Cryogenics Group Oak Ridge, TNFebruary 3–4, 2003
Cryogenic Engineering Conference
C2-B-03Spallation Neutron Source
Cryogenic System Installation
D.R. Hatfield, D.E. Richied, M.P. Howell, Oak Ridge National LaboratoryD.M. Arenius, V. Ganni, Thomas Jefferson National Accelerator Facility
September 24, 2003
Cryogenics Group Oak Ridge, TN2
February 3–4, 2003
Installation
• CHL – Helium Purifier System– Helium Storage Tank System– Helium Process Piping– Helium Compressor System– 4.5K Cold Box– 2.1K Cold Box– Utility System
Cryogenics Group Oak Ridge, TN3
February 3–4, 2003
CHL Equipment Layout
Cryogenics Group Oak Ridge, TN4
February 3–4, 2003
•– Heli um Ga s Stora ge Pi pin g
Heli um ga s pi pin g t o 8 tan ks ( T rin ity supplie d) with 8 va lve rac ks ( J labsupplie d)C ross- ove r pipin g ra c k (J lab suppl ie d)High pre ssure he li um un l oa din g sta tion (J lab suppl ie d)Pi pin g to purif ie r c ol d b ox (J lab supplie d), 2 rec ov e ry c ompre ssor s (J lab supplie d), an d the in te rface to the c ross- ove r pi pin g rac k
– C ompre ssor R oom Pi pin gHeli um ga s pi pin g t o/ f rom the ma in compre ssors ( PH PK supplie d) t o the trench pi pin g an d t o the South wa ll pi pin gOil pi pin g t o th e c ompre ssors an d oil mana ge men t pi pin g to the trench pi pin g an d t o the South wa ll pi pin gWate r pi pin g to/ f rom the c ompre ssors t o the trench pi pin g an d ex ten sion s t o CTF (f ut ure) an d t o th e c ol d b ox room Heli um ga s pi pin g t o/ f rom the ga s ma na ge men t va lve rac k (J labsupplie d) t o th e trench pi pin g Heli um pi pin g ex ten sion s wi th isola tion va lve s t o C TF in the trench pi pin g
Cryogenics Group Oak Ridge, TN5
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN6
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN7
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN8
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN9
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN10
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN11
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN12
February 3–4, 2003
Installation
• Syste m Brea kdown – c on tinue d– South Wall Pipin g
Heli um ga s pi pin g t o/ f rom the c ompre ssor room pi pin g an d t o/ f romthe c ol d b ox room an d t o the oil re mova l eq ui pme n t (Jlab supplie d)Oil pi pin g f rom the oil re mova l eq ui pme n t t o the c ompre ssor roompi pin gHeli um ga s pi pin g t o/ f rom the a mb ient va porize r (J lab suppl ie d) in te rfacin g be twe en the c ol d b ox and c ompre ssors an d t o the va poriz e r va lve rac k3 a t mh eli um suppl y di strib ution
– C ol d Box R oom Pi pin g4.5K Main C old Box
– Rigging and installation of the 4.5K cold box (supplied by LindeBOC)
– Reassembly of the cold box and removal of shipping braces (Linde)– Helium gas piping to/from the cold box to the compressors via south
wall piping system– Helium gas piping to the recovery compressors for cool down and
cleanup of the system and the beds in the cold box and the 3 atmhelium supply
Cryogenics Group Oak Ridge, TN13
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN14
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN15
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN16
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN17
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN18
February 3–4, 2003
Installation
• Syste m Brea kdown – c on tinue d– Instrument air and water piping to the cold box
Sub -A tmosph e ric C old Box ( 2.1K Col d Box )– Rigging and installation of the 2.1K cold box (Jlab supplied)– Rigging and installation of frequency converters and magnetic
bearing cabinets (Jlab supplied) and power cables– Loading cold compressors and adjusting (SNS/Jlab/Air Liquide)– Leak check of the cold box vacuum shell– Helium gas piping to recovery compressors for cleanup/cool down
of the system and 3 atm supply– Vacuum piping connections– Instrument air and water piping
Suppl y an d Return Expan si on Can s– Rigging and installation of the Supply expansion can– Rigging and installation of the Return expansion can– Guard vacuum piping connections to the vacuum pump skid (Jlab
supplied)– Relief and cool down piping connections to the return expansion
can
Cryogenics Group Oak Ridge, TN19
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN20
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN21
February 3–4, 2003
Installation
• System Breakdown – continued Guard Vacuum System
– Rigging and installation of the vacuum pump skid (Jlab supplied)– Piping to the vacuum skid from the tunnel piping– Instrument air and water piping
– Utility EquipmentLHe dewar, U-tubes (Jlab supplied) LN2 dewar (Chart supplied) and the LN2 distribution piping (Jlab supplied)Instrument air system (Jlab supplied)Water piping to/from and in the cold box room to the compressor roomRecovery compressors (Jlab supplied)Purifier cold box (Jlab supplied)U-Tubes (Jlab supplied)Test Heaters (Jlab supplied) for system verification
Cryogenics Group Oak Ridge, TN22
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN23
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN24
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN25
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN26
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN27
February 3–4, 2003
Installation
Cryogenics Group Oak Ridge, TN28
February 3–4, 2003
Installation
• Pi pin g an d Equi pme n t Pac ka ge s– Heli um ga s st ora ge pipin g– C ompre ssor room pi pin g– South wa ll pi pin g– C ol d b ox room pi pin g– U tility pi pin g
• In sta llati on– Ge ne ra l Spec if ica ti on N o. 79000-A-0010 Rev-02 (Ge ne ra l pi pin g
spec if ica ti on f or SN S CHL heli um ga s, oil re mov a l, gua rd v ac uum,in strumen t a ir an d c oolin g wa te r pi pin g syste ms) i s use d to c on trol a ll the wa r m pi pin g
– De ta iled spec if ica ti on s a re use d t o c on trol each of the in sta lla ti on pac ka ge s li ste d ab ov e
– F or Syste m A cce pta nce, the f oll owin g In sta lla ti on Chec ks an d Ce rtif ica ti on s a re to b e pe rf or me d on each in sta lla ti on packa ge
Clean line ss c e rtif ica ti on– Number of times the system has been evacuated and backfilled with
nitrogen
Cryogenics Group Oak Ridge, TN29
February 3–4, 2003
Installation
• System Acceptance - continued– Final moisture content in the cold trap (should be none)– The ultimate vacuum at the pump in the connected system– The vacuum pump blank off (ultimate) pressure
Pressure test certification– Is the pressure test complete as per the specification?
Leak test certification– Is the leak test complete as per the specification?
Safety check certification– Are all the relief devices verified for their set pressure?– Are all the relief devices installed?– Are all the temporary plugs removed?
QA department check certification– Are all the QA requirements met for this sub system?
Safety Committee check certification– Are all the safety requirements met for this sub system, which
includes mechanical and electrical?
Cryogenics Group Oak Ridge, TN30
February 3–4, 2003
Installation
• Helium Gas Storage Piping– Connect the 8 helium storage gas tanks and the other
associated valve racks and piping as followsPrepare the gas tanks per specification 79000-A-0020 Rev-00 (SNS Direction for Helium Gas Storage Area)Install the piping per specification 79000-A-0011 Rev-00 (SNS CHL Helium Gas Storage System Piping Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to the commissioning group
Cryogenics Group Oak Ridge, TN31
February 3–4, 2003
Installation
• Compressor Room Piping– Connect the 6 helium compressors, gas management and
the other associated piping as followsInstall the piping per specification 79000-A-0012 Rev-00 (SNS CHL Helium Compressor Room Piping System Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to the commissioning group
Cryogenics Group Oak Ridge, TN32
February 3–4, 2003
Installation
• South Wall Piping– Connect the helium compressor piping to the oil removal and
then to the 4.5K cold box piping and the other associated piping as follows
Install the piping per specification 79000-A-0013 Rev-01 (SNS CHL South Wall Piping System Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to the commissioning group
Cryogenics Group Oak Ridge, TN33
February 3–4, 2003
Installation
• Cold Box Room Piping– Connect the 4.5K cold box, 2.1K cold box, guard vacuum
system and the other associated piping as followsInstall the piping per specification 79000-A-00xx Rev-0x (SNS CHL xxxxxx Piping System Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to the commissioning group
Cryogenics Group Oak Ridge, TN34
February 3–4, 2003
Installation
• Utility Piping– Instrument air system
Install the piping per specification 79000-A-00xx Rev-0x (SNS CHL xxxxxx Piping System Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to thecommissioning group
– Guard Vacuum systemInstall the piping per specification 79000-A-00xx Rev-0x (SNS CHL xxxxxx Piping System Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to thecommissioning group
Cryogenics Group Oak Ridge, TN35
February 3–4, 2003
Installation
• U tility Pi pin g - c on tin ue d– LN2/ GN2 syste m
In sta ll the pi pin g pe r spec if ica ti on 79000-A-00xx Rev-0x ( SN S CHL xxxxxx Pi pin g Syste m Spec if ica ti on)Clean the syste m a s sta te d in the ab ove spec if icati on sC ompl e te the pre ssure check an d lea k chec k a s sta te d in the ab ove spec if ica ti on sPr ov i de the in sta lla ti on check an d the six ce rtif ica ti on s t o thec ommi ssi on ing gr oup
– Purif ie rPurif ie r c ol d b ox
– Install the piping per specification 79000-A-00xx Rev-0x (SNS CHL xxxxxx Piping System Specification)
– Clean the system as stated in the above specifications– Complete the pressure check and leak check as stated in the above
specifications– Provide the installation check and the six certifications to the
commissioning group
Cryogenics Group Oak Ridge, TN36
February 3–4, 2003
Installation
• Utility Piping - continuedRecovery compressor
– Install the piping per specification 79000-A-00xx Rev-0x (SNS CHL xxxxxx Piping System Specification)
– Clean the system as stated in the above specifications– Complete the pressure check and leak check as stated in the
above specifications– Provide the installation check and the six certifications to the
commissioning group– LHe Dewar
Install the piping per specification 79000-A-00xx Rev-0x (SNS CHL xxxxxx Piping System Specification)Clean the system as stated in the above specificationsComplete the pressure check and leak check as stated in the above specificationsProvide the installation check and the six certifications to thecommissioning group