Project Constraint/Challenges faced in 11 Tx site
RoW permission from Govt. Authority (City corporation, RAJUK) Regulatory permission (BTRC) Conflict with Building owner Adverse weather World Cup Cricket 2011 Fiber constraint Resource constraint Priorities of other project
Future Challenges & Solutions:
InternalInternalTP-OBPTP-OBP
1. Vendor provided fiber & patch shelf standardization according to GP Standard.
2. Road owner identification (RoW) during TR3. Building owner permission just 1 week after fiber TR4. End 2 End fiber loss during fiber acceptance 5. Transparent communication regarding fiber PAT6. Equal priority to fiber project7. Utilization of Go4fiber patch shelf.
InternalInternalTP-OBPTP-OBP
Major Stakeholders
CW_Fiber
ROMTP
SAAcceptance
Rollout