3.[2.7.5.3.] Media Lifecycle

Destruction of expired data

1.6.5.4.[2.7.5.4.] Hierarchical Storage Management1.6.5.5.[2.7.5.5.] Document Management

1.6.6.[2.7.6.] Asset Management

Effective data center asset management is necessary for both regulatory and contractual compliance. It can improve life cycle management, and facilitate inventory reductions by identifying under-utilized hardware and software, potentially resulting in significant cost savings. An effective management process requires combining current Information Technology Infrastructure Library (ITIL) and Information Technology Asset Management (ITAM) best practices with accurate asset information, ongoing governance and asset management tools. The best systems/tools should be capable of asset discovery, manage all aspects of the assets, including physical, financial and contractual, life cycle management with Web interfaces for real time access to the data. Recognizing that sophisticated systems may be prohibitively expensive, asset management for smaller environments may be able to be managed by spreadsheets or simple database. Optimally, a system that could be shared among campuses while maintaining restricted permission levels, would allow for more comprehensive and uniform participation, such as the Network Infrastrucure Asset Management System (NIAMS), http://www.calstate.edu/tis/cass/niams.shtml

The following are asset categories to be considered in a management system:

Physical Assets – to include the grid, floor space, tile space, racks and cables. The layout of space and the utilization of the attributes above are literally an asset that needs to be tracked both logically and physically.

Network Assets – to include routers, switches, firewalls, load balancers, and other network related appliances.

Storage Assets – to include Storage Area Networks (SAN), Network Attached Storage (NAS), tape libraries and virtual tape libraries.

Server Assets – to include individual servers, blade servers and enclosures.

37

Page 38: Data Center Best Practice and Architecture

Electrical Assets – to include Universal Power Supplies (UPS), Power Distribution Units (PDU), breakers, outlets (NEMA noted), circuit number and grid location of same. Power consumption is another example of logical asset that needs to be monitored by the data center manager in order to maximize server utilization and understand, if not reduce, associated costs.

Air Conditioning Assets – to include air conditioning units, air handlers, chiller plants and other airflow related equipment. Airflow in this instance may be considered a logical asset as well but the usage plays an important role in a data center environment. Rising energy costs and concerns about global warming require data center managers to track usage carefully. Computational fluid dynamics (CFD) modeling can serve as a tool for maximizing airflow within the data center.

Data Center Security and Safety Assets – Media access controllers, cameras, fire alarms, environmental surveillance, access control systems and access cards/devices, fire and life safety components, such as fire suppression systems.

Logical Assets – T1’s, PRI’s and other communication lines, air conditioning, electrical power usage. Most importantly in this logical realm is the management of the virtual environment. Following is a list of logical assets or associated attributes that would need to be tracked:

o A list of Virtual Machines o Software licenses in use in data centero Virtual access to assets

VPN access accounts to data center Server/asset accounts local to the asset

Information Assets – to include text, images, audio, video and other media. Information is probably the most important asset a data center manager is responsible for. The definition is: An information asset is a definable piece of information, stored in any manner, recognized as valuable to the organization. In order to achieve access users must have accurate, timely, secure and personalized access to this information.

The following are asset groupings to be considered in a management system:

By Security Levelo Confidentialityo FERPAo HIPPAo PCI

By Support Organizationo Departmental

38

Page 39: Data Center Best Practice and Architecture

o Computer Center Supportedo Project Team

Criticalityo Critical (ex. 24x7 availability)o Business Hours only (ex. 8AM - 7 PM)o Noncritical

By Funding Source (useful for recurring costs)o Departmental fundedo Project fundedo Division funded

1.6.6.1.[2.7.6.1.] Tagging/Tracking1.6.6.2.[2.7.6.2.] Licensing1.6.6.3.[2.7.6.3.] Software Distribution

1.6.7.[2.7.7.] Problem Management

Problem Management investigates the underlying cause of incidents, and aims to prevent incidents of a similar nature from recurring. By removing errors, which often requires a structural change to the IT infrastructure in an organization, the number of incidents can be reduced over time. Problem Management should not be confused with Incident Management. Problem Management seeks to remove the causes of incidents permanently from the IT infrastructure whereas Incident Management deals with fighting symptoms to incidents. Problem Management is proactive while Incident Management is reactive.

1.6.7.1.[2.7.7.1.] Fault Detection - A condition often identified as a result of multiple incidents that exhibit common symptoms. Problems can also be identified from a single significant incident, indicative of a single error, for which the cause is unknown, but for which the impact is significant.

1.6.7.2.[2.7.7.2.] Correction - An iterative process to diagnose known errors until they are eliminated by the successful implementation of a change under the control of the Change Management process.

1.6.7.3.[2.7.7.3.] Reporting - Summarizes Problem Management activities. Includes number of repeat incidents, problems, open problems, repeat problems, etc.

1.6.8.[2.7.8.] Security1.6.8.1.[2.7.8.1.] Data Security

Data security is the protection of data from accidental or malicious modification, destruction, or disclosure. Although the subject of data security is broad and multi-faceted, it should be an overriding concern in the design and operation of a data center. There are multiple laws, regulations and standards that are likely to be applicable such as the Payment Card Industry Data Security Standard, ISO 17799 Information Security Standard, California SB 1386, California AB 211, the California State University Information Security Policy and Standards to name a few. It is required to periodically prove compliance to these standards and laws.

39

Page 40: Data Center Best Practice and Architecture

1.6.8.2.[2.7.8.2.] EncryptionEncryption is the use of an algorithm to encode data in order to render a message or other file readable only for the intended recipient. Its primary functions are to ensure non-repudiation, integrity, and confidentiality in both data transmission and data storage. The use of encryption is especially important for Protected Data (data classified as Level 1 or 2). Common transmission encryption protocols and utilities include SSL/TLS, SecureShell, and IPSec. Encrypted Data Storage programs include PGP's encryption products (other security vendors such as McAfee have products in this space as well), encrypted USB keys, and TrueCrypt's free encryption software. Key management (exchange of keys, protection of keys, and key recovery) should be carefully considered.

1.6.8.3.[2.7.8.3.] AuthenticationAuthentication is the verification of the identity of a user. From a security perspective it is important that user identification be unique so that each person can be positively identified. Also the process of issuing identifiers must be secure and documented. There are three types of authentication available:

What a person knows (e.g., password or passphrase) What a person has (e.g., smart card or token) What a person is or does (e.g., biometrics or keystroke dynamics)

Single-factor authentication is the use one of the above authentication types, two-factor authentication uses two of them, and three-factor authentication uses all of them.

Single-factor password authentication remains the most common means of authentication ("What a person knows"). However due to the computing power of modern computers in the hands of attackers and technologies such as "rainbow tables", passwords used for single factor authentication may soon outlive their usefulness. Strong passwords should be used and a password should never be transmitted or stored without being encrypted. A reasonably strong password would be a minimum of eight characters and should contain three of the following four character types: lower case alpha, upper case alpha, number, and special character.

1.6.8.4.[2.7.8.4.] Vulnerability Management1.6.8.4.1.[2.7.8.4.1.] Anti-malware Protection

Malware (malicious code, such as viruses, worms, and spyware, written to circumvent the security policy of a computer) represents a threat to data center operations. Anti malware solutions must be deployed on all operating system platforms to detect and reduce the risk to an acceptable level. Solutions for malware infection attacks include firewalls (host and network), antivirus/anti-spyware, host/network intrusion protection systems, OS/Application hardening and patching. Relying on only anti virus solutions will not fully protect a computer from malware. Determining the correct mix and configuration of the anti-malware solutions depends on the value and type of services provided by a server. Anti virus, firewalls, and intrusion protection systems need to be regularly updated in order to respond to current threats.

1.6.8.4.2.[2.7.8.4.2.] Patching

40

Page 41: Data Center Best Practice and Architecture

The ongoing patching of operating systems and applications are important activities in vulnerability management. Patching includes file updates and configuration alterations. Data Center Operations groups should implement a patching program designed to monitor available patches, categorize, test, implement, and monitor the deployment of OS and application patches. In order to detect and address emerging vulnerabilities in a timely manner, campus staff members should frequently monitor announcements from sources such as BugTraq, REN-ISAC, US-Cert, and Microsoft and then take appropriate action. Both timely patch deployment and patch testing are important and should be thoughtfully balanced. Patches should be applied via a change control process. The ability to undo patches is highly desirable in case unexpected consequences are encountered. Also the capability to verify that patches were successfully applied is important.

1.6.8.4.3.[2.7.8.4.3.] Vulnerability ScanningThe datacenter should implement a vulnerability scanning program such as regular use of McAfee’s Foundstone.

1.6.8.4.4.[2.7.8.4.4.] Compliance ReportingCompliance Reporting informs all parties with responsibility for the data and applications how well risks are reduced to an acceptable level as defined by policy, standards, and procedures. Compliance reporting is also valuable in proving compliance to applicable laws and contracts (HIPAA, PCI DSS, etc.). Compliance reporting should include measures on:

How many systems are out of compliance. Percentage of compliant/non-compliant systems. Once detected out of compliance, how quickly a system comes into compliance.

Compliance trends over time.

1.6.8.5.[2.7.8.5.] Physical SecurityWhen planning for security around your Data Center and the equipment contained therein, physical security must be part of the equation. This would be part of a "Defense-in-Depth" security model. If physical security of critical IT equipment isn't addressed, it doesn't matter how long your passwords are, or what method of encryption you are using on your network - once an attacker has gained physical access to your systems, not much else matters.

See section 2.4.1.6 for description of access control

41

mberg, 08/12/09,
Remove product reference and describe specific toolsets that are typically used, such as port scanning, password crack tools, etc.
Page 42: Data Center Best Practice and Architecture

<insert diagram of reference model with key components as building blocks>

42

Page 43: Data Center Best Practice and Architecture

2.[3.] Best Practice Components

2.1.[3.1.] Standards2.1.1.[3.1.1.] ITIL

The Information Technology Infrastructure Library (ITIL) Version 3 is a collection of good practices for the management of Information Technology organizations. It consists of five components whose central theme is the management of IT services. The five components are Service Strategy (SS), Service Design (SD), Service Transition (ST), Service Operations (SO), and Service Continuous Improvement (SCI). Together these five components define the ITIL life cycle with the first four components (SS, SD, ST and SO) at the core with SCI overarching the first four components. SCI wraps the first four components and depicts the necessary concern of each of the core components to continuously look for ways to improve the respective ITIL process.

ITIL defines the five components in terms of functions/activities, concepts, and processes, as illustrated below:

Service Strategy Main Activities Key Concepts ProcessesDefine the Market Utility & Warranty Service Portfolio ManagementDevelop Offerings Value Creation Demand ManagementDevelop Strategic Assets Service Provider Financial ManagementPrepare Execution Service Model

Service Portfolio

Service DesignFive Aspects of SD Key Concepts ProcessesService Solution Four “P’s”: People, Processes,

Products, & PartnersService Catalog Management

Service Management Systems and Solutions

Service Design Package Service Level Management

Technology and Management Architectures & Tools

Delivery Model Options Availability Management

Processes Service Level Agreement Capacity ManagementMeasurement Systems, Methods & Metrics

Operational Level Agreement IT Service Continuity Management

43

Page 44: Data Center Best Practice and Architecture

Underpinning Contract Information Security ManagementSupplier Management

Service TransitionProcesses Key ConceptsChange Management Service ChangesService Asset & Configuration Management Request for ChangeRelease & Deployment Management Seven “R’s” of Change ManagementKnowledge Management Change TypesTransition Planning & Support Release UnitService Validation & Testing Configuration Management Database (CMDB)Evaluation Configuration Management System

Definitive Media Library (DML)

Service OperationAchieving the Right Balance Processes FunctionInternal IT View versus External Business View

Event Management Service Desk

Stability versus Responsiveness Incident Management Technical ManagementReactive versus Proactive Problem Management IT Operations ManagementQuality versus Cost Access Management Application Management

Request Fulfillment

Service Continuous ImprovementThe 7 Step Improvement Process to identify vision and strategy, tactical and operational goals

1. Define what you should measure2. Define what you can measure3. Gather the data. Who? How? When? Integrity of the data?4. Process the data. Frequency, format, system, accuracy.5. Analyze the data. Relationships, trends, according to plan, targets met, corrective actions?6. Present and use the information assessment summary action plans, etc.7. Implement corrective action.

2.1.2.[3.1.2.] ASHRAE

ASHRAE modified their operational envelope for data centers with the goal of reducing energy consumption. For extended periods of time, the IT manufacturers recommend that data center operators maintain their environment within the recommended envelope. Exceeding the recommended limits for short periods of time should not be a problem, but running near the allowable limits for months could result in increased reliability issues. In reviewing the available data from a number of IT manufacturers the 2008 expanded recommended operating envelope is the agreed-upon envelope that is acceptable to all the IT manufacturers, and operation within this envelope will not compromise overall reliability of the IT equipment.

44

Page 45: Data Center Best Practice and Architecture

Following are the previous and 2008 recommended envelope data:

2004 Version 2008 Version

Low End Temperature 20°C (68 °F) 18°C (64.4 °F)

High End Temperature 25°C (77 °F) 27°C (80.6 °F)

Low End Moisture 40% RH 5.5°C DP (41.9 °F)

High End Moisture 55% RH 60% RH & 15°C DP (59 °F DP)

<Additional comments on the relationship of electro static discharge (ESD) and relative humidity and the impact to printed circuit board (PCB) electronics and component lubricants in drive motors for disk and tape.>

2.1.3.[3.1.3.] Uptime Institute2.2.[3.2.] Hardware Platforms

2.2.1.[3.2.1.] Servers2.2.1.1.[3.2.1.1.] Server Virtualization

1. Practices

a. Production hardware should run the latest stable release of the selected hypervisor, with patching and upgrade paths defined and pursued on a scheduled basis with each hardware element (e.g. blade) dual-attached to the data network and storage environment to provide for load balancing and fault tolerance.

b. Virtual machine templates should be developed, tested and maintained to allow for consistent OS, maintenance and middleware levels across production instances. These templates should be used to support cloning of new instances as required and systematic maintenance of production instances as needed.

c. Virtual machines should be provisioned using a defined work order process that allows for an effective understanding of server requirements and billing/accounting expectations.

This process should allow for interaction between requestor and provider to ensure appropriate configuration and acceptance of any fee-for-service arrangements.

d. Virtual machines should be monitored for CPU, memory, network and disk usage. Configurations should be modified, with service owning unit participation, to ensure an optimum balance between required and committed capacity.

45

Page 46: Data Center Best Practice and Architecture

Post-provisioning capacity analysis should be performed via a formal, documented process. For example, a 4 VCPU virtual machine with 8 gigabytes of RAM that is using less than 10% of 1 VCPU and 500 megabytes of RAM should be adjusted to ensure that resources are not wasted. This process should be formal, documented and performed on a frequent basis.

e. Virtual machine boot/system disks should be provisioned into a LUN maintained in the storage environment to ensure portability of server instances across hardware elements.

f. To reduce I/O contention, virtual machines with high performance or high capacity requirements should have their non-boot/system disks provisioned using dedicated LUNs mapped to logical disks in the storage environment.

g. Virtual machines should be administered using a central console/resource such as VMWare VirtualCenter. However, remote KVM functionality should also be implemented to support remote hypervisor installation and patching and remote hardware maintenance.

h. A virtual development environment should be implemented, allowing for development and testing of new server instances/templates, changes to production instances/templates, hypervisor upgrades and testing of advanced high-availability features.

2.2.2.[3.2.2.] Storage

1. Practices

a. Develop meaningful naming convention when defining components of the SAN. This readily identifies components, quickly presents information about them and reduces likelihood of misunderstandings.

b. Use different types of storage to produce tiers. High speed fiber channel drives are not necessary for all applications. A mix of fiber with various SATA capacity and speed drives produces a SAN that balances performance with cost.

c. Utilize NDMP when able for NFS. Whenever possible use NDMP to backup NFS files on the SAN. Backups are faster and network traffic is reduced. However, make sure the target for the backup is not the same storage device as the SAN if you are doing disk to disk backups.

d. Isolate iSCSI from regular network traffic. SAN iSCSI traffic should be on its own network using its own switches for performance and security reasons.

46

Page 47: Data Center Best Practice and Architecture

e. Ensure partition alignment between servers and SAN disks. Misalignment of partitions will cause one or two additional I/O’s for every read or write. This can have a huge performance impact on large files or databases.

f. Use thin provisioning where possible. Some SAN vendor tools allow you to dynamically grow and shrink storage allocations. A large amount of storage can be assigned to a server but doesn’t get allocated until it is needed.

g. Use deduplication where possible. Deduplication on VTL’s have been in use for quite a while but deduplication of primary storage is fairly new. Keep an eye on the technology and begin to apply conservatively.

2.2.2.1.[3.2.2.1.] Storage Virtualization1. To abstract storage hardware for device/array independence

2. To provide replication/mirroring for higher availability, DR/BC, etc.

2.3.[3.3.] Software2.3.1.[3.3.1.] Operating Systems

2.3.1.1. Decision matrix for OS platforms (Windows, Linux, HP-UX, AIX)2.3.1.2. Licensing considerations2.3.1.3. Support for OS platforms (sys admin skill set maintenance, outsourcing)

2.3.2.[3.3.2.] Middleware2.3.2.1.[3.3.2.1.] Identity Management

2.3.3.[3.3.3.] Databases2.3.3.1. Decision matrix for DB platforms (Oracle, MSSQL, Informix, MySQL)2.3.3.2. Preferred internal development platforms2.3.3.3. Licensing considerations2.3.3.4. Support for DB platforms (training, sourcing)

2.3.4.[3.3.4.] Core/Enabling Applications2.3.4.1.[3.3.4.1.] Email

2.3.4.1.1.[3.3.4.1.1.] Spam Filtering2.3.4.2.[3.3.4.2.] Web Services2.3.4.3.[3.3.4.3.] Calendaring2.3.4.4.[3.3.4.4.] DNS2.3.4.5.[3.3.4.5.] DHCP2.3.4.6.[3.3.4.6.] Syslog2.3.4.7.[3.3.4.7.] Desktop Virtualization2.3.4.8.[3.3.4.8.] Application Virtualization

2.3.5.[3.3.5.] Third Party Applications2.3.5.1.[3.3.5.1.] LMS2.3.5.2.[3.3.5.2.] CMS2.3.5.3.[3.3.5.3.] Help Desk/Ticketing

2.4.[3.4.] Delivery Systems2.4.1.[3.4.1.] Facilities

47

Page 48: Data Center Best Practice and Architecture

2.4.1.1.[3.4.1.1.] Tiering Standards

2.4.1.2.[3.4.1.2.] Spatial Guidelines and Capacities1. The Data Center should be located in an area with no flooding sources

directly above or adjacent to the room. Locate building water and sprinkler main pipes, and toilets and sinks away from areas alongside or above the Data Center location.

2. The Data Center is to be constructed of slab-to-slab walls and a minimum one-hour fire rating. All penetrations through walls, floors, and ceilings are to be sealed with an approved sealant with fire ratings equal to the penetrated construction.

3. FM-200 gaseous fire suppression will be used, possibly supplemented with VESDA smoke detection with 24/7 monitoring.

4. Provide a 20 millimeter vapor barrier for the Data Center envelope to allow maintaining proper humidity. Provide R-21 minimum insulation. If any walls are common to the outside, increase the R factor to achieve the same effect based on the exterior wall construction.

5. All walls of the Data Center shall be full height from slab to under floor above.

6. All paint within the Data Center shall be moisture control/anti-flake type.

7. The redundant UPS systems and related critical electrical equipment should be located in separate rooms external to the data center. Redundant systems such as UPS systems (not parallel) not connected together shall be located in separate rooms where not cost prohibitive.

8. Provide at least one set of double doors or one 3’-6” wide door into the Data Center to facilitate the movement of large equipment.

9. There will be a Network Operation Center (NOC) outside the data center; KVMs will be located inside the Data Center as well as in the NOC.

10. A portion of future data center expansion space may be used for staging, storage and test/development.

11. Interior windows, if any, on fire-rated walls between the Data Center and adjacent office spaces shall be one-hour rated. No windows are permitted in Data Center exterior walls.

12. Column spacing shall be 30’x 30’ or greater.

48

Page 49: Data Center Best Practice and Architecture

13. The concrete floor beneath the raised access floor in the Data Center is to be sealed with appropriate water based sealer prior to the installation of the raised access floor. IT equipment cabinets can range to 2,000 lbs each. Subfloor load capacity shall not be less than 150 lbs/SF for the Data Center and 250 lbs/SF for electrical and mechanical support areas.

14. Ceiling load capacity for suspension of data and power cable tray, ladder rack and HVAC ductwork shall not be less than 50 lbs/SF.

15. A steel roof shall be provided. Consider installing a redundant roof or fire-proof gypsum board ceiling (especially if the original roof is wooden). Roof load capacity shall not be less than 40 lbs/SF with capability to add structural steel for support of HVAC heat rejection equipment.

16. HVAC heat rejection equipment may be installed on grade if space allows, otherwise on the roof. Utility power transformers, standby generators and switchgear will be installed on grade.

17. Provide two drains with anti-backflow in the floor unless cost prohibitive.

18. Provide a minimum ceiling height of 12.5' clear from the floor slab to the bottom of beams in the Data Center.

19. A 24” raised access floor would be required (please refer to details in this document). The access floor will be used as the primary cool air supply plenum and should be kept free of cables, piping or other equipment that can cause obstruction of airflow.

20. Power cabling shall be routed in raceway overhead, mounted on equipment racks or suspended overhead from the ceiling.

21. Data cabling and fiber shall be routed overhead in cable tray or on ladder rack.

22. All doors into the Data Center and Lab areas are to be secured with locks. All doors into the Data Center are to have self-closing devices. All doors should have the appropriate fire rating per the NFPA and local codes. The doors shall have a full 180-degree swing.

23. All construction in the Data Center is to be complete a minimum three weeks prior to occupancy. This includes walls, painting, backboards, doors, frames, hardware, windows, VCT floor, ceiling grid and tile (if specified), lights, sprinklers, fire suppression systems, electrical, HVAC and UPS. Temporary power and HVAC are not acceptable. Rooms must be wet-mop cleaned to remove all dust prior to installing equipment.

24. Orient light fixtures to run between and parallel with equipment rows in the Data Center.

49

Page 50: Data Center Best Practice and Architecture

25. Motion sensors shall be used for data center lighting control for energy efficiency.

2.4.1.3.[3.4.1.3.] Electrical Systems

<This section from Lawrence Berkeley National Laboratories. The referenced Design Guidelines Sourcebook is by PG&E. http://hightech.lbl.gov/DCTraining/best-practices-technical.html >

1. Electrical Infrastructure

Maximize UPS Unit Loading

o When using battery based UPSs, design the system to maximize the load factor on operating

UPSs. Use of multiple smaller units can provide the same level of redundancy while still maintaining higher load factors, where UPS systems operate most efficiently. For more information, see Chapter 10 of the Design Guidelines Sourcebook.

Specify Minimum UPS Unit Efficiency at Expected Load Points

o There are a wide variety of UPSs offered by a number of manufacturers at a wide range of

efficiencies. Include minimum efficiencies at a number of typical load points when specifying UPSs. Compare offerings from a number of vendors to determine the best efficiency option for a given UPS topography and feature set. For more information, see Chapter 10 of the Design Guidelines Sourcebook.

Evaluate UPS Technologies for the Most Efficient

o New UPS technologies that offer the potential for higher efficiencies and lower maintenance costs

are in the process of being commercialized. Consider the use of systems such as flywheel or fuel cell UPSs when searching for efficient UPS options. For more information, see Chapter 10 of the Design Guidelines Sourcebook.

2. Lighting

Use Occupancy Sensors

o Occupancy sensors can be a good option for datacenters that are infrequently occupied.

Thorough area coverage with occupancy sensors or an override should be used to insure the lights stay on during installation procedures when a worker may be 'hidden' behind a rack for an extended period.

Provide Bi-Level Lighting

o Provide two levels of clearly marked, easily actuated switching so the lighting level can be easily

changed between normal, circulation space lighting and a higher power detail work lighting level. The higher power lighting can be normally left off but still be available for installation and other detail tasks.

Provide Task Lighting

o Provide dedicated task lighting specifically for installation detail work to allow for the use of lower,

circulation space and halls level lighting through the datacenter area.

2.4.1.4.[3.4.1.4.] HVAC Systems

<This section from Lawrence Berkeley National Laboratories. The referenced Design Guidelines Sourcebook is by PG&E. http://hightech.lbl.gov/DCTraining/best-practices-technical.html >

1. Mechanical Air Flow Management

Hot Aisle/Cold Aisle Layout

Blank Unused Rack Positions

50

Page 51: Data Center Best Practice and Architecture

o Standard IT equipment racks exhaust hot air out the back and draw cooling air in the front.

Openings that form holes through the rack should be blocked in some manner to prevent hot air from being pulled forward and recirculated back into the IT equipment. For more information, see Chapter 1 of the Design Guidelines Sourcebook.

Use Appropriate Air Diffusers

Position supply and returns to minimize mixing

o Diffusers should be located to deliver air directly to the IT equipment. At a minimum, diffusers

should not be placed such that they direct air at rack or equipment heat exhausts, but rather direct air only towards where IT equipment draws in cooling air. Supplies and floor tiles should be located only where there is load to prevent short circuiting of cooling air directly to the returns; in particular, do not place perforated floor supply tiles near computer room air conditioning units using the as a return air path. For more information, see Chapters 1 and 2 of the Design Guidelines Sourcebook.

Minimize Air Leaks in Raised Floor

2. Mechanical Air Handler Systems

Use Redundant Air Handler Capacity in Normal Operations

o With the use of Variable Speed Drives and chilled water based air handlers, it is most efficient to

maximize the number air handlers operating in parallel at any given time. Power usage drops approximately with the square of the velocity, so operating two units at 50% capacity uses a sum total less energy than a single unit at full capacity. For more information, see Chapter 3 of the Design Guidelines Sourcebook.

Configure Redundancy to Reduce Fan Power Use in Normal Operation

o When multiple small distributed units are used, redundancy must be equally distributed.

Achieving N+1 redundancy can require the addition of a large number of extra units, or the oversizing of all units. A central air handler system can achieve N+1 redundancy with the addition of a single unit. The redundant capacity can be operated at all times to provide a lower air handler velocity and an overall fan power reduction, since fan power drops with the square of the velocity. Light loading. For more information, see Chapter 3 of the Design Guidelines Sourcebook.

Control Volume by Variable Speed Drive on Fans Based on Space Temperature

The central air handlers should use variable fan speed control to minimize the volume

of air supplied to the space. The fan speed should be varied in series with the supply air temperature in a manner that reduces fan speed to the minimum speed possible before increase supply air temperature above a reasonable set point. Typically, supply air of 60F is appropriate to provide the sensible cooling required by datacenters. For more information, see Chapters 1 and 3 of the Design Guidelines Sourcebook.

3. Mechanical Humidification

Use Widest Suitable Humidity Control Band

Centralize Humidity Control

Use Lower Power Humidification Technology

o There are several options for lower power, non-isothermal humidification, including air or water

pressure based 'fog' systems, air washers, and ultrasonic systems. For more information, see Chapter 7 of the Design Guidelines Sourcebook.

4. Mechanical Plant Operation

Use Free Cooling / Waterside Economization

o Free cooling provides cooling using only the cooling tower and a heat exchanger. It is very

attractive in dry climates and for facilities that have local concerns about outside air quality that may cause concern about the use of standard airside economizers. For more information, see Chapters 4 and 6 of the Design Guidelines Sourcebook.

Monitor System Efficiency

o Install reliable, accurate monitoring of key plant metrics such as such kW/ton. The first cost of

monitoring can be quickly recovered by identifying common efficiency problems, such as: low refrigerant charge, non-optimal compressor mapping, incorrect sensors, incorrect pumping

51

Page 52: Data Center Best Practice and Architecture

control, etc. Efficiency monitoring provides the information needed for facilities personnel to optimize the system's energy performance during buildout and avoid efficiency decay and troubleshoot developing equipment problems over the life of the system. For more information, see Chapter 4 of the Design Guidelines Sourcebook.

Rightsize the Cooling Plant

o Due to the critical nature of the load and unpredictability of future IT equipment loads, datacenter

cooling plants are oversized. The design should recognize that the standard operating condition will be at partload and optimize for efficiency accordingly. Consistent part-load operation dictates using well know design approaches to part load efficiency such as utilizing redundant towers to improve approach, using multiple chillers with variable speed drive, variable speed pumping throughout, chiller staging optimized for partload operation, etc. For more information, see Chapter 4 of the Design Guidelines Sourcebook.

2.4.1.5.[3.4.1.5.] Fire Protection & Life Safety2.4.1.6.[3.4.1.6.] Access Control2.4.1.7.[3.4.1.7.] Commissioning

<This section from Lawrence Berkeley National Laboratories. The referenced Design Guidelines Sourcebook is by PG&E. http://hightech.lbl.gov/DCTraining/best-practices-technical.html >

1. Commissioning and Retrocommissioning

Perform a Peer Review

o A peer review offers the benefit of having the design evaluated by a professional without the

preconceived assumptions that the main designer will inevitably develop over the course of the project. Often, efficiency, reliability and cost benefits can be achieved through the simple process of having a fresh set of eyes, unencumbered by the myriad small details of the project, review the design and offer suggestions for improvement.

Engage a Commissioning Agent

o Commissioning is a major task that requires considerable management and coordination

throughout the design and construction process. A dedicated commissioning agent can ensure that commissioning is done in a thorough manner, with a minimum of disruption and cost.

Document Testing of All Equipment and Control Sequences

o Develop a detailed testing plant for all components. The plan should encompass all expected

sequence of operation conditions and states. Perform testing at with the support of all relevant trades — it is most efficient if small errors in the sequence or programming can be corrected on-the-spot rather than relegated to the back and forth of a traditional punchlist. Functional testing performed for commissioning does not take the place of equipment startup testing, control point-to-point testing or other standard installation tests.

Measure Equipment Energy Onsite

o Measure and verify that major pieces of equipment meet the specified efficiency requirements.

Chillers in particular can have seriously degraded cooling efficiency due to minor installation damage or errors with no outward symptoms, such as loss of capacity or unusual noise.

Provide Appropriate Budget and Scheduling for Commissioning

o Commissioning is a separate, non-standard, procedure that is necessary to ensure the facility is

constructed to and operating at peak efficiency. Additional time commitment beyond a standard construction project will be required from the contractors. Coordination meetings dedicated to commissioning are often required at several points during construction to ensure a smooth and effective commissioning.

Perform Full Operational Testing of All Equipment

o Commissioning testing of all equipment should be performed after the full installation of the

systems are complete, immediately prior to occupancy. Normal operation and all failure modes should be tested. In many critical facility cases, the use of load banks to produce a realistic load on the system is justified to ensure system reliability under design conditions.

Perform a Full Retrocommissioning

o Many older datacenters may have never been commissioned, and even if they had performance

degrades over time. Perform a full commissioning and correct any problems found. Where control

52

Page 53: Data Center Best Practice and Architecture

loops have been overridden due to immediate operational concerns, such as locking out condenser water reset due to chiller instability, diagnose and correct the underlying problem to maximize system efficiency, effectiveness, and reliability.

Recalibrate All Control Sensors

Where Appropriate, Install Efficiency Monitoring Equipment

o As a rule, a thorough retrocommissioning will locate a number of low-cost or no-cost areas where

efficiency can be improved. However, without a simple means of continuous monitoring, the persistence of the savings is likely to be low. A number of simple metrics (cooling plant kW/ton, economizer hours of operation, humidification/dehumidification operation, etc.) should be identified and continuously monitored and displayed to allow facilities personnel to recognize when system efficiency has been compromised.

2.4.2.[3.4.2.] Load Balancing/High Availability2.4.3.[3.4.3.] Connectivity

2.4.3.1.[3.4.3.1.] Network2.4.3.1.1.[3.4.3.1.1.] Network Virtualization

1. Use of VLANs for LAN security and network management

a. Controlling network access through VLAN assignment

b. Using VLANs to present multiple virtual subnets within a given physical subnet

c. Using VLANs to present one virtual subnet across portions of many physical subnets

2. Use of MPLS for WAN security and network management

a. Multiprotocol Label Switching (MPLS) used to create Virtual Private Networks (VPNs) to provide traffic isolation and differentiation.

2.4.3.1.2.[3.4.3.1.2.] Structured Cabling2.4.4.[3.4.4.] Operations

2.4.4.1.[3.4.4.1.] Staffing2.4.4.2.[3.4.4.2.] Training2.4.4.3.[3.4.4.3.] Monitoring2.4.4.4.[3.4.4.4.] Console Management2.4.4.5.[3.4.4.5.] Remote Operations

2.4.5.[3.4.5.] Accounting2.5.[3.5.] Disaster Recovery

2.5.1.[3.5.1.] Relationship to overall campus strategy for Business Continuity2.5.2.[3.5.2.] Relationship to CSU Remote Backup – DR initiative2.5.3.[3.5.3.] Infrastructure considerations2.5.4.[3.5.4.] Operational considerations

2.5.4.1.[3.5.4.1.] Recovery Time Objectives and Recovery Point Objectives discussed in 2.7.3.1 (Backup and Recovery

2.5.4.2.[3.5.4.2.] Resource-sharing between campuses: Cal State Fullerton/San Francisco State example

53

Page 54: Data Center Best Practice and Architecture

<sourced from ITAC Disaster Recovery Plan Project, http://drp.sharepointsite.net/itacdrp/default.aspx >

CSU, Fullerton has established a Business Continuity computing site at San Francisco State University. The site allows a number of critical computing functions to remain in service in the event of severe infrastructure disruption, such as complete failure of both CENIC links to the Internet, failure of the network core on the Fullerton campus, or complete shutdown of the Fullerton Data Center.

CSU, Fullerton is the only CSU campus to establish such extensive off-site capabilities.

The goal of the site is to provide continuity for the most critical computing services that can be supported in a cost-effective manner. Complete duplication of every central computing resource on the Fullerton campus is prohibitively expensive, and San Francisco State’s Data Center could not provide the space for that much equipment. (The same is true for SFSU. Fullerton does not have the space, cooling, or electrical to duplicate all the equipment at SFSU.)

Major capabilities include continuity of access to:

The main campus website: www.fullerton.edu The faculty/student Portal: my.fullerton.edu Faculty/staff email; Student email (provided by Google, but accessed via the Fullerton Portal) Blackboard Learning Solutions (hosted by Blackboard ASP, but accessed via the

Fullerton Portal) CMS HR, Finance, and Student applications (hosted by Unisys in Salt Lake City,

but accessed via the Fullerton Portal) Brass Ring H.R. recruitment system (hosted by Brass Ring) OfficeMax ordering system GE Capital state procurement card system

With these capabilities, educational and business activities can continue while the infrastructure interruption is resolved.

In addition to complete operation, the remote site can substitute for specific resources, such as the campus website. This “granular” approach provides significant flexibility for responding to specific computing issues in the Data Center.

A number of significant resources were found to be too costly to duplicate off site, including:

CMS Data warehouse Filenet document repository Voice mail IBM mainframe (which is to be decommissioned in Dec, 2008)

54

Page 55: Data Center Best Practice and Architecture

The project does not provide continuity for resources provided outside of Fullerton IT.

The project began with initial discussions between the CIO’s of Fullerton and San Francisco in 2006, where they agreed in concept to provide limited “hosting” for equipment from the other campus. An arrangement was worked out with CENIC, the statewide data network provider, to use features of the “Border Gateway Protocol” to allow a campus to switch a portion of the campus Internet Protocol (IP) space from their main campus to the remote campus in a matter of seconds. This capability was perfected and tested in the summer of 2007.

A major innovation was the use of the “backup” CENIC link at SFSU to provide Internet access for Fullerton’s remote site. This completely avoids Fullerton having any impact on the SFSU network. We use no IP addresses at SF. They make no changes to their firewall or routers. We need no network ports. And, all Internet traffic to our site goes through the backup CENIC link, not through SFSU’s primary link.

Fullerton purchased an entire cabinet of equipment, including firewall, network switch, servers, and remote management of keyboards and power plugs. The equipment was tested locally and transported to San Francisco in January, 2008.

The site became operational in February, 2008.

All maintenance and monitoring of the remote equipment is done through the Internet from the Fullerton campus. Staff at San Francisco provide no routine assistance. This has several important benefits: (1) it places little burden on the remote “host”. (2) it avoids the need to train staff at the remote campus and re-train when personnel turn-over. And (3) it allows the entire remote site to be relocated to a different remote host with almost no change.

Because the remote site is connected to Fullerton through a VPN tunnel, the same Op Manager software that monitors equipment on the Fullerton campus also monitors the servers at SFSU. Any unexpected server conditions at SFSU automatically trigger alerts to Fullerton staff.

To avoid unexpected disruption, the Continuity site is activated manually by accessing the Firewall through the Internet and changing a few rules. Experience with the unexpected consequences of setting up “automated” systems prompted this design.

The SFSU site contains a substantial capability, including:

Domain controllers for Fullerton’s two Microsoft Active Directory domains (AD and ACAD)This provides secure authentication to the portal and email servers, and would

55

Page 56: Data Center Best Practice and Architecture

allow Active Directory to be rebuilt if the entire Fullerton Data Center were destroyed.

Web Server Portal Server Application Servers for running batch jobs and synchronizing the Portal

databases Microsoft Exchange email servers Blackberry Enterprise Server (BES) to provide continuity for Blackberry users SQL database servers CMS Portal servers (this capability not totally implemented yet because CMS

Student is just coming “on line” during 2008) Email gateway server

Because the SFSU site constantly replicates domain updates and refreshes the Portal database daily, the SFSU site is a better source of much information than the tape backups kept at Iron Mountain.

56

Page 57: Data Center Best Practice and Architecture

Network Diagrams

Figure 1 – Intercampus network diagram Figure 2 – Remote LAN at DR site

2.5.4.3.[3.5.4.3.] Memorandum of Understanding

Campuses striking partnerships in order to share resources and create geographic diversity for data stores will want to document the terms of their agreement, representing elements such as physical space, services, access rights and effective dates. Following is a sample template (sourced from ITAC DR site):

MOU SSU-SJSUSonoma State University

Rider A, Page 1 of 1

MEMORANDUM OF UNDERSTANDING

This MEMORANDUM OF UNDERSTANDING is entered into this 1st day of September, 2008, by and between Sonoma State University, Computer Operations, Information Technology Department and San Jose State University, University Computing and Telecomm.

57

Page 58: Data Center Best Practice and Architecture

Each campus will provide, for use by the other campus: 2 each - 19” racks, mounting equipment specification (EIA-310-C) and requisite power and cooling for same.

Power provided by Sonoma State University will include uninterrupted power supply (UPS) and diesel generator backup power.

PHYSICAL LOCATION OF HOSTED EQUIPMENT

Sonoma State University will station the two 19” racks for San Jose State University in the Sonoma State University Information Technology data center. Collocated network devices will reside in a physically segregated LAN.

San Jose State University will station the two racks for Sonoma State University …

LOGICAL LOCATION OF HOSTED EQUIPMENT

Equipment stationed by SJSU in the two racks in the SSU data center will be provisioned in a segregated security zone behind a firewall interface whose effective security policy is specified by the hosted campus. Security policy change requests for the firewall by SJSU will be accomplished within 7 days of receipt by SSU.

PHYSICAL ACCESS BY SISTER CAMPUS

Physical access to the two racks in the SSU data center by SJSU support staff will be granted according to the escorted visitor procedures in place at SSU. Physical access is available during normal business hours (8am – 5pm) by appointment or emergency access on a best effort basis by contacting the SSU emergency contact listed in this document.

Physical access to the two racks in the SJSU data center by SSU support staff will be granted according to …

SERVICES PROVIDED BY HOST CAMPUS

SSU Computer Operations staff will provide limited services to SJSU as required during normal business hours (8am – 5pm) or after hours on a best effort basis by contacting the SSU emergency contact listed in this document. Limited services are defined to be such things as tasks not to exceed 1 hour of labor such as visiting a system console for diagnostic purposes, power cycling a system, or other simple task that cannot be performed remotely by SJSU.

58

Page 59: Data Center Best Practice and Architecture

SJSU Computer Operations staff will provide limited services to SSU as required during normal business hours (8am – 5pm) or after hours on a best effort basis by contacting the SJSU emergency contact listed in this document. Limited services are defined to be such things as tasks not to exceed 1 hour of labor such as visiting a system console for diagnostic purposes, power cycling a system, or other simple task that cannot be performed remotely by SSU.

SECURITY REQUIREMENTS

Level-one data in transit or at rest must be encrypted. Each campus will conform to CSU information security standards as they may apply to equipment stationed at the sister campus and cooperate with the sister campus’ Information Security Officer pertaining to audit findings on their collocated servers.

The point of contact person for Sonoma State University will be Mr. Samuel Scalise (707 664-3065, [email protected]). The point of contact person for San Jose State University will be Mr. Don Baker (408 924-7820 [email protected]).

The emergency point of contact person for Sonoma State University will be Mr. Don Lopez (707 291-4970, [email protected]). The emergency point of contact for San Jose State University will be …

No charges to either party since equipment, services and support are mutualThe term of this MOU shall be September 1, 2008 through June 30, 2009.

2.6.[3.6.] Total Enterprise Virtualization

In order to allow IT organizations to remain nimble to the increased complexity of application provisioning and delivery, and to maximize the unused capacity of compute and storage resources, virtualization is key. And while virtualizing servers and storage are obvious targets for optimization, total enterprise virtualization would encompass additional layers, extending to desktop virtualization and application virtualization. Data centers that are able to deliver services dynamically to meet demand will have other virtualization layers as well, such as virtualizing connectivity to storage systems and the network.

The following are characteristics of a dynamic data center:

Enables workload mobility Automatically managed through orchestration Seamlessly leverages external services Service-oriented Highly available

59

Page 60: Data Center Best Practice and Architecture

Energy and space efficient Utilizes a unified fabric Secure and regulatory compliant

Achieving these characteristics requires investments in some of the following key enabling technologies:

1. Server Virtualization

Server virtualization's ability to abstract the system hardware away from the workload (i.e., guest OS +application) enables the workload to move from one system to another without hardware compatibility worries. In turn, this opens up a whole new world of IT agility possibilities that enable the administrator to dynamically shift workloads to different IT resources for any number of reasons, including better resource utilization, greater performance, high availability, disaster recovery, server maintenance, and even energy efficiency. Imagine a data center that can automatically optimize workloads based on spare CPU cycles from highly energy-efficient servers.

Issues to be aware of in server virtualization: licensing, hardware capabilities, application support, and administrator trust with critical applications to virtual platforms.

2. Storage Virtualization

Storage virtualization is an increasingly important technology for the dynamic data center because it brings many of the same benefits to the IT table as server virtualization. Storage virtualization is an abstraction layer that decouples the storage interface from the physical storage, obfuscating where and how data is stored. This virtualization layer not only creates workload agility (not tied to a single storage infrastructure), but it also improves storage capacity utilization, decreases space and power consumption, and increases data availability. In fact, storage and server virtualization fit hand and glove, facilitating a more dynamic data center together by enabling workloads to migrate to any physical machine connected to the storage virtualization layer that houses the workload's data.

3. Automation and orchestration

Storage virtualization is an increasingly important technology for the dynamic data center because it brings many of the same benefits to the IT table as server virtualization. Storage virtualization is an abstraction layer that decouples the storage interface from the physical storage, obfuscating where and how data is stored. This virtualization layer not only creates workload agility (not tied to a single storage infrastructure), but it also improves storage capacity utilization, decreases space and power consumption, and increases data availability. In fact, storage and server

60

Page 61: Data Center Best Practice and Architecture

virtualization fit hand and glove, facilitating a more dynamic data center together by enabling workloads to migrate to any physical machine connected to the storage virtualization layer that houses the workload's data.

The best automation and orchestration software can reduce the management complexity created by workload mobility. Workflow automation and orchestration tools use models and policies stored in configuration management databases (CMDBs) that describe the desired data center state and the actions that automation must take to keep the data center operating within administrator-defined parameters. These tools put the IT administrator in the role of the conductor, automating systems and workload management using policy-based administration.

4. Unified Fabric with 10GbE

10 Gigabit Ethernet (10GbE) is an important dynamic data center-enabling technology because it raises Ethernet performance to a level that can compete with specialized I/O fabrics, thereby potentially unifying multiple I/O buses into a single fabric. For example, SANs today operate on FC-based fabrics running at 2, 4, and now 8 Gb speeds. Ethernet, at 10 Gb, has the performance potential (i.e., bandwidth and latency) to carry both SAN and network communication I/O on the same medium.

Just like 1GbE and Fast Ethernet before it, 10GbE will become the standard network interface shipped with every x86/64 server, increasing host connectivity to shared resources and increasing workload mobility. Using 10GbE as a universal medium, administrators can move workloads between physical servers without worrying about network or SAN connectivity.

The development of Converged Enhanced Ethernet, or Cisco’s version called Data Center Ethernet, allows for lossless networks that can do without the overhead of TCP/IP and therefore rival Fibre Channel (FC) for transactional throughput. iSCSI is already a suitable alternative for many FC applications, but Fibre Channel over Ethernet (FCoE) should close the gap for those systems that still cannot tolerate the relative inefficiencies of iSCSI.

One of the key benefits of a unified fabric within the data center is putting the network team in the role of managing all connectivity, including the storage networks, which are often managed by the storage administrators whose time could be better spent on managing the data and archival and recovery processes rather than the connectivity.

5. Desktop and Application Virtualization

6. Cloud computing

61

Page 62: Data Center Best Practice and Architecture

Not for everything, dependent on service offerings, APIs

Abstraction layer

Internal and external

[Key concepts extracted from “The Dynamic Data Center” by The Burton Group]

2.7.[3.7.] Management Disciplines2.7.1.[3.7.1.] Service Management

2.7.1.1.[3.7.1.1.] Service Level Agreements2.7.2.[3.7.2.] Project Management2.7.3.[3.7.3.] Configuration Management2.7.4.[3.7.4.] Data Management

2.7.4.1.[3.7.4.1.] Backup and Recovery

One of the essential elements of an effective business continuity plan resides within backup and disaster recovery infrastructure component. While the technical issues pertaining to hardware and software are critical to the implementation of an effective backup and disaster recovery plan, well written standards and policies are the lynchpin of a successful backup and recovery program deployment. In this regard, development of backup and disaster recovery standards and policies are responsibility of enterprise governance. In doing this, the Chancellor’s Office must make decisions about the classification and retention of business information. This is not a trivial task as evidenced by the complex legal compliance issues posed by Family Educational Rights and Privacy Act (FERPA), The Health Insurance Portability and Accountability Act (HIPAA), Sarbanes-Oxley (SOX) statutes present a moving target with severe penalties for non-compliance.

1. Assumptions:

a. Budget constraints drive the technological solution for backup/recovery.

b. RPO/RTO requirements are driven by business and legal constraints (FERPA, HIPAA, SOX, etc.) and should be defined by enterprise governance.

c. The requirements defined by the governance process will be a critical factor in establishing recovery point objectives (RPO) and recovery time objectives (RTO) and must be congruent with budget.

62

Page 63: Data Center Best Practice and Architecture

d. RPO and RTO have a major influence on the backup/recovery technological solution.

e. The backup window, i.e., the time slot within which backups must take place (so as to not interfere with production) is a significant constraint on the backup/recovery design.

f. A tiered approach to the backup/recovery architecture mitigates budget and backup window constraints.

g. Sizing of the tiers is driven largely by the retention and recovery time objectives and corresponding budget constraints.

h. Lower tiers generally set expectations for faster recovery time and lower cost of implementation.

i. Sizing of tiers of backup/recovery storage should be as large as is practicable. Subject to budget constraints, as much storage as possible at each tier means lower RPO/RTO.

2. Best Practices

a. Work with CSU and SSU governance bodies to establish retention requirements for electronic media. Review and insure that established retention requirements comply with state and federal legal requirements.

b. Work with CSU and SSU governance bodies to establish business continuity and disaster requirements.

c. RPO and RTO objectives will have a significant impact on the design of the backup and disaster recovery plan: higher expectations for RPO and RTO will drive the costs of the requisite technological design.

d. The backup/recovery architecture should be a tiered design consisting of:

Tier 1

The first tier of storage is volume snapshots for immediate recovery under user control. This typically is referred to as “snap reserve” and is set aside when the volume is configured.

User control at tier one facilitates restoration of backup files without support from operations staff.

Tier 2

63

Page 64: Data Center Best Practice and Architecture

The second tier of online storage is a disk target for backups such as a virtual tape library (VTL). This would be the target of system backups which more effectively utilize the available backup window. The sizing of tier 2 will drive the availability of the backup datasets on the VTL. The higher the capacity of the disk target, the longer these backup datasets can be retained. Recovery time from disk is much faster that other archive media such as magnetic tape and hence, can support more aggressive recovery time objectives. De-duplication should be employed to reduce the footprint of the backup dataset.

Tier 3

The third tier is deployed for longer term archival of backup datasets. Tier 3 strategies can be disk-based but budget constraints often rule out disk based solution. Magnetic tape solutions are usually more economical and the chosen media for archival systems.

e. Magnetic media stored off-site should be encrypted using LTO-4 tape drives and a secure key management system. Key management is vital to ensure timely decryption. This is particularly true during a disaster recovery process when magnetic media must be utilized to recover on a remote site. Without effective and timely key management, the encrypted backup tapes are useless.

f. A copy of encrypted full backup datasets should be stored at another CSU campus serviced by a different power grid and if possible in a different seismic zone at a minimum in a different earthquake fault zone as established by the California State Geologist. The schedule of remote backup datasets will be determined by the recovery point objective (RPO) established by the CSU governance body. The movement of and tracking of the encrypted backup datasets will be defined in a memorandum of understanding between the sister campuses who engage in the reciprocal agreement.

g. For more aggressive recovery time objective requirements, a WAN-based remote backup system should be employed. While the cost of a WAN-based solution is significantly higher than a magnetic media solution, disaster recovery would be much faster. In addition, a WAN-based system could also dove tail into a high availability architecture where the backup datasets could feed redundant systems on the sister campus and provide for failover in the event of an outage in the primary datacenter.

2.7.4.2.[3.7.4.2.] Archiving2.7.4.3.[3.7.4.3.] Hierarchical Storage Management

64

Page 65: Data Center Best Practice and Architecture

2.7.4.4.[3.7.4.4.] Document Management2.7.5.[3.7.5.] Asset Management

2.7.5.1.[3.7.5.1.] Tagging/Tracking2.7.5.2.[3.7.5.2.] Licensing2.7.5.3.[3.7.5.3.] Software Distribution

2.7.6.[3.7.6.] Problem Management2.7.6.1.[3.7.6.1.] Fault Detection2.7.6.2.[3.7.6.2.] Correction2.7.6.3.[3.7.6.3.] Reporting

2.7.7.[3.7.7.] Security2.7.7.1.[3.7.7.1.] Data Security2.7.7.2.[3.7.7.2.] Encryption2.7.7.3.[3.7.7.3.] Authentication2.7.7.4.[3.7.7.4.] Antivirus protection2.7.7.5.[3.7.7.5.] OS update/patching2.7.7.6.[3.7.7.6.] Physical Security