32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
The Commissioning PlanTable of Contents
1. Overview _______________________________________________________ 2-3
A. Commissioning Plan Overview
B. Abbreviations and Definitions
2. Commissioning Team Members _____________________________________ 4-5
A. Commissioning Team Member Table
B. Commissioning Team Member Organizational Chart
3. Commissioning Process ___________________________________________ 6-9
A. Commissioning Activity Schedule Matrix
B. Commissioning Activities Matrix
4. Commissioning Activities __________________________________________ 10-24
4.1 Introduction
4.2 Design Phase Commissioning
4.3 Construction Phase Commissioning
4.4 Acceptance Phase Commissioning
5. Systems to be Commissioned __________________________________ 25-26
6. Commissioning Schedule ___________________________________ 27
7. Appendix 1 – Forms __________________________________________ 28-31
8. Appendix 2 – List of Equipments to be Commissioned ___________________ 32-50
9. Process Flow Chart and Issues Log __________________________________ 50
_________________________________________________________________________________ Commissioning Plan Page 1 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
1. Overview
A. Commissioning Plan Overview
Developing a Commissioning Plan is essential in implementing a successful commissioning process. The plan outlines each team member’s role and commissioning responsibilities for a project and includes a schedule and scope of commissioning activities. The plan has its own section detailing what activities will be accomplished and guidance on who and how it is completed.
Commissioning begins early in the construction process by reviewing the design documentation and confirming the design intent and the ‘Commissionability’ of the services and systems to be commissioned.
During installation of the services reticulation, elemental testing is carried out such as duct leakage, cable insulation etc. to ensure the installation meets the required standards.
Testing of the individual items of plant and equipment follows this and in some instances, plant testing at factory, prior to shipping to site, is required.
Maintenance Training is an essential process during commissioning and this is best accomplished by having the future maintenance staffs attend on the commissioning works as well as NSC arranging classroom training on the plant, equipment and systems installed in the development.
Preparation of the Operating and Maintenance manuals to a defined standard and the correct preparation of test records provides the owner with a fully documented facility which can be operated with confidence and as problems arise during the operation, the information needed for maintenance and re-setting of controls (when needed) is readily available.
A commissioning report is to include information and data to provide an accurate quantitative record of system measurements and information. Reports also shall include notes and comments, as appropriate, to provide the reviewer with additional details related to the test procedure, system operation and results.
_________________________________________________________________________________ Commissioning Plan Page 2 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
B. Abbreviations and Definitions
BOD Basis of DesignCxA Commissioning Agent, Owner’s OPR Owner’s Project RequirementFPT Functional Performance TestPFT Pre-functional TestingTAB Testing, Adjusting and BalancingO&M Operation and Maintenance Manual
_________________________________________________________________________________ Commissioning Plan Page 3 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
2. Commissioning Team Members
A. Commissioning Team Members Table
Commissioning Team Members
1. Owner’s Commissioning Agent Forsspac2. Testing and Commissioning Management TBA3. Design Consultant TBA4. Consultants/Designers:
Architect of Record TBA Project Manager DCI Property Manager CBRE LEED Consultants DLS Telecommunications Meinhardt, Phils. Mechanical Designer Meinhardt, Phils. Electrical Designer Meinhardt, Phils. Plumbing & Sanitary Designer Meinhardt, Phils. Fire Protection Designer Meinhardt, Phils. BMS & Security Meinhardt, Phils.
5. Contractors: General Contractor TBA Mechanical Contractor TBA
TAB Contractor TBA Plumbing Sanitary Contractor TBA
Fire Protection Contractor TBA Electrical Contractor TBA BMS & Security Contractor TBA
6. Suppliers:
_________________________________________________________________________________ Commissioning Plan Page 4 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
_________________________________________________________________________________ Commissioning Plan Page 5 of 49Revision 0
B. Commissioning Team Member Organization Chart
• Testing and Commissioning
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
3. Commissioning Process
A. Commissioning Activity Schedule Matrix
Commissioning Roles & Responsibilities Matrix Legend: S
uppliers
Nom
inated Sub-C
ontractors
General C
ontractor
Com
missioning A
gent ,CxA
Designers (M
PI)
LE
ED
Consultant (D
LS
)
Project M
anager (DC
I)
Property M
anager, PM
(CB
RE
)
C- Conduct & Document F- FacilitateR- Review and Comment W- Witness & ReportA- Approve D- Develop
P- Participate
Activity
DESIGN PHASE COMMISSIONINGCreate or Update Commissioning Plan D R R RCreate or Update Issues Log D RDesign Kick Off Meeting F P P PSpecification and Drawing Review 50% CD’s R A P RUpdate OPR R D R AUpdate BOD R D R ABasis of Design Review R A RSpecification and Drawing Review 95% CD’s R A P RDefine training requirements of Owners personnel F R P APre Bid Meeting P P P F PCONSTRUCTION PHASE COMMISSIONING
Construction Kick Off Meeting P P P C P P P P
Create Commissioning Duration Schedule D D D F R A REquipment Submittals Review P P P R A P PUpdate Issues Log R R R R P P RUpdate Commissioning Plan R R R C R R RUpdate OPR and BOD R D R RSite Observations for all Systems and Equipment W P RDevelop Testing Methodologies D D F R R R
Create Pre Functional Equipment Installation Check Sheets D D F R A R
Perform Pre Functional Equipment Installation Check Sheets C C P W R RCreate Pre Functional Test Equipment Start Up Check Sheets D D F R A RPerform and Document Pre Functional Start Up Tests C C P W RPerform and Document Static Tests C C P P ACreate Pre Functional Controls Point to Point Check Sheets D D F R A R
Perform Pre Functional Controls Point to Point Check Sheets C C P W A R
Develop Operating and Maintenance Manual D D F R R A
_________________________________________________________________________________ Commissioning Plan Page 6 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
Commissioning Roles & Responsibilities Matrix
Legend:
Suppliers
Nom
inated Sub-C
ontractors
General C
ontractor
Com
missioning A
gent ,CxA
(FPC
)
Designers (M
PI)
LE
ED
Consultant (D
LS
)
Project M
anager (DC
I)
Property M
anager, PM
(CB
RE
)
C = Conduct & Document F = FacilitateR = Review and Comment W = Witness & ReportA = Approve D = Develop
P = Participate
Activity
ACCEPTANCE AND TURNOVER PHASE
Create Functional Performance Test Check Sheets P P P D P PWitness functionality of FTP tests C C F W W WApprove Functional Tests Results C C F A R RReview Testing Methodologies D D F A R RReview Operating and Maintenance Manuals D D F R R ACreate Training Schedules with Owner D D F P R RUpdate Issues Log R P P RUpdate OPR R R D RUpdate BOD R D R RDocument Owner Training C C F R R R ACreate Final Commissioning Report D R A RCreate Final System Manual F F F A R R R
_________________________________________________________________________________ Commissioning Plan Page 7 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
B. Commissioning Activities Matrix
Activity / Deliverable DueReview
Comments Due
Revisions / Response
Due
DESIGN PHASE COMMISSIONINGCreate or Update Commissioning Plan
Create or Update Issues LogDesign Kick Off Meeting
Specification & Drawing Review 50% CD’sUpdate OPRUpdate BODBasis of Design ReviewSpecification and Drawing Review near 95% CD’sDefine training requirements of Owners personnelPre Bid MeetingCONSTRUCTION PHASE COMMISSIONINGConstruction Kick Off MeetingCreate Commissioning Duration ScheduleEquipment Submittals ReviewUpdate Issues LogUpdate Commissioning PlanUpdate OPR and BODSite Observations for all Systems and EquipmentDevelop Testing MethodologiesCreate Pre Functional Equipment Installation Check Sheets
Perform Pre Functional Equipment Installation Check Sheets
Create Pre Functional Test Equipment Start Up Check Sheets
Perform and Document Pre Functional Start Up Tests
Perform and Document Static Tests
Create Pre Functional Controls Point to Point Check SheetsPerform Pre Functional Controls Point to Point Check Sheets
Activity / Deliverable DueReview
Comments Due
Revisions / Response
Due
ACCEPTANCE AND TURNOVER PHASE
_________________________________________________________________________________ Commissioning Plan Page 8 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
Create Functional Performance Test Check SheetsWitness functionality of FTP testsApprove Functional Tests ResultsReview Testing MethodologiesReview Operating and Maintenance ManualsCreate Training Schedules with OwnerUpdate Issues LogUpdate OPRUpdate BODDocument Owner TrainingCreate Final Commissioning ReportCreate Final System Manual
4. Commissioning Activities
4.1. IntroductionThe purpose of this section is to describe the requirements for commissioning a project.
_________________________________________________________________________________ Commissioning Plan Page 9 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
4.2. Design Phase Commissioning
4.2.1. Introduction
During the Design Phase, the design professionals create the Contract Documents. The Contract Documents turn the OPR into working design documents. The CxA shall evaluate and document that the Contract Documents conform to the OPR. The CxA shall evaluate the Systems, equipment and components incorporated into the Contract Documents to ensure they conform to the OPR from the standpoint of commissionability, maintainability, functionality and best practices.
4.2.2. Design Phase Responsibilities
4.2.2.1. Commissioning Team Members
The required Commissioning Team members for the Design Phase are:
a. Owner’s Representativesb. Commissioning Agent, (CxA)c. Programming Professionalsd. Architecte. Mechanical Engineerf. Electrical Engineerg. Project Manager
4.2.2.2. Commissioning Team Responsibilities
The commissioning team has the responsibility of facilitating the commissioning process for the project. Each individual team member is responsible for contributing to the commissioning processes according to their individual project responsibilities.
4.2.3. Design Phase Activities
4.2.3.1. Design Kick-off Meeting
The CxA shall conduct an initial Kick-off Meeting with the Design Team and the Owner. The purpose of the meeting will be to establish the purpose and proposed processes for commissioning the design and to review the Design Phase Commissioning Plan.
4.2.3.2. Commissioning Schedule of Activities
The CxA shall verify that commissioning activities are incorporated into the Design Phase schedule.
_________________________________________________________________________________ Commissioning Plan Page 10 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
4.2.3.3. Evaluate Basis of Design Conformance
The design professional will prepare the Basis of Design (BOD) document in response to the OPR. The BOD includes the Design Narrative and the Design Criteria. The CxA verifies that the BOD conforms to the requirements of the OPR.
The Design Narrative shall include the following:
a. Project location and special site requirementsb. Design parameters: weather data and source, space occupancy, all
internal and special equipment energy requirements, and other criteria used that may define the methodology used to complete the analysis.
c. Sustainability design parameters including: Renewable Energy, Carbon footprint and total system energy efficiency
d. Design assumptions and limitationse. Energy management systems sophisticationf. System and controls sophistication of Owner’s operating personnelg. Sizing criteria to be used.h. Accepted safety factors incorporated into the designi. Accepted levels of redundancyj. Reference to specific equipment selection limitations as to make
model numbersk. Operation assumptionsl. Codes, standards and guidelines to be utilized for the design
The CxA shall evaluate the BOD for conformance to the OPR from the standpoint of commissionability, maintainability, functionality and industry accepted best practices and produce an evaluation document.
4.2.3.4. Commissioning Specification
The CxA shall review the contract commissioning specifications and verify that they are included in the contract documents. The CxA shall assist in creating commissioning specifications to be included in the contract documents. The commissioning specifications should include the following:
a. Specification describing the basic commissioning process that will be used on the project by the CxA, located in the general requirement area of the specification
b. Specification describing the commissioning activities required of the Mechanical, Electrical, Control and TAB contractors, located in each individual discipline specification section.
c. Specification describing the commissioning activities required of any Vendor or equipment supplier or specialty subcontractor, located in each individual vendor, supplier or subcontractor specification section.
_________________________________________________________________________________ Commissioning Plan Page 11 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
4.2.3.5. Establish Training Requirements
The CxA shall work with the Owner and the design professionals to define the training requirements for the Owner’s personnel. Verify that these requirements are incorporated into the project specifications. Training should include:
a. Theory of operation presented by the Engineerb. Sustainability methods and measures presented by the Green
Building Accredited Professional or the Engineer.c. Start Up procedure, shut down procedures, operating procedures and
Maintenance procedures for each type of equipment and system presented by the manufacturer or contractor
d. Control system operations and programming training. Include durations extended over time.
e. Specify classroom instruction duration and field demonstration duration for each training event.
f. O&M manual review for warranty repair or replacement proceduresg. Review of all warranty durations and start dates
4.2.3.6. Schematic Design Document Evaluation
The CxA shall complete a thorough evaluation of the Schematic Design (SD), or a 35% design review of documents to establish that the Mechanical systems, equipment and components are identified and can be installed in compliance with the OPR and the BOD. Schematic Design Document Evaluation may include: engineering calculations, system selection, system selection criteria, flow sheet designs and major component selection.
4.2.3.7. Design Development Document Evaluation
The CxA shall complete a thorough evaluation of the Design Development (DD), or a 65% design review of documents and submitted criteria for continued compliance to the OPR and BOD; Evaluate design documents for commissioning specifications and requirements; Draft preliminary Commissioning Specifications and Supplemental Commissioning Language for other specifications if required. Design Development Document Evaluation should include zoning requirements, specifications, typical room layouts, system main layouts, riser layouts, standard details, schedules and coordination requirements.
4.2.3.8. Contract Documents Evaluation
The CxA shall evaluate the contract documents at a near Construction Document level (95%). The Design CxA may evaluate the drawings and specifications at each milestone; Schematic Design (35%), Design Development (65%) and Construction Documents (100%). The
_________________________________________________________________________________ Commissioning Plan Page 12 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
frequency of evaluation shall be specified or as mutually agreed to between the Owner / Buyer. The CxA shall evaluate drawings and specifications for each system, component and equipment for its commissionability, maintainability, functionality and best practices.
4.2.3.9. Meetings
The CxA shall conduct all commissioning team meetings and shall issue via DCI meeting minutes as documentation of these meeting.
4.2.3.10. Update OPR and the BOD
The Owner must update the OPR and the design professionals must update the BOD during design phase to incorporate any approved changes that may have developed due to changes, additions, deletions, or other modifications incorporated into the final Contract Documents.
4.2.3.11. Update the Commissioning Plan
The CxA shall update the Commissioning Plan to include any additional Commissioning Team members, procedures and schedules or design phase commissioning requirements developed in the Design Commissioning Process.
4.2.3.12. Issues Log Management
The Owner shall manage the Issues Log as to timely issue answers and resolutions. The Owner has the final authority over issue resolution disagreements or interpretations. The final Issues Log, its statements and its statements answers shall become a permanent record of the commissioning process.
4.2.3.13. Update the Issues Log Documentation
The CxA shall create and maintain the Issues Log. The Issues Log shall be used throughout the commissioning process, going from a Design Phase issue log to a Construction Phase issue log, to an Acceptance Phase issue log and finally to a Warranty Phase issue log. The final (complete) issue log shall become a part of the final Commissioning Report.
4.2.3.14. Pre-Bid Meeting
The Owner conducts a Pre-Bid meeting to assist contractors in answering any questions about the systems or the commissioning process. The CxA shall attend the Pre-Bid meeting to fully explain the commissioning requirements of the Contract Documents and allow the contractors to
_________________________________________________________________________________ Commissioning Plan Page 13 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
understand their role in the commissioning process and its associated costs. Provide any assistance required by the Owner in answering written questions (in the form of clarifications or addendum recommendations) during the bidding process.
4.2.4. Design Phase Documentation
The following commissioning documents are produced during the Design phase commissioning if these activities are included in commissioning scope of work.
a. Updated Owner’s Project Requirements b. Updated Commissioning Plan c. Updated Basis of Design from Designersd. Contract Document Evaluation e. Updated Issues Log f. Pre-Bid Meeting minutes or documentation
4.3. Construction Phase Commissioning
4.3.1. Introduction
During the Construction Phase the commissioning team works to verify the equipment and systems are installed in accordance with the design documents and are operable, maintainable and ready for functional testing.
4.3.2. Construction Phase Responsibilities
4.3.2.1. Commissioning Team Members
The commissioning team members for the Construction Phase are:
a. Owner’s Representativeb. Commissioning Representativec. Design Team Representatived. Construction Manager Representativee. General Contractor Representativef. Mechanical Contractor Representativeg. Electrical Contractor Representativeh. Plumbing and Sanitary Contractor Representativei. Fire Protection Contractor Representativej. BMS & Security Contractor Representativek. Test & Balance Representativel. Chiller, AHU, FCU Representativem. Cooling Tower Representativen. Pumps ( A/C & Domestic ) Representativeo. Specialty Contractor Representative
GondolaLandscaping
_________________________________________________________________________________ Commissioning Plan Page 14 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
4.3.2.2. Commissioning Team Responsibilities
The commissioning Team has the responsibility of facilitating the commissioning process for the project. Each individual team member shall be responsible for contributing to the commissioning processes according to their individual project responsibilities.
4.3.3. Construction Phase Activities
4.3.3.1. Construction Kick-off Meeting
The CxA thru DCI shall conduct an initial commissioning meeting with all contractors and commissioning team members. The purpose of the meeting will be to review the Construction Phase Commissioning process and activities for the commissioning for the project. During the meeting the CxA shall review the following:
a. The Commissioning Planb. The basic commissioning to be utilized on the projectc. The individual roles and responsibilities of each participating
Commissioning Team memberd. Documentation requirementse. Communication and reporting proceduresf. The check sheets and forms to be utilized on the projectg. The commissioning duration schedules
The CxA shall create the meeting agenda, lead the meeting and prepare and distribute the meeting minutes via DCI.
4.3.3.2. Commissioning Duration Schedule
The CxA shall prepare a duration schedules for the contractors for the commissioning activities required by the commissioning plan. These duration schedules should be incorporated into the contractor’s project schedule to track all commissioning activities of the Commissioning Team.
4.3.3.3. Commissioning Team Meetings
The CxA shall conduct an initial commissioning meeting with all contractors and commissioning team members. The purpose of the meeting will be to review the Construction Phase Commissioning process and activities for the commissioning of the project. At a minimum, review the following:
a. Create the agendab. Attend and lead meetingc. Schedule and review the commissioning activities
_________________________________________________________________________________ Commissioning Plan Page 15 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
d. Coordinate commissioning meetings with construction meetings and activities
e. Prepare and distribute meeting minutes via DCI.
4.3.3.4. Equipment Submittal Review
The CxA shall review all pertinent Mechanical equipment submittals to support the Commissioning Process. The submittal and shop drawing review should include: a. The submittal and shop drawing information is utilized to
create the appropriate PFT check sheets and forms for the project. b. The CxA shall review the submittals and shop drawings for
commissionability, maintainability, functionality, best practices and for conformance to the CD’s, OPR and BOD.
c. The CxA shall document any found issues on the project Issue Log. The Issues Log shall be forwarded to the Consultants MPI and DCI. Any comments shall be endorsed by the Consultant and thru DCI to appropriate comments to the Commissioning Team members for resolution.
4.3.3.5. Site Observations
During the course of construction, the CxA shall visit the site to inspect the progress of the construction with respect to the Mechanical systems, equipment and components being commissioned. The purpose of the inspection is to verify that the construction complies with the Contract Documents, the OPR identify and document any quality issues that may lead to functional issues. Site observations are forwarded to DCI for their review and endorsement to the appropriate team member. If site observation issues are not automatically accepted and resolved the issue is added to the issue Log for resolution.
4.3.3.6. Pre-Functional Tests (PFT)
There are several types of Systems PFT that shall be performed during the construction phase: installation verification tests, static tests, and equipment startup tests.
4.3.3.6.1. Systems & Controls Installation Verification Tests
The contractor must verify that all work is installed in accordance with the contract documents or the manufacturer’s recommendations and provide the associated check sheets verifying such. The contractor must document that all equipment is installed in the correct location and is operable in accordance with the contract documents. The CxA shall provide the installation verification check sheets if not available from the manufacturers or contractors. The CxA shall
_________________________________________________________________________________ Commissioning Plan Page 16 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
perform the installation inspections at his discretion. The CxA or his staff shall validate the Installation Verification Check sheets completed by the contractor by back checking them through site observations. Completion of all installation verification tests signifies that those systems are ready for start up activities. Examples of these tests include:
a. All piping systems and components installationsa. All duct systems and component installationsb. All Mechanical equipment installationc. All Building Automation/Control equipment and
component installation
Installation Verification tests shall include the following:
a. Material or Equipment Name or descriptionb. Model Numberc. Type and Sized. Serial Numbere. Installation & location to design requirements verificationf. Maintenance access verificationg. Installation complete and ready for start-up
4.3.3.6.2. Static Tests
The contractor must perform hydrostatic and pressure tests as described in the Contract Documents. All hydrostatic and pressure tests must be verified by contractor or code authority as required by the Contract Documents or as dictated by the local codes. Complete static test sheets are then provided to the CxA.
Examples of these tests include:
a. Hydrostatic testing of all piping systems to the appropriate test pressure and duration
b. Pressure testing of all ducts for leakage determination
4.3.3.6.3. Mechanical Equipment Startup Tests
The contractor or vendor who has contractual obligation to provide start up services shall start up the systems and equipment in accordance with the Contract Documents and the manufacturer’s requirements. Completed start up check sheets are then provided to the CxA. The CxA shall observe and document these start up tests. At a minimum start up tests should include the following:
a. Manufacturer’s Name
_________________________________________________________________________________ Commissioning Plan Page 17 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
b. Model Numberc. Type and Sized. Serial Numbere. Actual Settings or Adjustmentsf. Actual Electrical Characteristicsg. Actual Loadh. Operating data as required by the manufacturer
4.3.3.6.4. Control System Startup Tests
The CxA shall provide a 100% point to point control system test and sensor calibration as verification of the control system operational status with no sampling strategies allowed. The control point to point test shall verify the system operations from the system graphic to the end sensor or control device. The control tests should include the following:
a. Controller Manufacturerb. Controller or System Identificationc. Verification of Controller Communicationd. Pin Addresse. Point ID and Namef. Point Typeg. Connected device descriptionh. Verification of action and polarityi. Verification of status indicationj. Actual sensor reading, system reading and offset
4.3.3.7. Update the OPR and the BOD
The Owner shall update the OPR and the design professionals shall update the BOD during construction phase to incorporate any approved Mechanical changes that may have developed due to changes, additions, deletions, or other modifications incorporated into the final construction.
4.3.3.8. Update the Commissioning Plan
The CxA shall update the Commissioning Plan to include any changes to the commissioning team members, their responsibilities, contact information, procedures, schedules or changes to the commissioning requirements as a result of the Construction Phase. DCI to issue copies of PMI to the CxA so as to monitor changes and the Commissioning Plan shall also be updated to include all revised or added check sheets or forms utilized during the Pre-Functional Tests.
4.3.3.9. Issues Log & Deficiency Resolution
The CxA shall report deficiencies from any PFT on the Issues Log and it shall be distributed via DCI to the appropriate members of the
_________________________________________________________________________________ Commissioning Plan Page 18 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
Commissioning Team for resolution. The CxA shall work with the Commissioning Team Members to ensure that the issues are completely understood and the responsibilities for response or corrective action are completely understood. The Owner must manage the issue log for resolution of all outstanding issues and the CxA shall assist as necessary to complete the issue log. After corrective action, retests shall be performed to verify conformance. When deficiencies are resolved, the issues shall be signed off on the Issues Log by the CxA and the appropriate commissioning team member. Issues that are resolved in a manner not consistent with the OPR must be approved by the Owner.
4.3.3.10. Operations and Maintenance (O&M) Manuals.
The Contractors shall create and assemble the Operations and Maintenance Manuals as contractually required. The drawings and manuals are then forwarded to the Project Manager for review and approval. The CxA shall review all Record Documents and Operations and Maintenance Manuals for accuracy and completeness to the Contract Documents and for conformance to the OPR. DCI shall review and approve these documents after review by the CxA. The Record Documents and the O&M Manuals should include:
a. Final Approved Submittalsb. Final Approved Shop Drawingsc. Record Documentsd. Service Procurement informatione. Operating Manuals specifically tailored to the exact equipment,
systems and components installedf. Maintenance requirements and proceduresg. Lubrication lists and instructionsh. Recommended spare parts lists with purchase contact informationi. Warranty information
4.3.4. Construction Phase Documentation
The following commissioning documents are produced during the Construction Phase commissioning: a. Kick-off team meeting agenda and minutesb. Agendas and Minutes of all commissioning team meetings c. Commissioning duration schedulesd. Submittal & Shop Drawing review documents e. Site Observation reports f. Pre-Functional Test report check sheets: Installation Verification Tests, Static
Tests and Equipment Startup Testsg. Updated Owner’s Project Requirements h. Updated Issues Log
4.4. Acceptance Phase Commissioning
_________________________________________________________________________________ Commissioning Plan Page 19 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
4.4.1. Introduction
During the Acceptance Phase, the building systems are complete and fully functional. The main focus of the commissioning efforts during the acceptance phase is to:
a. Verify that the building system is functionally completeb. Coordinate the Owner’s Personnel Training
Functional Performance Tests (FPTs) verify appropriate sequential performance of automated systems and stability of these sequences under normal, upset and transitional conditions. FPT are used to verify that the building systems are functionally complete.
4.4.2. Acceptance Phase Responsibilities
4.4.2.1. Commissioning Team Members
The commissioning team members for the Acceptance Phase are:
a. Owner’s Representativesb. Commissioning Representativec. Design Team Representatived. Construction Manager Representativee. General Contractor Representativef. Mechanical Contractor Representativeg. Electrical Contractor Representativeh. Plumbing and Sanitary Contractor Representativei. Fire Protection Contractor Representativej. BMS & Security Contractor Representativek. Test & Balance Representative ( through LCPI)l. Chiller, AHU, FCU Representativem. Cooling Tower Representativen. Pumps ( A/C & Domestic ) Representativeo. Specialty Contractor Representative
GondolaLandscaping
4.4.2.2. Commissioning Team Responsibilities
The Commissioning Team has the responsibility of facilitating the commissioning process for the project. Each individual team member shall be responsible for contributing to the commissioning processes according to their individual project responsibilities.
4.4.3. Acceptance Phase Activities
4.4.3.1. Commissioning Duration Schedule
_________________________________________________________________________________ Commissioning Plan Page 20 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
The CxA shall continue to monitor and update the duration schedule for the contractors for the commissioning activities in the Acceptance Phase required by the Commissioning Plan. These duration schedules should track all commissioning activities of the Commissioning Team in this Phase.
4.4.3.2. Commissioning Team Meetings
This CxA shall continue to attend and lead all commissioning meetings as required with the Commissioning Team to review progress of the commissioning effort and reinforce individual responsibilities.
4.4.3.3. Testing, Adjusting and Balancing Report Verification
The CxA shall verify that the completeness and accuracy of the final Testing, Adjusting and Balancing Report. This verification shall include repeatable observations of selected TAB readings. The CxA shall pick readings to be repeated at random. If these tests do not show repeatability to the TAB report within specified balance tolerances, the TAB contractor shall be required to re-balance the selected systems until repeatability is proved. The CxA shall determine the extent and quantity of repeatability tests to prove the integrity of the balance efforts.
4.4.3.4. Functional Performance Tests (FPT)
Functional Performance Tests shall be designed by the CxA and performed by the Commissioning Team. The CxA or his staff shall observe and facilitate the FPT for all systems that have operating sequences. The CxA shall review and comment on the Functional Performance Test results. FPT shall be performed for all sequences with no sampling strategies allowed except for application specific, factory programmed devices that cannot have the program modified in the field. The FPT tests shall include the following:
a. System descriptionb. Specific function being testedc. Functional test designd. Description of data points testede. Description of test duration and test interval timesf. Description of test setpoints and setpoint changesg. Description of test report documentation requirementsh. Description of test pass / fail criteria
4.4.3.5. Test Documents / AS-Built Drawings and Operations and Maintenance (O&M) Manuals.
The Contractors shall create and assemble the Operations and Maintenance Manuals as contractually required. The drawings and
_________________________________________________________________________________ Commissioning Plan Page 21 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
manuals are then forwarded to the design professional for review and approval. The CxA shall review all Test Documents and Operations and Maintenance Manuals for accuracy and completeness to the Contract Documents and for conformance to the OPR. The CxA shall review these documents after review and approval by the design professional. The Record Documents and the O&M Manuals should include:
j. Final Approved Submittalsk. Final Approved Shop Drawingsl. Test Documentsm. Service Procurement informationn. Operating Manuals specifically tailored to the exact equipment,
systems and components installedo. Maintenance requirements and proceduresp. Lubrication lists and instructionsq. Recommended spare parts lists with purchase contact informationr. Warranty information
The CxA shall verify that the Test Documents and O&M Manuals are reviewed, approved and delivered to the Owner in accordance with programme schedule and prior to Owner training.
4.4.3.6. Owner Training
The CxA shall work with the contractor and Owner to schedule and plan the training activities so that training occurs in a coordinated and coherent fashion. The CxA shall assist in the development of training schedules and agendas, encourage the use of a combination of “classroom” and field training, and assist the contractors in the development of training agendas for each system, piece of equipment or component installed in the project.
The contractors, sub-contractor and suppliers provide the training instruction and provide training materials. Additional operator skill training may be provided via PMI as an additional scope item if desired by the Owner.
The CxA shall document Owner training events by video taping presentations and demonstrations for future use by the Owner.
4.4.3.7. Update the OPR and BOD (Acceptance Phase)
The Owner shall update the OPR and the design professionals shall update the BOD during Construction Phase to incorporate any approved Mechanical changes that may have developed due to changes, additions, deletions, or other modifications incorporated during the Acceptance Phase.
4.4.3.8. Update the Commissioning Plan (Acceptance Phase)
_________________________________________________________________________________ Commissioning Plan Page 22 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
The CxA shall update the Commissioning Plan to include any changes to the Commissioning Team members, their responsibilities, their contact information, procedures, schedules or changes to the commissioning requirements as a result of the Acceptance Phase. The commissioning Plan shall also be updated to include all revised or added check sheets or forms utilized during the Functional Performance Tests. The Commissioning Plan should include:
a. Description of the commissioning process utilized for the projectb. Commissioning Team member identification and contact informationc. Team member responsibilitiesd. Commissioning FPT Forms indexe. Copies of all typical FPT forms
4.4.3.9. Issues Log & Deficiency Resolution (Acceptance Phase)
The Owner must manage the Issue Log as to timely issue answers and resolution. The Owner shall have final authority over issue resolution disagreements or interpretations. The final issues Log, its statements and its statement responses shall become permanent record of the commissioning process.
4.4.3.10. Update the Issues Log
The CxA shall report deficiencies from the FPT on the Issues Log and it shall be distributed to the appropriate members of the Commissioning Team via DCI for resolution. The CxA shall work with the Commissioning Team Members to ensure that the issues are completely understood. The Owner must manage to issue log for resolution of all outstanding issues and the CxA shall assist as necessary to complete the issue log. After corrective action, retests shall be performed to verify conformance. When deficiencies are resolved, the issues shall be signed off on the Issues Log by the CxA and the appropriate Commissioning Team Member(s). All issues log items shall be resolved or answered by the appropriate commissioning team member. Issues that are resolved in a manner that are not consistent with the OPR must be approved by the Owner. If after three attempts by the CxA to obtain an issue resolution a CxA can issue a certified report by clearly describing the unresolved issue in the Commissioning Report executive summary.
4.4.3.11. Final Commissioning Report
Based on the accumulated commissioning work completed as described above, the CxA shall assemble the data into a final Commissioning
_________________________________________________________________________________ Commissioning Plan Page 23 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
Report. The final report will incorporate the final record documents for each system, as appropriate. The commissioning Report shall include:
a. Certification Pageb. Commissioning Report Indexc. Executive Summaryd. Commissioning Plane. Complete Pre-Functional Commissioning Check Sheets and Formsf. TAB Verification Datag. Completed Functional Performance Testsh. Observation Reportsi. Issues Logj. All pertinent correspondences
4.4.3.12. System Manual
At the end of the Acceptance Phase the CxA shall produce the Systems Manual. The purpose of the Systems Manual is to provide the Owner and his operators with the permanent record of all pertinent documents required for future operation, commissioning and validation processes of the facility. The Systems Manual should be provided to the Owner on electronic format. The final system manual should include the following:
a. Summaryb. The final Approved Submittals and Shop Drawingsc. Final OPRd. Final BODe. Final Contract Documents (Record drawings / AS-builts)f. Final Operating and Maintenance Manualsg. Final Commissioning Reporth. Operator Training Materialsi. Recommended Standard Operation Proceduresj. TAB Report
4.4.4. Acceptance Phase Documentation
The following commissioning documents are produced during the Acceptance Phase:
a. Completed TAB Verification Forms b. Complete Functional Performance Tests Report Forms c. O&M Review Document d. Commissioning Report e. Systems Manualf. Training Agenda
_________________________________________________________________________________ Commissioning Plan Page 24 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
5. Systems to be Commissioned
The following systems will be commissioned in this project.
HVAC System
__ Chiller System including controls, piping, pumps and variable speed drives__ Pumps__ Piping cleaning and flushing__ Chemical treatment__ Ductwork__ Air Handling Units__ DX units__ Ducted FCU’s__ Cooling Tower__ Terminal/VAV Units__ Exhaust fan system__ Fresh air fan system__ Ventilating fans__ Jet fans__ Testing, Adjusting and Balancing (TAB) works__ Building Automation System__ Pressurization system__ Smoke exhaust system
Electrical System
__ Electrical system power quality__ Lighting/ lighting controls__ Electrical power outlets__ Electrical panel boards__ Distribution boards__ Motor control center__ Communication system__ Security system__ Uninterruptible power supply__ Emergency power system
Fire Protection System
__ Fire Detection and Alarm system__ Pre-action sprinkler system__ Foam suppression system__ Fire sprinkler system
Plumbing & Sanitary
__ Potable Water Supply System__ Non Potable Water Supply
_________________________________________________________________________________ Commissioning Plan Page 25 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
__ Sanitary and Vent System__ Storm Drainage System__ Water Features
LP Gas Tank SystemFuel Oil SystemVertical Transportation System
6. Commissioning Schedule
_________________________________________________________________________________ Commissioning Plan Page 26 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
_________________________________________________________________________________ Commissioning Plan Page 27 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
7. Appendix 1 – Forms
Water Features
1. Central Water Feature Circulating Pump Performance Test2. Entry Water Feature – Setting to Work Checklist3. Entry Water Feature Circulating Pump Performance Test
Liquefied Petroleum Gas
1. LPG – Pre Commissioned Checklist Visual Inspection2. LPG – Gas Leak Detector Functional Test3. LPG – Final Inspection Checklist
Plumbing System
1. Functional Test – Booster Pump2. Booster Pump – Pre-start-up Checklists3. Flushing Test4. Cold Water Line – Flushing Test5. Gravity Flow Test6. Plumbing Fixtures / Fittings Checklist & Operational Test7. Submersible Pumps - Pre-Functional Testing (PFT) Equipment Checklist8. Submersible Pumps - Pre-Functional Testing (PFT) Equipment Start-up & Functional
Performance Testing (FPT)9. Transfer Pump - Pre-Functional Testing (PFT) Equipment Checklist10. Transfer Pump - Pre-Functional Testing (PFT) Equipment Start-up & Functional Performance
Testing (FPT)
Fuel Oil System
1. Pre-Commissioning Checklist Bulk Storage Tank2. Functional Test Bulk Storage Tank (BST Dip Stick) Content Gauge3. Functional Test Bulk Storage Tank (BST) High / Low Level Float Control4. Pre-Commissioning Checklist Fuel Oil Day Tank5. Functional Test Fuel Day Tank High / Low Level Gauge Control6. Pre-Commissioning Checklist Fuel Transfer Pump7. Functional Test Fuel Transfer Pump
Mechanical System (Air Distribution System)
1. Air Distribution System – Terminal Summary2. Air Distribution system – Duct Traverse3. Variable Air Volume Box – Equipment checklist4. Variable Air Volume Box - Pre-Functional Testing (PFT) Equipment Start-up & Functional
Performance Testing (FPT)5. Pre-Cooled Air Handling Unit – Equipment Checklist6. Pre-Cooled Air Handling Unit – Pre-Functional Testing (PFT) Equipment Start-up 7. Pre-Cooled Air Handling Unit –Functional Performance Testing (FPT)
_________________________________________________________________________________ Commissioning Plan Page 28 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
8. Air Handling Unit Pre-functional Testing (PFT) Equipment Checklist9. Air Handling Unit Pre-functional Testing (Equipment Start-up)10. Air Handling Unit Functional Performance Test11. Fan Pre-functional Testing (PFT) Equipment Checklist12. Fan Pre-functional Testing (PFT) Equipment Start-up & Functional Performance Testing
(FPT) 13. Staircase Pressurization Fan - Functional Performance Testing (PFT) Equipment Start-up &
Functional Performance Testing (FPT) 14. Staircase Pressurization Fan - Functional Performance Testing (PFT) 15. Staircase Pressurization Pre-functional Performance Testing (PFT) Equipment Checklist16. FCU /ACU Pre-functional Testing (PFT) Equipment Checklist17. FCU / ACU Functional Performance Test (PFT) Equipment Start-up & Functional
Performance Testing (FPT)18. FCU Cassette Type Pre-functional Testing (PFT) Equipment Checklist19. FCU Cassette Type Pre-functional Testing (PFT) Equipment Start-up & Functional
Performance Testing (FPT)20. FCU Ducted Type Pre-functional Testing (PFT) Equipment Checklist 21. FCU Ducted Type Pre-functional Testing (PFT)Equipment Start-up & Functional
Performance Testing (FPT)
Mechanical System (Water Distribution System)
1. Water Distribution System – Water Balance Test Sheet2. Chiller Equipment Checklist 3. Chiller – Pre-functional Testing Equipment Start-up4. Pump – Equipment Checklist5. Pump – Equipment Checklist6. Chilled Water Pump – Pre-functional Testing Equipment Start-up7. Condenser Water Pump – Pre-functional Testing Equipment Start-up8. Cooling Tower – Equipment Checklist9. Cooling Tower – Equipment Checklist10. Cooling Tower - Pre-functional Testing Equipment Start-up11. Air Separator – Equipment Checklist12. Air Separator - Pre-functional Testing Equipment Start-up13. Expansion Tank – Equipment Checklist14. Expansion Tank - Pre-functional Testing Equipment Start-up15. Chemical Pot Feeder – Equipment checklist
Paging System
1. PA System Functional Test2. Public Address System – Functional Test3. PA System Walk-through Test4. PA System Equipment Rack & Accessories Walk-through Test
_________________________________________________________________________________ Commissioning Plan Page 29 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
Generator
1. Emergency Standby Generator System Pre-commissioning Checklist2. Generator - Functional Test3. Generator Start-up & Load Test
Low Voltage System
1. Meter Center – Visual Inspection Checklists2. Low Voltage System – Pre-commissioning Checklists3. Voltage/Phase Reading & Functional Test4. Low Voltage System Visual & Functional Test5. Functional Performance Test – Retightening of Bolts6. Functional Performance Test – Ground Fault Check7. Low Voltage System Simulation Test
Electrical Lighting System
1. Lighting Fixtures Checklists2. Common Area Lighting & Power Visual & Functional Test3. Functional Performance Testing – Voltage & Current Test4. Lighting Fixtures Functional Test5. Lighting Fixtures Lux – Functional Test
Fire Detection & Alarm System
1. FACP, FATB & FAS Field Devices Pre-functional Test Equipment Checklists2. Fireman’s Telephone Jack Pre-functional Testing3. Functional Performance Testing Alarm Test4. Pre-functional Testing FACP Equipment Start-up5. Pre-functional Test Main FACP Panel (EVAC) Test6. Functional Test Main FACP Panel (EVAC) Test
Fire Protection System
1. Jockey Pump Inspection Checklists2. Inspection Checklist Portable Fire Extinguisher3. Inspection Checklist Fire Hose Cabinet Station4. Roof Manifold Hose Valve (Siamese) Visual Inspection5. Electric Driven Fire Pump Inspection Checklist6. Electric Driven Pump Pre-start Up Checklist7. Electric Driven Fire Pump Performance Test8. Jockey Pump Performance Test9. 4-way Fire Department Connection Visual Inspection10. Fire Protection Flushing Test11. Float Control Valve Functional Test12. Sprinkler Pressure Reducing Valve Station13. Sprinkler Alarm Check Valve Assembly14. Sprinkler Floor Control Valve assembly
_________________________________________________________________________________ Commissioning Plan Page 30 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
15. Electric Fire Pump Alignment Test
Building Management System
1. Pre-commissioning Checklist - DDC for AHU / EF’s / FCU / ATS /Pumps2. Functional Test – Point-to-Point Test (all connected devices)3. Functional Test of all inputs and control devices
Security System1. Pre-commissioning Checklist – CCTV Camera2. Functional Test – CCTV Camera3. Functional Test - CCTV Digital Video Recorder4. Pre-Commissioning Checklist – CCTV Control Console5. Functional Test – Matrix Switch 6. Functional Test- Host / Work Station
_________________________________________________________________________________ Commissioning Plan Page 31 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
8. Appendix 2 – List of Equipments to be Commissioned
Forssman Pacific Corporation Legend: Additional
Zuellig Project For VerificationDeleted
Scope Reference
#
ISTO Reference #
SystemType of System
Equipment Mark DescriptionLocation /
Area
STCS-01 Zuellig - 001 Telecommunication Auxiliary MDF Main Distribution Frame 1st LevelSTCS-02 Zuellig - 002 Telecommunication Auxiliary IDF-L1 Intermediate Distribution Frame 1st LevelSTCS-03 Zuellig - 003 Telecommunication Auxiliary IDF-L2 Intermediate Distribution Frame 2nd LevelSTCS-04 Zuellig - 004 Telecommunication Auxiliary IDF-L3 Intermediate Distribution Frame 3rd LevelSTCS-05 Zuellig - 005 Telecommunication Auxiliary IDF-L4 Intermediate Distribution Frame 4th LevelSTCS-06 Zuellig - 006 Telecommunication Auxiliary IDF-L5 Intermediate Distribution Frame 5th LevelSTCS-07 Zuellig - 007 Telecommunication Auxiliary IDF-L6 Intermediate Distribution Frame 6th LevelSTCS-08 Zuellig - 008 Telecommunication Auxiliary IDF-L7 Intermediate Distribution Frame 7th LevelSTCS-09 Zuellig - 009 Telecommunication Auxiliary IDF-L8 Intermediate Distribution Frame 8th LevelSTCS-10 Zuellig - 010 Telecommunication Auxiliary IDF-L9 Intermediate Distribution Frame 9th LevelSTCS-11 Zuellig - 011 Telecommunication Auxiliary IDF-L10 Intermediate Distribution Frame 10th LevelSTCS-12 Zuellig - 012 Telecommunication Auxiliary IDF-L11 Intermediate Distribution Frame 11th LevelSTCS-13 Zuellig - 013 Telecommunication Auxiliary IDF-L12 Intermediate Distribution Frame 12th LevelSTCS-14 Zuellig - 014 Telecommunication Auxiliary IDF-L13 Intermediate Distribution Frame 13th LevelSTCS-15 Zuellig - 015 Telecommunication Auxiliary IDF-L14 Intermediate Distribution Frame 14th LevelSTCS-16 Zuellig - 016 Telecommunication Auxiliary IDF-L15 Intermediate Distribution Frame 15th LevelSTCS-17 Zuellig - 017 Telecommunication Auxiliary IDF-L16 Intermediate Distribution Frame 16th LevelSTCS-18 Zuellig - 018 Telecommunication Auxiliary IDF-L17 Intermediate Distribution Frame 17th LevelSTCS-19 Zuellig - 019 Telecommunication Auxiliary IDF-L18 Intermediate Distribution Frame 18th LevelSTCS-20 Zuellig - 020 Telecommunication Auxiliary IDF-L19 Intermediate Distribution Frame 19th LevelSTCS-21 Zuellig - 021 Telecommunication Auxiliary IDF-L20 Intermediate Distribution Frame 20th LevelSTCS-22 Zuellig - 022 Telecommunication Auxiliary IDF-L21 Intermediate Distribution Frame 21st LevelSTCS-23 Zuellig - 023 Telecommunication Auxiliary IDF-L22 Intermediate Distribution Frame 22nd LevelSTCS-24 Zuellig - 024 Telecommunication Auxiliary IDF-L23 Intermediate Distribution Frame 23rd LevelSTCS-25 Zuellig - 025 Telecommunication Auxiliary IDF-L24 Intermediate Distribution Frame 24th LevelSTCS-26 Zuellig - 026 Telecommunication Auxiliary IDF-L25 Intermediate Distribution Frame 25th LevelSTCS-27 Zuellig - 027 Telecommunication Auxiliary IDF-L26 Intermediate Distribution Frame 26th LevelSTCS-28 Zuellig - 028 Telecommunication Auxiliary IDF-L27 Intermediate Distribution Frame 27th LevelSTCS-29 Zuellig - 029 Telecommunication Auxiliary IDF-L28 Intermediate Distribution Frame 28th LevelSTCS-30 Zuellig - 030 Telecommunication Auxiliary IDF-L29 Intermediate Distribution Frame 29th LevelSTCS-31 Zuellig - 031 Telecommunication Auxiliary IDF-L30 Intermediate Distribution Frame 30th LevelSTCS-32 Zuellig - 032 Telecommunication Auxiliary IDF-L31 Intermediate Distribution Frame 31st LevelSTCS-33 Zuellig - 033 Telecommunication Auxiliary IDF-L32 Intermediate Distribution Frame 32nd LevelSTCS-34 Zuellig - 034 Telecommunication Auxiliary IDF-L33 Intermediate Distribution Frame 33rd Level
SS-01 Zuellig - 035 Access Control & Monitoring Auxiliary Workstation Workstation 1st LevelSS-02 Zuellig - 036 Access Control & Monitoring Auxiliary Master Control Panel Master Control Panel 1st Level
SS-03 Zuellig - 037 Access Control & Monitoring Auxiliary Card Readers - B1 Card ReadersCommon
Area
SS-04 Zuellig - 038 Carpark Management AuxiliaryCar Access Controller
(Entrance) Car Access Controller (Entrance)Common
Area
_________________________________________________________________________________ Commissioning Plan Page 32 of 49Revision 0
Forssman
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
SS-05 Zuellig - 039 Carpark Management AuxiliaryCar Access Controller
(Exit) Car Access Controller (Exit)Common
Area
SS-06 Zuellig - 040 Guard Tour Auxiliary Guard Tour Tracking Guard Tour Tracking Common
AreaCCTV-01 Zuellig - 041 Closed Circuit TV Auxiliary DVR 1 Data Video Recorder 1st LevelCCTV-02 Zuellig - 042 Closed Circuit TV Auxiliary DVR 2 Data Video Recorder 1st LevelCCTV-03 Zuellig - 043 Closed Circuit TV Auxiliary DVR 3 Data Video Recorder 1st LevelCCTV-04 Zuellig - 044 Closed Circuit TV Auxiliary Matrix Controller Matrix Controller 1st Level
CATV-01 Zuellig - 045Community Antenna
Television Auxiliary 1st Level - CATV System CATV System 1st Level
CATV-02 Zuellig - 046Community Antenna
Television Auxiliary2nd Level - CATV
System CATV System 2nd Level
CATV-03 Zuellig - 047Community Antenna
Television Auxiliary3rd Level - CATV
System CATV System 3rd Level
CATV-04 Zuellig - 048Community Antenna
Television Auxiliary 4th Level - CATV System CATV System 4th Level
CATV-05 Zuellig - 049Community Antenna
Television Auxiliary 5th Level - CATV System CATV System 5th Level
CATV-06 Zuellig - 050Community Antenna
Television Auxiliary 6th Level - CATV System CATV System 6th Level
CATV-07 Zuellig - 051Community Antenna
Television Auxiliary 7th Level - CATV System CATV System 7th Level
CATV-08 Zuellig - 052Community Antenna
Television Auxiliary 8th Level - CATV System CATV System 8th Level
CATV-09 Zuellig - 053Community Antenna
Television Auxiliary 9th Level - CATV System CATV System 9th Level
CATV-10 Zuellig - 054Community Antenna
Television Auxiliary10th Level - CATV
System CATV System 10th Level
CATV-11 Zuellig - 055Community Antenna
Television Auxiliary11th Level - CATV
System CATV System 11th Level
CATV-12 Zuellig - 056Community Antenna
Television Auxiliary12th Level - CATV
System CATV System 12th Level
CATV-13 Zuellig - 057Community Antenna
Television Auxiliary13th Level - CATV
System CATV System 13th Level
CATV-14 Zuellig - 058Community Antenna
Television Auxiliary14th Level - CATV
System CATV System 14th Level
CATV-15 Zuellig - 059Community Antenna
Television Auxiliary15th Level - CATV
System CATV System 15th Level
CATV-16 Zuellig - 060Community Antenna
Television Auxiliary16th Level - CATV
System CATV System 16th Level
CATV-17 Zuellig - 061Community Antenna
Television Auxiliary17th Level - CATV
System CATV System 17th Level
CATV-18 Zuellig - 062Community Antenna
Television Auxiliary18th Level - CATV
System CATV System 18th Level
CATV-19 Zuellig - 063Community Antenna
Television Auxiliary19th Level - CATV
System CATV System 19th Level
CATV-20 Zuellig - 064Community Antenna
Television Auxiliary20th Level - CATV
System CATV System 20th Level
CATV-21 Zuellig - 065Community Antenna
Television Auxiliary21st Level - CATV
System CATV System 21st Level
CATV-22 Zuellig - 066Community Antenna
Television Auxiliary22nd Level - CATV
System CATV System 22nd Level
CATV-23 Zuellig - 067Community Antenna
Television Auxiliary23rd Level - CATV
System CATV System 23rd Level
CATV-24 Zuellig - 068Community Antenna
Television Auxiliary24th Level - CATV
System CATV System 24th Level
CATV-25 Zuellig - 069Community Antenna
Television Auxiliary25th Level - CATV
System CATV System 25th Level
CATV-26 Zuellig - 070Community Antenna
Television Auxiliary26th Level - CATV
System CATV System 26th Level
CATV-27 Zuellig - 071Community Antenna
Television Auxiliary27th Level - CATV
System CATV System 27th Level
CATV-28 Zuellig - 072Community Antenna
Television Auxiliary28th Level - CATV
System CATV System 28th LevelCATV-29 Zuellig - 073 Community Antenna Auxiliary 29th Level - CATV CATV System 29th Level
_________________________________________________________________________________ Commissioning Plan Page 33 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
Television System
CATV-30 Zuellig - 074Community Antenna
Television Auxiliary30th Level - CATV
System CATV System 30th Level
CATV-31 Zuellig - 075Community Antenna
Television Auxiliary31st Level - CATV
System CATV System 31st Level
CATV-32 Zuellig - 076Community Antenna
Television Auxiliary32nd Level - CATV
System CATV System 32nd Level
CATV-33 Zuellig - 077Community Antenna
Television Auxiliary33rd Level - CATV
System CATV System 33rd Level
CATV-34 Zuellig - 078Community Antenna
Television Auxiliary34th Level - CATV
System CATV System 34th LevelFDAS-01 Zuellig - 079 Fire Detection System Auxiliary MFACP Main Fire Alarm Control Panel 1st LevelFDAS-02 Zuellig - 080 Fire Detection System Auxiliary FDAS - B1 Fire Alarm System Bsmt 1FDAS-03 Zuellig - 081 Fire Detection System Auxiliary FDAS - B2 Fire Alarm System Bsmt 2FDAS-04 Zuellig - 082 Fire Detection System Auxiliary FDAS - B3 Fire Alarm System Bsmt 3FDAS-05 Zuellig - 083 Fire Detection System Auxiliary FDAS - B4 Fire Alarm System Bsmt 4FDAS-06 Zuellig - 084 Fire Detection System Auxiliary FDAS - B5 Fire Alarm System Bsmt 5FDAS-07 Zuellig - 085 Fire Detection System Auxiliary FDAS - L1 Fire Alarm System 1st LevelFDAS-08 Zuellig - 086 Fire Detection System Auxiliary FDAS - L2 Fire Alarm System 2nd LevelFDAS-09 Zuellig - 087 Fire Detection System Auxiliary FDAS - L3 Fire Alarm System 3rd LevelFDAS-10 Zuellig - 088 Fire Detection System Auxiliary FDAS - L4 Fire Alarm System 4th LevelFDAS-11 Zuellig - 089 Fire Detection System Auxiliary FDAS - L5 Fire Alarm System 5th LevelFDAS-12 Zuellig - 090 Fire Detection System Auxiliary FDAS - L6 Fire Alarm System 6th LevelFDAS-13 Zuellig - 091 Fire Detection System Auxiliary FDAS - L7 Fire Alarm System 7th LevelFDAS-14 Zuellig - 092 Fire Detection System Auxiliary FDAS - L8 Fire Alarm System 8th LevelFDAS-15 Zuellig - 093 Fire Detection System Auxiliary FDAS - L9 Fire Alarm System 9th LevelFDAS-16 Zuellig - 094 Fire Detection System Auxiliary FDAS - L10 Fire Alarm System 10th LevelFDAS-17 Zuellig - 095 Fire Detection System Auxiliary FDAS - L11 Fire Alarm System 11th LevelFDAS-18 Zuellig - 096 Fire Detection System Auxiliary FDAS - L12 Fire Alarm System 12th LevelFDAS-19 Zuellig - 097 Fire Detection System Auxiliary FDAS - L13 Fire Alarm System 13th LevelFDAS-20 Zuellig - 098 Fire Detection System Auxiliary FDAS - L14 Fire Alarm System 14th LevelFDAS-21 Zuellig - 099 Fire Detection System Auxiliary FDAS - L15 Fire Alarm System 15th LevelFDAS-22 Zuellig - 100 Fire Detection System Auxiliary FDAS - L16 Fire Alarm System 16th LevelFDAS-23 Zuellig - 101 Fire Detection System Auxiliary FDAS - L17 Fire Alarm System 17th LevelFDAS-24 Zuellig - 102 Fire Detection System Auxiliary FDAS - L18 Fire Alarm System 18th LevelFDAS-25 Zuellig - 103 Fire Detection System Auxiliary FDAS - L19 Fire Alarm System 19th LevelFDAS-26 Zuellig - 104 Fire Detection System Auxiliary FDAS - L20 Fire Alarm System 20th LevelFDAS-27 Zuellig - 105 Fire Detection System Auxiliary FDAS - L21 Fire Alarm System 21st LevelFDAS-28 Zuellig - 106 Fire Detection System Auxiliary FDAS - L22 Fire Alarm System 22nd LevelFDAS-29 Zuellig - 107 Fire Detection System Auxiliary FDAS - L23 Fire Alarm System 23rd LevelFDAS-30 Zuellig - 108 Fire Detection System Auxiliary FDAS - L24 Fire Alarm System 24th LevelFDAS-31 Zuellig - 109 Fire Detection System Auxiliary FDAS - L25 Fire Alarm System 25th LevelFDAS-32 Zuellig - 110 Fire Detection System Auxiliary FDAS - L26 Fire Alarm System 26th LevelFDAS-33 Zuellig - 111 Fire Detection System Auxiliary FDAS - L27 Fire Alarm System 27th LevelFDAS-34 Zuellig - 112 Fire Detection System Auxiliary FDAS - L28 Fire Alarm System 28th LevelFDAS-35 Zuellig - 113 Fire Detection System Auxiliary FDAS - L29 Fire Alarm System 29th LevelFDAS-36 Zuellig - 114 Fire Detection System Auxiliary FDAS - L30 Fire Alarm System 30th LevelFDAS-37 Zuellig - 115 Fire Detection System Auxiliary FDAS - L31 Fire Alarm System 31st LevelFDAS-38 Zuellig - 116 Fire Detection System Auxiliary FDAS - L32 Fire Alarm System 32nd LevelFDAS-39 Zuellig - 117 Fire Detection System Auxiliary FDAS - L33 Fire Alarm System 33rd LevelFDAS-40 Zuellig - 118 Fire Detection System Auxiliary FDAS - L34 Fire Alarm System 34th LevelBGM-01 Zuellig - 119 Background Music & PA Auxiliary 1st Level - BGM/PA BGM/PA System 1st Level
BMS-01 Zuellig - 120Building Management
System Auxiliary Workstation Workstation 1st Level
BMS-02 Zuellig - 121Building Management
System Auxiliary DDC - Exhaust Fans Direct Digital System - EFCommon
Area
BMS-03 Zuellig - 122Building Management
System Auxiliary DDC - Fan Coil Units Direct Digital System - FCUCommon
AreaBMS-04 Zuellig - 123 Building Management Auxiliary DDC - Fire Pump Direct Digital System - FP Common
_________________________________________________________________________________ Commissioning Plan Page 34 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
System Area
BMS-05 Zuellig - 124Building Management
System Auxiliary DDC - Jockey Pump Direct Digital System - JPCommon
Area
BMS-06 Zuellig - 125Building Management
System Auxiliary DDC - Fire Water Tank Direct Digital System - EWTCommon
Area
BMS-07 Zuellig - 126Building Management
System Auxiliary DDC - EE / EL Room Direct Digital System - EE/ELCommon
Area
BMS-08 Zuellig - 127Building Management
System AuxiliaryDDC - Non Potable
Water Tank Direct Digital System - NPWTCommon
Area
BMS-09 Zuellig - 128Building Management
System AuxiliaryDDC - Potable Water
Tank Direct Digital System - PWTCommon
Area
BMS-10 Zuellig - 129Building Management
System Auxiliary DDC - Fuel Oil Pump Direct Digital System - FOPCommon
Area
BMS-11 Zuellig - 130Building Management
System Auxiliary DDC - Suppy Fans Direct Digital System - SFCommon
Area
BMS-12 Zuellig - 131Building Management
System Auxiliary DDC - Sump Pump Direct Digital System - SPCommon
Area
BMS-13 Zuellig - 132Building Management
System Auxiliary DDC - Jet Fans Direct Digital System - JFCommon
Area
BMS-14 Zuellig - 133Building Management
System Auxiliary DDC - AHU Direct Digital System - AHUCommon
Area
BMS-15 Zuellig - 134Building Management
System AuxiliaryDDC - Carpark Supply
Fan Direct Digital System - CSFCommon
Area
BMS-16 Zuellig - 135Building Management
System Auxiliary DDC - Gray Water Tank Direct Digital System - GWTCommon
Area
BMS-17 Zuellig - 136Building Management
System AuxiliaryDDC - General Exhaust
Fans Direct Digital System - GEFCommon
Area
BMS-18 Zuellig - 137Building Management
System AuxiliaryDDC - Automatic Transfer Swith Direct Digital System - ATS
Common Area
BMS-19 Zuellig - 138Building Management
System AuxiliaryDDC - Kitchen Exhaust
Fans Direct Digital System - KEFCommon
Area
BMS-20 Zuellig - 139Building Management
System AuxiliaryDDC - Kitchen Supply
Fans Direct Digital System - KSFCommon
Area
BMS-21 Zuellig - 140Building Management
System AuxiliaryDDC - Carpark Exhaust
Fans Direct Digital System - CEFCommon
Area
BMS-22 Zuellig - 141Building Management
System AuxiliaryDDC - Stair
Pressurization Fan Direct Digital System - SPFCommon
AreaNP-01 Zuellig - 142 Electrical System Electrical T1 Transformer Bsmt 4NP-02 Zuellig - 143 Electrical System Electrical T2 Transformer Bsmt 4NP-03 Zuellig - 144 Electrical System Electrical T3 Transformer Bsmt 4NP-04 Zuellig - 145 Electrical System Electrical T4 Transformer Bsmt 4NP-05 Zuellig - 146 Electrical System Electrical T5 Transformer Bsmt 4NP-06 Zuellig - 147 Electrical System Electrical T6 Transformer Bsmt 4NP-07 Zuellig - 148 Electrical System Electrical HVSG High Voltage Switchgear Bsmt 4NP-08 Zuellig - 149 Electrical System Electrical LVSG-1 Low Voltage Switchgear Bsmt 3NP-09 Zuellig - 150 Electrical System Electrical LVSG-2 Low Voltage Switchgear Bsmt 3NP-10 Zuellig - 151 Electrical System Electrical LVSG-3 Low Voltage Switchgear Bsmt 1NP-11 Zuellig - 152 Electrical System Electrical LVSG-4 Low Voltage Switchgear Bsmt 1NP-12 Zuellig - 153 Electrical System Electrical LVSG-5 Low Voltage Switchgear Bsmt 1NP-13 Zuellig - 154 Electrical System Electrical LVSG-6 Low Voltage Switchgear Bsmt 1NP-14 Zuellig - 155 Electrical System Electrical MVSG Medium Voltage Switchgear Bsmt 1
NP-15 Zuellig - 156 Electrical System Electrical TVSS1Transient Voltage Surge
Suppressor Bsmt 1
NP-16 Zuellig - 157 Electrical System Electrical TVSS2Transient Voltage Surge
Suppressor Bsmt 1NP-17 Zuellig - 158 Electrical System Electrical DB-MB5-2 Distribution Boards Bsmt 5NP-18 Zuellig - 159 Electrical System Electrical DB-MB5-1 Distribution Boards Bsmt 5NP-19 Zuellig - 160 Electrical System Electrical DB-B5-1 Distribution Boards Bsmt 5NP-20 Zuellig - 161 Electrical System Electrical DB-B5-2 Distribution Boards Bsmt 5NP-21 Zuellig - 162 Electrical System Electrical DB-MB4 Distribution Boards Bsmt 4NP-22 Zuellig - 163 Electrical System Electrical DB-B4-1 Distribution Boards Bsmt 4NP-23 Zuellig - 164 Electrical System Electrical DB-B4-2 Distribution Boards Bsmt 4
_________________________________________________________________________________ Commissioning Plan Page 35 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
NP-24 Zuellig - 165 Electrical System Electrical DB-MB3 Distribution Boards Bsmt 3NP-25 Zuellig - 166 Electrical System Electrical DB-B3-1 Distribution Boards Bsmt 3NP-26 Zuellig - 167 Electrical System Electrical DB-B3-2 Distribution Boards Bsmt 3NP-27 Zuellig - 168 Electrical System Electrical SMDB-MB3 Sub-Main Distribution Boards Bsmt 3NP-28 Zuellig - 169 Electrical System Electrical DB-MB2 Distribution Boards Bsmt 2NP-29 Zuellig - 170 Electrical System Electrical DB-B2-1 Distribution Boards Bsmt 2NP-30 Zuellig - 171 Electrical System Electrical DB-B2-2 Distribution Boards Bsmt 2NP-31 Zuellig - 172 Electrical System Electrical DB-MB1 Distribution Boards Bsmt 1NP-32 Zuellig - 173 Electrical System Electrical SMDB-B1 Sub-Main Distribution Boards Bsmt 1NP-33 Zuellig - 174 Electrical System Electrical DB-B1-1 Distribution Boards Bsmt 1NP-34 Zuellig - 175 Electrical System Electrical DB-B1-2 Distribution Boards Bsmt 1NP-35 Zuellig - 176 Electrical System Electrical DB-Telco-1 Distribution Boards Bsmt 1NP-36 Zuellig - 177 Electrical System Electrical DB-Telco-2 Distribution Boards Bsmt 1NP-37 Zuellig - 178 Electrical System Electrical SMDB-AHU-01 Sub-Main Distribution Boards 1st LevelNP-38 Zuellig - 179 Electrical System Electrical SMDB-AHU-02 Sub-Main Distribution Boards 1st LevelNP-39 Zuellig - 180 Electrical System Electrical SMDB-AHU-03 Sub-Main Distribution Boards 30th LevelNP-40 Zuellig - 181 Electrical System Electrical SMDB-AHU-04 Sub-Main Distribution Boards 30th LevelNP-41 Zuellig - 182 Electrical System Electrical SMDB-M31-ELEV Sub-Main Distribution Boards 31st LevelNP-42 Zuellig - 183 Electrical System Electrical SMDB-M34-ELEV Sub-Main Distribution Boards 34th LevelNP-43 Zuellig - 184 Electrical System Electrical Busduct 1 Busduct CommonNP-44 Zuellig - 185 Electrical System Electrical Busduct 2 Busduct CommonNP-45 Zuellig - 186 Electrical System Electrical Busduct 3 Busduct CommonNP-46 Zuellig - 187 Electrical System Electrical Busduct 4 Busduct CommonNP-47 Zuellig - 188 Electrical System Electrical Busduct 5 Busduct CommonNP-48 Zuellig - 189 Electrical System Electrical DB-MG Distribution Boards 1st LevelNP-49 Zuellig - 190 Electrical System Electrical DB-M2 Distribution Boards 2nd LevelNP-50 Zuellig - 191 Electrical System Electrical DB-M3 Distribution Boards 3rd LevelNP-51 Zuellig - 192 Electrical System Electrical DB-M4 Distribution Boards 4th LevelNP-52 Zuellig - 193 Electrical System Electrical DB-M5 Distribution Boards 5th LevelNP-53 Zuellig - 194 Electrical System Electrical DB-M6 Distribution Boards 6th LevelNP-54 Zuellig - 195 Electrical System Electrical DB-M7 Distribution Boards 7th LevelNP-55 Zuellig - 196 Electrical System Electrical DB-M8 Distribution Boards 8th LevelNP-56 Zuellig - 197 Electrical System Electrical DB-M9 Distribution Boards 9th LevelNP-57 Zuellig - 198 Electrical System Electrical DB-M10 Distribution Boards 10th LevelNP-58 Zuellig - 199 Electrical System Electrical DB-M11 Distribution Boards 11th LevelNP-59 Zuellig - 200 Electrical System Electrical DB-M12 Distribution Boards 12th LevelNP-60 Zuellig - 201 Electrical System Electrical DB-M13 Distribution Boards 13th LevelNP-61 Zuellig - 202 Electrical System Electrical DB-M14 Distribution Boards 14th LevelNP-62 Zuellig - 203 Electrical System Electrical DB-M15 Distribution Boards 15th LevelNP-63 Zuellig - 204 Electrical System Electrical DB-M16 Distribution Boards 16th LevelNP-64 Zuellig - 205 Electrical System Electrical DB-M17 Distribution Boards 17th LevelNP-65 Zuellig - 206 Electrical System Electrical DB-M18 Distribution Boards 18th LevelNP-66 Zuellig - 207 Electrical System Electrical DB-M19 Distribution Boards 19th LevelNP-67 Zuellig - 208 Electrical System Electrical DB-M20 Distribution Boards 20th LevelNP-68 Zuellig - 209 Electrical System Electrical DB-M21 Distribution Boards 21st LevelNP-69 Zuellig - 210 Electrical System Electrical DB-M22 Distribution Boards 22nd LevelNP-70 Zuellig - 211 Electrical System Electrical DB-M23 Distribution Boards 23rd LevelNP-71 Zuellig - 212 Electrical System Electrical DB-M24 Distribution Boards 24th LevelNP-72 Zuellig - 213 Electrical System Electrical DB-M25 Distribution Boards 25th LevelNP-73 Zuellig - 214 Electrical System Electrical DB-M26 Distribution Boards 26th LevelNP-74 Zuellig - 215 Electrical System Electrical DB-M27 Distribution Boards 27th LevelNP-75 Zuellig - 216 Electrical System Electrical DB-M28 Distribution Boards 28th LevelNP-76 Zuellig - 217 Electrical System Electrical DB-M29 Distribution Boards 29th LevelNP-77 Zuellig - 218 Electrical System Electrical DB-M30 Distribution Boards 30th LevelNP-78 Zuellig - 219 Electrical System Electrical DB-M31 Distribution Boards 31st LevelNP-79 Zuellig - 220 Electrical System Electrical DB-M32 Distribution Boards 32nd Level
_________________________________________________________________________________ Commissioning Plan Page 36 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
NP-80 Zuellig - 221 Electrical System Electrical DB-M33 Distribution Boards 33rd LevelNP-81 Zuellig - 222 Electrical System Electrical DB-B3-UPS Distribution Boards Bsmt 3NP-82 Zuellig - 223 Electrical System Electrical DB-L3-UPS Distribution Boards 3rd LevelNP-83 Zuellig - 224 Electrical System Electrical DB-L13-UPS Distribution Boards 13th LevelNP-84 Zuellig - 225 Electrical System Electrical DB-L8-UPS Distribution Boards 8th LevelNP-85 Zuellig - 226 Electrical System Electrical DB-L18-UPS Distribution Boards 18th LevelNP-86 Zuellig - 227 Electrical System Electrical DB-L23-UPS Distribution Boards 23rd LevelNP-87 Zuellig - 228 Electrical System Electrical DB-L28-UPS Distribution Boards 28th LevelNP-88 Zuellig - 229 Electrical System Electrical DB-L33-UPS Distribution Boards 33rd LevelNP-89 Zuellig - 230 Electrical System Electrical GPS-1 Generator Paralleling Switchgear Bsmt 1NP-90 Zuellig - 231 Electrical System Electrical GPS-2 Generator Paralleling Switchgear Bsmt 1NP-91 Zuellig - 232 Electrical System Electrical MCC-M34-CT Motor Control Center 34th LevelNP-92 Zuellig - 233 Electrical System Electrical MCC-B2-CHWP Motor Control Center Bsmt 2
CAP-01 Zuellig - 234 Electrical System Electrical CAP-1 Capacitor Bank Bsmt 1CAP-02 Zuellig - 235 Electrical System Electrical CAP-2 Capacitor Bank Bsmt 1CAP-03 Zuellig - 236 Electrical System Electrical CAP-3 Capacitor Bank Bsmt 1CAP-04 Zuellig - 237 Electrical System Electrical CAP-4 Capacitor Bank Bsmt 1EP-01 Zuellig - 238 Electrical System Electrical Genset - 1 Generator Bsmt 2EP-02 Zuellig - 239 Electrical System Electrical Genset - 2 Generator Bsmt 2EP-03 Zuellig - 240 Electrical System Electrical Genset - 3 Generator Bsmt 2EP-04 Zuellig - 241 Electrical System Electrical Genset - 4 Generator Bsmt 2EP-05 Zuellig - 242 Electrical System Electrical Genset - 5 Generator Bsmt 2CH-01 Zuellig - 243 Chilled Water Mechanical PWC-01 Packaged Water Chiller Bsmt 2CH-02 Zuellig - 244 Chilled Water Mechanical PWC-02 Packaged Water Chiller Bsmt 2CH-03 Zuellig - 245 Chilled Water Mechanical PWC-03 Packaged Water Chiller Bsmt 2CH-04 Zuellig - 246 Chilled Water Mechanical PWC-04 Packaged Water Chiller Bsmt 2CH-05 Zuellig - 247 Chilled Water Mechanical CT-01 Cooling Tower Roof DeckCH-06 Zuellig - 248 Chilled Water Mechanical CT-02 Cooling Tower Roof DeckCH-07 Zuellig - 249 Chilled Water Mechanical CT-03 Cooling Tower Roof DeckCH-08 Zuellig - 250 Chilled Water Mechanical CT-04 Cooling Tower Roof DeckCH-09 Zuellig - 251 Chilled Water Mechanical CHWP-01 Chilled Water Pump Bsmt 2CH-10 Zuellig - 252 Chilled Water Mechanical CHWP-02 Chilled Water Pump Bsmt 2CH-11 Zuellig - 253 Chilled Water Mechanical CHWP-03 Chilled Water Pump Bsmt 2CH-12 Zuellig - 254 Chilled Water Mechanical CHWP-04 Chilled Water Pump Bsmt 2CH-13 Zuellig - 255 Chilled Water Mechanical CHWP-05 Chilled Water Pump Bsmt 2CH-14 Zuellig - 256 Chilled Water Mechanical COWP-01 Condenser Water Pump Bsmt 2CH-15 Zuellig - 257 Chilled Water Mechanical COWP-02 Condenser Water Pump Bsmt 2CH-16 Zuellig - 258 Chilled Water Mechanical COWP-03 Condenser Water Pump Bsmt 2CH-17 Zuellig - 259 Chilled Water Mechanical COWP-04 Condenser Water Pump Bsmt 2CH-18 Zuellig - 260 Chilled Water Mechanical COWP-05 Condenser Water Pump Bsmt 2CH-19 Zuellig - 261 Chilled Water Mechanical ET-1 (Bladder) Expansion Tank (Bladder) Roof DeckCH-20 Zuellig - 262 Chilled Water Mechanical SFU-01 Sand Filter Unit Roof DeckFO-01 Zuellig - 263 Fuel Oil Mechanical FOP-01 Fuel Oil Pump Bsmt 3FO-02 Zuellig - 264 Fuel Oil Mechanical FOP-02 Fuel Oil Pump Bsmt 3FO-03 Zuellig - 265 Fuel Oil Mechanical FOP-03 (Stand-by) Fuel Oil Pump Bsmt 3FO-04 Zuellig - 266 Fuel Oil Mechanical MT-1 Main Tank (Diesel) Bsmt 5FO-05 Zuellig - 267 Fuel Oil Mechanical MT-2 Main Tank (Diesel) Bsmt 5FO-06 Zuellig - 268 Fuel Oil Mechanical MT-3 Main Tank (Diesel) Bsmt 5FO-07 Zuellig - 269 Fuel Oil Mechanical MT-4 Main Tank (Diesel) Bsmt 5FO-08 Zuellig - 270 Fuel Oil Mechanical MT-5 Main Tank (Diesel) Bsmt 5FO-09 Zuellig - 271 Fuel Oil Mechanical MT-6 Main Tank (Diesel) Bsmt 5FO-10 Zuellig - 272 Fuel Oil Mechanical DT-1 Day Tank (Diesel) Bsmt 2FO-11 Zuellig - 273 Fuel Oil Mechanical DT-2 Day Tank (Diesel) Bsmt 2FO-12 Zuellig - 274 Fuel Oil Mechanical DT-3 Day Tank (Diesel) Bsmt 2FO-13 Zuellig - 275 Fuel Oil Mechanical DT-4 Day Tank (Diesel) Bsmt 2FO-14 Zuellig - 276 Fuel Oil Mechanical DT-5 Day Tank (Diesel) Bsmt 2
_________________________________________________________________________________ Commissioning Plan Page 37 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
FP-01 Zuellig - 277 Fire Protection SystemFire
Protection FP-1 (Duty) Fire Pump Bsmt 5
FP-02 Zuellig - 278 Fire Protection SystemFire
Protection FP-2 (Stand-by) Fire Pump Bsmt 5
FP-03 Zuellig - 279 Fire Protection SystemFire
Protection JP-03 Jockey Pump Bsmt 5
FP-04 Zuellig - 280 Fire Protection SystemFire
Protection FP-Basement 1 Sprinkler System Bsmt 1
FP-05 Zuellig - 281 Fire Protection SystemFire
Protection FP-Basement 2 Sprinkler System Bsmt 2
FP-06 Zuellig - 282 Fire Protection SystemFire
Protection FP-Basement 3 Sprinkler System Bsmt 3
FP-07 Zuellig - 283 Fire Protection SystemFire
Protection FP-Basement 4 Sprinkler System Bsmt 4
FP-08 Zuellig - 284 Fire Protection SystemFire
Protection FP-Basement 5 Sprinkler System Bsmt 5
FP-09 Zuellig - 285 Fire Protection SystemFire
Protection Ground Level - FP Sprinkler System 1st Level
FP-10 Zuellig - 286 Fire Protection SystemFire
Protection 2nd Level - FP Sprinkler System 2nd Level
FP-11 Zuellig - 287 Fire Protection SystemFire
Protection 3rd Level - FP Sprinkler System 3rd Level
FP-12 Zuellig - 288 Fire Protection SystemFire
Protection 4th Level - FP Sprinkler System 4th Level
FP-13 Zuellig - 289 Fire Protection SystemFire
Protection 5th Level - FP Sprinkler System 5th Level
FP-14 Zuellig - 290 Fire Protection SystemFire
Protection 6th Level - FP Sprinkler System 6th Level
FP-15 Zuellig - 291 Fire Protection SystemFire
Protection 7th Level - FP Sprinkler System 7th Level
FP-16 Zuellig - 292 Fire Protection SystemFire
Protection 8th Level - FP Sprinkler System 8th Level
FP-17 Zuellig - 293 Fire Protection SystemFire
Protection 9th Level - FP Sprinkler System 9th Level
FP-18 Zuellig - 294 Fire Protection SystemFire
Protection 10th Level - FP Sprinkler System 10th Level
FP-19 Zuellig - 295 Fire Protection SystemFire
Protection 11th Level - FP Sprinkler System 11th Level
FP-20 Zuellig - 296 Fire Protection SystemFire
Protection 12th Level - FP Sprinkler System 12th Level
FP-21 Zuellig - 297 Fire Protection SystemFire
Protection 13th Level - FP Sprinkler System 13th Level
FP-22 Zuellig - 298 Fire Protection SystemFire
Protection 14th Level - FP Sprinkler System 14th Level
FP-23 Zuellig - 299 Fire Protection SystemFire
Protection 15th Level - FP Sprinkler System 15th Level
FP-24 Zuellig - 300 Fire Protection SystemFire
Protection 16th Level - FP Sprinkler System 16th Level
FP-25 Zuellig - 301 Fire Protection SystemFire
Protection 17th Level - FP Sprinkler System 17th Level
FP-26 Zuellig - 302 Fire Protection SystemFire
Protection 18th Level - FP Sprinkler System 18th Level
FP-27 Zuellig - 303 Fire Protection SystemFire
Protection 19th Level - FP Sprinkler System 19th Level
FP-28 Zuellig - 304 Fire Protection SystemFire
Protection 20th Level - FP Sprinkler System 20th Level
FP-29 Zuellig - 305 Fire Protection SystemFire
Protection 21st Level - FP Sprinkler System 21st Level
FP-30 Zuellig - 306 Fire Protection SystemFire
Protection 22nd Level - FP Sprinkler System 22nd Level
FP-31 Zuellig - 307 Fire Protection SystemFire
Protection 23rd Level - FP Sprinkler System 23rd Level
FP-32 Zuellig - 308 Fire Protection SystemFire
Protection 24th Level - FP Sprinkler System 24th Level
FP-33 Zuellig - 309 Fire Protection SystemFire
Protection 25th Level - FP Sprinkler System 25th Level
_________________________________________________________________________________ Commissioning Plan Page 38 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
FP-34 Zuellig - 310 Fire Protection SystemFire
Protection 26th Level - FP Sprinkler System 26th Level
FP-35 Zuellig - 311 Fire Protection SystemFire
Protection 27th Level - FP Sprinkler System 27th Level
FP-36 Zuellig - 312 Fire Protection SystemFire
Protection 28th Level - FP Sprinkler System 28th Level
FP-37 Zuellig - 313 Fire Protection SystemFire
Protection 29th Level - FP Sprinkler System 29th Level
FP-38 Zuellig - 314 Fire Protection SystemFire
Protection 30th Level - FP Sprinkler System 30th Level
FP-39 Zuellig - 315 Fire Protection SystemFire
Protection 31st Level - FP Sprinkler System 31st Level
FP-40 Zuellig - 316 Fire Protection SystemFire
Protection 32nd Level - FP Sprinkler System 32nd Level
FP-41 Zuellig - 317 Fire Protection SystemFire
Protection 33rd Level - FP Sprinkler System 33rd Level
FP-42 Zuellig - 318 Fire Protection SystemFire
Protection 34th Level - FP Sprinkler System 34th Level
FP-43 Zuellig - 319 Fire Protection SystemFire
Protection Pre-Action Sprinkler-B5 Pre-Action Sprinkler System Bsmt 5
FP-44 Zuellig - 320 Fire Protection SystemFire
Protection Pre-Action Sprinkler-B4 Pre-Action Sprinkler System Bsmt 4
FP-45 Zuellig - 321 Fire Protection SystemFire
Protection Pre-Action Sprinkler-B1 Pre-Action Sprinkler System Bsmt 1
FP-46 Zuellig - 322 Fire Protection SystemFire
Protection Pre-Action Sprinkler-L34 Pre-Action Sprinkler System 34th Level
FP-47 Zuellig - 323 Fire Protection SystemFire
Protection Foam Suppression-B5 Foam Suppression System Bsmt 5
FP-48 Zuellig - 324 Fire Protection SystemFire
Protection FHC - Low Zone Fire Hose Cabinet Common
FP-49 Zuellig - 325 Fire Protection SystemFire
Protection FHC - High Zone Fire Hose Cabinet CommonAH-01 Zuellig - 326 Mechanical System Mechanical AHU-G-01 Air Handling Unit 1st LevelAH-02 Zuellig - 327 Mechanical System Mechanical AHU-G-02 Air Handling Unit 1st LevelAH-03 Zuellig - 328 Mechanical System Mechanical AHU-G-03 Air Handling Unit 1st LevelAH-04 Zuellig - 329 Mechanical System Mechanical AHU-G-04 Air Handling Unit 1st LevelAH-05 Zuellig - 330 Mechanical System Mechanical AHU-L2-01 Air Handling Unit 2nd LevelAH-06 Zuellig - 331 Mechanical System Mechanical AHU-L3-01 Air Handling Unit 3rd LevelAH-07 Zuellig - 332 Mechanical System Mechanical AHU-L3-02 Air Handling Unit 3rd LevelAH-08 Zuellig - 333 Mechanical System Mechanical AHU-L4-01 Air Handling Unit 4th LevelAH-09 Zuellig - 334 Mechanical System Mechanical AHU-L4-02 Air Handling Unit 4th LevelAH-10 Zuellig - 335 Mechanical System Mechanical AHU-L5-01 Air Handling Unit 5th LevelAH-11 Zuellig - 336 Mechanical System Mechanical AHU-L6-01 Air Handling Unit 6th LevelAH-12 Zuellig - 337 Mechanical System Mechanical AHU-L7-01 Air Handling Unit 7th LevelAH-13 Zuellig - 338 Mechanical System Mechanical AHU-L8-01 Air Handling Unit 8th LevelAH-14 Zuellig - 339 Mechanical System Mechanical AHU-L9-01 Air Handling Unit 9th LevelAH-15 Zuellig - 340 Mechanical System Mechanical AHU-L10-01 Air Handling Unit 10th LevelAH-16 Zuellig - 341 Mechanical System Mechanical AHU-L11-01 Air Handling Unit 11th LevelAH-17 Zuellig - 342 Mechanical System Mechanical AHU-L12-01 Air Handling Unit 12th LevelAH-18 Zuellig - 343 Mechanical System Mechanical AHU-L13-01 Air Handling Unit 13th LevelAH-19 Zuellig - 344 Mechanical System Mechanical AHU-L14-01 Air Handling Unit 14th LevelAH-20 Zuellig - 345 Mechanical System Mechanical AHU-L15-01 Air Handling Unit 15th LevelAH-21 Zuellig - 346 Mechanical System Mechanical AHU-L16-01 Air Handling Unit 16th LevelAH-22 Zuellig - 347 Mechanical System Mechanical AHU-L17-01 Air Handling Unit 17th LevelAH-23 Zuellig - 348 Mechanical System Mechanical AHU-L18-01 Air Handling Unit 18th LevelAH-24 Zuellig - 349 Mechanical System Mechanical AHU-L19-01 Air Handling Unit 19th LevelAH-25 Zuellig - 350 Mechanical System Mechanical AHU-L20-01 Air Handling Unit 20th LevelAH-26 Zuellig - 351 Mechanical System Mechanical AHU-L21-01 Air Handling Unit 21st LevelAH-27 Zuellig - 352 Mechanical System Mechanical AHU-L22-01 Air Handling Unit 22nd LevelAH-28 Zuellig - 353 Mechanical System Mechanical AHU-L23-01 Air Handling Unit 23rd LevelAH-29 Zuellig - 354 Mechanical System Mechanical AHU-L24-01 Air Handling Unit 24th Level
_________________________________________________________________________________ Commissioning Plan Page 39 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
AH-30 Zuellig - 355 Mechanical System Mechanical AHU-L25-01 Air Handling Unit 25th LevelAH-31 Zuellig - 356 Mechanical System Mechanical AHU-L26-01 Air Handling Unit 26th LevelAH-32 Zuellig - 357 Mechanical System Mechanical AHU-L27-01 Air Handling Unit 27th LevelAH-33 Zuellig - 358 Mechanical System Mechanical AHU-L28-01 Air Handling Unit 28th LevelAH-34 Zuellig - 359 Mechanical System Mechanical AHU-L29-01 Air Handling Unit 29th LevelAH-35 Zuellig - 360 Mechanical System Mechanical AHU-L5-02 Air Handling Unit 5th LevelAH-36 Zuellig - 361 Mechanical System Mechanical AHU-L6-02 Air Handling Unit 6th LevelAH-37 Zuellig - 362 Mechanical System Mechanical AHU-L7-02 Air Handling Unit 7th LevelAH-38 Zuellig - 363 Mechanical System Mechanical AHU-L8-02 Air Handling Unit 8th LevelAH-39 Zuellig - 364 Mechanical System Mechanical AHU-L9-02 Air Handling Unit 9th LevelAH-40 Zuellig - 365 Mechanical System Mechanical AHU-L10-02 Air Handling Unit 10th LevelAH-41 Zuellig - 366 Mechanical System Mechanical AHU-L11-02 Air Handling Unit 11th LevelAH-42 Zuellig - 367 Mechanical System Mechanical AHU-L12-02 Air Handling Unit 12th LevelAH-43 Zuellig - 368 Mechanical System Mechanical AHU-L13-02 Air Handling Unit 13th LevelAH-44 Zuellig - 369 Mechanical System Mechanical AHU-L14-02 Air Handling Unit 14th LevelAH-45 Zuellig - 370 Mechanical System Mechanical AHU-L15-02 Air Handling Unit 15th LevelAH-46 Zuellig - 371 Mechanical System Mechanical AHU-L16-02 Air Handling Unit 16th LevelAH-47 Zuellig - 372 Mechanical System Mechanical AHU-L17-02 Air Handling Unit 17th LevelAH-48 Zuellig - 373 Mechanical System Mechanical AHU-L18-02 Air Handling Unit 18th LevelAH-49 Zuellig - 374 Mechanical System Mechanical AHU-L19-02 Air Handling Unit 19th LevelAH-50 Zuellig - 375 Mechanical System Mechanical AHU-L20-02 Air Handling Unit 20th LevelAH-51 Zuellig - 376 Mechanical System Mechanical AHU-L21-02 Air Handling Unit 21st LevelAH-52 Zuellig - 377 Mechanical System Mechanical AHU-L22-02 Air Handling Unit 22nd LevelAH-53 Zuellig - 378 Mechanical System Mechanical AHU-L23-02 Air Handling Unit 23rd LevelAH-54 Zuellig - 379 Mechanical System Mechanical AHU-L24-02 Air Handling Unit 24th LevelAH-55 Zuellig - 380 Mechanical System Mechanical AHU-L25-02 Air Handling Unit 25th LevelAH-56 Zuellig - 381 Mechanical System Mechanical AHU-L26-02 Air Handling Unit 26th LevelAH-57 Zuellig - 382 Mechanical System Mechanical AHU-L27-02 Air Handling Unit 27th LevelAH-58 Zuellig - 383 Mechanical System Mechanical AHU-L28-02 Air Handling Unit 28th LevelAH-59 Zuellig - 384 Mechanical System Mechanical AHU-L29-02 Air Handling Unit 29th LevelAH-60 Zuellig - 385 Mechanical System Mechanical AHU-L30-01 Air Handling Unit 30th LevelAH-61 Zuellig - 386 Mechanical System Mechanical AHU-L31-01 Air Handling Unit 31st LevelAH-62 Zuellig - 387 Mechanical System Mechanical AHU-L32-01 Air Handling Unit 32nd LevelAH-63 Zuellig - 388 Mechanical System Mechanical AHU-L33-01 Air Handling Unit 33rd Level
FC/AC-01 Zuellig - 389 Mechanical System Mechanical FCU/ACCU-DX-R-01A FCU - DX Type Roof DeckFC/AC-02 Zuellig - 390 Mechanical System Mechanical FCU/ACCU-DX-R-01B FCU - DX Type Roof DeckFC/AC-03 Zuellig - 391 Mechanical System Mechanical FCU/ACCU-DX-R-01C FCU - DX Type Roof DeckFC/AC-04 Zuellig - 392 Mechanical System Mechanical FCU/ACCU-DX-R-02 FCU - DX Type Roof DeckFC/AC-05 Zuellig - 393 Mechanical System Mechanical FCU/ACCU-B1-03B FCU - DX Type Bsmt 1FC/AC-06 Zuellig - 394 Mechanical System Mechanical FCU/ACCU-B1-04B FCU - DX Type Bsmt 1FC/AC-07 Zuellig - 395 Mechanical System Mechanical FCU/ACCU-G-08B FCU - DX Type 1st LevelFC/AC-08 Zuellig - 396 Mechanical System Mechanical FCU/ACCU-G-01 FCU - DX Type 1st LevelFC/AC-09 Zuellig - 397 Mechanical System Mechanical FCU/ACCU-G-02 FCU - DX Type 1st LevelFC/AC-10 Zuellig - 398 Mechanical System Mechanical FCU/ACCU-B1-05 FCU - DX Type Bsmt 1FC/AC-11 Zuellig - 399 Mechanical System Mechanical FCU/ACCU-B1-06 FCU - DX Type Bsmt 1FC/AC-12 Zuellig - 400 Mechanical System Mechanical FCU/ACCU-B2-04B FCU - DX Type Bsmt 2
FC-01 Zuellig - 401 Mechanical System Mechanical FCU-B5-01 Fan Coil Unit Bsmt 5FC-02 Zuellig - 402 Mechanical System Mechanical FCU-B5-02 Fan Coil Unit Bsmt 5FC-03 Zuellig - 403 Mechanical System Mechanical FCU-B5-03 Fan Coil Unit Bsmt 5FC-04 Zuellig - 404 Mechanical System Mechanical FCU-B4-01 Fan Coil Unit Bsmt 4FC-05 Zuellig - 405 Mechanical System Mechanical FCU-B4-02 Fan Coil Unit Bsmt 4FC-06 Zuellig - 406 Mechanical System Mechanical FCU-B4-03 Fan Coil Unit Bsmt 4FC-07 Zuellig - 407 Mechanical System Mechanical FCU-B4-04 Fan Coil Unit Bsmt 4FC-08 Zuellig - 408 Mechanical System Mechanical FCU-B4-05 Fan Coil Unit Bsmt 4FC-08 Zuellig - 408 Mechanical System Mechanical FCU-B3-01 Fan Coil Unit Bsmt 3FC-09 Zuellig - 409 Mechanical System Mechanical FCU-B3-02 Fan Coil Unit Bsmt 3
_________________________________________________________________________________ Commissioning Plan Page 40 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
FC-10 Zuellig - 410 Mechanical System Mechanical FCU-B3-03 Fan Coil Unit Bsmt 3FC-11 Zuellig - 411 Mechanical System Mechanical FCU-B3-04 Fan Coil Unit Bsmt 3FC-12 Zuellig - 412 Mechanical System Mechanical FCU-B3-05 Fan Coil Unit Bsmt 3FC-13 Zuellig - 413 Mechanical System Mechanical FCU-B3-06 Fan Coil Unit Bsmt 3FC-14 Zuellig - 414 Mechanical System Mechanical FCU-B3-07 Fan Coil Unit Bsmt 3FC-15 Zuellig - 415 Mechanical System Mechanical FCU-B3-09 Fan Coil Unit Bsmt 3FC-16 Zuellig - 416 Mechanical System Mechanical FCU-B2-01 Fan Coil Unit Bsmt 2FC-17 Zuellig - 417 Mechanical System Mechanical FCU-B2-02 Fan Coil Unit Bsmt 2FC-18 Zuellig - 418 Mechanical System Mechanical FCU-B2-03A Fan Coil Unit Bsmt 2FC-19 Zuellig - 419 Mechanical System Mechanical FCU-B2-04 Fan Coil Unit Bsmt 2FC-20 Zuellig - 420 Mechanical System Mechanical FCU-B1-01 Fan Coil Unit Bsmt 1FC-21 Zuellig - 421 Mechanical System Mechanical FCU-B1-02 Fan Coil Unit Bsmt 1FC-22 Zuellig - 422 Mechanical System Mechanical FCU-B1-03A Fan Coil Unit Bsmt 1FC-23 Zuellig - 423 Mechanical System Mechanical FCU-B1-04A Fan Coil Unit Bsmt 1FC-24 Zuellig - 424 Mechanical System Mechanical FCU-B1-07 Fan Coil Unit Bsmt 1FC-25 Zuellig - 425 Mechanical System Mechanical FCU-G-01A Fan Coil Unit 1st LevelFC-26 Zuellig - 426 Mechanical System Mechanical FCU-G-01B Fan Coil Unit 1st LevelFC-27 Zuellig - 427 Mechanical System Mechanical FCU-G-01C Fan Coil Unit 1st LevelFC-28 Zuellig - 428 Mechanical System Mechanical FCU-G-01D Fan Coil Unit 1st LevelFC-29 Zuellig - 429 Mechanical System Mechanical FCU-G-02 Fan Coil Unit 1st LevelFC-30 Zuellig - 430 Mechanical System Mechanical FCU-G-03 Fan Coil Unit 1st LevelFC-31 Zuellig - 431 Mechanical System Mechanical FCU-G-04 Fan Coil Unit 1st LevelFC-32 Zuellig - 432 Mechanical System Mechanical FCU-G-05 Fan Coil Unit 1st LevelFC-33 Zuellig - 433 Mechanical System Mechanical FCU-G-06 Fan Coil Unit 1st LevelFC-34 Zuellig - 434 Mechanical System Mechanical FCU-G-07 Fan Coil Unit 1st LevelFC-35 Zuellig - 435 Mechanical System Mechanical FCU-G-08A Fan Coil Unit 1st LevelFC-36 Zuellig - 436 Mechanical System Mechanical FCU-G-09 Fan Coil Unit 1st LevelFC-37 Zuellig - 437 Mechanical System Mechanical FCU-G-10 Fan Coil Unit 1st LevelFC-38 Zuellig - 438 Mechanical System Mechanical FCU-L2-02 Fan Coil Unit 2nd LevelFC-39 Zuellig - 439 Mechanical System Mechanical FCU-L3-01 Fan Coil Unit 3rd LevelFC-40 Zuellig - 440 Mechanical System Mechanical FCU-L3-01 Fan Coil Unit 3rd LevelFC-41 Zuellig - 441 Mechanical System Mechanical FCU-L3-02 Fan Coil Unit 3rd LevelFC-42 Zuellig - 442 Mechanical System Mechanical FCU-L3-03 Fan Coil Unit 3rd LevelFC-43 Zuellig - 443 Mechanical System Mechanical FCU-L3-04 Fan Coil Unit 3rd LevelFC-44 Zuellig - 444 Mechanical System Mechanical FCU-L4-01 Fan Coil Unit 4th LevelFC-45 Zuellig - 445 Mechanical System Mechanical FCU-L5-01 Fan Coil Unit 5th LevelFC-46 Zuellig - 446 Mechanical System Mechanical FCU-L6-01 Fan Coil Unit 6th LevelFC-47 Zuellig - 447 Mechanical System Mechanical FCU-L7-01 Fan Coil Unit 7th LevelFC-48 Zuellig - 448 Mechanical System Mechanical FCU-L8-01 Fan Coil Unit 8th LevelFC-49 Zuellig - 449 Mechanical System Mechanical FCU-L9-01 Fan Coil Unit 9th LevelFC-50 Zuellig - 450 Mechanical System Mechanical FCU-L10-01 Fan Coil Unit 10th LevelFC-51 Zuellig - 451 Mechanical System Mechanical FCU-L11-01 Fan Coil Unit 11th LevelFC-52 Zuellig - 452 Mechanical System Mechanical FCU-L12-01 Fan Coil Unit 12th LevelFC-53 Zuellig - 453 Mechanical System Mechanical FCU-L13-01 Fan Coil Unit 13th LevelFC-54 Zuellig - 454 Mechanical System Mechanical FCU-L14-01 Fan Coil Unit 14th LevelFC-55 Zuellig - 455 Mechanical System Mechanical FCU-L15-01 Fan Coil Unit 15th LevelFC-56 Zuellig - 456 Mechanical System Mechanical FCU-L16-01 Fan Coil Unit 16th LevelFC-57 Zuellig - 457 Mechanical System Mechanical FCU-L17-01 Fan Coil Unit 17th LevelFC-58 Zuellig - 458 Mechanical System Mechanical FCU-L18-01 Fan Coil Unit 18th LevelFC-59 Zuellig - 459 Mechanical System Mechanical FCU-L19-01 Fan Coil Unit 19th LevelFC-60 Zuellig - 460 Mechanical System Mechanical FCU-L20-01 Fan Coil Unit 20th LevelFC-61 Zuellig - 461 Mechanical System Mechanical FCU-L21-01 Fan Coil Unit 21st LevelFC-62 Zuellig - 462 Mechanical System Mechanical FCU-L22-01 Fan Coil Unit 22nd LevelFC-63 Zuellig - 463 Mechanical System Mechanical FCU-L23-01 Fan Coil Unit 23rd LevelFC-64 Zuellig - 464 Mechanical System Mechanical FCU-L24-01 Fan Coil Unit 24th LevelFC-65 Zuellig - 465 Mechanical System Mechanical FCU-L25-01 Fan Coil Unit 25th Level
_________________________________________________________________________________ Commissioning Plan Page 41 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
FC-66 Zuellig - 466 Mechanical System Mechanical FCU-L26-01 Fan Coil Unit 26th LevelFC-67 Zuellig - 467 Mechanical System Mechanical FCU-L27-01 Fan Coil Unit 27th LevelFC-68 Zuellig - 468 Mechanical System Mechanical FCU-L28-01 Fan Coil Unit 28th LevelFC-69 Zuellig - 469 Mechanical System Mechanical FCU-L29-01 Fan Coil Unit 29th LevelFC-70 Zuellig - 470 Mechanical System Mechanical FCU-L30-01 Fan Coil Unit 30th LevelFC-71 Zuellig - 471 Mechanical System Mechanical FCU-L31-01 Fan Coil Unit 31st LevelFC-72 Zuellig - 472 Mechanical System Mechanical FCU-L32-01 Fan Coil Unit 32nd LevelFC-73 Zuellig - 473 Mechanical System Mechanical FCU-L33-01 Fan Coil Unit 33rd LevelFC-74 Zuellig - 474 Mechanical System Mechanical FCU-L3-02 Fan Coil Unit 3rd LevelFC-75 Zuellig - 475 Mechanical System Mechanical FCU-L4-02 Fan Coil Unit 4th LevelFC-76 Zuellig - 476 Mechanical System Mechanical FCU-L5-02 Fan Coil Unit 5th LevelFC-77 Zuellig - 477 Mechanical System Mechanical FCU-L6-02 Fan Coil Unit 6th LevelFC-78 Zuellig - 478 Mechanical System Mechanical FCU-L7-02 Fan Coil Unit 7th LevelFC-79 Zuellig - 479 Mechanical System Mechanical FCU-L8-02 Fan Coil Unit 8th LevelFC-80 Zuellig - 480 Mechanical System Mechanical FCU-L9-02 Fan Coil Unit 9th LevelFC-81 Zuellig - 481 Mechanical System Mechanical FCU-L10-02 Fan Coil Unit 10th LevelFC-82 Zuellig - 482 Mechanical System Mechanical FCU-L11-02 Fan Coil Unit 11th LevelFC-83 Zuellig - 483 Mechanical System Mechanical FCU-L12-02 Fan Coil Unit 12th LevelFC-84 Zuellig - 484 Mechanical System Mechanical FCU-L13-02 Fan Coil Unit 13th LevelFC-85 Zuellig - 485 Mechanical System Mechanical FCU-L14-02 Fan Coil Unit 14th LevelFC-86 Zuellig - 486 Mechanical System Mechanical FCU-L15-02 Fan Coil Unit 15th LevelFC-87 Zuellig - 487 Mechanical System Mechanical FCU-L16-02 Fan Coil Unit 16th LevelFC-88 Zuellig - 488 Mechanical System Mechanical FCU-L17-02 Fan Coil Unit 17th LevelFC-89 Zuellig - 489 Mechanical System Mechanical FCU-L18-02 Fan Coil Unit 18th LevelFC-90 Zuellig - 490 Mechanical System Mechanical FCU-L19-02 Fan Coil Unit 19th LevelFC-91 Zuellig - 491 Mechanical System Mechanical FCU-L20-02 Fan Coil Unit 20th LevelFC-92 Zuellig - 492 Mechanical System Mechanical FCU-L21-02 Fan Coil Unit 21st LevelFC-93 Zuellig - 493 Mechanical System Mechanical FCU-L22-02 Fan Coil Unit 22nd LevelFC-94 Zuellig - 494 Mechanical System Mechanical FCU-L23-02 Fan Coil Unit 23rd LevelFC-95 Zuellig - 495 Mechanical System Mechanical FCU-L24-02 Fan Coil Unit 24th LevelFC-96 Zuellig - 496 Mechanical System Mechanical FCU-L25-02 Fan Coil Unit 25th LevelFC-97 Zuellig - 497 Mechanical System Mechanical FCU-L26-02 Fan Coil Unit 26th LevelFC-98 Zuellig - 498 Mechanical System Mechanical FCU-L27-02 Fan Coil Unit 27th LevelFC-99 Zuellig - 499 Mechanical System Mechanical FCU-L28-02 Fan Coil Unit 28th Level
FC-100 Zuellig - 500 Mechanical System Mechanical FCU-L29-02 Fan Coil Unit 29th LevelFC-101 Zuellig - 501 Mechanical System Mechanical FCU-L30-02 Fan Coil Unit 30th LevelFC-102 Zuellig - 502 Mechanical System Mechanical FCU-L31-02 Fan Coil Unit 31st LevelFC-103 Zuellig - 503 Mechanical System Mechanical FCU-L32-02 Fan Coil Unit 32nd LevelFC-104 Zuellig - 504 Mechanical System Mechanical FCU-L33-02 Fan Coil Unit 33rd LevelFC-105 Zuellig - 505 Mechanical System Mechanical FCU-L31-03A Fan Coil Unit 31st LevelFC-106 Zuellig - 506 Mechanical System Mechanical FCU-L31-03B Fan Coil Unit 31st LevelFC-107 Zuellig - 507 Mechanical System Mechanical FCU-L31-03C Fan Coil Unit 31st LevelFC-108 Zuellig - 508 Mechanical System Mechanical FCU-L21-03A Fan Coil Unit 21st LevelFC-109 Zuellig - 509 Mechanical System Mechanical FCU-L21-03B Fan Coil Unit 21st LevelFC-110 Zuellig - 510 Mechanical System Mechanical FCU-L21-03C Fan Coil Unit 21st LevelFC-111 Zuellig - 511 Mechanical System Mechanical FCU-L21-03D Fan Coil Unit 21st LevelFC-112 Zuellig - 512 Mechanical System Mechanical FCU-R-01A Fan Coil Unit Roof DeckFC-113 Zuellig - 513 Mechanical System Mechanical FCU-R-01B Fan Coil Unit Roof DeckFC-114 Zuellig - 514 Mechanical System Mechanical FCU-R-01C Fan Coil Unit Roof DeckFC-115 Zuellig - 515 Mechanical System Mechanical FCU-R-02 Fan Coil Unit Roof DeckFC-116 Zuellig - 516 Mechanical System Mechanical FCU-B4-05 Fan Coil Unit Bsmt 4EF-01 Zuellig - 517 Mechanical System Mechanical SF-R-01 Supply Fan Roof DeckEF-02 Zuellig - 518 Mechanical System Mechanical SF-R-02 Supply Fan Roof DeckEF-03 Zuellig - 519 Mechanical System Mechanical SF-R-03 Supply Fan Roof DeckEF-04 Zuellig - 520 Mechanical System Mechanical SF-R-04 Supply Fan Roof DeckEF-05 Zuellig - 521 Mechanical System Mechanical EF-B5-01 Exhaust Fan Bsmt 5
_________________________________________________________________________________ Commissioning Plan Page 42 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
EF-06 Zuellig - 522 Mechanical System Mechanical EF-B5-02 Exhaust Fan Bsmt 5EF-07 Zuellig - 523 Mechanical System Mechanical EF-B5-03 Exhaust Fan Bsmt 5EF-08 Zuellig - 524 Mechanical System Mechanical EF-B5-04 Exhaust Fan Bsmt 5EF-09 Zuellig - 525 Mechanical System Mechanical EF-B5-05 Exhaust Fan Bsmt 5EF-10 Zuellig - 526 Mechanical System Mechanical EF-B5-06 Exhaust Fan Bsmt 5EF-11 Zuellig - 527 Mechanical System Mechanical EF-B5-07 Exhaust Fan Bsmt 5EF-12 Zuellig - 528 Mechanical System Mechanical EF-B5-08A Exhaust Fan Bsmt 5EF-13 Zuellig - 529 Mechanical System Mechanical EF-B5-08B Exhaust Fan Bsmt 5EF-14 Zuellig - 530 Mechanical System Mechanical EF-B5-08C Exhaust Fan Bsmt 5EF-15 Zuellig - 531 Mechanical System Mechanical EF-B4-01 Exhaust Fan Bsmt 4EF-16 Zuellig - 532 Mechanical System Mechanical EF-B4-02 Exhaust Fan Bsmt 4EF-17 Zuellig - 533 Mechanical System Mechanical EF-B4-03 Exhaust Fan Bsmt 4EF-18 Zuellig - 534 Mechanical System Mechanical EF-B4-04 Exhaust Fan Bsmt 4EF-19 Zuellig - 535 Mechanical System Mechanical EF-B4-05 Exhaust Fan Bsmt 4EF-20 Zuellig - 536 Mechanical System Mechanical EF-B4-06 Exhaust Fan Bsmt 4EF-21 Zuellig - 537 Mechanical System Mechanical EF-B4-07 Exhaust Fan Bsmt 4EF-22 Zuellig - 538 Mechanical System Mechanical EF-B4-08 Exhaust Fan Bsmt 4EF-23 Zuellig - 539 Mechanical System Mechanical EF-B4-09 Exhaust Fan Bsmt 4EF-24 Zuellig - 540 Mechanical System Mechanical EF-B4-09A Exhaust Fan Bsmt 4EF-25 Zuellig - 541 Mechanical System Mechanical EF-B4-09B Exhaust Fan Bsmt 4EF-26 Zuellig - 542 Mechanical System Mechanical EF-B3-01 Exhaust Fan Bsmt 3EF-27 Zuellig - 543 Mechanical System Mechanical EF-B3-02 Exhaust Fan Bsmt 3EF-28 Zuellig - 544 Mechanical System Mechanical EF-B3-03 Exhaust Fan Bsmt 3EF-29 Zuellig - 545 Mechanical System Mechanical EF-B3-04 Exhaust Fan Bsmt 3EF-30 Zuellig - 546 Mechanical System Mechanical EF-B3-05 Exhaust Fan Bsmt 3EF-31 Zuellig - 547 Mechanical System Mechanical EF-B3-06 Exhaust Fan Bsmt 3EF-32 Zuellig - 548 Mechanical System Mechanical EF-B3-07 Exhaust Fan Bsmt 3EF-33 Zuellig - 549 Mechanical System Mechanical EF-B3-09 Exhaust Fan Bsmt 3EF-34 Zuellig - 550 Mechanical System Mechanical EF-B3-10A Exhaust Fan Bsmt 3EF-35 Zuellig - 551 Mechanical System Mechanical EF-B3-10B Exhaust Fan Bsmt 3EF-36 Zuellig - 552 Mechanical System Mechanical EF-B3-11 Exhaust Fan Bsmt 3EF-37 Zuellig - 553 Mechanical System Mechanical EF-B3-12 Exhaust Fan Bsmt 3EF-38 Zuellig - 554 Mechanical System Mechanical EF-B3-13 Exhaust Fan Bsmt 3EF-39 Zuellig - 555 Mechanical System Mechanical EF-40 Zuellig - 556 Mechanical System Mechanical EF-B2-01 Exhaust Fan Bsmt 2EF-41 Zuellig - 557 Mechanical System Mechanical EF-B2-02 Exhaust Fan Bsmt 2EF-42 Zuellig - 558 Mechanical System Mechanical EF-B2-03 Exhaust Fan Bsmt 2EF-43 Zuellig - 559 Mechanical System Mechanical EF-B2-04 Exhaust Fan Bsmt 2EF-44 Zuellig - 560 Mechanical System Mechanical EF-B2-05 Exhaust Fan Bsmt 2EF-45 Zuellig - 561 Mechanical System Mechanical EF-B2-06 Exhaust Fan Bsmt 2EF-46 Zuellig - 562 Mechanical System Mechanical EF-B2-07 Exhaust Fan Bsmt 2EF-47 Zuellig - 563 Mechanical System Mechanical EF-B2-08 Exhaust Fan Bsmt 2EF-48 Zuellig - 564 Mechanical System Mechanical EF-B2-09 Exhaust Fan Bsmt 2EF-49 Zuellig - 565 Mechanical System Mechanical EF-B2-10 Exhaust Fan Bsmt 2EF-50 Zuellig - 566 Mechanical System Mechanical EF-B1-01 Exhaust Fan Bsmt 1EF-51 Zuellig - 567 Mechanical System Mechanical EF-B1-02 Exhaust Fan Bsmt 1EF-52 Zuellig - 568 Mechanical System Mechanical EF-B1-03 Exhaust Fan Bsmt 1EF-53 Zuellig - 569 Mechanical System Mechanical EF-B1-04 Exhaust Fan Bsmt 1EF-54 Zuellig - 570 Mechanical System Mechanical EF-B1-05 Exhaust Fan Bsmt 1EF-55 Zuellig - 571 Mechanical System Mechanical EF-B1-06 Exhaust Fan Bsmt 1EF-56 Zuellig - 572 Mechanical System Mechanical EF-B1-07 Exhaust Fan Bsmt 1EF-57 Zuellig - 573 Mechanical System Mechanical EF-B1-08 Exhaust Fan Bsmt 1EF-58 Zuellig - 574 Mechanical System Mechanical EF-B1-09 Exhaust Fan Bsmt 1EF-59 Zuellig - 575 Mechanical System Mechanical EF-B1-10A Exhaust Fan Bsmt 1EF-60 Zuellig - 576 Mechanical System Mechanical EF-B1-10B Exhaust Fan Bsmt 1EF-61 Zuellig - 577 Mechanical System Mechanical EF-B1-11A Exhaust Fan Bsmt 1
_________________________________________________________________________________ Commissioning Plan Page 43 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
EF-62 Zuellig - 578 Mechanical System Mechanical EF-B1-11B Exhaust Fan Bsmt 1EF-63 Zuellig - 579 Mechanical System Mechanical EF-B1-015 Exhaust Fan Bsmt 1EF-64 Zuellig - 580 Mechanical System Mechanical EF-65 Zuellig - 581 Mechanical System Mechanical EF-B1-12A Exhaust Fan Bsmt 1EF-66 Zuellig - 582 Mechanical System Mechanical EF-B1-12B Exhaust Fan Bsmt 1EF-65 Zuellig - 581 Mechanical System Mechanical EF-B1-13A Exhaust Fan Bsmt 1EF-66 Zuellig - 582 Mechanical System Mechanical EF-B1-13B Exhaust Fan Bsmt 1EF-67 Zuellig - 583 Mechanical System Mechanical EF-B1-14 Exhaust Fan Bsmt 1EF-68 Zuellig - 584 Mechanical System Mechanical EF-G-01 Exhaust Fan 1st LevelEF-69 Zuellig - 585 Mechanical System Mechanical EF-G-02 Exhaust Fan 1st LevelEF-70 Zuellig - 586 Mechanical System Mechanical EF-G-03 Exhaust Fan 1st LevelEF-71 Zuellig - 587 Mechanical System Mechanical EF-G-04 Exhaust Fan 1st LevelEF-72 Zuellig - 588 Mechanical System Mechanical EF-G-05 Exhaust Fan 1st LevelEF-73 Zuellig - 589 Mechanical System Mechanical EF-L2-01 Exhaust Fan 2nd LevelEF-74 Zuellig - 590 Mechanical System Mechanical EF-L32-01 Exhaust Fan 32nd LevelEF-75 Zuellig - 591 Mechanical System Mechanical EF-L33-01 Exhaust Fan 33rd LevelEF-76 Zuellig - 592 Mechanical System Mechanical EF-R-01 Exhaust Fan Roof DeckEF-77 Zuellig - 593 Mechanical System Mechanical EF-R-02 Exhaust Fan Roof DeckEF-78 Zuellig - 594 Mechanical System Mechanical EF-R-03 Exhaust Fan Roof DeckEF-79 Zuellig - 595 Mechanical System Mechanical EF-R-04 Exhaust Fan Roof DeckEF-80 Zuellig - 596 Mechanical System Mechanical SF-B5-01 Supply Fan Bsmt 5EF-81 Zuellig - 597 Mechanical System Mechanical SF-B5-02 Supply Fan Bsmt 5EF-82 Zuellig - 598 Mechanical System Mechanical SF-B5-03 Supply Fan Bsmt 5EF-83 Zuellig - 599 Mechanical System Mechanical SF-B5-04 Supply Fan Bsmt 5EF-84 Zuellig - 600 Mechanical System Mechanical SF-B4-01 Supply Fan Bsmt 4EF-85 Zuellig - 601 Mechanical System Mechanical SF-B4-02 Supply Fan Bsmt 4EF-86 Zuellig - 602 Mechanical System Mechanical SF-B4-03 Supply Fan Bsmt 4EF-87 Zuellig - 603 Mechanical System Mechanical SF-B4-04 Supply Fan Bsmt 4EF-88 Zuellig - 604 Mechanical System Mechanical SF-B4-05A Supply Fan Bsmt 4EF-89 Zuellig - 605 Mechanical System Mechanical SF-B4-05B Supply Fan Bsmt 4EF-90 Zuellig - 606 Mechanical System Mechanical SF-B4-06 Supply Fan Bsmt 4EF-91 Zuellig - 607 Mechanical System Mechanical SF-B3-01 Supply Fan Bsmt 3EF-92 Zuellig - 608 Mechanical System Mechanical SF-B3-02 Supply Fan Bsmt 3EF-93 Zuellig - 609 Mechanical System Mechanical SF-B3-03 Supply Fan Bsmt 3EF-94 Zuellig - 610 Mechanical System Mechanical SF-B3-04 Supply Fan Bsmt 3EF-95 Zuellig - 611 Mechanical System Mechanical SF-B3-05A Supply Fan Bsmt 3EF-96 Zuellig - 612 Mechanical System Mechanical SF-B3-05B Supply Fan Bsmt 3EF-97 Zuellig - 613 Mechanical System Mechanical SF-B3-06 Supply Fan Bsmt 3EF-98 Zuellig - 614 Mechanical System Mechanical SF-B2-01 Supply Fan Bsmt 2EF-99 Zuellig - 615 Mechanical System Mechanical SF-B2-02 Supply Fan Bsmt 2EF-100 Zuellig - 616 Mechanical System Mechanical SF-B2-03 Supply Fan Bsmt 2EF-101 Zuellig - 617 Mechanical System Mechanical SF-B1-01A Supply Fan Bsmt 1EF-102 Zuellig - 618 Mechanical System Mechanical SF-B1-01B Supply Fan Bsmt 1EF-103 Zuellig - 619 Mechanical System Mechanical SF-G-01 Supply Fan 1st LevelEF-104 Zuellig - 620 Mechanical System Mechanical JF-B5-01.1 Jet Fan Bsmt 5EF-105 Zuellig - 621 Mechanical System Mechanical JF-B5-01.2 Jet Fan Bsmt 5EF-106 Zuellig - 622 Mechanical System Mechanical JF-B5-01.3 Jet Fan Bsmt 5EF-107 Zuellig - 623 Mechanical System Mechanical JF-B5-01.4 Jet Fan Bsmt 5EF-108 Zuellig - 624 Mechanical System Mechanical JF-B5-01.5 Jet Fan Bsmt 5EF-109 Zuellig - 625 Mechanical System Mechanical JF-B5-01.6 Jet Fan Bsmt 5EF-110 Zuellig - 626 Mechanical System Mechanical JF-B5-01.7 Jet Fan Bsmt 5EF-111 Zuellig - 627 Mechanical System Mechanical JF-B5-01.8 Jet Fan Bsmt 5EF-112 Zuellig - 628 Mechanical System Mechanical JF-B5-01.9 Jet Fan Bsmt 5EF-113 Zuellig - 629 Mechanical System Mechanical JF-B5-01.10 Jet Fan Bsmt 5EF-114 Zuellig - 630 Mechanical System Mechanical JF-B5-01.11 Jet Fan Bsmt 5EF-115 Zuellig - 631 Mechanical System Mechanical JF-B4-01.1 Jet Fan Bsmt 4
_________________________________________________________________________________ Commissioning Plan Page 44 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
EF-116 Zuellig - 632 Mechanical System Mechanical JF-B4-01.2 Jet Fan Bsmt 4EF-117 Zuellig - 633 Mechanical System Mechanical JF-B4-01.3 Jet Fan Bsmt 4EF-118 Zuellig - 634 Mechanical System Mechanical JF-B4-01.4 Jet Fan Bsmt 4EF-119 Zuellig - 635 Mechanical System Mechanical JF-B4-01.5 Jet Fan Bsmt 4EF-120 Zuellig - 636 Mechanical System Mechanical JF-B4-01.6 Jet Fan Bsmt 4EF-121 Zuellig - 637 Mechanical System Mechanical JF-B4-01.7 Jet Fan Bsmt 4EF-122 Zuellig - 638 Mechanical System Mechanical JF-B4-01.8 Jet Fan Bsmt 4EF-123 Zuellig - 639 Mechanical System Mechanical JF-B4-01.9 Jet Fan Bsmt 4EF-124 Zuellig - 640 Mechanical System Mechanical JF-B4-01.10 Jet Fan Bsmt 4EF-125 Zuellig - 641 Mechanical System Mechanical JF-B4-01.11 Jet Fan Bsmt 4EF-126 Zuellig - 642 Mechanical System Mechanical JF-B3-01.1 Jet Fan Bsmt 3EF-127 Zuellig - 643 Mechanical System Mechanical JF-B3-01.2 Jet Fan Bsmt 3EF-128 Zuellig - 644 Mechanical System Mechanical JF-B3-01.3 Jet Fan Bsmt 3EF-129 Zuellig - 645 Mechanical System Mechanical JF-B3-01.4 Jet Fan Bsmt 3EF-130 Zuellig - 646 Mechanical System Mechanical JF-B3-01.5 Jet Fan Bsmt 3EF-131 Zuellig - 647 Mechanical System Mechanical JF-B3-01.6 Jet Fan Bsmt 3EF-132 Zuellig - 648 Mechanical System Mechanical JF-B3-01.7 Jet Fan Bsmt 3EF-133 Zuellig - 649 Mechanical System Mechanical JF-B3-01.8 Jet Fan Bsmt 3EF-134 Zuellig - 650 Mechanical System Mechanical JF-B3-01.9 Jet Fan Bsmt 3EF-135 Zuellig - 651 Mechanical System Mechanical JF-B3-01.10 Jet Fan Bsmt 3EF-136 Zuellig - 652 Mechanical System Mechanical JF-B3-01.11 Jet Fan Bsmt 3EF-137 Zuellig - 653 Mechanical System Mechanical JF-B2-01.1 Jet Fan Bsmt 2EF-138 Zuellig - 654 Mechanical System Mechanical JF-B2-01.2 Jet Fan Bsmt 2EF-139 Zuellig - 655 Mechanical System Mechanical JF-B2-01.3 Jet Fan Bsmt 2EF-140 Zuellig - 656 Mechanical System Mechanical JF-B2-01.4 Jet Fan Bsmt 2EF-141 Zuellig - 657 Mechanical System Mechanical JF-B2-01.5 Jet Fan Bsmt 2EF-142 Zuellig - 658 Mechanical System Mechanical JF-B2-01.6 Jet Fan Bsmt 2EF-143 Zuellig - 659 Mechanical System Mechanical JF-B2-01.7 Jet Fan Bsmt 2EF-144 Zuellig - 660 Mechanical System Mechanical JF-B2-01.8 Jet Fan Bsmt 2EF-145 Zuellig - 661 Mechanical System Mechanical JF-B2-01.9 Jet Fan Bsmt 2EF-146 Zuellig - 662 Mechanical System Mechanical JF-B2-01.10 Jet Fan Bsmt 2EF-147 Zuellig - 663 Mechanical System Mechanical JF-B2-01.11 Jet Fan Bsmt 2EF-148 Zuellig - 664 Mechanical System Mechanical JF-B1-01.1 Jet Fan Bsmt 1EF-149 Zuellig - 665 Mechanical System Mechanical JF-B1-01.2 Jet Fan Bsmt 1EF-150 Zuellig - 666 Mechanical System Mechanical JF-B1-01.3 Jet Fan Bsmt 1EF-151 Zuellig - 667 Mechanical System Mechanical JF-B1-01.4 Jet Fan Bsmt 1EF-152 Zuellig - 668 Mechanical System Mechanical JF-B1-01.5 Jet Fan Bsmt 1EF-153 Zuellig - 669 Mechanical System Mechanical JF-B1-01.6 Jet Fan Bsmt 1EF-154 Zuellig - 670 Mechanical System Mechanical JF-B1-01.7 Jet Fan Bsmt 1EF-155 Zuellig - 671 Mechanical System Mechanical JF-B1-01.8 Jet Fan Bsmt 1EF-156 Zuellig - 672 Mechanical System Mechanical JF-B1-01.9 Jet Fan Bsmt 1EF-157 Zuellig - 673 Mechanical System Mechanical JF-B1-01.10 Jet Fan Bsmt 1EF-158 Zuellig - 674 Mechanical System Mechanical JF-B1-01.11 Jet Fan Bsmt 1EF-159 Zuellig - 675 Mechanical System Mechanical JF-B3-01B Jet Fan Bsmt 3EF-160 Zuellig - 676 Mechanical System Mechanical JF-B3-01C Jet Fan Bsmt 3EF-161 Zuellig - 677 Mechanical System Mechanical JF-B3-01D Jet Fan Bsmt 3EF-162 Zuellig - 678 Mechanical System Mechanical JF-B3-01E Jet Fan Bsmt 3EF-163 Zuellig - 679 Mechanical System Mechanical JF-B3-01F Jet Fan Bsmt 3EF-164 Zuellig - 680 Mechanical System Mechanical JF-B3-02A Jet Fan Bsmt 3EF-165 Zuellig - 681 Mechanical System Mechanical JF-B3-02B Jet Fan Bsmt 3EF-166 Zuellig - 682 Mechanical System Mechanical JF-B3-02C Jet Fan Bsmt 3EF-167 Zuellig - 683 Mechanical System Mechanical JF-B3-03A Jet Fan Bsmt 3EF-168 Zuellig - 684 Mechanical System Mechanical JF-B3-03B Jet Fan Bsmt 3EF-169 Zuellig - 685 Mechanical System Mechanical JF-B3-04A Jet Fan Bsmt 3EF-170 Zuellig - 686 Mechanical System Mechanical JF-B3-04B Jet Fan Bsmt 3EF-171 Zuellig - 687 Mechanical System Mechanical JF-B3-04C Jet Fan Bsmt 3
_________________________________________________________________________________ Commissioning Plan Page 45 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
EF-172 Zuellig - 688 Mechanical System Mechanical JF-B3-04D Jet Fan Bsmt 3EF-173 Zuellig - 689 Mechanical System Mechanical JF-B3-05A Jet Fan Bsmt 3EF-174 Zuellig - 690 Mechanical System Mechanical JF-B3-05B Jet Fan Bsmt 3EF-175 Zuellig - 691 Mechanical System Mechanical JF-B3-05C Jet Fan Bsmt 3EF-176 Zuellig - 692 Mechanical System Mechanical JF-B3-05D Jet Fan Bsmt 3EF-177 Zuellig - 693 Mechanical System Mechanical JF-B3-06A Jet Fan Bsmt 3EF-178 Zuellig - 694 Mechanical System Mechanical JF-B3-06B Jet Fan Bsmt 3EF-179 Zuellig - 695 Mechanical System Mechanical JF-B3-06C Jet Fan Bsmt 3EF-180 Zuellig - 696 Mechanical System Mechanical JF-B3-07A Jet Fan Bsmt 3EF-181 Zuellig - 697 Mechanical System Mechanical JF-B3-07B Jet Fan Bsmt 3EF-182 Zuellig - 698 Mechanical System Mechanical JF-B3-07C Jet Fan Bsmt 3EF-183 Zuellig - 699 Mechanical System Mechanical JF-B3-07D Jet Fan Bsmt 3EF-184 Zuellig - 700 Mechanical System Mechanical JF-B2-01A Jet Fan Bsmt 2EF-185 Zuellig - 701 Mechanical System Mechanical JF-B2-01B Jet Fan Bsmt 2EF-186 Zuellig - 702 Mechanical System Mechanical JF-B2-01C Jet Fan Bsmt 2EF-187 Zuellig - 703 Mechanical System Mechanical JF-B2-01D Jet Fan Bsmt 2EF-188 Zuellig - 704 Mechanical System Mechanical JF-B2-02A Jet Fan Bsmt 2EF-189 Zuellig - 705 Mechanical System Mechanical JF-B2-02B Jet Fan Bsmt 2EF-190 Zuellig - 706 Mechanical System Mechanical JF-B2-03A Jet Fan Bsmt 2EF-191 Zuellig - 707 Mechanical System Mechanical JF-B2-03B Jet Fan Bsmt 2EF-192 Zuellig - 708 Mechanical System Mechanical JF-B2-04A Jet Fan Bsmt 2EF-193 Zuellig - 709 Mechanical System Mechanical JF-B2-04B Jet Fan Bsmt 2EF-194 Zuellig - 710 Mechanical System Mechanical JF-B2-04C Jet Fan Bsmt 2EF-195 Zuellig - 711 Mechanical System Mechanical JF-B2-05A Jet Fan Bsmt 2EF-196 Zuellig - 712 Mechanical System Mechanical JF-B2-05B Jet Fan Bsmt 2EF-197 Zuellig - 713 Mechanical System Mechanical JF-B2-05C Jet Fan Bsmt 2EF-198 Zuellig - 714 Mechanical System Mechanical JF-B2-06A Jet Fan Bsmt 2EF-199 Zuellig - 715 Mechanical System Mechanical JF-B2-06B Jet Fan Bsmt 2EF-200 Zuellig - 716 Mechanical System Mechanical JF-B2-06C Jet Fan Bsmt 2EF-201 Zuellig - 717 Mechanical System Mechanical JF-B2-06D Jet Fan Bsmt 2EF-202 Zuellig - 718 Mechanical System Mechanical JF-B2-07A Jet Fan Bsmt 2EF-203 Zuellig - 719 Mechanical System Mechanical JF-B2-07B Jet Fan Bsmt 2EF-204 Zuellig - 720 Mechanical System Mechanical JF-B2-07C Jet Fan Bsmt 2EF-205 Zuellig - 721 Mechanical System Mechanical JF-B2-07D Jet Fan Bsmt 2EF-206 Zuellig - 722 Mechanical System Mechanical JF-B1-01A Jet Fan Bsmt 1EF-207 Zuellig - 723 Mechanical System Mechanical JF-B1-01B Jet Fan Bsmt 1EF-208 Zuellig - 724 Mechanical System Mechanical JF-B1-01C Jet Fan Bsmt 1EF-209 Zuellig - 725 Mechanical System Mechanical JF-B1-01D Jet Fan Bsmt 1EF-210 Zuellig - 726 Mechanical System Mechanical JF-B1-02A Jet Fan Bsmt 1EF-211 Zuellig - 727 Mechanical System Mechanical JF-B1-02B Jet Fan Bsmt 1EF-212 Zuellig - 728 Mechanical System Mechanical JF-B1-03A Jet Fan Bsmt 1EF-213 Zuellig - 729 Mechanical System Mechanical JF-B1-03B Jet Fan Bsmt 1EF-214 Zuellig - 730 Mechanical System Mechanical JF-B1-04A Jet Fan Bsmt 1EF-215 Zuellig - 731 Mechanical System Mechanical JF-B1-04B Jet Fan Bsmt 1EF-216 Zuellig - 732 Mechanical System Mechanical JF-B1-04C Jet Fan Bsmt 1EF-217 Zuellig - 733 Mechanical System Mechanical JF-B1-04D Jet Fan Bsmt 1EF-218 Zuellig - 734 Mechanical System Mechanical JF-B1-05A Jet Fan Bsmt 1EF-219 Zuellig - 735 Mechanical System Mechanical JF-B1-05B Jet Fan Bsmt 1EF-220 Zuellig - 736 Mechanical System Mechanical JF-B1-05C Jet Fan Bsmt 1EF-221 Zuellig - 737 Mechanical System Mechanical JF-B1-06A Jet Fan Bsmt 1EF-222 Zuellig - 738 Mechanical System Mechanical JF-B1-06B Jet Fan Bsmt 1EF-223 Zuellig - 739 Mechanical System Mechanical JF-B1-06C Jet Fan Bsmt 1EF-224 Zuellig - 740 Mechanical System Mechanical JF-B1-07A Jet Fan Bsmt 1EF-225 Zuellig - 741 Mechanical System Mechanical JF-B1-07B Jet Fan Bsmt 1EF-226 Zuellig - 742 Mechanical System Mechanical JF-B1-07C Jet Fan Bsmt 1EF-227 Zuellig - 743 Mechanical System Mechanical JF-B1-07D Jet Fan Bsmt 1
_________________________________________________________________________________ Commissioning Plan Page 46 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
EF-228 Zuellig - 744 Mechanical System Mechanical SF-B2-04 Supply Fan Bsmt 2PF-01 Zuellig - 745 Mechanical System Mechanical SPF-L2-01 Stair Pressurization Fan 2nd LevelPF-02 Zuellig - 746 Mechanical System Mechanical SPF-L31-01 Stair Pressurization Fan 31st LevelPF-03 Zuellig - 747 Mechanical System Mechanical SPF-R-01 Stair Pressurization Fan Roof DeckPF-04 Zuellig - 748 Mechanical System Mechanical SPF-R-02 Stair Pressurization Fan Roof DeckPF-05 Zuellig - 749 Mechanical System Mechanical LLPF-R-01 Lift Lobby Pressurization Fan Roof Deck
VAV-01 Zuellig - 750 Mechanical System Mechanical VAV-2-01 Variable Air Volume 2nd LevelVAV-02 Zuellig - 751 Mechanical System Mechanical VAV-2-02 Variable Air Volume 2nd LevelVAV-03 Zuellig - 752 Mechanical System Mechanical VAV-2-03 Variable Air Volume 2nd LevelVAV-04 Zuellig - 753 Mechanical System Mechanical VAV-2-04 Variable Air Volume 2nd LevelVAV-05 Zuellig - 754 Mechanical System Mechanical VAV-2-05 Variable Air Volume 2nd LevelVAV-06 Zuellig - 755 Mechanical System Mechanical VAV-2-06 Variable Air Volume 2nd LevelVAV-07 Zuellig - 756 Mechanical System Mechanical VAV-2-07 Variable Air Volume 2nd LevelVAV-08 Zuellig - 757 Mechanical System Mechanical VAV-2-08 Variable Air Volume 2nd LevelVAV-09 Zuellig - 758 Mechanical System Mechanical VAV-2-09 Variable Air Volume 2nd LevelVAV-10 Zuellig - 759 Mechanical System Mechanical VAV-2-10 Variable Air Volume 2nd LevelVAV-11 Zuellig - 760 Mechanical System Mechanical VAV-2-11 Variable Air Volume 2nd LevelVAV-12 Zuellig - 761 Mechanical System Mechanical VAV-2-12 Variable Air Volume 2nd LevelVAV-13 Zuellig - 762 Mechanical System Mechanical VAV-2-13 Variable Air Volume 2nd LevelVAV-14 Zuellig - 763 Mechanical System Mechanical VAV-2-14 Variable Air Volume 2nd LevelVAV-15 Zuellig - 764 Mechanical System Mechanical VAV-2-15 Variable Air Volume 2nd LevelVAV-16 Zuellig - 765 Mechanical System Mechanical VAV-2-16 Variable Air Volume 2nd LevelVAV-17 Zuellig - 766 Mechanical System Mechanical VAV-2-17 Variable Air Volume 2nd LevelVAV-18 Zuellig - 767 Mechanical System Mechanical VAV-2-18 Variable Air Volume 2nd LevelVAV-19 Zuellig - 768 Mechanical System Mechanical VAV-2-19 Variable Air Volume 2nd LevelVAV-20 Zuellig - 769 Mechanical System Mechanical VAV-2-20 Variable Air Volume 2nd LevelVAV-21 Zuellig - 770 Mechanical System Mechanical VAV-2-21 Variable Air Volume 2nd LevelPL-01 Zuellig - 771 Plumbing System Plumbing P-TP-1 Duty Transfer Pump Bsmt 5PL-02 Zuellig - 772 Plumbing System Plumbing P-TP-1 Stand-by Transfer Pump Bsmt 5PL-03 Zuellig - 773 Plumbing System Plumbing NP-TP-2 Duty Transfer Pump Bsmt 5PL-04 Zuellig - 774 Plumbing System Plumbing NP-TP-2 Stand-by Transfer Pump Bsmt 5PL-05 Zuellig - 775 Plumbing System Plumbing G-TP-1 Duty Transfer Pump Bsmt 2PL-06 Zuellig - 776 Plumbing System Plumbing G-TP-1 Stand-by Transfer Pump Bsmt 2PL-07 Zuellig - 777 Plumbing System Plumbing P-BP-1 Booster Pump Roof DeckPL-08 Zuellig - 778 Plumbing System Plumbing P-BP-2.1 Booster Pump Roof DeckPL-09 Zuellig - 779 Plumbing System Plumbing P-BP-2.2 Booster Pump Roof DeckPL-09 Zuellig - 779 Plumbing System Plumbing NP-BP-1 Booster Pump Roof DeckPL-10 Zuellig - 780 Plumbing System Plumbing NP-BP-2.1 Booster Pump Roof DeckPL-10 Zuellig - 779 Plumbing System Plumbing NP-BP-2.2 Booster Pump Roof DeckPL-11 Zuellig - 781 Plumbing System Plumbing SP-1 Duty Sump Pump Bsmt 5PL-12 Zuellig - 782 Plumbing System Plumbing SP-2 Duty Sump Pump Bsmt 5PL-13 Zuellig - 783 Plumbing System Plumbing SP-3 Duty Sump Pump Bsmt 5PL-14 Zuellig - 784 Plumbing System Plumbing SP-4 Duty Sump Pump Bsmt 5PL-15 Zuellig - 785 Plumbing System Plumbing SP-1 Stand-by Sump Pump Bsmt 5PL-16 Zuellig - 786 Plumbing System Plumbing SP-2 Stand-by Sump Pump Bsmt 5PL-17 Zuellig - 787 Plumbing System Plumbing SP-3 Stand-by Sump Pump Bsmt 5PL-18 Zuellig - 788 Plumbing System Plumbing SP-4 Stand-by Sump Pump Bsmt 5PL-19 Zuellig - 789 Plumbing System Plumbing E-1 Elevator Pump Bsmt 5PL-20 Zuellig - 790 Plumbing System Plumbing E-1 Elevator Pump Bsmt 5PL-21 Zuellig - 791 Plumbing System Plumbing E-1 Elevator Pump Bsmt 5PL-22 Zuellig - 792 Plumbing System Plumbing E-1 Elevator Pump Bsmt 5PL-23 Zuellig - 793 Plumbing System Plumbing SE-1 Duty Sewage Ejector Pump Bsmt 5PL-24 Zuellig - 794 Plumbing System Plumbing SE-1 Stand-by Sewage Ejector Pump Bsmt 5PL-25 Zuellig - 795 Plumbing System Plumbing SE-2 Sewage Ejector Pump Bsmt 5PL-26 Zuellig - 796 Plumbing System Plumbing SF-1 Screen Filter Bsmt 5PL-27 Zuellig - 797 Plumbing System Plumbing UV-1 UV Sterilizer Bsmt 5
_________________________________________________________________________________ Commissioning Plan Page 47 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
PL-28 Zuellig - 798 Plumbing System Plumbing UV-2 UV Sterilizer Bsmt 5
PL-28 Zuellig - 798 Plumbing System Plumbing WF-CP-1Water Feature Recirculating
Pump Bsmt 1
PL-29 Zuellig - 799 Plumbing System Plumbing WF-CP-2Water Feature Recirculating
Pump Bsmt 1
PL-30 Zuellig - 800 Plumbing System Plumbing WF-CP-3Water Feature Recirculating
Pump Bsmt 1
PL-31 Zuellig - 801 Plumbing System Plumbing WF-CP-4Water Feature Recirculating
Pump Bsmt 1
PL-32 Zuellig - 802 Plumbing System Plumbing WF-CP-5Water Feature Recirculating
Pump Bsmt 1PL-33 Zuellig - 803 Plumbing System Plumbing WF-F-1 Water Feature Screen Filter Bsmt 1PL-34 Zuellig - 804 Plumbing System Plumbing WF-F-2 Water Feature Screen Filter Bsmt 1PL-35 Zuellig - 805 Plumbing System Plumbing WF-F-3 Water Feature Screen Filter Bsmt 1PL-36 Zuellig - 806 Plumbing System Plumbing WF-F-4 Water Feature Screen Filter Bsmt 1PL-37 Zuellig - 807 Plumbing System Plumbing WF-F-5 Water Feature Screen Filter Bsmt 1PL-38 Zuellig - 808 Plumbing System Plumbing WF-F-6 Water Feature Screen Filter Bsmt 1PL-39 Zuellig - 809 Plumbing System Plumbing MP-1 Chlorine Metering Pump Bsmt 1PL-40 Zuellig - 810 Plumbing System Plumbing PD - Basement 5 Parking Drain Bsmt 5PL-41 Zuellig - 811 Plumbing System Plumbing PD - Basement 4 Parking Drain Bsmt 4PL-42 Zuellig - 812 Plumbing System Plumbing PD - Basement 3 Parking Drain Bsmt 3PL-43 Zuellig - 813 Plumbing System Plumbing PD - Basement 2 Parking Drain Bsmt 2PL-44 Zuellig - 814 Plumbing System Plumbing PD - Basement 1 Parking Drain Bsmt 1PL-46 Zuellig - 815 Plumbing System Plumbing PL - Ground Floor Plumbing & Sanitary System 1st LevelPL-47 Zuellig - 816 Plumbing System Plumbing PL - Level 2 Plumbing & Sanitary System 2nd LevelPL-48 Zuellig - 817 Plumbing System Plumbing PL - Level 3 Plumbing & Sanitary System 3rd LevelPL-49 Zuellig - 818 Plumbing System Plumbing PL - Level 4 Plumbing & Sanitary System 4th LevelPL-50 Zuellig - 819 Plumbing System Plumbing PL - Level 5 Plumbing & Sanitary System 5th LevelPL-51 Zuellig - 820 Plumbing System Plumbing PL - Level 6 Plumbing & Sanitary System 6th LevelPL-52 Zuellig - 821 Plumbing System Plumbing PL - Level 7 Plumbing & Sanitary System 7th LevelPL-53 Zuellig - 822 Plumbing System Plumbing PL - Level 8 Plumbing & Sanitary System 8th LevelPL-54 Zuellig - 823 Plumbing System Plumbing PL - Level 9 Plumbing & Sanitary System 9th LevelPL-55 Zuellig - 824 Plumbing System Plumbing PL - Level 10 Plumbing & Sanitary System 10th LevelPL-56 Zuellig - 825 Plumbing System Plumbing PL - Level 11 Plumbing & Sanitary System 11th LevelPL-57 Zuellig - 826 Plumbing System Plumbing PL - Level 12 Plumbing & Sanitary System 12th LevelPL-58 Zuellig - 827 Plumbing System Plumbing PL - Level 13 Plumbing & Sanitary System 13th LevelPL-59 Zuellig - 828 Plumbing System Plumbing PL - Level 14 Plumbing & Sanitary System 14th LevelPL-60 Zuellig - 829 Plumbing System Plumbing PL - Level 15 Plumbing & Sanitary System 15th LevelPL-61 Zuellig - 830 Plumbing System Plumbing PL - Level 16 Plumbing & Sanitary System 16th LevelPL-62 Zuellig - 831 Plumbing System Plumbing PL - Level 17 Plumbing & Sanitary System 17th LevelPL-63 Zuellig - 832 Plumbing System Plumbing PL - Level 18 Plumbing & Sanitary System 18th LevelPL-64 Zuellig - 833 Plumbing System Plumbing PL - Level 19 Plumbing & Sanitary System 19th LevelPL-65 Zuellig - 834 Plumbing System Plumbing PL - Level 20 Plumbing & Sanitary System 20th LevelPL-66 Zuellig - 835 Plumbing System Plumbing PL - Level 21 Plumbing & Sanitary System 21st LevelPL-67 Zuellig - 836 Plumbing System Plumbing PL - Level 22 Plumbing & Sanitary System 22nd LevelPL-68 Zuellig - 837 Plumbing System Plumbing PL - Level 23 Plumbing & Sanitary System 23rd LevelPL-69 Zuellig - 838 Plumbing System Plumbing PL - Level 24 Plumbing & Sanitary System 24th LevelPL-70 Zuellig - 839 Plumbing System Plumbing PL - Level 25 Plumbing & Sanitary System 25th LevelPL-71 Zuellig - 840 Plumbing System Plumbing PL - Level 26 Plumbing & Sanitary System 26th LevelPL-72 Zuellig - 841 Plumbing System Plumbing PL - Level 27 Plumbing & Sanitary System 27th LevelPL-73 Zuellig - 842 Plumbing System Plumbing PL - Level 28 Plumbing & Sanitary System 28th LevelPL-74 Zuellig - 843 Plumbing System Plumbing PL - Level 29 Plumbing & Sanitary System 29th LevelPL-75 Zuellig - 844 Plumbing System Plumbing PL - Level 30 Plumbing & Sanitary System 30th LevelPL-76 Zuellig - 845 Plumbing System Plumbing PL - Level 31 Plumbing & Sanitary System 31st LevelPL-77 Zuellig - 846 Plumbing System Plumbing PL - Level 32 Plumbing & Sanitary System 32nd LevelPL-78 Zuellig - 847 Plumbing System Plumbing PL - Level 33 Plumbing & Sanitary System 33rd LevelPL-79 Zuellig - 848 Plumbing System Plumbing DD - Level 34 Deck Drain 34th LevelRS-01 Zuellig - 849 2-way Radio Auxiliary Transceivers Transceivers Common
_________________________________________________________________________________ Commissioning Plan Page 48 of 49Revision 0
32nd FLOOR EXECUTIVE OFFICESZUELLIG BUILDING 14 May 2012PASEO DE ROXAS CORNER MAKATI AVENUEMAKATI CITY, PHILIPPINES ________________________________________________________________________________________
RS-02 Zuellig - 850 2-way Radio Auxiliary Splitters Splitters CommonRS-03 Zuellig - 851 2-way Radio Auxiliary Repeater Base Station Repeater Base Station 1st LevelRS-04 Zuellig - 852 2-way Radio Auxiliary Head and Equipment Head and Equipment 1st Level
BGM-02 Zuellig - 853 Background Music & PA Auxiliary 2nd Level - BGM/PA BGM/PA System 2nd LevelBGM-03 Zuellig - 854 Background Music & PA Auxiliary 3rd Level - BGM/PA BGM/PA System 3rd LevelBGM-04 Zuellig - 855 Background Music & PA Auxiliary 4th Level - BGM/PA BGM/PA System 4th LevelBGM-05 Zuellig - 856 Background Music & PA Auxiliary 5th Level - BGM/PA BGM/PA System 5th LevelBGM-06 Zuellig - 857 Background Music & PA Auxiliary 6th Level - BGM/PA BGM/PA System 6th LevelBGM-07 Zuellig - 858 Background Music & PA Auxiliary 7th Level - BGM/PA BGM/PA System 7th LevelBGM-08 Zuellig - 859 Background Music & PA Auxiliary 8th Level - BGM/PA BGM/PA System 8th LevelBGM-09 Zuellig - 860 Background Music & PA Auxiliary 9th Level - BGM/PA BGM/PA System 9th LevelBGM-10 Zuellig - 861 Background Music & PA Auxiliary 10th Level - BGM/PA BGM/PA System 10th LevelBGM-11 Zuellig - 862 Background Music & PA Auxiliary 11th Level - BGM/PA BGM/PA System 11th LevelBGM-12 Zuellig - 863 Background Music & PA Auxiliary 12th Level - BGM/PA BGM/PA System 12th LevelBGM-13 Zuellig - 864 Background Music & PA Auxiliary 13th Level - BGM/PA BGM/PA System 13th LevelBGM-14 Zuellig - 865 Background Music & PA Auxiliary 14th Level - BGM/PA BGM/PA System 14th LevelBGM-15 Zuellig - 866 Background Music & PA Auxiliary 15th Level - BGM/PA BGM/PA System 15th LevelBGM-16 Zuellig - 867 Background Music & PA Auxiliary 16th Level - BGM/PA BGM/PA System 16th LevelBGM-17 Zuellig - 868 Background Music & PA Auxiliary 17th Level - BGM/PA BGM/PA System 17th LevelBGM-18 Zuellig - 869 Background Music & PA Auxiliary 18th Level - BGM/PA BGM/PA System 18th LevelBGM-19 Zuellig - 870 Background Music & PA Auxiliary 19th Level - BGM/PA BGM/PA System 19th LevelBGM-20 Zuellig - 871 Background Music & PA Auxiliary 20th Level - BGM/PA BGM/PA System 20th LevelBGM-21 Zuellig - 872 Background Music & PA Auxiliary 21st Level - BGM/PA BGM/PA System 21st LevelBGM-22 Zuellig - 873 Background Music & PA Auxiliary 22nd Level - BGM/PA BGM/PA System 22nd LevelBGM-23 Zuellig - 874 Background Music & PA Auxiliary 23rd Level - BGM/PA BGM/PA System 23rd LevelBGM-24 Zuellig - 875 Background Music & PA Auxiliary 24th Level - BGM/PA BGM/PA System 24th LevelBGM-25 Zuellig - 876 Background Music & PA Auxiliary 25th Level - BGM/PA BGM/PA System 25th LevelBGM-26 Zuellig - 877 Background Music & PA Auxiliary 26th Level - BGM/PA BGM/PA System 26th LevelBGM-27 Zuellig - 878 Background Music & PA Auxiliary 27th Level - BGM/PA BGM/PA System 27th LevelBGM-28 Zuellig - 879 Background Music & PA Auxiliary 28th Level - BGM/PA BGM/PA System 28th LevelBGM-29 Zuellig - 880 Background Music & PA Auxiliary 29th Level - BGM/PA BGM/PA System 29th LevelBGM-30 Zuellig - 881 Background Music & PA Auxiliary 30th Level - BGM/PA BGM/PA System 30th LevelBGM-31 Zuellig - 882 Background Music & PA Auxiliary 31st Level - BGM/PA BGM/PA System 31st LevelBGM-32 Zuellig - 883 Background Music & PA Auxiliary 32nd Level - BGM/PA BGM/PA System 32nd LevelBGM-33 Zuellig - 884 Background Music & PA Auxiliary 33rd Level - BGM/PA BGM/PA System 33rd LevelBGM-34 Zuellig - 885 Background Music & PA Auxiliary 34th Level - BGM/PA BGM/PA System 34th Level
9. Process Flow Chart & Issues Log
i. Witnessing & Test Results Validation Process Flow chart
ii. Submittal Review Process Flow Chat
iii. Issue Log Form
_________________________________________________________________________________ Commissioning Plan Page 49 of 49Revision 0