63
Causes of Project Delay in the Construction Industry in
Afghanistan
Ghulam Abbas Niazai and Kassim Gidado
Abstract
It is widely accepted that a project is successful when it is finished on time but
unfortunately, due to many reasons, in Afghanistan a large number of construction projects
fail to meet their original contact time. Construction delays are the most serious problems
which send bad signals to foreign investors thereby slowing down the national
development. A comprehensive survey; therefore, on time performance of various
construction projects was carried out to identify the critical factors that cause construction
delays in Afghanistan.
From in-depth literature studies, eighty three causes of delay were identified.
Questionnaires were then developed and sent to 60 carefully selected construction industry
stakeholders including: clients, contractors, and consultants in Afghanistan. The findings
show that the main critical factors that cause construction delays in Afghanistan are:
security, corruption, poor qualification of the contractor’s technical staff, payment delays
by clients, and poor site management and supervision by contractor. This paper also
explores and provides some recommendations to reduce the impact of delays on
construction projects in Afghanistan.
Keywords: Construction projects, Delay causes, Afghanistan
1. Introduction
Delay is a major problem in construction industry. Trauner et al. (2009) defines that construction delays make something happen later than expected, to cause something to be
performed later than planned, or to not act timely. Delay can affect any activity of work in
a schedule and results in many problems between parties. According to Al-Khalil and Al-
Ghafly (1999) delays can adversely impact on project stakeholders, such as clients,
contractors and designers. To the client, delay perceives loss of revenue due to lack of
rentable space or lack of production facilities. On the other hand, delay can be meant to the
contractor as higher overhead costs, higher material and labour costs because the project
takes longer than it was planned.
Having finished the projects on time (Assaf and Al-Hejji, 2006) can be marked as an
indicator of efficiency, but the construction activities involves of many unpredictable
factors and variables arisen from various sources. These resources may include
environmental circumstances, availability of resources, stakeholders’ performance and
contractual relations. Nevertheless, Trauner et al. (2009) states that it is hardly ever occur
that a construction project is finished within the planned time.
64
2. Literature Review
Many researches and articles have been carried out on causes of delay in construction
projects. The findings of such studies have been reviewed for this research. Chan and
Kumaraswamy (1997) did a survey to assess the relative importance of 20 potential delay
factors in Hong Kong construction projects and five key factors were found, such as poor
risk management and supervision, unforeseen site conditions, slow decision making,
client-initiated variations, and work variations. However, Al-Momani (2000) in a research
on construction delays in 130 public projects in Jordan found that weather, site conditions,
late deliveries, economic conditions and increase in quantity are the critical factors which
cause construction delays in Jordan construction industry.
Kaming et al. (1997) carried out a research to study the impact factors on 31 high-rise
projects in Indonesia and it was found that time overrun is less severe than cost overruns.
The significant factors that lead to cost overrun are material fluctuation, inaccurate
material estimation and degree of complexity. Whereas, design changes, poor labor
productivity, inadequate planning, and resource shortages are marked as time overruns.
Mezher & Tawil (1998) carried out a research in to find out the Causes of delays in the
construction industry in Lebanon. A total of 64 causes of delays were identified through
research in which client, contractor and consultant were undertaken the study. All three
parties generally agreed on the ranking of the major categories of delay factors. Owners
had more concerns with regard to financial issues, while contractors ranked contractual
relationships highest, and finally, consultants firms ranked project management highest.
These causes were categorized in 10 main groups: materials, manpower, equipment,
financing, changes, government relations, project management, site conditions,
environment and contractual relationships. Long et al. (2008) conducted a study to find
out the cause of delays and cost overrun in Vitinam and 7 critical factors were identified
such as, Slowness and Lack of constraint; Incompetence; Design; Market and Estimate;
Financial capability; Government; and Worker.
Assaf and Al-Hejji (2006) studied the causes of delay in large building construction
projects in Saudi Arabia. They found 73 factors that cause construction delays. They
categorized these factors into 9 groups. Some of the most important causes of delay
included approval of shop drawings, delays in contractors' payment by owners, design
changes by owners, cash problems during construction, the slowness of the owners'
decision-making process, design errors, excessive bureaucracy in project-owner
organization, labour shortages and inadequate labour skills.
Assaf et al. (1995) identified 56 main causes of delay in Saudi large building construction
projects and their relative importance. Based on the contractors surveyed the most
important delay factors were: preparation and approval of shop drawings, delays in
contractor’s progress, payment by owners and design changes. Koushki et al. (2005)
carried out a research in Kuwait and identified estimates of time delays and cost increases
and their causes. The three main causes of delays are changing orders, owners’ financial
constraints, and owners’ lack of experience. And three first causes of cost overruns are
contractor- related problems, material-related problems and owners’ financial constraints.
3. Objectives of the study
The following objectives are developed to achieve the aim of the research
65
1. To identify the causes of delays in construction industry in Afghanistan
2. To study the differences in ideas of the three main stakeholders, including clients,
contractors and consultants.
3. To identify the significant factors that causes delays in Afghanistan.
The aim of first objective is to identify the list of factors that cause construction delays,
while the third objective focuses on the top ten causes of construction delays.
4. Research Methodology
The research conducted in this study is mostly exploratory in nature. Both primary and
secondary data are used in this research, and data has been obtained through two primary
avenues – desk research and questionnaire. Firstly, from in-depth literature studies and
discussing with some construction practitioners, eighty three causes of delay were
identified, which is presented in Table 1. Then, a questionnaire form was developed in
order to evaluate the effects of the factors that cause construction delays.
Firstly, a pilot study was conducted to verify whether the questions are relevant in respect
to the objectives of the study. The pilot study was conducted in the University of Brighton
and the questions were discussed with the research supervisor and two other senior
lecturers. The questionnaires included with a cover letter were sent to 60 construction
practitioners, including, clients, contractors, and consultants. The construction parties, who
actively involved in Afghanistan construction industry, were asked to response the
questionnaires.
The questionnaire was divided into two main parts. Part one includes the details of the
respondents and organizations in order to get the information about the respondent’s details
and organization as well. Part two includes factors that cause construction delays in
Afghanistan. This part is comprised of nine categories such as, projects itself; client,
contractor, consultant, designer, materials, equipment, labor, and external factors. The
questions were based on the Likert’s scale of five ordinal measures from 1 to 5 (very low
effect to very high effect) according to level of contributing.
Data were collected through questionnaire forms and importance index were used to
analyze the data gathered. Agreement between each two parties in respect to the causes of
delays was also tested. In light of findings of the research, recommendations for
minimizing the impact of delays were made.
5. Data Analysis Method
The following statistical techniques and index were used for analyzing the data collected:
Importance Index: The most frequent index used for construction delays is Importance
Index . According to Long et al. (2008) to rank different factors from various groups of
causes the Relative Importance Index is an appropriate index for analyzing construction
delays. It is computed as below:
(1)
66
Where: a = constant expressing the weight assigned to each responses (ranging from 1 very
low effects to 5 very high effects), n= frequency of the responses for each cause and N =
total number of responses
5.1 Spearman’s Rank Correlation
According to Assaf and Al-Hejji (2006) spearman’s rank correlation is a non-parametric
test. Correlation is a relationship measure among different parties or factors and the
strength and direction of the relationship. This method mainly used to show the degree of
agreement between the different parties. The correlation coefficient varies between +1 and
-1, where +1 implies a perfect positive relationship (agreement), while -1 results from a
perfect negative relationship (disagreement). The value near to zero indicates little or no
correlation. In this research this correlation is used to find out the degree of agreement
between parties. This correlation is computed by the following formula:
(2)
Where: is the Spearman rank correlation coefficient between two parties, d is the
difference between ranks assigned to variables for each cause and n is the number of pairs
of rank.
Table 1. List of causes of delay categorized into nine groups
No Causes of Delay Group
1 Original contract duration is too short Project
2 Legal disputes b/w various parties Project
3 Inadequate definition of substantial completion Project
4 Ineffective delay penalties Project
5 Type of construction contract (Turnkey, and etc.) Project
6 Type of project bidding and award (negotiation, lowest price, etc.) Project
7 Delay in progress payments by owner Client
8 Delay to furnish and deliver the site to the contractor by the owner Client
9 Change orders by owner during construction Client
10 Late in revising and approving design documents by owner Client
11 Delay in approving shop drawings and sample materials Client
12 Poor communication and coordination by owner and other parties Client
13 Slowness in decision making process by owner Client
14 Conflicts between joint-ownership of the project Client
15 Unavailability of incentives for contractor Client
16 Suspension of work by owner Client
17 Difficulties in financing project by contractor Contractor
18 Conflicts in sub-contractors schedule in execution of project Contractor Contractor
19 Rework due to errors during construction Contractor
20 Conflicts b/w contractor and other parties (consultant and owner) Contractor
21 Poor site management and supervision by contractor Contractor
22 Poor communication and coordination by contractor with other parties Contractor
23 Ineffective planning and scheduling of project by contractor Contractor
24 Improper construction methods implemented by contractor Contractor
25 Delays in sub-contractors work Contractor
26 Inadequate contractor’s work Contractor
27 Frequent change of sub-contractors because of their inefficient work Contractor
28 Poor qualification of the contractor’s technical staff Contractor
29 Delay in site mobilization Contractor
67
30 Delay in performing inspection and testing by consultant Consultant
31 Delay in approving major changes in the scope of work by consultant Consultant
32 Inflexibility (rigidity) of consultant Consultant
33 Poor communication/coordination between consultant and other parties Consultant
34 Late in reviewing and approving design documents by consultant Consultant
35 Conflicts between consultant and design engineer Consultant
36 Inadequate experience of consultant Consultant
37 Mistakes and discrepancies in design documents Designer
38 Delays in producing design documents Designer
39 Unclear and inadequate details in drawings Designer
40 Complexity of project design Designer
41 Insufficient data collection and survey before design Designer
42 Misunderstanding of owner’s requirements by design engineer Designer
43 Inadequate design-team experience Designer
44 Un-use of advanced engineering design software Designer
45 Shortage of construction materials in market Materials
46 Changes in material types and specifications during construction Materials
47 Delay in material delivery Materials
48 Damage of sorted material while they are needed urgently Materials
49 Delay in manufacturing special building materials Materials
50 Late procurement of materials Materials
51 Late in selection of finishing materials due to diversity in market Materials
52 Equipment breakdowns Equipment
53 Shortage of equipment Equipment
54 Low level of equipment-operator’s skill Equipment
55 Low productivity and efficiency of equipment Equipment
56 Lack of high-technology mechanical equipment Equipment
57 Wrong selection Equipment
58 Shortage of labors Labor
59 Unqualified workforce Labor
60 Nationality of labors Labor
61 Low productivity level of labors Labor
62 Personal conflicts among labors Labor
63 Weak motivation Labor
64 Security External
65 Warlords influence External
66 Corruption External
67 Natural disasters ( flood, landslides, …) External
68 Effects of subsurface conditions (e.g., soil, high water table, etc.) External
69 Inclement weather (very cold, very hot, rain…) External
70 Unavailability of utilities in site External
71 Effect of social and cultural factors External
72 Traffic control and restriction at job site External
73 Accident during construction External
74 Delay in providing services from utilities (such as water, electricity) External
75 Permits from municipality External
76 Permits for foreign labourers External
77 Building codes External
78 Bureaucracy in Government agencies External
79 Permit from the urban planning bureau External
80 Permit from Order of Engineers External
81 Changes in government regulations and laws External
82 Poor government judicial system for construction dispute settlement External
83 Market inflation External
68
6. Research findings and results
6.1 General characteristics of respondents
Out of 60 set of questionnaires distributed, with the proportion of (20 for clients, 25 for
contractors, and 15 for consultants), 24 questionnaires were fully responded. Whereas, 3
set of questionnaires were not correctly filled in, hence the 21 set of questionnaires which
were useable for the analysis. The feedbacks comprise of 33 % clients, 42% contractors
and 25% consultants which forms 35% of total responses. 48% respondents have less than
5 years, 33% between 5 – 15 years and 19% who have more than 15 years experience.
6.2 Ranking of delay causes
The causes of delays were ranked on the basis of Importance Index explained earlier from
the viewpoint of three stakeholders (clients, contractors and consultants). The list of causes
which is categorized into nine groups is presented in Table 1.
6.3 Importance delay of causes
The importance index was used to rank the effect of each cause of delay. Table 2 presents
the 10 key factors ranked by clients, contractors, and consultants. Two causes of delay are
common between all parties, which are ‘security’ and ‘corruption’. Both clients and
consultants reported that poor qualification of the contractor’s technical staff and
difficulties in financing project by contractor are the most sever causes of delay by the
contractors. Contractors reported that delay in progress payment by the client is one of the
significant causes of delay. Consultants like clients agreed that ineffective planning and
scheduling of project by contractor is another key driver in delaying projects in
Afghanistan.
6.4 Significant causes of delay
The importance index was employed to rank the significant causes of delay. All three
parties, including clients, contractors and consultants contributed to rank the significant
factors of delays. The result in Table 3 shows that the top 10 major causes of construction
delays in Afghanistan are security with importance rank of 0.913 and corruption with
importance rank of 0.830 followed by poor qualification of the contractor’s technical staff,
poor site management and supervision by contractor, ineffective planning and scheduling
of project by contractor, and difficulties in financing project by contractor. Delay in
progress payments by owner and type of project bidding and award (negotiation, lowest
price) are another critical factors which result in delays. The finding clearly indicates that
‘Bureaucracy in Government agencies’ is also one of the key sources of construction
delays in Afghanistan. Bureaucracy leads to lengthy and complex payment process in
government agencies, and the process can take as long as four to five months. These 10
significant causes of delays are strongly contributing to construction delays in Afghanistan.
69
Table 2. Importance delay of causes reported by parties
No Client Contractor Consultant
1 Security Security Security
2
Poor qualification of the
contractor’s technical staff
Delay in progress
payments by owner
Poor qualification of the
contractor’s technical staff
3
Difficulties in financing
project by contractor
Corruption Type of project bidding
and award (negotiation,
lowest price and etc.)
4
Unqualified workforce Suspension of work by
owner
Poor site management and
supervision by contractor
5
Poor communication and
coordination by contractor
with other parties
Inadequate design-team
experience
Corruption
6
Insufficient data collection
and survey before design
Late in revising and
approving design
documents by owner
Ineffective planning and
scheduling of project by
contractor
7
Corruption Change orders by owner
during construction
Frequent change of sub-
contractors because of
their inefficient work
8
Ineffective planning and
scheduling of project by
contractor
Bureaucracy in
Government agencies
Bureaucracy in
Government agencies
9
Frequent change of sub-
contractors because of their
inefficient work
Mistakes and
discrepancies in design
documents
Difficulties in financing
project by contractor
10
Poor site management and
supervision by contractor
Delays in producing
design documents
Delay in progress
payments by owner
Table 3. Significant causes of delay
Cause of delay
Client Contractor Consultant Overall
Index Rank Index Rank Index Rank Index Rank
Security 0.886 1 0.933 1 0.920 1 0.913 1
Corruption 0.827 7 0.825 3 0.838 5 0.830 2
Poor qualification of the
contractor’s technical staff 0.857 2 0.688 17 0.850 2 0.798 3
Delay in progress
payments by owner 0.732 21 0.844 2 0.726 10 0.767 4
Poor site management and
supervision by contractor 0.772 10 0.688 22 0.839 4 0.766 5
Ineffective planning and
scheduling of project by
contractor 0.800 8 0.643 32 0.837 6 0.760 6
70
Type of project bidding
and award (negotiation,
lowest price and etc.) 0.745 16 0.689 21 0.840 3 0.758 7
Difficulties in financing
project by contractor 0.833 3 0.662 43 0.760 9 0.752 8
Poor communication and
coordination by contractor
with other parties 0.83 5 0.689 16 0.725 11 0.748 9
Frequent change of sub-
contractors because of
their inefficient work 0.791 9 0.623 45 0.800 7 0.738 10
6.5 Ranking of Sources (Groups) of Delays
The causes are categorized into nine groups. Rankin of these groups associated with degree
of severity by clients, contractors and consultants are shown in Table 4 - 7. Tables 4 - 6
present that, both client and consultant specified ‘contractor’, and ‘materials’ causes as
sources of delay. However, Contractor indicated that ‘designer’ and ‘client’ mostly
contribute to construction delays. The combined results shown in Table 7 presents that
delay in construction projects is mostly originated by the ‘contractor’, followed by
‘designer’ and ‘materials’, while ‘project related cause’ is less important.
6.6 Importance Rank Correlation
The Spearman’s rank correlation coefficient is applied to measure the degree of agreement
or disagreement associated with the importance ranking of each two stakeholders for a
single factor of delay, while ignoring the ranking of the third party. The results present that
the highest degree of agreement is between clients and contractors which is 60.5%. The
lowest degree of agreement is between contractors and consultants which is 54%. The
relative agreement between each two parties is shown in Table 8.
Table 4. Ranking of Sources (Groups) of Delays by client
Sources (Groups) of delay by ‘Client’
Degree of Severity
Index Rank
Contractor-related factors 0.732 1
Designer-related factors 0.696 2
Materials-related factors 0.668 3
Labor-related factors 0.651 4
Consultant-related factors 0.644 5
Equipment-related factors 0.64 6
Client-related factors 0.631 7
External factors 0.606 8
Project-related factors 0.605 9
71
Table 5. Ranking of Sources (Groups) of Delays by contractor
Sources (Groups) of delay by ‘Contractor’
Degree of Severity
Index Rank
Designer-related factors 0.684 1
Client-related factors 0.665 2
Contractor-related factors 0.635 3
Materials-related factors 0.632 4
Consultant-related factors 0.631 5
Equipment-related factors 0.617 6
External factors 0.598 7
Labor-related factors 0.565 8
Project-related factors 0.563 9
Table 6. Ranking of Sources (Groups) of Delays by consultant
Sources (Groups) of delay by ‘Consultant’
Degree of Severity
Index Rank
Contractor-related factors 0.714 1
Materials-related factors 0.639 2
Client-related factors 0.637 3
External factors 0.630 4
Consultant-related factors 0.613 5
Labor-related factors 0.606 6
Equipment-related factors 0.600 7
Designer-related factors 0.599 8
Project-related factors 0.597 9
Table 7. Ranking of Sources (Groups) of Delays combined results
Sources (Groups) of delay 'Combined results'
Degree of Severity
Index Rank
Contractor-related factors 0.71 1
Designer-related factors 0.667 2
Materials-related factors 0.647 3
Labor-related factors 0.638 4
Consultant-related factors 0.629 5
Equipment-related factors 0.621 6
Client-related factors 0.61 7
External factors 0.59 8
Project-related factors 0.588 9
72
Table 8. Importance Rank Correlation
Parties
Spearman rank correlation
coefficient
Client - contractors 0.605
Client - consultant 0.551
Contractor - consultant 0.540
7. Summary and Conclusion
Construction delay in Afghanistan is explained through literature review and field survey.
Through in-depth literature review 83 causes of delay were identified, the factors
combined into nine groups. Three major stakeholders, including 20 client, 25 contractors
and 15 consultants responded the questionnaire forms. The respondents reported that
contract with less than 12months highly contributes to delays. The most common time
spent for the most delayed projects in Afghanistan is between 1 to 6 months.
The importance index was used to rank the effect of each cause of delay. It was found that
only two causes of delay are common between all parties, which are ‘security’ and
‘corruption’. Clients like consultants agreed that ineffective planning and scheduling of
project by contractor, poor qualification of the contractor’s technical staff and difficulties
in financing project by contractor are the most sever causes of delay by the contractors.
Whereas, the contractor reported that delay in progress payment by the client is one of the
significant causes of delay.
Contractor indicates that designer and client are the significant source of delays, while both
client and consultant specified ‘contractor’, and ‘materials’ causes as sources of delay. The
combined result of group causes shown that mostly the delay is caused by the ‘contractor’,
followed by ‘designer’ and ‘materials’, while ‘project related cause’ is less important. The
value of Spearman’s rank presents that the highest degree of agreement is between clients
and contractors which is 60.5%. The lowest degree of agreement is between contractors
and consultants which is 54%.
The importance index was used to rank the significant causes of delay, and it was found
that top 10 major causes of construction delays in Afghanistan are security and corruption
followed by poor qualification of the contractor’s technical staff, poor site management
and supervision by contractor, ineffective planning and scheduling of project by contractor,
and difficulties in financing project by contractor. Delay in progress payments by owner
and type of project bidding and award (negotiation, lowest price) are another critical
factors which contribute to construction delays.
8. Recommendations
8.1 General Recommendations
The following points can be recommended in order to reduce the impact of delays in
construction projects in Afghanistan:
1. Security issues have prevented some projects from being completed on schedule. Poor
security is the most difficult challenges that stakeholders face in implementing
73
construction projects. The security concerns in some parts particularity in south and
south east of Afghanistan has delayed projects and increased costs. Therefore, more
attention is required to be considered in maintaining security situations to provide
opportunities for contractors to complete the projects on timely manner.
2. Corruption constitutes a serious threat to Afghanistan Construction Industry
improvement as it has significant effects on construction delays. There is an urgent
need for developing a legal framework for fighting corruption, whereas the current
framework has been outdated and unclear.
3. Another critical factor is ‘poor site management and supervision by contractor’. There
is a need for contractor in improving abilities of managers, engineers which is a vast
demand in successful completion of projects. Thus, the contractors have to adapt some
essential innovative management techniques, including organizing and controlling, and
team building and value engineering that may be more efficient and effective. Having
applied these techniques, it would guarantee to reduce the risk of such critical factors.
4. Ineffective planning and scheduling has also a major impact on construction delays.
Effective planning and programming of a project is a must to secure early completion
of the project. The planning process should be developed from start of the project until
completion of a project. The planning stages should be devised very carefully, starting
from strategic, tactical and operational planning.
5. Another problem in contributing delays in Afghanistan is difficulties in financing
project by contractor. A serious attention must be paid in project feasibility. A vivid
mechanism for selecting the contractors who are financially capable to run the projects
without incurring delays is a must.
6. Delay in progress payment by client is a critical cause of delays, and as a result many
projects are behind schedule in Afghanistan. There is a serious need for the clients to
devise an explicit mechanism to speed up the payment process. The qualified
consultants and quantity surveyors, who are often responsible for issuing the
calculating and payment certificates, should be employed to ease the process. On the
other hand, Bureaucracy in government agencies also suspends the payment progress.
Therefore, it is advised that the government should find a way how to narrow down the
process.
8.2 Recommendation for Parties
To minimize and control delays in construction projects, the following issues can be
recommended by all parties:
8.2.1 Client
The clients should pay special attention to the following factors:
Pay progress payment to the contractors on time as it weakens the contractors
ability to finance the work
Minimize changes in order during construction so as to avoid delays
Speed up reviewing and approving of design documents
8.2.2 Contractor
The contractors should give more attention to the following factors:
Improve the knowledge and skills of technical staff
Manage the financial resources and plan cash flow by utilizing progress payment
74
Planning and scheduling the works from start of project and during the work to
match with the resources and time to develop the work to avoid delays
Improve site management and supervision to achieve completion of work within
specified time
8.2.3 Consultant
Consultants should focus on the following points:
Avoid delays in reviewing and approving design documents
Build up the knowledge and skills of technical staff
Improve coordination between parties
8.3 Recommendations for future studies
More research on construction delays should be done in order to develop guidelines, or
methods of minimizing the effects of construction delays in Afghanistan. Furthermore,
similar research should be performed in various provinces or cities of Afghanistan. In order
to providing more reliable data it is required to carry out studies for each specific type of
construction projects, including highways, dam construction projects, utilities and etc.
Surely, detailed surveys required to be performed to find out the effect of financing and
cash flow problems on delays in construction projects.
9. References
Al Khalil, M. and Ghaflu, M.A. (1999) Delay in public utility projects in Saudi Arabia.
International Journal of Project Management, 17(2), 101-106.
Al-Momani, A.H. (2000) Construction delays: a quantitative analysis. International
Journal of Project Management, 18(1), 5–9.
Assaf, S.A., Al-Khalil, M. and Al-Hazmi, M. (1995). Causes of Delay in Large Building
Construction Projects. Journal of Project Management in Engineering ASCE, 2; 45-50.
Assaf, S.A. and Al Hejji, S. (2006) Causes of delay in large construction projects.
International Journal of Project Management, 24, 349-357.
Chan, D.W.M. and Kumaraswamy, M.M. (1997) An evaluation of construction time
performance in the building industry. Journal of Building and Environment, 31(6),
569-578.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D., and Harris, F.C. (1997) Factors influencing
construction time and cost overruns on highrise projects in Indonesia. Journal of
Construction Management and Economics, 15(1), 83-94.
Koushki, P.A., Al-Rashid, K., and Kartam, N. (2005) Delays and cost increases in the
construction of private residential projects in Kuwait. Construction Management and
Economics, 23(3), 285-294.
Long, L.H., Lee, Y.D. and Lee, J. Y. (2008) Delay and Cost Overruns in Vietnam Large
Construction Projects:A Comparison with Other Selected Countries. Journal of Civil
Engineering, 12(6), 367-377.
Mezher, T.M. and Tawil, W. (1998) Causes of delays in the construction industry in
Lebanon. Engineering, Construction and Architectural Management 5(3), 252-260.
Trauner, J.T., Manginelli, W.A., Lowe, J.S., Nagata, M.F. and Furniss, B.J. (2009)
Construction Delays: understanding them clearly and Delay Analysis in Construction
Analyzing them correctly. London: Elsevier Inc.