1. Metro Rail (Amendment) Act 2009 is applicable to
Chennai Metropolitan area.
2. Clause 7 of Chapter IV of the Act specifies appointment
of Commissioners of Metro Railway Safety (CMRS).
3. Clause 14 of Chapter V ‘opening of Metro railway’
requires sanction of the Central Government beforerequires sanction of the Central Government before
opening of a Metro Railway for public carriage. Vide
Clause 21 these powers can be delegated to CMRS.
http://www.delhimetrorail.com 2
4. Clause 15 of the Chapter V specifies formalities to be
complied before giving sanction:
“I. The Central Government obtain a report from CMRS
that
a. CMRS has made careful inspection of the Metro
Railway and Rolling Stock
b. The Moving and Fixed dimension has not
infringed.
c. The track structure, strength of bridges,c. The track structure, strength of bridges,standard of signalling system, tractionsystem, general structural character of civilworks and the size of, maximum gross loadupon ,the axles of any rolling stock, complywith the requirements .
d. In his opinion, Metro Railway can be opened for
the public carriage of passengers without any
danger to the public using it.”
http://www.delhimetrorail.com 3
Considering these legal aspects certain approvals are
obtained by CMRL from the Central Government.
Central Government in terms of Section 2, Clause 1(a) of
Metro Act in relation to technical planning and safety of
Metro Railway means the Ministry of Government of IndiaMetro Railway means the Ministry of Government of India
dealing with railways.
http://www.delhimetrorail.com 4
CMRL vide letter no. 161/CMR/2011 dated 11-02-2011 haveasked for procedures and documentations required forobtaining statutory clearances from Ministry of Railways andCMRS in respect of :
1. Rolling Stock.
2. Track Structure
3. Signalling and Telecommunication.
4. OHE Traction System.
5. Civil Structures.5. Civil Structures.
6. Safety and Man Power Planning
7. Opening of the section by CMRS.
In addition to above fire clearance from Fire Officer forArchitectural plans and compartmentation etc of sations isrequired at planning stage. Subsequently at operationalstage occupancy certificate from Fire Department would berequired. This is a prerequisite to CMRS inspection.
http://www.delhimetrorail.com 5
1. Approval of SOD is desirable before procurement.
2. Submission of request to the Carriage Directorate of the
RDSO for issue of provisional Speed Certificate for
conducting Oscillation and EBD trial.
� Request is to be enclosed with technical details of-Request is to be enclosed with technical details of-
� Rolling Stock
� Track
� Bridges
� Viaduct
� Tunnels
� Signalling & Traction System
� For detail refer Annexure 1and 2
http://www.delhimetrorail.com 6
3. Application to CMRS for conducting Oscillation and EBDtrials.
� Application to be enclosed with the followingCertificates/ Documents-
a. Joint Safety Certificate signed by HODs of
Rolling stock, Operation, S&T, Electrical
Traction and Track.
b. Track Certificate by track HOD.
c. Bridge Engineers Certificate by Chief Bridge
Engineer / CPM / CE (Construction).
d. Copy of RDSO’s Speed Certificate along with
compliance of Conditions stipulated in the
certificate.
e. safety procedure for testing and
commissioning
f. Time Table for trials
http://www.delhimetrorail.com 7
g. EIG sanctions and compliance of conditions ifany
h. Sanction of Dept. of Telecommunication fordynamic clearance.
i. Copy of approved Schedule of Dimension
j. OHE Fitness Certificate
k. General Introduction of Rolling Stockk. General Introduction of Rolling Stock
l. Track Structure Approval
� CMRS insists on trial section length of 10 KMs (minimum).
� Condonation of infringement to SOD (if any) by Ministry ofRailways required before submission of application toCMRS.
http://www.delhimetrorail.com 8
4. Final Speed Certificate is issued by RDSO based on results ofOscillation and EBD trials.
5. Application (in3 sets) for sanctioning of Rolling Stock to besubmitted to the Secretary (Civil Engineering)/ MOR throughCMRS/CCRS for MOR’s approval.
Documents to be enclosed with the application:
� Final Speed Certificate
� Form XIX- Joint Safety Certificate� Form XIX- Joint Safety Certificate
� Form VIII- Brief particulars of Rolling Stock and technical
details of the System
� Bridge Certificate
� Track Certificate
� Track Structure Approval
http://www.delhimetrorail.com 9
� OHE Certificate
� Form XVII- infringement of moving and Fixed Dimensions
jointly signed by HODs of Civil, track, S&T, Electrical ,
and Rolling Stock.
� EMC Control Plan
� RDSO’s Oscillation trial report� RDSO’s Oscillation trial report
� RDSO’s EBD trial report
� Approval of Signal and Train control System
� Approval of Electrical Traction System.
http://www.delhimetrorail.com 10
� Railway Board has circulated a performance criteria offastening system for ballastless track vide letter no.2009/proj./MAS/9/2 dated 21-05-2010.
� The proposal of Track structure chosen by a Metroadministration is submitted to the Railway board (in 2sets) along with the following:sets) along with the following:
� Details of Rails
� Plinth / slab design
� Fastening system
� Details of performance (minimum 5 years)
� Test Reports (Item 4.4 and beyond in the performancecriteria)
� Technical calculation and Drawings (Anchor Bolt,plinth reinforcement etc.)
http://www.delhimetrorail.com 11
� One set of proposal is submitted to RDSO by the Railway
Board for appraisal.
� If necessary, further details are submitted to RDSO/Railway
Board and clarification provided.
� Compliance of Performance Criteria submitted by DMRC to
MOR is given under Annexure-3
http://www.delhimetrorail.com 12
� Signal and Telecom System submitted to Ministry of
Railways for approval of:
1. Type of Signalling
2. Back up Signalling
3. Interlocking
4. Train Control System
5. Type of Track Circuits.
6. Point Machine for M/L and Depot.
7. Redundancy in cab equipment for ATP (cab
signalling)
8. Technical clearance for telecommunication.
9. Positive Train Identification.
10. Platform screen door. (Annexure 4)
http://www.delhimetrorail.com 13
Telecommunication System
� Proposed Telecommunication System shall comprise of the
following five subsystem
1. Fibre Optic Transmission system
2. Telephone System
3. Train Mobile radio system
4. Public Address system and4. Public Address system and
5. Closed Circuit Television (CCTV) system.
http://www.delhimetrorail.com 14
� Approval For Flexible OHE
As Delhi Metro’s Flexible OHE design is similar to that
Indian Railways and Standard follows are as per Indian
Railways Traction manual and hence no separate
clearance was required.
Same approach can be adopted by CMRL. They may
advice to the MOR.
� Approval For Rigid OCS
• Design is submitted to Ministry of Railways for
technical approval. (Annexure-A)
http://www.delhimetrorail.com 15
� The Electrical Inspector General (EIG) is to be approached
for giving clearances for
� Energisation of the 25 kV OHE and sectioning and
paralleling posts.
� Receiving Sub Stations
� 33 kV Sub –Stations
� DG sets etc.
� The application is sent along with the format 10-03 & 10-
15 for Flexible OHE and 10-03 to 10-12 for Rigid OHE duly15 for Flexible OHE and 10-03 to 10-12 for Rigid OHE duly
signed by concerned officers involved in construction and
O&M wing.
� Any accident due to electrocution to be reported to EIG.
http://www.delhimetrorail.com 16
� Nomination of EIG is done by the Ministry of Power
� The Min. of Power is to be approached for authorization
to EIG of Railways or EIG of State Government (Annexure
D & Annexure E).
� Lifts
Lift Inspector of concerned state Government will need
to be approached at two stages i.e. Pre erection
permission and subsequently for lift license at
commissioning stage.commissioning stage.
� Escalators
For escalators, a nominated Escalator Inspector of
State Govt. is approached for approval.
We understand that there is no inspector of
escalator in Tamil Nadu. However, it may be checked.
These are also prerequisite to CMRS inspection.
http://www.delhimetrorail.com 17
� Loading standards for Viaduct and Bridges is submitted to
the Railway Board for approval.
� These would include:
� Dead Load
� Live Load
Forces due to curvature and eccentricity of Track� Forces due to curvature and eccentricity of Track
� Temperature effect
� Friction resistance of expansion bearing
http://www.delhimetrorail.com 18
� Longitudinal forces
� Racking force
� Forces on parapets
� Wind pressure effect
� Force and effect due to earthquake
� Force due to derailment
� Live Load for platform.(Annexure – I)
http://www.delhimetrorail.com 19
� SAFETY Clearances
� No safety related clearance from outside agency
except statutory clearance by CMRS is required.
� Manpower Planning� Manpower Planning
� No clearance from any outside agency except CMRS
who will have to satisfy that adequate maintenance
facilities and trained manpower is available before
commissioning .
http://www.delhimetrorail.com 20
1. Nomination of CMRS to be notified by MOUD with the
concurrence of Ministry of Civil Aviation
2. Application to CMRS for statuary inspection of section
following prerequisites need to be firmed up–
a) Sanction of Rolling Stock by MOR.a) Sanction of Rolling Stock by MOR.
b) Approval of Track Structure by MOR.
c) Approval of Signal and Train Control Supply System
by MOR
d) Approval of Electrical Traction system by MOR
e) Approval of Schedule of Dimension by MOR
f) General Rules for Opening to be notified by MOUD.
g) Loading Standards by MOR.
http://www.delhimetrorail.com 21
3. Manuals and Procedures required
a. Track Maintenance
b. Rolling Stock operation and maintenance.
c. signal engineering.
d. AC Traction.
e. Train Operating Procedures.
f. Station and Depot working orders.
4. The application is submitted to CMRS in 3 identical originalsets. CMRS keeps one for his office and forward the othersto CCRS and MOR.to CCRS and MOR.
� Documents submitted along with application are to besigned by officer not below SAG Level. These documentsare
4.1 Administrative note
4.2 Forms :
i. Curve abstract - Form I
http://www.delhimetrorail.com 22
ii. Gradient abstract - Form II
iii. Bridge abstract - Form III
iv. Viaduct abstract - Form IV
v. Important Bridge abstract - Form V
vi. Ballast and permanent way - Form VI
vii. Station and station sites - Form VII
viii. Brief particulars of rolling stock - Form VIII
ix. Brief particulars of Traction Installation - Form IXix. Brief particulars of Traction Installation - Form IX
x. Power Supply Installation abstract - Form X
xi. Restricted OHE clearance abstract -Form XI
xii. Electrical crossing over metro railway Track abstract
-Form XII
xiii. Traction maintenance depot abstract -Form XIII
http://www.delhimetrorail.com 23
xiv. Ventilation smoke management and Fire safety measures
- Form XIV
xv. Brief particulars of signal and train control system-
- Form XV
xvi. Certificate from Chief Executive Officer - Form XVI
xvii. Infringement of moving and fixed dimensions- Form XVII
xviii. Load deflection test of Bridges - Form XVIII
xix. Joint Safety certificate for Rolling Stock - Form XIX
xx. Signalling safety Certificate - Form XX
4.3 Index plan and sections
4.4 Drawings
i. Station architectural / Layout
ii. Running Section
iii. OHE Layout Plans
iv. Signalling Scheme plans for section and control table
http://www.delhimetrorail.com 24
4.5 Station working orders of station and control table
4.6 Check List of Question and Answers.
4.7 Clearance of Fire safety measures of stations by local
Authority.
4.8 EIG Sanction and compliance of conditions.4.8 EIG Sanction and compliance of conditions.
4.9 Clearance from Department of telecommunication
4.10 Certificate regarding safety instructions &
precautionary measures.
4.11 License for working of lifts and elevators (If applicable)
http://www.delhimetrorail.com 25
� CMRS inspects the section by Motor Trolley accompanied by the Directors/officers nominated by CEO and other SAG/JAG level officers.
� Following aspects are examined:� Station to be manned with trained staff, having knowledge of relevant rules and procedures.
� Adequacy of all works pertaining to station exit/entry, firemen’s staircase, platform, staircases, lighting and ventilation etc.firemen’s staircase, platform, staircases, lighting and ventilation etc.
� Passenger facilities such as toilets, ticket office functioning, AFC system, Escalators, lifts etc.
� Fire protection, detection, suppression and disaster management measures.
� Adequate public announcement and display system.� proper signage and boards at prominent locations and technical rooms are properly manned.
http://www.delhimetrorail.com26
� Railings on viaduct in elevated section, at platform and
staircases etc.
� Walkway in tunnels.
� Measurement of curves, turnouts, track features, track
spacing, clearances of parapets, tunnels and other
features.
� Measurement of OHE clearance, signals etc.
� All electrical and signaling systems with the assistance of
Dy.CRS S&T and Electrical.
� After trolleying down both UP and DN lines, the
confirmatory speed test by train is done on both the lines
including emergency evacuation system from train, ATP
functions etc.
http://www.delhimetrorail.com 27
� Following the inspection, CMRS accords sanction for
opening of corridor for introduction of commercial
services.
� A detailed inspection report is prepared and submitted to� A detailed inspection report is prepared and submitted to
MOR, MOUD and DMRC by CMRS.