Transcript
Page 1: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 1

Undulator System Components Status

Dean Walters

Page 2: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 2

Undulator System Components Status

Components

Vacuum ComponentsChamber

Quad Spool

Bellows

EVAC Flanges

DiagnosticsRFBPM

Beam Finder Wire

Beam Loss Monitor

Page 3: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 3

Vacuum Chamber End bi-metal flange welding

From:

E Trakhtenberg

G Weimerslage

Page 4: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 4

Vacuum ChamberGraphical Display of Surface finish Data

Z' and X' Data of Delivered Chambers

0

5

10

15

20

25

0 10 20 30 40 50 60

X' (mrad)

Z' (

mra

d)

Series1

Very Desirable

Acceptable

Should be Avoided

From:

E Trakhtenberg

G Weimerslage

The average of all vacuum chambers is 14.86 mrad in Z′ and 35.14 mrad in X′, the rms of Z’ is 15.5 mrad and X’ is 36.9 mrad. Selecting the best 33 chambers yields an rms for Z’ of 13.9 mrad and X’ of 34.2 mrad. Extrusions 7, 10, 16, 28 and 35 were sacrificed to verify surface finish in the middle of the extrusions

15.5

36.9

Page 5: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 5

Quad Spool

DesignFlexible mini-bellows

Surface finish measurements of the central tube show a roughness of Sq=.18 µmIssue with aluminum plating covering the seal face of the EVAC flange, the vendor has addressed this during the course of the production run.Fifteen units have now been shippedThe production run is due to be complete by the end of June

Page 6: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 6

Bellows Module

Initially the supplier had problems with the welding of the SST adapter to the flange. The supplier solved the problem by using the micro-TIG welding process.All (35) units have assembled, baked, packaged, and shipped to SLAC. The last group went to SLAC on 6 June 2008

Page 7: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 7

EVAC Flange SystemFlange Permeability

Flanges from the manufacturer have been found to have a high (1.21) magnetic permeability.Testing has shown that while the permeability is high it will not interfere with devices in the beamline.

Flange Sealing ExperienceSLAC has started to assemble girders and has had to make vacuum seals using EVAC Flanges.Their initial results have been good and bad.

One thing that has been seen is that the pits in the copper gaskets are thought to be a source of leaks.ANL is now inspecting all gaskets for pits before sending to SLAC.

SLAC is experiencing what ANL went through before consistent results were achieved.

Through testing at ANL it was found that lubrication of the chain clamp is important, ANL is using Dicronite lubricate on all chains in the Undulator Vacuum System.

Page 8: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 8

BFW Assembly Mounted on Adjustable Support

Adjustable Mounting Support

(Modified since) Vacuum Pump Connector (2.75” Conflat Flange)

Card Position Monitor (Limit switches)

Air Supply Shut Off Valve

Pneumatic Solenoid Valve

Precision Screw

Electrical Connectors for Wire Signals

Vacuum Chamber Connection Flange

(NW-50 CeFix w/Clamp)

Beam Port

Pneumatic Cylinder

Alignment Fiducials

Frame

Compression Spring Positioner

Potentiometer

Housing

Assembly model courtesy: J. Bailey, ANL

Page 9: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 9

Moving Slide Assembly (Solid Body)

Cylinder BoreFixed to Frame

Kinematic Stop Bottom Plate

Secured to Slide Block

Kinematic Stop Top PlateFixed to Frame

(Adjustable using precision Screws)

Electrical Connector and Feedthrough

Secured to Slide Rod

Top of Return SpringFixed to Frame

Slide BlockSecured to Slide Rod

Card Mount BlockSecured to Slide Rod

Assembly model courtesy: J. Bailey, ANL

Page 10: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 10

Revised Design

Precision Screw

Spring Loaded

Positioner

Locking Screw with Lock Washer

Clearance between slide rod and frame

Top Kinematic Plate attached to

Frame

Frame

Precision Screws

Assembly model courtesy: J. Bailey, ANL

Page 11: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 11

Beam Finder WireRepeatability Testing

Page 12: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 12

Repeatability Test BFW S#04Sensor Readings

-30

-20

-10

0

10

0 20 40 60 80 100

Cycles

Dis

plac

emen

t (M

icro

ns)

Pt. C

Pt. BPt. A

Repeatability Test BFW S#04Calculated Displacements at Card Centerline

-10

0

10

20

30

0 20 40 60 80 100 120

Cycles

Dis

plac

emen

t (M

icro

ns)

Horizontal

Vertical

“Keyence” Displacement Sensors (Typ.)

Repeatability Test Arrangement

BFW Repeatability Test Arrangement and Results

Physics Requirements: 65 Micron Horizontal & 30 Micron Vertical (RMS)

Page 13: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 13

Production of the BFW

Page 14: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 14

Vacuum Conditioning

Page 15: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 15

Beam Finder Wire Status and Schedule

Page 16: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 16

RFBPM Production Altair End Caps

Production End Caps are in spec electrically and mechanically Problems with polishing resolvedProduction ramping up with 10 sets first received 4/22/08

Measurement

LCLS BPM End Caps #1LCLS BPM End Caps

#2

RMS (nm)

Sa (nm)

PV (nm)

RMS (nm)

Sa (nm)

PV (nm)

1 21.9 17.3 411 45.7 30.6 2066

2 23.5 18.6 659 48.6 32.5 1898

3 23.6 18.9 548 43.0 29.4 1674

4 23.9 18.7 433 47.9 33.2 1880

Average 23.2 18.4 513 46.3 31.4 1880

Page 17: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 17

K1 K2

Au-GeAu-Sn

Au-GE

Au-SnH2

Sn-Ag-Cu

K1

K2

Order of Joining

Order of Joining

Single Piece Transitions

K2 K1

Au-CuAu-Ge

Au-Sn

Au-GeAu-SnH2

Sn-Ag-Cu

Au-Sn H2

Sn-Ag-Cu

This allows windows to be jointed, tested, and selected before joining

to the cavity body.

Strongest Design

Solder Joint Considerations

Page 18: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 18

Joining Window to Transition

Use of a Moly ring limits the expansion of the copper which then limits the compression of the glass window.

Page 19: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 19

Brazing Fixture

This is the body mounted in the fixture for joining the Transitions to the Body

Page 20: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 20

RFBPM Windows QC Results

Page 21: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 21

Monitoring Windows Quality

Windows Process Chart

0

2

4

6

8

10

12

8 9 10 11 12 13 14 15

Group Number

Th

ickn

ess

(mil

s)

0

1

2

3

4

5

6

7

8

9

10

No

. o

f D

efec

ts Minimum

Maximum

Average

Defects

Page 22: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 22

Repair of Soldered Assembly

Page 23: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 23

BPM Window Statistics

Transition and window soldered with Georo filler materialSub Assemblies are Vacuum checked before brazed to bodyIn the last run of windows being brazed to transitions there were 11 of 13 defect free parts made.Transitions are soldered with Orotin to the bodies

Page 24: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 24

RFBPM Status and Schedule

Page 25: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 25

Beam Loss Monitor

Beam Line Detector:

Detailed and Assembly Drawings:(engineering review and tolerancing).

Detector Head.

Detector BFW Mounting Bracket.

Undulator Motion Tracking Adapter.

Page 26: D Walters Undulator System Componentsdrw@aps.anl.gov June 17, 2008 1 Undulator System Components Status Dean Walters

D Walters

Undulator System Components [email protected]

June 17, 2008 26

Conclusions

Except for the Beam Loss Monitor all other components are in productionItems that have completed production

Vacuum ChamberVacuum Chamber SupportBeam Finder Wire SupportBPM SupportBellows Module : Final Unit 6/6/08

Items still in the process of productionBPM cavity - (36% complete) : Final Unit 7/31/08Beam Finder Wire - (45% complete) : Final Unit 7/8/08Quad Spool - (45% complete) : Final Unit 6/24/08Long Break Spool and its support : Final Unit 6/18/08


Recommended