Land Acquisition and Resettlement Plan
December 2019 Project Number: 45371-007
IND: Madhya Pradesh Irrigation Efficiency
Improvement Project Pipeline Distribution System of Zone 3 for Command Area CCA 63548-ha – Left Bank
Prepared by the Madhya Pradesh Water Resource Department with the assistance of the Project Contractor (L&T Construction, India) for India and the Asian Development Bank. This land acquisition and resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Land Acquisition & Resettlement Plan (This document is prepared in accordance to the ADB Resettlement Plan Requirement as described in ADB Safeguard Policy Statement, 2009)
Document Stage: Final Draft
India: Madhya Pradesh Irrigation Efficiency Improvement Project
Subproject:
Pipeline Distribution of Zone 3 for Command Area CCA 63548
ha of Kundalia Irrigation Project- Left Bank
December 2019
2
CURRENCY EQUIVALENTS (As of 31st December 2019)
Currency unit – Indian Rupee (Rs) INR 1.00 = $ ------------------ $ 1.00 = ---------------------
ABBREVIATIONS
ADB : Asian Development Bank AH : Affected Households AP : Affected People BSR : Basic Schedule of Rate CSC : Construction Supervision Consultant DC : Distribution Chamber DMS : Detailed Measurement Survey DP : Displaced People DPR : Detailed Project Report EA : Executive Agency FGD : Focus Group Discussion GOMP : Government of Madhya Pradesh GRM : Grievance Redress Mechanism GRC : Grievance Redress Committee IA : Implementing Agency IP : Indigenous People KIP : Kundalia Irrigation Project LAR : Land Acquisition and Resettlement LVC : Land Valuation Committee MFF : Multi Tranche Financing Facility MPIEIP : Madhya Pradesh Irrigation Efficiency Improvement Project NGO : Non Governmental Organization PIU : Project Implementation Unit PPTA : Project Preparatory Technical Assistance PS : Pumping Station RF : Resettlement Framework ROW : Right of Way LARP Land Acquisition and Resettlement Plan R&R : Resettlement and Rehabilitation SC : Scheduled Caste SIA : Social Impact Assessment SPS : Safeguard Policy Statement ST : Scheduled Tribe WRD : Water Resources Department WUA : Water User Association
1
CONTENTS
Page
I. EXECUTIVE SUMMARY 5
A. Introduction 5
B. Scope of Land Acquisition 5
C. Land Acquisition Impacts 6
D. Consultations with DPs and their Participation 7
E. Legal Framework 7
F. Entitlements, Assistance and Benefits 7
G. Land Acquisition Budget and Financing Plan 8
H. Grievance Redress Mechanism 8
I. Institutional Arrangement 8
J. Implementation Schedule 9
K. Monitoring and Reporting 9
II. PROJECT DESCRIPTION 10
A. Introduction 10
B. General Profile of the Subproject Area 12
C. Subproject Impacts and Benefits 12
D. Minimizing Land Acquisition 13
E. Scope and Objectives of Preparation of Land Acquisition and Resettlement Plan (LARP) 13
F. Methodology adopted for Socio-economic Survey 14
III. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 16
A. Land Acquisition Requirement 16
B. Resettlement Impacts 17
C. Loss of Private Land in Subproject. 17
D. Loss of Structures in the Subproject 18
E. Loss of other Assets in the Subproject 18
F. Loss of Livelihood in the Subproject 18
G. Significance of Impact on Land Owners 18
IV. SOCIO-ECONOMIC INFORMATION AND PROFILE 20
A. Census Socioeconomic Survey 20
B. Demographic Profile of DPs 20
C. Socio-economic Profile 23
D. Key Socio-economic Indicators 26
V. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION 28
A. Public Consultations 28
B. Methods of Consultation 28
C. Outcome of the Consultations 30
D. Conclusions of the Group Consultations 34
E. Plan for further Consultation in the Project 34
F. Information Disclosure 35
VI. GRIEVANCE REDRESS MECHANISMS (GRM) 36
2
VII. LEGAL FRAMEWORK 38
A. Introduction 38
B. Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCT in LARR), 2013 38
C. Legal and Policy Frameworks of Madhya Pradesh State: 39
D. ADB’s Safeguard Policy Statement (SPS), 2009 40
E. Comparison of Government and ADB Policies 41
F. R&R Policy Framework for the Subproject 45
G. Valuation of Assets 48
VIII. ENTITLEMENTS, ASSISTANCE AND BENEFITS 51
A. Introduction 51
B. Cut-off-Date for Entitlement 51
C. Subproject Entitlement 51
D. Loss of land 52
E. Loss of Structures 52
F. Loss of trees and crops 52
G. Additional assistance to vulnerable households 52
H. Loss of community infrastructure/common property resources 53
I. Temporary Impacts 53
J. Entitlement Matrix 53
IX. RELOCATION, INCOME RESTORATION AND REHABILITATION 66
A. Basic Provision for Relocation 66
B. Income Restoration and Rehabilitation 66
C. Provisions for Loss of Livelihood 67
D. Additional Support from Ongoing Poverty Reduction Programs 67
X. LAND ACQUISITION BUDGET AND FINANCING PLAN 69
A. Introduction 69
B. Compensation Payment 69
C. Compensation for Community Property Resources 70
D. LAP Implementation and Support Cost 70
E. Sources of Funding and Fund Flow Management 70
XI. INSTITUTIONAL ARRANGEMENTS AND CAPACITY DEVELOPMENT 72
A. Institutional Requirement 72
B. Executing Agency 72
C. Land Acquisition Management at PIU/PMU 72
D. Capacity Building on RP in the EA 75
XII. IMPLEMENTATION SCHEDULE 76
A. Introduction 76
XIII. MONITORING AND REPORTING 78
A. Need for Monitoring and Reporting 78
B. Monitoring by PIU 78
C. Monitoring Indicators 78
D. Reporting Requirements 79
3
TABLES :
Table 1 : Summary of Impacts on Properties ......................................................................... 6
Table 2: Details of Components of the Subproject ...............................................................11
Table 3: Land Acquisition Requirements ..............................................................................16
Table 4: Ownership of Land Affected in the Subproject ......................................................17
Table 5: Details of Displaced Persons in the Subproject .....................................................17
Table 6 : Significance of Land Impact ...................................................................................18
Table 7 : All Displaced Persons by Sex .................................................................................20
Table 8 : Displaced Household by Religion ..........................................................................21
Table 9 : Displaced Household by Social Category ..............................................................22
Table 10 : Family Size of the Household ...............................................................................22
Table 11 : Age Group of DPs ..................................................................................................23
Table 12 : Educational level of DPs .......................................................................................23
Table 13 : Occupation of DPs .................................................................................................24
Table 14 : Monthly Household Income of DHs ......................................................................25
Table 15 : Vulnerable (mutually exclusive) ...........................................................................25
Table 16 : Key Socio-economic Indicators ............................................................................27
Table 17: Consultation Methods ............................................................................................28
Table 18: Consultation Locations ..........................................................................................29
Table 19 : Summary of the Consultation Outcome ...............................................................33
Table 20: Format for Public Consultation and Disclosure Plan ...........................................35
Table 21: The Comparison of ADB and GOI Policy ..............................................................41
Table 22: Entitlement Matrix ...................................................................................................54
Table 23: Estimated Budget for Implementation of the RP ..................................................71
Table 24: Agencies Responsible for Resettlement Implementation ....................................73
FIGURES : Figure 1: Schematic of Kundalia Irrigation Project Left Bank .............................................11
Figure 2: An Overview of the Grievance Redress Mechanism.............................................37
ANNEXURES : Annexure 1 : Summary of Affected Persons and Common Property Resources ...............80
Annexure 2 : Summary of Affected Persons and Common Property Resources ...............85
Annexure 3 : Summary of Affected Persons and Common Property Resources ...............89
Annexure 4 : Summary of Affected Persons and Common Property Resources ...............90
Annexure 5 : Summary of Affected Persons and Common Property Resources ...............91
Annexure 6 : Summary of Affected Persons and Common Property Resources ...............94
Annexure 7 : Summary of Affected Persons and Common Property Resources ...............98
Annexure 8 : Summary of Affected Persons and Common Property Resources ............. 101
Annexure 9 : Summary of Affected Persons and Common Property Resources ............. 104
Annexure 10 : Summary of Affected Persons and Common Property Resources ........... 105
Annexure 11 : Summary of Affected Persons and Common Property Resources ........... 106
4
Annexure 12 : Approved Collector Rates of Agriculture Land of Nalkheda Tehsil, Agar Malwa District ........................................................................................................................ 109
Annexure 13 : MSP Rates By MP Govt. ............................................................................... 114
Annexure 14 : Memorandum of Understanding (MOU) to document foregone compensation for temporary land use ................................................................................ 115
5
I. EXECUTIVE SUMMARY
A. Introduction
1. Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to
achieve high irrigation efficiency and water productivity in the State. The MPIEP includes the
development of the Kundalia Irrigation Project (KIP), which is a pressurized pipeline distribution
system for 1, 30,690 hectares (ha) cultivable command area (CCA) and for supply of water for
potable and industrial use.
2. Government of Madhya Pradesh has received loan from Asian Development Bank for
implementation of the Project. The Water Resource Department (WRD) of Madhya Pradesh is
the Implementing Agency (IA) for the Project. Presently L&T Construction as a DBO Contractor
has been engaged for construction and to manage the scheme operation and maintenance for
an initial period of 5 years, with support to hand-over the long term management to a joint
management organization comprised of WRD, a private contractor, and a project-level Water
User Association (WUA).
3. In compliance with the applicable Government of India, State Government legal and
policy framework and ADB SPS 2009, a Land Acquisition and Resettlement Plan (LARP) for this
subproject covering Distribution Pipeline and Outlet Management Syatem (OMS) of Zone 3 of
Left Bank is prepared as per the detailed design. The LARP also complies with the Land
Acquisition Framework (LAF) for the project agreed between WRD and ADB.This subproject is
considered as Category-B as per Involuntary Resettlement (IR) categorization is concerned.
4. The objective of this LARP is to assist the affected people to improve, or at least restore
their living standards to the pre-project level. The document describes the magnitude of impact,
mitigation measures proposed, method of valuation of land, structure and other assets, eligibility
criteria for availing benefits, baseline socio-economic characteristics, entitlements based on
type of losses and tenure, the institutional arrangement for delivering the entitlements and
mechanism for resolving grievances and monitoring.
B. Scope of Land Acquisition
5. There will be Outlet Management System (OMS) of 235 outlets of 1X2 Meter each and
distribution pipelines ranging from Diameter 400 mm to 1700 mm, to be laid in 12 Villages of
Tehsil Nalkheda of District Agar Malwa.For laying of underground distribution pipelines there will
be involvement of only temporary acquisition of land.
6. The Distribution Pipeline of different Diameters will be laid in 12 affected Villages for
which 5.777 ha of private land and 0.737 ha of Government land needs to be acquired
temporarily till the laying of the underground pipelines for a maximum duration of 6 months.
7. For construction of all the above components of the subproject of Zone 3, there will be
total requirement of 6.561 Ha of land which includes 5.824 ha of private land and 0.737 ha of
6
Government land. For construction of permanent structures of 235 OMS, 0.047 ha of private
land will be acquired permanently.
C. Land Acquisition Impacts
8. The land requirement for all the temporary and permanent structures of this subproject,
land has been divided into two categories, that is private land of 5.824 ha and 0.737 ha of
Government Land. The OMS of 235 outlets may require 0.047 ha of land permanently.
Therefore total requirement of private and government land will be 6.561 ha for this subproject.
9. The land will be acquired temporarily as per the provisions of Pipeline Act 2013 of
GOMP for the alignment of the pipeline. But for permanent acquisition of land, it will be as per
Consent Land Purchase Policy’ 2013 of the State. In case of failure of negotiations, the land will
be acquired as per the provisions of RFCTLARR Act 2013. In case of any negotiated
settlement, an independent external party engaged by the EA, namely Prof. Vivek Bhatt of
Water & Land Management Institute (WALMI) will document the negotiations and settlement
processes as per ADB norms.
10. There are 403 affected households comprising a population of 2347 APs in all the 12
Villages. Among other impacts, there is 1 timber tree, 3 other fruit bearing trees and parts of
some standing orchard trees are also being impacted which have been divided in three
categories for paying compensation to AHs. However, the above impacts will be permanent for
which compensation will be paid for the loss incurred to them.
11. There is no Community Property Resources (CPR) being affected in this subproject.
There are mainly bushes found on the impacted government land due to scarcity of water in the
area. There are no informal settlers found living or cultivating land in the subproject area. The
Summary of impacts on the properties is presented in the following Table No. 1 which indicates
that there is no significant impact on land and livelihood of the AHs due to temporary acquisition
of land:--
Table 1 : Summary of Impacts on Properties
S. No.
Type of Impact AHs APs
Type of Ownership
of Land
Land Acquis
(Ha)
Physically Displaced Yes / No
Significance of Impact
1 Temporary
403
2347 Private Revenue
5.777
No
Insignificant Impact less than
10% on the properties of AHs
2 Temporary 0 0 Government Land
0.737 No -------
2 Permanent (235 OMS)
- - Private Revenue
0.047 No
Insignificant Impact less than
10% on the properties of AHs
Total 403 2347 6.561
7
D. Consultations with DPs and their Participation
12. Aside from direct consultations with DHs / DPs during socio-economic survey, Group
Consultations were held in 11 impacted Villages in 3 phases. All relevant aspects of project
designs, details of impact to their private properties were physically assessed and discussed
with the stakeholders and affected communities. In all 402 persons (69 females and 333 males)
participated in the group consultations, held in 11 Villages of Nalkheda Tehsil on 13th
November’2018, 14th to 16th April’ 2019 and 24thto 26th June’ 2019. The Elected People’s Representatives of the affected areas also took part in these group consultations.
13. The affected population is very much concerned about the early completion of the
project looking to the long term benefits of this project. Information will be disseminated to APs
at various stages. Information including magnitude of loss, detailed asset valuations,
entitlements and special provisions, grievance procedures, timing of payments, Civil works
schedule was discussed and LAP will be disclosed during project implementation. This will be
done through public consultations and made available to APs as brochures, leaflets, or booklets
in Hindi being the local language. The Hindi version of a summary of LAP along with Entitlement
Matrix and structure and process of grievance redressal will be disclosed.
E. Legal Framework
14. The legal framework and principles adopted for addressing land acquisition and
resettlement issues in the Project have been guided by the existing legislation and policies of
the GOI, the Government of Madhya Pradesh, Asian Development Bank and the Land
Acquisition Framework (LAF) adopted for the project. Prior to the preparation of the LARP, a
detailed analysis of the existing national and state policies was undertaken and a RF has been
prepared for the entire program. This subproject LARP is prepared based on the review and
analysis of all applicable legal and policy frameworks of the Country and ADB Policy
requirements. The gaps between the Polices have been identified and addressed to ensure that
the LARP adheres to the SPS (2009) requirements. All compensation and other assistances will
be paid to all DPs prior to their physical / economic displacement.
15. The State Government of Madhya Pradesh has come up with a “Consent Land Purchase Policy’ 2013 for direct purchase of land through negotiations. In case of failure of any
negotiations, the permanent land acquisition in this subproject context will be according to the
process and provisions of RFCTLARR Act’2013. Since the land may be acquired compulsorily if
the negotiations of the Consent Land Purchase Policy fail so the Safeguard Requirement 2 of
ADB SPS 2009 will be applicable for all the provisions to be implemented in this subproject.
F. Entitlements, Assistance and Benefits
16. In case of land acquisition, the date of publication of preliminary notification for
acquisition under section Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (RFCT in LARR Act – 2013) will be treated as the
cut-off date. For non-titleholders, the cut-off date will be the end of the census survey which is
8
30th June’ 2019. Land and structures affected under the subproject will be compensated at
replacement cost. DPs who settle in the affected areas after the cut-off date will not be eligible
for any compensation. They, however, will be given sufficient advance notice and requested to
vacate premises and dismantle affected structure, if any, prior to subproject implementation.
17. The EA will provide adequate and appropriate replacement of land and structures or
cash compensation at full replacement cost for lost land and structures, adequate compensation
for partially damaged structures, and relocation assistance, according to the Entitlement Matrix.
The EA will compensate to the non-title holders for the loss of assets other than land, such as
dwellings, and also for other improvements to the land, at full replacement cost. Besides
payment of compensation amount, the entitled DHs will be given Rehabilitation Assistance and
Grants for Skill development of their wards if there is permanent and significant impact on their
properties. The entitlements to the non-titleholders will be given only if they occupied the land or
structures in the subproject area prior to the cut-off date.
G. Land Acquisition Budget and Financing Plan
18. The WRD will make funds available as required to cover all compensation, resettlement
assistance cost and grant for skill upgradation from its budgetary provisions. The proposed
budget rates, as well as the costs, are based on field level information and experience in
resettlement management. The cost estimates for the implementation of LAP for this subproject
is Rs. 4.91 Million.
H. Grievance Redress Mechanism
19. During implementation of LARP of the Project as a whole, some grievances may arise
so there is always a need of some mechanism to redress the grievances of the affected
population. Therefore a project level combined GRM is in place for addressing social,
environmental and project related grievances. The GRC has been formed vide order dated
24.10.2019. Other than disputes relating to ownership rights and apportionment issues on which
the LARR Authority has jurisdiction, the GRC reviews grievances involving all resettlement
benefits, relocation and payment of assistances. No grievance has been received by GRC till
date.
I. Institutional Arrangement
20. The Executing Agency (EA) for the Project is the Ministry of Water Resources,
Government of Madhya Pradesh, and the Implementing Agency (IA) is Water Resources
Department, GOMP. The PMU was established at Rajgarh and remains functional since
16.04.2018 and shall remain functional for the whole subproject duration. The existing Camp
Office at Zeerapur Tehsil Head Quarter has already been established which is the Project
Implementation Unit (PIU). This office will be functional for the whole Subproject duration.
9
J. Implementation Schedule
21. The time for implementation of LARP will be scheduled as per the overall subproject
implementation. After the detailed design completed, requirement of updating of LARP will be
checked by L&T Constructions. If updated LARP is required, the approval from the EA should
be obtained prior paying compensation to the affected people. The contractor will pay
compensations for all temporary land acquisition but EA will pay the compensation for
permanent acquisition of impacted land. The commencement of work will only be undertaken on
the lands and properties, where compensations have been fully paid.
K. Monitoring and Reporting
22. Land Acquisition and Resettlement Plan (LARP) implementation for the subproject will
be closely monitored by the EA, which is Water Resources Department of GOMP. Keeping in
view the significance of resettlement impacts of the overall project, the monitoring mechanism
for this project will have monitoring by Project Management Unit (PMU) / PIU and monitoring by
an external resettlement expert. The position of resettlement expert has been advertised and
sufficient numbers of EOI have been received. PMU will be responsible for overall supervision
and implementation of the LARP. PIU will prepare monthly progress reports on resettlement
activities and submit to PMU. The Project Management Unit (PMU) of MPWRD will submit semi-
annual reports to ADB.
10
II. PROJECT DESCRIPTION
A. Introduction
23. Madhya Pradesh Irrigation Efficiency Improvement Project (MPIEIP) is intended to
achieve high irrigation efficiency and water productivity in the State. The MPIEP includes the
development of the Kundalia Irrigation Project (KIP), which is a pressurized pipeline distribution
system for 1, 30,690 hectares (ha) cultivable command area (CCA) and for supply of water for
potable and industrial use.
24. Government of Madhya Pradesh has received loan from Asian Development Bank for
implementation of the Project. The Water Resource Department (WRD) of Madhya Pradesh is
the Implementing Agency (IA) for the Project.Presently L&T Construction as a DBO Contractor
has been engaged for construction and to manage the scheme operation and for maintenance
for an initial period of 5 years, with support to hand-over the long term management to a joint
management organization comprised of WRD, a private contractor, and a project-level Water
User Association (WUA).
25. The main pumping stations will be located at the end of concrete-lined approach
channels constructed on the left bank of the reservoir. The DCs are proposed on the nearby
hills and the water from pumping stations will be pumped through raising mains (pipelines) to
the DCs. Water will be discharged from DCs through pressurized secondary pipelines to the
designated command areas. All pipelines under this Project will be underground only. The total
area to be irrigated by Kundalia Pipeline Irrigation Project will be 1,30,690 ha of agriculture land
in Agar Malwa and Rajgarh District of Madhya Pradesh. Out of the proposed land to be
irrigated, there will be a CCA 63548 ha of land from the Left Bank in Agar Malwa District.
26. This Land Acquisition and Resettlement Plan has been prepared for one of the
subproject of Zone 3 of Left Bank of Kundalia Irrigation Project which comprises of Pipeline
Distribution System to be passing through 12 Villages in Tehsil Nalkheda of District Agar Malwa
and 235 OMS of 1 X 2 Meter each. The components of this subproject, proposed to be
constructed are depicted in the following Figure: 1 and described in Table No. 2:
11
Figure 1: Schematic of Kundalia Irrigation Project Left Bank
Table 2: Details of Components of the Subproject
COMPONENTS OF THE SUBPROJECT DETAILS OF THE SUBPROJECT
235 Outlet Management System of
1 Meter X 2 Meter Each
235 OMS will require 0.047 ha of land
permanently. Each OMS will be constructed in
between a Block of Land of 30 Ha of land.
Distribution Pipeline System-
417 Meters of Pipeline - Diameter 1100 mm
3728 Meters of Pipeline - Diameter 1000 mm
946 Meters of Pipeline - Diameter 900 mm
3876 Meters of Pipeline - Diameter 800 mm
1350 Meters of Pipeline - Diameter 700 mm
2334 Meters of Pipeline - Diameter 600 mm
977 Meters of Pipeline - Diameter 500 mm
4415 Meters of Pipeline -Diameter 450 mm
18298 Meters of Pipeline-Diameter 400 mm
The Underground Distribution Pipelines of
different diameters ranging from 400 mm to 1700
mm will be passing through an area of 6.514 ha
of land. These Distribution Pipelines will be
passing through the Land Holdings of 403 DHs
and 2347 DPs, in 12 Villages of Tehsil Nalkheda
of Distt. Agar Malwa.
12
27. In compliance with the applicable Government of India, State Government and ADB
legal and policy framework, a Land Acquisition and Resettlement Plan (LARP) for these above
mentioned components is prepared as per its detailed design. The LARP also comply with the
Land Acquisition Framework (LAF) for the Project agreed between WRD and ADB. This
subproject is considered as Category-B as per Involuntary Resettlement (IR) categorization is
concerned.
B. General Profile of the Subproject Area
28. The subproject area lies in 12 Villages in Nalkheda Tehsil of Agar Malwa District. Agar
Malwa District became the 51st District of Madhya Pradesh on 16 August 2013. It was carved
out of the existing Shajapur District. Agar town is its administrative headquarters Agar Malwa
District has two Sub Divisions, Agar Malwa Division and Susner Division. There are four Tehsils
that is Agar Malwa, Badod, Susner and Nalkheda in Agar Malwa District.
29. The total population of Agar is 5, 71,278 out of which 2, 93,052 are males and 2, 78,226
are females. As per the Census 2011, the literacy rate of Agar is 80.3%. Thus Agar has higher
literacy rate compared to 69.1% of Shajapur District. The male literacy rate is 87.8% and the
female literacy rate is 72.31% in Agar. There is Schedule Caste (SC) constitutes 13.8% while
Schedule Tribe (ST) are only 1.3% of the total population in Agar Malwa.
C. Subproject Impacts and Benefits
30. At the moment the area is suffering acute shortage of water for irrigation and drininking
purposes. The proposed pressurized pipeline will give long-term benefits of irrigation to the local
population of the area. Once the project is completed they will be able to take two crops in a
year, which will improve their economic condition. This subproject has many positive impacts on
the local population of the area which will be benefitted immensely by this upcoming project.
31. Due to availability of water they will have an increased irrigation potential. The irrigation
will be through underground-pressurized distribution pipelines so there will not be any
evaporation of water and that may prove to be a low maintenance scheme of irrigation. Once
the benefitted population will be able to take two crops in a year they will have better living
standards. Due to sustained availability of water there will be increased green cover in the area.
The increased green cover in the area will help in conservation of the forest.
32. The Subproject area is mainly dependent on farming and therefore with the availability of
irrigation facilities in the area the yield of the crop will be doubled and the quality of the grains
will also improve. To sell the surplus grains there will be improved market facilities in the area.
The availability of better marketing facilities in the adjoining areas will improve their economic
condition resulting into better life style, status and in confidence building.
33. The proposed subproject can be viewed as boosting economic growth and poverty
reduction which will bring substantial social and economic development in the region. The social
benefits arising due to the subproject will be triggered off to improved irrigation potential and
better market facilities, which will also open up wider work and opportunities for increased
13
frequency of interaction with outsiders. This will increase the awareness level of the people in
the villages with regard to their health and nutrition, lesser rate of mortality, value of education
and proper utilization of available resources.
34. Due to their exposure with adjoining developed areas and interaction with the
government, non-government and other development agents will help people to gain new
knowledge on improved farming, land development, development and maintenance of natural
resources through the formation of various economic and social development groups. All these
developments in the area will open new horizons of their economic development and confidence
building not only for them but even for the next generations.
D. Minimizing Land Acquisition
35. Efforts have been made through appropriate project design to minimize adverse social
impacts and to reduce disruption of livelihood by avoiding any physical displacement of the
affected households. Due measures were taken to reroute the alignment of the pipeline to save
any shelters and other permanent structures in the impacted area. Under the subproject, land
acquisition of private land will be there because of laying of Distribution Pipeline and
construction of 235 OMS. But the significance of the impact on their properties and livelihood
will be less than 10% as indicated in the following Table No. 6 regarding Significance of impact.
36. The 235 Outlet Management System of 1X2 M each, will be permanent structures so a
minimal 0.047 ha of land will be acquired permanently. The Outlet Management System will be
constructed in between a Chak (Block of Land) of 30 Ha of land. Therefore, there will be total
need of 0.047 ha of private land to be acquired for 235 outlet management system.
37. There will be alignment of Distribution Pipeline net work of different diameters of pipes to
be laid underground ranging from 1700 mm, 1600 mm, 1500 mm, 1400 mm, 1300 mm, 900
mm, 800 mm, 700 mm, 600 mm, 500 mm, 450 mm and 400 mm. The impacted lands of these
AHs will be acquired temporarily for a maximum period of 6 months for laying of these
underground pipelines.
38. There will be only temporary impact on the properties of 403 AHs as 5.777 ha of private
land and 0.737 ha of Government land will be impacted. During construction period the
temporarily AHs will get double crop compensation as well as 15% cost of the impacted land as
per the Pipeline Act of the State. Once the construction work is over the temporarily impacted
land will be brought back to its pre project scenario and handed over to the AHs.
E. Scope and Objectives of Preparation of Land Acquisition and Resettlement Plan (LARP)
39. The objective of this LARP is to assist the affected people to improve, if possible, or at
least restore their living standards to the pre-project level. The document describes the
magnitude of impact, mitigation measures proposed, method of valuation of land, structure and
other assets, eligibility criteria for availing benefits, baseline socio-economic characteristics,
14
entitlements based on type of losses and tenure, the institutional arrangement for delivering the
entitlements and mechanism for resolving grievances and monitoring.
40. Implementation of the Subproject will involve total land acquisition of 6.561 ha of land in
which there will be 5.824 Ha of Private Land of 403 households and 0.737 ha of Government
Land. Because for Laying of underground distribution pipeline, there will be only temporary
acquisition of land.This LARP has been prepared on the basis of subproject census and
socioeconomic survey findings and in consultation with various AHs and DPs.
41. The LARP comply with ADB Safeguard Policy Statement-2009 designed by ADB to
protect the rights of the affected persons and communities. The issues identified and addressed
in this document are as follows:-
(a) Type and extent of loss of land / non-land assets, loss of livelihood, loss of common property resources and social infrastructure;
(b) Impacts on vulnerable groups like poor, women and other disadvantaged sections of society including non-title holder DPs,
(c) Public consultation and peoples participation in the subproject; (d) Existing legal and administrative framework and formulation of resettlement (e) Preparation of entitlement matrix, formulation of relocation strategy and
restoration of businesses / income; (f) R&R cost estimate including provision for fund and; (g) Institutional framework for the implementation of the plan, including grievance
redress mechanism, monitoring & reporting.
F. Methodology adopted for Socio-economic Survey
42. For preparation of LARP, Socio-economic survey was carried as 403 households
comprising a population of 2347 APs are being affected due to construction of the components
of this subproject. All the permanent structures are proposed to be constructed on private and
government land as mentioned in Table No.3 of this LARP.
43. The census survey includes the (i) Inventory of 100% losses of land and non-land
assets, (ii) Categorization and measurements of potential loss, (iii) Physical measurements of
the affected assets / structures, (iv) Identification of trees and crops, (v) Collection of information
on household characteristics, including social, economic and demographic profile.
44. In this Subproject private property of 403 households and 2347 APs in 12 Villages is
being affected so group consultations were held with stakeholders, people’s representatives,
general public, women, Government officials and the concerning Officials of L&T Construction in
11 impacted Villages in 3 phases.
45. The primary data for the study was collected through group discussion/ interviews with
the Project Affected Persons (PAPs) and peoples representative with the help of a pre-tested
and well-structured questionnaire. Important aspects covered in the questionnaire are the
identification particulars of PAPs, Family details of the respondent, assets and irrigation
facilities, details of infrastructures, land utilization, cropping pattern, commercial / self
15
employment activities, household income, expenditure, type of effects, losses and status of
women. There was extensive observation of the life and culture of the respondents while having
group consultations and Interviews with the PAFs.
46. To ensure peoples’ participation in the planning phase and aiming at promotion of public
understanding and fruitful solutions of developmental problems such as local needs of farmers
and prospects of resettlement, various sections of stakeholders were consulted through group
consultations, individual interviews, formal and informal consultations.
16
III. SCOPE OF LAND ACQUISITION AND RESETTLEMENT
A. Land Acquisition Requirement
47. The component of this subproject is of temporary nature which involves construction of
Distribution Pipelines to be laid underground in 12 Villages of Tehsil Nalkheda of District Agar
Malwa. There will be only temporary impact on the properties of 403 AHs so the private land of
5.777 ha and 0.737 ha of Government Land has to be acquired temporarily till the construction
work is completed in maximum durartion of 6 months.
48. There will be 235 OMS of 1M X 2 M which may require 0.047 ha of land which will be
acquired permanently because these 235 OMS will be permanent structures and each outlet
valve will be constructed in between a chak (Block of land) of 30 ha of land. For construction of
these 235 OMS there will be requirement of 0.047 ha of private land. The detailed land
requirements of this subproject are presented in Table: 3.
Table 3: Land Acquisition Requirements
Sl. No. Components Nature of Acquisition Area (in Ha)
1 5538 meters of 1700 mm pipelines Temporary 0.352
2 1899 meters of 1600 mm pipelines Temporary 0.087
3 1804 meters of 1500 mm pipelines Temporary 0.119
4 185 meters of 1400 mm pipelines Temporary 0.444
5 1367 meters of 1300 mm pipelines Temporary 0.463
6 4559 meters of 900 mm pipelines Temporary 0.789
7 4934 meters of 800 mm pipelines Temporary 0.821
8 3308 meters of 700 mm pipelines Temporary 0.355
9 3696 meters of 600 mm pipelines Temporary 0.052
10 1191 meters of 500 mm pipelines Temporary 0.541
11 968 meters of 450 mm pipelines Temporary 0.608
12 4398 meters of 400 mm pipelines Temporary 1.883
13 *235 Outlet Management System Permanent 0.047
Total 6.561 *235 Outlet Management System of 1m X 2m in size
17
B. Resettlement Impacts
49. There will be alignment of distribution pipelines of different diameters ranging from 400
mm to 1700 mm to be laid in 12 Villages of Tehsil Nalkheda, which will be acquired temporarily.
Therefore total requirement of private and government land for this purpose will be 6.514 ha.
The minimal land of 0.047 ha for 235 Outlet Management System has to be acquired
permanently as per the Consent Land Purchase Policy’ 2013 of Government of Madhya
Pradesh or as per the RFCTLARR Act 2013, if negotiations fails.
50. There will be impact on private agriculture land of 5.777 ha of 403 affected households
and 0.737 ha of Government land which needs to be acquired temporarily for laying of
distribution pipeline. Besides this 0.047 ha of private land will be acquired permanently for 235
outlet management system. These 403 affected households comprise a population of 2347
Affected Persons. The details of ownership and the type of land is being summarized in the
following Table: 4
Table 4: Ownership of Land Affected in the Subproject
Sl. No. Type of Ownership Household Permanent Temporary Total
(in Ha) (in Ha) (in Ha)
1 Private Revenue 403 0.047 5.777 5.824
2 Government 0 0 0.737 0.737
Total 403 0.047 6.514 6.561
C. Loss of Private Land in Subproject
51. Most of the losses are of temporary nature so may require temporary land acquisition
and the impacted properties will have to be duly compensated as per the provisions of the
Pipeline Act of the State. The land of 403 affected households and 2347 APs will be affected
temporarily. The inventory of losses of the land and other assets for each affected household
has been prepared based on the losses to be incurred to them due to construction of the
distribution pipeline in this subproject. The total land of 6.561 ha area to be impacted and its
utilization has been indicated in the following Table No.5.
Table 5: Details of Affected Persons in the Subproject
Sl. No. Type of Impacts Affected Households Affected Persons
1 Temporary Use 403 2347
Total 403 2347
18
D. Loss of Structures in the Subproject
52. There is no loss of any shelters or any permanent structures in the impacted area. There
is no impact on any other commercial land or Community Property Resources (CPR) also which
is being utilized by the local population of the affected area.
E. Loss of other Assets in the Subproject
53. Among other impacts, there are 3 Fruit bearing trees and 1 Timber Tree and some parts
of Orange Orchards trees, which have been divided in three categories. These trees will also be
permanently impacted under this subproject. These impacts are due to laying of distribution
pipeline in the impacted area. However, the impacts will be permanent for which due
compensation will be paid for the loss incurred to them. The cash compensation will be paid for
all these losses for which the inventory of the losses has been prepared based on the physical
census survey of the area.
F. Loss of Livelihood in the Subproject
54. The properties of 403 DHs are being impacted temporarily for laying of underground
distribution pipeline. After construction work is over, they get their land back in its prior
condition. Besides this, as per the provisions of Pipeline Act of GOMP for temporary acquisition
of land, they will get double crop compensation and 15% of the cost of the impacted land based
on the prevailing cost of the land as per Collector’s Guideline of the land in that area. No
physical displacement will occur of these DPs because their houses are not impacted.The
amount of compensation will give them an opportunity to develop their other properties and to
start any small scale work for income generation. Besides this, the proposed project will give
them assured irrigation benefits enabling them to have at least two crops in a year for their
economic upliftment and better standard of living.There is no significant impact on the properties
and livelihood of 403 DHs so there is no need to arrange any Skill up-gradation training for this
category of DHs. Even then, they can be encouraged to take the benefits of the ongoing skill up-
gradation training programs conducted by the State Government and GOI.
G. Significance of Impact on Land Owners
55. The analysis of significance of impact on the properties of AH’s indicates that out of total 403 affected households and 2347 affected persons, the peroperties of all 403 households are
being impated less than 10% which has been presented in the following Table No.-6.
Table 6 : Significance of Land Impact S.No. Scale of Impact Household Persons %HH
1. Insignificant Impact on the
properties of Temporary 403 AHs
which is less than 10% Impact
403
2347
100.00
Total 403 2347 100.00
19
56. The analysis of the above Table no. 6 itself indicates that there is insignificant impact,
which is less than 10% on the properties of all 403 affected households so the amount of
compensation due to the AHs is also not much. Therefore’ there is lack of interest in taking that meager amount of compensation by AH, due to the hassles of lengthy formalities of the
Government. Secondly, there may be more than 3-5 shareholders in the family for that little
amount of Compensation which includes their married sisters too. The whole procedure of
getting that amount of compensation may cost more than the amount of compensation they may
get, so the AHs don’t find it feasible to take much pains for such little amount of compensation.
In such type of cases it was decided that, the AH, if wants to forego the amount of
compensation has to sign a Memorandum of Understanding (MOU) to be documented, to
forego that amount of compensation. But before signing of the MOU by the AH, the amount of
compensation due to the AH will be informed to the respective family for them to take a rationale
decision in the matter. The Format of the MOU is at Annexure 14.
20
IV. SOCIO-ECONOMIC INFORMATION AND PROFILE
A. Census Socioeconomic Survey
57. The Census field survey enumerated all private assets / properties and common
property resources within the proposed alignment of the distribution pipeline in 12 villages
located in Nlakheda Tehsil of District Agar Malwa. For every Affected Household (AH), a pre-
tested structured questionnaire was administered during the socio-economic survey and
inventory of losses. The conducted survey recorded details of (i) identification of the Displaced
Households (DH); (ii) type, use and extent of losses of the AHs; and (iii) enumerating their
losses based on their entitlement matrix
58. In addition to recording the above information, detailed socio-economic characteristics,
including a demographic profile of members of the household, standard of living, inventory of
physical assets, vulnerability characteristics, indebtedness level, health and sanitation, and
ascertaining perceptions about project, resettlement options and compensation, was collected
from all Project Affected 403 households living in 12 villages of Nalkheda comprising a
population of 2347 Affected Persons in Tehsil Nalkheda. Details of Common Property
Resources (CPR) within the alignment were also recorded.
59. The DPs are categorized in two categories that is either temporary or permanent impact
on their properties. Out of 403 affected households, all 403 households will be temporarily
affected.The impact of loss of properties of 403 households is mainly of temporary nature which
is being acquired temporarily mainly for distribution pipeline alignment.
B. Demographic Profile of DPs
1. Sex Ratio amongst the DPs
60. In this subproject the pipeline is passing through the properties of 403 affected
households having 2347 affected persons. Therefore amongst all 403 surveyed affected
households there is 52.96% of male population and 47.04% of female population. Out of all 403
surveyed households, the males in 402 AHs are heading the family and there is only one
women headed household in these 12 affected surveyed Villages of Nalkheda Tehsil of District
Agar Malwa.
Table 7 : All Displaced Persons by Sex
Name of village Male Female Total Percentage
Bhaisoda 99 103 202 8.61
Deharigujar 34 33 67 2.85
Dharola 350 299 649 27.65
Dokapura 69 57 126 5.37
Gudrawan 120 122 242 10.31
Molyakhedi 29 25 54 2.30
21
Najarkheda 114 96 210 8.95
Nalkheda 60 54 114 4.86
Padana 148 133 281 11.97
Pheti 75 64 139 5.92
Pilwas 88 66 154 6.56
Semali 57 52 109 4.64
Total 1243 1104 2347 100.00 Percentage 52.96 47.04 100.00
2. Household by Religion
61. 403 Affected Households were also surveyed based on religion and the data analysis
indicates that there are 364 Hindu AHs comprising 90.32% of the surveyed population. There
are 27 AHs comprising 6.70% of Surveyed Households follow Muslim faith. There are 12 AHs
following Jainism. No Christian families found living in these 12 affected villages.
Table 8 : Displaced Household by Religion
Name of village Hindu Muslims Jain Total Percentage
Bhaisoda 34 0 2 36 8.93
Deharigujar 12 0 0 12 2.98
Dharola 117 0 0 117 29.03
Dokapura 10 6 1 17 4.22
Gudrawan 43 0 0 43 10.67
Molyakhedi 4 7 0 11 2.73
Najarkheda 19 5 0 24 5.96
Nalkheda 10 7 2 19 4.71
Padana 52 0 0 52 12.90
Pheti 16 2 7 25 6.20
Pilwas 27 0 0 27 6.70
Semali 20 0 0 20 4.96
Total 364 27 12 403 100.00 Percentage 90.32 6.70 2.98 100.00
3. Household by Social Group
62. The Social Category of the AHs was also judged by the socio-economic survey, which
indicates that there is majority of Other Backward Caste and General Caste population
comprising 70.72 % and 14.14% respectively of the total population in these 12 villages. The
Scheduled Caste representation is of 13.15 % and only 1.99% are belonging to ST Community
amongst these 403 affected households.
22
Table 9 : Displaced Household by Social Category
Name of village SC ST OBC General Total Percentage
Bhaisoda 1 0 32 3 36 8.93
Deharigujar 2 0 10 0 12 2.98
Dharola 34 0 74 9 117 29.03
Dokapura 0 0 12 5 17 4.22
Gudrawan 1 0 41 1 43 10.67
Molyakhedi 0 0 11 0 11 2.73
Najarkheda 5 0 10 9 24 5.96
Nalkheda 0 0 17 2 19 4.71
Padana 4 4 44 0 52 12.90
Pheti 1 4 9 11 25 6.20
Pilwas 5 0 6 16 27 6.70
Semali 0 0 19 1 20 4.96
Total 53 8 285 57 403 100.00 Percentage 13.15 1.99 70.72 14.14 100.00
4. Household by Size of Family
63. Family of size 1-5 members account for 55.83% followed by 24.07% having 6-7
members in the family. There is 10.67% of families having more than 8 or 9 Members and
9.43% families are having more than 10 Members in the family. Therefore common size of the
family is of 1-5 Members.
Table 10 : Family Size of the Household Name of village 1 to 5
Members 6 or 7
Members 8 or 9
Members Above 10 Members
Total Percentage
Bhaisoda 23 6 3 4 36 8.93
Deharigujar 6 5 0 1 12 2.98
Dharola 67 30 13 7 117 29.03
Dokapura 6 3 4 4 17 4.22
Gudrawan 24 10 6 3 43 10.67
Molyakhedi 7 4 0 0 11 2.73
Najarkheda 6 6 5 7 24 5.96
Nalkheda 9 6 2 2 19 4.71
Padana 32 13 2 5 52 12.90
Pheti 17 5 3 0 25 6.20
Pilwas 15 5 3 4 27 6.70
Semali 13 4 2 1 20 4.96
Total 225 97 43 38 403 100.00 Percentage 55.83 24.07 10.67 9.43 100.00
23
5. Age Group of DPs
64. 28.67% of DPs are in the age group of 21 years and below followed by 29.87% coming
under the age group of 22-35 years, followed by 22.67% coming under the age group of 36-50
years, 13.93% belonging to age group of 51-65 years of age and only 4.86 % of APs are more
than 65 years of age. The analysis indicates that the life expectancy in these affected villages is
still not very high due to lack of awareness regarding good health.
Table 11 : Age Group of DPs
Name of village Upto 21
Years
22 to 35
Years
36 to 50
Years
51 to 65
Years
Above 65
Years
Total Percentage
Bhaisoda 58 57 42 37 8 202 8.61
Deharigujar 29 14 11 8 5 67 2.85
Dharola 192 187 159 75 36 649 27.65
Dokapura 27 38 37 22 2 126 5.37
Gudrawan 65 84 48 33 12 242 10.31
Molyakhedi 18 14 14 5 3 54 2.30
Najarkheda 84 65 30 22 9 210 8.95
Nalkheda 24 43 17 20 10 114 4.86
Padana 68 88 69 46 10 281 11.97
Pheti 33 39 32 30 5 139 5.92
Pilwas 43 42 44 13 12 154 6.56
Semali 32 30 29 16 2 109 4.64
Total 673 701 532 327 114 2347 100.00 Percentage 28.67 29.87 22.67 13.93 4.86 100.00
C. Socio-economic Profile
1. Educational level of DPs
65. The data analysis of educational level indicates that 44.35% of APs are still not
educated, followed by 14.10% who are only primary school passed, followed by 14.96% who
are 6th to 8th Class passed, 14.83% are 9th to Class 12th passed. There are 8.86% APs who are
graduates followed by 2.90 %who are post graduates and none are Diploma Holders.
Table 12 : Educational level of DPs
Name of village
Upto 5th
6th - 8th
9th - 12th
Graduate
Post Graduat
e
Illiterate
Total Percentage
Bhaisoda 39 36 37 20 2 68 202 8.61
24
Deharigujar 8 5 2 1 0 51 67 2.85
Dharola 88 110 81 61 17 292 649 27.65
Dokapura 20 17 22 12 17 38 126 5.37
Gudrawan 29 48 30 29 2 104 242 10.31
Molyakhedi 11 8 13 2 2 18 54 2.30
Najarkheda 44 22 20 16 1 107 210 8.95
Nalkheda 22 18 35 6 6 27 114 4.86
Padana 18 36 22 3 1 201 281 11.97
Pheti 15 16 31 27 15 35 139 5.92
Pilwas 21 25 33 20 4 51 154 6.56
Semali 16 10 22 11 1 49 109 4.64
Total 331 351 348 208 68 1041 2347 100.00 Percentage 14.1
0 14.96 14.83 8.86 2.90 44.35 100.0
0
2. Occupation of DPs
66. The occupation of DP’s indicates that 22.11% are cultivators followed by 6.43% who are
agricultural laborers, 68.98% are not in any work force. 0.81% are in Government Jobs, 0.98%
are in Private Jobs and only 0.68 % are Shopkeepers. Therefore majority of population belongs
to agricultural sector either as land owner / cultivator or as agriculture laborers.
Table 13 : Occupation of DPs
Name of village
Cultivators Agricultural Laborer
Govt. Job
Private Job
Shop-keeper
Not in Workforce
Total Percentage
Bhaisoda 37 12 1 1 2 149 202 8.61
Deharigujar 15 3 0 2 0 47 67 2.85
Dharola 148 44 7 10 0 440 649 27.65
Dokapura 28 5 0 0 3 90 126 5.37
Gudrawan 72 5 3 0 0 162 242 10.31
Molyakhedi 11 4 2 0 0 37 54 2.30
Najarkheda 24 28 0 4 0 154 210 8.95
Nalkheda 21 9 2 1 2 79 114 4.86
Padana 90 12 0 3 0 176 281 11.97
Pheti 25 6 1 0 6 101 139 5.92
Pilwas 28 18 2 0 3 103 154 6.56
Semali 20 5 1 2 0 81 109 4.64
Total 519 151 19 23 16 1619 2347 100.00 Percentage 22.11 6.43 0.81 0.98 0.68 68.98 100.00
25
3. Income of Household
67. Household income of 53.35% affected population is up to Rupees Rs10,000 per month
followed by 33.50% having income of Rs 10,001 to 20,000 per month. 7.44% affected
population having monthly income as Rs 20,001 to 25,000 per month followed by 5.71% having
monthly income more than Rs. 25,000 per month.The Villagers being either illetrate or less
educated are not able to give their exact monthly income but even then they are economically in
a better condition than the AHs of Right Bank due to better yield and cost of the crops sown..
Table 14 : Monthly Household Income of DHs
Name of village
Upto 10000
10001 to 20000
20001 to 25000
Above 25000
Total Percentage
Bhaisoda 21 13 2 0 36 8.93
Deharigujar 5 6 1 0 12 2.98
Dharola 66 36 9 6 117 29.03
Dokapura 7 3 3 4 17 4.22
Gudrawan 24 14 1 4 43 10.67
Molyakhedi 9 1 1 0 11 2.73
Najarkheda 14 7 2 1 24 5.96
Nalkheda 12 5 1 1 19 4.71
Padana 30 20 0 2 52 12.90
Pheti 12 8 2 3 25 6.20
Pilwas 12 9 5 1 27 6.70
Semali 3 13 3 1 20 4.96
Total 215 135 30 23 403 100.00 Percentage 53.35 33.50 7.44 5.71 100.00
4. Impact to Vulnerable Households (mutually exclusive)
68. The vulnerable population was also assessed amongst 403 DHs. The weakest section
representing 15.14% is Below Poverty Line (BPL), there is only 1 women headed household
having represention of 0.25% found living amongst these 403 surveyed households. There is
near about 13.15% of SC population and 1.99% of Scheduled Tribe population was found
amongst these 403 AHs. The vulnerable status of AHs in the Project, which is mutually
exclusive in the order of priority as presented in the following table is given below:
Table 15 : Vulnerable (mutually exclusive)
Name of village
Women HH
BPL ST SC Not Applicable
Total Percentage
Bhaisoda 0 5 0 1 30 36 8.93
Deharigujar 0 3 0 2 7 12 2.98
Dharola 0 14 0 34 69 117 29.03
26
Dokapura 0 3 0 0 14 17 4.22
Gudrawan 0 4 0 1 38 43 10.67
Molyakhedi 0 7 0 0 4 11 2.73
Najarkheda 0 8 0 5 11 24 5.96
Nalkheda 1 5 0 0 13 19 4.71
Padana 0 2 4 4 42 52 12.90
Pheti 0 2 4 1 18 25 6.20
Pilwas 0 5 0 5 17 27 6.70
Semali 0 3 0 0 17 20 4.96
Total 1 61 8 53 280 403 100.00 Percentage 0.25 15.14 1.99 13.15 69.48 100.00
D. Key Socio-economic Indicators
69. The key socio-economic indicators established, based on the socio-economic survey
carried out in the months of March and April’ 2019 presented in the following table.The data
analysis of the socio-economic indicators represents that average monthly income of the family
in Bhaisoda Village is Rs. 9872 with 2 earners, Deharigurjar Village it is Rs. 11180 per month
with 2 earners, in Dharola Village it is Rs 12079 per month with 3 earners, in Dokapura it is Rs.
18210 with 3 earners, in Gudrawan it is 12746 with 2 earners, in Molyakhedi it is Rs.8825 with 2
earners, in Najarkheda it is Rs. 9496 with 2 earners, in Nalkheda it is Rs. 9846 with 2 earners, in
Padana it is Rs.11878 with 3 earners, in Pheti it is Rs.12950 with 3 earners, in Pilwas it is
Rs.12530 with 3 earners and in Semali it is Rs. 17708 with 3 earners.
70. In Village Bhaisoda 14 households are having separate kitchens, 35 AHs are having
Separate Toilet, 36 have separate bath, 36 have electricity, 36 have drinking water facility, 36
households have LPG Cooking Connection and no Women headed household in this Village. In
Village Deharigurjar no households have separate kitchen, 7 households have separate toilet,
12 have separate bath, 12 AHs have electricity and drinking water facility and 10 LPG Gas
Connections. In Village Dharola 46 households are having separate kitchen, 89 are having
separate toilet, 113 are having separate bath, 127 are having electricity, 117 have drinking
water facility and 112 households have LPG Connection with no Women headed household.
71. 11 households in Village Dokapura are having separate Kitchen, 17 of them have
separate toilets, 17 of them have separate bath, 17 have electricity, 17 of them have Drinking
water facility, 17 have LPG connection and no women headed household in this Village. In
Village Gudrawan 10 households are having separate kitchen, 40 have separate toilet, 42 have
separate bath, 43 of them have Electricity and Drinking water facility,39 of them have LPG
connection with no women headed household in this village. In Molyakhedi Village 8 households
have separate Kitchen, 9 have separate toilets, 11 of them have separate Bath, electricity and
drinking water facility and 10 of them have LPG connection but no women headed family was
found amongst these surveyed families. In Najarkheda surveyed village, there is 1 separate
Kitchen, 19 separate Toilet, 24 of them have separate bath, electricity and drinking water facility
27
and 21 have LPG connection with no women headed household. In Village Nalkheda 9 have
separate kitchen, 19 have separate toilet, 19 have separate bath, 19 of them have electricity
and drinking water facility, 19 have LPG connection and 1 women headed household. In Village
Padana there are 3 separate Kitchen, 45 separate toilet and 50 separate bath, 52 of them have
electricity and drinking water facility, 39 of them have LPG connection. In Village Pheti, there
are 13 separate Kitchen, 24 separate toilet, 25 separate bath, 25 of them have electricity and
drinking water facility, 24 have LPG connection.
72. In Pilwas Village, there are 7 separate kitchen, 24 separate Toilet, 27 separate bath and
27 have the facility of electricity, drinking water and LPG connection. In Village Semali, there are
3 separate kitchen, 20 separate toilet, bath, electricity, drinking water facility and LPG
connection. The analysis of the data indicates that there is awareness about having separate
kitchens, separate toilets and separate bath in their houses. They have electricity and drinking
water facility. 374 households have LPG Cooking Medium in their house, which is making their
life much easier than before. This habit of cooking on LPG is helping in the conseravtion of our
valuable forest though there is not much wood available in the area due to scarcity of water in
these 12 impacted and other adjoining villages of this area.
Table 16 : Key Socio-economic Indicators
Name of village
Monthly
Family Income
Number of
Earners
Permanent
Having Sepa rate
Kitchen
Having Sepa rate
Toilet
Having Sepa rate Bath
Having Electri
city
DrinkingWater HSC
LPG for
Cooking
Family Size
WomenHHs
Total
Bhaisoda 9872 2 1 14 35 36 36 36 36 5.61 0 10073.6
Deharigujar 11180 2 1 0 7 12 12 12 10 5.58 0 11241.6
Dharola 12079 3 1 46 89 113 127 117 112 5.55 0 12692.5
Dokapura 18210 3 1 11 17 17 17 17 17 7.41 0 18317.4
Gudrawan 12746 2 1 10 40 42 43 43 39 5.63 0 12971.6
Molyakhedi 8825 2 1 8 9 11 11 11 10 4.91 0 8892.91
Najarkheda 9496 2 1 1 19 24 24 24 21 8.75 0 9620.75
Nalkheda 9846 2 1 9 19 19 19 19 19 6.00 1 9960
Padana 11878 3 1 3 45 50 52 52 39 5.40 0 12128.4
Pheti 12950 3 1 13 24 25 25 25 24 5.56 0 13095.6
Pilwas 12530 3 1 7 24 27 27 27 27 5.70 0 12678.7
Semali 17708 3 1 3 20 20 20 20 20 5.45 0 17820.5
Total 147320 30 12 125 348 396 413 403 374 71.56 1 149494
28
V. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
A. Public Consultations
73. In order to engage with the community and enhance public understanding about the
Project and address the concerns and issues pertaining to compensation, rehabilitation and
resettlement, individual interviews and meetings were undertaken amongst the various sections
ofstakeholders and people’s representative. The consultations with the APs and other
stakeholders will continue throughout the LARP preparation and its implementation period.
B. Methods of Consultation
74. Consultations and discussions were held during socio-economic survey period with both
primary and secondary stakeholders. The primary stakeholders include Project AHs / APs,
project beneficiaries and implementing agency (MPWRD). The secondary stakeholder includes
revenue officers and elected representatives of the local bodies.
75. During the socio-economic survey, Direct Consultations were held with the AHs, APs,
Officials of District Administration, Officials of PIU (MPWRD) and Elected Members of the Local
Panchayats. The elected representatives of local bodies were also consulted regarding the
perception of the Project.
Table 17: Consultation Methods
Stakeholders
Consultation Methods
Affected Persons / Affected Households
Direct and Group Consultations
Local Communities
Group Consultations
Local Elected Members
Individual interview, discussions
Concerned Officials from Government
Individual meeting /interviews, discussions
Stake Holders and General Public
Consultation Meetings
29
76. In addition to the web disclosure of the draft LARP, detailed consultations regarding the
extent of IR impact if any and the mitigation measures proposed in the draft LARP will be
disclosed to the APs and general public through public meetings held along the project. The
LARP disclosure meetings will be held to explain the contents and provisions of the Draft LARP
and obtain the feedback, suggestions and objections, if any, on the draft LARP and accordingly
make suitable amendments/corrections before finalizing the LARP.
77. All relevant aspects of project design, details of impact to private properties were
discussed with local communities in11 Villages of Tehsil Nalkheda on 13th November’2018, 14th
April to 16th April’ 2019 and from 24th and 26th June’2019. A total of 402 persons (69 females
and 333 males) participated in the consultations in these 11 Villages.The date, venue, number
of participants village wise and the photographs are provided below. The issues and concerns
raised during the consultations are summarized and provided in the following table:
Table 18: Consultation Locations
Location of villages
Nalkheda Tehsil, District Agar Malwa
Date Number of
Male
Participants
Number of
Female
Participants
Molyakhedi, Teh. Nalkheda, Distt. Agar Malwa 13.11.2018 67 13
Dehari Gurjar, Teh.Nalkheda, Distt.Agar Malwa 13.11.2018 26 0
Dharola, Teh. Nalkheda, Distt. Agar Malwa 14.04.2019 35 8
Dokapura, Teh. Nalkheda, Distt. Agar Malwa 14.04.2019 30 9
Gudrawan, Teh. Nalkheda, District Agar Malwa 15.04.2019 25 7
Pilwas, Teh. Nalkheda, District Agar Malwa 15.04.2019 29 4
Padana, Teh. Nalkheda, Distt. Agar Malwa 16.04.2019 38 7
Bhaisoda, Teh. Nalkheda, Distt. Agar Malwa 24.06.2019 24 8
Nalkheda, Teh. Nalkheda, Distt. Agar Malwa 25.06.2019 21 7
Semali, Teh. Nalkheda, Distt. Agar Malwa 25.06.2019 18 6
Najarkheda, Teh. Nalkheda, Distt. Agar Malwa 26.06.2019 20 0
Total 11 Villages Male 333+Female 69 = 402 -- 333 69
30
Consultations with Villagers and People’s Representative
C. Outcome of the Consultations
78. The consultations were held with the Affected Households, Affected Persons, General
Public and the People’s Representatives in 11 Villages to provide information about the
proposed Project activities and expected impacts of the project and their concerns about the
upcoming project. Other key stakeholders include representatives of Government Entities
involved in the planning, design, implementation and operation of the Project, which includes
PIU (MPWRD) and Revenue Department of Government of Madhya Pradesh.
79. During Consultations the Officials of PIU and Engineers of L&T Constructions explained
them the technical aspects of the Project and Resettlement Specialist discussed with them, their
entitlements matrix as per the applicable policies of the State, RFCTLARRA’ 2013 and SPS 2009 of Asian Development Bank (ADB).The affected population was informed about the
inventory of their 100% losses being taken into account by the Census and Socio-economic
survey team. Therefore the affected population was requested that they should give full co-
operation in giving all the details of their properties and their family to the survey team so that
their rights and privileges can be taken care of as per their entitlement matrix.
80. Affected families and General Public of Village Molyakhedi were gathered in large
number in the leadership of their, the then Legislator Murlidhar Patidar and informed that they
are already taking two crops of Wheat, Soyabean, Gram and other pulses.in a year by lift
31
irrigation from Lakhundar River. For this lift irrigation they have laid their personal pipes from
River Lakhundar to their agricultural fields. They wanted an assurance from the Company that
their pipeline should not be damaged while digging of the pipeline of the project. They also
demanded that after digging the trench for Laying of the pipeline it should be filled properly in
which the stone should go below and soil should come on top so that the impacted piece of land
becomes cultivable again. The AHs were assured that their demands will be taken care of by
the Company at the time of Laying of the pipeline. This Village has its own importance because
it is impacted at the time of Laying of the rising main as well as during the alignment of other
distribution pipelines. The residents of this Village have lots of Orange Orchards and they have
very good yield from these Orchards so they wanted that their Orange Orchards should be
saved and if they need to be impacted then they should get enough compensation. The people
were informed that they will get compensation of their impacted trees whether they are fruit
bearing trees or other type of tres. The Villagers are very well aware of the benefits of the
project as well as about their rights and priveleges.
81. There are near about 100 houses in the Village Dehari Gurjar. There is majority of Gurjar
population that’s why the Village is called Dehari Gurjar.They also informed that there is a Stop
Dam at Village Lakhundar so take the benefit of lift irrigation by their own pipeline system. The
Kundalia Dam constructed on Kalisindh River is also only 2 Km away from the Village. There is
only one Primary School in the Village and teachers come from outside and teach.These
Villagers are also keen that their personal pipeline should be saved at the time of construction
activities. Because the project benefits will be accrued permanently after 3 years so till then their
source of irrigation should be taken care of. The company assured to take care of the situation.
82. In Dharola Village there will be alignment of distribution pipeline causing temporary
impact on their properties. The AHs said that in Orange Orchards, if the trees come in the
alignment of the pipeline then they will be cut causing permanent loss to them. The Villagers
said that they plant the orange trees at a width of 16 feet in between two rows of the orange
trees. Therefore due efforts should be made that the alignment of the pipeline should be in such
a way that it should not damage their trees because there is enough space in between the two
rows of the trees. The crops grown in the area are Wheat, Soyabean, Masoor and Chana
Pulses as well as Onions as a cash crop. People’s representatives were also involved in public consultations and their perception about the proposed project was taken at length. The Group
Consultation was conducted in Dharola Village in which elders of the Village and other People’s Representative also took active part in the discussions.
83. The consultations were held in Village Gudrawan in which there is mixed population of
Patidars, Carpenters and Harijans. Devilal Harijan of the Village informed that Distribution
Pipeline is passing through this village. Padana Village is also affected in Zone 3 of this Project
in which there is Female Sarpanch Sugan Bai. Knahaiyalal Patidar informed that there is a
mixed population of OBC Sondhia Thakur, Patidars and some families of ST Bhil Thakur. The
Villagers of Dhokpura are very hopeful that upcoming irrigation project will bring manifold
benefits in their area. Consultations were held in Village Najarkheda in which there is alignment
of distribution pipeline causing only temporary impact for a period of 6 months on their
32
properties. There are also many orange orchards in the area and people want that their orange
trees should not be cut and instead efforts should be made to save the fruit giving trees..
84. The Consultations were held with the people of Nalkheda in which 1 Women Headed
Household was found. There is near about 5500 population in Village Bhaisoda. Patidar
Community is in Majority and Beeram Malviya is the Sarpanch in this Village. There is a big
temple on the main road of the Village so people sit there and have religious and social talks
there.It is a source of recreation for them too.The people of the Villages were requested to give
full co-operation to the survey team for their proper socio economic survey and prepartion of
inventory of their losses which will be for their betterment in future. Since there is a positive
atmosphere regarding the project so people are willing to render their full co-operation at any
level of the project so that the benefits of the project are accrued to them at the earliest.
85. People were informed about their entitlement matrix during consultations and interviews
conducted in 11 affected villages. The interviews were conducted by the Resettlement
Specialist who made the affected population aware about the upcoming Kundalia Irrigation
Project and their entitlements as per the Pipeline Act of the State due to temporary acquisition
of their land. The local population is very well aware about the project and are more than willing
to render their 100% co-operation during implementation of the project as they know very well
about the forthcoming benefits of the project.
86. The community consultations indicated that local population had been suffering acute
shortage of water for drinking and irrigation purposes. Due to shortage of irrigation facilities,
they are not able to take two crops in a year and the crop yields are also not up to their
expectations. These factors have been the root cause of their low standard of living. The
upcoming Project will open new horizons for them when they will be able to take two good yield
crops every year. The proposed Project will not only improve the standard of living of the APs
but it will be a source of bringing over all development of the population living in the adjoining
areas also.
87. Consultations and participation with primary stakeholders will further be held in future to
ensure their understanding about the potential impacts of the Project on their livelihoods. To
understand the perception and attitude of the people about the Project, detailed interviews, and
group discussions have been developed and will be conducted by the Safeguard Resettlement
Specialist with stakeholders in future implementation of the Project. This will bring very fruitful
results when stakeholders will feel involved from the origination of the Project and even
throughout the implementing stage. They will consider themselves to be a part of the proposed
Project resulting into their 100% cooperation in its implementation. Their full-fledged cooperation
will enhance the speed of the implementation of the Project.
33
Table 19 : Summary of the Consultation Outcome
Issues Discussions / Suggestion Mitigation Measures Proposed
Prior Notice regarding construction work to be given to the Affected Population
The AP’s should be given prior notice before taking up the Construction Work of the Subproject.
APs will be given prior information at least 60 days before starting the construction work. Due precautions will be taken so that no harm is caused to the affected and the local population residing in the area..
Benefits should be extended to the affected population as per their entitlement.
Planning should be made in such a manner so that the Local population should be benefited by the Project.
It will be ensured that the affected population is given priority in extending the benefits of the proposed project as per their entitlement matrix.
Local Labor should be given preference in the construction work.
The local labor should be engaged / employed in the Project related activities.
It will be ensured that the affected population is given preference in hiring of casual labor for construction work undertaken by the Contractor.
Home privacy, routine activities and safety of Women should be taken care of.
Home privacy, routine activities, safety and security of women should not be disturbed due to construction of the project.
Due measures will be taken to ensure that the privacy of women and girls should not be disturbed due to the construction of the Project. The Company will take due precautions in this regard.
Though their lands will be temporarily acquired for the project work but prior information should be given to them before taking possession of the said land.
Despite the temporary impacts on their properties, prior information should be given before commencement of the work so that DPs can harvest their crops before being damaged.
The APs will be informed at least 60 days before taking up the construction work in the agriculture fields so that they can harvest their crops if they are reaped. They will be given all the information regarding the impacts and benefits of the proposed project.
Construction work should be undertaken with due precautions to save their personal pipelines of lifting water for irrigation purposes till the completion of KIP.
In some of the Villages the villagers have their personal pipelines which they have been using for lift irrigation purposes which should not be damaged when the distribution pipelines of KIP will be laid.
The Villagers were assured that due care will be taken during construction activities so that their personal pipelines of lift irrigation are not being damaged.
Due care should be taken while filling up the trenches after laying of the pipeline
Villagers suggested that while filling up the trenches, the stones should go deep inside and soil comes on top so that the impacted strip of land becomes cultivable again.
The Villagers were assured that while refilling of the dug trenches, due care will be taken that the stone will be put in the down layer and soil is filled in the upper layer enabling the strip of the impacted land cultivable again.
Construction work should be undertaken with due precautions to save their pipelines of lift irrigation till the completion of KIP
In some of the Villages the villagers have their personal pipelines which they have been using for lift irrigation purposes which should not be damaged when the distribution pipelines of KIP will be laid.
The Villagers were assured that due care will be taken during construction activities so that their personal pipelines of lifting the water for irrigation purposes are not being damaged.
34
D. Conclusions of the Group Consultations
88. From both direct and group consultations, it is noted that people are well aware about
the upcoming Project as various surveys have been going on and the news is spread by word of
mouth from each other. Despite this they were not aware of the extent of manifold benefits
proposed and the likely impacts of the Project on the local population. In this Project there is
mainly temporary impact on their properties and when the construction activities are over their
land will be brought back to its pre project condition. Therefore the stakeholders are well aware
of the fact that they will have some teething problems in the transition phase which is nothing in
comparison to the benefits they will get from the Project. There is no resistance found amongst
the affected population and the general public regarding the implementation of the Project
instead there is great acceptance of the upcoming project.
89. The Consultations held with stakeholders in three phases indicate that the stake holders
are very supportive about the Project and are more than willing to undergo the impact on their
properties for long-term benefits to be accrued by them through the KIP. The local population is
very well aware of the benefits of the proposed project and are willing to render their 100%
cooperation in the implementation of the project.
E. Plan for further Consultation in the Project
90. The effectiveness of the R&R program is directly related to the degree of continuing
involvement of those affected by the Subproject. Several additional rounds of consultations with
APs will form part of the further stages of subproject preparation and implementation. The
implementing Resettlement Specialist will be entrusted with the task of conducting these
consultations during LARP implementation, which will involve disclosure on compensation,
assistance options, and entitlement package and income restoration measures suggested for
the subproject. The consultation will continue throughout the subproject implementation period.
The following set of activities will be undertaken for effective implementation of the LARP:
(a) In case of any change in engineering alignment planning the APs and other stakeholders will be consulted in selection of pipe alignment for minimization of resettlement impacts, development of mitigation measures etc.
(b) Together with the Resettlement Specialist, the PIU will conduct information dissemination sessions in the subproject area and solicit the help of the local community/ leaders and encourage the participation of the AP’s in Plan implementation.
(c) During the implementation of LARP, Resettlement Specialist will organize public meetings, and will appraise the communities about the progress in the implementation of subproject works, including awareness regarding pipeline laying as per the proposed alignment and other construction works.
(d) Consultation and focus group discussions will be conducted with the vulnerable groups like Women, OBC, SC and ST population to ensure that the vulnerable groups understand the process and their needs are specifically taken into consideration.
(e) To make reasonable representation of Women in the subproject planning and implementation they will be specifically involved in consultation process.
35
91. A Public Consultation and Disclosure Plan will be prepared by the PIU / Resettlement
Specialist for the smooth and speedy implementation of the Subproject in the following format
as mentioned below:
Table 20: Format for Public Consultation and Disclosure Plan
Proposed Activity
Task Assigned Responsible
Agencies
Public Notification
Notify eligibility cut-off date for Major Sons
PIU
Disclosure of LAP Translate LAP in Hindi and disclose at PIU Office and Village Council
PIU
Distribution of R&R information leaflet
Prepare R&R information leaflet and distribute to Aps
PIU
Internet disclosure of the LAP / RP
Post LAP / RP on ADB and / or EA website
ADB/PIU
Consultative meetings during joint measurement survey
Face to face meetings with APs
PIU
Disclosure of updated LAP / RP
Disclosure after joint measurement survey
PIU
Internet disclosure of the updated LAP
Updated LAP posted on ADB and/or EA website
ADB/PIU
F. Information Disclosure
92. The EA will provide relevant LARP information, including information from the above
mentioned documents in a timely manner, in accessible places such as PIU Office and
Panchayat / Village Gram Sabha translated in local language, if necessary.
93. LARP information will be disseminated to APs at various Stages. Information including
magnitude of loss, detailed asset valuations, entitlements and special provisions, grievance
procedures, timing of payments, displacement schedule, Civil works schedule will be disclosed
during LARP implementation.
36
VI. GRIEVANCE REDRESS MECHANISMS (GRM)
94. There will be 403 households and 2347 persons to be affected due to this Subproject so
looking into the present and future needs of proper resettlement of the affected population of the
upcoming Irrigation Project as a whole, a GRM is proposed to be established to provide
avenues for AHs / APs to submit grievances that may arise from time to time. A two-tier GRM
for the Project is proposed which has been outlined as below:-.
95. The first tier Grievance Redressal Cell (GRC) at Project, PIU/PMU level will comprise of:
i. Sub Divisional Magistrate (SDM), Revenue Department as Chairperson ii. Executive Engineer (EE), PMU Level (WRD) as Secretary of GRC iii. R&R Officer, PMU Level (WRD) of GRC iv. A representative from local NGOs or a local person of repute and standing in
the Society or an Elected Representative from the locality. v. A representative from Displaced Persons.
96. The second tier GRC at District level will comprise of:
i. Project Director, PMU, WRD as Chairperson ii. Executive Engineer,(WRD) as Secretary of GRC at PIU Level iii. R&R Officer at PIU Level, (WRD) of GRC iv. A representative from local NGOs or a local person of repute and standing in
the Society or an Elected Representative/ Zila Parishad Member.
97. The GRC at PIU level will meet once every month during the implementation of RP, but
if necessary more meetings will be called for as required to resolve a complaint. The Assistant
Manager, PMU of project will act as the secretariat of GRC, and will keep records of all
complaints, such as: date of receiving complaint; meetings to resolve the complaint; action
taken and date of communication sent to complainant. The contractor’s site office and PIU office will display notices indicating whom to contact if anybody has any grievance. The APs will be
informed that they could submit grievances either to PIU office or to GRC secretary, or the
representative of APs. The GRC meeting will be at least convened once in a month, or as much
as needed when grievances need to be resolved. The complaint/grievance will be redressed in
one month’s time, and written communication will be sent to the complainant. The PIU will
continually coordinate with the secretary of GRC to record a complaint registered by GRC with
details of complaints lodged, date of personal hearing, action taken, and date of communication
sent to the complainant.
98. For the second tier GRC at District level, the EE will act as the secretary of GRC. The
second tier will focus on finding resolutions for the complainants, and with time frame not more
than 4 weeks. The second tier GRC is also expected to resolve a grievance that could not be
resolved by the first tier GRC. This GRM is not substitute or part of the Land Acquisition
Rehabilitation and Resettlement (LARR) authority; the complainants are free to approach the
jurisdictional LARR Authority to have their grievance resolved. The complainant can access the
37
appropriate Land Acquisition Rehabilitation and Resettlement (LARR) Authority at any time and
not necessarily go through the GRC.
99. Other than disputes relating to ownership rights and apportionment issues on which the
LARR Authority has jurisdiction, the GRC will review grievances involving all resettlement
benefits, relocation and payment of assistances. The GRM should be in place at the time when
disclosure of the RP is initiated by WRD and should continue throughout the project
implementation period.
100. The GRC will aim to provide a time-bound and transparent mechanism to voice and
resolve social, environmental, and project related concerns linked to the project. The GRC is not
intended to bypass the government’s inbuilt redressed process, nor the provisions of the statute,
but rather it is intended to address APs concerns and complaints promptly, making it readily
accessible to all segments of the APs, and is scaled to the risks and impacts of the Project.
Figure 2: An Overview of the Grievance Redress Mechanism
Complaints by individual DP, Groups, or institutions
Complaints by People’s representatives: political,
religious, community
Stage-1 GRC Meeting at Project/PIU level
(Complaints to GRC in written form
Stage-1 GRC Meeting at District Level
Decision of Stage 2 GRC – Convey the decision to Public / Chairman and other members of Step
1GRC
Decision to be taken within one month of receipt
of complaint
Decision to be taken within one month of receipt
of complaint
GRC process ends
Simple
Complex issues
2 Months
38
VII. LEGAL FRAMEWORK
A. Introduction
101. The legal framework and principles adopted for addressing resettlement issues in the
subproject have been guided by the existing legislation and policies of the Government of India
(GOI), the Government of Madhya Pradesh, Asian Development Bank and the Resettlement
Framework (RF) adopted for the project. Prior to the preparation of the LARP, a detailed
analysis of the existing national and state policies was undertaken and a RF has been prepared
for the entire program. The section below provides details of the various national and state level
legislations studied and their applicability within this framework. This LARP is prepared based
on the review and analysis of all applicable legal and policy frameworks of the country and ADB
policy requirements. A summary of applicable acts and policies is presented in the following
paragraphs and the detailed policy analysis is provided in the RF.
B. Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCT in LARR), 2013
102. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 (RFCT in LARR Act - 2013) has been effective from January 1,
2014 after receiving the assent of the President of Republic of India.
103. The aims and objectives of the Act include: (i) to ensure, in consultation with institutions
of local self-government and Gram Sabhas established under the constitution of India, a
humane, participative, informed and transparent process for land acquisition for industrialization,
development of essential infrastructural facilities and urbanization with the least disturbance to
the owners of the land and other affected families; (ii) provide just and fair compensation to the
affected families whose land has been acquired or proposed to be acquired or are affected by
such acquisition; (iii) make adequate provisions for such affected persons for their rehabilitation
and resettlement; (iv) ensure that the cumulative outcome of compulsory acquisition should be
that affected persons become partners in development leading to an improvement in their post-
acquisition social and economic status and for matters connected therewith or incidental
thereto.
104. Section 27 of the Act defines the method by which market value of the land shall be
computed under the proposed law. Schedule I outlines the proposed minimum compensation
based on a multiple of market value. Section 31 of the Act specifies rehabilitation and
resettlement award for the affected families and the entitlements are defined in the Schedule II
and III. Under Schedule II various R&R assistance like house construction allowance, land
development assistance, option for annuity and employment, subsistance grant, transport
allowance etc. are made and under Schedule III it specifies various infrastructural facilities and
basis minimum amenities to be provided at new resettlement site in case of project based
relocation.
39
C. Legal and Policy Frameworks of Madhya Pradesh State:
1) “Madhya Pradesh Bhumigat Pipeline, Cable Avan Duct (Bhumi ki Upyokta
ke Adhikaron Ka Arjan) Adhiniyam, 2012 (No. 5 of 2013)” – (To be referred as The Madhya Pradesh Pipeline Act, 2013)
RULES
(a) Assessment of Compensation –
105. The competent authority shall decide the loss of crop income, compensation of trees and
other losses from the land mentioned therein for the period of laying of underground pipeline,
cable or duct, in the following manner :-
i. Any un irrigated land shall be considered as single cropped and irrigated
land shall be considered as double cropped. If no crops are taken in last
three years, the land shall be deemed as “fallow land” and the loss of crop income shall not be calculated for such land. In other cases, the loss
of crop income shall be calculated as follows :-
Calculation of crop income
= Standard
outcome of crop X
Minimum support price of crop
X 2
ii. In addition to the compensation as referred under rule (1), if any the
compensation shall be payable at the rate of fifteen percent of market
value of that land on the date of publication of the declaration under sub-
section (1) of section 4.
iii. If the laying of underground pipeline, cable or duct is not completed within
the stipulated period by the State Government or the Corporation, as the
case may be, it shall be liable to pay the loss for such additional period
which was taken beyond the stipulated period and also be liable for
additional payment at the rate of five percent of the market value of that
land.
40
i. The Madhya Pradesh Government Order No. F 12-2 / 2014 / 07 / 2A Dated 12.11.2014 regarding the ‘Consent Land Purchase Policy’
106. For the development of the State, different infrastructures are being constructed for
which the private land has to be acquired. The process of Land Acquisition is not only time
taking but involves heavy financial cost also. To save this cost and time a consideration amount
in lieu of impacted private properties is offered to the owner of the land and other properties
attached to it. The main conditions of this Circular are as follows:-
i. This Policy is applicable only where there is a need to acquire Private Land for construction of permanent structures for the project.
ii. This Policy of Land Purchase is not only cost effective but saves lot of time in Land Acquisition procedure.
iii. A lump sum compensation / grant / consideration amount is being given to the affected household and his private properties are purchased by the Government with the mutual consent of the affected person or affected household.
iv. If land is required for any developmental purposes the District Collector is approached for making such type of land available to the concerned Department. If suitable Government land is available for the purpose then the same land shall be transferred to the concerned Department. If such type of suitable Government land is not available for the purpose then the procedure of purchase of private land with mutual consent is adopted.
D. ADB’s Safeguard Policy Statement (SPS), 2009
107. The objectives of ADB's SPS (2009) with regard to involuntary resettlement are: (i) to
avoid involuntary resettlement wherever possible; (ii) to minimize involuntary resettlement by
exploring project and design alternatives; (iii) to enhance, or at least restore, the livelihoods of
all displaced persons in real terms relative to pre-project levels; and (iv) to improve the
standards of living of the displaced poor and other vulnerable groups.
108. ADB's SPS (2009) covers physical displacement (relocation, loss of residential land, or
loss of shelter) and economic displacement (loss of land, assets, access to assets, income
sources, or means of livelihoods) as a result of; (i) involuntary acquisition of land, or (ii)
involuntary restrictions on land use or on access to legally designated parks and protected
areas. It covers displaced persons whether such losses and involuntary restrictions are full or
partial, permanent or temporary.
109. The three important elements of ADB’s SPS (2009) are: (i) compensation at replacement
cost for lost assets, livelihood, and income prior to displacement; (ii) assistance for relocation,
including provision of relocation sites with appropriate facilities and services; and (iii) assistance
for rehabilitation to enhance, or at least restore, the livelihoods of all displaced persons relative
to pre-project level standard of living.
41
E. Comparison of Government and ADB Policies
110. The new act ‘The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’, which has integrated provisions of National Rehabilitation and Resettlement Policy (2007) with that of The Land Acquisition Act (LAA) of
1894 (as amended in 1984), recognizes title holders and non-titleholders affected by land
acquisition. Whereby, squatters and encroachers are excluded from the purview of the act.
111. RFCT in LARR Act – 2013 has come into effect from January 1, 2014. This Act is both
complement the revision of the NRRP (2007) and decrease significantly the gaps between the
LAA and ADB's SPS, 2009. The Act also expands compensation coverage of the principal act
by requiring that the value of trees, plants, or standing crops damaged must also be included
and Solatium being 100% of all the amounts inclusive. The Act furthermore has match ADB
requirements for all compensation to be paid prior to project taking possession of any land.
112. Therefore, the RFCT in LARR Act – 2013 has established near equivalence of the
Government’s policies with those of ADB's SPS, 2009. Adoption of the below principles for the
project has ensured that both are covered in their application to this project. A comparison of
ADB and GOI policy and measures to fill the gaps is presented in the Table: 21.
Table 21: The Comparison of ADB and GOI Policy Aspect ADB Safeguard
Requirement Fair Compensation and Transference in Land
Acquisition, Rehabilitation and Resettlement Act, 2013
Measures to Bridge the
GAP
1 Screen the project
Screen the project to identify past, present, and future involuntary resettlement impacts and risks. Conduct survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement
4 (I) it is obligatory for the appropriate Government intends to acquire land for a public purpose to carry out a Social Impact Assessment study in consultation with concerned Panchayat, Municipality or Municipal Corporation, as the case may be, at village level or ward level in the affected area. The Social Impact Assessment study report shall be made available to the public in the manner prescribed under section 6.
Screening of all sub-projects in line with the IR checklist of ADB, towards enabling identification of the potential resettlement impacts and associated risks.
2 Consultation with stake holders and establish grievance redress mechanism
Carryout consultations with displaced persons, host communities and concerned NGOs. Inform all displaced persons of their entitlements and resettlement
Whenever a Social Impact Assessment is required to be prepared under section 4, the appropriate Government shall ensure that a public hearing is held at the affected area, after giving adequate publicity about the date, time and venue for the public hearing, to ascertain the views of the affected families to be recorded
No gap between SPS and RFCTLARR. Act 2013 Given A project level GRM will be included.
42
Aspect ADB Safeguard Requirement
Fair Compensation and Transference in Land
Acquisition, Rehabilitation and Resettlement Act, 2013
Measures to Bridge the
GAP
options and included in the Social Impact Assessment Report. The Land Acquisition Rehabilitation and Resettlement Authority shall be established in each State by the concerned State Government to hear disputes arising out of projects where land acquisition has been initiated by the State Government or its agencies.
3. Improve, or at least restore, the livelihoods of all displaced, and payment at replacement cost
Improve or restore livelihoods of all DPs through: (i) land-based resettlement strategies; (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes if possible.
The Collector having determined the market value of the land to be acquired shall calculate the total amount of compensation to be paid to the land owner (whose land has been acquired) by including all assets attached to the land. Livelihood losers are eligible for various rehabilitation grants.
No gap between SPS and FCTLARR. Assets to be compensated at replacement cost without depreciation and other Livelihood assistances and income restoration measures will be included.
4. Assistance for displaced persons
Provide physically and economically displaced persons with needed assistance
Schedule I, provides market value of the land and value of the assets attached to land. Schedule II provides R&R package for land owners and for livelihood losers including landless and special provisions for Scheduled Tribes.
No gap between SPS and FCTLARR. Entitlement Matrix outlines compensation and assistance for DPs.
5. Improve standard of living of displaced vulnerable
Improve the standards of living of the displaced poor and other vulnerable groups,
Special provisions are provided for vulnerable groups.
No gap between SPS and FCTLARR. Entitlement
43
Aspect ADB Safeguard Requirement
Fair Compensation and Transference in Land
Acquisition, Rehabilitation and Resettlement Act, 2013
Measures to Bridge the
GAP
groups including women, to at least national minimum standards
Matrix outlines assistance for vulnerable groups.
6. Negotiated Settlement
Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status
FCTLARR only apply in case of land acquired/purchased for PPP projects and for Private Companies. Section: 2. (2), and 46.
Provisions outlined in ADB SPS will be followed for the project.
7. Compensation For non-title holders
Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets.
Non-titleholders on acquired land area is only included but not clear about non-titleholders in existing govt. land
Provisions outlined in ADB SPS will be followed for the project.
8. Requirement of RP
Prepare a resettlement plan / indigenous peoples plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting
Preparation of Rehabilitation and Resettlement Scheme including time line for implementation. Section: 16. (1) and (2). Separate development plans to be prepared. Section 41
No gap between SPS and FCTLARR. RP will be prepared for subprojects with impact.
44
Aspect ADB Safeguard Requirement
Fair Compensation and Transference in Land
Acquisition, Rehabilitation and Resettlement Act, 2013
Measures to Bridge the
GAP
framework, budget, and time-bound implementation schedule.
9. Public disclosure
Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to displaced persons and other stakeholders. Disclose the final resettlement plan and its updates to displaced persons and other stakeholders
Under clause 18, the Commissioner shall cause the approved Rehabilitation and Resettlement Scheme to be made available in the local language to the Panchayat, Municipality or Municipal Corporation. As the case may be, and the offices of the District Collector, the Sub-Divisional Magistrate and the Tehsil, and shall be published in the affected areas, in such manner as may be prescribed and uploaded on the website of the appropriate Government.
In addition to the publishing of the approved resettlement plan, the RF includes provision for disclosure of the various documents pertaining to RP implementation.
10. Cost of resettlement
Include the full costs of measures proposed in the resettlement plan and indigenous peoples plan as part of project’s costs and benefits. For a project with significant involuntary resettlement impacts and / or indigenous peoples plan, consider implementing the involuntary resettlement component of the project as a stand-alone operation.
16. (I) Upon the publication of the preliminary notification under sub-section (/) of section 11 by the Collector, the Administrator for Rehabilitation and Resettlement shall conduct a survey and undertake a census of the affected families, in such manner and within such time as may be Prescribed, which shall include: (a) particulars of lands and immovable properties being acquired of each affected family; (b) livelihoods lost in respect of land losers and landless whose livelihoods are primarily dependent on the lands being acquired; (c) a list of public utilities and Government buildings which are affected or likely to be affected, where resettlement of affected families is involved; (d) details of
No gap between SPS and FCTLARR. Cost of resettlement will be covered by the EA.
45
Aspect ADB Safeguard Requirement
Fair Compensation and Transference in Land
Acquisition, Rehabilitation and Resettlement Act, 2013
Measures to Bridge the
GAP
the amenities and infrastructural facilities which are affected or likely to be affected, where resettlement of affected families is involved; and (e) details of any common property resources being acquired'
11. Taking over possession before Payment of compensation
Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation.
38 (I) The Collector shall take possession of land after ensuring that full payment ofcompensation as well as rehabilitation and resettlement entitlements are paid or tendered to the entitled persons within a period of three months for the compensation and a period of six months for the monetary part of rehabilitation and resettlement entitlements listed in the Second Schedule commencing from the date of the award made under section 30.
No gap between SPS and FCTLARR.
12. Monitoring Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.
48 (I)The Central Government may, whenever necessary for national or inter-State projects, constitute a National Monitoring Committee for reviewing and monitoring the implementation of rehabilitation and resettlement schemes or plans under this Act.
For project, monitoring mechanism and frequency will follow ADB SPS based on categorization.
F. R&R Policy Framework for the Subproject
113. Based on the above analysis of Government provisions and ADB policy, the following
resettlement principles are adopted for this Project:
(a) Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks if any. Determine the scope of resettlement
46
planning through a survey and / or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks. Measures to avoid and minimize involuntary resettlement impacts include the following: (i) explore alternative alignments or locations which are less impacting, (ii) ensure the appropriate technology is used to reduce land requirements, (iii) modify the designs, cross sections, and geometrics of components to minimize the ROW and ensure involuntary resettlement is avoided or minimized.
(b) Carry out meaningful consultations with displaced persons, host communities,
and concerned non government organizations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and evaluation of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and indigenous peoples if any, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the concerns of displaced persons. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.
(c) Improve, or at least restore, the livelihoods of all displaced persons through; (i)
land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement cost for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.
(d) Provide physically and economically displaced persons with needed assistance,
including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.
(e) Improve the standards of living of the displaced poor and other vulnerable
groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing.
(f) Develop procedures in a transparent, consistent, and equitable manner if land
acquisition is through negotiated settlement1 to ensure that those people who
1 ADB SPS 2009 (Safeguards Requirements 2) does not apply to negotiated settlements. The policy is
encourages acquisition of land and other assets through a negotiated settlement wherever possible, based on meaningful consultation with affected persons, including those without title to assets. A
47
enter into negotiated settlements will maintain the same or better income and livelihood status.
(g) Ensure that displaced persons without titles to land or any recognizable legal
rights to land are eligible for all compensation, relocation and rehabilitation measures, except land. .
(h) Prepare a resettlement plan elaborating on the entitlements of displaced
persons, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule. This resettlement plan will be approved by ADB prior to contract award.
(i) Disclose a draft resettlement plan, including documentation of the consultation
process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to displaced persons and other stakeholders. Disclose the final resettlement plan and its updates to displaced persons and other stakeholders.
(j) Conceive and execute involuntary resettlement as part of a development project
or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.
(k) Pay compensation and provide other resettlement entitlements before physical or
economic displacement if any. Implement the resettlement plan under close supervision throughout project implementation.
(l) Monitor and assess resettlement outcomes, their impacts on the standard of
living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.
(m) It is proposed to follow the provisions of Pipeline Act 2013 also because KIP
relates to mainly Pipeline Project. Though the implementation of this Pipeline Act 2013 is possible only if there is mainly temporary impact on the properties of the affected population. But if there is permanent impact on their properties due to construction of permanent structures then the land has to be permanently acquired by following RFCTLARRA’ 2013.
(n) But before going into long and time taking procedure of permanent Land
Acquisition, efforts should be made to follow the provisions of “Consent Land Purchase Policy” vide GOMP order dated 12.11.2014 in which the required land
negotiated settlement will offer adequate and fair price for land and/or other assets. Also, an independent external party will be engaged to document the negotiation and settlement processes. In cases where the failure of negotiations would result in expropriation through eminent domain or the buyer could acquire the property regardless of its owner’s decision to sell it or not, will trigger ADB’s involuntary resettlement policy. The Safeguard Requirements 2 will apply in such cases, including preparing a resettlement plan.
48
is purchased by the Government with the Mutual Consent of the affected person. But if the negotiations fail for the purchase of land with mutual consent then the procedure of permanent LAQ has to be followed as per RFCTLARR Act’ 2013.
(o) Regarding the eligibility of compensation, all APs will be provided with
compensation and rehabilitation grant if their land is adversely affected, houses partially or fully demolished, and other properties such as crops, trees and other facilities or access to these properties will be damaged due to the project. Lack of legal documents of their customary rights of occupancy/titles shall not affect their eligibility for compensation. It also must be noted that during the project implementation stage, if there are any changes in the alignments, there by adversely affecting the land, livelihood or other assets of the people, the same shall be compensated in keeping within the applicable framework.
(p) The framework stipulates payment of compensation as per the assessed value of
the land and structure to the APs. In addition to compensation payments made by Land Acquisition Officer / competent authority, the APs will receive additional assistance in cash or kind to match replacement costs, which is the difference between the market value and the assessed value, if any, for lost assets (land and houses), transaction costs such as stamps / registration costs (in case of purchase of replacement land) and other cash grants and resettlement assistance such as shifting allowance, compensation for loss of work days / income due to dislocation. Female-headed households and other vulnerable households (such as Scheduled Tribes/Scheduled Castes, disabled, elderly) will be eligible for further cash assistance for relocation and house reconstruction provided they are permanently affected and displacement becomes inevitable..
(q) The Entitlement Matrix lists various types of losses, identification / eligibility and
entitlements and provides basic parameters for preparation of compensation and resettlement benefits. The matrix would apply to additional subprojects, based on the specific project impacts.
G. Valuation of Assets
114. The valuation of affected land and structures will be governed by the following process:
115. Land surveys for determining the payment of compensation would be conducted on the
basis of updated official records and ground facts. The land records containing information like
legal title, and classification of land will be updated expeditiously for ensuring adequate cost
compensation and allotment of land to the entitled displaced persons. In cases of areas, where
official land records don’t exist, formal land/property boundaries of private property owned by the tribal households can be determined through the process of community consultation and
discussion with village head and village council members.
116. Based on such information, land can be classified and land record can be updated and
compensation assessment can be made. Records as they are on the cut-off date will be taken
into consideration while determining the current use of land. The uneconomic residual land
remaining after land acquisition will be acquired as per the provisions of RFCT in LARR Act,
2013. The owner of such land/property will have the right to seek acquisition of his entire
49
contiguous holding/ property provided the residual land is less than the average land holding of
the District.
117. The methodology for verifying the replacement cost for each type of loss will be as per
the provision made in the RFCT in LARR Act -2013. But before going into lengthy and time
taking procedure of LAQ it is advisable to negotiate with owner of the required land to sell his
land to the Concerned Government Department following the principle of “Consent Land
Purchase Policy” vide GOMP Circular dated 12.11.2014. But if negotiations fail with the owner of the required land then the land has to be acquired by RFCTLARR Act 2013.
1. Valuation of Land
118. The District Collector/Deputy Commissioner shall determine the market value of the land
with assessment of (a) the market value, if any, specified in the Indian Stamp Act, 1899 for the
registration of sale deeds or agreements to sell, as the case may be, in the area, where the land
is situated; or (b) the average sale price for similar type of land situated in the nearest village or
nearest vicinity area; or (c) consented amount of compensation as agreed upon, whichever is
higher.
119. Where the market value as per above section (1) cannot be determined for the reason
that: (a) the land is situated in such area where the transactions in land are restricted by or
under any other law for the time being in force in that area; or(b) the registered sale deeds or
agreements to sell for similar land are not available for the immediately preceding three years;
or(c) the market value has not been specified under the Indian Stamp Act, 1899; the appropriate
authority, the State Government concerned shall specify the floor price or minimum price per
unit area of the said land based on the Price calculated in the manner specified in the above
section (1) in respect of similar types of land situated in the immediate adjoining areas.
120. The market value calculated as per above section (1) shall be multiplied by a factor of
(a) 1 (one) to 2 (two) in rural areas based on the distance of project from Urban Area as notified
by the Government of Madhya Pradesh; and (b) one in urban areas.
121. Solatium amount equivalent to 100% of the market value calculated on the basis of
above (1 or 2) x 3.
Hence: The cost of land in rural areas = X + 100% of X, The cost of land in urban areas = X + 100% of X Where X = Market Value as determined above x 1 to 2.
2. Valuation of Building and Structure
122. The District Collector/Deputy Commissioner in determining the market value of the
building and other immovable property or assets attached to the land or building which are to be
acquired shall use the services of a competent engineer or any other Specialist in the relevant
50
field, as may be considered necessary by him. The cost of buildings will be estimated based on
updated Basic Schedule of Rates (BSR) as on date without depreciation. Solatium of 100% will
be added to the estimated market value of the structure as per the provision of RFCT in LARR
Act 2013. For valuation of structure/building following parameters should be taken into account:
(a) From where they used to buy materials (b) Type of shops (Private or State-owned) (c) Distance to be traveled (d) Sources (local or foreign) and the cost of various materials (e) Who will build the structures (owner or contractor) and whether they will use the
hired labor or their own labor (cost of labor will be considered); (f) Obtaining cost estimates by meeting at least three contractors/suppliers in order
to identify cost of materials and labor (g) Identifying the cost of different types of houses of different categories and
compare the same with district level prices.
3. Valuation of Trees
123. Compensation for trees will be based on their full replacement cost. The District
Collector/Deputy Commissioner for the purpose of determining the market value of trees and
plants attached to the land acquired, use the services of experienced persons in the field of
agriculture, forestry, Horticulture, Sericulture, or any other field, as may be considered
necessary by him.
124. Even after payment of compensation, DPs would be allowed to take away the materials
salvaged from their dismantled houses and shops and no charges will be levied upon them for
the same. In case of any structures not removed by the DPs in stipulated 60 days period, a
notice to that effect will be issued intimating that DPs can take away the materials so salvaged
within 48 hours of their demolition; otherwise, the same will be disposed by the project authority
without giving any further notice.
125. Trees standing on the land owned by the Government will be disposed of through open
auction by the concerned Revenue Department/ Forest Department. DPs will be provided with
an advance notice of three months prior to relocation. Further, all compensation and assistance
will be paid to DPs at least 60 days prior to displacement or dispossession of assets.
126. For temporary impact on land and common property resources, any land required by the
project on a temporary basis will be compensated in consultation with land owners and will be
restored to previous status or better quality. Implementation issues can be found in the
Entitlement Matrix.
51
VIII. ENTITLEMENTS, ASSISTANCE AND BENEFITS
A. Introduction
127. This subproject will have 403 DHs as 5.777 ha of private land and 0.737 ha of
Government land will be impacted due to construction of laying of Distribution Pipeline as
mentioned in Table 3 involving acquisition of Private and Government Land. Private Land of
0.047 ha will be acquired permanently for construction of 235 OMS. However, there will not be
any physical displacement under the subproject because there will be very insignificant impact
on the properties and livelihood of the affected population because there will be mainly
temporary acquisition of land. This section deals with the entitlement provisions as per the
anticipated impacts for the Kundalia Micro Irrigation Project.
B. Cut-off-Date for Entitlement
128. In case of land acquisition, the date of publication of preliminary notification for
acquisition under section 11 of the RFCT in LARR Act – 2013 will be treated as the cut-off date.
For non-titleholders, the cut-off date will be the end of the census survey which is 30th June’ 2019 in this subproject. The cut-off date for non-titleholders will be officially declared by the IA
along with the disclosure of RP and additionally notified in the project area through newspaper
and communicated to DPs during consultation. They, however, will be given sufficient advance
notice, requested to vacate premises and dismantle affected structures prior to subproject
implementation. Their dismantled structures materials will not be confiscated and they will not
pay any fine or suffer any sanction.
C. Subproject Entitlement
129. At present 6.561 ha of Private Land and Government Land will be affected temporarily
and permanently so entitlement of compensation of all the affected private properties as per
their entitlement matrix will be paid as mentioned in LAP/RP of the subproject. The provisions of
the entitlements of the project as a whole will also be followed in letter and spirit in phases
according to the upcoming subprojects of KIP-Left Bank. In accordance with the R&R measures
outlined in the project Resettlement Framework, all displaced households and persons will be
entitled to a combination of compensation packages and resettlement assistance depending on
the nature of ownership rights on lost assets and scope of the impacts including socio-economic
vulnerability of the displaced persons and measures to support livelihood restoration if livelihood
impacts are envisaged. The displaced persons will be entitled to the following five types of
compensation and assistance packages:
(a) Compensation for the loss of land, crops / trees at their replacement cost; (b) Compensation for structures (residential / commercial) and other immovable
assets at their replacement cost; (c) Assistance in lieu of the loss of business / wage income and income restoration
assistance; (d) Assistance for shifting and provision for relocation site (if required), and (e) Rebuilding and/ or restoration of community resources / facilities.
52
D. Loss of land
130. Loss of land will be compensated at replacement cost plus refund of transaction cost
(including land registration cost, and stamp duties) incurred for purchase of replacement land. If
the residual plot(s) is (are) not viable, i.e., the DP becomes a marginal farmer, three options are
to be given to the DP, subject to his acceptance which are (i) The DP remains on the plot, and
the compensation and assistance paid to the tune of required amount of land to be acquired, (ii)
Compensation and assistance are to be provided for the entire plot including residual part, if the
owner of such land wishes that his residual plot should also be acquired by the EA, the EA will
acquire the residual plot and pay the compensation for it and (iii) If the DP is from vulnerable
group, compensation for the entire land by means of land for land will be provided if AP wishes
so, provided that land of equal productive value is available. The replacement of land option will
be considered by the District Collector while acquiring land wherever feasible alternate land is
available. All fees, stamp duties, taxes and other charges, as applicable under the relevant
laws, incurred in the relocation and rehabilitation process, are to be borne by the EA.
131. The compensation measures suggested in this RP based on the LARR Act -2013, which
includes, market value, solatium, transition cost, interest in case of delay along with other
assistance items aligns with the criteria of replacement cost of the assets.
E. Loss of Structures
132. Loss of Structures will be compensated at replacement value with other assistance to
both titleholders and non-titleholders. The details of entitlement will be as:
(a) Compensation for structure at the replacement cost to be calculated as per latest prevailing basic schedules of rates (BSR) without depreciation.
F. Loss of trees and crops
133. Loss of trees and crops will be compensated by cash compensation. The entitlements to
the DPs losing trees and crops will be:
(a) Advance notice to harvest crops, fruits, and timbers. (b) Compensation for standing crops in case of such loss, based on an annual crop
cycle at market value (c) Compensation for trees based on timber value at market price, and
compensation for perennial crops and fruit trees at annual net product market value multiplied by remaining productive years; to be determined in consultation with the Forest Department for timber trees and the Horticulture Department for other trees/crops.
G. Additional assistance to vulnerable households
(a) Vulnerable households include BPL, SC, ST, WHH, Disabled, elderly and non-titleholders will be paid with special assistances as detailed below if they are impacted permanently due to construction of the subproject.
53
(b) One time lump sum assistance of Rs. 25,000 to vulnerable households will be paid if they are experiencing permanent and singnificant impact on their properties and livelihood. This will be paid above and over the other.
(c) Receive preference in income restoration training program under the project. (d) Preference in employment under the project during construction and
implementation. (e) Access to basic utilities and public services.
H. Loss of community infrastructure/common property resources
134. Though there is no community infrastructure is being impacted in this subproject but in
case if there is any possibility in near future for this or other subprojects then the impacted,
Common Property Resources (CPR) will be compensated either by paying them compensation
at replacement cost of the property/structure to the community (registered trust, society or
village committee as appropriate) or by reconstruction of the community structure in consultation
with the affected community.
I. Temporary Impacts
135. Temporary impacts on agricultural land due to plant site for contractor etc will be eligible
for cash compensation for loss of income potential including:
(a) Any land required by the Project on a temporary basis will be compensated in consultation with the landholders.
(b) Rent at market value for the period of occupation (c) Compensation for assets at replacement cost (d) Restoration of land to previous or better quality (e) Location of construction camps will be fixed by contractors in consultation with
Government and local community. (f) 60 Days advance notice regarding construction activities, including duration and
type of temporary loss of livelihood. (g) Cash assistance based on the minimum wage/average earnings per month for
the loss of income/livelihood for the period of disruption, and contractor’s actions to ensure there is no income/access loss.
(h) Any unanticipated impacts due to the subproject will be documented during the implementation phase and mitigated based on provision made in the Entitlement Matrix of this Resettlement Plan.
J. Entitlement Matrix
136. An Entitlement Matrix has been developed, that summarizes the types of losses and the
corresponding nature and scope of entitlements; and is in compliance with National Laws and
ADB SPS-2009 (refer to Table 22). All compensation and other assistances will be paid to all
DPs prior to physical or economic displacement. After payment of compensation, DPs would be
allowed to take away the materials salvaged from their dismantled houses and shops and no
charges will be levied upon them for the same. The cost of salvaged materials will not be
deducted from the overall compensation amount due to the DPs. A notice to that effect will be
issued intimating that DPs can take away the materials.
54
Table 22: Entitlement Matrix S.N. Type of
Loss Application Definition of
Entitled Person Compensation Policy Implementation
Issue
Responsible Agency
Land
1-a Loss of private land
Agricultural land2, homestead land or vacant plot
Legal titleholders/ Family with traditional titleholders3
• Compensation at
replacement cost or
land-for-land where
feasible.4If land-for-land
is offered, titles will be
in the name of original
landowners. • One time Resettlement
allowance5 of Rs.
50,000 per affected
family6
• Each affected family
shall be eligible for
choosing one time
assistance option from:
(i) Where jobs are
created through the
project, employment for
at least one member of
the affected family with
suitable training and
skill development in the
required field; or (ii)
One-time payment of
Rs. 500,000 per
affected family.
• Displaced
families7belong to
• Compensation
accounts for all
taxes and fees,
and does not
account for any
depreciation.
• Vulnerable
households will
be identified
during the
census.
• Re-titling to be
completed prior
to project
completion
• For option of
choosing job
created through
project, job will
be paid at living
wage and
monitored by
CSC.
District Collector/Deputy Commissioner shall determine the market value of the land and multiply by the factors and add 100% solatium as specified in LARR Act. PIU will ensure provision of notice. PIU will verify the extent of impacts through a 100% survey of APs, determine assistance, and identify vulnerable households.
2 The LARR, 2013 Act says no irrigated multi cropped land shall be acquired under this Act, except in exceptional
circumstances, as a demonstrable last resort. Wherever such land is acquired, an equivalent area of cultivable wasteland
shall be developed for agricultural purposes or an amount equivalent to the value of land acquired shall be deposited with
the appropriate Government for investment in agriculture for enhancing food-security. Such costing shall also reflect while
preparing Resettlement Budget. 3 Traditional land rights refer to households with customary rights to land, and shall be treated equivalent to
titleholders. The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 defines “Forest Dwelling Scheduled Tribes” as the members or community of the Scheduled Tribes who primarily reside in andwho depend on the forests and forest lands for bona fide livelihood needs and includes the Scheduled Tribe pastoralist communities. The act provides right to in situ rehabilitation including alternative land in cases where the Scheduled Tribes and other traditional forest dwellers have been illegally evicted or displaced from forest land of any description without receiving their legal entitlement or rehabilitation prior to the 13th of December 2005.
4 Including option for compensation for non-viable residual portions. 5 The LARR Act–2013 specifies that each affected family shall be given one time Resettlement Allowance of Rs.50,000/- only. 6 ‘Family’ includes a person, his or her spouse, minor children, minor brothers and minor sisters dependent on him. Widows,
divorcees and women deserted by families shall be considered separate family. An adult of either gender with or without
spouse or children or dependents shall be considered as a separate family – as defined under LARR Act–2013. 7Displaced family" as defined by the LARR Act–2013, means any family, who on account of acquisition of land has to be
relocated and resettled from the affected area to the resettlement area. According to ADB SPS-2009, displaced persons are
those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced
55
Scheduled Caste (SC)
and Scheduled Tribe
(ST) of Scheduled
Areas will receive
additional one-time Rs.
50,000 as subsistence
allowance.
• Additional assistance to
Vulnerable Households
1-b Loss of private land
Agricultural land, homestead land or vacant plot
Tenants and leaseholders (whether having written tenancy/lease documents or not / Sharecroppers
• Compensation for rental deposit or unexpired lease (such amount will be deducted from the compensation of land owners).
• Displaced families belong to Scheduled Caste (SC) and Scheduled Tribe (ST) of Scheduled Areas will receive additional one-time Rs. 50,000 as subsistence allowance
• Additional assistance to Vulnerable Households
• Land owners will reimburse tenants and leaseholders land rental deposit or unexpired lease
• Vulnerable households will be identified during the census.
PIU will confirm land rental and ensure tenants and leaseholders receive reimbursement for land rental deposit or unexpired lease, and report to PIU. PIU will ensure provision of notice.
2-a Loss of Government land
Vacant plot, Agricultural land, homestead land
Leaseholders • Compensation for
rental deposit or
unexpired lease (such
amount will be
deducted from the
compensation of the
lessee).
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
• Vulnerable households will be identified during the census.
PIU will ensure provision of notice and identify vulnerable households.
(loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of
land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. Thus, under
this RF, the subsistence allowance is applicable for all affected families losing land irrespective of their nature of physical or
economic displacement.
56
2-b Loss of Government land
Vacant plot, Agricultural land, homestead land
Non-Title Holders/Squatters8, Encroachers9
• At least 60 days
advance notice to shift
from occupied land.
• Notice to harvest
standing seasonal
crops and
compensation.
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance
• Additional assistance
as Vulnerable
Households
• As per ADB SPS-2009, all NTH are considered as vulnerable households.
PIU will ensure provision of notice. PIU will identify vulnerable households.
Residential Structures10 3-a Loss of
residential structure
Residential structure and other assets11
Legal titleholders Family with traditional land right
Each affected family
shall be eligible for
choosing one time
assistance option from:
(i) Replacement
cost of the
structure and
other assets (or
part of the
structure and
other assets, if
remainder is
viable) without
depreciation;
Or
(ii) In Rural area,
the displaced
family will be
provided with the
option of
constructed
house as per
Indira
AwaasYojana
specifications in
lieu of cash
• Compensation
accounts for all
taxes and fees,
and does not
account for any
depreciation.
• Vulnerable
households will
be identified
during the
census.
• Wherevers DPs
opt for self-
construction,
land and
structures will
be
compensated at
replacement
cost
• Assessment of
viability of
remaining
structure will be
made in
consultation
District Collector/Deputy Commissioner shall determine the market value of the structure and add 100% solatium as specified in LARR Act. Valuation committee will verify replacement value. PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.
8Squatters are those who have no recognizable rights on the land that they are occupying. 9 Encroachers are those who build a structure which is in whole or is part of an adjacent property to which he/she has no title. 10Some of the entitlements under section are the same as previous rows as it is structured separately for each
affected category and should not be duplicated in reading 11 Other assets include, but is not limited to walls, fences, sheds, wells, etc.
57
compensation;
(iii) In Urban area,
the displaced
family will be
provided with the
option of
constructed
house of
minimum 50 sq.
m. plinth area in
lieu of cash
compensation.
• Fees, taxes, and other
charges related to
replacement structure.
• Right to salvage
materials from
structure and other
assets with no
deductions from
replacement value.
• One-time Resettlement
allowance of Rs.
50,000 per affected
household
• One time financial
assistance of Rs.
25,000 to the families
losing cattle sheds for
reconstruction
• All displaced families
will receive one time
shifting assistance of
Rs. 50,000 towards
transport costs etc.
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
with DPs
3-b Loss of residential structure
Residential structure and other assets
Tenants and leaseholders
• Replacement cost of
part/whole of structure
constructed by the
tenant/leaseholder
Land/structure
owners will
reimburse tenants
and leaseholders
Valuation committee will verify replacement value. PIU will
58
without depreciation,
and this will be
deducted from the
compensation amount
of the owner.
• Compensation for
rental deposit or
unexpired lease.
• Right to salvage
materials (of the
portion constructed by
tenants or
leaseholders) from
structure and other
assets
• One time Resettlement
allowance of Rs.
50,000 per affected
family
• One time financial
assistance of Rs.
25,000 to the families
losing cattle sheds for
reconstruction.
• All displaced families
will receive one time
Shifting assistance of
Rs. 50,000 towards
transport costs etc
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
rental deposit or
unexpired lease.
Vulnerable
households will
be identified
during the
census.
verify the extent of impacts through a 100% surveys of AHs determine assistance, verify and identify vulnerable households.
3-c Loss of residential structure
Residential structure and other assets
Non-Title Holders/ Squatters, Encroachers
• Replacement cost of
structure constructed
by the squatter without
depreciation
• Right to salvage
materials from
structure and other
assets
• One time Resettlement
allowance of Rs.
Vulnerable
households will
be identified
during the
census.
PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.
59
50,000 per affected
family
• All displaced families
will receive one time
shifting assistance of
Rs. 50,000 towards
transport costs etc.
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
Commercial Structures
4-a Loss of commercial structure
Commercial structure and other assets
Legal titleholders Family with traditional land right
• Replacement cost of
the structure and other
assets (or part of the
structure and other
assets, if remainder is
viable) without
depreciation
• Fees, taxes, and other
charges related to
replacement structure.
• Right to salvage
materials from
structure and other
assets with no
deductions from
replacement value.
• One time Resettlement
allowance of Rs.
50,000 per affected
family
• One time financial
assistance of Rs.
25,000 to the families
losing shop for
reconstruction of shop.
• All physically displaced
families will receive
one time shifting
assistance of Rs.
50,000 towards
transport costs etc.
• Compensation
accounts for all
taxes and fees,
and does not
account for any
depreciation.
• Vulnerable
households will
be identified
during the
census.
Valuation committee will determine replacement value. PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.
60
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
4-b Loss of commercial structure
Commercial structure and other assets
Tenants and leaseholders
• Replacement cost of
part/whole of structure
constructed by the
tenant/leaseholder
without depreciation,
and this will be
deducted from the
compensation amount
of the owner.
• Compensation for
rental deposit or
unexpired lease.
• Right to salvage
materials (of the
portion constructed by
tenants or
leaseholders) from
structure and other
assets
• One time Resettlement
allowance of Rs.
50,000 per affected
family
• All displaced families
will receive one time
shifting assistance of
Rs. 50,000 towards
transport costs etc.
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
Land/structure
owners will
reimburse tenants
and leaseholders
land rental
deposit or
unexpired lease.
Vulnerable
households will
be identified
during the
census.
Valuation committee will determine replacement value. PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households.
61
4-c Loss of commercial structure
Commercial structure and other assets
Non-Title Holders/Squatters, Encroacher
• Replacement cost of
structure constructed
by the squatter without
depreciation
• Right to salvage
materials from
structure and other
assets
• One time Resettlement
allowance of Rs.
50,000 per affected
family
• All displaced families
will receive one time
shifting assistance of
Rs. 50,000 towards
transport costs etc.
• Displaced families
belong to Scheduled
Caste (SC) and
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
Vulnerable
households will
be identified
during the
census.
PIU will verify the extent of impacts through a 100% surveys of AHs determine assistance, verify and identify vulnerable households.
Livelihood 5 Loss of
livelihood Livelihood Legal titleholder
losing business/ commercial establishment Family with traditional land right Commercial tenant Commercial leaseholder Employee in commercial establishment Agricultural laborer (long term) Artisans Squatters
• One time financial
assistance of minimum
Rs. 25,000.
• Skill up-gradation
training to APs opted
for (one member of the
affected family) income
restoration.
• Preference in
employment under the
project during
construction and
implementation.
• Monthly Subsistence
allowance of Rs. 3,000
for one year (total Rs.
36,000) from the date
of award
• Displaced families
belong to Scheduled
Caste (SC) and
Vulnerable
households will
be identified
during the
census.
PIU will verify the extent of impacts through a 100% survey of AHs determine assistance, verify and identify vulnerable households. For Agricultural laborer (long timer) Only those who are in fulltime / permanent employment of the land owner will be eligible for this assistance. Seasonal
62
Scheduled Tribe (ST)
of Scheduled Areas will
receive additional one-
time Rs. 50,000 as
subsistence allowance.
• Additional assistance
to Vulnerable
Households
experiencing significant
losses
agricultural laborers will not be entitled for this assistance.
Trees and Crops 6 Loss of
trees and crops
Standing trees and crops
Legal titleholder Family with traditional land right Agricultural tenant/ leaseholder Sharecroppers Non-Title Holders Squatter
• Advance notice to
harvest crops, fruits,
and timbers.
• Compensation for
standing crops in case
of such loss, based on
an annual crop cycle at
market value
• Compensation for trees
based on timber value
at market price, and
compensation for
perennial crops and
fruit trees at annual net
product market value
multiplied by remaining
productive years; to be
determined in
consultation with the
Forest Department for
timber trees and the
Horticulture
Department for other
trees/crops.
• Harvesting prior
to acquisition
will be
accommodated
to the extent
possible
• Work schedules
will avoid
harvest season.
• Seasonal crops
will be given at
least 60-day
notice. If notice
cannot be
given,
compensation
for standing
crops will be
compensated at
market value.
• Market value of
trees/crops has
to be
determined.
PIU will ensure provision of notice. Valuation Committee will undertake valuation of standing crops, perennial crops and trees, and finalize compensation rates in consultation with APs.
Vulnerable
7 Impacts on vulnerable APs
All impacts Vulnerable APs • Vulnerable households
experiencing losses
associated with items
1-a, 1-b, 2-a, 2-b, 3-a,
3-b, 3-c, 4-a, 4-b, 4-c, 5
and 6 will receive a
onetime lump sum
assistance of Rs. 25
0000. This vulnerability
assistance will be paid
to the vulnerable
household above and
over other
Vulnerable
households will
be identified
during the census
and
implementation of
project.
PIU will verify the extent of impacts through a 100% surveys of AHs determine assistance, verify and identify vulnerable households. The PIU with support from the CSC and
63
compensation and
assistances provided.
• For vulnerable
households
experiencing temporary
and insignificant losses
described in items 8
and 9, the contractor
will ensure that any
land restrictions will not
adversely impact any
vulnerable household
members.12 For
example, senior and
disabled households
members will be
provided adequate
alternative access
roads where
construction has
restricted land access.
• Receive preferential in
income restoration
training program under
the project.
• Preference in
employment under the
project during
construction and
implementation
• Access to basic utilities
and public services
NGO13will conduct a training need assessment in consultations with the displaced persons so as to develop appropriate income restoration schemes. Suitable trainers or local resources will be identified by PIU and NGO in consultation with local training institutes.
Temporary Loss 8 Temporary
loss of land14
Land temporarily required for sub-project construction
Legal titleholders Family with traditional land right
• Any land required by
the Project on a
temporary basis will be
compensated as per
the Pipeline Act and in
consultation with DPs.
• Rent at market value
Assessment of
impacts if any on
structures, assets,
crops and trees
due to temporary
occupation.
Valuation Committee will determine rental value and duration of construction survey and consultation with
12 Significant losses include: (i) being physically displaced from housing, or (ii) losing 10% or more of an affected
households’ productive assets (income generating). 14 Temporary possession of land for project purpose can be taken only for three years from the date of
commencement of such possession/occupation. 13When suitable NGO is not available, the PIU will be staffed with qualified and experienced social workers to assist
the IA in RP implementation 14 Temporary possession of land for project purpose can be taken only for three years from the date of
commencement of such possession/occupation.
64
for the period of
occupation
• Compensation for
assets at replacement
cost
• Restoration of land to
previous or better
quality15.
• Location of
construction camps will
be fixed by contractors
in consultation with
Government and local
community.
Site restoration.
Landowners
electing to decline
compensation
must sign the
MoU in the
Presence of a
third party
withness. All
Mou’s will be included in the
RP or Social
Monitoring Report
APs. PIU will ensure compensation is paid prior to site being taken-over by contractor. Contractor will be responsible for site restoration.
9 Temporary disruption of livelihood
Land temporarily required for sub-project construction.
Legal titleholders, non-titled Aps
• 60 days advance
notice regarding
construction activities,
including duration and
type of disruption.
• Cash assistance based
on the minimum
wage/average earnings
per month for the loss
of income/livelihood for
the period of disruption,
and contractor’s actions to ensure there
is no income/access
loss consistent with the
EMP.16
Assistance to mobile vendors/hawkers to temporarily shift for continued economic activity.17
• Identification of
alternative
temporary sites
to continue
economic
activity.
Valuation Committee will determine income lost. Contractors will
perform actions
to minimize
income/access
loss.
Common Resources 10 Loss and
temporary impacts on common resources
Common resources
• Communities • Replacement or
restoration of the
affected community
facilities – including
public water stand
posts, public utility
posts, temples,
Follow ADB SPS PIU and Contractor.
15 If the land has become permanently unfit to be used for the purpose for which it was used immediately before the
commencement of such term, and if the persons interested shall so require, the appropriate Government shall proceed under the Act to acquire the land as if it was needed permanently for a public purpose.
16 This includes: leaving spaces for access between mounds of soil, providing walkways and metal sheets to maintain access across trenches for people and vehicles where required, increased workforces to finish work in areas with impacts on access, timing of works to reduce disruption during business hours, phased construction schedule and working one segment at a time and one side of the road at a time.
17For example assistance to shift to the other side of the road where there is no construction.
65
shrines, etc.
Other 11 Any other
loss not identified
• DPs
Communities
• Unanticipated
involuntary impacts will
be documented during
the implementation
phase and mitigated
based on provision
made in the RF.
PIU will finalize the entitlements in line with ADB’s SPS, 2009.
66
IX. RELOCATION, INCOME RESTORATION AND REHABILITATION
A. Basic Provision for Relocation
137. There will be temporary impact on the properties of 403 households. Due measures will
be taken to take care of any situation which may arise at the later stages also. The EA will
provide adequate and appropriate replacement land and structures if available or cash
compensation at full replacement cost for lost land and structures, adequate compensation for
partially damaged structures, and relocation assistance, according to the Entitlement Matrix.
The EA will compensate to the non-titleholders for the loss of assets other than land, such as
dwellings, and also for other improvements to the land, at full replacement cost. The
entitlements to the non-titleholders will be given only if they occupied the land or structures in
the subproject area prior to the cut-off date. There will not be any displacement of population in
this Subproject but in case of any physical displacement, the EA will provide:
(a) relocation assistance, better housing at resettlement site*s with comparable access to employment and production opportunities, and civic infrastructure and community services as required;
(b) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and
(c) Opportunities to derive appropriate development benefits from the subproject such as direct employment, engagement as petty contractor, supplying raw materials etc.
B. Income Restoration and Rehabilitation
138. The impact of the Subproject will be temporary as it involves the construction of
alignment of Distribution Pipeline.There will be temporary and partial impact on the private
properties of the 403 affected households for which AHs will get due compensation as per the
provisions of Pipeline Act of the State. The provisions of the Pipeline Act of the State will be
extended for temporary acquisition of their impacted land and provisions of RFCTLARR or
Consent Land Purchase Policy of the State if there is any permanent acquisition of land.
139. There will not be any significant loss of their properties due to temporary acquisition of
land. Even then, they can develop their land with the compensation amount which they will get
against the loss of their impacted land. There is no community infrastructure being impacted in
this subproject but in case if there is any possibility in near future then the impacted Common
Property Resources (CPR) will be compensated either by paying them compensation at
replacement cost to the community (registered trust, society or village committee as
appropriate) or reconstruction of the community structure in consultation with the affected
community.
140. The objective of the R&R package included in the subproject entitlement matrix is to
support the DPs to improve or at least restore the livelihoods. There is no loss of any livelihood
because the impact on their properties is insignigficant due to temporary acquisition of land. In
case of business loss will also be easily restored by the DPS with the help of R&R assistance
67
provided under the Subproject. The specific measure provided under the entitlement matrix of
this RP is listed below.
• Vulnerable households will receive preferential in income restoration training program under the project.
• Vulnerable households will have preference in employment under the project during construction and implementation.
• Project will ensure access to basic utilities and public services by vulnerable households
141. Though there will not be any significant impact on the properties and livelihood of DHs
due to temporary acquisition of their land, even then the wards of the APs will be encouraged to
take up ITI Courses in the adjoining Government run Industrial Training Institutes (ITI’s). After
taking such trainings they can start their self-employment avocations. As it is pressure on
agriculture land is increasing day by day as the number of family members is increasing in every
generation but the area of the land holding is still the same. Taking up some other job avenues
by the younger generation will be for the betterment of their families as it will reduce the extra
pressure on the agriculture land.
C. Provisions for Loss of Livelihood
142. In cases where land acquisition affects commercial structures, affected business owners
are entitled to:
(a) the costs of re-establishing commercial activities elsewhere; (b) the net income lost during the transition period; and (c) the costs of transferring and reinstalling plant, machinery, or other equipment.
143. Business owners with legal rights or recognized or recognizable claims to land where
they carry out commercial activities are entitled to replacement property of equal or greater
value or cash compensation at full replacement cost. Non-titleholder households losing
business structure and livelihood will be compensated for the structure loss and receive
transitional assistance as well. The EA will ensure that no physical displacement or economic
displacement will occur until:
(a) compensation at full replacement will be paid to each displaced person for subproject components or sections that are ready to be constructed;
(b) other entitlements listed in the resettlement plan have been provided to displaced persons; and
(c) a comprehensive income and livelihood rehabilitation program, supported by an adequate budget, is in place to help displaced persons improve, or at least restore, their incomes and livelihoods.
D. Additional Support from Ongoing Poverty Reduction Programs
144. In addition to Subproject-sponsored programs, the implementing RS will play a proactive
role to mobilize DPs to get benefits from various government schemes and ensure their
accessibility particularly of vulnerable groups. In India, Panchayat Government Systems at the
68
village, block and district levels are now responsible for planning and implementation of all anti-
poverty programs funded by the central and state governments. The implementing RS will work
with the Panchayat Governments to make available to the DPs benefits of some of the ongoing
pro-poor programs for poverty reduction of GOI.
69
X. LAND ACQUISITION BUDGET AND FINANCING PLAN
A. Introduction
145. The land acquisition cost estimate for this subproject includes compensation for loss of
land, loss of structures, loss of trees and Rehabilitation Assistance / Grant as per their impacts
and eligibilities.
B. Compensation Payment
146. Compensation for Crop Loss: The private land of 5.777 ha, has to be acquired
temporarily for Laying of underground distribution Pipeline. Since there is only temporary
acquisition of land therefore the provisions of Pipeline Act of the State has been implemented
for payment of compensation.The provisions of Pipeline Act includes double crop compensation
to be paid to the AHs. The calculation of Crop Compensation is based on Standard outcome of
Soyabean Crop which is grown during the construction period to be under taken in sub-project
area of Zone-3 in Left Bank of KIP. The Standard Outcome of Soyabean Crop is estimated to be
approximately 20 Quintals production in One Hectare of Land in this area. The Double Crop
Compensation for temporary land acquisition is based on the Standard outcome of the crop to
be multiplied by the Minimum Support Price (MSP) as declared by Ministry of Agriculture &
Farmers Welfare, GOI.
147. Compensation for Temporary Land Acquisition: In addition to the compensation as
referred above, the compensation for temporary land acquisition of 5.777 ha shall be payable at
the rate of 15% of the market value of the impacted land. The compensation is based on 15
percent amount of an average cost of the market value of irrigated agriculture land as per the
Collector Guideline of the total 12 impacted villages of sub-project area of Zone-3 in Left Bank
of KIP.
148. Compensation for Permanent Land Acquisition: The 235 OMS of 1 X 2 Meter in size
will require 0.047 ha of private land which needs to be acquired permanently so Compensation
has to paid for 0.047 ha of private land.
149. Compensation for Trees: For cost estimate in LARP for affected private trees
enumerated during the census survey, a lump sum rate of Rs. 15,000/- for fruit bearing trees
and Rs. 3000/- for non fruit bearing trees has been considered based on the market
assessment. Compensation for standing Orange Orchard Trees will also be paid based on three
categories. In Category-A there are 128 Orange trees, in Category-B there are 63 orange trees
and only 7 Orange trees in C-Category to be impacted in sub-project. There are 3 other variety
of fruit bearing trees and 1 Timber private tree which may come in the alignment of the
distribution pipeline.
150. For Orange fruit trees in standing orchards, the trees have been divided in three
categories for compensation purposes in which Category-A includes presently fruit bearing trees
estimating their cost to be Rs. 15000 per tree based on their yearly production of Rs 3000 each
year for an estimated period of five years. Category-B includes those orange trees which will
70
start giving fruits after 2-3 years estimating it to be Rs. 1000 yearly of one tree for a period of
five years and Category-C are the trees which have been planted recently estimating them to be
Rs.100 each tree.
151. Livelihood Resources: Due to temporary acquisition of impacted land, the impact on
the properties and livelihood of AHs will be insignificant so for skill development the AHs will be
encouraged to take Vovational Training from the Government ITI’s and take advantage of the
ongoing schemes of State and the Central Government.
C. Compensation for Community Property Resources
152. There will be impact only on 0.737 ha of Government Land. No Community Property
Resources are to be impacted due to the alignment of this subproject.
153. The required Public / Government land will be transferred in the name of WRD by
respective departments and therefore not included in the resettlement cost.
D. LAP Implementation and Support Cost
154. The WRD has decided to hire Resettlement Officer / Expert for implementation of RR
activities. The implementation support cost including Hiring of Resettlement Specialist,
conducting public consultation, grievance redress cost etc. will be borne by administrative
expenses of WRD. A 10% Contingency Charges has been added in this subproject in order to
hire the services of Resettlement Specialist for implementation purposes and for conducting GR
Meetings and to adjust any cost escalation during subproject implementation.
E. Sources of Funding and Fund Flow Management
155. The cost related to permanent land acquisition and resettlement will be borne by the
Executive Agency (EA) MPWRD. The EA will ensure allocation of funds and availability of
resources for smooth implementation of the subproject R&R activities. The EA will, in advance,
initiate the process and will try to keep the approval for the R&R budget in the fiscal budget
through the ministry of finance in GOMP. In the case of assistance and other rehabilitation
measures, the EA will directly or through the Contractor pay the money or any other assistance
as stated in the LAP to DPs. The implementing Resettlement Expert / Specialist will be involved
in facilitating the disbursement process and rehabilitation program. The cost estimate for the
LAP implementation of this Subproject is Rs 4.91 Million.
71
Table 23: Estimated Budget for Implementation of the RP
Sl. No. Item Unit Rate Amount
A Compensation for Land in Ha/Rs in Rupees
1 Compensation for Private Land (235 Outlet Management System which has to be a concrete base of 1x2 meters each)
0.047 (Ha) 1454750 68373.25
2 100% Solatium of Permanent Private Land Acquisition for 235 OMS
68373.25 (Rs)
100% 68373.25
Subtotal A 136746.50
B Compensation For Temporary Acquisition and Crop Loss
in Ha/Nos Rupees in Rupees
1 Compensation for temporary land acquisition and standing crops for underground pipe lines, piped canals and distribution system18
5.777 (Ha) 135000 779895
In addition to the compensation of Crop Loss, 15% of the market value of that impacted land will be added as per Special Provision of Pipeline Act of GOMP 201319
5.777 (Ha) 218212 1260610.72
2 Compensation for standing orange orchard Trees (As classified in A-Category)
128 (Trees)
15000 1920000
3 Compensation for standing orange orchard Trees (As classified in B-Category)
63 (Trees)
5000 315000
4
Compensation for standing orange orchard (C-Category- including cost of planting material, manures and fertilizers, Insecticides and pesticides, land leveling, cost of labor and fencing etc.)
7 (Trees)
100 700
5 Other Fruit Bearing Tree 3 15000 45000
6 Timber Tree 1 3000 3000 Subtotal B 4324205.72
Total (A+B) 4460952.22
Contingency (10%)for Hiring RS, Conducting GR Meetings & Cost Escalation 446095.22
GRAND TOTAL 4907047.44
18 Sources : Considering Soyabean Crop Rates of Rs. 3399/- per Quintal from from the Ministry of Agriculture &
Farmers Welfare, GOI as Annexed at Annexure – 12.Average Production of Soyabean crops per year is 20 Quintal per Ha in this subproject area is taken from Preveious years crop production Data of Horticulture Department and discussions and feedback from the Farmers of the Subproject Area.
19 Srouce : Considered Agriculture Land cost from the Collertor Guideline of Nalkheda Tehsil, Agar Malwa District. Annexure – 11. As far as the land cost is concerned, it has been arrived by addining the land cost of all impacted Villages and after taking out an average cost of the area which is reasonaly high. The budget has been prepared based on 15% of the land cost for payment of compensation as per Pipeline Act which seems to be low.
72
XI. INSTITUTIONAL ARRANGEMENTS AND CAPACITY DEVELOPMENT
A. Institutional Requirement
156. For implementation of LARP of the Project there will be a set of institutions involved at
various levels and stages of the subproject. For successful implementation of the LAP the
proposed institutional arrangement with their role and responsibility has been outlined in this
section. The primary institutions, which will be involved in this implementation process, are the
following:
(a) Project Implementation Unit (PIU)/ Project Management Unit (PMU)
(b) Land Valuation Committee (LVC)-Section 26 of the act defines the method by which market value of the land shall be computed under the proposed law. A Land Valuation Committee is formed under the Chairmanship of the concerned District Collector to assess the prevailing market value of the land. Based on this Collector’s Guideline is published based on a multiple of market value.
(c) Village Level Committee (VLC)- It is the duty of Gram Sabha to perform not
only functions of fixing accountability over the Panchayat but, also to make it an executive body with separate standing village level committees (VLC) entrusted with several functions for overall development of the Village.
(d) PMU Level Grievance Redress Committee
B. Executing Agency
157. The Executing Agency (EA) for the Project is the Ministry of Water Resources,
Government of Madhya Pradesh, and the Implementing Agency (IA) is Water Resources
Department, GOMP. The existing Branch Office at Zeerapur Tehsil Head Quarter has already
been established which will be the PIU/PMU. This office will be functional for the whole
Subproject duration.
C. Land Acquisition Management at PIU/PMU
158. PIU/PMU headed by a Project Director (PD) responsible for the overall execution of the
subproject. The PD will be responsible for (i) overall implementation of R&R activities according
to the RP and equally responsible for land acquisition and R&R activities in the field; (ii) ensure
availability of budget for R&R activities; (iii) liaison with district administration for support for land
acquisition and implementation of R&R.
159. The PIU/PMU will appoint/depute one full-time Manager level official as the
Resettlement Officer (RO) for the entire duration of resettlement activities, with relevant
experience in land acquisition and resettlement issues. The PIU will maintain all data base and
work closely with DPs and other stakeholders. Based on regularly updated data, a central
database will also be maintained by PIU.
73
160. The PIU/PMU officials and RO will require to enhance their capacities in R&R
implementation. The staff will undergo an orientation and training in resettlement management
at the beginning of the project. . The training activities will focus on issues concerning (i)
principles and procedures of land acquisition, (ii) public consultation and participation, (iii)
entitlements and compensation disbursement mechanisms, (iv) Grievance Redressal, and (v)
monitoring of resettlement operation. The training would specifically focus on the differences
between provisions of ADB policy and the relevant country laws. The awareness of these
differences and the need to follow the provisions of the ADB *Policy are critical for successful
implementation of the LARP.
161. The RO will work closely with the District Collector to expedite the payments of
compensation for land acquisition and assistance to DPs. The RO will be assisted by the
support staff for planning and implementation of resettlement activities in the subproject. Some
of the specific functions of the PIU with regard to resettlement management will include:
(a) Overall responsibility of implementation and monitoring of R&R activities in the Project;
(b) Ensure availability of budget for R&R activities; (c) Liaison lined agencies support implementation of R&R; (d) Coordinating with line Departments. (e) Translation of RP in local language; (f) Liaison with district administration for dovetailing government’s income
generating and developmental programs for the DPs; (g) Ensure the inclusion of those DPs who may have not been covered during the
census survey; (h) facilitate the opening of accounts in local banks to transfer assistance to DPs,
and organize the disbursement of Cheque for assistance in the affected area in public;
(i) Monitor physical and financial progress on land acquisition and R&R activities; (j) Participate in regular meetings in GRC; and (k) Organize monthly meetings to review the progress on R&R.
162. The roles and responsibilities of various agencies to be involved in resettlement planning
process and implementation of resettlement activities are summarized in following Table 24
Table 24: Agencies Responsible for Resettlement Implementation Key Agency Responsibility
EA (WRD) • Make final decision on pipelines alignment to be included under the project
• Overall responsibility for project design, feasibility, construction and operation and guide PIU
• Ensure that sufficient funds are available to properly implement all agreed social safeguards measures
• Ensure that all subprojects comply with the provisions of ADB’s SPS 2009 and GOI’s policies and regulations
• Submit semi-annual safeguards monitoring reports to ADB Project Implementation Units/PMU
• Disseminate project information to the project affected community with assistance from DPR Consultant
• Ensure establishment of Grievance Redress Committee at the
74
Key Agency Responsibility district level for grievance redress with assistance from DPR Consultant
• Approve LAP prepared by DBO contractor
• Disclosure of project information in public spaces and through relevant media.
• Disseminate project information to the community in coordination with DPR Consultants
• Facilitate the socioeconomic survey and census • Facilitate consultation by the civil works contractor with community
throughout implementation • Oversee land acquisition and coordinate with Deputy Commissioner • Supervise the mitigation measures during implementation and its
progress • Conduct internal monitoring and prepare reports
DBO Contractor
• Recruit R&R staff and establish LA team/unit. The team leader should have experience in R&R preparation and implementation based on the Government of India and ADB requirement
• Undertake consultations involving community and DPs • Prepare due diligence report if no land acquisition • Prepare LAP in accordance to the LAF, and obtain approval of LAP
from PIU/PMU prior implementing payment to DPs • Encourage community/ DPs to voluntarily participate during the
implementation • Consult community and PIU regarding location of construction
camps and sign agreement with titleholder for temporary use of land and restore the land to equal or better condition upon completion
• Pay compensation for temporary acquisition for laying pipeline based on LAP
• Commence construction only when alignment is free of encumbrance
• Respond in a timely fashion to recommendations from GRCs District level officials • Provide any existing socioeconomic information, maps and other
related information to DPR Consultant prior to the field data/information collection activities.
• Act as the local focal point of information dissemination • Execute land acquisition process
Community Based Organizations
• Ensure the community participation at various stages of the project • Coordination with stakeholder organizations • Assist in Monitoring of the project
Village Level Committee
• Provide correct data and information from project formulation stage • Assist the project team in redressal of grievances and to implement
the project smoothly • Arrange proper community participation
ADB • Review RF and due diligence / RP and endorse or modify the project classification
• Review planning documents and disclose the draft and final reports on the ADB’s website as required
75
Key Agency Responsibility
• Monitor implementation through review missions • Provide assistance to the EA and IA of subprojects, if required, in
carrying out its responsibilities and for building capacity for safeguard compliance
• Monitor overall compliance of the project to ADB SPS
D. Capacity Building on RP in the EA
163. Water Resources Department of Government of Madhya Pradesh is a fully owned
Department of the Ministry of Water Resources, Government of Madhya Pradesh. WRD has
required experience in planning and managing land acquisition and R&R activities. The WRD
has already established a PIU headed by Executive Engineer who will be acting as the Project
Director and will be supported by a Resettlement Officer (RO) for dealing with the land
acquisition and resettlement for the subproject.
164. All concerned staff both at head office and field level involved in land acquisition
activities will undergo an orientation and training in ADB resettlement policy and management.
Broadly, the training will cover various topics such as (i) Principles and procedures of land
acquisition; (ii) Public consultation and participation; (iii) Entitlements and Compensation &
assistance disbursement mechanisms; Grievance redress; and (iv) Monitoring of resettlement
operations. These will be covered through a formal workshop by the consultant under the
ongoing technical assistance program. The specific components under the training will cover the
following:
(a) Understanding of the ADB Policy Guidelines and requirements and differences
between country policy and laws
(b) Understanding of the policy and procedure adopted for the Subproject
(c) Understanding of the Implementation Schedule activities step-by-step
(d) Understanding of the Monitoring and reporting mechanism
(e) Understanding of the economic rehabilitation measures
76
XII. IMPLEMENTATION SCHEDULE
A. Introduction
165. Implementation of LAP mainly consists of compensation to be paid for affected land,
structures and rehabilitation and resettlement activities. The time for implementation of LAP will
be scheduled as per the overall subproject implementation. All activities related to the land
acquisition and resettlement must be planned to ensure that compensation is paid prior to
displacement and commencement of civil works. The EAs and PIU will ensure that no physical
or economic displacement of displaced households will occur until: (i) compensation at full
replacement cost has been paid to each displaced person for project components or sections
that are ready to be constructed; (ii) other entitlements listed in the resettlement plan are
provided to the displaced persons; and (iii) a comprehensive income and livelihood rehabilitation
program, supported by adequate budget, if any, should be in place to help displaced persons,
improve, or at least restore, their incomes and livelihoods.
166. If the detailed design for pumping station, rising man, and distribution chamber will be
revised during detailed design, the updated LAP will need to be prepared by the DBO contractor
and submit for approval by Government and ADB. The updated LAP will be disclosed prior to
implementation. Public consultation, monitoring will be undertaken routinely throughout the
subproject duration. However, the schedule is subject to modification depending on the
progress of the subproject activities.
77
SL No.
Activity 2019 2020
June July December January February March Project Preparation
1 Identifications of DPs
2 Conduct socioeconomic survey, census
3 Prepare social safeguard documents
4 ADB and Government approval of RPs
5 Appointment of Resettlement Officer
Land Acquisition for Non-Sample Projects
6 Land Acquisition
7 Payment of Compensation
8 Relocate houses, shops, businesses Rehabilitation of DPs
9 Income Restoration (if required)
10 Restoration of Community Resources Construction
11 Issue Notice for Start of Civil Work
12 Civil works Ongoing Activities
13 Grievance Redressing 14 Consultations with DPs 15 Internal Monitoring
16 External Monitoring (if required)
78
XIII. MONITORING AND REPORTING
A. Need for Monitoring and Reporting
167. Monitoring and reporting are critical activities in resettlement management in order to
ameliorate problems faced by the DPs and develop solutions immediately. Monitoring is a
periodic assessment of planned activities providing ongoing inputs. It facilitates change and
gives necessary feedback of activities and the directions on which they are going. In other
words, monitoring apparatus is crucial mechanism for measuring subproject performance and
fulfillment of the subproject objectives.
B. Monitoring by PIU
168. One of the main roles of PIU will be to see proper and timely implementation of all
activities in LAP. Monitoring will be a regular activity for PIU and Resettlement Officer at this
level will see the timely implementation of R&R activities. PIU will prepare monthly reports on
the progress of LAP Implementation. PIU will collect information from the subproject site and
assimilate in the form of monthly report to assess the progress and results of LAP
implementation and adjust work program where necessary, in case of delays or any
implementation problems as identified. This monitoring will form parts of regular activity and
reporting on this will be extremely important in order to undertake mid-way corrective steps. The
monitoring by PIU will include:
(a) administrative monitoring: daily planning, implementation, feedback and trouble shooting, individual DP database maintenance, and progress reports;
(b) socio-economic monitoring: case studies, using baseline information for comparing DP socio-economic conditions, evacuation, demolition, salvaging materials, morbidity and mortality, community relationships, dates for consultations, and number of appeals placed; and
(c) Impact monitoring: Income standards restored/improved, and socioeconomic conditions of the displaced persons. Monitoring reports documenting progress on resettlement implementation and RP completion reports will be provided by the PIU for review and approval from ADB.
C. Monitoring Indicators
169. The most crucial components/indicators to be monitored are specific contents of the
activities and entitlement matrix. The LAP/RP contains indicators and benchmarks for
achievement of the objectives under the resettlement program. These indicators and
benchmarks are of three kinds:
(a) Process indicators including subproject inputs, expenditures, staff deployment,
etc. (b) Output indicators indicating results in terms of numbers of affected people
compensated and resettled, training held, credit disbursed, etc and (c) Impact indicators related to the longer-term effect of the subproject on people's
lives.
79
D. Reporting Requirements
170. Land Acquisition and Resettlemet Plan implementation for the subproject will be closely
monitored by the EA which is Water Resources Department of GOMP. Keeping in view the
significance of resettlement impacts of the overall project, the monitoring mechanism for this
project will have monitoring by the Project Management Unit (PMU). PIU is responsible for
implementation of the Land Acquisition and Resettlement Plan. PIU will prepare monthly
progress reports on resettlement activities and submit to PMU. The Project Management Unit
(PMU) of WRD will submit semi-annual monitoring reports to ADB. All the LARP-monitoring
reports will be disclosed to DPs as per procedure followed for disclosure of resettlement
documents by the EA. The monitoring reports will also be disclosed on ADB’s website.
80
Annexure 1 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 1700 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fuit Trees
Orange Category
Other Trees
1 721
GOVT. LAND, SER ALAM, SERGUL KHAN, LIYAJ KHAN, IKBAL, SARAFRAJ KHAN, BABULAL, KHUB CHAND, BAGIRATHA, YAKUB KHAN, LIYAKAT KHAN
Molyakhedi
7.15, 0.153, 1.007, 1.007, 1.007, 1.007, 0.487, 0.488, 0.488, 0.993, 0.993 0.218
2 654 BADRILAL LAKSHMINARAYAN
Deharigujar 2.04 0.037
3 654 1.Ghanasyam F. Lakshminarayan, 2.Badrilal F. Lakshminarayan
Deharigujar 0.4, 1.64
0.017
4 652 Govt. Land Deharigujar 2.72 0.002
5 651 Radhesyam, Ghansyam, Atmaram, Govind F. Narayana
Deharigujar 1.04 0.026
6 650 Govt. Land Deharigujar 0.75 0.019
7 649 Govt. Land Deharigujar 0.05 0.005
8 648/1 Tolaram F. Ramratan Deharigujar 0.87 0.020 1 A
9 648/2 Bondarsingh F. Samandarsingh
Deharigujar 0.6 0.000
10 215
GANGA RAM, PREMNARAYANA, DHIRAPA SINGH, RAMCHARANA, BALAHABAPRASADA, RAJAKUMBARA BAI, DURGA LAL
Dharola
0.687, 0.687, 0.687, 0.687, 3.156, 1.045, 1.675
0.017
81
11 215
GANGA RAM, PREMNARAYANA, DHIRAPA SINGH, RAMCHARANA, BALAHABAPRASADA, RAJAKUMBARA BAI, DURGA LAL
Dharola
0.687, 0.687, 0.687, 0.687, 3.156, 1.045, 1.675
0.051
12 640 Lakshminarayana F. Tholaram Deharigujar 1.21 0.022
13 620 Chhamabai H. Dayaram Deharigujar 0.35 0.000
14 619 1.Hokamsingh F. Banshilal 2.Badrilal F. Lala
Deharigujar 0.23, 0.15
0.019
15 618 Sharadabai H. Vallabh Deharigujar 0.36 0.024
16 617 Govt. Land Deharigujar 0.19 0.005
17 615 Govt. Land Deharigujar 0.23 0.005
18 548 1.Sitaram F. Gangaram, 2.Prahlad F. Gangaram
Deharigujar 0.17, 0.36
0.020
19 547 1.Madanlal F. Bheru, 2.Bahadarsingh F. Nanuram
Deharigujar 0.19, 0.38
0.010
20 190 NANU RAM Dharola 1.442 0.019
21 191 DURGA LAL Dharola 0.355 0.009
22 192 GOBARDHANA, HAKAMASINGH, MADANA
Dharola 0.14, 0.215, 0.345
0.031
23 193 SHITA BAI Dharola 0.575 0.005
24 194 MUTHARA LAL, SAGITA BAI, RODU LAL
Dharola 0.326, 0.364, 0.774
0.032
25 182 GOVT. LAND Dharola 0.512 0.024
26 179 GIRI RAJA, KALU RAM Dharola 0.157, 0.564
0.017
27 178 SURESH CHANDRA Dharola 1.494 0.031
28 177 SHITA BAI Dharola 1.212 0.017
29 177 SHITA BAI Dharola 1.212 0.009
30 176 SHITA BAI Dharola 0.961 0.017
31 174 SHANTI BAI, GIRI RAJ BADRILAL
Dharola 0.219, 0.438
0.001
32 175 RODU LAL RATAN LAL Dharola 0.314 0.026 2 B
33 770 GIRI RAJ BHAWAR LAL, SHANTI BAI
Dharola 0.408, 0.710
0.034 3 B
34 141 BABU LAL BHAWAR LAL, RODU LAL RATAN LAL
Dharola 0.428, 0.418
0.017 2 B
35 771 BALLABH PRASAD GIRI RAJ, GORDHAN KALURAM
Dharola 0.428, 0.428
0.039
82
36 776 GOVT. LAND Dharola 0 0.019
37 775 1.Govt. Land, 2.Dariyavbai H. Bhanwarlal
Dharola 0, 0.084 0.007
38 780 Nanuram F. Gangaram Dharola 0.669 0.013
39 781 Govt. Land Dharola 0 0.007
40 782 Govt. Land Dharola 0.188 0.002
41 742 1.Nanuram F. Gangaram, 2.Babulal, Giriraj F. Jagadhish
Dharola 0.115, 0.405
0.024
42 869 Govt. Land Dharola 0.031 0.007
43 867 Govt. Land Dharola 0 0.024
44 866 Bhanwarbai H. Kesharsingh Dharola 0.94 0.007
45 883 Mahendrasingh F. Bhagawansingh
Dharola 0.073 0.007 4 A
46 882
1.Govt. Land, 2.Ranjithsingh, Harisingh, Suratsingh, Gokalsingh F. Karansingh
Dharola 0.031, 0.01
0.003
47 865 Mahendrasingh F. Bhagawansingh
Dharola 0.909 0.014
48 885 Chattarsingh F. Chandarsingh Dharola 0.763 0.029
49 885 Chattarsingh F. Chandarsingh Dharola 0.763 0.005
50 889 Govt. Land Dharola 0.261 0.003
51 892 Govt. Land Dharola 0 0.010
52 893 Govt. Land Dharola 0 0.002
53 891 1.Sharada H. Shivlal, 2.Pannalal F. Ghisa
Dharola 0.23, 0.199
0.005 2,6 C,A
54 890 Govt. Land Dharola 0.261 0.003
55 904 Dinesh F. Balchand Dharola 0.115 0.003
56 905 Govt. Land Dharola 0.418 0.005
57 906 Govt. Land Dharola 0.188 0.006
58 907 Shantibai H. Pirulal Dharola 0.774 0.022
59 908 Pannalal F. Ghisa Dharola 1.264 0.034
60 1000 1.Purabai H. Badrilal, 2.Lalithabai H. Banshilal
Dharola 0.868, 0.867
0.031 2,2 B,C
61 999 Govt. Land Dharola 0.449 0.007
62 991 Balu, Tulsiram F. Mangu Dharola 0.125 0.005
63 990 Siddnath, Ramprasad F. Devisingh
Dharola 0.105 0.009
64 970 1.Kedar F. Bhagchand, 2.Nandram, Radhesyam F. Badrilal
Dharola 0.052, 0.355
0.030
65 969 Govt. Land Dharola 0.46 0.015
66 958 Pannalal F. Shivlal Dharola 0.031 0.003
83
67 959 Rameswar, Ramkaran, Vishnulal, Badrilal F. Bapulal
Dharola 0.533 0.020
68 952 1.Siddnath, Ramprasad F. Devisingh, 2.Sundarlal F. Dhulichand
Dharola 0.084, 0.125
0.009
69 1142 Govt. Land Dharola 0.167 0.007
70 1132 Govt. Land Dharola 0.282 0.005
71 1143 1.Mohanlal F. Ramchandra, 2.Govt. Land
Dharola 0.24, 0.355
0.002
72 1144 Govt. Land Dharola 0.261 0.004
73 1161 1.Sithabai H. Gopilal, 2.Govt. Land
Dharola 1.045, 0.575
0.034
74 1131 Govt. Land Dharola 0.219 0.003
75 1130 Govt. Land Dharola 0.993 0.029
76 1126 Siddhu F. Chitha Dharola 0.094 0.003
77 1238 1.Shankarlal F. Narsingh, 2.Kamal F. Ukarlal
Dharola 1.045, 0.24
0.015
78 1234 1.Mohanlal F. Ramchandra, 2.Satyanarayana F. Ramchandra
Dharola 0.504, 0.505
0.017
79 1235 1.Govt. Land, 2.Trilokchand F. Siddardh
Dharola 0, 0.8 0.026
80 1235 1.Govt. Land, 2.Trilokchand F. Siddardh
Dharola 0, 0.8 0.005
81 1236 1.Balu F. Amara, 2.Mohanlal F. Dhannalal
Dharola 1.672, 0.470
0.061 12 A
82 1233 1.Govt. Land, 2.Jagannath F. Bapulal
Dharola 0.69, 2 0.005
83 1252 Govt. Land Dharola 0.449 0.003
84 1253 1.Govt. Land, 2.Badrilal F. Manna
Dharola 1.923, 1.045
0.043
85 1263 Sri Ram Mandir Dharola 1.411 0.031
86 1264 Rameswar F. Kanwarlal Dharola 1.902 0.038 9 B
87 1547 Kousalyabai H. Rameswar Dharola 0.585 0.015
88 1546 Kousalyabai H. Rameswar Dharola 0.282 0.015
89 1545 Badrilal F. Gordhanlal Dharola 0.272 0.010
90 1544 Bherulal F. Badrilal Dharola 0.272 0.015
91 1537 Bherulal F. Badrilal Dharola 0.554 0.017
92 1519 1.Gopal, Babulal F. Banshilal, 2.Mohanlal F. Dhannalal
Dharola 0.763, 0.575
0.032
93 1693 Githabai H. Banshilal Dharola 0.345 0.027
94 1690 1.Githabai H. Banshilal, 2.Yuvrajsingh F. Lalsingh
Dharola 0.364, 0.282
0.027 6 A
84
95 1704 1.Yuvrajsingh F. Lalsingh, 2.Narayansingh F. Banesingh
Dharola 0.464, 0.581
0.031 6 A
96 1686 Govt. Land Dharola 0.92 0.003
97 1730 1.Rameswar, Syam, Omkarlal F. Rajaram, 2.Gangabai H. Mohanlal
Dharola 0.588, 0.144
0.063
98 1731 1.Sangitha Bai H. Dineshkumar, 2.Govindsingh F. Banesingh
Dharola 0.47, 0.4
0.041 6 A
99 1732 1.Syamlal F. Mathuralal, 2.Munnibai H. Chothmal
Dharola 0.105, 0.344
0.019 3 C
100 1656 1.Syamlal F. Mathuralal, 2.Dilip F. Syamlal
Dharola 0.671, 0.024
0.003 4 B
85
Annexure 2 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 1600 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 1656 1.Syamlal F. Mathuralal, 2.Dilip F. Syamlal
Dharola 0.671, 0.024
0.031
2 1659 Dilip F. Syamlal Dharola 0.69 0.026
3 1660 Chothmal F. Mathuralal Dharola 0.721 0.021 8 A
4 1661 1.Munnibai H. Chothmal, 2.Govt. Land
Dharola 0.355, 0.637
0.018
5 1651 1.Syamlal F. Mathuralal, 2.Rodmal F. Mathuralal
Dharola 0.209, 0.679
0.026 6 A
6 1650 GOVT. LAND Dharola 2.142 0.019
7 1650 GOVT. LAND Dharola 2.142 0.043
8 1835 GOVT. LAND Dharola 0.23 0.042
9 1834
BHABAR LAL, AMRA, SIBANARAYANA, RODU, KALU, HINDU, BADRI LAL, GANGARAM, LALU
Dharola
0.627, 0.053, 0.617, 0.627, 0.418, 0.627, 0.617, 0.627, 0.418
0.016
10 1834
BHABAR LAL, AMRA, SIBANARAYANA, RODU, KALU, HINDU, BADRI LAL, GANGARAM, LALU
Dharola
0.627, 0.053, 0.617, 0.627, 0.418, 0.627, 0.617, 0.627, 0.418
0.037
11 1857 GOVT. LAND Dharola 0.094 0.008
12 1645 GOVT. LAND Dharola 18.709 0.046
86
13 219 RAMA NARAYANA, SITA RAMA, RADHESYAMA, RAMA PRASAD
Padana
0.209, 0.08, 0.11, 0.019
0.028
14 221 KAMALESH Padana 2.067 0.022
15 221 KAMALESH Padana 2.067 0.021
16 226 SRI MAHA DEV Padana 0.993 0.040
17 225 CHANDRA, KALU, RAMEH CHANDRA
Padana 0.518, 0.411, 0.419
0.051 1 A
18 225 CHANDRA, KALU, RAMEH CHANDRA
Padana 0.518, 0.411, 0.419
0.005
19 223 GOVT. LAND Padana 0 0.026
20 254 KAMALESH Padana 1.055 0.038
21 258 GOVT. LAND Padana 0.46 0.022
22 518
MAHESH, KALU RAMA, NANDA RAMA, LALA SINGH, BHABARA LAL, CHANDRA SINGH
Padana 0.073, 0.627,
0.016 4 B
23 517 MAHESH Padana 0.105 0.006
87
Annexure 3 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 1500 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 517 MAHESH Padana 0.105 0.006
2 516 SIBA LAL Padana 0.293 0.012
3 513 RAMA CHANDA Padana 0.941 0.053
4 504 RAMCHAND F. KANIRAM Padana 0.314 0.000
5 513 Ramchand F. Kaniram Padana 0.941 0.000 9 A
6 504 Ramchand F. Kaniram Padana 0.314 0.018 2 A 1
7 505 Govt. Land Padana 0.282 0.006
8 505 Govt. Land Padana 0.282 0.019
9 499 Ramlal F. Shivsingh Padana 0.324 0.026
10 489 Ramchandra F. Kaniram Padana 0.209 0.009 5 B
11 455 1.Bherusingh F. Motilal, 2.Ramsingh F. Motilal
Padana 0.084 0.007
12 487 Jasodabai, Leelabai, Bhulibai, Syamubai, Rukmabai F. Banwarlal
Padana 0.282 0.007 4 B
13 487 Jasodabai, Leelabai, Bhulibai, Syamubai, Rukmabai F. Banwarlal
Padana 0.282 0.008
14 483 Siddnath F. Mangilal Padana 0.11 0.012
15 479 1.Govt. Land 2.Sanjay F. Badrilal
Padana 0,
0.079 0.013
16 477 1.Siddnath F. Mangilal, 2.Govt. Land
Padana 0.094,
0 0.009
17 476 Balusingh F. Parbatsingh Padana 0.219 0.004
18 475 1.Andarsingh F. Bhuwan, 2.Karansingh F. Indarsingh
Padana 0.115, 0.115
0.004
19 473 1.Dheerajsingh, Kishan F. Udhesingh, 2.Bherusingh F. Motilal
Padana 0.178, 0.094
0.003
88
20 473 1.Dheerajsingh, Kishan F. Udhesingh, 2.Bherusingh F. Motilal
Padana 0.178, 0.094
0.008
21 471 1.Pursingh F. Karansingh, 2.Mathurabai H. Gokulsingh
Padana 0.102, 0.204
0.015
22 469 Govt. Land Padana 0.009
23 460 1.Gangaram F. Bhagawansingh, 2.Ramlal F. Mangilal
Padana 0.011, 0.021
0.000
24 459 Mangilal F. Dhula Padana 0.219 0.012 8 A
25 463 Govt. Land Padana 0.073 0.011
26 462 Govt. Land Padana 0 0.001
27 464 1.Tejsingh F. Antharsingh, 2.Devisingh F. Bherusingh
Padana 0.113, 0.185
0.007
28 607 Govt. Land Padana 0.836 0.009
29 608 Govt. Land Padana 0.293 0.002
30 605 Durgesh F. Devilal Padana 0.835 0.041
31 620 1.Govt. Land 2.Ayodyabai H. Pannalal
Padana 0,
0.157 0.018
32 622 Ayodyabai H. Pannalal Padana 0.502 0.015
33 623 Niranjan F. Kanhaiyalal Padana 0.627 0.008
34 1069 1.Ayodyabai H. Pannalal, 2.Bardibai H. Ramsingh
Padana 1.881 0.006
35 1069 1.Ayodyabai H. Pannalal, 2.Bardibai H. Ramsingh
Padana 1.881 0.066
36 1006 1.Seethabai, Banshilal 2.Parbatsingh F. Omkarsingh
Padana 0.094, 0.063
0.011
37 1007 Seethabai, Banshilal Padana 0.732 0.030
38 1003
1.Devisingh, Gokulsingh F. Bherulal, 2.Dheerajsingh, Kishan F. Udhesingh
Padana 0.46, 0.356
0.060
89
Annexure 3 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 1400 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 1003
1.Devisingh, Gokulsingh F. Bherulal, 2.Dheerajsingh, Kishan F. Udhesingh
Padana 0.46, 0.356
0.034
2 1001 Tejbai H. Ramnarayana Padana 0.763 0.018
3 1000 1.Balusingh F. Parbatsingh, 2.Pursingh F. Karansingh
Padana 1.091, 0.545
0.000
90
Annexure 4 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 1300 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 1000 1.Balusingh F. Parbatsingh, 2.Pursingh F. Karansingh
Padana 1.091, 0.545
0.046
2 999 Pursingh F. Karansingh Padana 0.432 0.014
3 969 1.Mangilal, Balusingh F. Amara 2.Narayana F. Raysingh
Padana 0.972, 0.941
0.068
4 968 Govt. Land Padana 0.105 0.002
5 950 1.Mangilal F. Dhula, 2.Antarsingh F. Mangilal
Padana 1.212, 0.095
0.051
6 950 1.Mangilal F. Dhula, 2.Antarsingh F. Mangilal
Padana 1.212, 0.095
0.010
7 946 1.Mangilal, Balchand F. Kalu, 2.Fathesingh, Abhaysingh F. Dhariyav
Padana 0.282, 0.282
0.008
8 932 1.Dayaram F. Nanda 2.Ramlal F. Devisingh
Padana 0.874, 0.251
0.068 4 B
9 932 1.Dayaram F. Nanda 2.Ramlal F. Devisingh
Padana 0.874, 0.251
0.018 1 B
10 940 1.Madhusudhan F. Ramchand, 2.Asharam F. Kalu
Padana 1.066, 0.324
0.014
11 945 Govt. Land Padana 0.261 0.003
12 944 1.Asharam F. Kalu, 2.Kanhaiyalal F. Nandram
Padana 0.094, 0.836
0.029
13 943 Govt. Land Padana 2.424 0.026
91
Annexure 5 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 900 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 654 BADRILAL LAKSHMINARAYAN
Deharigujar 2.04 0.005
2 651 RADHESHYAM DHANSHYAM NARAYAN
Deharigujar 1.04 0.011
3 219 BISHUNU DASH, RADU Dharola 0.865, 1.135 0.014
4 220 KALU RAM, BHAGIRATHA Dharola 0.667, 0.667 0.042
5 221 CHANDARA SINGH, PRAVULAL, BANESINGH, RAMCHARANA
Dharola
1.861, 1.861, 0.93, 0.93 0.005
6 222 GOVT. LAND Dharola 0.251 0.002
7 223 CHANDARA SINGH Dharola 1.274 0.012
8 224 PREMCHAND, RADU, GORILAL, RAMA PRASADA, PRABALA KUMARA, ISWARA
Dharola
3.344, 1.077, 5.333, 0.941, 1.306, 2.019 0.018
9 211 GOVT. LAND Dharola 0.031 0.009
10 210 BABU, SHIDDHI BAI Dharola 2,
1.492 0.063
11 210 BABU, SHIDDHI BAI Dharola 2,
1.492 0.068
12 237 RADU, PREMA CHANDRA, GORI LAL, PURA LAL, NARMADA BAI
Dharola
0.282, 0.094, 2.33,
0.784, 2.09 0.028
92
13 237 RADU, PREMA CHANDRA, GORI LAL, PURA LAL, NARMADA BAI
Dharola
0.282, 0.094, 2.33,
0.784, 2.09 0.035
14 246 RODU Dharola 0.366 0.021
15 293 GOVT. LAND Dharola 0.721 0.001
16 279 SANGITA BAI Dharola 0.46 0.001
17 278 SANGITA BAI Dharola 0.554 0.007
18 278 SANGITA BAI Dharola 0.554 0.001
19 317 GIRI RAJA Dharola 0.24 0.005
20 321 GIRI RAJA Dharola 0.324 0.002
21 322 GHISHA LAL, DINESHA Dharola 1.704, 0.941 0.022
22 363 DHAPU BAI, GOPALA Dharola 0.063, 0.303 0.005
23 362 DHAPU BAI Dharola 0.752 0.012
24 361 GHANASYAMA Dharola 0.721 0.012
25 360 BABU LAL Dharola 0.105 0.005
26 359 DEVI SINGH Dharola 0.836 0.005
27 379 BABU LAL, DEVI SINGH, KALU RAM
Dharola 0.167, 0.157, 0.021 0.001
28 379 BABU LAL, DEVI SINGH, KALU RAM
Dharola 0.167, 0.157, 0.021 0.006
29 398 GOVT. LAND Dharola 0.784 0.002
30 407 SURESHA KUMAR, UMILI BAI, DEVI SINGH, BISHNU
Dharola
1.912, 0.7,
0.956, 0.956 0.032
31 408 GHANASYAMA Dharola 0.773 0.059
32 2778 GOVT. LAND Dharola 5.351 0.023
33 2779 GOVT. LAND Dharola 0.073 0.002
34 2791 RODU, VERU, MOHAN Dharola 2,
0.836, 0.418 0.041
35 2792 GOVT. LAND Dharola 0.105 0.002
36 2796 GOVT. LAND Dharola 3.396 0.029
37 2793 MOHAN Dharola 1.359 0.000
38 2799 MOHAN Dharola 1.359 0.023
39 2801 RAM KARAN GANGARAM, BHAGIRATH GANGARAM
Dharola 1.583, 1.583 0.037
93
40 2802 RAMKARAN, BALU, DEBA, GIRDHARI, RAMESH CHANDRA, BALDEB
Dharola
0.436, 0.436, 0.873, 0.872, 0.982, 0.508 0.004
41 2803 GOVT. LAND Dharola 0.261 0.004
42 2804 BAGIRATHA, AMRA, RODU, SANKAR, DEBA
Dharola
1.15, 0.765, 0.765, 0.766, 0.766 0.032
43 504 RAMCHAND F. KANIRAM Padana 0.314 0.005 3 B
44 509 RAMCHAND F. KANIRAM Padana 0.178 0.009
45 508 1.RAMCHAND F. KANIRAM 2.KANHAIYALAL F. MATHURALAL
Padana 1.641, 0.418
0.023 4 A
46 493 1.KANHAIYALAL F. MATHURALAL 2.RAMLAL F. SHIVSINGH
Padana 0.14, 0.299
0.009 1 A
47 592 GOVT. LAND Padana 0.199 0.003
48 594 KARANA SINGH Padana 0.92 0.015
49 600 GOKULA SINGH, RAMA SINGH, BABU SINGH, CHANDRA SINGH
Padana
0.06, 0.06, 0.06, 0.06, 0.06
0.009
50 1115
1.JAMALSINGH, GOKULSINGH, BANESINGH 2.BALU, RUGNATH, SIDDU, KALU
Padana 2.055, 1.17
0.045
94
Annexure 6 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 800 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha) Aff Area
Fruit Trees
Orange Category
Other Trees
1 2804 BAGIRATHA, AMRA, RODU, SANKAR, DEBA
Dharola 1.15, 0.765,
0.765, 0.766, 0.766 0.016
2 2614 JANAKILAL, RODMAL, GIRIRAJ, NARAYANA, KISAN LAL, SAMBHU LAL
Dharola 1.812, 1.275, 1.625, 0.93, 0.841, 0.841 0.028
3 486 JANAKILAL KANHAEIYALAL Pheti 1.87 0.030
4 493 BIKRAM BHAWARLAL, RADHESHYAM NATHULAL
Pheti 2.2 0.015
5 494 DEVISINGH NATHULAL, BHEIRULAL BHAWARLAL, RADHESHYAM NATHULAL
Pheti 2.26
0.015
6 509
SHIBANARAYAN SIDHANATH, NANADKISHORE SIDHANATH, BADRILAL KUWARLAL
Pheti 1.25
0.019
7 508
SHIBANARAYAN SIDHANATH, NANADKISHORE SIDHANATH, BADRILAL KUWARLAL
Pheti 1.59
0.035
8 506 MANGILAL NARAYAN Pheti 0.34 0.008
9 505 PRABHULAL NARAYAN, MAGILAL NARAYAN
Pheti 1.67 0.009
10 505 PRABHULAL NARAYAN, MAGILAL NARAYAN
Pheti 1.67 0.008
11 500 DILLIPKUMAR TARACHANDRA
Pheti 1.1 0.017 1
12 501 MANGILAL KANHAEIYALAL, MANJUDEVI ABHAYAKUMAR
Pheti 2.09 0.008
13 557 MANGILAL BASANTILAL, MANJUDEVI ABHAYAKUMAR
Pheti 1.04 0.002
95
14 557 MANGILAL BASANTILAL, MANJUDEVI ABHAYAKUMAR
Pheti 1.04 0.007
15 556 RAMAKUWARBAI RAMSINGH
Pheti 0.41 0.018
16 558 MANGILAL RAMACHANDRA, AMBARAM KANHAEIYALAL
Pheti 0.4 0.004
17 546 HARILAL GYARSILAL Pheti 0.56 0.008
18 692
DIPAK ISWAR SURESH SONABAI, RAMPRASAD GOPILAL, KANHAEIYALAL KALU
Pheti 2.3
0.024
19 689 RAMKUWARBAI RAMSINGH Pheti 0.3 0.004
20 688 KISHANLAL KANIRAM Pheti 0.3 0.014
21 687 DUGESH SHIBALAL Pheti 0.3 0.004
22 686 GOVT. LAND Pheti 0.3 0.004
23 684 DAKHABAI DIPCHAND Pheti 3.65 0.030
24 681 ABHAYAKUMAR TARACHAND
Pheti 1.94 0.006
25 681 ABHAYAKUMAR TARACHAND
Pheti 1.94 0.002
26 229/3 1.Dinesh F. Ramchandra, 2.Mangilal F. Motilal
Dokapura 0.331, 0.209 0.016
27 229/4 Rugnath F. Ramchandra Dokapura 0.993 0.014
28 229/4 Rugnath F. Ramchandra Dokapura 0.993 0.010
29 231/2 Govt. Land Dokapura 0.627 0.002
30 228 1.Govt. Land, 2.Krushi Upamandi Nalkheda
Dokapura 2.948, 6.8 0.011
31 259/1 Prakashchand F. Soubhagmal
Dokapura 1.996 0.023
32 259/1 Prakashchand F. Soubhagmal
Dokapura 1.996 0.003
33 256/3 Prakashchand F. Soubhagmal
Dokapura 0.214 0.006
34 256/2 Not Available Dokapura 0.597 0.008
35 256/5 Neha Karthika F. Vittal Das Dokapura 0.281 0.006
36 256/1 Anshul F. Vittal Das Dokapura 0.314 0.000
37 246/1 Kasthurchand F. Khuba Dokapura 0.836 0.007
38 246/1 Kasthurchand F. Khuba Dokapura 0.836 0.006
39 248 Jagadhish, Bhagawansingh, Radhesyam F. Kunwarlal
Dokapura 1.233
0.019
40 247 1.Mangilal, Leelabai, Sanjubai F. Puralal 2.Abdul Alim F. Mushi Khan
Dokapura 0.293, 0.627
0.005
96
41 1115
1.JAMALSINGH, GOKULSINGH, BANESINGH 2.BALU, RUGNATH, SIDDU, KALU
Padana 2.055, 1.17 0.015
42 1117 GOVT. LAND Padana 0.261 0.002
43 1118
BANESINGH HAJARILAL, DULESINGH GHANSI, KAILASH AMARSINGH, GIRDHARILAL DHANNA
Padana 0.209, 0.836, 0.251, 0.251
0.053
44 1118
BANESINGH HAJARILAL, DULESINGH GHANSI, KAILASH AMARSINGH, GIRDHARILAL DHANNA
Padana 0.209, 0.836, 0.251, 0.251
0.030
45 160 Mukesh F. Rajaram Gudrawan 0.58 0.014
46 159/1 Shantibai Gudrawan 0.34 0.002
47 159/2 Rugnath F. Deepa Gudrawan 0.45 0.002
48 152/2 Mangilal, Ramlal, Girdhari, Rajaram F. Bhagawansingh
Gudrawan 0.105 0.016 2 A
49 152/1 Jamalsingh, Banesingh, Gokulsingh F. Hajarilal
Gudrawan 0.43 0.008
50 43 Balu F. Deepa Gudrawan 0.4 0.000
51 151 Kevalsingh F. Gokalsingh Gudrawan 0.32 0.016
52 44 Bhimsingh F. Motisingh Gudrawan 1 0.004
53 49 1.Rampyari F. Banshilal, 2.Sampath Bai H. Kamalsingh
Gudrawan 1.52, 1.52 0.016
54 49 1.Rampyari F. Banshilal, 2.Sampath Bai H. Kamalsingh
Gudrawan 1.52, 1.52 0.006
55 50/3 Narbadhabai H. Harinarayana
Gudrawan 1.21 0.012
56 50/2 Narbadhabai H. Harinarayana
Gudrawan 1.21 0.008
57 51 1.Kanhaiyalal F. Gangaram, 2.Ramchandra F. Gangaram
Gudrawan 0.24, 0.24 0.012
58 98 1.Gopal F. Radhesyam 2.Kamal F. Radhesyam
Gudrawan 0.14, 0.38 0.010
59 111 1.Ramprasad F. Lala 2.Suresh F. Durgalal
Gudrawan 0.35, 0.13 0.001
60 99 Jayantibai H. Hiralal Gudrawan 0.18 0.005
61 110 Jayantibai H. Hiralal Gudrawan 1.42 0.000
62 109/1 Jayantibai H. Hiralal Gudrawan 1.01 0.006
63 109/2 Hamsabai H. Manishkumar Gudrawan 0.94 0.004 5 B
97
64 109/2 Hamsabai H. Manishkumar Gudrawan 0.94 0.004
65 108/1 Devisingh F. Hiralal Gudrawan 1.1 0.013
66 335 Govt. Land Gudrawan 2.29 0.003
67 352 Jayantibai H. Hiralal Gudrawan 1.19 0.020
68 349 Govt. Land Gudrawan 0.31 0.002
69 350 Premchand F. Mathuralal Gudrawan 0.5 0.002
70 350 Premchand F. Mathuralal Gudrawan 0.5 0.006 1 B
71 391 Premchand F. Mathuralal Gudrawan 0.6 0.010
72 390 Omprakash F. Mathuralal Gudrawan 0.61 0.014
98
Annexure 7 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 700 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 247 1.Mangilal, Leelabai, Sanjubai F. Puralal 2.Abdul Alim F. Mushi Khan
Dokapura 0.293, 0.627
0.006
2 250 1.Amanabi H. Ajij Khan 2.Mangilal, Leelabai, Sanjubai F. Puralal
Dokapura 0.209, 0.543
0.002
3 590 Abdul Rashid, Abdul Vahid F. Abdul Hafij
Dokapura 1.045 0.004
4 589 1.Hemalatha Bai H. Mukesh, 2.Deva Ji F. Nathu
Dokapura 0.034, 0.009 0.016
5 589 1.Hemalatha Bai H. Mukesh, 2.Deva Ji F. Nathu
Dokapura 0.034, 0.009 0.008
6 588
1.Abdul Rahim, Abdul Jalil, Abdul Vakil F. Shakur Khan 2.Govt. Land
Dokapura 0.679, 0.272
0.013
7 586
1.Abdul Rahim, Abdul Jalil, Abdul Vakil F. Shakur Khan 2.Mahendrakumar, Chatar F. Kanhaiyalal
Dokapura 0.575, 0.944
0.008
8 585 1.Abdul Mukim F. Abdul Hakim, 2.Rustham Khan F. Mamraj Khan
Dokapura 0.554, 0.554
0.001
9 585 1.Abdul Mukim F. Abdul Hakim, 2.Rustham Khan F. Mamraj Khan
Dokapura 0.554, 0.554
0.011
10 574 Vishnuprasad Brujamohan Krishnavallabh F. Radha Krishna
Dokapura 0.355
0.001
11 578 GOVT. LAND Dokapura 0 0.001
12 577 GOVT. LAND Dokapura 0 0.001
13 577 GOVT. LAND Dokapura 0 0.001
14 579 GOVT. LAND Dokapura 0 0.007
15 481 GOVT. LAND Dokapura 0.334 0.000
16 580 PIR KHAN Dokapura 0.042 0.001
99
17 508 GOVT. LAND Dokapura 1.275 0.001
18 509 GOVT. LAND Dokapura 0.366 0.004
19 518 SONERAB Dokapura 0.084 0.001
20 518 SONERAB Dokapura 0.084 0.006
21 526 MUBARIK KHAN, RAGHUNATHA RAB
Dokapura 0.739 0.005
22 1327 Saroja Devi H. Chintaman Nalkheda 0.073 0.002
23 1329 Saroja Devi H. Chintaman Nalkheda 0.188 0.002
24 1328 Saroja Devi H. Chintaman Nalkheda 0.178 0.008
25 1330 Ragunath Rao, Ashok Rao F. Balvanth Rao
Nalkheda 0.105 0.004
26 1325 Anshul F. Ragunath Rao Nalkheda 0.345 0.006
27 1325 Anshul F. Ragunath Rao Nalkheda 0.345 0.003 4 A
28 1313 Not Available Nalkheda 0.001
29 1266 Govt. Land Nalkheda 0 0.003
30 1265 Govt. Land Nalkheda 0 0.001
31 1264 Shabbir Khan F. Shakur Khan Nalkheda 0.387 0.006
32 1262 Shabbir Khan F. Shakur Khan Nalkheda 0.272 0.002
33 1261 1.Sardar Khan F. Noor Khan, 2.Aarif Khan F. Kamluddin Khan
Nalkheda 0.146, 0.157 0.006
34 1229 Jarinabai H. Jamaluddin Nalkheda 0.449 0.004
35 1230 Govt. Land Nalkheda 0 0.004
36 1250 Hasinabai H. Kamaluddin Nalkheda 0.303 0.001
37 1234 Jarinabai H. Jamaluddin Nalkheda 0.606 0.009
38 1239 Govt. Land Nalkheda 0.261 0.002
39 1023 Sardarbai H. Bhanwarlal Nalkheda 0.491 0.005
40 1023 Sardarbai H. Bhanwarlal Nalkheda 0.491 0.006
41 1022 Tilokchand, Syamlal F. Prabhulal
Nalkheda 0.439 0.015
42 729 Tilokchand, Syamlal F. Prabhulal
Nalkheda 0.031 0.002
43 728 Tilokchand, Syamlal F. Prabhulal
Nalkheda 0.052 0.002
44 726 Govt. Land Nalkheda 0 0.001
45 727 Abdul Jalil, Abdul Hanif F. Abdul Rashid
Nalkheda 0.439 0.000
46 727 Abdul Jalil, Abdul Hanif F. Abdul Rashid
Nalkheda 0.439 0.008
47 746 Kesharbai H. Bhanwarlal Nalkheda 0.334 0.010
48 747 Trilokchand F. Prabhulal Nalkheda 0.282 0.002
49 756 Bhanwaribai H. Prabhulal Nalkheda 0.356 0.001 3 B
50 757 Govt. Land Nalkheda 0.021 0.001
51 758 Govt. Land Nalkheda 0 0.001
100
52 764 Govt. Land Nalkheda 0.042 0.002
53 765 Not Available Nalkheda 0 0.002
54 766 Not Available Nalkheda 0 0.008
55 390 Omprakash F. Mathuralal Gudrawan 0.61 0.004
56 561 Badrilal F. Harilal Gudrawan 0.6 0.009
57 554 Dholathram F. Ramlal Gudrawan 0.27 0.009
58 534 Sureshkumar F. Hiralal Gudrawan 0.22 0.009
59 531 Jagannath F. Rugnath Gudrawan 0.11 0.001
60 530 Kousalyabai H. Govardhanlal Gudrawan 0.11 0.001
61 473 Mohanlal F. Devisingh Gudrawan 0.82 0.014
62 640 Paramanand F. Bhuvaniram Gudrawan 0.69 0.001
63 640 Paramanand F. Bhuvaniram Gudrawan 0.69 0.010
64 663 Sitharam F. Ramlal Gudrawan 0.42 0.001
65 662 Narbadhabai H. Harinarayana Gudrawan 0.5 0.011
66 667 Shivnarayana F. Keshoram Gudrawan 0.68 0.007
67 666 Govind F. Rameswar Gudrawan 0.49 0.011
68 693 Tilokchand F. Dholathram Gudrawan 1.76 0.029
69 693 Tilokchand F. Dholathram Gudrawan 1.76 0.005
70 692 Tilokchand F. Dholathram Gudrawan 0.5 0.000
71 694 1.Tilokchand F. Dholathram, 2.Rameswar F. Keshoram
Gudrawan 1.4, 1 0.029
72 734 Govardhanlal F. Ramkaran Gudrawan 0.76 0.007
73 733 Govardhanlal F. Gopal Gudrawan 0.82 0.011 6 A
74 732 Ghansyam F. Ramprasad Gudrawan 0.24 0.006
75 731 1.Ghansyam F. Ramprasad, 2.Gopal F. Ramprasad
Gudrawan 0.15, 0.4
0.001 12 A
76 720 Ghansyam F. Ramprasad Gudrawan 0.33 0.007 8 A
77 723 Bapulal F. Keshoram Gudrawan 1.11 0.003
78 722 Bhuvaniram, Kanhaiahlal F. Keshoram
Gudrawan 1.09 0.010
79 6 Lakkha F. Chatara Gudrawan 0.7 0.001
80 721/1 Dhigvijaysingh F. Vikramsingh Gudrawan 1.2 0.006
81 721/2 Pujabai H. Suresh Gudrawan 0.68 0.021
82 8 Lakkha F. Chatara Gudrawan 0.62 0.006
83 104 CHANDAR BAI F. KANA JI Najarkheda 1.41 0.005
101
Annexure 8 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 600 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 766 Not Available Nalkheda 0 0.003
2 762 Govt. Land Nalkheda 0 0.002
3 700/3 Babulal F. Bhanwarlal Nalkheda 0.461 0.003
4 701 Govt. Land Nalkheda 0 0.004
5 700/1 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan
Nalkheda 0.773
0.003
6 698/1 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan
Nalkheda 0.314
0.009
7 697 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan
Nalkheda 0.062
0.004
8 698/2/1 Not Available Nalkheda 0.073 0.002
9 696 Jabbarkhan, Ayayubkhan, Anisakhan F. Jhammankhan
Nalkheda 0.021
0.002
10 695 Habib Khan F. Rustham Khan Nalkheda 0 0.003
11 694 Habib Khan F. Rustham Khan Nalkheda 0.084 0.003
12 699 Govt. Land Nalkheda 0.073 0.001
13 812 Narayana F. Ghasiram Nalkheda 0.031 0.001
14 459 Mapi Mandir Sri Jayeswar Mahadev Ji
Nalkheda 0.899 0.007
15 481 Anisabi H. Ilak Khan Nalkheda 1.097 0.002 3 A
16 481 Anisabi H. Ilak Khan Nalkheda 1.097 0.005
17 462/2/3 Habib Khan F. Rustham Khan Nalkheda 1.035 0.016 4 B
18 462/2/2 Shaharaj Khan F. Rusthum Khan
Nalkheda 1.034 0.004
19 462/2/2 Shaharaj Khan F. Rusthum Khan
Nalkheda 1.034 0.010
20 474 1.Kamalabai H. Himmathmal, 2.Siddnath F. Bhavana
Nalkheda 0.680, 0.209
0.004
102
21 473 1.Govt. Land, 2.Kamalabai H. Himmathmal
Nalkheda 0.509, 0.209
0.022
22 473/1578 Himmathmal F. Mathuramal Nalkheda 1.233 0.006
23 435 Kamalabai H. Himmathmal Bhaisoda 0.82 0.016
24 436 Rameshchand F. Nathulal Bhaisoda 0.42 0.003
25 433 1.Himmathmal F. Mathuramal, 2.Kamalabai H. Himmathmal
Bhaisoda 0.09, 1.5
0.001
26 433 1.Himmathmal F. Mathuramal, 2.Kamalabai H. Himmathmal
Bhaisoda 0.09, 1.5
0.004 2 B
27 438 Lakshmichand F. Nathulal Bhaisoda 1.25 0.010 6 A
28 441 SAMPATBAI DHULA Bhaisoda 0.76 0.006
29 439 LAXMICHAND BHERULAL Bhaisoda 0.96 0.015
30 440 NATHU MANGU Bhaisoda 0.21 0.004
31 432 GOVT. LAND Bhaisoda 2.55 0.007
32 240 RAMESWAR PIRULAL Bhaisoda 0.96 0.009
33 241 SIDABNATH RAMESWAR Bhaisoda 0.88 0.010
34 241 SIDABNATH RAMESWAR Bhaisoda 0.88 0.005
35 248 CHANDRASEKHAR LAXMINARAYAN
Bhaisoda 0.44 0.007
36 249 GANGABAI BADRILAL Bhaisoda 0.45 0.004
37 247 DHANSINGH NATHULAL Bhaisoda 0.63 0.006
38 251 SHYAMSUNDER KRUSHNABALLAVH, RAMPAL PRABHULAL
Bhaisoda 1.13, 0.73
0.015
39 252 BADRILAL BHERULAL Bhaisoda 1.07 0.001
40 104 CHANDAR BAI F. KANA JI Najarkheda 1.41 0.015
41 103 ISWAR SINGH SHIV SINGH Najarkheda 0.79 0.008
42 102 GOVT. LAND Najarkheda 0.16 0.004
43 100 SYAM SINGH UKAR SINGH Najarkheda 1.85 0.019
44 96 NOOR KHAN KARIM KHAN Najarkheda 0.5 0.006
45 95 VAJIR KHAN KARIM KHAN Najarkheda 0.44 0.005
46 93 VIKRAM SINGH RAM SINGH Najarkheda 0.61 0.006
47 92 BAL CHANDRA UKAR Najarkheda 0.32 0.008
48 183 SANTOSH RAM CHANDRA, RAM LAL PURA
Najarkheda 0.4, 1 0.004
103
49 183 SANTOSH RAM CHANDRA, RAM LAL PURA
Najarkheda 0.4, 1 0.012
50 247 GOVT. LAND Najarkheda 2 0.003
51 246 NARAYANA MADHO Najarkheda 0.46 0.008
52 245 SRI RAM MANDIR Najarkheda 0.62 0.015
53 235 RAJENDRA VIKRAM SINGH Najarkheda 1.68 0.003
54 244 NARENDRA SINGH VIKRAM SINGH
Najarkheda 0.81 0.016
55 243 BHERU SINGH UDAY SINGH
Najarkheda 0.96 0.014
56 236 BHERU SINGH, RAMNATH SINGH UDAY SINGH
Najarkheda 1.79 0.005
57 239 UDAY SINGH, AMAR SINGH KESHAR SINGH
Najarkheda 0.63 0.016 1 A
58 242 NOT AVAILABLE Najarkheda 0.75 0.004
59 1249 LAXMI NARAYANA Pilwas 1.69 0.016
60 1250 GOVT. LAND Pilwas 0.42 0.004
61 1252 NOT AVAILABLE Pilwas 0.005
62 1271 GITA BAI Pilwas 0.83 0.008 5 A
104
Annexure 9 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 500 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 252 BADRILAL BHERULAL Bhaisoda 1.07 0.003
2 253 BAPULAL BHERU Bhaisoda 0.46 0.005
3 253 BAPULAL BHERU Bhaisoda 0.46 0.003
4 254 MURALI RAMPRASAD, GORDHANLAL MATHURALAL
Bhaisoda 0.59, 0.29
0.005
5 255 PIRULAL HARINARAYAN, LAXMICHAND GHASIRAM
Bhaisoda 0.44, 0.45 0.009
6 271 BHERULAL DEVISINGH Bhaisoda 0.9 0.010
7 277 PABANKUMAR BADRILAL Bhaisoda 0.42 0.008
8 276 KALURAM NARAYAN Bhaisoda 0.68 0.005
9 274 KOSALYABAI SIDABNATH Bhaisoda 0.99 0.003
10 275 ANIL BALKISHAN Bhaisoda 0.89 0.010
11 285 MOHANLAL PIRULAL Bhaisoda 0.68 0.005
12 287 KAMAL MANGILAL Bhaisoda 0.17 0.003
13 288 LAKHANLAL JAGANNATH Bhaisoda 0.17 0.005
14 378 GOVT. LAND Bhaisoda 1.5 0.004
15 1271 GITA BAI Pilwas 0.83 0.004
16 1272 KANHEIYA LAL Pilwas 0.41 0.007 6 B
17 1279 PUKHRAJ KUMAR Pilwas 1.08 0.017
18 1286/2 BHAMBAR LAL Pilwas 2.07 0.009
19 1277 BHAMBAR LAL Pilwas 0.51 0.001
20 1296 GOBINDA SINGH Pilwas 1.67 0.010
105
Annexure 10 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 450 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 378 GOVT. LAND Bhaisoda 1.5 0.001
2 372 RAMKARAN JAGANNATH Bhaisoda 0.34 0.001
3 371 DINESH KUWARLAL Bhaisoda 0.57 0.005
4 370 BHERULAL DEVISIJNGH Bhaisoda 0.88 0.002
5 366 LAKHANLAL JAGANNATH Bhaisoda 1.02 0.005
6 369 KAMAL MANGILAL Bhaisoda 0.43 0.001
7 367 BHERULAL DEVISINGH Bhaisoda 0.52 0.004
8 336 1.MANOHARSINGH BHARATSINGH, 2.RAJESHKUMAR SAGARMAL
Bhaisoda 0.31, 0.02
0.007
9 132 GOVT. LAND Bhaisoda 1.02 0.001
10 106 TEJKARAN BALCHANDRA Bhaisoda 0.5 0.001
11 130 GOVT. LAND Bhaisoda 0.96 0.007
12 111 BODIYA MAGU Bhaisoda 0.52 0.001
13 128 SIDABNATH PARBAT Bhaisoda 4.04 0.003
14 128 SIDABNATH PARBAT Bhaisoda 4.04 0.011
15 950 GOVT. LAND Bhaisoda 1.24 0.001
16 942 GOVT. LAND Bhaisoda 0.44 0.001
17 944 SIDHU SEBA Bhaisoda 0.42 0.001
18 939 GOVT. LAND Bhaisoda 1.5 0.001
19 960 GOVT. LAND Bhaisoda 2.69 0.002
20 975 GOVT. LAND Bhaisoda 7.33 0.005
21 1296 GOBINDA SINGH Pilwas 1.67 0.001
22 1292 SIMA KUMBAR Pilwas 1.1 0.005
23 1294 BALU Pilwas 0.71 0.007
24 1506 GOVT. LAND Pilwas 0.45 0.001
25 1507 BALU SINGH Pilwas 1.66 0.002
26 1518 JIBAN SINGH Pilwas 1.18 0.008
27 1516 ISWARA SINGH Pilwas 1.15 0.002
106
Annexure 11 : Summary of Affected Persons and Common Property Resources
MAIN PIPE LINE – 400 mm
S.No Survey Number
Farmer Name (Zone-3 DY1) Village Name
Area (Ha)
Aff Area
Fruit Trees
Orange Category
Other Trees
1 1516 ISWARA SINGH Pilwas 1.15 0.003
2 1526 BHAGABAN SINGH Pilwas 0.28 0.004
3 1527 KESAR SINGH Pilwas 0.68 0.002
4 1529 KRUSNA BAI Pilwas 0.3 0.003
5 1530 KRUSNA BAI Pilwas 0.29 0.003
6 1531 MAN SINGH Pilwas 1.7 0.007
7 1534 SUVASACHAND,GANGA BAI
Pilwas 1.22 0.012
8 1535 GOVT. LAND Pilwas 3.5 0.007
9 1615 GOVT. LAND Pilwas 0.5 0.001
10 1616 GOVT. LAND Pilwas 1.01 0.003
11 1620 ANOP SINGH Pilwas 1.21 0.013
12 1624 GOVT. LAND Pilwas 1.4 0.005
13 1628 BHAGIRATHA Pilwas 0.41 0.004
14 1630 RAM LAL Pilwas 0.41 0.015
15 1631 MOHAN Pilwas 0.46 0.000
16 1632 DEBI LAL Pilwas 0.46 0.005
17 1643 UMADEBI Pilwas 0.62 0.003
18 1642 GIRI RAJ Pilwas 0.41 0.003
19 1641 BANSI LAL Pilwas 0.63 0.000
20 975 GOVT. LAND Bhaisoda 7.33 0.008
21 987 GOVT. LAND Bhaisoda 0.62 0.005
22 989 DEVISINGH MANGU Bhaisoda 0.26 0.004
23 988 SALIM KHAMMAN KHAN Bhaisoda 0.24 0.006
24 997 GOVT. LAND Bhaisoda 1.97 0.008
25 166 GOVT. LAND Semali 1.003 0.001
26 146 GOVT. LAND Semali 0.732 0.004
27 144 GIRI RAJ Semali 0.209 0.004
28 143 ATMARAM Semali 0.753 0.000
29 145 KESAR SINGHA, JAYA NARAYANA, AKHILESHA
Semali 0.068, 0.068, 0.366 0.007
107
30 132
GIRI RAJ, GOVT. LAND, KAYLASA, FULCHAND, RAMPRASAD, RAMESHA, KANHEIYALAL
Semali
1.4, 0.073, 0.105, 0.105, 0.105, 0.104, 0.209 0.011
31 131 SHAKUNTALA BAI, SUNDAR BAI
Semali 0.209, 0.199 0.005
32 130 BHARAT SINGHA Semali 0.035 0.004
33 130 BHARAT SINGHA Semali 0.035 0.006
34 183 OM PRAKASH MADAN, RADHESYAM MADAN
Semali 0.331, 0.474 0.012
35 120 GANESHARAM Semali 0.867 0.002
36 189 RADHESYAM Semali 0.272 0.005
37 190 JAYA NARAYANA, BABU LAL, KAYLASHA
Semali 0.601, 0.737, 0.951 0.004
38 119 BHARAT SINGHA, LILA BAI, SIBA SINGHA, KANTI BAI
Semali
2.09, 0.637, 0.105, 0.658 0.007
39 108 NOT GIVEN, OM PRAKASHA, KRUSHNA BAI
Semali 0.036, 0.732, 0.732 0.005
40
183
SANTOSHA, RAM LAL, SIBA LAL, RUKHMANI BAI, SANGITA BAI, MANGU, NARAYANA, ISAK KHAN, RAIS KHAN, RAJAK KHAN, MANGI LAL
Najarkheda
0.4, 1, 0.8, 0.8, 0.51, 0.6, 0.4, 0.2, 0.2, 0.06,
0.2, 0.8 0.015
187 GOVT. LAND Najarkheda 0.11 0.001
188 GOVT. LAND Najarkheda 0.2 0.003
192 RAMESHA Najarkheda 0.4 0.012
191 NANURAM Najarkheda 0.4 0.002
63 MOHAN SINGH Najarkheda 1.71 0.006
41
557 MANGILAL BASANTILAL, MANJUDEVI ABHAYAKUMAR
Pheti 1.04 0.002
501 MANGILAL KANHAEIYALAL, MANJUDEVI ABHAYAKUMAR
Pheti 2.09 0.002
108
543 RAEMMOHAMAD SARID KHAN
Pheti 1.57 0.005
554 BHERULAL AMARSINGH Pheti 0.16 0.000
551 CHANDANBALAL SANJAYAKUMAR
Pheti 0.63 0.008
544 SOHANBAI SAGARMAL Pheti 2.85 0.007
542 SUNILKUMAR SAGARMAL Pheti 0.26 0.000
541 SUNITABAI SUNILKUMAR Pheti 1.17 0.006
540 PRAKASHCHANDRA ROOPCHANDRA
Pheti 1.04 0.005
536 RAUF KHAN TURAB KHAN Pheti 8.47 0.020
42
681 ABHAYAKUMAR TARACHAND
Pheti 1.94 0.015
685 GOVT. LAND Pheti 5.73 0.002
679 GOVT. LAND Pheti 7.53 0.012
43
251
SHYAMSUNDER KRUSHNABALLAVH, RAMPAL PRABHULAL, PRABHULAL SHIBANARAYAN
Bhaisoda 2.06
0.001
252 BADRILAL BHERULAL Bhaisoda 1.07 0.006
254
MURALI RAMPRASAD, GORDHANLAL MATHURALAL, MISHRILAL MATHURALAL
Bhaisoda 1.18
0.004
257 BINOD RODMAL Bhaisoda 0.68 0.003 2 A
258 SATIBAI SHIBANARAYAN Bhaisoda 0.43 0.003
261 GOVT. LAND Bhaisoda 0.23 0.001
432 GOVT. LAND Bhaisoda 2.55 0.002
473 GOVT. LAND Bhaisoda 0.33 0.002
471 DEVISINGH BANSILAL Bhaisoda 0.5 0.004
472 PREMNARAYAN RAMLAL Bhaisoda 0.42 0.004
475 BADRILAL NATHULAL Bhaisoda 0.67 0.000
109
Annexure 12 : Approved Collector Rates of Agriculture Land of Nalkheda Tehsil, Agar Malwa District
110
111
112
113
114
Annexure 13 : MSP Rates By MP Govt.
115
Annexure 14 : Memorandum of Understanding (MOU) to document foregone compensation for temporary land use
116