Following the BTOP MoneyWhat to do after the grant arrives
Merit’s REACH-3MC Project
Educause August 4, 2010
Bob StovallVP, Network Operations & Engineering
Agenda Merit for Michigan REACH-3MC Scope Funded – Challenges Begin
Learning the Bureaucracy! Engineering the Network Implementation & Delivery Lesson’s Learned Measuring Success! Questions & Answers
1
The Michigan Education Research Information Triad (MERIT) formed in 1966 because, “significant benefits might be gained from sharing computing resources via an electronic linkage…”
Merit is a 501(c)3 non-profit organization. Merit operates the longest running Regional Optical Network
(RON) in the country. Established Affiliate Member program in 1990 to connect Higher
Education, K-12 Schools, Libraries, Government, Health Care, Research Organizations, and other Non-profit Organizations.
1969 NSF grant for computer networking with only comparable work at BBN (ARPANET)
Merit Embarks on a Fiber and Wireless Backbone Strategy in 2003
2010 ARRA grant to construct a middle-mile fiber optic infrastructure in rural areas of Michigan (REACH-3MC)
2
About Merit
2
Merit for Michigan
Merit’s Goal has been to interconnect the Upper Peninsula and Lower Peninsula by fiber
2008 Competed UP, Bridge, and most of Southern lower Peninsula
2009 ARRA Opportunity
3
Merit for MichiganREACH-3MC – Awarded!
Rural, Education, Anchor, Community, Healthcare – Michigan Middle Mile Collaborative
Merit’s ARRA application was approved on 1/20/10.
Middle-mile network covering over 955 miles and reaching 33 counties.
72 strands of fiber 3 – For-Profit Partners
4
REACH-3MC Scope Routes are in four corridors:
Southern Corridor, Monroe to Benton Harbor Western Corridor, Benton Harbor to
Mackinaw City Central Corridor, Mount Pleasant to Hillman Eastern Corridor, Midland to Oscoda
Segment lengths are selected to match fiber loss verses optical system transmission capability
Intermediate cities were selected for “drive by” to allow future service to under served areas
5
Engineering the Network
Engineering & Build Process: 955+ Miles! Dedicated Project Manager Environmental Assessment Engineering Permitting Materials Construction Equipment installation
6
Engineering the NetworkEnvironmental Assessment:
Required by NEPA Must be completed within 6 months of notification Permitting and Construction cannot start until EA is
accepted
Permitting Process: Engineering firm creates the permit documentation Require digital photographs of all utility poles Merit team will submit permits to the appropriate entities Control the process and priorities
7
Funded – Opportunities Begin Learning the NTIA/BTOP Program
Compliance Environmental Assessment State Historic Preservations Office Tribal Historic Preservations Office Quarterly Reports
How are we responding? Breaking down the process…keeping in mind the easy
and hard stuff. 1st Engineering, 2nd Construction, 3rd Materials
Streamlining processes and managing the dollars Manage those easy wins!
8
Engineering the Network
Using one Engineering firm for the whole project Provides consistent documentation Consistent process Easier to project manage Control cost
Unit pricing $0.01/ft savings equals $57,400 over the whole
project Utility management
9
Engineering the NetworkConstruction:
Bid out as per unit (cost per foot and per splice) Economies of scale Increased flexibility Ability to move construction crews as needed ~20 Crews – estimated to complete 1 mile per day, 20 miles a day, estimated
to take 50 work days to complete the outside plant work Critical part is permitting and make-ready
Materials: Purchase in bulk! Economies of scale Consistent materials through out the infrastructure Control delivery of materials Consistent operational management after installation
10
Engineering the NetworkDetermining the fiber route/path:
Drive the route early and often Early spring Learn something different with each drive
Approach route in both directions Different direction, different perspective In urban areas walk the area
Search for existing conduit and infrastructure Already disturbed surfaces Someone else has already figured it out
Don’t believe the tools and documentation Visually verify each site
11
Engineering the Network
Route changes after EA submission Work with NTIA Project Officer Continue to investigate saving opportunities Work with local communities to discover current
infrastructure opportunities Remember changes must be aligned within the
scope of project
12
Implementation & Delivery
13
Fiber Utilization Plan: Merit will immediately light two pair of fiber
One fiber pair will be lit with long haul DWDM 10ge electronics and connect major sites
Approximately 150 to 200 miles apart No mid segment node insertions planned
The second fiber pair will be lit with CWDM 1ge electronics
This will be the access network Many mid segment insertions planned Driving signal both directions to nearest 10g node
Remaining dark fiber will be available for future network expansion and lease
14
10g North Node
10g South Node
1g Mid Node
1g Mid Node
Services – Leveraging the Infrastructure
REACH II
15
Lesson’s Learned – So Far!
Community outreach is critical Start engineering as soon as
possible Work closely with State
Governmental Agencies Department of Transportation Department of Natural Resourses State Historic Preservation Office Tribal Offices
16
Lesson’s Learned – So Far!
Manage the easy stuff Greatest areas of savings and speed The hard stuff is the great unknown
Keep utilities informed Competition is your greatest asset Manage in bite size pieces Learn from others
17
Discussion/Questions
More Information:http://www.merit.edu/meritformichigan/