Title page
Alcatel-Lucent 9100
Base Station |
IO 148 - Provide E1 Clock Out from BTS for NodeB Synchronization
3MN-00460-0486-UAZZA
Issue 1 | September 2012
Legal notice
Legal notice
Alcatel, Lucent, Alcatel-Lucent and the Alcatel-Lucent logo are trademarks of Alcatel-Lucent. All other trademarks are the property of their respective
owners.
The information presented is subject to change without notice. Alcatel-Lucent assumes no responsibility for inaccuracies contained herein.
Copyright © 2012 Alcatel-Lucent. All rights reserved.
Note:
Not to be used or disclosed except in accordance with applicable agreements.
Contents
About this document
Purpose ............................................................................................................................................................................................ viivii
Reason for reissue ....................................................................................................................................................................... viivii
New in this release ...................................................................................................................................................................... viivii
Intended audience ....................................................................................................................................................................... viivii
How to use this document ....................................................................................................................................................... viiiviii
Prerequisites ................................................................................................................................................................................. viiiviii
Conventions used ....................................................................................................................................................................... viiiviii
Related information ................................................................................................................................................................... viiiviii
Document support ...................................................................................................................................................................... viiiviii
Technical support ....................................................................................................................................................................... viiiviii
How to order ................................................................................................................................................................................... ixix
How to comment ........................................................................................................................................................................... ixix
1 Overview
Overview ...................................................................................................................................................................................... 1-11-1
Presentation ................................................................................................................................................................................. 1-11-1
Prerequisites ................................................................................................................................................................................ 1-21-2
Scheduling ................................................................................................................................................................................... 1-21-2
Telecom / Supervision Outage ............................................................................................................................................. 1-21-2
Resources ..................................................................................................................................................................................... 1-31-3
2 Scenario
Overview ...................................................................................................................................................................................... 2-12-1
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
iii
Provide E1 Clock Out from Indoor BTS for NodeB Synchronization
Interconnection Panel for Indoor BTS .............................................................................................................................. 2-22-2
E1 120-Ohm Cable Connection from MSCA (L 904 / 1) .......................................................................................... 2-32-3
Provide E1 Clock Out from Outdoor BTS for NodeB Synchronization
Interconnection Panel for Outdoor BTS ........................................................................................................................... 2-42-4
E1 120-Ohm Cable Connection from OUTC (L 904 / 1) ........................................................................................... 2-72-7
Completion Check List (CCL) for IO148
Completion Check List (CCL) for IO148 Required Information ............................................................................ 2-82-8
Contents
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
iv Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
List of figures
2-1 Interconnection Panel for Indoor BTS with TX Abis 2 highlighted (MBI3/5) ................................... 2-22-2
2-2 Interconnection Panel for Outdoor BTS with TX Abis 2 highlighted .................................................... 2-52-5
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
v
List of figures
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
vi Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
About this documentAbout this document
Purpose
This document describes the method for providing synchronization for a collocated
NodeB from the BTS. Note that this feature is available starting from Release B12.
Reason for reissue
Issue number Reason for reissue
1 First official release of the document for B12.
New in this release
This section contains information about changes to the current document.
New features
None.
Other changes
None.
Intended audience
This document is intended for the following personnel:
• Site Planners.
• Installers
• Site administrators
• Supervisors
• Project managers
• Field service technicians
...................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
vii
How to use this document
No specific recommendation applies regarding the way readers should read this
document.
Prerequisites
You must have a basic understanding of the following:
• Basic knowledge of Alcatel-Lucent BSS equipment
• Experience of electrical mounting and cabling.
Conventions used
This section gives information on conventions.
Vocabulary conventions
None.
Typographical conventions
The following typographical conventions are used in this document:
Appearance Description
Italicized text Emphasized information.
graphical user interface text Text that is displayed in a graphical user interface or in a
hardware label.
Document reference, reference
number
Related document that is referenced in the document.
Related information
None.
Document support
For support in using this or any other Alcatel-Lucent document, contact Alcatel-Lucent at
one of the following telephone numbers:
• 1-888-582-3688 (for the United States)
• 1-317-377-8618 (for all other countries)
Technical support
For technical support, contact your local Alcatel-Lucent customer support team. See the
Alcatel-Lucent Support web site (http://www.alcatel-lucent.com/support/) for contact
information.
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
viii Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
How to order
To order Alcatel-Lucent documents, contact your local sales representative or use Online
Customer Support (OLCS) (http://support.alcatel-lucent.com)
How to comment
To comment on this document, go to the Online Comment Form (http://infodoc.alcatel-
lucent.com/comments/) or e-mail your comments to the Comments Hotline
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
ix
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
x Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
1 1Overview
Overview
Purpose
This Overview gives information needed by project managers and foremen, for
presentation to the customer and for site planning.
Contents
Presentation 1-1
Prerequisites 1-2
Scheduling 1-2
Telecom / Supervision Outage 1-2
Resources 1-3
Presentation
Overview
Use this scenario to connect a BTS to an IP NodeB that is collocated in order to provide
the E1 clock out from the BTS for IP NodeB synchronization. This scenario applies to all
types of Indoor and Outdoor 9100 BTSs.
...................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
1-1
Prerequisites
Overview
You must have the following site specific information:
• The BTS has the Abis port 2 free
• All items required by this operation are available
• All tools required by this operation are available.
Scheduling
Overview
This procedure can be performed for already installed BTSs and NodeBs that are
collocated.
Human Resources
One person is required to perform this task.
Duration
5 minutes.
Telecom / Supervision Outage
Overview
None.
Overview Prerequisites
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
1-2 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
Resources
Tools
You must have the following tools.
Hardware Tools
Use the following table to check, at base, the availability of the required tools.
Refer to the Alcatel-Lucent GSM 2G - Kits - Tools Catalogue for Field Activity to check
the content.
Name Reference Calibration
Basic set of tools OUT 001 No
Installation Kits
Use the following table to check, onsite, the mandatory or optional delivery item kits.
The used symbols are:
• ♢ = mandatory kit
• # = technical choice kit
• ∇ = customer option kit.
Kits Mnemonic Reference Quantity
# E1 cable
L 904 - 1 (for 120-ohm, 1 pair
of wires)
CA120S 3BK 08941 AAAA -
Supplies
None.
Applicable Documents
You must have the following documents or have electronic access to the following
documents:
• Alcatel-Lucent GSM 2G - Kits - Tools Catalogue for Field Activity
• Alcatel-Lucent 9100 BTS - Hardware Description
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
1-3
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
1-4 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
2 2Scenario
Overview
Purpose
This Scenario presents all checks needed before starting the operations, and all detailed
tasks to be performed during the operations.
Contents
Provide E1 Clock Out from Indoor BTS for NodeB Synchronization 2-2
Interconnection Panel for Indoor BTS 2-2
E1 120-Ohm Cable Connection from MSCA (L 904 / 1) 2-3
Provide E1 Clock Out from Outdoor BTS for NodeB Synchronization 2-4
Interconnection Panel for Outdoor BTS 2-4
E1 120-Ohm Cable Connection from OUTC (L 904 / 1) 2-7
Completion Check List (CCL) for IO148 2-8
Completion Check List (CCL) for IO148 Required Information 2-8
...................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
2-1
Provide E1 Clock Out from Indoor BTS for NodeB
Synchronization
Interconnection Panel for Indoor BTS
Overview
In the following figure, the position from which the clock for NodeB will be provided is
highlighted.
The figure provides an example to show the position of the TX Abis 2 on the KRONE
connector. It is the same for other Interconnection Panels variants.
Figure 2-1 Interconnection Panel for Indoor BTS with TX Abis 2 highlighted
(MBI3/5)
Scenario
Provide E1 Clock Out from Indoor BTS for NodeB
Synchronization
Interconnection Panel for Indoor BTS
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-2 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
E1 120-Ohm Cable Connection from MSCA (L 904 / 1)
Procedure
Connect the synchronization cable:
...................................................................................................................................................................................................
1 Remove the PCM lightening protection from KRONE connector of MSCA board
...................................................................................................................................................................................................
2 Prepare the head of L907/1 cable.
...................................................................................................................................................................................................
3 Insert the L 907/1 wires using the mandatory KRONE original tool in the TX of Abis 2
(6th position of the KRONE connector).
...................................................................................................................................................................................................
4 Fit the lightening protection to the KRONE connector.
Scenario
Provide E1 Clock Out from Indoor BTS for NodeB
Synchronization
E1 120-Ohm Cable Connection from MSCA (L 904 / 1)
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
2-3
E N D O F S T E P S...................................................................................................................................................................................................
Provide E1 Clock Out from Outdoor BTS for NodeB
Synchronization
Interconnection Panel for Outdoor BTS
Overview
In the following figure, the position from which the clock for NodeB will be provided is
highlighted.
Scenario
Provide E1 Clock Out from Outdoor BTS for NodeB
Synchronization
Interconnection Panel for Outdoor BTS
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-4 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
Figure 2-2 Interconnection Panel for Outdoor BTS with TX Abis 2 highlighted
Scenario
Provide E1 Clock Out from Outdoor BTS for NodeB
Synchronization
Interconnection Panel for Outdoor BTS
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
2-5
The figure above provides an example to show the position of the TX Abis 2 on the
KRONE connector. It is the same for other Interconnection Panels variants.
Scenario
Provide E1 Clock Out from Outdoor BTS for NodeB
Synchronization
Interconnection Panel for Outdoor BTS
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-6 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
E1 120-Ohm Cable Connection from OUTC (L 904 / 1)
Procedure
Connect the synchronization cable:
...................................................................................................................................................................................................
1 Remove the PCM lightening protection from KRONE connector of OUTC board.
...................................................................................................................................................................................................
2 Prepare the head of L907/1 cable.
...................................................................................................................................................................................................
3 Insert the L 907/1 wires using mandatory KRONE original tool in the TX of Abis 2 (6th
position of the KRONE connector).
...................................................................................................................................................................................................
4 Fit the lightening protection to the KRONE connector.
Scenario
Provide E1 Clock Out from Outdoor BTS for NodeB
Synchronization
E1 120-Ohm Cable Connection from OUTC (L 904 / 1)
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
2-7
E N D O F S T E P S...................................................................................................................................................................................................
Completion Check List (CCL) for IO148
Completion Check List (CCL) for IO148 Required Information
Date, Time and Duration of Work
Start End Duration
Responsible: Visa: Date:
Traffic Outage
Start End Comments
1
2
3
4
5
6
Comments
Scenario
Completion Check List (CCL) for IO148
Completion Check List (CCL) for IO148 Required Information
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-8 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
Scenario Completion Check List (CCL) for IO148 Required Information
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012
2-9
Scenario Completion Check List (CCL) for IO148 Required Information
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-10 Alcatel-Lucent 9100 BTS
3MN-00460-0486-UAZZA
Issue 1 September 2012