8/2/2019 Building DATA
1/23
Sl. No. Description Unit Quantity Rate Rs.
RBR-FNDN1
b
1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto a lead of 50 m,
Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 240 cum
a)Labour
Mate da -
Mazdoor Unskilled da 8.32 258.00
b) Machinery
H draulic Excavator 1 cum bucket ca acit hour 6.00 2009.50
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
BLD-CSTN-
2-5
2 Plain Cement concrete (1:4:8) using 40 mm metal with
concrete mixture. All work upto plinth level.Unit = 1cum
A. MATERIALS:
Cement k 162.00 5300.00
Coarse a re ate 40 mm cum 0.90 1094.70
Fine a re ate Sand cum 0.45 630.62
Seigniorage charges for C.A cum 0.90 0.00
Seigniorage charges for F.A cum 0.45 0.00
Water (including for curing) kl 1.20 77.00
B. MACHINERY
Concrete Mixer 10 / 7 cft 0.2 / 0.8 cum ca acit hour 1.00 248.40
C. LABOUR:
Mason 1st class day 0.10 342.00
Mazdoor (unskilled) day 1.39 258.00
Overheads & Contractors Profit @ 14%
Grand Total
3 RCC M- 20 nominal mix (Cement:fine aggregate: coarse aggregate)
corresponding to Table 9 of IS 456 using 20mm size graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as mixing, laying
concrete, curing, centering, shuttering etc.,complete but excludingA FOOTINGS UNIT 1.00
A. MATERIALS:
Cement for mix kg 400.00 5300.00
Coarse aggregate 20mm cum 0.90 1273.70
Fine aggregate cum 0.45 630.62
Water including kl 1.20 77.00
Add Seignorage charges on CA @
Water including
Total
B. MACHINERY
COMPOUND WALL DATA
SATTENAPALLE MUNICIPALITY
DATA 2011-2012
Note: 1. Cost of dewatering upto 5% ofa+b may be added, where required, upto 10 per cent of labo
Assessment for dewatering shall be made as per site conditions.
(included in material rate)
(included in material rate)
8/2/2019 Building DATA
2/23
Sl. No. Description Unit Quantity Rate Rs.
Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80
Fuel/Energy charges Hour 0.133 61.90
Needle Vibrator 60mm dia (petrol) Hour 1.00 6.20
Fuel/Energy charges Hour 0.667 18.60
Centering charges cum 1.00 59.00
Total
C. LABOUR
Labour charges for centering cum 1.00 330.00Crew for concrete mixer Hour 1.00 141.70
Crew for needle vibrator Hour 1.00 102.00
Mason Class-1 Day 0.133 285.00
Mason Class-2 Day 0.267 260.00
Mazdoor (unskilled) Day 3.60 215.00
Total
Add 20% over basic rate on labour component for Municipal area
ABSTRACT
A. Cost of Material including seigniorage charges
B. Hire charges for Machinery
C. Cost of Labour
D. Contractors Profit &over heads on (A+B+C)
Total cost for 1.00 cum
COLUMNS UNIT 1.00
A. MATERIALS:
Cement for mix kg 400.00 5300.00
Coarse aggregate 20mm cum 0.90 1273.70
Fine aggregate cum 0.45 630.62
Water including kl 1.20 77.00
Add Seignorage charges on CA @
Water including
Total
B. MACHINERY
Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80
Fuel/Energy charges Hour 0.133 61.90
Needle Vibrator 60mm dia (petrol) Hour 1.00 6.20
Fuel/Energy charges Hour 0.667 18.60
Centering charges cum 1.00 89.00
Total
C. LABOUR
Labour charges for centering cum 1.00 747.00
Crew for concrete mixer Hour 1.00 141.70
Crew for needle vibrator Hour 1.00 102.00
Mason Class-1 Day 0.133 285.00
Mason Class-2 Day 0.267 260.00
Mazdoor (unskilled) Day 3.60 215.00
Total
Add 20% over basic rate on labour component for Municipal area
ABSTRACT
A. Cost of Material including seigniorage charges
B. Hire charges for Machinery
C. Cost of Labour
D. Contractors Profit &over heads on (A+B+C)
(included in material rate)
B
(included in material rate)
8/2/2019 Building DATA
3/23
Sl. No. Description Unit Quantity Rate Rs.
Total cost for 1.00 cum
C PLINTH BEAM UNIT 1.00
A. MATERIALS:
Cement for mix kg 400.00 5300.00
Coarse aggregate 20mm cum 0.90 1273.70
Fine aggregate cum 0.45 630.62
Water including kl 1.20 77.00
Add Seignorage charges on CA @
Water including
Total
B. MACHINERY
Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80
Fuel/Energy charges Hour 0.133 61.90
Needle Vibrator 60mm dia (petrol) Hour 1.00 6.20
Fuel/Energy charges Hour 0.667 18.60
Centering charges cum 1.00 993.00
Total
C. LABOUR
Labour charges for centering cum 1.00 795.00
Crew for concrete mixer Hour 1.00 141.70
Crew for needle vibrator Hour 1.00 102.00
Mason Class-1 Day 0.133 285.00
Mason Class-2 Day 0.267 260.00
Mazdoor (unskilled) Day 3.60 215.00
Total
Add 20% over basic rate on labour component for Municipal area
ABSTRACT
A. Cost of Material including seigniorage charges
B. Hire charges for Machinery
C. Cost of Labour
D. Contractors Profit &over heads on (A+B+C)
Total cost for 1.00 cum
D BEAMS UNIT 1.00
A. MATERIALS:
Cement for mix kg 400.00 5300.00
Coarse aggregate 20mm cum 0.90 1273.70
Fine aggregate cum 0.45 630.62
Water including kl 1.20 77.00
Add Seignorage charges on CA @
Water including
Total
B. MACHINERY
Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80
Fuel/Energy charges Hour 0.133 61.90
Needle Vibrator 60mm dia (petrol) Hour 1.00 44.80
Fuel/Energy charges Hour 0.667 18.60
Centering charges cum 1.00 1276.00
Total
C. LABOUR
Labour charges for centering cum 1.00 795.00
Crew for concrete mixer Hour 1.00 141.70
Crew for needle vibrator Hour 1.00 102.00
(included in material rate)
(included in material rate)
(included in material rate)
(included in material rate)
8/2/2019 Building DATA
4/23
Sl. No. Description Unit Quantity Rate Rs.
Mason Class-1 Day 0.133 285.00
Mason Class-2 Day 0.267 260.00
Mazdoor (unskilled) Day 3.60 215.00
Total
Add 20% over basic rate on labour component for Municipal area
ABSTRACT
A. Cost of Material including seigniorage chargesB. Hire charges for Machinery
C. Cost of Labour
D. Contractors Profit &over heads on (A+B+C)
Total cost for 1.00 cum
E ROOF SLAB UNIT 1.00
A. MATERIALS:
Cement for mix kg 400.00 5300.00
Coarse aggregate 20mm cum 0.90 1273.70
Fine aggregate cum 0.45 630.62
Water including kl 1.20 1273.70
Add Seignorage charges on CA @
Water including
Total
B. MACHINERY
Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80
Fuel/Energy charges Hour 0.133 61.90
Needle Vibrator 60mm dia (petrol) Hour 1.00 44.80
Fuel/Energy charges Hour 0.667 18.60
Centering charges cum 1.00 143.00
Total
C. LABOUR
Labour charges for centering cum 1.00 89.00
Crew for concrete mixer Hour 1.00 141.70
Crew for needle vibrator Hour 1.00 102.00
Mason Class-1 Day 0.133 285.00
Mason Class-2 Day 0.267 260.00
Mazdoor (unskilled) Day 3.60 215.00
Total
Add 20% over basic rate on labour component for Municipal area
ABSTRACT
A. Cost of Material including seigniorage charges
B. Hire charges for Machinery
C. Cost of Labour
D. Contractors Profit &over heads on (A+B+C)
Total cost for 1.00 cum
BLD-CSTN
2-18
4 Supplying, fitting and placing HYSD bar reinforcement in
foundation complete as per drawings and technical
specifications for Bars below 36 mm dia including over laps
and wasta e where the are not weldedUnit = t
(a) Material
HYSD bars including 5 per cent for overlaps and wastage t 1.05 44000.00
Bindin wire k 6.00 55.00
1000 &
1200
(included in material rate)
(included in material rate)
8/2/2019 Building DATA
5/23
Sl. No. Description Unit Quantity Rate Rs.
(b) Labour for cutting, bending, shifting to site, tying and
placing in positionBlacksmith / Bar bender day 2.00 360.00
Mazdoor (Unskilled) day 6.40 258.00
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)Rate per t = a+b+c+d
Rate per kg = a+b+c+d /1000
Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement k . 480.00 5300.00
Sand includin 5% wasta e cum 1.05 630.62
Sei niora e char es for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixin mortar da 0.20 258.00
Grand Total
BLD-CSTN PLASTERING
BLD-CSTN6-1
5 Plastering with CM (1:3), 12 mm thick to ceiling includingcost & conveyance of all materials and labour charges curing
etc., complete
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 3257.75
Sei niora e char es for F.A cum 0.15 0.00
B. LABOUR:
Mason 1st class day 0.60 342.00
Mazdoor (unskilled) day 0.96 258.00
Overheads & Contractors Profit @ 14%
Grand Total
BLD-CSTN6-1
6 Plastering with CM (1:3), 20 mm thick to ceiling includingcost & conveyance of all materials and labour charges curing
etc., completeUnit = 10 sqm
A. MATERIALS:
Cement Mortar 1:3 cum 0.21 3257.75
Sei niora e char es for F.A cum 0.21
B. LABOUR:
Mason 1st
class day 0.91 342.00
Mazdoor unskilled da 1.60 258.00
Overheads & Contractors Profit @ 14%
Grand Total
7 Refilling the foundation with excavated soils other than sand
complying with standard specification for finished item of
work - 1cuma)Labour
Mazdoor Unskilled da 0.31 258.00
c&d) Overheads & Contractors Profit
Rate per cum
8 Brick Masonry in CM (1:6) with 2nd class Bricks traditional
size 23 x 11 x 7 cms including cost of all materials and labour
Note: When Motor mix is changed proportionate quantity of cement has to be submitted
8/2/2019 Building DATA
6/23
Sl. No. Description Unit Quantity Rate Rs.
Unit = 1 cum
A. MATERIALS:
Cement kg 48.00 5300.00
Bricks traditional size 23x11x7 cms 2nd class nos 512.00 3100.00
Fine a re ate Sand cum 0.20 630.62
Sei niora e char es for sand cum 0.20
B. LABOUR:
Mason 1st class day 0.24 342.00
Mason 2nd class day 0.56 312.00Mazdoor unskilled da 1.89 258.00
c) Overheads & Contractors Profit @ 14%
Rate per cum (a+b+c)
9 White washing two coats with whiting of approved quality to
give an even shade after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials
including cost of all materials, labour charges and incidental
such as scaffolding, lift charges etc., complete for finished
item of work, but excluding conveyance charges of materials
A. MATERIAL
Whiting/White Cement kg 2.00 25.00
Gum, conjee water, or prickly pear juice including necessary fire wood LsB. LABOUR
Painter 1st class day 0.21 360.00
Mazdoor (unskilled) day 0.32 258.00
Sundries includin brushes ladders etc. 1% 158.16
c) Overheads & Contractors Profit @ 14%
Rate per 10 sqm
Rate per 1 sqm
10 Colour washing two coats over plastered wall surface as per
Standard specification. - 10 sqmA. MATERIAL
Rate for "White Washin " two coats s m 10.00 24.30
Add: For Colours, etc., (50 % of above rate)
c) Overheads & Contractors Profit @ 14%
Rate per 10 sqm
Rate per 1 sqm
11 Flooring with 15 mm thick Polished black Kadapa slabs
(0.457x0.457M) , set over base coat of C.M (1:8) 12 mm thick
over CC bed already laid or RCC roof slab, including pointing
with cement mortar 1:3 duly filling joints nearly, including
cost of all materials like flooring stone, cement, sand, and
water etc., complete, including seigniorage charges, labour
charges for dressing of flooring stones etc., complete for
finished item of work, but excluding the cost of conveyance of
A. MATERIALS:
Polished black Kadapa slabs minimum of 15 mm thick
0.457x0.457M BMT-B.06 sqm 10.50 107.60
Cement for CM (1:8) proportion for base coat kg. 21.60 5300.00
Cement for CM 1:3 proportion for pointing kg. 9.60 5300.00
Sand for CM (1:8) proportion cum 0.12 630.62
Sand for CM (1:3) proportion cum 0.02 630.62
B. LABOUR
Mason Class-1 Day 0.96 285.00
Mason Class-2 Day 2.24 260.00
Mazdoor (unskilled) Day 3.30 215.00
8/2/2019 Building DATA
7/23
Sl. No. Description Unit Quantity Rate Rs.
Add Water Charges @ 1% 1565.50
Add 20% on Labour 1565.50
Total (a+b)
c) Overheads & Contractors Profit @ 14%
Cost of 10 sqm
Cost of 1 sqm
12 Flooring with Polished Bethamcherla coloured stone
minimum 25 mm thick (0.254 M x 0.254 M), set over base
coat of cement mortar (1:8) 12 mm thick over CC bed already
laid or RCC roof slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm & jointed neatly
with cement paste mixed with pigment of matching shade to
full depth, including cost of all materials like cement, sand
water and tiles etc., complete, including seigniorage charges,
etc., complete for finished item of work, but excluding the
cost of conveyance of all materials - 10 Sq.M
A. MATERIALS:Polished Bethamcherla coloured stone minimum 25 mm thick (0.254M
x0.254M sqm 10.10 215.20
Cement for CM (1:8) proportion for base coat kg. 21.60 5300.00
Cement for jointing & pointing kg. 6.00 25.00Pointing with CM (1:3) cum 1.00 3257.75
Deduct CM 1:3 cum 0.04 3257.75
Sand for CM (1:8) proportion cum 0.12 630.62
Seigniorage charges of sand cum 0.02
B. LABOUR
Mason Class-1 Day 0.96 285.00
Mason Class-2 Day 2.24 260.00
Mazdoor (unskilled) Day 3.30 215.00
Add Water Charges @ 1% 1565.50
Add 20% on Labour 1565.50
Total (a+b)
c) Overheads & Contractors Profit @ 14%
Cost of 10 sqm
Cost of 1 sqm
13 Skirting to internal walls with 25mm thick polished
Bethamcherla colored stone of first quality 125 mm height
with top edge flat nosed and joints corresponding to the floor
lines, set over base coat of CM (1:5) 12 mm thick with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointed with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc., complete
including seigniorage charges, etc., complete for finished
item of work, but excluding the cost of conveyance of all
A. MATERIALS:Polished Bethamcherla coloured stone minimum 25 mm thick (0.254M
x0.254M) sqm 10.10 215.20
Sand for cm 1:5 base coat cum 0.12 630.62
Cement for cm 1:5 base coat kgs 34.56 5300.00
Cement for slurr kgs 33.00 5300.00
White cement for jointing & pointing kgs 2.00 25.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Class-1 Day 0.96 285.00
Mason Class-2 Day 2.24 260.00
8/2/2019 Building DATA
8/23
Sl. No. Description Unit Quantity Rate Rs.
Mazdoor (unskilled) Day 3.30 215.00
Add Water Charges @ 1% 1565.50
Add 20% on Labour 1565.50
Total (a+b)
c) Overheads & Contractors Profit @ 14%
Cost of 10 sqm
Cost of 1 sqm
BLD-CSTN
6-10
14 Plastering with CM 2 coats, 12 mm thick, base coat in CM
(1:5), 8mm thick and top coat in CM (1:3), 4mm thick with
sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM 1:5 8 mm thickCement kg 31.70 5300.00
Fine aggregate (Sand) cum 0.11 630.62
Top Coat in CM(1:3), 4 mm thick
Cement k 19.20 5300.00
Fine a re ate Sand cum 0.04 630.62
Sei niora e char es for F.A cum 0.15
B. LABOUR:
Mason 1
st
classday 0.63 342.00
Mason 2nd
class day 1.47 312.00
Mazdoor unskilled da 3.90 258.00
C) Overheads & Contractors Profit @ 14%
Cost of 10 sqm
Cost of 1 sqm
15 SINTEX OR equivalent SLIDING 2 TRACK WINDOWS Supply
and fixing of two track or three track sliding window the
outer frame shall be 58 X 45mm with a wall thickness of
1.2mm 0.3mm. The sliding shutter frame is made of PVC
section 57 X 32mm with overall dimensions of 1.5mm
0.3mm provided with 5mm glazing. Roller bearings and
arrestor type handle cum lock shall be provided, complete, for
A. MATERIALS:
Basic Rate BMT-P.07 sqm 1.00 2680.00
B) Overheads & Contractors Profit @ 14%
Cost of 1 sqm
LD-CSTN-7
16 Flooring with ceramic tiles, set over base coat of cement
mortar (1:8), 12 mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement,
sand water and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of work, but
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles sqm 10.10 374.00
Cement for CM 1:8 for base coat k . 21.60 5.30
Cement for slurr k . 33.00 5.30
White cement k . 2.00 30.00
Sand for CM 1:8 cum 0.12 630.62
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason 1st
class day 0.96 342.00
Mason 2nd
class day 2.24 312.00
Mazdoor (unskiled) day 3.30 258.00
Note : When Mortar mix is changed proportionate quantity of cement has to be substituted
8/2/2019 Building DATA
9/23
Sl. No. Description Unit Quantity Rate Rs.
Add water charges 1% 1.00% 1878.60
Grand Total
C) Overheads & Contractors Profit @ 14%
Rate for 10 sqm
Rate for 1 sqm
17 Dadooing to walls with first quality glazed coloured tiles
approved colour of any size set over base coat of CM (1:3) 12
mm thick with cement slurry of honey like consistency spread
at the rate of 3.30 kgs per sqm and jointed with white cement
paste mixed with pigment of matching shade to full depth,
including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc.,
complete for finished item of work, but excluding the cost of
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick(p13-item No.38) sqm 10.00 374.00
Sand for cm 1:3 base coat cum 0.12 630.62
Cement for cm 1:3 base coat kgs 57.60 5.30
Cement for slurry kgs 33.00 5.30
White cement for ointin & ointin .no.29 i.372 k s 6.00 30.00
Sei niora e char es of sand
B. LABOUR
Mason 1st class day 0.77 342.00Mazdoor (unskiled) day 0.80 312.00
Mazdoor unskiled da 3.30 258.00
Add water charges 1% 1.00% 1364.34
Grand TotalC) Overheads & Contractors Profit @ 14%
Rate for 10 sqm
Rate for 1 sqm
18 Supplying and Fixing European Water Closet of 1st quality
conforming to IS:2556-Part-2-1973 of Hindustan / Neycer or
Parr ware make white lazed with 'S' traBasic Rate (BMW-D.14) Each 1.00 1250.00
B) Overheads & Contractors Profit @ 14%
Cost of 1 No
Assistant Engineer, Dy. Executive Engineer, Commission
Sattenapalle Municipality. Sattenapalle Municipality. Sattenapalle Muni
8/2/2019 Building DATA
10/23
Amount
2146.56
12057.00
14203.56
1988.50
16192.06
67.47
858.60
985.23
283.78
0.00
0.00
92.40
248.40
34.20
358.62
2861.23
400.57
3261.80
cum
2120.00
1146.33
283.78
92.40
0.00
0.00
3642.51
ur cost.
8/2/2019 Building DATA
11/23
Amount
44.80
8.23
6.20
12.41
59.00
130.64
330.00141.70
102.00
37.91
69.42
774.00
1455.03
291.01
1746.03
3642.51
130.64
1746.03
5519.18
772.68
6291.86
cum
2120.00
1146.33
283.78
92.40
0.00
0.00
3642.51
44.80
8.23
6.20
12.41
89.00
160.64
747.00
141.70
102.00
37.91
69.42
774.00
1872.03
374.41
2246.43
3642.51
160.64
2246.43
6049.58
846.94
8/2/2019 Building DATA
12/23
Amount
6896.52
cum
2120.00
1146.33
283.78
92.400.00
0.00
3642.51
44.80
8.23
6.20
12.41
993.00
1064.64
795.00
141.70
102.00
37.91
69.42
774.00
1920.03
384.01
2304.03
3642.51
1064.64
2304.03
7011.18
981.56
7992.74
cum
2120.00
1146.33
283.78
92.40
0.00
0.00
3642.51
44.80
8.23
44.80
12.41
1276.00
1386.24
795.00
141.70
102.00
8/2/2019 Building DATA
13/23
Amount
37.91
69.42
774.00
1920.03
384.01
2304.03
3642.511386.24
2304.03
7332.78
1026.59
8359.37
cum
2120.00
1146.33
283.78
1528.44
0.00
0.00
5078.55
44.80
8.23
44.80
12.41
143.00
253.24
89.00
141.70
102.00
37.91
69.42
774.00
1214.03
242.81
1456.83
5078.55
253.24
1456.83
6788.62
950.41
7739.02
46200.00
330.00
8/2/2019 Building DATA
14/23
Amount
720.00
1651.20
48901.20
6846.17
55747.368
55.74
2544.00
662.15
0.00
51.60
3257.75
488.66
0.00
205.20
247.68
941.54
131.82
1073.36
107.33
684.13
311.22
412.80
1408.15
197.14
1605.29
160.52
79.9811.20
91.18
8/2/2019 Building DATA
15/23
Amount
254.40
1587.20
126.12
82.08
174.72487.62
2712.14
379.70
3091.84
50.00
5.00
75.60
82.56
1.58
213.16
29.84
243.00
24.30
243.00
121.50
364.50
51.03
415.53
41.55
1129.80
114.48
50.88
75.67
12.61
1383.44
273.60
582.40
709.50
8/2/2019 Building DATA
16/23
Amount
15.66
313.10
1894.26
3277.70
458.88
3736.57
373.66
2173.52
114.48
150.00325.78
130.31
75.67
0.00
2969.76
273.60
582.40
709.50
15.66
313.10
1894.26
4864.02
680.96
5544.98
554.50
2173.52
75.67
183.17
174.90
50.00
0.00
2657.26
273.60
582.40
8/2/2019 Building DATA
17/23
Amount
709.50
15.66
313.10
1894.26
4551.52
637.21
5188.73
518.87
168.01
69.37
101.76
25.22
215.46
458.64
1006.20
2044.66
286.25
2330.92
233.09
2680.00
375.20
3055.20
3777.40
114.48
174.90
60.00
75.67
328.32
698.88
851.40
8/2/2019 Building DATA
18/23
Amount
18.79
6099.84
853.98
6953.82
695.38
3740.00
75.67
305.28
174.90
180.00
263.34249.60
851.40
13.64
5853.84819.54
6673.38
667.34
1250.00
175.00
1425.00
r,
ipality.
8/2/2019 Building DATA
19/23
Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc
e charges
deduct 14%
on
conveyance
Mpl. Area
allowancesA
1 2 3 4 5 6 7 8 91 Cost of Gravel Rajupalem 1Cum 15.00 80.00 158.50 -19.46 2
Gravel - 15 km
Upto 5 KM - 57.40
5 to 15 KM - 86.00
10x8.60
143.4
2 Sand for Mortor (including
seigniorage charges)
Amaravati1Cum 36.00 325.00 348.40 -42.78 6
Sand - 36 km
Upto 5 KM - 63.50
5 to 30 KM - 237.50
25x9.50
30 to 36 KM - 47.40
6x7.90
315.6
3 Sand for filling (including
seigniorage charges)
Amaravati1Cum 36.00 250.00 348.40 -42.78 5
4 Coarse aggregate 9.5 - 4.75mm
(including seigniorage charges)Perecherla 1Cum 23.00 520.00 234.50 -28.80 7
5 Quarry dust (Chips 2.36mm
&below)Perecherla 1Cum 23.00 255.00 234.50 -28.80 4
Metal - 23 km
Upto 5 KM - 63.50
5 to 23 KM 18x9.50 -
171.00
234.50
LEAD STATEMENT 2011-12
SATTENAPALLE MUNICIPALITY
8/2/2019 Building DATA
20/23
Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc
e charges
deduct 14%
on
conveyance
Mpl. Area
allowancesA
1 2 3 4 5 6 7 8 9
6 HBG Stone (Chips 2.36mm
&below)Perecherla 1Cum 23.00 415.00 234.5 -28.80 6
7 Aggregates of 40mm nominal size
(including seigniorage charges) Perecherla 1Cum 23.00 745.00 234.50 -28.80 9
8 Aggregates of 20mm nominal
size(including seigniorage charges) Perecherla 1Cum 23.00 1175.00 234.50 -28.80 1
9 Aggregates of 10mm nominal size
(including seigniorage charges) Perecherla 1Cum 23.00 820.00 234.50 -28.80 1
10 Aggregates of 6mm nominal size
(including seigniorage charges) Perecherla 1Cum 23.00 655.00 234.50 -28.80 8
11 Aggregates of 12.5mm nominal
size(including seigniorage charges) Perecherla 1Cum 23.00 980.00 234.50 -28.80 1
12 Niedle Vibrator 40mm (Petrol)Hour 6.00
Rs.12.40
for Fuel
Rs. 102.00 for
crew charges12 Niedle Vibrator 60mm (Petrol)
Hour 6.20Rs.18.60
for Fuel
Rs. 102.00 for
crew charges
0.7 Cum 20MM 1380.70 966.49 0.50 Cum 40MM 950.70 4
0.10 Cum 10MM 1025.70 102.57 0.30 Cum 20MM 1380.70 4
0.10 Cum 6MM 860.70 86.07 0.2 Cum 10MM 1025.70 2
0.10 Cum 12.5MM 1185.70 118.57
1273.70 1
Cum
20MM 40 MM
8/2/2019 Building DATA
21/23
Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc
e charges
deduct 14%
on
conveyance
Mpl. Area
allowancesA
1 2 3 4 5 6 7 8 9
13 Niedle Vibrator 60mm (Petrol)Hour 6.20
Rs. 18.60
for Fuel
Rs. 102.00 for
crew charges
14 Water Tanker(6000) Hour 345.00 3
15 Tipper 5 CumHour 351.30
Rs.233.90
for Fuel
Rs. 111.20 for
crew charges6
16 Angle Dozer 90 HpHour 1256.70
Rs.476.10
for Fuel
Rs.148.20 for
crew charges1
17 Concrete mixer 300/200 dieselHour 44.80
Rs.61.90
for Fuel
Rs. 141.70 for
crew charges2
18 Concrete mixer 600/400 dieselHour 77.00
Rs.123.80
for Fuel
Rs. 141.70 for
crew charges 3
19 Baching Plant 0.50 Cum(6 Cum/hr)Hour 91.00
Rs.60.40
for Fuel
Rs.213.40 for
crew charges 3
20 Disel generating set 30 KVAHour 48.70
Rs.495.00
for Fuel
Rs.85.00 for
crew charges
6
21 Disel generating set 50 KVAHour 92.80
Rs.742.50
for Fuel
Rs.85.00 for
crew charges8
22 Vibratory pad foot roller 8tHour 912.50
Rs.804.40
for Fuel
Rs. 170.00 for
crew charges1
23 Cement local M.T 5300.00 5
24 Steel local M.T 44000.00 44
24 M.S. Flats local M.T 42000.00 42
25 Bricks Second Class Local 1000 Nos 3100.00 3
26 Binding wire local Kg 55.00
8/2/2019 Building DATA
22/23
Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc
e charges
deduct 14%
on
conveyance
Mpl. Area
allowancesAmo
1 2 3 4 5 6 7 8 9 1
27 Water local KL 77.00 77
28 Motor Grader Hour 2600.00 260
29 Hydraulic Excavator Hour 2009.50 200
30 Front end Loader Hour 1320.00 132
31 Curing Compound ltr 95.00 95
36 Mason 1st class Each 285.00 57.00 342
37 Mason 2nd Class Each 260.00 52.00 312
38 Mazdoor (Unskilled) Each 215.00 43.00 258
39 Mate 260.00 52.00 312
40 Surveyor 350.00 70.00 420
41 Literate mazdoor 237.00 47.40 284
42 Diesel ltr 38.50 38
43 Petrol ltr 53.00 53
Assistant Engineer, Commissioner,
Sattenapalle Municipality. Sattenapalle Municipality.
Dy. Executive Engineer
Sattenapalle Municipality
8/2/2019 Building DATA
23/23
63.5
237.5
47.4
348.4