Transcript
Page 1: Achieving Readiness Pacific Northwest National Laboratory

Achieving ReadinessPacific Northwest National Laboratory

Operational Experience Committee Meeting, September 13, 2011Brad EvansPNNL Nuclear Safety & Facility Authorization

PNNL-SA-82612 Reviewed for Public Release

Page 2: Achieving Readiness Pacific Northwest National Laboratory

The Purpose of Readiness

Page 3: Achieving Readiness Pacific Northwest National Laboratory

Readiness is the Bridge

A systematic process focused on delivery of turn-key capability fully ready to operate safely and conduct research operations. The bridge between developing a Capability and starting Operations

Page 4: Achieving Readiness Pacific Northwest National Laboratory

Mitigate risks and deliver benefits

4

Risks Benefits• Major changes • Efficient and effective operations

• High hazards • Respected reputation

• Unique processes and training • Customer confidence

• Schedule constraints • Favorable award fee

• Elevated strategic and mission needs

• Improved business opportunities

Prevent missed action that could lead to delays in startupProvides a higher degree of confidence in operationsSound business practice and cost-effective

Why Readiness is necessary

Page 5: Achieving Readiness Pacific Northwest National Laboratory

Getting to Readiness:Through seamless integration

Tailored to RiskInstitutionalized in the “Phases of Project Management” procedureReinforces the tenets of Integrated Safety Management

ScopeHazardsControlsAll in place prior to operationsFeedback is always in place --- readiness is real-time

5

Page 6: Achieving Readiness Pacific Northwest National Laboratory

Getting to Readiness: Focus on starting turn-key capability

Evaluate Project scope + customer input = focused Readiness deliverables

DecideLevel of rigor required to assure delivery

Execute, document, validateAssure Readiness items are completed to expectations

Final acceptance to startBegin safe operations of the fully operational capability

6

Page 7: Achieving Readiness Pacific Northwest National Laboratory

The Best Part:Real experiences

Paul CraneDivision Manager, PNNL Nuclear and Materials Operations Division

Joe Cruz Division Manager, PNNL Projects and Engineering Division

Mark HartzellManager, EMSL Project Office

7

Page 8: Achieving Readiness Pacific Northwest National Laboratory

Successful Execution of Readiness at PNNL Category 2 Nuclear Facility

Paul CraneDivision Manager, PNNL Nuclear & Materials [email protected]

PNNL-SA-81089 Reviewed for Public Release

8

Page 9: Achieving Readiness Pacific Northwest National Laboratory

Pop Quiz

Question: What are the odds of completing a DOE-approved nuclear Readiness Assessment within 2 months of completion of construction?

A: Not a chanceB: 50/50C: It’s a sure thingD: Depends on the execution

Answer: D – Execution of the readiness principles described in this presentation can lead to a very successful and efficient completion of nuclear readiness activities

Page 10: Achieving Readiness Pacific Northwest National Laboratory

Contractor-led DOE-approved Readiness Assessment Scope of RPL Readiness Assessment

Category 2 Nuclear FacilityStart-up of 4 hot cells and 3 gloveboxes (newly constructed)

Radiochemical Processing Laboratory Readiness Assessment - Scope

10

Page 11: Achieving Readiness Pacific Northwest National Laboratory

Many Challenges to Successful Readiness Outcome

Stress: Critical path schedule to completion of $230M PNNL Capability Replacement Laboratory (CRL) ProjectChange: Prior to CRL Project, RPL was a limited-life facility schedule for shut-downMultiple Activities: Hot cell and glovebox construction and readiness one of many activities underway at facilityLimited Experience: No nuclear RA/ORR conducted at PNNL in ~10 yearsTime: Less than 2 months to go from completion of construction to DOE approval of RA => must be successful the first time with no significant issues

Recognition of these challenges and management approach led to successful RA outcome

Radiochemical Processing Laboratory Readiness Assessment - Challenges

11

Page 12: Achieving Readiness Pacific Northwest National Laboratory

Critical elements to successful RA outcome

Manage as a project with adequate authority of project leadClear understanding and documented agreement of “completion of construction” (competing priorities) and turnover from construction to operationsEarly documented agreement with approval authority of assessment criteria that will be evaluated – manage scope and scope creep

Radiochemical Processing Laboratory Readiness Assessment - Approach

12

Page 13: Achieving Readiness Pacific Northwest National Laboratory

Critical elements to successful RA outcome

Hold responsible parties accountable to “defend” readiness – establish CRADs and use affidavitsEarly and continued involvement of stakeholdersDry-run staff as many times as it takes to get it right – both administrative and operationalRobust and independent Management Self Assessment – As method to verify readiness, not to determine whether you are readySelect RA team with approval authority credibilitySelect and use capable and credible mentors

Radiochemical Processing Laboratory Readiness Assessment - Approach

13

Page 14: Achieving Readiness Pacific Northwest National Laboratory

Independent Readiness Assessment team identified one minor finding requiring resolution prior to start-upDOE approval obtained within days of requested approval to operateDOE-SC considers RPL RA as model execution of nuclear readiness process

Radiochemical Processing Laboratory Readiness Assessment - Outcome

14

Page 15: Achieving Readiness Pacific Northwest National Laboratory

Integration and Management Commitment: Delivering “Ready for Research Capability”

Joe CruzProjects and Engineering Division [email protected]

PNNL-SA-81089 Reviewed for Public Release

Page 16: Achieving Readiness Pacific Northwest National Laboratory

Pop Quiz

Q: When is a project finished?A: When it runs out of moneyB: When it runs out of timeC: When the project sheds scope to finishD: All of the aboveE: When a well understood and documented ‘finish line’ is achieved

A: Management must provide framework to deliver and set the expectation that E is the only acceptable answer

Page 17: Achieving Readiness Pacific Northwest National Laboratory

Opportunity Knocks

Project Management Manual due for a rewriteLessons learned from the Capability Replacement LaboratoryAssessment findingsToo many small ‘Band-Aid’ revisions

Non-nuclear readiness gaining momentum in DOEPNNL projects have complex systems and interfaces

Unique equipment, facilities, hazardsDesire to improve the reliability/efficiency of project deliveryLeverage the Achieving Readiness methodology

Page 18: Achieving Readiness Pacific Northwest National Laboratory

PNNL’s Approach to Readiness: Project Management Manual Revision Plan

CharterObjectives to guide authoring teamStakeholder group identified

PM, Engineering, CM, Contracts, Readiness, SafetySchedule

ApproachTailored approach: “Risk Drives the Rigor”Integrate readinessCore + process guide architectureMimic DOE critical decision process

OutcomesSafe and efficient execution

Page 19: Achieving Readiness Pacific Northwest National Laboratory

Project Phases and Project Decisions (PD)

Readiness inherent to PM approachEnsures clarity for project finish line for ALL involved parties (IPT)Ensure project delivers “ready to operate” condition

Page 20: Achieving Readiness Pacific Northwest National Laboratory

Lessons Learned

Tailoring is easier said than doneClearly state criteria for different levels of rigorClearly state differences in tailored approachThresholds are difficult to establish

Cookbook approach to readiness is keyWith a good checklist, anyone can do it – no excuses not to

Readiness component delivering desired improvementsFewer hiccups when occupying new spacesCustomers are pleased – view the approach as value added

Not free, but not expensiveReduces burden on customer and building functions

PMs may be reluctantChallenges and misconceptions

Page 21: Achieving Readiness Pacific Northwest National Laboratory

Using Readiness for Successful Delivery of New Research Capability

Mark HartzellManager, EMSL Project [email protected]

PNNL-SA-81089 Reviewed for Public Release

21

Page 22: Achieving Readiness Pacific Northwest National Laboratory

Environmental Molecular Science Laboratory

200,000sf research facilityBER user facilityProvides integrated experimental and computational resourcesThree science themes

Biological Interactions and DynamicsGeochemistry/Biogeochemistry and Subsurface ScienceScience of Interfacial Phenomena

22

Page 23: Achieving Readiness Pacific Northwest National Laboratory

EMSL Projects

$60M to develop and deploy transformational capabilities

34 separate instrument systems18-months to procure, modify space, and installInvolved 10 separate science leadsScope ranged from simple install to significant modifications

23

Quiet Wing10,000sfLow EMF low vibrationHigh res imaging (TEM+)

Radiochemistry AnnexLocated in new PSF5 existing labsExpands rad exhaust

AARA1 EMSL Capability Expansion2

Page 24: Achieving Readiness Pacific Northwest National Laboratory

How EMSL uses Readiness

Plan earlyDetermine Readiness scope during baseline developmentInclude discrete activities for readiness in schedule

Develop a comprehensive checklistTeam effort between the project, facility, and research staffStarts with the general categories from Achieving Readiness ProcessAssign individual responsibility

Prepare in advanceMeet throughout project execution to status and prepare

Complete and DocumentCompletion verified and documentedReadiness achieved when all approve

24

Page 25: Achieving Readiness Pacific Northwest National Laboratory

How research uses Readiness

Testing and QualificationEquipment Operations training for staffHazards (IOPS) and Emergency Preparedness

System AcceptanceMeets procurement requirements

Technical DocumentationVendor manuals received and archivedSpare parts list

Laboratory Space AcceptanceSpace ready for research

AdministrativeMITMEL

25

Page 26: Achieving Readiness Pacific Northwest National Laboratory

How Facilities and Operations uses Readiness

MaintenanceDeveloped preventative maintenance and calibration proceduresProvide special tools or training

OperationsAlarm responseOperator rounds

Technical documentationUpdated as-built and key drawings Design documentation

Laboratory space acceptanceNew or modified systems meet requirementsReady for operations

26

Page 27: Achieving Readiness Pacific Northwest National Laboratory

Benefits

Faster time to researchProcess leads to “ah-ha” momentsChanges project delivery to capability deliveryReduces operating riskFacilitates the dialog between facilities and researchDocuments ReadinessDevelops Lessons LearnedCan be quite smooth once you have done it

27

Page 28: Achieving Readiness Pacific Northwest National Laboratory

The challenge and misconceptions

The challengeCulture change: moving from how it was done to how it is done

28

The potential misconceptions

If you think: Ask yourself :

“How?”

“Where?”

“How are you demonstrating you're ready?”

“At what point before?”

“Is this too late?”

“Is there money to do it over?”

“We already ‘do’ readiness.”1

“It’s built into our process.”2

“This is another work barrier.”3

“I do ‘readiness’ before I start operations.”

4

“I involve the customer when I’m ready to turnover the project.”

5

“We don’t have money.”6

Page 29: Achieving Readiness Pacific Northwest National Laboratory

Lessons Learned

New first time lab technology Project managers – train them and followupReadiness needs to be planned, not ad-hoc

29

high risknon-nuclear

high risknuclear

low risknon-nuclear &high visibility

high risknuclear

Hazard Category 2 Nuclear Facility RANo RA in over 10 yearsTook Readiness seriouslyNear Flawless RA outcome

New, unique Fissile Materials PackageInitiated Readiness very late in the project life cycleQuickly evaluated and focused on minimum needs to safely deploySuccessful deployment and oversight assessment with no findings

Low Risk but High Visibility Projects 34 EMSL projects for latest state-of-the-art technologyAccelerate turnkey deliveries Necessary steps and key risks were not overlooked

Page 30: Achieving Readiness Pacific Northwest National Laboratory

Customize and apply Readiness to your site’s unique processes.Develop procedures and processes that integrate with your site’s lifecycles.Focus on implementation, it’s not as simple as it may seem.Train staff to sustain and expand a successful Readiness process.On-going support to ensure smooth integration into project management, research, and other site mission needs.Mentor and provide technical support for startups.Publish success – Articles in

NNSA June 2011 Tech BulletinPNNL Operating Experience/Lessons Learned

Support to Share Success

30

Page 31: Achieving Readiness Pacific Northwest National Laboratory

Contacts for Information and Support

31

Nick RegoliSenior Advisor, Startup and Operational ReadinessNuclear & Materials Operations Division Tel:  509-372-4765 [email protected]

Brad EvansNuclear Safety & Facility Authorization Manager Nuclear & Materials Operations DivisionTel:  [email protected]

Paul CraneNuclear & Materials Operations Division ManagerFacilities & Operations DirectorateTel:  [email protected]


Recommended