TelanganaS.No. Name of the Policy The Telangana Solar Policy 2015
1 Date of Issue May-152 Applicability 5 years
3 Objective Not Defined
4 Nodal Agency
5 Othe Important Agencies Solar Policy Cell, TSSPDCL, TSNPDCL, TSTransco, TSERC
6 Eligibility Criteria Not Defined
7 Financial Criteria Not Defined
8 Targets (MW) Not Defined
Telangana New & Renewable Energy development corporation
9 Implementation Plan
i. Not Defined
ii. Not Defined
iii. Solar plant for captive use Allowed
1. Solar Power Projects: for sale to Discom and for 3rd party sale2. Captive/Group captive generation3. Solar Roof top projects: off-grid and grid connected4. Off grid applications5. Projects of MNRE/GoI schemes6. Solar Parks
Solar Power Plants to Fulfill RPO/RGO
Solar Power Plants for 3rd Party sale
iii. Development of Solar Park
iv. Not Defined
v. Not Defined
vi. Rooftop: Sale to DISCOM Not Defined
vii. Rooftop: Sale to 3rd Party Not Defined
viii. Rooftop: Captive consumption
1. Solar Park: A). Characterized Concentrated zone for development of solar power projects.B). Solar park implementing agency (SPIA) will be formed by state governmenr. + central agency + Private sector participation or by state government + private sector participationC). SPIA will facitilate : Power evacuation + water arrangements + internal roads + administrative facilitySolar.D). Solar Park will cover: Solar power projects, Manufacturing units + R&D Centers + Training centers + Financial institutions.E). State will provide all facilities & incentives of central governement to participants of solar parks
Solar Power Plant under REC Mechanism
Solar power plant on Canal Top
1. All Incentives of MNRE & JSM2. The consumers are free to choose either net or gross meter option for sale of power to the DISCOMs under this policy.3. Tariff: Average cost of service of DISCOM at 11KV4. Exemption from Distribution charges & losses5. Online Application to DISCOM
ix. Decentralized/ and Off-Grid Solar Pumpsets
x. Project under bundled power Can be a part of solar park, not defined explicitly in the policy
10 Incentives
1). Timeline: 2 years from application, within time limits of PPA2). Approvals: can be taken from Solar policy cell (SPC) through single window clearance. Fee: Rs. 10,000/MW with cap of Rs. 2,00,00/MW.3). Deemed conversion to Non-Agricultural land status: by paying a conversion charge to Solar policy cell (SPC).4). Exemption from Land ceiling Act for firm orders/PPA/Successful bids. Standard land requirement : 5Cr./MW.5). Wheeling & transmission charges: Exempted for Captive and in case of third party sale charges will be applicable as it is.6). Banking: a). 100% allowed for all captive & OA, b). Banking Chages: 2% of energy, c). Baned units cannot be resumed/reedemed in peak months, d).unutilised banked energy shall be deemed puchase by DISCOMs at Avg. pooled purchased coste). Energy from synchronisatio to COD will be puchased by DICOM at the 1st years's tariff.7). electricity Duty: Will be waived for the new manufacturing and ancillaries of the solar project.8). CSS: Intra state: 100% exemption 9). Development charges & lareyut: Shall be payable @Rs. 25,000 per acre to respective Panchayat10). Refund of VAT:- After for 5 years11). Stamp duty:- 11). OA: Allowed for Intra-state transaction12.) PCB clearance: - Have to follow the procedure of PCB
11 Role of Nodal Agency
12 Not Defined
13 Not Defined
14 Not Defined
15 Single Window Clearance Single Window Clearance set up by TSDISCOM
16 Fees & Charges
Not Defined
The Nodal agency shall be responsible for: 1. Availing subsidy for solar rooftop systems,2. Solar pump sets, as per MNRE guidelines and shall co-ordinate with MNRE/Solar Policy Cell (SPC) of Discom
Procedure for Registration/approvals
Procedure for Interconnectivity
Solar Power Purchase obligation
i. Competitive Bidding (Rs.)
Not Defined
ii. REC (Supplying at APPC)
iii. Captive
iv. IPP for 3rd party sale
v Bundled power
vi Rooftop project (5-50 Kp)
vii Rooftop project (Above 50 Kp)
1 Land Allottment
18 Wheeling Charges
19 Wheeling Losses
20 Banking Charges 2% in terms of Energy
21 Cross Subsidy Surcharge Exempted
Exempted for Captive users, for 3rd party sale: TSSPDCL: 15.71 & TSNPDCL : 13.74 Rs./KVA/Month
Exempted for Captive users, for 3rd party sale: TSSPDCL :3.99% and TSNPDCL : 4.00%
KarnatakaThe Karnataka Solar Policy 2014-2021
22/05/20147 years
KREDL
2000 MW by FY 2021
1. 2000 MW by year 2021. i.e. FY 20202. Promote roof top generation3. Promote R&D
High Level project approval committee: Approval and overseeing the projects of more than 50 MW.
Grid Connected Utility Scal Project: Any Individual, firm, society, Institutions, Registered companies and Public utilitiesGrid Connected Roof top: All Individual, Institutional, Commercial buildings, Govt. Buildings, Owners, Industrial Units, Firms, Reistered companies, Public utilitiesOff Grid: Any Individual
Competitive Bidding: 2Cr./MW; REC: 50 Lakh/MW, 3rd Party Sale: 2Cr/MW
Grid Connected Utility Scal Projects: Minimum 1600 MW for Sale to ESCOMsGrid Connected Roof top Projects: Minimum 400 MW grid connected roof top generation by 2018FY 2015: Utility scale 350 MW, Roof Top: 100 MWFY 2016: Utility scale 150 MW, Roof Top: 100 MWFY 2017: Utility scale 150 MW, Roof Top: 100 MWFY 2018: Utility scale 150 MW, Roof Top: 100 MWFY 2019: Utility scale 200 MWFY 2020: Utility scale 200 MWFY 2021: Utility scale 200 MW
Bids will be invited by KREDL for projects more than 3 MWp under 2 categories " with AD" and "Without AD"
i. 3rd Party sale from solar pv project is allowedii. RECs cannot be availed in case of 3rd party sale
1. Promotion of distributed generation through small solar parks:Gov. Of Karnataka will provide financial assistance of Rs. 1Cr per solar park of area not less than 100 Acres through a PPP model2. Promotion of Integrated solar Parksi. GoK contemplates to create private land banks owned by individual farmers, group farmers, association at lease rates.
Not defined
Developers are required to pay a facitilation fees to KREDL, sale to ESCOMs will be at APPC and the project shall be monitored by ESCOMs and KPTCL.Minimum Capacity allowed: 1 MWp
GoK supports deployment of grid connected projects on the canal corridor
i. No, Minimum capacity limit on captive solar generation and,ii. REC can also be availed on Captive Generation
Through net meteringGov. Of Karnataka to amend building bye-laws
through Net Metering onlyGov. Of Karnataka to amend building bye-laws
Allowed for central and karnataka state owned PSUs
i. Distributed Generation by Land owning farmers: 1 MWp to Max 3MWp per owner,ii. Target was 300 MW on 1st come 1st serve basis.Iii. Street light, rooftop with battery, irrigation pump set etc.
i. Exemption from Entry Tax, Stamp duty, Registration charges, ii. Contract demand reduction to OA consumer, iii. Incentives scheme launched by MNRE,iv. Deemed conversion of land for solarv. No restriction on purchase of Land.vi. No waiting needed for approval for conversion of gricultural landvii. Exempted from any clearance from PCBviii. Reduction of supervision charges to 5%
Approval & Registration
Not defined
Not defined
developer in consultation with KPTCL shall finalize the location of receiving substation. Connectivity can be allowed at 400/220/110/66/33/11 KVsubstation
% of Solar on Total Consumption:FY 2015: 1.5%FY 2016: 1.75%FY 2017: 2.00%FY 2018: 2.25%FY 2019: 2.5%FY 2020: 2.75%FY 2021: 3.0%
Application Fee: 10,000/Project, Facitilation Fee: 1 Lac/MW, PBG: 10Lakh/MW
Application Fee: 10,000/Project, Facitilation Fee: 20,000/MW, PBG: 5Lakh/MW
Application Fee: 10,000/Project, Facitilation Fee: 25,000/MW, PBG: 3Lakh/MW
Application Fee: 10,000/Project, Facitilation Fee: 25,000/MW, PBG: 5Lakh/MW
Application Fee: 10,000/Project, Facitilation Fee: 10,000/MW, PBG: NA
Application Fee: 1,000Project, Facitilation Fee: 2,000/Project, PBG: NA
Application Fee: 10,000/Project, Facitilation Fee: 5,000/Project, PBG: NA
1. GOK contemplates deemed conversion of land for solar by amending section 95 of the Land reform act.2. Dy. Commissioner have the power to approve purchase of land under sectio 109 of Land reforms Act3. No need to wait for formal approval for Land conversion4. 10% Barren Land reserved for KREDL
Exempted for 10 years for Plants commissioned between 1st April 2013 till 31st March 2018
Exempted for 10 years for Plants commissioned between 1st April 2013 till 31st March 2018
Exempted for 10 years for Plants commissioned between 1st April 2013 till 31st March 2018
Exempted for 10 years for Plants commissioned between 1st April 2013 till 31st March 2018
Andhra PradeshAndhra Pradesh Solar Power Policy 2015
Feb-155 Years
NEDCAP
Not Defined
Not Defined
5000 MW by 2020
i. To target a minimum total solar power capacity addition of 5,000 MW in the next five years in the Stateii. To develop solar park(s)iii. To deploy solar pump set
"All registered companies, Government entities, partnership companies/ firms, individuals and all consumers of APDiscom(s) will be eligible"
Allowed, sale of electricity within and outside the state
i. Sale of power to AP Discom(s)ii. Third party sale / Captive useiii. Solar Parksiv. Solar Rooftop Projects – Gross/Net Meteringv. Solar pumpsets
"the Discoms would procure around 2,000 MW of solar power capacity in a phased manner within the next five (5) years".
i. The Govt. of A.P will develop Solar Parks with capacity additions of around 2,500 MW in the next five (5) yearsii. State will help facilitate in building up the necessary infrastructure like power evacuation, water requirements and internal roads.iii. Solar Park shall consist of: Solar Power Projects, Manufacturing Zones, R & D and Training Centres.iv. SPV will be established for development of infrastructure and management of Solar Park.v. SPV will develope the necessary infrastructure from the funds received from GoI and GoAP.vi. Development charges have to be paid by developers
REC available for captive solar plants and 3rd party sale
Allowed, captive use within the state only
Not Defined
Same as Sale to DISCOM
Not Explicitly defined"solar rooftop systems on public buildings, domestic, commercial and industrial establishments on gross and or net meter basis"."Maximum 1000 KWp at a single location will be permitted"."All incentives of MNRE are allowed. NEDCAP is the Nodal agency".
Not Defined
50,000 solar powered pumpsets will be operational in the State in the next five years
i. Solar plants for captive & 3rd party sale shall be exempted from transmission and wheeling charges.Ii. No distribution losses applicable for injection at 33KV & belowiii. 100% banking allowed @ 2% energy as chargesiv. Drawals from banked energy shall not be permitted from 1st Apr to 30th June & 1st Feb to 31st March of each financial year and during peak hours of the dayv. Energy before COD will treated as deemed banked energyv. Allowed for Intr-state transactionvi. exemption from ED for captive consumption, sale to DISCOM & 3rd party salevii. CSS exempted for 3rd party saleviii. Contract demand reduction allowed on 3rd party saleix. Deemed Industry statusx. Deemed PPP status for projects selling power to DISCOMsxi. Deemed NA status xii. Must run status for solar power plants: deemed schedulexiii. Exemption from NOC rewuirement from Pollution control board.
Not Defined
Not Defined
Shall be developed by NREDCAP
NREDCAP:i. Facilitate in obtaining revenue land – wherever is required.ii. Facilitate in getting power evacuation and/ or Open Accessiii. Facilitate water allocation from concerned departments.iv. Facilitate and process of proposals for availing subsidy for solar rooftop systems as per MNRE guidelines.v. Co-ordinate with MNRE/SECI/APTransco/Discom(s) and any other Central/State agencies in obtaining necessary clearances, approvals, grants and subsidies.
Evacuation line from interconnection point to grid substation to be laid by the APTRANSCO or DISCOM at the cost of the project developer.i. If developer wishes to lay evacuation line by themselves, they can do so by paying the supervision charges to APTRANSCO/DISCOMii. APTRANSCO/DISCOMs to ensure the technical feasibility for evacuation is granted within 21days of applying.
Registration fee of:i. Rs.1000 for capacities upto 5 KWpii. Rs. 5,000 for capacities above 5 KWp to 100 KWpiii. Rs,10,000 for capacities above 100 KWp to 1000KWp andiv. Rs.10,000 per MW for capacities more than 1000 KWp.
Exempted as per policy
Exempted as per policy
2% of Energy
Exempted as per policy
Registration fee of:i. Rs.1000 for capacities upto 5 KWpii. Rs. 5,000 for capacities above 5 KWp to 100 KWpiii. Rs,10,000 for capacities above 100 KWp to 1000KWp andiv. Rs.10,000 per MW for capacities more than 1000 KWp.
1. Deemed NA status2. Developer have to acquire land3. GoA will allot land as per Gov. Policy
RajasthanRajasthan Solar Energy Policy 2014
Oct-14Till new policy
To develope 25,000 MW of solar power
RREC
Not defined
Not defined
25000 MW in Rajasthan
State level screening committee (SLSC)State leve empowered committee (SLEC)
Through Competitive bidding
Solar Plants sanctioned under NSM schemeSolar Plants for sale to DISCOM to fulfill RPOSale through REC mechanismSolar plants for captive & 3rd party saleSolar rooftop plantsDecentralized & off-Grid solar applicationDevelopment of Solar Park
No maximum cap on setting up of plant for 3rd party sell and REC will also be available on 3rd party sale
No maximum cap on setting up of plant for captive consumption and REC will also be available on captive use
REC Allowed for captive and 3rd party sale of solar power
Not defined
Not defined
Not defined
Net metering mechanism only
Solar Parks by RREC: 1. RREC will be the nodal agency. 2. To develope infrastructure and management a SPV has been established which is a subsidiary of RRECDevelopment of solar park by Private Developers:1. An applicatio shall be submitted to RRECL with a processing fee @ 5000/Hectare + 10Lac + service Tax2. No celling limit in buying agricultural land3. Gov. land can also be allotted to the bidder.4. Joint ventures are allowed
Not defined
1. Industrial incentives available2. WRD will allocated power to the Solar power project from nearest water source3. SPV projects are kept under green category i.e. NOC from PCB can be obtained in 15 days4. Banking as per RREC5. Wheeling losses & charges as per RREC
Partially defined
Not defined in the Policy
Not defined
Registration & Approval of projects.Facitilation of Gov. Land & WaterFacitilating approval for evacuationFacitilation of excution of PPA/WBA
In accordance with RVPN @ 400, 220, 132 & 33/11 KV network
11 Paise/Kwh
3.80% of the energy injected
Not defined
For all Solar power projects: for project <= 10 MW: Rs.50,000/MWFor projects > 10 MW & <= 50 MW: 5 Lac per projectFor projects > 10 MW & <= 50 MW: 5 Lac per projectFor Projects > 50 MW & <= 100 MW: 10 Lac/projectFor projects > 100 MW: 300 Lac/projectPerformance Guarantee:For sale to 3rd party & captive: Rs. 10lac/MWFor others as per RFS/RFQ or RFP
SPV crystalline: 2.5 Hec/MWSPV crystalline with tracker: 3.5 Hec/MWSPV thin Film: 3.5 Hec/MW
NDS - 0.49 Rs./Unit @EHV and 0.43Rs/Unit @33KVLIP - 0.13 Rs/Unit @ 33 KV
Madhya PradeshMadhya Pradesh Solar Policy 2012
Feb-12Till New Policy
To Promote private players for solar power generation
MP- NRE
MPPMCL & MP TRNSCO
Category I: As defined in the RFQ/RFP of MPPMCLCategory II & III: Everyone is allowedCategory IV: As per NSM scheme
Category I: As defined in the RFQ/RFP of MPPMCLCategory II & III: No financial restrictionCategory IV: As per NSM scheme
Category I: To fullfil RPO of DISCOMsCategory II: No Limit, as per Private PlayerCategory III: No LimitCategory IV: As per NSM Scheme
Targets, Implementation plan as per RFP/RFQ by MPPMCL
Category wise division of solar plants, To take incentives of the policy project needs to be regiseterd under the policy by paying processing fee.Category I : Plants setup to sale power to DISCOM for fulfilling the RPOCategory II: Pants setup for 3rd party sale & captive useCategory III: Plants setup for RECsCategory IV: As sanctioned under NSM
Anyone can setup solar pv project on private land at anytime and for project on Gov. Land developer have to apply in RFP/RFQ by MPNRED
Anyone can setup solar pv project on private land at anytime and for project on Gov. Land developer have to apply in RFP/RFQ by MPNRED
There is a separate policy for solar parks
Not Defined
As per Tender, RFP/RFQ of DISCOMs
Not allowed
Net Metering Policy
Anyone can setup solar pv project on private land at anytime and for project on Gov. Land developer have to apply in RFP/RFQ by MPNRED
Not Defined
Not Defined
1. Surrender of Project: Developer at any time can withdraw the project by forefiteing the PG2. Transfer of the Project: Project can be transferred to anyone , Payment of Rs. 1Lac/MW shall be applicable.3. Exemption from ED & EC4. Subsidy of 4% on wheeling charges in terms of energy by Gov. of MP5. 100% banking allowed @ 2% charges in terms of energy6. Contract Demand reduction allowed for 3rd party, captive & REC sale7. 3rd Party sale allowed8. Industrial status and its benefits9. Entry Tax and VAT exemption10. CDM Benefits11. No need for formal approval from PCB
As per MPERC
in Initial stage, developing by TRIFAC & MP NRE
Project registration & approvalIssuing RFP and RFQ for projects on Gov. LandAssissting in Administrative approvalsPolicy formulation
1. Need administrative approval from MP-NRE2. Approval from CEIG for connectivity3. MPPTCL will provide connectivity at 33KV & above
Exempted ARR per ARR of DISCOM
2% in terms of Energy
Exempted ARR per ARR of DISCOM
Processing Fee: Rs. 1Lac/MWPerformance Gaurantee for Category II & III: Rs. 5Lac/MWPerformance Gaurantee for Category I & IV: as per relevant RFP/RFQ
Land will be allotted to MP-NRE, MP NRE will take the possession and a Land Use permission will be granted to the developer
Subsidy of 4% on wheeling charges:2% in terms of energy will be applicable
HaryanaHaryana Solar Power Policy 2014
Sep-14Mar-17
HAREDA
UHBVNL & DHBVNL
As per Bid document
Equity Investment of Rs. 3Cr./MW
1300 MW by 2022
100 MW to fulfill RPOSolar PV projects under NSM50 MW of rooftop solar
By March 2017, HAREDA shall get installed 100 MW capacity in two phases. In each phase, 50 MW capacities shall be selected through reverse bidding on the levellised tariff fixed by HERC. The entire power from the Solar Power Plant shall be purchased by DISCOMS of Haryana at tariff so discovered.
Allowed. The IPPs shall submit the application along with Feasible Detailed Project Report (FDPR) and processing fee of Rs.20, 000 per MW.
Allowed. The IPPs shall submit the application along with Feasible Detailed Project Report (FDPR) and processing fee of Rs.20, 000 per MW.
REC allowed on APPC sale to DISCOM
Not Defined
The State Government shall also support future projects in the subsequent phases of JNNSM and these projects shall be eligible for incentives given by the state government as per this policy.
i. Exemption from Land use charges, developement charges, scrutiny & infrastructure fee: Town & Country planning shall permit the use of land for solarii. Deemed industry statusiii. Banking of power allowediv.
The State DISCOMs shall purchase power on the basis of reverse auction. Developers can choose the cluster of public and private buildings provided maximum size of cluster could be 1 MW and no roof should be allowed for installation above 500 KW.
For consumption (5KW to 100 KW) any individual, industry etc can set up power plant on net metering basis.The surplus power shall be purchse by DISCOMs at Feed-In-TariffState with MNRE will provide financial assisstance of 40 % of the capital cost
Not Defined
1 village in each district shall be developed as model village in the field of solar energy.For Solar water pumping system, financial assistance @ 60 % of the cost of system to the beneficiaries, for lighting system GoH shall provide 40% subsidy and if beneficiary is a BPL or schedule caste then subsidy will be 80%GoH shall promoted SWHs and solar steam systems
i. Exemption from Land use charges, developement charges, scrutiny & infrastructure fee: Town & Country planning shall permit the use of land for solarii. Deemed industry statusiii. Banking of power allowed
Not available
Invite bids for Grid connected and rooftop power plants, provides project approval and registration
Grid connectivity and wheeling charges.- RE Developers have the option to pay off, in full or twelve equal monthly installments, the actual cost of construction of transmission line up to a distance of 10 KM from the interconnection point to HVPNL / Discoms. During the time till payment of cost of transmission a wheeling charge of 2% shall be levied
2015-16: 0.75%; 0.25% increase till 2019-20: 2.00% then 2020-21: 2.50% and by 2021-2022: 3.00%
0 %, wheeling losses not applicable on RE projects
Banking Charges not defined
Following charges will be applicable for all projects except for Captive use and 3rd party sale:i. 30 Lac/MW in the form of 6 BG of 5 Lac/MW eachii. Non refundable Application fee of 20,000iii. EMD od 5 Lac/MWiv. BG of Rs. 10Lac/MW as a security deposit for Grid connectivity
Developer shall procure wastelands / non – agricultural lands in case of land under panchayat developer have to enter into lease agreement with panchayat
2% by developer in case the power is purchased by the distribution licensee. In all other cases wheeling charges @ 85 Paisa/Unit
Solar Cess of 2 paise/unit shall be levied in the bills of consumers including OA consumers alongwith ED
GujaratGujarat Solar Power Policy 2009
Jan-09Mar-14
Promotion of Clean & green power in the State
Gujarat EnergyDevelopment Agency
Gujarat Power Corporation Ltd.
500 MW till 2014
Any company or body corporate or association of body of individuals, whether incorporated or not, or artificial juridical person, Minimum project capacity of a Solar Power Generators (SPG), in case of solar Photovoltaic (SPV) and Solar Thermal (ST) to be 5 MW each A maximum 500 MW SPG allowed for installationExperience of developing solar project of cost not less than 3.00Cr./MW
Internal Resource Generation: 1.20 Cr/MWNet Worth: 2.00 Cr./MWAnnual Turnover: 4.80Cr./MW
Not Defined
Not Defined
i. Contract Demand reduction upto 50%.Ii.Exemption from Electricity duty and cross subsidy surchargeiii. Deemed Schedulediv. CDM benefits
Done by GEDA and Gujarat Power Corporation Ltd.
1% by FY 2013
Not Defined
i. Identification of suitable locationii. Facilitation in arranging right of way, water and obtaining clearances
At the Network of GETCO at 66KV and above substation. Transmission line from solar substation to the GETCO substation shall be laid by GETCO.
Security deposit of Rs. 50Lac/MW
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
NIL
Not Defined
Exempted
10% of the energy fed for connection above 66KV7% of the energy fed for connection below 66KV
PunjabPunjab New & renewable Source of Energy policy 2012
Dec-12Till new policy
10% RE of total consumption by 2022
PEDA
PSPCL/PSPTCL
Not Defined
1000 MW by 2022
Internal resource generation : Rs. 75 Lac/MWNet worth: Rs. 1Cr./MWAnnual Turnover: Rs. 3Cr./MW
Not Defined
Not Defined
Separate policy for Roof top
Separate policy for Roof top
Separate policy for Roof top
Will be allocated through Competitive bidding based on percentage share of REC price.
Not Defined
PEDA shall facitilate bundled power scheme of MNRE, IREDA and NVVN
i. Banking Allowedii. Merit order dispatch not allowediii. Exemption from ED during construction & operation of projectiv. Exemption on VATv.100% exemption from payment of fee and stamp duty for registration/lease deed charges for the land required for the project.vi. 100% Exemption on entry taxvii. No NOC required from PCBviii. Deemed industrial statusix. Benefits of any relevant policy can be availed
Defined in Annexure 2 of the policy
1.5 % in FY 2015-16 and 2.5% by FY 2019-20
Approval of projectFacilitate clearances related to Land, Water & Evacuation
If the power is proposed to be sold to PSPCL/LICENSEE on Preferential tariff on long term basis, then the transmission line and associated bay at SPCL/LICENSEE grid substation along with ABT compliant Check meters and associated equipment will be provided by PSPCL/LICENSEE. In all other cases, the private developer shall be required to lay its own transmission lines from the switchyard ofits generation facility
State Gov. Shall provide Time bound clearances within 60 days from approval of project by PEDA
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
2% of the Energy fed into the Grid
Bank Gaurantee of Rs. 40Lac/MW after signing of Implementation agreement
Wherever the required land belonging to local bodies/ panchayats is available, the State would encourage the local bodies/ panchayats to provide the land for NRSE projects.
Inter state OA: 5.42%Intra State OA: Wheelin lossess + Charges = 2% of energy fed into the system
Inter state OA: 108 Paisa/UnitIntra State OA: Wheelin lossess + Charges = 2% of energy fed into the system
Industrial: 87 Paisa/UnitCommercial: 107 Paisa/Unit
TamilnaduTamilnadu Solar Energy Policy 2012
Jun-12FY 2015
TEDA
Not Defined
Not Defined
3000 MW solar generation by 2015
Year Wise installation of2013: Utility scale: 750 MW, Rooftop: 100 MW, REC: 150 MW2014: Utility scale: 550 MW, Rooftop: 125 MW, REC: 3252015: Utility scale: 200 MW, Rooftop: 125 MW, REC: 675 MW Total: Utility scale: 1500 MW, Rooftop: 350 MW, REC: 1150 MWTotal 3000 MW solar generation by 2015
Allowed
Not Defined
Not Defined
Not Defined
Shall be developed by competitive bidding1. Park of capacity 250 MW: 1-5 MW sized plants2. Park of capacity 600 MW: 5-10 MW sized plants3. Park of capacity 650 MW: above 10 MW sized plants
Domestic Consumer: a GBI of Rs. 2/unit for 1st 2 years, Rs. 1/Unit from next 2 years and then 0.5Rs./unit for solar rooftop generationSolar rooftop on Gov. Buildings are necessary
Not Defined
Not Defined
i. Tax benefit to manufacturing facility as per industrial policyii. Exclusive solar manufacturing parkiii. Exemption from EDiv. Tax concession as per Industrial policyv. 100% contract demand reductionvi. All statutory clearances via single window clearance system of TEDA
TEDA will facitilate all clearances and approvals
By Single Window clearance system
6% SPO (Starting 3% till Dec. 2013 & 6% from January 2014)
TEDA will facitilate approval of evacuation and connectivity to STU
A single windows clearance system is maintained by TEDA for all statutory clearances
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Wheeling Charges: 30% of Normal Applicable Charges
Not Defined
Not Defined
Mono/Polycrystalline: 3-4 AcreThin Film: 7.5-9 Acres
50% of Applicable CSS:Please click here for details
Uttar PradeshSolar Power Policy Uttar Pradesh (UP) 2013
201331 March 2017
UPPCL
Not Defined
Not Defined
500 MW by March 2017
1.To promote generation and use of clean and green power in the State by harnessing solar energy.2. To put in place an appropriate investment climate which could stimulate private sector participation in development of solar power3. To spread environmental awareness among the general public.4. To contribute to productive use of wastelands5. To enhance skills and create employment opportunities.6. To promote establishment of local manufacturing facilities.7. To build capacity in the State to initiate and sustain, use and effective management of newer technologies.
Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA)
i. Power can be sold to UUPPCL through competitive biddingii. 3rd Party selliii. For Captive use
i. UPPCL shall invite bids from SPDs on combititive bidding basis
GBI & Incentives shall not be available to such developers These plants, who want to avail the incentives as per this policy will have to register with the nodal agency, sign an agreement and furnish a performance bank guarantee till the commissioning of the project as per the time frame given in this policy.
Solar power plants of above 5 MW capacity to be built for captive use will also be eligible for the incentives under this policy either within the premises of the user plant or outside with wheeling arrangement.
Not Defined
Not Defined
i. All the incentives provided in Industrial Policy 2012, shall be applicable for all the solar power projectsii. For projects in Bundelkhand region, all the cost of transmission line shall be born by the STU/DISCOM
Not Defined
Not Defined
i. Calling for competitive biddingii. Creation of Land Bankiii. Facitilation of Gov. Landiv. Assistance in other Infrstructure
Time limit for commissioning of Solar PV projects will be within 13 months and 28 months in case of solar thermal projects from the date of signing of PPA.
The transmission line shall be constructed by the STU or Discom, whoever owns the feed in substation. However the entire cost of transmission including cost of construction of line, wheeling charges, losses etc. will be borne by the Project Developer and will not be met by the STU/Discom.
Nodal Agency will act as single window clearance for Solar Power Projects. Facilitation in all clearances approvals, permissions and consents required from the State Government/its agencies will be the main task of the nodal agency
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Above 11KV: 77.8 Paisa/unitAt 11 KV: 124 Pasia/Unit
Above 11 KV: 2.04%at 11 KV: 3.70%
Above 11 KV: 141.4Paisa/unitAt 11 KV: 87.2 Paisa/Unit
BiharBihar Policy for promotion of New and Renewable Energy Sources 2011
2011
Not Defined
Bihar Renewable Energy Development Agency
State Investment Board
Not Defined
Not Defined
Not Defined
Allowed
Allowed
The project developer shall necessarily offer to supply to Bihar State Electricity Board (BSEB)/Distribution Licensee a minimum of 25% of power generated from the respective New and Renewable Energy project, except for captive projects.
BSEB shall select developers on combititive basis. BREDA & BSIB will be the nodal agency
Not Defined
Not Defined
i. All the benefits of central policyii. Benefits under Industrial policyiii. Feasible site locations will be provided by BREDAiv. Exemption from EDv. No Entry & VAT on plant & machinary
Not Defined
Not Defined
Not Defined
The project developer shall be required to submit the application to State investment Promotion Board (SIPB), Department of Industries, Government of Bihar along with a pre-feasibility report, applicable processing fee & site details.Financial Closure: 8 monthsCommissioning: 24 Months from Approval
The capital cost of transmission system for evacuation of power to the nearest grid/ sub-station including all metering & protective instruments shall be born by BSEB, which shall be reimbursed to BSEB by the State Government, provided that the project developer offer to supply BSEB at least 50%, subject to a minimum of 2 MW, of power generated from RE projects. Else the entire project cost of transmission system for evacuation of power to the nearest grid/ sub-station including all metering & protective instruments shall be born by the project developer.
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Not Defined
Government land in the industrial area, if available and identified by the developer, may be leased in accordance with Government of Bihar policy for the allotment of land. The project developer may purchase private land directly from the owners, on their own. Use of agricultural land may be allowed for non-agricultural purposes.
North & South Bihar: 24.00 Paisa/Unit @33KV and 28.00 Pisa/Unit @ 11KV
at 33KV: 5.00%at 11KV: 6.00%
132 kV consumers = 22 Ps/kWh.33 kV consumers (other than HTSS) = 53 Ps/kWh.11 kV consumers (other than HTSS) = 44 Ps/kWhHTSS consumers (33 kV & 11 kV) = Nil