EFFECTOR CORPORATION
PROPOSED THREE STOREYBOOK MARKET ON LOT 11, 12,13, AND 14 AT JALAN TUANKU
ABDUL RAHMAN,50350 FEDERAL TERRITORY
OF KUALA LUMPUR
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,
Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICALKawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,
Buler Engineering Sdn. Bhd.(No Syarikat : 641462-W)
QUANTITY SURVEYOR Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd
(No Syarikat :5265637S)
SHEET NO.
CLIENT
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
1201
ARCHITECT
Effector Corporation(No Syarikat :417634A)
SUBMISSION DATE7th OCTOBER 2015
PROJECT LEADERAR. PRINCE FAVIS ISIP
PROJECT MEMBERSCH'NG XING YUEKIAN SOON JEANLEONG CARMEN
LIEW HUI ENTAN HENG YEE
DRAWING LIST
COVER PAGE
KEY PLAN, LOCATION PLAN &SITE PLAN(CONSTRUCTION DRAWING)KEY PLAN, LOCATION PLAN &SITE PLAN(FIRE FIGHTING DRAWING)
GROUND FLOOR PLAN(CONSTRUCTION DRAWING)
GROUND FLOOR PLAN(FIRE FIGHTING DRAWING)
FIRST FLOOR PLAN(CONSTRUCTION DRAWING)
FIRST FLOOR PLAN(FIRE FIGHTING DRAWING)
SECOND FLOOR PLAN(CONSTRUCTION DRAWING)
SECOND FLOOR PLAN(FIRE FIGHTING DRAWING)
MEZZANINE FLOOR PLAN(CONSTRUCTION DRAWING)
MEZZANINE FLOOR PLAN(FIRE FIGHTING DRAWING)
FRONT ELEVATION & BACKELEVATION(CONSTRUCTION DRAWING)
SECTION B-B & SECTION C-C(CONSTRUCTION DRAWING)
ROOF PLAN(CONSTRUCTION DRAWING)
SECTION A-A(CONSTRUCTION DRAWING)
DOORS AND WINDOWSSCHEDULE(CONSTRUCTION DRAWING)DOORS AND WINDOWSSCHEDULE(CONSTRUCTION DRAWING)
SHEET NO.
01
2A
2B
3A
3B
4A
4B
5A
5B
6A
6B
07
08
09
10
11
12
LEONG CARMEN
DRAWN BY
CH'NG XING YUEKIAN SOON JEANLEONG CARMENCH'NG XING YUEKIAN SOON JEANLEONG CARMENCH'NG XING YUEKIAN SOON JEANLEONG CARMEN
LIEW HUI ENTAN HENG YEE
CH'NG XING YUEKIAN SOON JEANLEONG CARMEN
LIEW HUI ENTAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
TAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
TAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
TAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
TAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
TAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
TAN HENG YEE
KIAN SOON JEANLEONG CARMENLIEW HUI EN
KIAN SOON JEANLEONG CARMEN
LIEW HUI EN
TAN HENG YEECH'NG XING YUE
TAN HENG YEECH'NG XING YUE
TAN HENG YEECH'NG XING YUE
CIVIL & STRUCTURE ENGINEER
ENGINEER
Kg. BaruStation
PWTC Stn
Chow Kit Stn
Vision City Stn
MenaraKL Stn
Sultan Ismail/ BB Stn
Imbi Stn
Sultan Sulaiman Stn
TunSambanthanStn
KL SentralStation
BangsarStation
Syed PutraStation
Taman SeputehStation
Abdullah HukumStation
Setia WangsaStation
JelatekStation
Pasar KeramatStation
DamaiStation
Ampang ParkStation
KLCCStation
Dang WangiStation
Masjid JamekStation
Pasar SeniStation
Masjid JamekStation
BandarayaStation
Sultan IsmailStation
PWTCStation
Tun RazakStation
Bandar BaruSentulStation
Sentul TimurStation
Plaza RakyatStation
Hang TuahStation
PuduStation
Chan Sow LinStation
MaluriStation
CHOW KIT
DATARANMERDEKA
KUALA LUMPURCITY CENTRE
BRICKFIELDS
BUKITDAMANSARA
MONTKIARA
PUDU
BUKITBINTANG
SENTUL
TITIWANGSA
TAMAN DUTA
MALURI
BANGSAR
SEGAMBUT
KEPONG WANGSA MAJU
LOR
ON
G H
AJI T
AIB
4
LOR
ON
G H
AJI T
AIB
3
JALAN HAJI TAIB
JALA
N
TU
ANKU
A
BDU
L
RAH
MAN
JALAN CHOW KIT
JALAN RAJA ALANG
JALA
N H
AJI H
USS
EIN
CHOW KITSTATION
LOR
ON
G H
AJI T
AIB
1
LOR
ON
G H
AJI T
AIB
2
JALAN SERI AMAR
JALAN RAJA MUDA ABDUL AZIZ
JALAN SULTAN AZLAN SHAH
2250
06000
24200
4A
5A
C2
C1
12140
6400
29360
F
A
E
BC
2
6
7
3
5
8
4
D
1
2390 121404750
10070
3670
7150
4250
6440
2524
080
50
3950
1370
2860
2550
2550
6680
3580
8200
MUAZ TEXTILES
WM TRADING SDN. BHD.
KEDAI EMAS WAFA
JALA
N T
UAN
KU A
BDU
L R
AHM
AN
JALAN HAJI TAIB
A
P1-7
C
BP1-8-1
P1-8-2
KEHENDAK-KEHANDAK JABATAN BOMBA & PENYELAMAT BAGI BANGUNAN 1-5TINGKATKEHENDAK-KEHANDAK JABATAN BOMBA & PENYELAMAT BAGI BANGUNAN 1-5 TINGKATPelan Tapak1. Adakan buah pili bomba jenis tiang pengeluaran dua hala dengan pengeluaran air sebanyak 1362 liter seminit bagi
setiap pili bomba dan 2724/4086 lit/min apabila 2/3 buah pili bomba dibuka serentak (Pressurized Hydrant).Paip-paip yang digunakan untuk sistem pili bomba hendaklah dari jenis G.I. kelas `C' atau `Steel Line Cement Pipe'.`Fitting' yang digunakan untuk jenis paip-paip tersebut hendaklah dibuat daripada `Wrought Steel'.
2. Mengadakan 2 talian hos berukuran 64mm x 30m dan sebatang nozzle dari jenis `Jet & Spray' yang ditempatkan didalam peti cabinet berhampiran dengan tiap-tiap pili bomba.
3. Adakan jalan akses perkakas bomba (access road) dengan kelebaran tidak kurang 6 meter yang bolehmenanggung beban 25 tan sepertimana yang ditandakan di dalam pelan.
4. Kecerunan jalan akses perkakas bomba hendaklah tidak kurang 1:125. Ketinggian kelegaan hendaklah tidak kurang daripada 5 meter.6. Jarak antara bangunan hendaklah mematuhi Jadual Ke Enam UBBL 1984.
Kehendak-kehendak Am1. Semua pendawaian elektrik bagi sistem kecemasan hendaklah di dalam konduit logam atau daripada kabel yang
mempunyai penebat mineral tahan api. Pemasangannya hendaklah sepanjang kawasan yang paling kurang risikokebakarannya dan mematuhi UUK 253, UUKBS 1984.
2. Semua elemen struktur hendaklah mempunyai tempoh ketahanan api mengikut UBBL 1984.3. Adakan sistem pengudaraan bagi tangga keselamatan samada secara biasa atau mekanikal.4. Semua papan tanda keselamatan kebakaran hendaklah mematuhi MS 982:19855. Sila kemukakan tiga (3) set buku operasi mengikut syarat-syarat Jabatan Bomba dan Penyelamat Malaysia.
Kehendak-kehendak Aktif1. Adakan unit penggera kebakaran jenis pecah kaca mengikut syarat-syarat penentuan Tatatertib Amalan Piawaian
British atau mana-mana yang dibenarkan oleh Jabatan Bomba dan Penyelamat Malaysia.2. Adakan suis pengasingan elektrik (electrical isolation switch) dan hendaklah tidak menjejaskan apabila ia ditutup.3.. Adakan sistem siaraya awam (public address system) dan pemasangannya hendaklah menepati
kehendak-kehendak Jabatan Bomba dan Penyelamat Malaysia.4. Adakan sebuah pusat pemerintahan dan kawalan kebakaran di lantai tetuan (designated floor) yang dilengkapi
dengan peti penggera kebakaran.5. Adakan unit alat pemadam api yang bersesuaian menurut MS 1539:Part1:2002 sepertimana yang ditandakan di
dalam pelan.6. Ruangan lobi lif hendaklah dilindungi dibina dari bahan rintangan api dua jam dan hendaklah dilindungi dengan alat
pengesan asap mengikut UBBL 1984.7. Adakan sistem komunikasi bomba (telefon bomba). Sistem komunikasinya hendaklah tiga hala dan penempatannya
didalam tangga keselamatan/lobi menentang kebakaran, bilik motor lif, bilik pam bomba dan bilik jana kuasa.8. Adakan lampu tanda `KELUAR' kecemasan yang menggunakan dua kuasa karan sepertimana yang ditandakan di
dalam pelan. Lampu-lampu tersebut tersebut hendaklah dari jenis yang dibenarkan oleh Jabatan Bomba danPenyelamat Malaysia.
9. Adakan lampu kecemasan yang menggunakan dua kuasa karan sepertimana yang ditandakan di dalam pelan.Lampu-lampu tersebut hendaklah dari jenis yang dibenarkan oleh Jabatan Bomba dan Penyelamat Malaysia.
Kehendak-kehendak Pasif1. Penggunaan siling bangunan hendaklah menepati kehendak-kehendak UBBL 19842. Semua tangga keselamatan hendaklah dikepong dengan tembok batu bata setebal 115mm atau tangga terbuka
yang memenuhi kehendak-kehendak UBBL 1984 sepertimana yang ditandakan di dalam pelan3. Adakan pintu rintangan api satu jam sepertimana yang ditandakan di dalam pelan. Pemasanganya hendaklah
tertutup sendiri dan tertutup rapat4. Dinding bagi setor yang disifatkan merbahaya hendaklah setebal 100mm batu bata dan pintunya dari jenis rintangan
api satu jam dipasang dengan 'door-closer'5. Semua lubang perkhidmatan (sevice shaft) hendaklah ditutup di setiap tingkat dengan bahan rintangan api dua jam6. Semua bilik bagi penempatan pam bomba dan janakuasa hendaklah dibina dari tembok batu batayang tahan
rintangan api dua jam. pintu-pintunya hendaklah dari rintangan api satu jam7. Semua dinding pembahagi dalaman hendaklah dari jenis rintangan api 1/2 jam dan dari jenis yang dibenarkan oleh
Jabatan Bomba dan Penyelamat Malaysia
Peringatan1. Segala syarat-syaratyang dikemukakan adalah tertakluk kepada rekabentuk dan kegunaan serta lokasi bangunan
tersebut. Sekiranya sebarang perubahan yang dilakukan ke atas rekabentuk atau kegunaanya seperti yangdicatatkan di atas pelan maka hendaklah dirujuk kejabatan ini dikaji semula
2. Segala pemilihan bahan dan penggunaannya yang berkaitan dengan keselamatan kebakaran bagi projek cadanganserta sistem pencegahan kebakaran hendaklah mematuhi UBBL 1984 dan peraturan-peraturan yang diterimasahaja dan yang dibenarkan oleh Jabatan Bomba dan Penyelamat Malaysia.
3. Pengesahan pelan ini adalah tidak tertakluk kepada penyimpanan, penggunaan, pemprosesan dan penghasilanbahan berbahaya atau kimia berbahaya setelah pelan disahkan maka pelan bangunan tersebut hendaklah dirujukkembali ke jabatan ini untuk dikaji semula
4. Pelan lukisan dan pengiraan bagi semua pemasangan tetap hendaklah dikemukakan ke Jabatan Bomba danPenyelamat Malaysia. Jumlah pelan-pelan yang dikemukan hendaklah tidak kurang (3) perenggu
5. Mana-mana premis yang mengendalikan, memproses atau menyimpan bahan-bahan bahaya hendaklah diadakantanda khas mengikut symbol 'Hazchem Code'. Tanda-tanda hendaklah mudah dilihat.
AS SHOWN
2A
KEY PLAN
2015/ARC3524/BT2/P1/2A
BUILDING NOTES1. Subdivisions of lots to be carried out in accordance with approved R.S. Plan.2. These works are to be carried out under the supervision of ARCHITECT.3. Figured dimension to be carried out before those measured by scale.4. Subsoil invertigation to be carried out before development commences.5. To submit Land Clearance Certificate.6. R.C. Details and Calculations to be submitted by ENGINEERS before commencing building operations.7. Roads and Drains to be made up in accordance with approved Road & Drainage Plans before commencing
operations.8. All building materials and debris to be removed from site on completion of works.9. No building materials are to be deposited on any public streets, drains, and open spaces.10. No Occupational Certificate will be issued unless all materials, refuse debris are removed from site.11. All 4 1/2in BWK. in cement mortar 1:3 and reinforced with "EXMET" at every 4th course.12. D.P.C. to be provided to all BWK.13. All mass conc. to be 1:3:4 and reinf. conc. 1:2:4.14. Walls of kitchen, W.C. and bath to have 5'-0" high glazed tiles and all corners rounded off.15. All structural timber to be of secondary hardwood and tanalised.16. Provide a Council approved Dustbin to each house.17. Proved Iron Gratings to all outlets.18. Provide water supply to JKR specifications.19. Water to kitchen to be directed from mains.20. Sanitary, Road and Drainage Plans shall be submitted separately and approved before commencing building
operations.21. All sanitary ware C.I. pipes to be fitted with inspection covers.22. Concrete lintels over door and window frames must be properly reinforced according to the span of lintels and
supported independently without bearing the load directly over the frames.23. All M.S. security bard to louvred window shall be not less than 58 in diameter.24. All roof trusses shall be fixed with proper size 16mm bolts and nuts and not nails.25. All foundations shall be confined within the limit of the Lot Boundary and no encroachment shall be permitted
outside the property limits.26. Building construction shall not commence until plans for hoarding have been submitted and approved and the
hoarding erected and inspected.27. Hoarding shall not be less than 8 feet high with slanting top and pedestrian walkway and shall be properly anchored
to the ground.
NLOCATION PLAN SITE PLAN
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CH'NG XING YUE, KIAN SOON JEAN& LEONG CARMEN
Kg. BaruStation
PWTC Stn
Chow Kit Stn
Vision City Stn
MenaraKL Stn
Sultan Ismail/ BB Stn
Imbi Stn
Sultan Sulaiman Stn
TunSambanthanStn
KL SentralStation
BangsarStation
Syed PutraStation
Taman SeputehStation
Abdullah HukumStation
Setia WangsaStation
JelatekStation
Pasar KeramatStation
DamaiStation
Ampang ParkStation
KLCCStation
Dang WangiStation
Masjid JamekStation
Pasar SeniStation
Masjid JamekStation
BandarayaStation
Sultan IsmailStation
PWTCStation
Tun RazakStation
Bandar BaruSentulStation
Sentul TimurStation
Plaza RakyatStation
Hang TuahStation
PuduStation
Chan Sow LinStation
MaluriStation
CHOW KIT
DATARANMERDEKA
KUALA LUMPURCITY CENTRE
BRICKFIELDS
BUKITDAMANSARA
MONTKIARA
PUDU
BUKITBINTANG
SENTUL
TITIWANGSA
TAMAN DUTA
MALURI
BANGSAR
SEGAMBUT
KEPONG WANGSA MAJU
2250
06000
24200
4A
5A
C2
C1
12140
6400
29360
F
A
E
BC
2
6
7
3
5
8
4
D
1
2390 121404750
10070
3670
7150
4250
6440
2524
080
50
3950
1370
2860
2550
2550
6680
3580
8200
MUAZ TEXTILES
WM TRADING SDN. BHD.
KEDAI EMAS WAFA
JALA
N T
UAN
KU A
BDU
L R
AHM
AN
JALAN HAJI TAIB
H
A
P1-7
C
BP1-8-1
P1-8-2
LOR
ON
G H
AJI T
AIB
4
LOR
ON
G H
AJI T
AIB
3
JALAN HAJI TAIB
JALA
N
TU
ANKU
A
BDU
L
RAH
MAN
JALAN CHOW KIT
JALAN RAJA ALANG
JALA
N H
AJI H
USS
EIN
CHOW KITSTATION
LOR
ON
G H
AJI T
AIB
1
LOR
ON
G H
AJI T
AIB
2
JALAN SERI AMAR
JALAN RAJA MUDA ABDUL AZIZ
JALAN SULTAN AZLAN SHAH
KEHENDAK-KEHANDAK JABATAN BOMBA & PENYELAMAT BAGI BANGUNAN 1-5TINGKATKEHENDAK-KEHANDAK JABATAN BOMBA & PENYELAMAT BAGI BANGUNAN 1-5 TINGKATPelan Tapak1. Adakan buah pili bomba jenis tiang pengeluaran dua hala dengan pengeluaran air sebanyak 1362 liter seminit bagi
setiap pili bomba dan 2724/4086 lit/min apabila 2/3 buah pili bomba dibuka serentak (Pressurized Hydrant).Paip-paip yang digunakan untuk sistem pili bomba hendaklah dari jenis G.I. kelas `C' atau `Steel Line Cement Pipe'.`Fitting' yang digunakan untuk jenis paip-paip tersebut hendaklah dibuat daripada `Wrought Steel'.
2. Mengadakan 2 talian hos berukuran 64mm x 30m dan sebatang nozzle dari jenis `Jet & Spray' yang ditempatkan didalam peti cabinet berhampiran dengan tiap-tiap pili bomba.
3. Adakan jalan akses perkakas bomba (access road) dengan kelebaran tidak kurang 6 meter yang bolehmenanggung beban 25 tan sepertimana yang ditandakan di dalam pelan.
4. Kecerunan jalan akses perkakas bomba hendaklah tidak kurang 1:125. Ketinggian kelegaan hendaklah tidak kurang daripada 5 meter.6. Jarak antara bangunan hendaklah mematuhi Jadual Ke Enam UBBL 1984.
Kehendak-kehendak Am1. Semua pendawaian elektrik bagi sistem kecemasan hendaklah di dalam konduit logam atau daripada kabel yang
mempunyai penebat mineral tahan api. Pemasangannya hendaklah sepanjang kawasan yang paling kurang risikokebakarannya dan mematuhi UUK 253, UUKBS 1984.
2. Semua elemen struktur hendaklah mempunyai tempoh ketahanan api mengikut UBBL 1984.3. Adakan sistem pengudaraan bagi tangga keselamatan samada secara biasa atau mekanikal.4. Semua papan tanda keselamatan kebakaran hendaklah mematuhi MS 982:19855. Sila kemukakan tiga (3) set buku operasi mengikut syarat-syarat Jabatan Bomba dan Penyelamat Malaysia.
Kehendak-kehendak Aktif1. Adakan unit penggera kebakaran jenis pecah kaca mengikut syarat-syarat penentuan Tatatertib Amalan Piawaian
British atau mana-mana yang dibenarkan oleh Jabatan Bomba dan Penyelamat Malaysia.2. Adakan suis pengasingan elektrik (electrical isolation switch) dan hendaklah tidak menjejaskan apabila ia ditutup.3.. Adakan sistem siaraya awam (public address system) dan pemasangannya hendaklah menepati
kehendak-kehendak Jabatan Bomba dan Penyelamat Malaysia.4. Adakan sebuah pusat pemerintahan dan kawalan kebakaran di lantai tetuan (designated floor) yang dilengkapi
dengan peti penggera kebakaran.5. Adakan unit alat pemadam api yang bersesuaian menurut MS 1539:Part1:2002 sepertimana yang ditandakan di
dalam pelan.6. Ruangan lobi lif hendaklah dilindungi dibina dari bahan rintangan api dua jam dan hendaklah dilindungi dengan alat
pengesan asap mengikut UBBL 1984.7. Adakan sistem komunikasi bomba (telefon bomba). Sistem komunikasinya hendaklah tiga hala dan penempatannya
didalam tangga keselamatan/lobi menentang kebakaran, bilik motor lif, bilik pam bomba dan bilik jana kuasa.8. Adakan lampu tanda `KELUAR' kecemasan yang menggunakan dua kuasa karan sepertimana yang ditandakan di
dalam pelan. Lampu-lampu tersebut tersebut hendaklah dari jenis yang dibenarkan oleh Jabatan Bomba danPenyelamat Malaysia.
9. Adakan lampu kecemasan yang menggunakan dua kuasa karan sepertimana yang ditandakan di dalam pelan.Lampu-lampu tersebut hendaklah dari jenis yang dibenarkan oleh Jabatan Bomba dan Penyelamat Malaysia.
Kehendak-kehendak Pasif1. Penggunaan siling bangunan hendaklah menepati kehendak-kehendak UBBL 19842. Semua tangga keselamatan hendaklah dikepong dengan tembok batu bata setebal 115mm atau tangga terbuka
yang memenuhi kehendak-kehendak UBBL 1984 sepertimana yang ditandakan di dalam pelan3. Adakan pintu rintangan api satu jam sepertimana yang ditandakan di dalam pelan. Pemasanganya hendaklah
tertutup sendiri dan tertutup rapat4. Dinding bagi setor yang disifatkan merbahaya hendaklah setebal 100mm batu bata dan pintunya dari jenis rintangan
api satu jam dipasang dengan 'door-closer'5. Semua lubang perkhidmatan (sevice shaft) hendaklah ditutup di setiap tingkat dengan bahan rintangan api dua jam6. Semua bilik bagi penempatan pam bomba dan janakuasa hendaklah dibina dari tembok batu batayang tahan
rintangan api dua jam. pintu-pintunya hendaklah dari rintangan api satu jam7. Semua dinding pembahagi dalaman hendaklah dari jenis rintangan api 1/2 jam dan dari jenis yang dibenarkan oleh
Jabatan Bomba dan Penyelamat Malaysia
Peringatan1. Segala syarat-syaratyang dikemukakan adalah tertakluk kepada rekabentuk dan kegunaan serta lokasi bangunan
tersebut. Sekiranya sebarang perubahan yang dilakukan ke atas rekabentuk atau kegunaanya seperti yangdicatatkan di atas pelan maka hendaklah dirujuk kejabatan ini dikaji semula
2. Segala pemilihan bahan dan penggunaannya yang berkaitan dengan keselamatan kebakaran bagi projek cadanganserta sistem pencegahan kebakaran hendaklah mematuhi UBBL 1984 dan peraturan-peraturan yang diterimasahaja dan yang dibenarkan oleh Jabatan Bomba dan Penyelamat Malaysia.
3. Pengesahan pelan ini adalah tidak tertakluk kepada penyimpanan, penggunaan, pemprosesan dan penghasilanbahan berbahaya atau kimia berbahaya setelah pelan disahkan maka pelan bangunan tersebut hendaklah dirujukkembali ke jabatan ini untuk dikaji semula
4. Pelan lukisan dan pengiraan bagi semua pemasangan tetap hendaklah dikemukakan ke Jabatan Bomba danPenyelamat Malaysia. Jumlah pelan-pelan yang dikemukan hendaklah tidak kurang (3) perenggu
5. Mana-mana premis yang mengendalikan, memproses atau menyimpan bahan-bahan bahaya hendaklah diadakantanda khas mengikut symbol 'Hazchem Code'. Tanda-tanda hendaklah mudah dilihat.
AS SHOWN
2B
KEY PLAN
2015/ARC3524/BT2/P1/2B
BUILDING NOTES1. Subdivisions of lots to be carried out in accordance with approved R.S. Plan.2. These works are to be carried out under the supervision of ARCHITECT.3. Figured dimension to be carried out before those measured by scale.4. Subsoil invertigation to be carried out before development commences.5. To submit Land Clearance Certificate.6. R.C. Details and Calculations to be submitted by ENGINEERS before commencing building operations.7. Roads and Drains to be made up in accordance with approved Road & Drainage Plans before commencing
operations.8. All building materials and debris to be removed from site on completion of works.9. No building materials are to be deposited on any public streets, drains, and open spaces.10. No Occupational Certificate will be issued unless all materials, refuse debris are removed from site.11. All 4 1/2in BWK. in cement mortar 1:3 and reinforced with "EXMET" at every 4th course.12. D.P.C. to be provided to all BWK.13. All mass conc. to be 1:3:4 and reinf. conc. 1:2:4.14. Walls of kitchen, W.C. and bath to have 5'-0" high glazed tiles and all corners rounded off.15. All structural timber to be of secondary hardwood and tanalised.16. Provide a Council approved Dustbin to each house.17. Proved Iron Gratings to all outlets.18. Provide water supply to JKR specifications.19. Water to kitchen to be directed from mains.20. Sanitary, Road and Drainage Plans shall be submitted separately and approved before commencing building
operations.21. All sanitary ware C.I. pipes to be fitted with inspection covers.22. Concrete lintels over door and window frames must be properly reinforced according to the span of lintels and
supported independently without bearing the load directly over the frames.23. All M.S. security bard to louvred window shall be not less than 58 in diameter.24. All roof trusses shall be fixed with proper size 16mm bolts and nuts and not nails.25. All foundations shall be confined within the limit of the Lot Boundary and no encroachment shall be permitted
outside the property limits.26. Building construction shall not commence until plans for hoarding have been submitted and approved and the
hoarding erected and inspected.27. Hoarding shall not be less than 8 feet high with slanting top and pedestrian walkway and shall be properly anchored
to the ground.
NLOCATION PLAN SITE PLAN
FIRE FIGHTING LEGENDALARM BELL
DRY POWDER EXTINGUISER( WEIGHT =9KG)
BREAK GLASSSMOKE DETECTOR
FIRE HYDRANT
"KELUAR" SIGNEMERGENCY LIGHTHOSE REEL & WET RISER
CO2 CYLINDER (45.5 KG EACH)
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CH'NG XING YUE, KIAN SOON JEAN& LEONG CARMENBOMBA ANNOTATIONLEONG CARMEN & TAN HENG YEE
4A
5A
C2C1
REFUSE CHAMBER
ELE CW TELDR
M&E
UP
UP
6400
UP
32130
F AE BC
2
6
7
3
5
8
4
D
1
G
A
P1-8
CB
P1-9-1 P1-9-2
2390
4250
6440
2524
012140
475080
50
10070
3950
3670
7150
1370
2860
2550
2550
6680
3580
8200
MALE TOILET
FEMALE TOILET
DISABLED
KITCHEN
TOILET
LOADING BAY
CAFE
1 2 3 4 5 6 7 8 9 10 11
12131415161718192021
12345678910111213141516171819202122
123456789
16151413121110
249.15m2
5700mm
HW
UFUF
TP
49.1m2
12400mm
VS
UFUF
VT
MV
15.85m2
mm
-
UFUF
CR
MV
166.32m2
4000mm
HW
UFUF
TP
MV
46.4m2
4200mm
HW
MFAP
TP
-
NV
46.4m2
-
HW
-UF
TP
NV
4.6m2
-
HW
-UF
TP
NV
47.4m2
-
-
-UF
TP
NV
15.2m2
-
UF
CR
MV
-UF
6.7m2
-
UF
CR
MV
-UF
8.1m2
3900mm
GR
UFUF
GR
NV
12.8m2
3900mm
GR
UFUF
GR
NV
8m2
3900mm
VS
UFCT
VT
MV
4.7m2
3900mm
-
UFUF
CR
MV
MARKET PLACE
FFL = +0.000 FFL = +0.800
FFL = -0.405
FFL = -0.180
FFL = +0.000
FFL = -0.025
FFL = +0.000FFL = +0.000
FFL = +0.000
FFL = +0.000
FFL = +0.000
FFL = +0.000
FIRESTAIRCASE 1
FFL = +0.000
FIRESTAIRCASE 2
FFL = -0.025
LENGTH : 2150HEIGHT : 180RATIO : 1:12
LENGTH : 1800HEIGHT : 180RATIO : 1:10
MUAZ TEXTILE
WM TRADING SDN. BHD.
LIBRARY
COURTYARD
3.5m2
3900mm
GR
UFUF
GR
NV
FFL = -0.025
01D
02D
03D
04D
04D
04D
05D
07D
07D
08D
01FRD
01FRD
02FRD
02FRD
02FRD
02FRD
03FRD
01W
01W
01W
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
115MM THICK FAIR FACED BRICKWALL
230MM THICK CLAYBRICKS PARTIWALL
RC STAIRCASE TO ENGR'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
2770
03W
PIVOT DOOR-SHELVES
EXISTING COLUMNS
1:100
3A
GROUND FLOOR PLAN
2015/ARC3524/BT2/P1/3A
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACESGROUNDFLOOR
LIBRARYMARKET PLACECOURTYARDCAFEKITCHEN
M&E ROOM
AREA
46.40m2
415.47m2
52.00m2
49.10m2
8.00m2
4.70m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
4.64m2
41.55m2
5.20m2
4.91m2
0.80m2
0.47m2
2.32m2
20.78m2
2.60m2
2.46m2
0.40m2
0.24m2
STEEL FRAME DOUBLE PANELS ,PLYWOOD PIVOT DOOR & 2nos. CENTER HUNGS DOORSETS
DOOR LEGEND DOOR SIZE LOCATION NO. TOTAL
STEEL FRAME DOUBLE PANELS ,PLYWOOD PIVOT DOOR & 1nos. CENTER HUNGS DOORSETSMETAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINTPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONMETAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINTMETAL FRAME SINGLE LEAF ,TWO HOUR FIRE RATED SOLIDTIMBER DOOR WITH 4.nos. S.S. HINGES & LOCKSET /IRONMONGERY C/W WATERPROOFED EPOXY PAINT
2300 X 3500mm
2000 x 3500mm
1350 X 2180mm
850 X 2180mm
2300 X 3500mm
1000 X 2200mm
850 X 2180mm
750 X 2110mm
LIBRARY
LIBRARY
CORRIDOR
MALE TOILET
DISABLED TOILET
KITCHEN
BOMBA TELEPHONECOLD WATER
DRY RISER
M&E ROOM
1
1
1
1
1
1
2
3 SETS111
FEMALE TOILET 2
2 SETS
3 SETS
1 SET
1 SET
1 SET
1 SET
1 SET
130MM THK ALUMINIUM LOUVERS WITH 45°HORIZONTAL BLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL
KITCHEN
16111
1
19 SETS
1 SET
840 X 650mm FIVE FOOT WALKWAYMALE TOILET
FEMALE TOILETDISABLED TOILET
ANODIZED ALUMINIUM SLIDING WINDOW WITH 8MM THKCLEAR GLASS
1660 X 1290mm
CALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION
DOOR SCHEDULE WINDOW SCHEDULE
REFUSE CHAMBER 6.70m2 0.67m2 0.34m2
01W
03W
01D
02D
03D
04D
05D
07D
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWO HOURFIRE RATED SOLID TIMBER DOOR & 10 nos. S.S HINGES &TWO HOUR RATED LOCK SET / IROMONGEREY TO ARCH'SAPP
1150 X 2180mm FIRE STAIRCASE 1FIRE STAIRCASE 2
11
2 SETS
METAL ROLLER SHUTTER 1000 X 2600mm REFUSE CHAMBER 1 1 SET08D
01FRD
02FRD
03FRD
01D
02D
01D
01W
07D
03W
03FRD
08D
11.45m2
80.84m2
75.12m2
55.44m2
5.94m2
1.58m2
2.60m2
11.45m2
80.84m2
75.12m2
55.44m2
5.94m2
1.58m2
2.60m2
FIRE STAIRCASE 1FIRE STAIRCASE 2MALE TOILETFEMALE TOILETDISABLED TOILET
15.85m2
15.20m2
8.10m2
12.80m2
3.50m2
1.59m2
1.52m2
0.81m2
1.28m2
0.35m2
0.80m2
0.76m2
0.40m2
0.64m2
0.18m2
01FRD
01FRD
04D
01W
04D
01W
05D
01W
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CH'NG XING YUEDOORS & WINDOWS ANNOTATIONTAN HENG YEESPECIFICATIONSLIEW HUI ENFINISHES BOXLIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS SCHEDULES &CALCULATION TABLELEONG CARMEN
4A
5A
C2C1
REFUSE CHAMBER
ELE CW TELDR
M&E
UP
UP
6400
UP
32130
F AE BC
2
6
7
3
5
8
4
D
1
G
2390
4250
6440
2524
012140
475080
50
10070
3950
3670
7150
1370
2860
2550
2550
6680
3580
8200
MALE TOILET
FEMALE TOILET
DISABLED
KITCHEN
TOILET
LOADING BAY
CAFE
1 2 3 4 5 6 7 8 9 10 11
12131415161718192021
12345678910111213141516171819202122
123456789
16151413121110
249.15m2
5700mm
HW
UFUF
TP
49.1m2
12400mm
VS
UFUF
VT
MV
15.85m2
mm
-
UFUF
CR
MV
166.32m2
4000mm
HW
UFUF
TP
MV
46.4m2
4200mm
HW
MFAP
TP
-
NV
46.4m2
-
HW
-UF
TP
NV
4.6m2
-
HW
-UF
TP
NV
47.4m2
-
-
-UF
TP
NV
15.2m2
-
UF
CR
MV
-UF
6.7m2
-
UF
CR
MV
-UF
8.1m2
3900mm
GR
UFUF
GR
NV
12.8m2
3900mm
GR
UFUF
GR
NV
8m2
3900mm
VS
UFCT
VT
MV
4.7m2
3900mm
-
UFUF
CR
MV
MARKET PLACE
FFL = +0.000 FFL = +0.800
FFL = -0.405
FFL = -0.180
FFL = +0.000
FFL = -0.025
FFL = +0.000FFL = +0.000
FFL = +0.000
FFL = +0.000
FFL = +0.000
FFL = +0.000
FIRESTAIRCASE 1
FFL = +0.000
FIRESTAIRCASE 2
FFL = -0.025
LENGTH : 2150HEIGHT : 180RATIO : 1:12
LENGTH : 1800HEIGHT : 180RATIO : 1:10
MUAZ TEXTILE
WM TRADING SDN. BHD.
LIBRARY
COURTYARD
3.5m2
3900mm
GR
UFUF
GR
NV
FFL = -0.025
01D
02D
03D
04D
04D
04D
05D
07D
07D
08D
01FRD
01FRD
03FRD
01W
01W
01W
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
115MM THICK FAIR FACED BRICKWALL
230MM THICK CLAYBRICKS PARTIWALL
RC STAIRCASE TO ENGR'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
2770
03W
PIVOT DOOR-SHELVES
EXISTING COLUMNS
H
02FRD
02FRD
02FRD
02FRD
1:100
3B
GROUND FLOOR PLAN
2015/ARC3524/BT2/P1/3B
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACESGROUNDFLOOR
LIBRARYMARKET PLACECOURTYARDCAFEKITCHEN
M&E ROOM
AREA
46.40m2
415.47m2
52.00m2
49.10m2
8.00m2
4.70m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
4.64m2
41.55m2
5.20m2
4.91m2
0.80m2
0.47m2
2.32m2
20.78m2
2.60m2
2.46m2
0.40m2
0.24m2
STEEL FRAME DOUBLE PANELS ,PLYWOOD PIVOT DOOR & 2nos. CENTER HUNGS DOORSETS
DOOR LEGEND DOOR SIZE LOCATION NO. TOTAL
STEEL FRAME DOUBLE PANELS ,PLYWOOD PIVOT DOOR & 1nos. CENTER HUNGS DOORSETSMETAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINTPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONMETAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINTMETAL FRAME SINGLE LEAF ,TWO HOUR FIRE RATED SOLIDTIMBER DOOR WITH 4.nos. S.S. HINGES & LOCKSET /IRONMONGERY C/W WATERPROOFED EPOXY PAINT
2300 X 3500mm
2000 x 3500mm
1350 X 2180mm
850 X 2180mm
2300 X 3500mm
1000 X 2200mm
850 X 2180mm
750 X 2110mm
LIBRARY
LIBRARY
CORRIDOR
MALE TOILET
DISABLED TOILET
KITCHEN
BOMBA TELEPHONECOLD WATER
DRY RISER
M&E ROOM
1
1
1
1
1
1
2
3 SETS111
FEMALE TOILET 2
2 SETS
3 SETS
1 SET
1 SET
1 SET
1 SET
1 SET
130MM THK ALUMINIUM LOUVERS WITH 45°HORIZONTAL BLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL
KITCHEN
16111
1
19 SETS
1 SET
840 X 650mm FIVE FOOT WALKWAYMALE TOILET
FEMALE TOILETDISABLED TOILET
ANODIZED ALUMINIUM SLIDING WINDOW WITH 8MM THKCLEAR GLASS
1660 X 1290mm
CALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION
DOOR SCHEDULE
WINDOW SCHEDULE
REFUSE CHAMBER 6.70m2 0.67m2 0.34m2
01W
03W
01D
02D
03D
04D
05D
07D
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWO HOURFIRE RATED SOLID TIMBER DOOR & 10 nos. S.S HINGES &TWO HOUR RATED LOCK SET / IROMONGEREY TO ARCH'SAPP
1150 X 2180mm FIRE STAIRCASE 1FIRE STAIRCASE 2
11
2 SETS
METAL ROLLER SHUTTER 1000 X 2600mm REFUSE CHAMBER 1 1 SET08D
01FRD
02FRD
03FRD
01D
02D
01D
01W
07D
03W
03FRD
08D
11.45m2
80.84m2
75.12m2
55.44m2
5.94m2
1.58m2
2.60m2
11.45m2
80.84m2
75.12m2
55.44m2
5.94m2
1.58m2
2.60m2
FIRE STAIRCASE 1FIRE STAIRCASE 2MALE TOILETFEMALE TOILETDISABLED TOILET
15.85m2
15.20m2
8.10m2
12.80m2
3.50m2
1.59m2
1.52m2
0.81m2
1.28m2
0.35m2
0.80m2
0.76m2
0.40m2
0.64m2
0.18m2
01FRD
01FRD
04D
01W
04D
01W
05D
01W
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
FIRE FIGHTING LEGENDALARM BELL
DRY POWDER EXTINGUISER( WEIGHT =9KG)
BREAK GLASSSMOKE DETECTOR
FIRE HYDRANT
"KELUAR" SIGNEMERGENCY LIGHTHOSE REEL & WET RISER
CO2 CYLINDER (45.5 KG EACH)
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CH'NG XING YUEDOORS & WINDOWS ANNOTATIONTAN HENG YEESPECIFICATIONSLIEW HUI ENFINISHES BOXLIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS SCHEDULES &CALCULATION TABLELEONG CARMENBOMBA ANNOTATIONLEONG CARMEN & TAN HENG YEE
UP
UP
REFUSE CHAMBER
UP
23 24 25 26 27 28 29 30 31 32 33
3435363716171819202122
2526272829303132
2324
333637383940414243
3435
44
ELE CW TELDR
10070
MALE TOILET
FEMALE TOILET
DISABLEDTOILET
F AE BC
2
6
7
3
5
8
4
D
1
G
A
P1-8
CB
P1-9-1 P1-9-2
29360
4250
2390 6400
3950
121404750
121407150
29
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
363719202122232425
33323130282726 34
4A
5A
C2C1
115.4m2
3900mm
HW
UFUF
TP
MV
116.32m2
8100mm
HW
UFUF
TP
MV
46.4m2
5800mm
HW
UFUF
TP
MV
VOID
VOID
VOID
35FIRESTAIRCASE 1
FIRESTAIRCASE 2
15.85m2
mm
-
UFUF
CR
MV
15.2m2
-
UF
CR
MV
-UF
6.7m2
-
UF
CR
MV
-UF
FFL = +3.900
FFL = +4.400
FFL = +3.900
FFL = +4.400FFL = +3900FFL = +3.900
LENGTH : 11880HEIGHT : 500RATIO : 1:24
ROOF
CAFEMARKET PLACE
04D
04D
04D
05D
08D
09D
10D
01FRD
01FRD
02FRD
02FRD
02FRD
02FRD
01W
01W
01W
900MM (W) X 3100MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
RC STAIRCASE TO ENGR'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
230MM THICK CLAYBRICKS PARTIWALL
1:100
4B
FIRST FLOOR PLAN
2015/ARC3524/BT2/P1/4B
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACESFIRSTFLOOR
MARKET PLACECAFE
AREA
231.72m2
46.4m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
23.17m2
4.64m22.32m2
20.78m2
DOOR LEGEND DOOR SIZE LOCATION NO. TOTALPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATION
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
850 X 2180mm
2300 X 3500mm
850 X 2180mm
MALE TOILET
DISABLED TOILET
BOMBA TELEPHONECOLD WATER
DRY RISER
1
1
3 SETS111
FEMALE TOILET 23 SETS
1 SET 130MM THK ALUMINIUM LOUVERS WITH 45°HORIZONTAL BLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL111
3 SETS840 X 650mm MALE TOILETFEMALE TOILET
DISABLED TOILET
CALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION DOOR SCHEDULE
WINDOW SCHEDULE
01W
04D
05D
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWOHOUR FIRE RATED SOLID TIMBER DOOR & 10 nos. S.SHINGES & TWO HOUR RATED LOCK SET / IROMONGEREYTO ARCH'S APP
1150 X 2180mm FIRE STAIRCASE 1FIRE STAIRCASE 2
11
2 SETS01FRD
02FRD
09D
121.76m2
120.07m2352.62m2
73.67m2
CAFE09D
10D ALUMINIUM BI-FOLD PATIO DOOR WITH 5 SERIES OF HINGED
DOORS
ALUMINIUM BI-FOLD PATIO DOOR WITH 7 SERIES OF HINGEDDOORS
CAFE
1 1 SET
1 1 SET
7460 X 3700mm
5920 X 3700mm
10D
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
1000 X 2200mm REFUSE CHAMBER07D 1 1 SET
FIRE STAIRCASE 1FIRE STAIRCASE 2MALE TOILETFEMALE TOILETDISABLED TOILET
15.85m2
15.20m2
8.10m2
12.80m2
3.50m2
1.59m2
1.52m2
0.81m2
1.28m2
0.35m2
0.80m2
0.76m2
0.40m2
0.64m2
0.18m2
REFUSE CHAMBER 6.70m2 0.67m2 0.34m2
01FRD
01FRD
04D
01W
04D
01W
05D
01W
07D
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
FIRE FIGHTING LEGENDALARM BELL
DRY POWDER EXTINGUISER( WEIGHT =9KG)
BREAK GLASSSMOKE DETECTOR
FIRE HYDRANT
"KELUAR" SIGNEMERGENCY LIGHTHOSE REEL & WET RISER
CO2 CYLINDER (45.5 KG EACH)
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
LIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS ANNOTATIONTAN HENG YEESPECIFICATIONSLIEW HUI ENFINISHES BOXLIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS SCHEDULES &CALCULATION TABLELEONG CARMENBOMBA ANNOTATIONLEONG CARMEN & TAN HENG YEE
UP
UP
REFUSE CHAMBER
UP
23 24 25 26 27 28 29 30 31 32 33
3435363716171819202122
2526272829303132
2324
333637383940414243
3435
44
ELE CW TELDR
10070
MALE TOILET
FEMALE TOILET
DISABLEDTOILET
F AE BC
2
6
7
3
5
8
4
D
1
G
A
P1-8
CB
P1-9-1 P1-9-2
29360
4250
2390 6400
3950
121404750
121407150
29
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
363719202122232425
33323130282726 34
4A
5A
C2C1
115.4m2
3900mm
HW
UFUF
TP
MV
116.32m2
8100mm
HW
UFUF
TP
MV
46.4m2
5800mm
HW
UFUF
TP
MV
VOID
VOID
VOID
35FIRESTAIRCASE 1
FIRESTAIRCASE 2
15.85m2
mm
-
UFUF
CR
MV
15.2m2
-
UF
CR
MV
-UF
6.7m2
-
UF
CR
MV
-UF
FFL = +3.900
FFL = +4.400
FFL = +3.900
FFL = +4.400FFL = +3900FFL = +3.900
LENGTH : 11880HEIGHT : 500RATIO : 1:24
ROOF
CAFEMARKET PLACE
04D
04D
04D
05D
08D
09D
10D
01FRD
01FRD
02FRD
02FRD
02FRD
02FRD
01W
01W
01W
900MM (W) X 3100MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
RC STAIRCASE TO ENGR'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
230MM THICK CLAYBRICKS PARTIWALL
1:100
4B
FIRST FLOOR PLAN
2015/ARC3524/BT2/P1/4B
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACESFIRSTFLOOR
MARKET PLACECAFE
AREA
231.72m2
46.4m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
23.17m2
4.64m22.32m2
20.78m2
DOOR LEGEND DOOR SIZE LOCATION NO. TOTALPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATION
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
850 X 2180mm
2300 X 3500mm
850 X 2180mm
MALE TOILET
DISABLED TOILET
BOMBA TELEPHONECOLD WATER
DRY RISER
1
1
3 SETS111
FEMALE TOILET 23 SETS
1 SET 130MM THK ALUMINIUM LOUVERS WITH 45°HORIZONTAL BLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL111
3 SETS840 X 650mm MALE TOILETFEMALE TOILET
DISABLED TOILET
CALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION DOOR SCHEDULE
WINDOW SCHEDULE
01W
04D
05D
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWOHOUR FIRE RATED SOLID TIMBER DOOR & 10 nos. S.SHINGES & TWO HOUR RATED LOCK SET / IROMONGEREYTO ARCH'S APP
1150 X 2180mm FIRE STAIRCASE 1FIRE STAIRCASE 2
11
2 SETS01FRD
02FRD
09D
121.76m2
120.07m2352.62m2
73.67m2
CAFE09D
10D ALUMINIUM BI-FOLD PATIO DOOR WITH 5 SERIES OF HINGED
DOORS
ALUMINIUM BI-FOLD PATIO DOOR WITH 7 SERIES OF HINGEDDOORS
CAFE
1 1 SET
1 1 SET
7460 X 3700mm
5920 X 3700mm
10D
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
1000 X 2200mm REFUSE CHAMBER07D 1 1 SET
FIRE STAIRCASE 1FIRE STAIRCASE 2MALE TOILETFEMALE TOILETDISABLED TOILET
15.85m2
15.20m2
8.10m2
12.80m2
3.50m2
1.59m2
1.52m2
0.81m2
1.28m2
0.35m2
0.80m2
0.76m2
0.40m2
0.64m2
0.18m2
REFUSE CHAMBER 6.70m2 0.67m2 0.34m2
01FRD
01FRD
04D
01W
04D
01W
05D
01W
07D
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
FIRE FIGHTING LEGENDALARM BELL
DRY POWDER EXTINGUISER( WEIGHT =9KG)
BREAK GLASSSMOKE DETECTOR
FIRE HYDRANT
"KELUAR" SIGNEMERGENCY LIGHTHOSE REEL & WET RISER
CO2 CYLINDER (45.5 KG EACH)
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
LIEW HUI ENDOORS & WINDOWS ANNOTATIONTAN HENG YEESPECIFICATIONSLIEW HUI ENFINISHES BOXLIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS SCHEDULES &CALCULATION TABLELEONG CARMENBOMBA ANNOTATIONLEONG CARMEN & TAN HENG YEE
DOWN
DOWN
DOWN
A
P1-8
CB
P1-9-1 P1-9-2
VOID
F AE BC
2
6
7
3
5
8
4
D
1
G
38
54
56
45 46 47 48 49 50 51 52 53 55
573943 40414244
DRELE CW TEL
MALE TOILET
FEMALE TOILET
DISABLEDTOILET
REFUSE CHAMBER
3637
33323130292827 34
38394041424344
2526272829303132
2324
333637383940414243
3435
44
32130
4250
2390 6400
3950
121404750
12140 100707150
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
4A
5A
C2C1
47.9m2
-
UF
EA
NV
-
-
51m2
4000mm
GR
ASUF
GR
AC
115.42m2
5600mm
HW
UFUF
TP
MVVOID
VOID
VOID
35FIRESTAIRCASE 1
FIRESTAIRCASE 2
15.85m2
mm
-
UFUF
CR
MV
15.2m2
-
UF
CR
MV
-UF
6.7m2
-
UF
CR
MV
-UF
FFL = +7.800
FFL = +7.800
FFL = +7.800
FFL = +7.800
FFL = +7.620
FFL = +7.800
SKYLIGHT ROOF
PUBLISHING OFFICE
MEETING AREA
COURTYARD
51m2
4000mm
GR
ASUF
GR
AC
FFL = +7.800
04D
04D
04D
05D
08D
11D
01FRD
01FRD
02W
01W
01W
01W
03D
06D
900MM (W) X 3100MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
RC STAIRCASE TO ENGR'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
115MM THICK FAIR FACED BRICKWALL
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
SKYLIGHT ROOF
2770
02FRD
02FRD
02FRD
02FRD
1:100
5A
SECOND FLOOR PLAN
2015/ARC3524/BT2/P1/5A
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACESSECONDFLOOR
PUBLISHING OFFICEMEETING AREA
FIRE STAIRCASE 1FIRE STAIRCASE 2MALE TOILETFEMALE TOILETDISABLED TOILET
AREA
51.00m2
51.00m2
15.85m2
15.20m2
8.10m2
12.80m2
3.50m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
5.10m2
5.10m2
1.59m2
1.52m2
0.81m2
1.28m2
0.35m2
2.55m²
0.80m2
0.76m2
0.40m2
0.64m2
0.18m2
DOOR LEGEND DOOR SIZE LOCATION NO. TOTAL
PLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATION
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
850 X 2180mm
2300 X 3500mm
850 X 2180mm
MALE TOILET
DISABLED TOILET
BOMBA TELEPHONECOLD WATER
DRY RISER
1
1
3 SETS111
FEMALE TOILET 23 SETS
1 SET130MM THK ALUMINIUM LOUVERS WITH 45° HORIZONTALBLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL
111
3 SETS840 X 650mm MALE TOILETFEMALE TOILET
DISABLED TOILET
CALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION
DOOR SCHEDULE
WINDOW SCHEDULE
REFUSE CHAMBER 6.70m2 0.67m2 0.34m2
01W
04D
05D
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWOHOUR FIRE RATED SOLID TIMBER DOOR & 10 nos. S.SHINGES & TWO HOUR RATED LOCK SET / IROMONGEREYTO ARCH'S APP
1150 X 2180mm FIRE STAIRCASE 1FIRE STAIRCASE 2
11
2 SETS
SOLID SINGLE LEAF TIMBER DOOR WITH 4 nos. S.SHINGES & LOCK SET / IROMONGEREY C/WWATERPROOFED EPOXY PAINT
1020 X 2480mm PUBLISHING OFFICE 1 1 SET06D
01FRD
02FRD
01FRD
01FRD
04D
01W
04D
01W
05D
01W
07D
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
55.38m2
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
113.40m2106.38m2
62.40m2
COURTYARD 47.90m2 4.79m2 79.1m2 31.20m2
03D
06D
11D
2.40m²
2.55m²
ANODIZED ALUMINIUM FRAME WITH 8MM THK CLEAR GLASS02W 800 x 3500mm PUBLISHING OFFICE 1 1 SET
6460 X 2540mm 1 1 SET11D
03D
ALUMINIUM BI-FOLD PATIO DOOR WITH 5 SERIES OFHINGED DOORS AND A SWING DOOR
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
1350 X 2180mm CORRIDOR 1 1 SET
PUBLISHING OFFICE
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
1000 X 2200mm REFUSE CHAMBER07D 1 1 SET
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
TAN HENG YEEDOORS & WINDOWS ANNOTATIONTAN HENG YEESPECIFICATIONSLIEW HUI ENFINISHES BOXLIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS SCHEDULES &CALCULATION TABLELEONG CARMEN
DOWN
DOWN
DOWN
A
P1-8
CB
P1-9-1 P1-9-2
VOID
F AE BC
2
6
7
3
5
8
4
D
1
G
383943 40414244
DRELE CW TEL
MALE TOILET
FEMALE TOILET
DISABLEDTOILET
REFUSE CHAMBER
3637
33323130292827 34
38394041424344
2526272829303132
2324
333637383940414243
3435
44
29360
4250
2390 6400
3950
121404750
12140 100707150
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
4A
5A
C2C1
47.9m2
-
UF
EA
NV
-
-
51m2
4000mm
GR
ASUF
GR
AC
115.42m2
5600mm
HW
UFUF
TP
MVVOID
VOID
VOID
35
FIRESTAIRCASE 1
FIRESTAIRCASE 2
15.85m2
mm
-
UFUF
CR
MV
15.2m2
-
UF
CR
MV
-UF
6.7m2
-
UF
CR
MV
-UF
FFL = +7.800
FFL = +7.800
FFL = +7.800
FFL = +7.800
FFL = +7.620
FFL = +7.800
SKYLIGHT ROOF
PUBLISHING OFFICE
MEETING AREA
COURTYARD
51m2
4000mm
GR
ASUF
GR
AC
FFL = +7.800
04D
04D
04D
05D
08D
11D
01FRD
01FRD
02W
01W
01W
01W
03D
06D
900MM (W) X 3100MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
RC STAIRCASE TO ENGR'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
115MM THICK FAIR FACED BRICKWALL
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
SKYLIGHT ROOF
54
56
45 46 47 48 49 50 51 52 53 55
57
02FRD
02FRD
02FRD
02FRD
1:100
5B
SECOND FLOOR PLAN
2015/ARC3524/BT2/P1/5B
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACESSECONDFLOOR
PUBLISHING OFFICEMEETING AREA
FIRE STAIRCASE 1FIRE STAIRCASE 2MALE TOILETFEMALE TOILETDISABLED TOILET
AREA
51.00m2
51.00m2
15.85m2
15.20m2
8.10m2
12.80m2
3.50m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
5.10m2
5.10m2
1.59m2
1.52m2
0.81m2
1.28m2
0.35m2
2.55m²
0.80m2
0.76m2
0.40m2
0.64m2
0.18m2
DOOR LEGEND DOOR SIZE LOCATION NO. TOTAL
PLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATIONPLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATION
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
850 X 2180mm
2300 X 3500mm
850 X 2180mm
MALE TOILET
DISABLED TOILET
BOMBA TELEPHONECOLD WATER
DRY RISER
1
1
3 SETS111
FEMALE TOILET 23 SETS
1 SET130MM THK ALUMINIUM LOUVERS WITH 45° HORIZONTALBLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL
111
3 SETS840 X 650mm MALE TOILETFEMALE TOILET
DISABLED TOILET
CALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION
DOOR SCHEDULE
WINDOW SCHEDULE
REFUSE CHAMBER 6.70m2 0.67m2 0.34m2
01W
04D
05D
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWOHOUR FIRE RATED SOLID TIMBER DOOR & 10 nos. S.SHINGES & TWO HOUR RATED LOCK SET / IROMONGEREYTO ARCH'S APP
1150 X 2180mm FIRE STAIRCASE 1FIRE STAIRCASE 2
11
2 SETS
SOLID SINGLE LEAF TIMBER DOOR WITH 4 nos. S.SHINGES & LOCK SET / IROMONGEREY C/WWATERPROOFED EPOXY PAINT
1020 X 2480mm PUBLISHING OFFICE 1 1 SET06D
01FRD
02FRD
01FRD
01FRD
04D
01W
04D
01W
05D
01W
07D
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
55.38m2
2.51m2
2.51m2
2.40m2
2.40m2
8.60m2
2.60m2
113.40m2106.38m2
62.40m2
COURTYARD 47.90m2 4.79m2 79.1m2 31.20m2
03D
06D
11D
2.40m²
2.55m²
ANODIZED ALUMINIUM FRAME WITH 8MM THK CLEAR GLASS02W 800 x 3500mm PUBLISHING OFFICE 1 1 SET
6460 X 2540mm 1 1 SET11D
03D
ALUMINIUM BI-FOLD PATIO DOOR WITH 5 SERIES OFHINGED DOORS AND A SWING DOOR
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
1350 X 2180mm CORRIDOR 1 1 SET
PUBLISHING OFFICE
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 4.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
1000 X 2200mm REFUSE CHAMBER07D 1 1 SET
FIRE FIGHTING LEGENDALARM BELL
DRY POWDER EXTINGUISER( WEIGHT =9KG)
BREAK GLASSSMOKE DETECTOR
FIRE HYDRANT
"KELUAR" SIGNEMERGENCY LIGHTHOSE REEL & WET RISER
CO2 CYLINDER (45.5 KG EACH)
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
TAN HENG YEEDOORS & WINDOWS ANNOTATIONTAN HENG YEESPECIFICATIONSLIEW HUI ENFINISHES BOXLIEW HUI EN & KIAN SOON JEANDOORS & WINDOWS SCHEDULES &CALCULATION TABLELEONG CARMEN
BOMBA ANNOTATIONLEONG CARMEN & TAN HENG YEE
DOWN
F AE BC
2
6
7
3
5
8
4
D
1
G
56
5448 49 50 51 52 53 55
59 5758
32130
4250
2390 6400
3950
121404750
12140 100707150
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
4A
5A
C2C1
VOID
VOID
FIRESTAIRCASE 2
SKYLIGHT ROOF
SKYLIGHT ROOF
A
P1-8
CB
P1-9-1 P1-9-2
VOID
VOID
VOID
VOID
2770
SKYLIGHT ROOF
WATER TANK ROOM
36m2
-
UF
CR
NV
-UF
FFL = +10.500
15.2m2
-
UF
CR
MV
-UF
FFL = +10.500
100MM THICK FAIR FACED BRICKWALL
ALUMINIUM LOUVRES
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
WATER TANK TO MANUF'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
100MM Ø RWDP TO MANUF'S DETAIL
150MM WIDTH SCUPPER DRAIN TOENGR'S DETAIL
RC STAIRCASE TO ENGR'S DETAIL
01FRD
01W
01W
01W
01W
01W
1:100
6A
MEZZANINE FLOOR PLAN
2015/ARC3524/BT2/P1/6A
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACES
MEZZANINEFLOOR FIRE STAIRCASE 1
WATER TANK ROOM
AREA
15.85m236.0m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
1.59m23.60m2
0.80m21.80m2
DOOR LEGEND DOOR SIZE LOCATION NO. TOTALCALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION DOOR SCHEDULE
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWOHOUR FIRE RATED SOLID TIMBER DOOR & 10 nos. S.SHINGES & TWO HOUR RATED LOCK SET / IROMONGEREYTO ARCH'S APP
1150 X 2180mm FIRE STAIRCASE 1 1 1SETS01FRD
01FRD
01W
2.51m238.73m2
2.51m22.73m2
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
130MM THK ALUMINIUM LOUVERS WITH 45°HORIZONTAL BLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL
5 5 SETS840 X 650mm WATER TANK ROOM
WINDOW SCHEDULE
01W
LEONG CARMEN
DOWN
F AE BC
2
6
7
3
5
8
4
D
1
G
56
5448 49 50 51 52 53 55
59 5758
32130
4250
2390 6400
3950
121404750
12140 100707150
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
4A
5A
C2C1
VOID
VOID
FIRESTAIRCASE 2
SKYLIGHT ROOF
SKYLIGHT ROOF
A
P1-8
CB
P1-9-1 P1-9-2
VOID
VOID
VOID
VOID
2770
SKYLIGHT ROOF
WATER TANK ROOM
36m2
-
UF
CR
NV
-UF
FFL = +10.500
15.2m2
-
UF
CR
MV
-UF
FFL = +10.500
100MM THICK FAIR FACED BRICKWALL
ALUMINIUM LOUVRES
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
WATER TANK TO MANUF'S DETAIL
1000mm HIGH WROUGHT IRON FIRESTAIRCASE HANDRAIL
100MM Ø RWDP TO MANUF'S DETAIL
150MM WIDTH SCUPPER DRAIN TOENGR'S DETAIL
RC STAIRCASE TO ENGR'S DETAIL
01FRD
01W
01W
01W
01W
01W
1:100
6B
MEZZANINE FLOOR PLAN
2015/ARC3524/BT2/P1/6B
LEGENDFINISHING LAYER, FLOOR AREA ANDFINISH FLOOR LEVEL
WALL FIN. CODE CEILING FIN. CODEFLOOR FIN. CODE SKIRTING FIN. CODE
VENTILATION CEILING HT. (MM)SPACE AREA (SQM)
FFL
WALL FINISHESAPCTGRUF
ACOUSTIC PANELCERAMIC TILEGRANITEUNFINISHED
CEILING FINISHESASUF
ALUMINIUM STRIP PANELUNFINISHED
CEILING FINISHESCRCT
CEMENT RENDERCERAMIC TILE
FINISHING CODES
GRVTTPEA
GRANITEVINYL TILETIMBER PANELEARTH
SKIRTING FINISHESCT CERAMIC TILEGRHWVSUF
GRANITEHARDWOODVINYL SHEETUNFINISHED
VENTILATIONNVMV
NATURAL VENTILATIONMECHANICAL VENTILATION
AC AIR-CONDITIONED
SPACES
MEZZANINEFLOOR FIRE STAIRCASE 1
WATER TANK ROOM
AREA
15.85m236.0m2
TYPES OF OPENINGS LIGHTING VENTILATION10% REQUIRED (sqm) PROVIDED (sqm) 5% REQUIRED (sqm) PROVIDED (sqm)
1.59m23.60m2
0.80m21.80m2
DOOR LEGEND DOOR SIZE LOCATION NO. TOTALCALCULATION TABLE FOR NATURAL LIGHTING AND VENTILATION DOOR SCHEDULE
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWOHOUR FIRE RATED SOLID TIMBER DOOR & 10 nos. S.SHINGES & TWO HOUR RATED LOCK SET / IROMONGEREYTO ARCH'S APP
1150 X 2180mm FIRE STAIRCASE 1 1 1SETS01FRD
01FRD
01W
2.51m238.73m2
2.51m22.73m2
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12130MM THK ALUMINIUM LOUVERS WITH 45°HORIZONTAL BLADES
WINDOW LEGEND WINDOW SIZE LOCATION NO. TOTAL
5 5 SETS840 X 650mm WATER TANK ROOM
WINDOW SCHEDULE
01W
LEONG CARMEN
FIRE FIGHTING LEGENDALARM BELL
DRY POWDER EXTINGUISER( WEIGHT =9KG)
BREAK GLASSSMOKE DETECTOR
FIRE HYDRANT
"KELUAR" SIGNEMERGENCY LIGHTHOSE REEL & WET RISER
CO2 CYLINDER (45.5 KG EACH)
F AE BC
2
6
7
3
5
8
4
D
1
G
A
P1-8
CB
P1-9-1 P1-9-2
32130
4250
2390 6400
3950
121404750
12140 100707150
3670
1370
2524
0
8050
6440
2860
2550
2550
6680
3580
8200
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
CUSTOM PROFILE STEEL GUTTER
2770
ALUMINIUM LOUVRES
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
1:100
07
ROOF PLAN
2015/ARC3524/BT2/P1/7
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
LEONG CARMEN & KIAN SOON JEANSPECIFICATIONSLIEW HUI EN
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
STEEL RAILING
10MM THK STEEL ROOF FASCIA
115MM THICK FAIR FACED BRICKWALL
400MM X 400MM HOLLOW SECTIONSTEEL COLUMNCOATED WITH FIRE RETARDANTPAINT
ALUMINIUM LOUVRES
2 6 73 5 841
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
STEEL STAIRCASE TO ENGR'SDETAIL,STEEL RAILING WELDEDONTO CAST-IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISH R= +/- 177MM T=+/-255MM
1500MM X 1000MM ALUMINIUMLOUVRES
200MM X 250MM STEEL L-BEAMCOATED WITH FIRE RETARDANTPAINT
10MM THK STEEL ROOF FASCIA
115MM THICK FAIR FACED BRICKWALL
200MM X 200MM HOLLOW SECTIONSTEEL COLUMN COATED WITH FIRERETARDANT PAINT
500MM X 600MM REINFORCEDCONCRETE COLUMN
ALUMINIUM LOUVRES
267 358 4 1
1:100
08
FRONT ELEVATION
2015/ARC3524/BT2/P1/8
KIAN SOON JEAN & LEONG CARMEN
BACK ELEVATION
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
8
MALE TOILET 1 CAFEKITCHENFEMALE TOILET 1
MALE TOILET 2 FEMALE TOILET 2
MALE TOILET 3 FEMALE TOILET 3
CW
CW
CWFIRE STAIRCASE1
FIXED GLASS PANEL
WOODEN BOOK RACK
FIBERGLASSREINFORCE CEILINGPANELS
COURTYARD
200MM THK RC SLAB TO ENGR'SDETAIL
FIRE STAIRCASE1
FIRE STAIRCASE1
RC STAIRCASE TO ENGR'SDETAIL
LIFT
VOID
300MM X 450MM STEEL I-BEAM
FF 4400mm
GF 0mm
500MM X 500MM REINFORCEDCONCRETE GROUND COLUMN
RF 14000mm
RF 12800mm
SF 7800mm
FF 3900mm
REINFORCED CONCRETE PILECAP TO ENGR'S DETAIL
1000MM HIGH WROUGHTIRON FIRE STAIRCASEHANDRAIL
230MM THICK CLAYBRICKSPARTI WALL
900MM (W) X 4050MM (L) X 12mmSTEEL FRAME WITH THICKTOUGHENED GLASS PANEL
200MMX600MM RC BEAM TOENGR'S DETAIL
267 35 4 1
BO
UN
DA
RY
LIN
E
BO
UN
DA
RY
LIN
E
VOID
VOID
115MM THICK FAIR FACEDBRICK WALL
900MM (W) X 4050MM (L) X 12mmTHICK TOUGHENED GLASS PANEL
200MM X 200MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
STEEL STAIRCASE TO ENGR'SDETAIL, STEEL RAILING WELDEDONTO CAST IN-SITU 400MM X 6MMTHICK PLATE BUSTER TO BE PAINTFINISHR= +/- 177MM T=+/-255MM
230MM THICK CLAYBRICKS PARTIWALL
2 6 73 5 841
RF 14000mm
RF 12800mm
SF 7800mm
FF 4400mm
FF 3900mm
GF 0mm
RF 11700mm
RF 10800mm
300MM X 450MM STEEL I-BEAM,COATED WITH FIRE RETARDANTPAINT
REINFORCED CONCRETE GROUNDCOLUMN AND CONCRETE PILE CAPTO ENGR'S DETAIL
BO
UN
DA
RY
LIN
E
BO
UN
DA
RY
LIN
E
1000MM HIGH WROUGHT IRONFIRE STAIRCASE HANDRAIL
CAFE LIBRARY MARKET PLACE
CAFE
FIRE STAIRCASE 2
FIRE STAIRCASE 2
FIRE STAIRCASE 2
1:100
09
SECTION B-B
2015/ARC3524/BT2/P1/9
SECTION C-C
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
CH'NG XING YUE & TAN HENG YEE
REFUSE CHAMBER
REFUSE CHAMBER
01
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH 3.nos.S.S. HINGES & LOCKSET / IRONMONGERY C/W WATERPROOFEDEPOXY PAINT
STEEL FRAME DOUBLE PANELS ,PLYWOOD PIVOT DOOR & 2nos. CENTER HUNGS DOORSETS
1
LIBRARY LIBRARY CORRIDOR
STEEL FRAME DOUBLE PANELS ,PLYWOOD PIVOT DOOR & 1 nos.CENTER HUNGS DOORSETS
1
TOILETS
KITCHEN
3
9
PLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH3.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED LAMINATION
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOOR WITH3.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
METAL ROLLER SHUTTER
7460 X 3700mm
ALUMINIUM BI-FOLD PATIO DOOR WITH 7 SERIES OF HINGED DOORSSOLID SINGLE LEAF TIMBER DOOR WITH 3 nos. S.S HINGES &LOCK SET / IROMONGEREY C/W WATERPROOFED EPOXY PAINT
PUBLISHING OFFICE
1
1
CAFE
1000 X 2600mm1020 X 2480mm
850 X 2180mm
1015 X 2200mm
1350 X 2180mm2000 x 3500mm2300 X 3500mm
-
-
-
-
-
-
-
-
-
-
- TOILETS
TOILETS
1
1
-
-
1
2
- 3
3
1
DISABLED TOILET
3
REFUSE CHAMBER
1
1
2300 X 3500mm
-
-
2
4
-
-
1
1
PLYWOOD FRAME SINGLE LEAF ,PLYWOOD FLUSHDOOR WITH 3.nos. S.S. HINGES & LOCKSET /IRONMONGERY C/W WATERPROOFED LAMINATION
TYPE
ELEVATION
PLAN
SIZE
DESCRIPTION
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
FLOOR FINISH LEVEL
TOTAL
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
LOC
ATI
ON
QU
AN
TITY
TYPE
ELEVATION
PLAN
SIZE
DESCRIPTION
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
FLOOR FINISH LEVEL
TOTAL
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
LOC
ATI
ON
QU
AN
TITY
-
-
-
-
-
1
1
DISABLED TOILET
DISABLED TOILET
1
1
D02D
03D
04D
05D
06D
07D
08D
09D
-
-
CORRIDOR
1
20001350
475 875
11502300
1150
8506901230
7460
195 1951000 1000 1000 1000 1000 1000 1000
1020 74601000880
1000
1015905 7000900
- -- -
- - - --
MEZZANINE FLR. - - - - -
MEZZANINE FLR.
MEZZANINE FLR.
MEZZANINE FLR.
- - - -
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
1:50
11
DOOR AND WINDOW
2015/ARC3524/BT2/P1/11
CH'NG XING YUE & TAN HENG YEE
SCHEDULE
FIVE FOOT WALKWAYTOILETS, DISABLED TOILETS
2
2
2
7
1.2MM THICK ZINCALUME FRAME SINGLE LEAF TWO HOUR FIRERATED SOLID TIMBER DOOR & 10 nos. S.S HINGES & TWO HOURRATED LOCK SET / IROMONGEREY TO ARCH'S APP
BOMBA TELEFONCOLD WATER
DRY RISER
3
4
4
11
MECHANICAL & ELECTRICAL ROOM
METAL FRAME SINGLE LEAF ,TWO HOUR FIRE RATED SOLIDTIMBER DOOR WITH 3.nos. S.S. HINGES & LOCKSET /IRONMONGERY C/W WATERPROOFED EPOXY PAINT
METAL FRAME SINGLE LEAF ,PLYWOOD FLUSH DOORWITH 3.nos. S.S. HINGES & LOCKSET / IRONMONGERY C/WWATERPROOFED EPOXY PAINT
6460 X 2540mm
ALUMINIUM BI-FOLD PATIO DOOR WITH 5 SERIES OF HINGED DOORS AND A SWING DOOR
1
PUBLISHING OFFICE
750 X 2110mm
850 X 2180mm1150 X 2180mm
FIRE STAIRCASE 1 & 2
FIRE STAIRCASE 1 & 2
FIRE STAIRCASE 1 & 2
-
-
1
1
-
-
TYPE
ELEVATION
PLAN
SIZE
DESCRIPTION
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
FLOOR FINISH LEVEL
TOTAL
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
LOC
ATI
ON
QU
AN
TITY
TYPE
ELEVATION
PLAN
SIZE
DESCRIPTION
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
FLOOR FINISH LEVEL
TOTAL
GROUND FLOOR
FIRST FLOOR
SECOND FLOOR
LOC
ATI
ON
QU
AN
TITY
5920 X 3700mm
1
-
CAFE
ALUMINIUM BI-FOLD PATIO DOOR WITH 5 SERIES OF HINGED DOORS
-
-
-
1 1
-
-
-
-
130MM THK ALUMINIUM LOUVERS WITH 45O HORIZONTALBLADES
840 X 650mm
3
30
19
3
TOILETS
PUBLISHING OFFICE KITCHEN
ANODIZED ALUMINIUM SLIDING WINDOW WITH 8MM THK CLEARGLASS
ANODIZED ALUMINIUM FRAME WITH 8MM THK CLEAR GLASS
1660 X 1290mm800 x 3500mm
-
1
-
1
-
-
-
1
-
1
-
-
10D
11D
01FRD
02FRD
03FRD
01W
02W
03W
DISABLED TOILETSTOILETS
DISABLED TOILETS
840830 830
1660800
6460
1070 1070 1070 1070 1070 1070
11505920
5920
495 985 985 988 985 995 495
6460 8507004928 970
- 5 - -
1 ---
MEZZANINE FLR.
MEZZANINE FLR.
MEZZANINE FLR.
MEZZANINE FLR.
- - FIRE STAIRCASE 1
- WATER TANK ROOM - -
-
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIPNo. 1 Jalan Taylor's,47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,47500 Subang Jaya, Selangor Darul Ehsan, Malaysia.
GENERAL NOTES1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLYFIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TOTHE ARCHITECT BEFORE PROCEEDING.
Ar. KIAN SOON JEAN
Professional ArchitectB.Sc. (HONOURS) (ARCHITECTURE)PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terimaterima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
7th OCT 2015
12
1:50
12
DOOR AND WINDOW
2015/ARC3524/BT2/P1/12
CH'NG XING YUE & TAN HENG YEE
SCHEDULE