Transcript
Page 1: ADCO Bu Hasa Incident 07 May 2011 (2)

Bu Hasa Incident, 7 May 2011

ADNOC Group Companies Briefing

Wednesday 20 July, 2011

Page 2: ADCO Bu Hasa Incident 07 May 2011 (2)

Incident Description

• BuHasa Central Degassing Station (CDS) had an Emergency Shut Down (ESD). It resulted in oil leaks from the flow lines of Bu407 & Bu 570resulted in oil leaks from the flow lines of Bu407 & Bu 570.

• The central station was normalized at midnight and operation teams started to open the closed wells. At 0125 Hrs, one of the crews observed a fire at Bu407 flow li ( i t l 200 t f th ll h d) d th llline (approximately 200 meters away from the well head) and the well was isolated from the Wellhead.

• Another Operations team (driver and four crew members) proceeded to Remote Degassing Station (RDS‐3)to isolate the well from the station. Close to RDS‐3there was a separate oil leak from the flowline of Bu570 covering the main access track (approximately 300 meters from the RDS‐3).

• While crossing the oil pool, the vehicle caught fire. It resulted in five causalities (four fatalities, and one crew member sustained minor injuries)

1

Page 3: ADCO Bu Hasa Incident 07 May 2011 (2)

Key Findings

1) The integrity of flow lines is not assured. (Under "upset" conditions ‐ when CDS is shutdown – pressure in the flow lines exceeds normal operating pressures and the chance of leaks is increased).

2) Bu Hasa CDS plant was shut‐in due to an ESD Level 1.2) Bu Hasa CDS plant was shut in due to an ESD Level 1.

• Trip initiated by a problem at the communication link between DCS and Emergency Shutdown System (ESD) with fuse failure in the ESD.

• Time to identify fault was around 6 hours. Time required to resolve problem was too long for such a y q p gfailure; especially for such a critical asset

3) Current design does not have over‐pressure protection at the existing wells.

• The HP pilot is an operational mechanism to close SSV and avoid holding the flow line under high pressure. Note flow lines are designed for CITHP Majority of wells did not trip on HP following the prolonged shut down and build up of pressure.

4) Wellhead maintenance is not always executed as per schedule.

5) Operations at night in response to emergency / incident was not identified as a “critical activity". Risk assessment and scenario analysis had not been undertaken.

6) HAZOP/ SIL revalidation for Bu Hasa facilities has not been undertaken within last 5 years.

2

7) Laborers are not issued with fire resistant coveralls.

8) Logistics management during emergency was not adequate or recorded

Page 4: ADCO Bu Hasa Incident 07 May 2011 (2)

Cause Tree Analysis

3

Page 5: ADCO Bu Hasa Incident 07 May 2011 (2)

Root Causes

1) Inadequate Risk Assessment 

2) Inadequate identification of job hazards (Night time journey for operation requirements not risk assessed)

3) Inadequate Enforcement of Critical Behaviors (Maintenance)3) Inadequate Enforcement of Critical Behaviors (Maintenance)

4) Inadequate work planning (Maintenance schedule for critical equipment were not met)

5) Inadequate Design for Pigging Chemical injection (for flow lines) (Flow (2) line design does not allow pigging/chemical injection)

6) Inadequate technical Review of Engineering design (ESD Design Redundancy) 

7) Inadequate Assessment of Required skills I Competency ( Lack of competent staff to ensure maintenance of SSV)

4

)

Page 6: ADCO Bu Hasa Incident 07 May 2011 (2)

5

Page 7: ADCO Bu Hasa Incident 07 May 2011 (2)

6

Page 8: ADCO Bu Hasa Incident 07 May 2011 (2)

7

Page 9: ADCO Bu Hasa Incident 07 May 2011 (2)

8

Page 10: ADCO Bu Hasa Incident 07 May 2011 (2)

9

Page 11: ADCO Bu Hasa Incident 07 May 2011 (2)

10

Page 12: ADCO Bu Hasa Incident 07 May 2011 (2)

11

Page 13: ADCO Bu Hasa Incident 07 May 2011 (2)

12

Page 14: ADCO Bu Hasa Incident 07 May 2011 (2)

13

Page 15: ADCO Bu Hasa Incident 07 May 2011 (2)

14

Page 16: ADCO Bu Hasa Incident 07 May 2011 (2)

15

Page 17: ADCO Bu Hasa Incident 07 May 2011 (2)

16

Page 18: ADCO Bu Hasa Incident 07 May 2011 (2)

17

Page 19: ADCO Bu Hasa Incident 07 May 2011 (2)

18

Page 20: ADCO Bu Hasa Incident 07 May 2011 (2)

Main Findings : Flowline Integrity

Finding

The integrity of flowlines is not assured. There remains a concern over internal and external corrosion. In a 2008 Flowline Integrity report, 61% of flowline leaks were attributed to external corrosion.

Under “upset” conditions when CDS is shutdown pressure in the flowlines exceeds normal operating pressure and theUnder “upset” conditions – when CDS is shutdown – pressure in the flowlines exceeds normal operating pressure and the chance of leaks increased.

Causes

•Specification for flowline is uncoated carbon steel pipe. Carbon steel is prone to internal & external corrosion.• Flowlines are difficult and often impossible to inspect for external corrosion i.e. buried under sand.

• Flowlines are not inspected routinely for internal corrosion. – IPS trials undertaken on 4” & 6” lines in 2004/5. Cost was high (especially as no launchers / receivers)

– Alternative methods to inspect for internal corrosion (e.g. strap on US devices) have been tested but not routinely used.

• Flowline replacement program is directionally good but the evaluation criteria for replacement are indicative (age, water cut etc) and criteria established with economic impact in mind. Only a few flowlines are identified for replacement each yearwhilst the actual exposure is higher.

• ADCO has acknowledged this flowline integrity problem and undertaken various studies and trials. However, ADCO focused on environmental risk and underestimated the safety risks. ADCO has worked to reduce the number of flowline leaks over the years with its flowline replacement program and has been effective in minimizing environmental impact with thorough clean‐up. With this  and did not resolve the issue with urgency.

HSEMS Element # 5.2 Asset Integrity

5 2 4 M i t i i i t it f i ti f iliti

19

o 5.2.4 Maintaining integrity of existing facilities

o 4.2.1 Improper risk evaluation & assessment

Page 21: ADCO Bu Hasa Incident 07 May 2011 (2)

ADCO OIL SPILLSADCO OIL SPILLSYTD A il 2011YTD A il 2011

50 100Number of Oil Spills % Recovery

YTD April 2011YTD April 2011

42

34

40 80

19

29

25 26

20

30

40

6026

1419 18

10

20

20

40

712

1

6

02003 2004 2005 2006 2007 2008 2009 2010 Apr 2011

0

20

No. of Onshore Spills > 6 Bbls No. of Onshore Spills < 6 BblsTotal No. of Oil Spills Total % Recovery

Page 22: ADCO Bu Hasa Incident 07 May 2011 (2)

Main Finding : Flowline Integrity (cont’d)Prior and Ongoing Work

• 2008 publication of “Oil Pipeline Integrity assessment & Management Report”, Bu Hasa.

Recommends hydrotesting @ 125% MAWP to ensure integrity for > 5 yrs; mothballing for > 3 days no flow; Inspection using guided wave US or bell hole. [2005 – IPS trials 4” & 6” flowlines]g g

•1st Flowline taskforce in 2008 delivered “Standard for Integrity of New flowlines” in 2009.Tested magnetic tomography on 5 lines in Asab. Trial partially successful.

•October 2010 – Guided wave ultrasonic inspection of flowlines successfully trialed in Bu Hasa • 2nd Flowline taskforce was established by ADCO CEO in 2010 to focus on existing flowlines.2nd Flowline taskforce was established by ADCO CEO in 2010 to focus on existing flowlines.

– Workshop conducted with ADNOC group, consultants & contractors. Result : HDPE liners. Trial approved by CEO for 2 companies on 28th April 2011. 

– Extensive data gathering to analyze trends & identify critical lines. 

– March 2011 – taskforce refocused as ‘Flowline Leaks Management”. TOR covers:March 2011  taskforce refocused as  Flowline Leaks Management . TOR covers:

• Short Term (2011)  :  HDPE liner trials, flowlines pigging/dewatering strategy, mothballing, prioritized intervention

• Long Term (2012‐3)  : Martial selection strategy (GRE/RTP), Chemical treatment, coating, improvised supports

Recommendations

With urgency and dedicated resources finalize the revised flowline design specifications and integrity assurance practices sothat flowline leaks will be an “abnormal” occurrence i.e. move ASAP from study phase to implementation.

Priority to be afforded to those flowlines which have higher safety risk i e near RDS CDS track crossing near access tracks

21

Priority to be afforded to those flowlines which have higher safety risk i.e. near RDS, CDS, track crossing, near access tracks.

(It is recognized that a “turn around” program on flowline integrity will take time to enact. Operational controls will need to be put in place to manage the risks of flowline leaks in the interim.

Page 23: ADCO Bu Hasa Incident 07 May 2011 (2)

Main Finding : Flowline Integrity (cont’d)

Action Items

h f “ l l k ” h ld b f d f b d1. The TOR of “Flowline Leaks” team should be refocused for DELIVERY ‐ team resources to be reviewed; program established with defined deliverables and timeline to reflect the urgency; progress reports provided to Sponsor.

2. Start implementation of proven integrity assurance activities in the fields ASAP  i.e. considering hydrotesting, IPS of suitable flow lines, Guided wave US inspection.

3. Although the existing procedure requires flowline mothballing when flowlines are shut in for > 3 days, the current practice is > 3 months. Review procedure, amend if necessary and rigorously apply procedure (include in procedure how status of flowlines is to be monitored and assign responsibilities).p ( p g p )

22

Page 24: ADCO Bu Hasa Incident 07 May 2011 (2)

Main Finding : Field Operations at Night

FindingOperations and Field Services staff were mobilized to the field at night to either close wells (after plant trip) or open up 

wells (to re‐establish production).• Operations at night in response to emergency / incident was not identified as a “critical activity”. Risk assessment 

and scenario analysis had not been undertaken.• Although the ‘unwritten guide’ was to attend to wells that were directly accessible from main tracks, field staff 

traveled cross‐country.

Causes• Under pressure to manage wells and restore production, field staff were mobilized at night.• Bu Hasa Field Standing Order 02/2007 (Amendment 2) of 30th December 2008, night trips are authorized to “Respond to any emergencies / accidents / incidents in the Bu Hasa area. 18:00 hrs to 06:30 hrs”. Duty Manager approval is not required for authorized trips. Type of route is defined as “black top and sand track”. Being an authorized journey – no special preparations (hazard identification, specific route instructions, specific work instructions) were required or taken.

HSEMS Element # 6.1 Implementationo 1.1.6 Visibility – Management evaluate HSE aspects before business decisions takeno 1.1.6 Visibility  Management evaluate HSE aspects before business decisions takeno 6.1.1 Implementation of work instructions

23

Page 25: ADCO Bu Hasa Incident 07 May 2011 (2)

Main Finding : Field Operations at Night

Recommendations• Review field operating philosophy• Review field operating philosophy. 

oConsider manned RDS’s (vs adhoc night operations) & automation.• Night Operation should necessitate specific preparation with explicit authorization at appropriate level.• A  guide  is  required  to  assist  duty  managers  to  make  the  appropriate  decision  when  considering restoration of production after a plant trip versus field operation at nightrestoration of production after a plant trip versus field operation at night.

Action Items• Review operating philosophy wrt manning of RDS, automation etc. Prepare analysis and make proposal.p g p p y g , p y p p1. Amend field procedures & instructions such that night operation is considered as an abnormal and higher risk  activity  ‐ to  be  undertaken  after  consideration  of  inherent  risk  versus  objective  at  appropriate leadership level, under specific controls and defined procedure.• Quick win : Fit vehicles which could be mobilized at night with search/flood lights. (Already actioned in Bu g / g ( yHasa.)

24

Page 26: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding :  ESD trip and Response

Finding•Bu Hasa CDS plant was shut‐in due to an ESD Level 1.

• Trip initiated by a problem at the communication link between DCS and Emergency Shutdown p y p g ySystem (ESD) with fuse failure in the ESD.

•Time to identify fault was around 6 hours.• Time required to resolve problem was too long for such a failure; especially for such a critical asset.

Causes•The ESD system has dual power supplies i.e. redundancy provided in design. However, the other power supply card for this particular ESD system sector had been faulty for some time. Redundancy and therefore system reliability was thereby defeatedsystem reliability was thereby defeated.

•Power supply card failure is a reoccurring event i.e. > 15 failures.•Maintenance staff called to investigate DCS/ESD problem did not have sufficient familiarity with the systems to investigate and identify the problem quickly. There was a reliance on off‐site vendor support.

•HSEMS Element # 5.2 Asset Integrity & 3.4 Competencyo 5.2.4 Reliability of protective systemso 3.4 Competence assurance

25

Page 27: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding :  ESD trip and Response

Recommendations• Maintenance of safe guarding systems is essential. Spare parts must be stocked. Reoccurring problems h ld b l d b d d f d d b d bshould be resolved by Vendor. Any deviations from standard maintenance practice are to be approved by a designated authority (M.O.C.). In the case of Critical Safety Systems, it is proposed that authority to deviate from the standard practice is carried at Management level.•Improve on‐site support for control and safe guarding systems

d ( d d d l l•Review competence and training requirements. (Recommend training engineers to an advanced level of systems troubleshooting) Review the current practices in sister OPCO’s.

•Provide 24/7 coverage with trained systems engineers.

Action Items1. Ensure  that  Critical  Safety  Systems  (especially  ESD,  F&G)  are  properly  maintained.  Resolve  the 

reoccurring power supply  failures with Vendor.  In  the mean  time, ensure adequate spare parts are available to account for frequent power supply card failuresavailable to account for frequent power supply card failures.

2. Establish positions and define competency requirements for System Engineers.

26

Page 28: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding :  SSV reliability & functioning

Finding•The majority of wells did not trip on HP following the prolonged shut down and build up of pressure.•Note : Flowlines are designed for CITHP•Note :  Flowlines are designed for CITHP.

CausesHP pilots are found to be frequently out of calibration or not functioning‐ HP pilots are found to be frequently out of calibration or not functioning.

-Set points of HP pilots are not systematically reviewed to account for the deterioration of flowlines due to corrosion. (Note : There is a difficulty to identify problematic flowlines and also to estimate the appropriate reduction in HP pilot set point.)

HSEMS Element # 6.3 Performance monitoring & Records

Recommendations•Review design philosophies and over pressure protection from the well head through RDSs all the way to the CDS in view of changing reservoir conditions, flowline aging and recent enhanced design practice. 

•Implement a work practice to periodically review the suitability of ‘wellhead to CDS’ facilities specification and  instrumentation  set points. Under MOC procedure,  accommodate  any  change  in  operating/design conditions and to be consistent with latest inspection/integrity records.

27

Page 29: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding : SSV reliability & functioning 

Action Items

1. Review Facilities Design from wellhead to CDS

2. Review the high pressure set point of pilots. The current set point of 1000 psig may be too high for either operational requirement or flowline condition.

3. SSV and associated pilots should be functionally tested, test results documented and signed off and results loaded in MAXIMO as per API RP 14 C.

4. Evaluate alternative pressure sensors with higher reliability for HP / LP pilots at wellhead (noting the harsh desert environment)harsh desert environment).

5. Review the SIL classification of the over‐pressure protection i.e. refer to new configuration with dual pilots and valves, as installed in selected service in other fields

6. Evaluate  surge  pressures which may  be  transferred  through  system  to wellheads when  CDS  ESD l lvalves close. 

28

Page 30: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding :  Wellhead Maintenance

FindingWellhead maintenance is not always executed as per schedule. 

Causes• Inadequate planning and assurance• Inadequate manpower resources• Many MAXIMO records for wellhead maintenance are inadequate to provide a reliable history record.• HSEMS Element # 5.2 Asset Integrity & 3.2 Resources 

o 5.2.4 Maintaining integrity of existing facilitieso 3.2.2 Resources

Recommendations• Resolve manpower resource requirement.• Analyze why staff are not loading data into MAXIMO and correct. (Training? Time? Supervision/)• Improve write‐up of  maintenance procedures for wellhead equipment (e.g. Standard Procedure 7070)• Institute an assurance maintenance management system including self‐audit verification process• Train staff on data analysis in MAXIMO. • Review functionality of MAXIMO for ease of use.

ActionsStarting with Bu Hasa field but eventually addressing all fields undertake a comprehensive review of

29

Starting with Bu Hasa field but eventually addressing all fields, undertake a comprehensive review of maintenance practices. Review to include fit for purpose procedures, manpower resource availability and competence, control and assurance processes, use of MAXIMO.

Page 31: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding : Emergency Response  & Incident Management 

Finding• HSE Team was not aware of the shutdown as ESD level 1 was not considered as an emergency• HSE Team was not aware of the shutdown as ESD level 1 was not considered as an emergency.• Inadequate communication means (mobile phones used; not radios).• Safety & loss prevention team was dispatched to attend fire at Bu 407; used GMC pick‐up. Unsuccessful attempt to fight fire of Bu‐407 flowline using powder fire extinguishers, carried in GMC pick‐up. 

• Later a second safety & loss prevention team took RIV as search & rescue support to gatch road (Bu‐570• Later, a second safety & loss prevention team took RIV as search & rescue support to gatch road (Bu 570 flowline).

• Insufficient resources at RAMS (staff and ambulances) to manage a multi‐casualty accident(s). • Logistics management during emergency was not adequate or recorded.

Causes• Lack of clarity as to when a fire should be fought or not. Where other facilities or people are not at risk, it is advised not to fight an oil leak fire. The fire avoids gas cloud. 

• The current Operating Philosophy is “burn down”. Implicitly and in relation to this specific event, fire fighting vehicles were not available for off‐road desert conditions.

• HSEMS Element # 5.6 Contingency Planningo 5.6.1 Contingency Planning

30

Page 32: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding : Emergency Response  & Incident Management 

Recommendations• Review emergency response procedure to consider an ESD as an ‘emergency’ event.• Review fire fighting philosophy to consider intervention to avoid fire escalation e.g. fire in close proximity to flowlines / field facilities.  Review fire fighting vehicle requirement (i.e. suitable for desert), water supply and equipment. 

• Decision already taken to recruit professional fire fighting teams across ADCO assets. This will resolve l d h d h f f h b lleadership issues and shortcomings on fire fighting capabilities.

• Medical : Assess the needs for staff and equipment against realistic scenarios. (Medics vs population?)• Emergency Response : Further training necessary in emergency management process, risk assessment & procedures.

d f ld d f d d f d• Order field communication equipment as identified. Repair defective radios.

Actions• With the learnings from this Bu Hasa incident and with view to the proposed establishment of professional fire fighting teams in the Fields, review emergency / accident equipment requirements, p g g , g y / q p q ,support resources, implementation and training requirements.

• This is a major initiative which would have been undertaken as a matter of course with the introduction of  the  fire  fighting  teams.  The  scope  of  this  initiative  needs  to  be  expanded  to  address  associated emergency response system shortfalls.

31

g y p y

Page 33: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding : PPE Coveralls

Finding

•Not all coveralls issued by ADCO are fire resistant.• Laborers are not issued with fire resistant coveralls. (Laborer who escaped Bu Hasa vehicle fire thought hisLaborers are not issued with fire resistant coveralls. (Laborer who escaped Bu Hasa vehicle fire thought his coveralls were “plastic” and therefore flammable.)

Causes

• Lack of definition as to which staff must wear fire resistant coveralls.

•HSEMS Element # 5.3 Standards & Procedures

o 5.3.4 consistent application of suitable standards

d iRecommendations

• Review specifications for coveralls with respect to fire resistance for both ADCO and contractor staff.• If specification is not the same for all staff – provide definition of requirements for the various work groups.g p

Actions

•Advise  end  users  (field  and  drilling  staff  and  contractors)  of  the work  situations  /  types  for which  fire resistant coveralls are mandated.

32

Page 34: ADCO Bu Hasa Incident 07 May 2011 (2)

Finding : HAZOP Revalidation

Finding

• HAZOP revalidation for Bu Hasa facilities has not been undertaken within last 5 years.SIL A t i d t i N b 2009• SIL Assessment was carried out in November 2009.

Causes

• HSEIA’s have been completed for all assets in 2009 and approved by ADNOC/SPC in 2010.

Th HSEIA d t i 5 l h d HAZOP lid ti h ll b d t d (Pl d t t• The HSEIA update is on a 5 year cycle where under HAZOP revalidation shall be conducted. (Planned start Bab in 2012)

•HSEMS Element # 4.1 Risk Identification, Evaluation & Assessment

o4.1.3 Up‐to‐date register of risks

Recommendations

Review adequacy of current plan for revalidation of HAZOP.

Actions

• Present plan for revalidation of HAZOP to GMC HSE and Risk Committee for endorsement.

33

Page 35: ADCO Bu Hasa Incident 07 May 2011 (2)

IMMEDIATE ACTION

• Identify High Risk flowlines: 

P i it t l t i d d t ko Proximity to people movement , i.e. roads, sand track 

o Close to facilities 

Congestiono Congestion 

• Wellhead Protection Equipment/Flowline: 

o Immediate campaign to functionally test all SSVs, SCSSVs, and wellheadmaintenance.

o Hydrotest of vulnerable flowlines and repair accordingly.

o Flowline approach to RDS, CDS: excavation, exposure, inspection, repair,pipeline crossing and coat accordingly

34

pipeline crossing and coat accordingly.

Page 36: ADCO Bu Hasa Incident 07 May 2011 (2)

OTHER ACTIONSOTHER ACTIONS

• Implement flow line integrity programme across ADCO fields. 

o Firm up aging flow line replacement philosophyo Firm up aging flow line replacement philosophy. 

o Review flow line specification to reflect changes in production stream e.g. watercut.

• Review night time journey management. 

o Review field operating and manning philosophy (i.e. CDS, RDS 24/7 coverage).

• Implement a maintenance assurance management system including self‐auditverification process.

• Review competency and training requirements (e.g. 24/7 coverage of trainedSystems Engineers).

35

• Conduct Hazop Campaign for existing facilities every 5 years. 

Page 37: ADCO Bu Hasa Incident 07 May 2011 (2)

thankthank

36

Page 38: ADCO Bu Hasa Incident 07 May 2011 (2)

Key Recommendations

1) With urgency and dedicated resources finalize the revised flow line design specifications and integrity assurance practices so that flow line leaks will be an"abnormal" occurrence Le. move ASAP from study phase to implementation.

2) Implement confirmed integrity assurance activities Le. hydro testing, mothballing, IPS of suitable flow lines.

3) Review field operating philosophy. Review manned RDS's (vs adhoc night operations) &consider automation

4) Overall DCS/ ESD system design needs to be revised to improve reliability.

• Improve on‐site support for control and safe guarding systems

• Review competence and training requirements. (Recommend training engineers to an advanced level of systems troubleshooting) Review the current practices in sister OPCOs.

• Provide 24/7 coverage with trained systems engineers.

5) Review Facilities Design from wellhead to CDS( consider involvement of SH's)5) Review Facilities Design from wellhead to CDS( consider involvement of SH s)

• Review the high pressure set point of pilots. The current set point of 1000 psig may be too high.

• Consider carrying out functional tests of wells high pressure trip systems by shutting down downstream valve and observing the trip of the SSV as pressure builds up. This should be carried out at frequent intervals (say every six months) and would also act as a test of flowline integrity.

• Evaluate alternative pressure sensors with higher reliability,

• Consider over‐pressure protection means

37

• Evaluate surge pressures (water‐hammer) which may be transferred through system to wellheads when CDS ESD  valves close.

Page 39: ADCO Bu Hasa Incident 07 May 2011 (2)

Key Recommendations (Cont’d)

6) Improve Maintenance

• Resolve manpower resource requirement.

• Analyze why staff are not loading data into MAXIMO and correct. (Training? Time?y y g ( g

• Supervisionj)

• Improve write‐up of maintenance procedures for wellhead equipment (e.g. Standard

• Procedure 7070)

• Institute an assurance maintenance management system including self‐audit

• verification process

• Train staff on data analysis in MAXIMO .

• Review functionality of MAXIMO for ease of use• Review functionality of MAXIMO for ease of use.

7) Review fire fighting philosophy to consider intervention to avoid fire escalation e.g. fire in close proximity to flowlines /field facilities. Review fire fighting vehicle requirement and equipment.

8) Medical: Assess the needs for staff and equipment against realistic scenarios. (Medics vs population?)

9) Emergency Response: Further training necessary in emergency management process, risk assessment &procedures.

10) Order field communication equipment as identified. Repair defective radios.

11) Review specifications for coveralls with respect to fire resistance for both ADCO and contractor staff.

38

) p p

12) Review adequacy of current plan for revalidation of HAZOP/SIL revalidation. Present evaluation and recommendation to GMCHSE and Risk Committee for endorsement.